Estimating Techniques for Duration

PMP · Schedule · 3 lessons · about 35 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Step 3 of developing the schedule is estimating effort and duration: how much work each activity takes, and how long it takes. If the estimates are off, the critical path, float and baseline that follow may be affected too. This chapter first separates effort from duration, and covers who should estimate and what influences duration. It then covers the three basic techniques (analogous, parametric and bottom-up) and how to choose among them. Last, it covers reserve analysis and the outputs of duration estimating: ranges, probabilities and the basis of estimates. Multipoint estimating is a large topic and has its own chapter next.

By the end of this chapter you should be able to do the following. Convert effort into duration. Know that the inputs to an estimate come from the person or group most familiar with the activity. Name factors such as the law of diminishing returns, and know that adding people does not always shorten the schedule. Choose among analogous, parametric and bottom-up estimating from the keywords in a question. Distinguish the ownership and authority of contingency reserve and management reserve. Read estimates expressed as "± days" and as probabilities, and state the basis of an estimate clearly.

Lessons in this chapter

Chapter map

Estimate effort and duration (inputs: activity list, resource estimates, risk register ...)

  • Effort (labor hours) → duration; inputs come from the person most familiar with the activity
  • Factors: law of diminishing returns, number of resources, advances in technology, cognitive bias (including team members' motivation)
  • Techniques: analogous (generally quicker and less costly, but can be less accurate) / parametric (statistical relationship) / bottom-up (decompose then aggregate; usually more detailed but takes longer) / multipoint estimating
  • Reserve analysis: contingency reserve (known-unknowns; for identified risks; inside the schedule baseline) / management reserve (unknown-unknowns; outside the baseline; use requires authorization)
  • Outputs: duration estimates (± ranges, probabilities, no lags), basis of estimates

How the exam tests this

There are three high-frequency question types. The first is choosing an estimating technique from a scenario, which is the most commonly tested. For example, when there are no comparable historical projects, analogous estimating is normally ruled out; when an activity cannot be estimated with a reasonable degree of confidence, you can decompose it further and use bottom-up estimating; when a reliable statistical relationship exists, use parametric estimating. (Common exam practice: choose bottom-up when you need accuracy and analogous when you need speed early on.) The second is concept distinctions, such as who provides the estimate inputs, how to handle a learning curve, and how contingency reserve differs from management reserve. The third is probability comparison, using "probability of finishing as planned = 1 − probability of delay".

Study tips and practice

  • Make a comparison card of the keywords for the four techniques, and circle the keywords in the stem of every technique-selection question.
  • Before you work a probability question, read carefully whether it asks for "the probability of being on time" or "the average delay".
  • Cost estimating uses the same group of techniques. Once you finish this chapter, the cost estimating material in the Finance topic will go quickly.

Lesson 1

Estimating Effort and Duration: Effort, Duration and Influencing Factors

Lesson video

Lesson overview

Once the activities are sequenced, you have to answer "how long does each activity take?" This is step 3 of developing the schedule, and its results feed straight into the critical path method: if the estimates are off, the critical path, the float and the baseline that follow may be affected too. This lesson first covers what you are estimating, so that you can separate "effort" from "duration". It then covers who does the estimating and how to bring several experts' numbers together, and finally the factors that influence duration. Among them, "adding people does not always shorten the schedule" is a favorite exam trap. Which estimating technique to use is the subject of the next lesson, and reserves and the basis of estimates come in lesson 3. ECO: Process domain, Task 8 (Plan and manage schedule), including estimating project tasks and using baseline and historical data.

What you estimate: effort and duration

This step, built on the resource estimates, determines the number of work periods (hours, days, weeks or other) needed to complete individual activities with estimated resources. Its key benefit is that it provides the amount of time and effort each activity will take to complete.

Keep two quantities apart. Effort is the number of labor units required to complete an activity, such as 120 labor hours. Duration is the number of work periods needed to complete the activity with the estimated resources, such as 5 days. To convert effort into duration you use the scope of work, the required resource types and skill levels, the estimated resource quantities and the resource calendars. For some activities the duration is set by the nature of the work and does not depend on how many resources there are, such as a 24-hour stress test, which does not get shorter however many people you add. PMBOK 8 treats these as constraints imposed on the duration, effort involved or type of resources: fixed duration, fixed effort or work, and a fixed number of resources. The experience of the team executing the activity, the risk involved in the activity and the schedule network analysis technique used also influence the estimates.

Calculation example: converting effort into duration

A report development activity is estimated at 288 labor hours, and 3 developers are assigned. Each is at work 8 hours a day, but according to the resource calendar, after meetings and communication each person has 6 productive hours a day.

  • Team output per day: 3 × 6 = 18 labor hours.
  • Duration: 288 ÷ 18 = 16 days.
  • Check: 18 labor hours × 16 days = 288 labor hours, which matches the effort.
  • If you wrongly used 8 hours: 288 ÷ (3 × 8) = 12 days, which underestimates the duration by 4 days.

So use productive hours, not nominal working hours, when you estimate.

Who estimates, and how to converge

The inputs for the estimates of duration originate from the person or group on the project team that is most familiar with the nature of the work for the specific activity. Estimates are also progressively elaborated: as more detailed and precise data become available about the design and engineering work, the quality of the estimates improves. If the early estimates were made by staff borrowed on a temporary basis, the project manager should review them, before the schedule is finalized, together with the team that will actually do the work.

