PMP Study Guide
Schedule
The PMP study guide for Schedule: 9 chapters and 23 lessons, about 4 h 26 min of study. Every lesson has worked examples with the explanation folded until you open it. Read the topic guide first ↓
Watch the free Schedule videos in the PMP video course →
Chapters in this topic
- 34Rolling Wave Planning and Developing the Schedule2 lessons
- 35Precedence Diagramming Method2 lessons
- 36Estimating Techniques for Duration3 lessons
- 37Multipoint (Three-Point) Estimating2 lessons
- 38Critical Path Method4 lessons
- 39Resource Leveling and Resource Smoothing2 lessons
- 40Critical Chain Method2 lessons
- 41Crashing vs. Fast Tracking3 lessons
- 42Schedule Baseline and Monitoring the Schedule3 lessons
Topic guide
What this topic covers
Schedule management answers three questions: when will the project finish, when will each activity be done, and what do we do when variances appear? PMBOK 8 places it in the Schedule Performance Domain, whose aim is to deliver the project on time. First it establishes how the schedule will be developed and managed. Then it turns the work step by step into a schedule model with sequence and timing. Finally it monitors and maintains that schedule during execution. After studying this topic you should be able to do the following. State what goes into a schedule management plan. Develop the schedule in four steps. Draw a network diagram and identify logical relationships. Estimate durations, including with multipoint estimating. Use the critical path method to calculate the duration and float. Recognize and resolve resource conflicts. Choose the right compression method when time is tight. Explain what the schedule baseline is for and respond correctly to variances.
Three processes, four steps, nine chapters
The Schedule Performance Domain in PMBOK 8 has three processes: Plan Schedule Management, Develop Schedule and Monitor and Control Schedule. PMBOK 8 folds defining activities, sequencing activities and estimating activity durations into the single process Develop Schedule, which runs internally in the four steps listed in Section 2.3.2.2: define activities, determine sequence, estimate effort and duration, and adjust. It is the process that is merged. None of the methods has gone away, and the exam still tests them, so this course teaches them in chapters organized by technique.
| Chapter | Related process or step | In one sentence |
|---|---|---|
| Rolling Wave Planning | Plan Schedule Management; Develop Schedule step 1 | Set the rules first, then break work packages into activities, and roll the plan forward when information is thin |
| Precedence Diagramming Method | Step 2, determine sequence | Who goes first and who goes second, drawn as a network diagram |
| Estimating Techniques for Duration | Step 3, estimate effort and duration | How long each activity takes, and how to hold reserves |
| Multipoint Estimating | Step 3 (a technique) | Three values to express uncertainty |
| Critical Path Method | Step 4, adjust | The longest path sets the duration, and float is calculated |
| Resource Leveling and Smoothing | Step 4, adjust | When there are not enough resources, adjust the dates |
| Critical Chain Method | Step 4, adjust | Takes resource constraints into account and pools safety time into buffers |
| Crashing and Fast Tracking | Step 4, adjust | What to do when the duration is too long |
| Schedule Baseline | Approving the baseline; Monitor and Control Schedule | What the approved plan is, and how to handle variances |
In the exam content outline, schedule falls mainly under Process domain Task 8, "Plan and manage schedule": developing the schedule according to the chosen development approach, coordinating with other projects and operational activities, estimating project tasks (milestones, dependencies, story points), using benchmarks and historical data, creating the schedule, establishing the baseline, executing the schedule management plan and analyzing schedule variances.
How the chapters fit together
Following the four steps of developing the schedule, the nine chapters form a pipeline: set the rules and break out activities (rolling wave planning); sequence (precedence diagramming method); estimate time (estimating techniques, multipoint estimating); calculate the duration and find what is critical (critical path method); adjust resources and duration (resource leveling and smoothing, critical chain method, crashing and fast tracking); and fix the baseline and watch the variances (schedule baseline). The calculations are concentrated in the middle: multipoint estimating calculates expected values, the critical path method does forward and backward passes and float, and compression questions calculate how paths change. The result of one step usually becomes the input to the next analysis: the activity list goes into the network diagram, the durations go into the critical path, and the critical path decides what can be compressed. But developing the schedule is iterative, and you go back and revise activities, sequence, estimates or resource arrangements when necessary.
The three development approaches have different emphases. Predictive projects typically establish and approve an overall schedule baseline early (rolling wave planning can be used to elaborate near-term activities step by step), and changes follow a formal procedure. Adaptive projects are often planned on fixed timeboxes and iterations that roll forward, and may also use flow-based scheduling such as Kanban, adjusting through release planning and backlog prioritization. Hybrid projects use key milestones for the high-level schedule, and the parts beneath them each use the method that suits them. Each chapter contrasts predictive and adaptive approaches, so first check which one a question is using.
How to study
Study in order, and work the calculation chapters with a pencil. Remember the four steps and what each one produces: the activity list, the network diagram, duration estimates, and the project schedule (the schedule baseline is established when it is approved). When a question asks "what is the next step?", first work out how far the project has got. Master five distinctions: mandatory versus discretionary dependencies, leads versus lags, total float versus free float, resource leveling versus resource smoothing, and crashing versus fast tracking. Practice three question types: scenario questions (next step, choose a technique), concept questions (keywords that map to techniques) and calculation questions (expected value, paths and float, duration after compression). Always write out the full expression for a calculation question and check it. For example, an expected value must fall between the optimistic and pessimistic values, and with path lengths you take the longest in the end. The explanation of each worked example is collapsed by default. Try it yourself first, then expand it to compare.
Common ways to lose points
- Treating the schedule management plan as the schedule: the former establishes how the schedule is developed and controlled, while activity-specific planned dates belong in the project schedule.
- Mixing up effort and duration estimates: adding resources does not always shorten the duration.
- Using the wrong formula in multipoint estimating when no distribution is specified, or putting the 4 in the wrong place.
- Reversing predecessor and successor when identifying logical relationships, or reversing the direction of lags and leads when calculating paths.
- Confusing total float with free float, and forgetting that there can be more than one critical path.
- Resource leveling can (and often does) change the critical path, while resource smoothing does not change the critical path.
- Crashing typically increases cost, while fast tracking may increase rework and risk; each applies under different conditions.
- The schedule baseline of a predictive project can be changed only through the Assess and Implement Changes process (in PMBOK 8's wording, following integrated change control). An adaptive project updates its schedule through the flexible mechanism it has agreed. If an error is found before the baseline is approved, simply correct it.