Cheat sheet · free to read or print
PMP Cheat Sheet: Schedule
The key points and common traps of 23 lessons in 9 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.
Rolling Wave Planning and Developing the Schedule
Lesson 1: The Schedule Management Plan and the Four Steps of Developing the Schedule
- The schedule management plan states how the schedule is built and managed. It contains no specific schedule.
- Five commonly tested contents: release and iteration length, level of accuracy, units of measure, control thresholds and rules of performance measurement.
- The four steps of developing the schedule are define activities, determine sequence, estimate effort and duration, and adjust. They proceed in this order, but the whole is iterative and you may go back and revise.
- PMBOK 8 folds defining activities, sequencing activities and estimating activity durations into Develop Schedule.
- "Adjust" covers a group of techniques: the critical path method, resource optimization, the critical chain method, schedule compression, what-if analysis and others.
- The schedule management plan says "how to manage" and contains no specific dates. Specific dates appear in the project schedule; the project schedule is an output of the schedule model; once approved, the schedule model becomes the schedule baseline.
- The four steps generally proceed in this order, but Develop Schedule is an iterative process: you can go back and revise, and steps can overlap. When a question asks "what is the next step?", first work out which step the project has reached. With only an activity list, the next step is sequencing. With a network diagram but no durations, the next step is estimating. Only when the critical path has been calculated and resources conflict does resource optimization come in.
- "Adjust" is the name for a group of techniques, not a single tool.
- A deviation within the threshold is handled by the project manager within their authority. A deviation that reaches or exceeds the threshold is handled with the action the schedule management plan specifies, and if it goes beyond your authority you escalate through the governance process. Do not go to the sponsor at the first sign of any deviation.
- Estimating is step 3, not step 1. Without defined activities you cannot estimate durations at the activity level, and without activity sequences and durations you cannot calculate the critical path.
Lesson 2: Decomposition, Rolling Wave Planning, and the Activity and Milestone Lists
- Defining activities decomposes work packages into activities. The scope baseline (WBS, WBS dictionary and so on) is the most important source of scope information.
- Rolling wave planning is progressive elaboration applied to the plan: detailed near term, high level later, refined as information grows.
- A planning package has a name and a rough scope and is not yet decomposed into activities.
- The activity list lists all activities, activity attributes are enriched step by step, and the milestone list marks each milestone as mandatory or optional.
- A milestone is a point in time with zero duration. It is not an activity.
- When the stem says "limited information", "future details are unclear" or "detailed for the near term, high level for the future", choose rolling wave planning. Do not define every activity in full all at once.
- Rolling wave planning does not mean "do not plan yet". Future work does have a plan, only at a lower level of detail, and the activity list and schedule must be updated regularly as the project moves on.
- The two "decompositions" are different. WBS decomposition breaks the project scope into work packages; decomposition in defining activities breaks work packages into activities.
- A milestone is not an activity. You cannot estimate a duration for it, and you cannot turn a real critical activity into a zero-duration activity just to "treat it as a milestone".
- A milestone must be marked mandatory or optional. A delivery date set by contract is a mandatory milestone.
Precedence Diagramming Method
Lesson 1: The Precedence Diagramming Method: Network Diagrams and the Four Logical Relationships
- PDM uses nodes for activities and links for logical relationships. Other names: the node method and AON.
- A predecessor comes first and a successor comes after. Several predecessors make a path convergence, and several successors make a path divergence.
- The four relationships are FS, FF, SS and SF. FS is the most common and SF is rarely used. Common exam practice: an unlabeled ordinary link is usually read as FS, unless the stem says otherwise.
- To identify a relationship, look at which end of the predecessor (start or finish) it depends on and which end of the successor it constrains.
- If a dependency is found wrong before the baseline is approved, correct the network diagram directly and update the schedule.
- To identify a relationship, ask two things: is it the start or the finish of the successor that is constrained, and is it the start or the finish of the predecessor that it depends on? The part before "to" is the predecessor and the part after it is the successor.
- FF and SS do not mean "at the same time". They fix the order at only one end, and the other end can still be offset.
- Descriptions like "can finish editing only after the writing is finished" are usually FF, and descriptions like "switching from the old system to the new one" are usually SF. Do not assume everything is FS.
- A predecessor is not an activity that is "earlier in time". It is an activity that comes first on the logical path. The same goes for a successor.
