Precedence Diagramming Method

PMP · Schedule · 2 lessons · about 27 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Once the activities are defined, you move to step 2 of developing the schedule: determine sequence. This step answers which activities must wait for others to finish and which can run at the same time, and draws the answer as a schedule network diagram. The usual technique is the precedence diagramming method (PDM), in which activities are drawn as nodes and linked by logical relationships. This chapter covers how to read a network diagram, how to identify the four logical relationships, how dependencies are classified, and how leads and lags are marked and calculated. It is the skeleton for the later work on estimating durations and on the critical path method, and the basis of calculation questions.

By the end of this chapter you should be able to do the following. Explain what predecessor activity, successor activity, path convergence and path divergence mean. Tell from a single sentence whether a relationship is FS, FF, SS or SF. Distinguish mandatory from discretionary dependencies and external from internal dependencies, and know that when you fast track, you review discretionary dependencies first. Read notations such as FS−3 and SS+10, and handle leads and lags correctly when you calculate path lengths.

Lessons in this chapter

Chapter map

Activity list → determine sequence → schedule network diagram (node method / AON)  
  Logical relationships: FS (most common), FF, SS, SF (rarely used)  
  Dependencies: mandatory (hard logic) / discretionary (soft logic); external / internal  
  Link notation: lead (FS−3), lag (FS+2) — they do not replace logical relationships and are not part of durations  
Simple all-FS path: path length = sum of activity durations + lags − leads; take the longest path  
(with SS, FF or SF relationships, calculate early start and early finish item by item according to each relationship's constraint)  

How the exam tests this

There are three kinds of questions. First, you are given one sentence and must identify the logical relationship; the key is "which end of the predecessor it depends on, and which end of the successor it constrains". Second, dependency scenario questions: a dependency on a non-project activity that the team usually does not control, a sequence that cannot change because of law, contract or the nature of the work, and a practice adopted from preference although another acceptable sequence exists, correspond to an external, a mandatory and a discretionary dependency respectively. Third, path calculations with leads and lags, where you list all the paths, add lags, subtract leads and take the longest.

Study tips and practice

  • To identify a relationship, sketch the two activities and circle the end each relationship depends on and the end it constrains.
  • For path calculations, always list every path first and calculate each one. Do not calculate only the path that looks longest.
  • This chapter ties closely to schedule compression: fast tracking begins with a review of discretionary dependencies, while crashing does not change dependencies.

Lesson 1

The Precedence Diagramming Method: Network Diagrams and the Four Logical Relationships

Lesson video

Lesson overview

Once activities are defined, you need to answer "who goes first and who goes second": which activities must wait for others to finish and which can run at the same time. This is step 2 of developing the schedule, and the usual diagramming technique is the precedence diagramming method (PDM). The schedule network diagram it produces is the skeleton for the later estimating and for calculating the critical path. This lesson covers two things: how to read a network diagram, and how to identify the four logical relationships among activities. The most common exam question gives you a sentence and asks which relationship it describes, and there are also scenario questions about what to do when a dependency has been marked wrongly. The next lesson covers types of dependencies and leads and lags. ECO: Process domain, Task 8 (Plan and manage schedule), which includes estimating project tasks (milestones, dependencies and so on).

The precedence diagramming method and the network diagram

Determine sequence is about determining the logical sequence in which the work will be carried out, to obtain the greatest efficiency given all of the project constraints. The precedence diagramming method is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed. It is also called the node method or AON (activity on node).

The activities at the two ends of a link have fixed names. A predecessor activity is an activity that logically comes before a dependent activity in a schedule. A successor activity is a dependent activity that logically comes after another activity in a schedule. Every work package and activity, except for the first and last, should be connected to at least one predecessor and at least one successor. An activity with more than one predecessor indicates a path convergence, and an activity with more than one successor indicates a path divergence. A convergence is held up by several activities and a divergence affects several, so risk is more concentrated there. PMBOK 8 also says that when multiple paths converge at a single point in time, or diverge from a single point in time, you should assess the need to aggregate schedule reserves.

