- Resource Leveling and Resource Smoothing
Schedule
Resource Leveling and Resource Smoothing
PMP · Schedule · 2 lessons · about 22 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
The critical path method looks only at paths and not at resources: it assumes that the people and equipment each activity needs are always available. In reality, one person may be scheduled into two activities at once, and a piece of equipment may be available only for certain periods, so a schedule built this way cannot be executed. Resource optimization reconciles the dates the network logic gives with the resources actually available. There are two common techniques, resource leveling and resource smoothing, and they differ in whether the adjustment may go beyond the float and so affect the critical path and the finish date (leveling may; smoothing does not). This is one of the most frequently tested comparisons in the schedule topic.
By the end of this chapter you should be able to do the following. List the situations that call for resource optimization and tell them apart from schedule compression. Explain what resource leveling does and demonstrate with an example how it lengthens the duration. Explain the boundary of resource smoothing and judge whether the float is enough. Choose between leveling and smoothing from the signals in the question.
Lessons in this chapter
- Lesson 1: When resource optimization applies, and resource leveling. The three situations where it applies (resources available only at certain times and in limited quantities, resources overallocated, and a need to even out resource usage); resource optimization is not schedule compression; resource leveling adjusts start and finish dates, may affect and change the critical path and push back the finish date; includes a full worked example.
- Lesson 2: Resource smoothing, and how it differs from resource leveling. Resource smoothing delays activities only within float and does not change the critical path or the finish date; for the same network, whether the float is enough decides between smoothing and leveling; a comparison table and the signals to read in a question.
Chapter map
| Signal in the question | Choice | Critical path | Finish date |
|---|---|---|---|
| Resource conflict, a longer duration is acceptable | Resource leveling | May change, may lengthen | May be pushed back |
| Resource conflict, the finish date cannot change and float is sufficient | Resource smoothing | Unchanged | Not pushed back |
| Resource conflict, the finish date cannot change but float is not enough | Smoothing cannot fully resolve the conflict; you need to adjust the resource supply, the scope, the activity logic, or a constraint such as the finish date | Depends on the adjustment | Depends on the adjustment |
| You need to shorten the duration | Not resource optimization; look at crashing and fast tracking |
Study tips and practice
- When you read a question, first decide whether it is a resource problem or a schedule problem.
- Both leveling and smoothing change start dates, so do not tell them apart by whether dates change. Look at whether the adjustment stays strictly within the float.
- In a worked example, calculate the float first, then judge whether the delay exceeds it.
- The longest path once resource constraints are considered is exactly what the next chapter, the critical chain method, deals with.
Lesson 1
When Resource Optimization Applies, and Resource Leveling
Lesson overview
A schedule produced by the critical path method assumes that resources come whenever they are called. In reality, the same engineer may be assigned to two activities in the same period, or a piece of equipment may be available for only a few days, and a plan like that simply cannot be executed. Resource optimization reconciles the dates the network logic gives with the resources actually available. The common resource optimization techniques mentioned in PMBOK 8 are mainly resource leveling and resource smoothing; PMBOK 8 lists them as examples, and they are not the only two. This lesson first covers when resource optimization is needed and how it differs from schedule compression, then covers resource leveling; the next lesson covers resource smoothing and compares the two. It covers ECO: Process domain, Task 8 (Plan and manage schedule), and also touches on Task 4 (Plan and manage resources).
When resource optimization is needed
Resource optimization is needed in each of the following situations: shared or critically required resources are available only at certain times or in limited quantities; resources are overallocated, for example when the same resource has been assigned to two or more activities during the same time period; or there is a need to keep resource usage at a constant level, avoiding sharp ups and downs. Resource optimization modifies the schedule model according to the supply of and demand for resources, and there are two common techniques: resource leveling and resource smoothing.
In the fourth step of developing the schedule, PMBOK 8 also reminds you that once the draft schedule is complete, team members should check whether the dates assigned to them conflict with resource calendars or with tasks on other projects, and then determine whether resource leveling is needed before the schedule is approved as the baseline. Resource demand is usually drawn as a resource histogram, with time on the horizontal axis and the quantity of resources on the vertical axis, and a day on which demand exceeds availability can be seen at a glance.