- If an error in the network diagram is found before the schedule baseline is approved, simply correct it and update the schedule. After the baseline is approved, a change in a predictive project goes through change control (adaptive or hybrid projects follow the change mechanism they have agreed).
Lesson 2: Types of Dependencies, and Leads and Lags
- A mandatory dependency (hard logic) cannot be violated. A discretionary dependency (soft logic) can be adjusted, and when you fast track you review discretionary dependencies first.
- An external dependency lies outside the project and is usually outside the team's control. If the other party is late or has not provided a date, contact it first to clarify the date, then build or update the dependency in the schedule and track it. An internal dependency is generally inside the team's control.
- A lead (FS−3) brings the successor forward and a lag (FS+2) pushes it back. First read the relationship type, then the number of days added or subtracted.
- Leads and lags do not replace logical relationships and are not counted in activity duration estimates.
- For a simple path of all-FS relationships, total path length = sum of activity durations + lags − leads, and the project duration is the longest path. When SS, FF or SF relationships are involved, work through each relationship's constraint item by item in a forward pass and a backward pass. Do not apply the shortcut directly.
- Only discretionary dependencies are the ones you can loosen first. Mandatory dependencies (for example, you cannot build the superstructure until the foundation is done) cannot be violated.
- "External" means the thing depended on is outside the project, and "mandatory" means the sequence cannot be violated. The two dimensions can be combined freely, so do not treat every external dependency as mandatory.
- Wording like "best practice", "customary practice" or "preferred sequence" points to a discretionary dependency. Wording like "required by contract" or "physically impossible" points to a mandatory dependency.
- When you calculate path length, add lags and subtract leads. Do not reverse the direction. An activity's own duration does not include either quantity.
- A lag is time you must wait and float is time you can delay. Do not mix them up.
Estimating Techniques for Duration
Lesson 1: Estimating Effort and Duration: Effort, Duration and Influencing Factors
- What you estimate: effort (labor hours) is converted into duration (work periods). Use productive hours and the resource calendar when converting.
- Inputs come from the person or group most familiar with the activity. Estimates made by temporary staff should be reviewed with the team that will do the work.
- Large disagreement among experts: in wideband Delphi, experts estimate individually, discuss the extreme values after each round and re-estimate until the numbers converge.
- Influencing factors: the law of diminishing returns, number of resources, advances in technology and cognitive bias (including team members' motivation). Adding people does not always shorten the schedule.
- Parkinson's law and student syndrome are common exam terms. They show that spare time gets used up.
- "Adding people always speeds things up" is wrong. If the stem says new resources need training, communication costs rise or resources are already saturated, lean toward the answer that efficiency falls and duration does not necessarily shorten.
- Effort is not duration. 120 labor hours could be 5 days or 15 days, depending on how many people are assigned and how many productive hours they have.
- Estimate inputs come from the person or group most familiar with the activity. The project manager does not set them alone, and a sponsor's approval does not make them right.
- When experts' numbers differ widely, do not simply average them and do not simply escalate. Have them explain their reasons and re-estimate.
- The learning curve, resource availability and risk are all factors to consider in estimating. When you find something missing, adjust the estimates of the affected activities and update the basis of estimates. Do not add one block of padding at the end.
Lesson 2: Analogous, Parametric and Bottom-Up Estimating
- Analogous: uses historical data from a similar project; quick, cheap, less accurate; used early on.
- Parametric: statistical relationship plus parameters; accuracy depends on the model and the data.
- Bottom-up: decompose, estimate item by item, then roll up; usually takes longer and is more accurate (common exam practice: most accurate, slowest).
- Multipoint estimating: uses three values to reflect uncertainty; covered in detail in the next chapter.
- Adaptive projects use story points, planning poker and T-shirt sizing; hybrid projects use each technique where it fits, then agree on a common basis to link them.
- The keywords in the stem decide the technique: similar project, statistical relationship, roll-up, uncertainty.
- "Refer to similar past projects", "early in the project", "very little information", "needs to be quick": analogous estimating.
- "Statistical relationship", "parametric model", "unit rate or labor hours times quantity": parametric estimating.
- "Roll up from work packages level by level", "most accurate, slowest" (common exam practice): bottom-up estimating.
- "Optimistic, pessimistic, most likely", "high uncertainty": multipoint estimating.
- When the new project differs greatly from past projects, the premise of analogous estimating does not hold, and you should decompose the work and estimate item by item.