Example: reading the network diagram of a neighborhood group-buying mini-app

The activities and their predecessors are as follows.

ActivityPredecessor
A Confirm requirementsNone
B Design the interfaceA
C Back-end developmentA
D Front-end developmentB
E Integration testingC, D
F Go liveE
  • A has two successors, B and C, so it is a path divergence: once requirements are confirmed, design and back-end work can start at the same time.
  • E has two predecessors, C and D, so it is a path convergence: integration cannot start until both the back end and the front end are done.
  • There are two paths from start to end: A→B→D→E→F and A→C→E→F. They meet at E, and F after it has only one predecessor.

A project schedule network diagram is a graphical representation of the logical relationships (also called dependencies) among the project schedule activities, and it can be drawn with project management software. Depending on the degree of decomposition, the sequence can be determined at different levels, including the control account, the work package or the activity.

The four logical relationships

The precedence diagramming method has four logical relationships. They differ in whether they depend on the start or the finish of the predecessor, and whether they constrain the start or the finish of the successor:

RelationshipMeaningExample
Finish-to-start (FS)A successor activity cannot start until a predecessor activity has finishedInstalling the operating system on a PC cannot start until the PC hardware is assembled
Finish-to-finish (FF)A successor activity cannot finish until a predecessor activity has finishedWriting a document is required to finish before editing the document can finish
Start-to-start (SS)A successor activity cannot start until a predecessor activity has startedLeveling concrete cannot begin until pouring the foundation begins
Start-to-finish (SF)A successor activity cannot finish until a predecessor activity has startedA new accounts payable system has to start before the old accounts payable system can be shut down
Figure 1: The four logical relationships of the precedence diagramming method

To identify a relationship, use a fixed two-question reading. In the name, the part before "to" refers to the start or finish of the predecessor, and the part after it refers to the start or finish of the successor. First ask: does the relationship constrain the start or the finish of the successor? Then ask: does it depend on the start or the finish of the predecessor? Together the two answers give the name. For example, "the review can be wrapped up only after the final drafts of all chapters are finished": it depends on the finish of the drafts and constrains the finish of the review, so it is FF. Or "the live broadcast can be switched on only once screen recording has started": it depends on the start of the recording and constrains the start of the broadcast, so it is SS.

In the precedence diagramming method, FS is the most commonly used logical relationship and SF is rarely used. An unlabeled link does not always mean FS. Common exam practice: in exam questions and typical network diagrams, an ordinary link with no relationship type marked is usually read as FS, unless the stem says otherwise.

Worked examples

Example 1 A dependency found wrongly marked before the baseline is approved

Question 1Example

A project manager on a logistics system project is developing the schedule, and the schedule baseline has not yet been approved. While reviewing the schedule network diagram, the project manager finds that the dependency between “user training” and “system go-live” was marked wrongly. What should the project manager do?

Show answer and explanation

Correct answer: A

A logistics system project is developing its schedule and the schedule baseline has not been approved. In reviewing the network diagram, the project manager finds the dependency between “user training” and “system go-live” is marked wrongly. What should the project manager do?

The schedule network diagram is a product of the determine sequence step, and a wrong dependency will affect every date and the critical path derived from it. The baseline has not yet been approved, so the network diagram and the schedule are still drafts. The project manager should correct the network diagram directly and update the schedule accordingly. Change control applies to approved baselines, which is not the case here, and there is no need to ask anyone else for approval. The answer is A.

Why the other options are wrong

  • B. Change requests and the change control board handle changes to approved baselines. Finding an error in a draft and sending it through the change procedure makes a simple problem complicated.
  • C. Using schedule reserve to absorb an error that could simply be corrected means carrying on with wrong logic, and the critical path and dates will be unreliable.
  • D. Dependencies are part of the project manager's and team's work when they determine sequence. The sponsor does not need to confirm them first, and treating a correction as a decision to escalate is also wrong.

Key takeaway If an error in the network diagram is found before the baseline is approved, correct it directly and update the schedule. Change control applies after approval.

Variation If the schedule baseline had already been approved, a wrongly marked dependency would require a change request, and the baseline would be amended only after change control.