When you read a question, first decide what kind of problem it is. Resource optimization deals with whether resources are sufficient and how to sequence conflicts; schedule compression (crashing and fast tracking) deals with how to shorten the duration. When the stem says “resources are limited and no new resources can be obtained” and asks how to resolve a resource conflict, it is a resource problem, and the answer is found in resource optimization. Only when the question asks you to shorten the duration do you look at crashing and fast tracking (crashing does not necessarily mean adding people; approving overtime or paying to expedite also counts, depending on whether the stem allows extra cost). Only when the stem says “without delaying the project” do you narrow down further to resource smoothing.
Resource leveling
Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources, and which may affect the critical path. It adjusts the start and finish dates of activities based on resource constraints, with the goal of balancing the demand for resources with the available supply. Available float can be used, so the project's critical path may change; the common result is that the critical path gets longer and the finish date is pushed back, although if the adjustment falls entirely within the available float, the duration may also stay the same.
Worked example: resource leveling lengthens the duration (Day 1 start)
After A (done by Ana, 2 days), B (Ben, 3 days) and D (Ben, 3 days) can start at the same time; after B comes C (Cole, 4 days); after D comes E (Dana, 3 days); when both C and E are finished, F (Eli, 2 days) follows.
Step 1: Schedule by logic. A runs Days 1-2; B and D both run Days 3-5; C runs Days 6-9 and E Days 6-8; F runs Days 10-11. A-B-C-F = 2 + 3 + 4 + 2 = 11 days is the critical path; A-D-E-F = 2 + 3 + 3 + 2 = 10 days has 1 day of total float.
Step 2: Spot the conflict. On Days 3-5 Ben has to do both B and D. On the resource histogram, Ben's demand on those three days is 2, but there is only 1 person.
Step 3: Level. Start with the non-critical activity: make D wait until B is done, so D runs Days 6-8, a delay of 3 days, which exceeds the 1 day of float. E is pushed to Days 9-11, and F has to wait for C (done on Day 9) and E (done on Day 11), so F runs Days 12-13.
Step 4: Result. The total duration goes from 11 days to 13 days. The new longest path is A-B-D-E-F = 2 + 3 + 3 + 3 + 2 = 13 days, and the formerly critical activity C now has 2 days of float.
Step 5: Check. From Day 3 to Day 8 Ben does only one activity each day, so the conflict is gone. The extra 2 days of duration are the price paid to keep Ben from being in two places at once (to avoid overlapping the assignments of B and D).
This example shows why resource leveling “may affect and lengthen the critical path”: to keep one resource from being split, a “resource relationship” (D has to wait for B) is added on top of the logical relationships. When leveling, it is best to move activities on non-critical paths first, because once activities on the critical path are moved, the duration is bound to be affected. Resource leveling is one of the effective ways to achieve resource optimization; if the adjustment goes beyond the available float, the duration may be lengthened.
In predictive projects, resource leveling is usually done before the schedule baseline is approved. Adaptive projects usually manage workload through timeboxes, team capacity and limiting work in progress, and rarely use activity-by-activity leveling based on a detailed activity network; scarce or shared resources still need to be coordinated when necessary.
Worked examples
Example 1 Scenario: not enough resources and no way to add people. What now?
The project manager at a manufacturer is responsible for two projects at once. One of them, a key project, needs a shorter duration, but there are not enough people, and the company has made clear it will add no more staff to either project. The activities in the schedule must be done in sequence, and none can run in parallel. What should the project manager do?
Show answer and explanation
Correct answer: D
The project manager runs two projects at once. The key project needs a shorter duration, but people are short, the company will not add staff, and the activities must be done in sequence with no room for parallel work.
Rule out the routes that do not work first: no more staff can be added, and with no activities that can run in parallel, fast tracking cannot be used. The resources are shared by the two projects, so analyze the two projects together to find the most effective way to allocate the shared resources, and adjust accordingly. This is the resource optimization approach of assessing before acting. The answer is D.
Why the other options are wrong
- A. Starting training without analyzing the problem jumps straight to a solution. Training also does not guarantee that skills meet project requirements, let alone shorten the duration.
- B. The stem states that the company will add no more staff, so asking for more people is a dead end. First optimize the shared resources across the two projects.
- C. Fast tracking requires activities that can run in parallel, and the stem says there are none, so the technique cannot be used.
Key takeaway When resources are short and fast tracking is not possible, first analyze and coordinate the shared resources; do not go straight to adding people, training or applying compression techniques.
Variation Only if activities could run in parallel would fast tracking be an option, and only if the company were willing to add staff, approve overtime or pay extra would crashing be an option; when resources are in conflict rather than short, use resource leveling.