- Analogous estimating involves some expert judgment, but "ask an experienced person to estimate" on its own is expert judgment, not analogous estimating.
- A story point is a relative size, not a duration. You cannot simply convert it to days and enter it in a predictive network diagram.
Lesson 3: Reserve Analysis and the Outputs of Duration Estimating
- Contingency reserve: for known-unknowns, inside the baseline, used by the project manager according to the risk management plan and the authority established, with no separate change control needed (common exam practice).
- Management reserve: for unknown-unknowns, outside the baseline, and its use is usually decided by senior leadership or management (common exam practice: request it through change control).
- When the schedule is behind, do a reserve analysis first: how much has been used, how much is left and whether it covers later risks. Then forecast the date.
- A duration estimate does not include lags. It may carry a range (± days) or a probability, and it must come with a basis of estimates.
- Probability of finishing as planned = 1 − probability of delay.
- Contingency reserve is inside the baseline and is used by the project manager according to the risk management plan and the authority established, with no separate change control needed (common exam practice). Management reserve is outside the baseline and its use is usually at the discretion of senior leadership or management, and the common exam practice is to request it through change control. Do not swap their ownership and authority.
- Contingency reserve answers identified risks and management reserve answers unknown-unknowns. Do not use management reserve to cover identified risks.
- A duration estimate does not include lags. It may carry a range or a probability, but it must come with a basis of estimates.
- For probability questions, first see what is asked: for "the probability of finishing as planned", use 1 minus the probability of delay; only for "the average delay" do you multiply probability by days.
- When there is a clear basis of estimates, the answer to a demand to "just cut 20%" is not to cut the numbers mechanically but to discuss reducing scope or activities.
Multipoint (Three-Point) Estimating
Formulas
- Expected Duration (Triangular Distribution)tO optimistic, tM most likely, tP pessimistic duration; the simple average of the three values
- Expected Duration (Beta Distribution, PERT)A weighted average with the greatest weight on the most likely value; use it when the question does not name a distribution (common exam practice)
- Back-Solving the Pessimistic Value (Beta Distribution)Used when the expected duration tE and the other two estimates are known
- Activity Standard Deviation (PERT)The usual PERT approximation of uncertainty from the estimate range; the wider the range, the larger the standard deviation
Lesson 1: Multipoint Estimating: Three Estimates and Two Formulas
- Three values: optimistic , most likely and pessimistic ; the approach derives from PERT.
- Use it when a single activity's estimate involves uncertainty and risk. When historical data are insufficient or the estimate rests mainly on judgment, the triangular distribution can be used.
- Triangular distribution: .
- Beta distribution (PERT, the default in common exam practice): .
- The result must fall between the optimistic and pessimistic values. When the three values are symmetric, the two formulas give the same answer.
- The denominator for the triangular distribution is 3 and for the beta distribution it is 6, and only the most likely value is multiplied by 4. Multiplying the optimistic or pessimistic value by 4 is the most common mistake.
- When no distribution is specified, common exam practice is to use the beta distribution (PERT). Use the formula with denominator 3 only when the stem says "triangular distribution" or "simple average".
- Match the three numbers to the right values. The stem order is often "pessimistic, optimistic, most likely". Do not substitute them in the order they appear.
- The expected value is not the most likely value and is not a commitment. It is only a weighted estimate.
- Multipoint estimating is for activities with uncertainty and risk, and is especially common when historical data are insufficient. When reliable historical data exist, analogous or parametric estimating can also be used.
Lesson 2: Multipoint Estimating: Worked Examples, Common Mistakes and Using the Results
- Four steps for a calculation (common exam practice): match the numbers, confirm the distribution, substitute into the formula, and check that the result lies between the optimistic and pessimistic values.
- Beta distribution: ; working backward, .
- The expected duration goes into the network diagram, and path length is the sum of the expected values.
- The range (pessimistic minus optimistic) reflects uncertainty: with the same expected value, the estimate with the wider range is more uncertain and the related risk should be assessed further and given more attention.
- The expected value and the most likely value are different concepts, and the numbers need not be equal (they may be the same for a symmetric distribution). The expected value is not a commitment either.
- Multiplying the pessimistic or optimistic value by 4, or writing the denominator as 3 or 4.
- Mismatching the three numbers: the order in the stem is often "pessimistic, optimistic, most likely". Do not substitute them in the order they appear.