Something wrong with this question?

Report an issue with this question

Example 2 "Can finish only after it finishes": which relationship

Question 2Example

An equipment operating manual is written chapter by chapter, and the reviewers are reviewing each chapter as it is written. The agreement in the schedule is that the review can wrap up only after the final drafts of all chapters are finished. In the schedule network diagram, which logical relationship should be used between “chapter final drafts” and “review”?

Show answer and explanation

Correct answer: D

An equipment operating manual is written chapter by chapter, and the reviewers review each chapter as it is written. It is agreed that the review can wrap up only after the final drafts of all chapters are finished. Which logical relationship links “chapter final drafts” and “review”?

Use two questions to identify a relationship. For the successor being constrained (the review), is it the start or the finish that is limited? The stem limits when the review can “wrap up”, that is, its finish. For the predecessor it depends on (the chapter final drafts), is it the start or the finish? It is “the final drafts are all finished”, that is, the finish. Depending on a finish and constraining a finish gives finish-to-finish (FF). The review may well have started long ago. It just cannot finish before the final drafts are finished, and that is a finish-to-finish constraint. The answer is D.

Why the other options are wrong

  • A. FS constrains the start of the successor, meaning the review could start only after the final drafts were done. The stem says the review runs along with the writing chapter by chapter and does not wait for the final drafts.
  • B. SS constrains the start of both activities, whereas the stem is about when the review finishes, so it does not fit.
  • C. SF depends on the start of the predecessor and constrains the finish of the successor. The stem depends on the finish of the final drafts, so it is not SF.

Key takeaway “It can finish only after the other finishes” is FF. The part before “to” is what it depends on (the predecessor) and the part after is the constrained end (the successor).

Variation If it said “the review can start only after the final drafts start”, that is SS. If it said “the review can start only after the final drafts are finished”, that is FS.

Something wrong with this question?

Report an issue with this question

Example 3 "Can start only after it starts": which relationship

Question 3Example

To make later review easier, an online course team requires that the live lesson can be switched on only once the screen-recording software has been started. The recording does not have to finish first. Which logical relationship should be used between “start recording” and “start the live broadcast”?

Show answer and explanation

Correct answer: C

An online course team requires that the live lesson can be switched on only once the screen-recording software has been started, and the recording does not have to finish first. Which logical relationship links “start recording” and “start the live broadcast”?

First see what is constrained: the start of the live broadcast. Then see what it depends on: the start of the recording. Only once the recording has started can the broadcast start. The stem specifically says the recording does not have to finish first, which rules out FS. Depending on a start and constraining a start gives start-to-start (SS). SS fixes only the order of the two starts. It does not require the predecessor to be finished, and it does not mean the two start at the same time. The answer is C.

Why the other options are wrong

  • A. FS would require the recording to finish before the broadcast starts. The recording runs alongside the broadcast, and the stem says it need not finish first.
  • B. FF constrains when the two finish. The stem is about starting the recording and switching on the broadcast, which are starts, so it does not fit.
  • D. SF depends on the start of the predecessor and constrains the finish of the successor. What the stem constrains is the start of the broadcast, not its finish.

Key takeaway “It can start only after the other has started” is SS. The predecessor does not have to be finished.

Variation If it said “the broadcast can end only after the recording has started”, the constrained end would be the finish of the broadcast, which is SF. If it said “the broadcast can start only after the recording ends”, that is FS.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • To identify a relationship, ask two things: is it the start or the finish of the successor that is constrained, and is it the start or the finish of the predecessor that it depends on? The part before "to" is the predecessor and the part after it is the successor.
  • FF and SS do not mean "at the same time". They fix the order at only one end, and the other end can still be offset.
  • Descriptions like "can finish editing only after the writing is finished" are usually FF, and descriptions like "switching from the old system to the new one" are usually SF. Do not assume everything is FS.
  • A predecessor is not an activity that is "earlier in time". It is an activity that comes first on the logical path. The same goes for a successor.
  • If an error in the network diagram is found before the schedule baseline is approved, simply correct it and update the schedule. After the baseline is approved, a change in a predictive project goes through change control (adaptive or hybrid projects follow the change mechanism they have agreed).