Something wrong with this question?
Example 2 Scenario: specialists are pulled away by several projects. How do you avoid added cost when planning?
A group's ERP rollout project is over budget. The cause is that the external implementation consultants cannot start until the company's internal business experts provide input, and those experts support several projects at once, so the input arrives late and the consultants are held up. After a review, the project manager concludes that this constraint should be considered when the schedule for the later phases is developed, to keep such costs from rising further. Which technique should be used?
Show answer and explanation
Correct answer: C
After a review, the project manager wants to handle this in the schedule for the later phases. The external consultants wait for the internal experts' input before they can start, the experts support several projects, and the consultants are held up, causing a cost overrun. The question asks which technique to use when developing the schedule to keep costs from rising further.
The root cause is that the schedule did not take into account the resource constraint that the experts are available only at certain times and in limited numbers. Resource leveling adjusts the start and end dates according to resource constraints so that the demand for resources balances with the available supply, scheduling the consultants' work after the experts' input so they do not sit idle. The answer is C.
Why the other options are wrong
- A. Crashing compresses the duration by adding resources and overtime, which increases cost, and here the aim is to avoid cost increases. It also does not solve the constraint that the experts are not available.
- B. Fast tracking overlaps activities. The consultants cannot start without the experts' input, so overlapping would only lengthen the waiting and raise the risk of rework.
- D. A contingency reserve can set aside budget at planning time for identified risks, but it only provides a cost cushion. It cannot resolve the resource constraint of the experts' limited availability.
Key takeaway When a key resource is split among several projects, use resource leveling to build the resource constraint into the schedule when you develop it.
Variation If the experts' free time falls within the float of the consultants' activities and the finish date must not change, resource smoothing is enough and the duration does not have to be extended.
Something wrong with this question?
Common traps
Common trap
- Resource optimization is not schedule compression: compression shortens the duration, while resource optimization makes the schedule feasible, and the duration may even get longer.
- Resource leveling can adjust critical path activities, so it may change the critical path and delay the finish date (if the adjustment falls entirely within the available float, the duration may also stay the same); resource smoothing does not change the critical path or delay the finish date (next lesson).
- A schedule produced by the critical path method does not consider resources, so it cannot be treated directly as an executable schedule.
- Do not resolve resource conflicts by “approving the baseline first and dealing with them one by one during execution”: you should decide whether leveling is needed before the baseline is approved.
- When the stem clearly says “no more people will be added”, asking for staff is a dead end, and you should first analyze and coordinate the existing resources. Crashing (in PMBOK 8: approving overtime, bringing in additional resources, or paying to expedite delivery) does not necessarily require adding people, so unless the stem also rules out overtime or extra cost, you cannot rule it out directly.
Key takeaways
Key point
- The three situations that need resource optimization: resources available only at particular times and in limited quantities, overallocated resources, and a wish to even out usage.
- There are two common resource optimization techniques, resource leveling and resource smoothing; neither is schedule compression.
- Resource leveling adjusts start and finish dates according to resource constraints, with the goal of balancing demand and supply.
- Resource leveling can use float and may change and lengthen the critical path, so move non-critical path activities first where possible.
- Before the baseline is approved, check the resource calendars and determine whether resource leveling is needed.
Lesson 2
Resource Smoothing, and How It Differs from Resource Leveling
Lesson overview
Resource leveling from the previous lesson can resolve resource conflicts, at the price of possibly lengthening the duration. What if the sponsor says the finish date cannot move by a single day? First try resource smoothing within the available float; if the float is insufficient, smoothing cannot resolve the whole conflict, and the constraint among the date, resources and scope must be addressed. This lesson first covers the definition and the boundaries of resource smoothing, then uses the same network in a comparison example to show how whether the float is enough decides “whether smoothing alone will do”, and finally lists the differences between leveling and smoothing and summarizes the signals to look for in a question. The difference between the two is one of the most frequently tested comparisons in the schedule topic. It covers ECO: Process domain, Task 8 (Plan and manage schedule).
Resource smoothing
Resource smoothing is a resource optimization technique in which free and total float are used without affecting the critical path. It adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. In resource smoothing, as opposed to resource leveling, the project's critical path is not changed and the completion date may not be delayed. In other words, activities may only be delayed within their free and total float. Resource smoothing may not be able to optimize all resources.