- The two formulas give the same result only when the most likely value is exactly the average of the optimistic and pessimistic values. Otherwise they differ. When both results appear among the options, go back to the stem and see whether it specifies a distribution.
- In a backward question, first multiply the expected value by 6 (beta) or by 3 (triangular), then subtract the known terms, and do not forget that the most likely value is multiplied by 4.
- What goes into the network diagram is the expected duration, not the most likely value.
- The expected value is not a commitment. An activity with a wide range needs more attention, not to be thrown out.
Critical Path Method
Formulas
- Critical Path DurationList every path, add up the durations (DU) along each, and take the largest; it is the shortest project duration; applies to FS relationships with no resource constraints (common exam practice); for a simple FS chain with lags or leads, path length = sum of durations + lags − leads; with SS, FF or SF relationships or other constraints, do a forward pass on the actual network logic. For example, activities of 5, 3 and 4 days with a 2-day lag in between: 5 + 3 + 4 + 2 = 14 days, not 12
- Float of a Simple Parallel PathOnly for simple parallel branches with no extra constraints, as a quick judgment; the total float of an activity is still calculated as LS − ES or LF − EF
- Early StartForward pass takes the maximum; Day 1 start convention, for FS networks with no leads or lags; if the project start is counted as Day 0 the formulas have no ±1 (common exam practice)
- Early FinishDU is the activity duration; Day 1 start convention, for FS networks with no leads or lags; if the project start is counted as Day 0 the formulas have no ±1 (common exam practice)
- Late FinishBackward pass takes the minimum; Day 1 start convention, for FS networks with no leads or lags; if the project start is counted as Day 0 the formulas have no ±1 (common exam practice)
- Late StartDU is the activity duration; Day 1 start convention, for FS networks with no leads or lags; if the project start is counted as Day 0 the formulas have no ±1 (common exam practice)
- Total FloatHow long an activity can be delayed without delaying the project completion date or violating a constraint; the two forms must agree, so use one to check the other
- Free FloatHow long an activity can be delayed without delaying the early start of its successor; for consecutive day counting, FS relationships and no leads or lags; with several successors use the earliest ES; FF ≤ TF
Lesson 1: The Critical Path and the Critical Path Method
- The critical path is the longest path in the network and determines the shortest project duration.
- The critical path method performs schedule network analysis without regard to resource limitations, and determines the float of each path at the same time.
- To find the critical path by hand: list all the paths, add each one up and take the maximum. In a simple network with no extra constraints, the difference in path lengths shows the float of a branch at a glance; the total float of an activity is still calculated as LS − ES or LF − EF.
- With no extra constraints, with network relationships and other activities unchanged and with no remedial action, a delay on a critical activity usually pushes back the project finish date by the same amount (with constraints or network changes, redo the schedule network analysis); only the part of a non-critical activity's delay that exceeds its total float delays the project.
- Predictive projects mainly use the critical path method; adaptive projects usually use iteration timeboxes or flow-based schedules and generally do not calculate a critical path activity by activity; hybrid projects use both in layers.
- The critical path is the path with the longest sum of durations, regardless of the number of activities; the single longest activity is not necessarily on the critical path.
- The shortest duration equals the length of the longest path. “Shortest” and “longest” describe the same thing, so do not let the wording confuse you.
- To decide whether something is critical, look at whether its total float is zero (or the least, when constraints apply), not at the number of its successors.
- The critical path method does not consider resources. The dates it produces are windows, not an approved schedule.
Lesson 2: Forward Pass and Backward Pass: The Seven-Box Node and a Step-by-Step Example
- The forward pass calculates ES and EF, and the backward pass calculates LS and LF; the difference between late and early is the total float.
- The formulas below assume that all dependencies are finish-to-start (FS) with no leads, lags or other date constraints. With the Day 1 start convention: ES = max(EF of predecessors) + 1, EF = ES + DU − 1, LF = min(LS of successors) − 1, LS = LF − DU + 1.
- TF = LF − EF = LS − ES; in an ordinary network with no externally imposed date constraints, the activities with zero TF form the critical path.
- Checking: in a case like this one, with two simple parallel paths, the difference in path lengths equals the total float of the activities on the non-critical branch; in a complex network, check against the results of the forward and backward passes.
- The dates are time windows, not an approved schedule; working days must be converted into calendar dates.
- The forward pass takes the maximum EF of the predecessors, and the backward pass takes the minimum LS of the successors. Reverse them and the whole diagram is wrong.