Key takeaways

Key point

  • PDM uses nodes for activities and links for logical relationships. Other names: the node method and AON.
  • A predecessor comes first and a successor comes after. Several predecessors make a path convergence, and several successors make a path divergence.
  • The four relationships are FS, FF, SS and SF. FS is the most common and SF is rarely used. Common exam practice: an unlabeled ordinary link is usually read as FS, unless the stem says otherwise.
  • To identify a relationship, look at which end of the predecessor (start or finish) it depends on and which end of the successor it constrains.
  • If a dependency is found wrong before the baseline is approved, correct the network diagram directly and update the schedule.

Lesson 2

Types of Dependencies, and Leads and Lags

Lesson video

Lesson overview

The previous lesson covered how activities are linked. This lesson covers why they must be linked that way, and whether time can be added on a link. The first is the classification of dependencies: mandatory or discretionary, external or internal. It determines which sequences can be changed and which have to be handled by coordination. The second is leads and lags, which make logical relationships fit reality more closely and bring a point that calculation questions often test: they count toward path length but not toward an activity's duration. The material appears in determining the sequence and is also a prerequisite for fast tracking and critical path calculations later on.

Two sets of attributes of a dependency

Besides the four logical relationships, every dependency has two sets of attributes: mandatory or discretionary, and internal or external. The first set answers "why does it have to be sequenced this way?", and the second answers "who controls this sequence?".

AttributeAlso calledMeaningCan the team change it?
Mandatory dependencyHard logic, hard dependencyLegally or contractually required, or inherent in the nature of the work, often a physical limitationCannot be violated
Discretionary dependencyPreferred logic, preferential logic, soft logicA sequence set from good practice in the application area or from the project's particular character, although other acceptable sequences existCan be adjusted
External dependencyNoneA relationship between project activities and non-project activities, such as a supplier delivery or a government approvalUsually outside the team's control
Internal dependencyNoneA precedence relationship between project activitiesGenerally inside the team's control

The two sets can be combined, giving four types: mandatory external, mandatory internal, discretionary external and discretionary internal. For example, testing must come after assembly: that is a mandatory internal dependency. Software testing cannot start until an external supplier delivers the hardware: that is a mandatory external dependency. On a construction job, doing the plumbing before the electrical work is good practice, but the two could also run in parallel: that is a discretionary internal dependency.

Discretionary dependencies should be fully documented because they can create arbitrary total float values and limit later scheduling options. When you are about to fast track, first go back and review the discretionary dependencies involved, to see which ones can be loosened so activities run in parallel. Mandatory dependencies should not be confused with assigning schedule constraints in the scheduling tool, and they cannot be dropped or violated at will.

External dependencies should be identified during planning and built into the schedule. If the other party is late or has not provided a date, contact it first to clarify and coordinate the date, then update the schedule and continue tracking the dependency. Because they are outside the team's control, all the project manager can do is coordinate and track, not decide directly. A dependency on the deliverables of another project in the program falls in the same category.

Leads and lags

You can add a quantity of time between two activities to make the relationship fit reality more closely:

  • A lead is the amount of time whereby a successor activity can be advanced with respect to a predecessor activity. Scheduling software often records it as a negative value for lag. For example, FS−3 means the successor can start when the predecessor still has 3 days to go.
  • A lag is the amount of time whereby a successor activity will be delayed with respect to a predecessor activity. For example, FS+2 means you must wait 2 more days after the predecessor finishes before the successor can start.

To read a link annotation, look first at which relationship it is, then at how many days are added or subtracted. For example, SS+10 means the successor can start only 10 days after the predecessor has started.

Key point

The use of leads and lags should not replace schedule logic, and duration estimates do not include any leads or lags. Activities and their related assumptions should be documented.

Calculation example: two paths, which one decides the duration

An office renovation project has four activities: "demolish old finishes" 6 days, "paint walls" 9 days, "procure furniture" 12 days and "deliver furniture" 4 days. The relationships are as follows. Demolition to painting is FS. Painting to furniture delivery is FS with a 2-day lead (furniture can be delivered when painting has 2 days left). Demolition to procurement is FS with a 5-day lag (the order is placed 5 days after demolition is finished). Procurement to delivery is FS. Find the shortest duration.