Three boundaries of smoothing are hidden in this passage: only activities that have float can be delayed; the delay cannot exceed the float; and when the float is not enough, the conflict cannot be resolved. So smoothing is a best-effort technique. Leveling can adjust dates further according to resource constraints and can usually resolve more conflicts, but it may change the critical path or push back the finish date, and it does not guarantee a complete resolution in every case either.
How to do it: the same network, and the float decides which to use
Take the network from the previous lesson: after A (Ana, 2 days), B (Ben, 3 days) and D (Ben, 3 days) can start at the same time; after B comes C (Cole, 4 days); after D comes E (Dana); when C and E are done, F (Eli, 2 days) follows. B and D both run Days 3-5, so Ben is assigned two activities at once. The conflict is the same; we change the duration of E and look at the result.
Case 1: E takes only 1 day, and smoothing alone is enough
Step 1: Find the float. A-B-C-F = 11 days is the critical path; A-D-E-F = 2 + 3 + 1 + 2 = 8 days, so D and E have 11 − 8 = 3 days of total float between them.
Step 2: Smooth. Delay D to Days 6-8, a delay of 3 days, exactly equal to the float and not beyond it. E is placed on Day 9, and F starts on Day 10, running Days 10-11 and finishing on Day 11, because C finishes on Day 9.
Step 3: Check. From Day 3 to Day 8 Ben does one thing each day; the total duration is still 11 days, the original critical path A-B-C-F has not lengthened, and the finish date has not moved. The 3 days of float of D and E are fully used up, and A-D-E-F has also reached 11 days, so there is no more room for delay, and from here on any slip on it affects the finish date. The adjustment all falls within the float, and this is resource smoothing.
Case 2: E takes 3 days, and smoothing is not enough
The path through D and E is 10 days long, with only 1 day of total float, and a 3-day delay exceeds it by 2 days. If you insist that Ben not be in two places at once, the duration must lengthen, and you have to accept resource leveling. Let Ben do B first and D afterward, forming a B→D resource order; the longest sequence that determines the finish date becomes A-B-D-E-F (including the resource-constrained order), for a total duration of 13 days. The logical relationships in the two cases are the same; the difference is that E's duration differs, which decides whether the float is enough.
How leveling and smoothing differ
| Resource leveling | Resource smoothing | |
|---|---|---|
| Goal | Balance resource demand with the available supply | Keep resource demand from exceeding predefined limits |
| What it may use | May use critical path activities and float | Delays only within free and total float |
| Critical path | May change; the common result is that it lengthens | Does not change |
| Finish date | May be pushed back | Is not pushed back |
| Effect | Best-effort balancing, possibly at the cost of a longer duration; may still not fully optimize when resources are absolutely insufficient | May not be able to optimize all resources |
Both techniques change the start dates of activities, so you cannot tell them apart by “whether dates changed”. What matters is whether the adjustment is held strictly within the float: resource smoothing must stay within the float and not affect the critical path; resource leveling is not bound by this restriction (a particular result may still stay within the float and leave the critical path unchanged).
Signals to read in a question, and how to apply them
- The question requires that “the finish date cannot change” or says “the client insists on on-time delivery”, and no outside resources are available: first try resource smoothing by moving non-critical activities later within their float. It can fully resolve the conflict only if enough float is available; otherwise the constraint conflict must be addressed.
- The question accepts a longer duration, or says “add three weeks to the schedule to resolve the resource unavailability”: resource leveling.
- When a key member is temporarily absent and the finish date should be affected as little as possible, if every candidate activity can release someone with the required skills and each reassignment causes the same activity delay, common exam practice is to pull from the activity with the longest total float because it can best absorb that delay.
- The same resource is scheduled on a critical activity and on an activity with float: making the activity with float wait is smoothing; making the critical activity wait lengthens the duration and is leveling.
Worked examples
Example 1 Scenario: a member is temporarily unavailable. Where do you pull someone from?
A multi-year ERP rollout project is in execution when a key team member suddenly resigns. The team is one person short, and a replacement will not arrive for several weeks. Several candidate activities can each release a member with the required skills, and pulling a member would cause the same activity delay in each case. The project manager decides to use a resource optimization method to minimize the effect. From which kind of candidate activity should the member be pulled?
Show answer and explanation
Correct answer: A
The project is in execution. A key member has suddenly resigned, and a replacement will not arrive for several weeks. The project manager wants to use resource optimization to minimize the effect. The question asks from which kind of activity to pull a member.