- The backward pass starts from the last activity, whose LF is the shortest project duration (when there is no externally imposed finish date).
- If you drop the “+1” or “−1”, or use EF = ES + DU − 1 for half a question and EF = ES + DU for the other half, your numbers will be off by 1.
- TF = LF − EF and TF = LS − ES must always be equal, so you can use them to check each other. If they are not equal, one step is wrong.
Lesson 3: Total Float and Free Float
- Total float: the maximum delay that does not delay the finish date, TF = LF − EF = LS − ES; activities in a simple serial chain share the slack.
- Free float: the maximum delay that does not delay the early start of the successor, FF = min(ES of successors) − EF − 1 (in this lesson, for networks with consecutive day counting, FS relationships and no leads or lags; with other logical relationships or with leads and lags, adjust accordingly).
- In a network without negative total float, FF is no greater than TF (see Common traps for the negative-float case); with no extra finish-date constraint, the FF of the last activity usually equals its TF.
- When an imposed date is earlier than the plan allows, negative float appears; first analyze the cause and develop acceleration strategies: consider schedule compression, or adjust logical relationships, leads and lags, and constraints that can be negotiated.
- When a non-critical activity is delayed, first verify whether the total float is enough, then decide whether to act.
- A large total float does not mean you can delay at will: in a simple serial chain, activities share the same stretch of slack, so once the earlier activity uses it, the later one has none.
- In an ordinary network calculation without negative total float, free float ≤ total float; this relationship cannot be applied when total float is negative; and an activity that has float can still have zero free float when its successor starts right after it.
- Negative float means the current plan cannot meet a constraint. It is a signal to analyze and develop acceleration strategies, of which schedule compression is one option, not a sign of being “very comfortable”.
- Delaying a non-critical activity is not always harmless: the project bears the part of the delay that exceeds the total float.
- Include leads and lags when you calculate path lengths.
Lesson 4: Characteristics of the Critical Path: Multiple Paths and Path Shifts
- There can be several critical paths; total float is usually zero and can be positive or negative when constraints apply.
- The closer a near-critical path is to the critical path, the greater the schedule risk.
- Delays, crashing and resource adjustments can all shift the critical path, after which the critical path analysis must be done again.
- If you compress only the current critical path and the other paths are unchanged, the reduction available before the path shifts is no more than its difference from the next-longest path; after the shift, reanalyze and compress the new critical path.
- Predictive projects use the critical path method; adaptive projects use iteration timeboxes or flow-based schedules; hybrid projects use them in layers.
- The total float of activities on the critical path is “usually” zero, not “always”; with constraints it can be positive or negative.
- The closer a near-critical path is to the critical path, the more dangerous it is; you cannot ignore it just because it is “not critical”.
- After the critical path is compressed, the reduction in duration is limited by the next-longest path, and the extra money spent does not necessarily buy time.
- A shift of the critical path is not a failure. Do not mechanically keep using the old list of critical activities, and do not immediately undo the crashing; reanalyze the paths, then decide to keep or adjust the crashing according to the schedule objective, incremental cost and risk.
- The critical path method deals only with path constraints; resource conflicts have to be resolved through resource optimization.
Resource Leveling and Resource Smoothing
Lesson 1: When Resource Optimization Applies, and Resource Leveling
- The three situations that need resource optimization: resources available only at particular times and in limited quantities, overallocated resources, and a wish to even out usage.
- There are two common resource optimization techniques, resource leveling and resource smoothing; neither is schedule compression.
- Resource leveling adjusts start and finish dates according to resource constraints, with the goal of balancing demand and supply.
- Resource leveling can use float and may change and lengthen the critical path, so move non-critical path activities first where possible.
- Before the baseline is approved, check the resource calendars and determine whether resource leveling is needed.
- Resource optimization is not schedule compression: compression shortens the duration, while resource optimization makes the schedule feasible, and the duration may even get longer.
- Resource leveling can adjust critical path activities, so it may change the critical path and delay the finish date (if the adjustment falls entirely within the available float, the duration may also stay the same); resource smoothing does not change the critical path or delay the finish date (next lesson).
- A schedule produced by the critical path method does not consider resources, so it cannot be treated directly as an executable schedule.
- Do not resolve resource conflicts by “approving the baseline first and dealing with them one by one during execution”: you should decide whether leveling is needed before the baseline is approved.