  • Path 1: demolition, painting, delivery: 6 + 9 + 4 − 2 = 17 days (subtract the lead).
  • Path 2: demolition, procurement, delivery: 6 + 5 + 12 + 4 = 27 days (add the lag).
  • Take the longest path: the shortest duration is 27 days, and path 2 is the critical path.
  • Check: if the 2-day lead were mistaken for a lag, path 1 would become 21 days, still less than 27, so the conclusion would not change. If all leads and lags were ignored, path 1 would be 19 days and path 2 would be 22 days, leading to the wrong answer of 22 days.

The two quantities work in opposite directions: a lag lengthens a path and a lead shortens it. In the end you compare the total lengths of the paths.

A lag is not the same thing as float. A lag is a wait you are required to observe. Float is flexibility calculated from the network logic: total float is the amount of time an activity can be delayed without delaying the project finish date, and free float is the amount of time an activity can be delayed without delaying the early start of its successor. Writing a required curing period as a lag is clearer than building it into the activity's duration, because if the curing method improves you only need to change the number on the link.

Worked examples

Example 1 Waiting for the power company to connect: which dependency is this

Question 1Example

A logistics company's new warehouse center project is ready to start, but the power company has not yet said when the substation connection will be made. To make the schedule realistic, what should the project manager do?

Show answer and explanation

Correct answer: D

A warehouse center project is ready to start, but the power company has not said when the substation will be connected. How can the schedule be made realistic?

The substation connection is the power company's responsibility and is outside the project team's control. A dependency between a project activity and a non-project activity is an external dependency. Because the other party has not provided a date, the project manager should first contact the power company to clarify the connection date, then build the external dependency and confirmed date into the schedule, plan the later activities accordingly and continue tracking it. The answer is D.

Why the other options are wrong

  • A. Crashing is used when a plan exists and the duration must be compressed. The problem here is that the schedule does not reflect the external dependency, and shortening later activities does not solve that.
  • B. The critical path method must rest on complete and correct dependencies. With the external dependency missing, the finish date it produces is unreliable.
  • C. Schedule network analysis also relies on complete logical relationships. With the external dependency missing, the total float it calculates is meaningless, so it cannot come before identifying the dependency.

Key takeaway A dependency on a party outside the project is an external dependency. If that party is late or has not provided a date, contact it first to clarify the date, then build the dependency into the schedule and track it.

Variation If an activity could start only after equipment arrives, as required by contract, it is also a mandatory dependency. If the team usually does art before development by habit, it is a discretionary internal dependency and can be adjusted.

Something wrong with this question?

Report an issue with this question

Example 2 Wait 3 days after it finishes, then start

Question 2Example

PMLyceum is renovating an exhibition hall. When the project manager develops the schedule, the plan allows 3 days of curing after the floor screed is finished, and only then can display case installation begin, so the screed can cure before the display cases go on it. Which of the following has the project manager applied?

Show answer and explanation

Correct answer: D

While developing the schedule for an exhibition hall renovation, the plan allows 3 days of curing after the floor screed is finished before display case installation can start. Which of the following has been applied?

The key signal is “after it finishes, you must wait another 3 days before starting”. A lag is the amount of time whereby a successor activity will be delayed with respect to a predecessor activity, and here it is written FS+3. The 3 days of curing are a required wait, recorded on the link, and they are not counted in the duration of the display case installation. If a fast-drying material shortened the curing, you would only change the number on the link. So what has been applied is a lag. The answer is D.

Why the other options are wrong

  • A. A lead is time by which the successor can start earlier, which is the opposite direction. The stem requires a delay, not an advance.
  • B. Free float is the amount of time an activity can be delayed without delaying the early start of its successor. It is calculated slack, not a required wait.
  • C. Total float is the amount of time an activity can be delayed without delaying the project finish date. It is also calculated slack, while a lag must be observed.