If you pull people from activities that have float, delaying those activities mainly consumes their float. As long as the delay stays within the available total float, the finish date is unaffected, which is exactly what resource smoothing does. The longer the total float, the more delay it can bear and the smaller the effect, so pull from the activity with the longest total float. Taking people from the critical path would deliberately push back the finish date, the opposite of the goal of minimizing the effect. The answer is A.
Why the other options are wrong
- B. Starting early does not mean having float; the activity may be on the critical path. Pulling people from it cannot guarantee that the finish date is unaffected.
- C. The activity furthest behind schedule needs the people more, and taking more would let the slippage grow. It may also be on the critical path.
- D. Critical path activities usually have the least float, so taking resources from them is the most likely to lengthen the critical path and the project duration. You should prefer to reassign people from activities that have more available total float and a matching skill set.
Key takeaway The critical path protects the duration, and non-critical paths supply resources; pulling people from the activity with the longest total float has the least effect.
Variation If the gap is larger than all the float can accommodate, smoothing is not enough, and you can only level resources and accept a longer duration, or look for other resources.
Something wrong with this question?
Example 2 Concept question with numbers: whom do you delay first?
On a project, only one engineer can do Activity M and Activity N, and both activities are scheduled for Days 4 to 6, which creates a conflict. M is on the critical path and has zero total float, while N has 5 days of total float. Which two judgments are correct? (Choose 2.)
Show answer and explanation
Correct answer: BC
Only one engineer can do M and N, and both are scheduled for Days 4 to 6. M is on the critical path, and N has 5 days of total float. You must judge whom to delay first and which technique each choice is.
The difference between smoothing and leveling lies in whether the delay goes beyond the float and whether the critical path is touched. Making N wait for M, so N runs from Day 7, delays N by 3 days, which does not exceed its 5 days of float, so the finish date and the critical path do not change; this is resource smoothing, and B is correct. Making M wait for N delays M, which has no float, by 3 days, so the finish date slips 3 days; this uses the critical path and is resource leveling, and C is correct. The answers are B and C.
- Option 1: M on Days 4-6, N on Days 7-9; N is delayed 3 days, 3 ≤ 5, the finish date is unchanged: smoothing
- Option 2: N on Days 4-6, M on Days 7-9; M is delayed 3 days and has no float, so the finish date slips 3 days: leveling
Why the other options are wrong
- A. M is on the critical path and has no float, so delaying it necessarily delays the finish date.
- D. Both techniques change start dates. The criterion is not whether dates change but whether the delay goes beyond float and touches the critical path; N's delay is within its float, so it is smoothing.
Key takeaway Delaying an activity within its available float to resolve a resource conflict is resource smoothing. If the adjustment instead delays a zero-float critical-path activity, it is resource leveling and affects the project duration.
Variation If N had only 2 days of total float, a 3-day delay would exceed it by 1 day; N's path would then become the new longest path and the finish date would slip 1 day, so it could only count as resource leveling.
Something wrong with this question?
Common traps
Common trap
- When the question requires “no delay”, so you can only adjust within float: resource smoothing. When a longer duration is acceptable: resource leveling.
- The two terms differ by only one word, and the exam tests whether the adjustment is held strictly within the float: smoothing is bound by that and does not change the critical path; leveling adjusts according to resource constraints and may go beyond the float and affect the critical path.
- Smoothing also changes dates, so you cannot tell the two apart by “whether dates changed”; look at whether the adjustment is held strictly within the float.
- Smoothing does not guarantee that every conflict is resolved. When the float is not enough, smoothing cannot resolve the whole conflict; if there are no extra resources and the conflict must be eliminated, you can turn to leveling.
- Do not treat resource optimization as schedule compression: crashing and fast tracking are meant to shorten the duration.
Key takeaways
Key point
- Resource smoothing delays activities only within free and total float, and does not change the critical path or push back the finish date.
- When the float is not enough, smoothing cannot resolve all the conflicts; in this example, with no extra resources and the conflict having to be eliminated, resource leveling is needed and the duration lengthens; in general, resource leveling may change the critical path or push back the finish date.
- Leveling can use the critical path and may lengthen the duration; smoothing leaves the critical path and the duration alone.
- To tell them apart, look at “whether the adjustment is held strictly within the float”, not at “whether dates changed”.
- When people are short and you cannot slip the date, if candidate members have the required skills and each reassignment causes the same delay, pull from the activity with the longest total float.
This chapter has 14 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.