- When the stem clearly says “no more people will be added”, asking for staff is a dead end, and you should first analyze and coordinate the existing resources. Crashing (in PMBOK 8: approving overtime, bringing in additional resources, or paying to expedite delivery) does not necessarily require adding people, so unless the stem also rules out overtime or extra cost, you cannot rule it out directly.
Lesson 2: Resource Smoothing, and How It Differs from Resource Leveling
- Resource smoothing delays activities only within free and total float, and does not change the critical path or push back the finish date.
- When the float is not enough, smoothing cannot resolve all the conflicts; in this example, with no extra resources and the conflict having to be eliminated, resource leveling is needed and the duration lengthens; in general, resource leveling may change the critical path or push back the finish date.
- Leveling can use the critical path and may lengthen the duration; smoothing leaves the critical path and the duration alone.
- To tell them apart, look at “whether the adjustment is held strictly within the float”, not at “whether dates changed”.
- When people are short and you cannot slip the date, if candidate members have the required skills and each reassignment causes the same delay, pull from the activity with the longest total float.
- When the question requires “no delay”, so you can only adjust within float: resource smoothing. When a longer duration is acceptable: resource leveling.
- The two terms differ by only one word, and the exam tests whether the adjustment is held strictly within the float: smoothing is bound by that and does not change the critical path; leveling adjusts according to resource constraints and may go beyond the float and affect the critical path.
- Smoothing also changes dates, so you cannot tell the two apart by “whether dates changed”; look at whether the adjustment is held strictly within the float.
- Smoothing does not guarantee that every conflict is resolved. When the float is not enough, smoothing cannot resolve the whole conflict; if there are no extra resources and the conflict must be eliminated, you can turn to leveling.
- Do not treat resource optimization as schedule compression: crashing and fast tracking are meant to shorten the duration.
Critical Chain Method
Lesson 1: The Critical Chain Method and Buffers
- The resource-loaded and resource-leveled critical path is the critical chain; critical chain project management adds pooled buffers and the buffer protection index (BPI; the next lesson covers what it compares and how to use it).
- Activity durations contain no safety margin; the safety margin is pooled into buffers placed at particular positions on the schedule path.
- The project buffer is at the end of the critical chain and protects the finish date; the feeding buffer is where a non-critical chain merges into the critical chain.
- Buffers replace task-level insurance time; they are not added on top of it.
- PMBOK 8: the resource-loaded and resource-leveled critical path is the critical chain; the two are synonymous. Common exam practice: when a question contrasts a critical path “scheduled only from logical relationships, with resources not yet considered” with the critical chain, answer “the critical chain considers resource constraints”; this treats the path before resource optimization as the point of comparison, and does not mean that the critical path method itself cannot consider resources.
- A buffer is not added after every activity; it is placed in particular positions as a pool, and it replaces each activity's own insurance time rather than being added on top.
- The project buffer protects the finish date, and the feeding buffer keeps the critical chain from being dragged down by non-critical chains. Do not mix up the positions.
- The critical chain method is not schedule compression and not resource smoothing; adding people and overtime is crashing.
Lesson 2: Buffer Management, and Comparing the Critical Chain Method with the Critical Path Method
- Buffer management: during execution, compare the percentage of project buffer remaining with the percentage of critical chain remaining; the signal is called the buffer protection index (BPI).
- The BPI protects the finish date; the SPI (the ratio of EV to PV) gauges how far the project is from the schedule baseline.
- Critical chain project management pools uncertainty into buffers, and durations contain no safety margin; compared with a path scheduled only by logic, it highlights resource constraints (in PMBOK 8 both methods call for a resource-leveled critical path).
- The logic of the two methods is nearly identical; the real difference is whether the percentage of buffer remaining is calculated.
- The critical chain method is neither crashing nor resource smoothing.
- The BPI protects the finish date, and the SPI measures how far you are from the baseline. Their uses are different; do not swap them.
- The BPI compares the percentage of buffer remaining with the percentage of critical chain remaining; it is not EV against PV, nor EV against AC.
- PMBOK 8: both methods call for building a resource-loaded and resource-leveled critical path; in the context of identifying the longest path or chain of tasks in the schedule, that critical path is synonymous with the critical chain. Common exam practice: when a question contrasts “a path built only from logical relationships” with the critical chain, choose “the critical chain considers resource constraints”.
- Adding resources and approving overtime is crashing, not the critical chain method.