Key takeaway A lag is time you must wait, and float is time you can delay. Do not mix them up.

Variation If it said display case installation could start when the floor screed had 1 day of work remaining, that would be FS with a 1-day lead (FS−1). If asked in whose duration the curing time is written, the answer is neither the screed's nor the installation's: it is recorded as the lag on the link.

Something wrong with this question?

Report an issue with this question

Example 3 Path calculation with leads and lags

Question 3Example

A mobile app project has 4 activities: “requirements” 8 days, “development” 21 days, “server procurement” 15 days and “deployment” 10 days. Requirements to development is finish-to-start (FS). Development to deployment is FS with a 3-day lead. Requirements to server procurement is FS with a 4-day lag. Server procurement to deployment is FS. Given these relationships, what is the minimum number of days needed to complete the project?

Show answer and explanation

Correct answer: B

You must find the shortest duration for four activities that have a lead and a lag. A lead shortens a path and a lag lengthens it, and in the end you take the longest path.

List all the paths first, then calculate each length: add lags and subtract leads. Requirements, development, deployment is one path, and requirements, server procurement, deployment is the other. The longer path decides the shortest duration and is the critical path. You cannot calculate only the path that looks longest, and you cannot ignore the time amounts on the links. The second path is longer, at 37 days. The answer is B.

  1. Path 1: requirements → development → deployment: 8 + 21 + 10 = 39 days; subtract the 3-day lead between development and deployment to get 36 days.
  2. Path 2: requirements → server procurement → deployment: 8 + 15 + 10 = 33 days; add the 4-day lag between requirements and server procurement to get 37 days.
  3. Take the longer path: max(36, 37) = 37 days. The critical path is requirements → server procurement → deployment.
  4. Check: adding up path 2 segment by segment gives 8 + 4 + 15 + 10 = 37, matching the figure above.

Why the other options are wrong

  • A. 36 days is the length of path 1 (requirements → development → deployment). It calculates only one path and misses the longer path 2.
  • C. 39 days ignores the lead and the lag and simply adds requirements, development and deployment: 8 + 21 + 10 = 39.
  • D. 42 days treats the lead as a lag: 8 + 21 + 10 + 3 = 42.

Key takeaway Path length = sum of activity durations + lags − leads, and then you take the longest path.

Variation If the lag on server procurement were 1 day, path 2 would become 8 + 1 + 15 + 10 = 34 days and path 1 at 36 days would be the longest, so the critical path would change to requirements → development → deployment and the answer would be 36 days.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Only discretionary dependencies are the ones you can loosen first. Mandatory dependencies (for example, you cannot build the superstructure until the foundation is done) cannot be violated.
  • "External" means the thing depended on is outside the project, and "mandatory" means the sequence cannot be violated. The two dimensions can be combined freely, so do not treat every external dependency as mandatory.
  • Wording like "best practice", "customary practice" or "preferred sequence" points to a discretionary dependency. Wording like "required by contract" or "physically impossible" points to a mandatory dependency.
  • When you calculate path length, add lags and subtract leads. Do not reverse the direction. An activity's own duration does not include either quantity.
  • A lag is time you must wait and float is time you can delay. Do not mix them up.

Key takeaways

Key point

  • A mandatory dependency (hard logic) cannot be violated. A discretionary dependency (soft logic) can be adjusted, and when you fast track you review discretionary dependencies first.
  • An external dependency lies outside the project and is usually outside the team's control. If the other party is late or has not provided a date, contact it first to clarify the date, then build or update the dependency in the schedule and track it. An internal dependency is generally inside the team's control.
  • A lead (FS−3) brings the successor forward and a lag (FS+2) pushes it back. First read the relationship type, then the number of days added or subtracted.
  • Leads and lags do not replace logical relationships and are not counted in activity duration estimates.
  • For a simple path of all-FS relationships, total path length = sum of activity durations + lags − leads, and the project duration is the longest path. When SS, FF or SF relationships are involved, work through each relationship's constraint item by item in a forward pass and a backward pass. Do not apply the shortcut directly.

This chapter has 20 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.