Crashing vs. Fast Tracking
Formulas
- Crash Cost SlopeExtra cost per day saved; crash the lowest-slope activity on the critical path first and re-analyze the critical path after compressing (common exam practice)
Lesson 1: Schedule Compression Basics and Crashing
- Schedule compression: shorten the schedule duration without reducing scope; redo the critical path analysis after compressing.
- When total float is negative, first analyze the cause and restore the schedule objective; you can compare schedule compression, adjusting the constraint and other options. When you use compression, the targets are critical path activities.
- Crashing: add resources to shorten the duration for the least incremental cost; it applies only to critical path activities that get faster when resources are added.
- Crash cost slope = (crash cost − normal cost) ÷ (normal duration − crash duration); crash the lowest slope first.
- Adding resources does not necessarily shorten the duration; only critical path activities that can be shortened by adding resources are suitable for crashing, and crashing may increase cost and/or risk.
- Schedule compression does not reduce scope. Cutting scope or skipping quality inspections is not schedule compression.
- You compress activities on the critical path. Compressing a non-critical path does not shorten the total duration.
- "Add extra resources", "approve overtime" and "pay to expedite" all describe crashing. They are not the critical chain method and not resource leveling.
- Adding resources does not necessarily shorten the duration, because the coordination cost of new people can cancel the effect. Only critical path activities that can be shortened by adding resources are suitable for crashing, and crashing may increase cost and/or risk.
- When a variance appears, analyze first and compare options. If the option changes an approved baseline or authorization, go through change control; within authority and tolerances, take corrective action directly.
Lesson 2: Fast Tracking, and a Worked Comparison with Crashing
- Fast tracking: turn sequential activities into activities that run at least partly in parallel; it may cause rework and increased risk, and needs more coordination.
- Before fast tracking, do the dependency analysis: review discretionary dependencies closely, and do not violate mandatory dependencies.
- Crashing mainly trades cost for time and fast tracking mainly trades risk for time; both may increase cost and risk.
- Multi-path compression: at each step choose the lowest-cost activity or combination that shortens all current critical paths, and compress together any new critical path that appears.
- When the schedule is behind, first analyze the variance and its root cause, then compare the cost, risk and feasibility of crashing, fast tracking and other corrective options. If the option affects the approved schedule baseline, submit and implement the approved change through the change control process.
- "Activities that were sequential are now parallel" and "start the following activity earlier" describe fast tracking, not adding resources.
- Fast tracking requires a close review of discretionary dependencies, and mandatory dependencies must not be violated. You must also confirm that the overlap really shortens the critical path.
- The main risks of fast tracking are rework and quality problems, and it may also increase cost.
- With several critical paths, compressing only one is as good as compressing none: every current critical path must be compressed enough to meet the target duration.
- Redo the critical path analysis after compressing. A path that was near-critical may become the new critical path.
Lesson 3: Choosing in Exam Questions: Crashing or Fast Tracking
- Two signals: can the logical relationships change, and can resources and budget be added (then confirm the activity is on the critical path and that compression really works).
- Budget can be increased, extra resources are available, and a critical path activity gets faster when resources are added: crashing. No extra resources, cost cannot increase, dependencies are discretionary and the overlap would shorten the critical path: evaluate fast tracking (it may still add cost and rework risk).
- The logical relationships are fixed: you cannot fast track, so crash if resources are available.
- CPI greater than 1 and SPI less than 1: cost efficiency is good while the schedule is behind; in common exam practice, when budget is authorized and critical path activities can be shortened by adding resources, lean toward crashing.
- Compression does not cut scope or quality; adaptive projects rely on reprioritizing the backlog and on velocity.
- "Add extra resources", "approve overtime" and "pay to expedite" describe crashing; "turn sequential activities into parallel ones" describes fast tracking.
- Do not choose crashing every time you see "speed up the schedule". First check whether there is budget and whether the logical relationships can change.
- Resource leveling may change the critical path and may lengthen the project duration, and compressing quality inspections or cutting scope is not schedule compression. Eliminate them when they appear as options.
- Monte Carlo analysis, earned value analysis and the critical chain method are not compression techniques.
- There is no fixed "schedule compression > crashing > fast tracking" order: first decide whether the stem asks about a category or a specific action, then match the conditions (common exam practice).
Schedule Baseline and Monitoring the Schedule
Lesson 1: The Schedule Baseline and the Three Forms of the Project Schedule
- The schedule baseline is the schedule model approved by stakeholders, with baseline start and finish dates, used for comparison with actual results. It can be changed through formal change control procedures (usually stricter on predictive projects, more flexible on adaptive and agile projects, which may even have no formal procedure).
- Contingency reserve is included in the schedule or cost baseline and can be used within established authority. Management reserve is not in the baseline; PMBOK 8: typically released at the discretion of senior leadership or management; common exam practice: use goes through change control.
- The schedule, cost and scope baselines together form the performance measurement baseline.
- Three common forms: milestone (high-level communication), summary bar chart (timing at a glance), detailed schedule (network diagram, for analyzing logic).
- Schedule data includes milestones, activities, activity attributes, assumptions and constraints, and is often supplemented by resource histograms and alternative schedules.
- The schedule baseline is not the project schedule. The baseline is the approved version, and changes to it go through change control; the project schedule is updated as work progresses.
- An unapproved draft cannot serve as the baseline. Establishing the baseline for the first time is approved by the sponsor or authorized stakeholders under the governance arrangements, and it is not a change to an existing baseline.
- For a scope change, evaluate its effect on the schedule and other baselines before approval. If it is approved and affects the approved schedule baseline, update the schedule baseline through the formal change control procedure; changing only the project schedule is not enough.
- The risk register and project calendars are project documents, not baselines. The baselines are the schedule, cost and scope baselines.
- A milestone schedule is often used for high-level communication, a bar chart shows activity timing at a glance, and a network diagram supports analysis of logical relationships. Choose the form by the stakeholders' information needs and do not swap them.
Lesson 2: Monitor and Control Schedule: Inputs, Tools, and the Focus for Predictive and Adaptive Projects
- Monitor and Control Schedule: monitor the project status to update the schedule and manage changes to the agreed-upon schedule, keeping the schedule realistic and executable.
- Tools: earned value analysis, trend analysis, variance analysis, what-if scenario analysis, burnup or burndown charts, plus the critical path method, resource optimization and schedule compression.
- SV = EV − PV and SPI = EV ÷ PV; use trend analysis to predict the future.
- Predictive projects look at status, reserves and changes; adaptive projects look at the amount of work delivered, velocity and backlog priority.
- When the team lacks confidence: review the estimates with the team and get their commitment.
- Trend analysis predicts the future, while root cause analysis finds the causes of problems that have already happened. They answer different questions.
- A milestone list is planning information. You cannot project later delays from it.
- Monitoring the schedule is not just looking at whether you are behind: you have to update the schedule and manage changes.
- Adaptive projects usually do not use baseline dates of individual activities as the main basis for monitoring. They compare the amount of work delivered and accepted with what was expected for that time cycle, and watch velocity, while still monitoring necessary milestones and date commitments.
- Schedule performance means comparing actual results with the applicable plan basis, not a verbal summary: predictive projects usually compare against the schedule baseline or agreed-upon schedule, and adaptive projects compare the amount of work delivered and accepted with what was expected for that time cycle.
Lesson 3: Variance Analysis and Schedule Changes
- The four steps for handling a deviation (common exam practice): analyze the cause first, compare with the control threshold, go through change control if the baseline must change, and finally update and communicate.
- A deviation inside the threshold is monitored as planned and handled within authority; beyond it, take the action the schedule management plan prescribes and escalate if necessary.
- A schedule baseline update modifies the original baseline, and once a significant change that affects the schedule is approved it must be formally integrated into the plan.
- An approved change that alters the timing updates the schedule baseline first.
- When the schedule forecast is later than the baseline, you can use it to evaluate responses such as schedule compression; resource optimization can also resolve resource supply and demand, over-allocation or uneven use.
- When a deviation appears, analyze the cause first. Do not immediately crash, add resources, cut scope or request reserves.
- A deviation within the control threshold is handled under the schedule management plan and authority; at or beyond the threshold, take the action the plan prescribes and escalate if it goes beyond your authority.
- To change the schedule baseline, you must submit a change request and update it only after approval. You cannot change first and file afterward.
- A baseline update must be formally integrated into the project management plan; changing only the project schedule is not enough.
- When an expected delay has not happened yet, review the plan and assess the impact first rather than crashing directly.
- Whether a deviation affects the finish date depends on its effect on the critical path, total float and near-critical paths: first find the lagging activities on the critical path; a deviation on a non-critical path that exceeds its total float will also delay completion.