When several experts give numbers that are far apart, do not simply average them and do not just escalate the disagreement. Use the wideband Delphi approach: each expert estimates individually, everyone then reveals their estimates and discusses the reasons and assumptions behind the highest and lowest values, and after each round of discussion the experts estimate again. After a few rounds of re-estimating the numbers converge. The disagreement often comes from an overlooked assumption, so the discussion is worth more than an average.

Factors that influence duration

FactorMeaning
Law of diminishing returnsWhen one factor (for example, a resource) is increased while all others stay fixed, a point is eventually reached at which each added unit yields a progressively smaller increase in output
Number of resourcesDoubling the resources does not always halve the time. Adding resources also brings knowledge transfer, learning curves and extra coordination, which can make duration longer
Advances in technologyAdopting more advanced technology may change the duration and the resource needs
Cognitive bias and team members' motivationPMBOK 8: biases such as planning fallacy and end-of-story illusion, phenomena such as Hofstadter's law, and even the motivation of team members may impact the accuracy of the scheduling process

Take one activity as an example. One person takes 12 days, two people take 7 days, three people take 6 days, and with four people the overhead of communication and dividing the work cancels the new hands, so it is still 6 days or even longer. That is diminishing returns. Adding resources to an activity, especially people who lack the skills or do not know the work, can increase the effort for training, communication and coordination, so marginal efficiency falls and the duration may not shorten at all (suitable resources who know the work may still shorten the duration, which is the basis of crashing). When a team uses a new technology for the first time, you must also include the learning curve in the estimate and not schedule at the efficiency of an experienced team.

Two more human tendencies are worth knowing. They are common exam terms. Parkinson's law says work expands to fill the time available. If you are given a week, even if the work could be done in a day, it will most likely drag on to Friday. Student syndrome is putting full effort in only when the deadline is close: relaxed at first and working overtime at the end. If every activity is given generous padding, the padding gets used up for nothing and later activities cannot make it back up. The critical chain method is designed to address exactly this.

Many things influence duration: the scope of work, the capability and number of resources, resource calendars, constraints, team experience, activity risk and the schedule network analysis technique, of which resources and risk are the two key ones. The resource requirements from resource estimating and the risks in the risk register are both inputs to duration estimating. PMBOK 8 also points out that cognitive biases such as planning fallacy and end-of-story illusion affect how accurate schedule estimates are.

Worked examples

Example 1 Expert estimates differ widely: what to do

Question 1Example

The project manager of a hospital information platform project is developing a detailed schedule and asks several subject matter experts (SMEs) for initial estimates of activity durations. The experts' numbers differ widely, and the project manager is concerned. How should the project manager help produce the estimates?

Show answer and explanation

Correct answer: D

In planning a hospital information platform project, the project manager asks several subject matter experts for initial estimates of activity durations. The numbers differ widely and the project manager is concerned. How should the project manager help produce the estimates?

When experts' numbers are far apart, the usual reason is that they are relying on different assumptions and information. Option D follows the wideband Delphi approach: after the experts have estimated individually, have the experts reveal their estimates, discuss the reasons and assumptions behind the highest and lowest values to remove bias and information gaps, and then re-estimate. Repeating this discuss-and-re-estimate cycle for a few rounds brings the estimates together until consensus is reached. The disagreement often comes from an overlooked assumption, so discussion is worth more than averaging. The answer is D.

Why the other options are wrong

  • A. The project manager should first coordinate the experts to resolve the differences. Reporting them straight to the sponsor avoids the problem, and the sponsor may not know the details of the activities.
  • B. Historical information is a useful reference but cannot replace the experts discussing their differences. After consulting it, each person still carries the original assumptions.
  • C. Adopting only what everyone agrees on hides the disagreement and the overlooked assumptions, and the risk is often exactly where the disagreement is.

Key takeaway When experts disagree widely, have them reveal their basis, discuss the extreme values, and re-estimate until the numbers converge.

Variation A project manager who simply averaged two experts' numbers would also not be ideal, because the average does not resolve the difference in assumptions. For an agile team, use planning poker for relative estimates. If the experts must submit anonymously without knowing each other's numbers, that corresponds to the classic (anonymous) Delphi technique.

Something wrong with this question?

Report an issue with this question

Example 2 First use of a new framework, and the estimates ignore the learning curve

Question 2Example

While reviewing the schedule, the project manager finds that the “mobile refactoring” team is using a new framework for the first time, but the duration estimates for its activities are still based on the efficiency of an experienced team and do not account for the learning curve. What should the project manager do?

Show answer and explanation

Correct answer: A

On review, the “mobile refactoring” team is using a new framework for the first time, but activity durations are still estimated at an experienced team's efficiency with no learning curve. What should be done?

Team proficiency is a factor that influences duration: using a new technology for the first time means lower efficiency and a need to learn and make mistakes. The estimates do not match the team's real level, so the problem should be dealt with at the estimating stage. For the affected activities, include the learning curve in the duration and update the basis of estimates so that the schedule becomes feasible. This addresses the affected activities and not the whole plan. The answer is A.

Why the other options are wrong

  • B. Waiting for variances to appear and then crashing is costly and risky, and the problem can be fixed entirely at the estimating stage.
  • C. Adding one block of buffer at the end of the plan does not identify which activities are affected and has no basis, so it cannot reflect the true duration of each activity.
  • D. Adding resources does not necessarily offset the learning curve. The effect depends on the skills of the added people and on whether the work can be done in parallel, and new people also need training and coordination, so duration may even get longer. More importantly, now that the basis of the estimates is found not to hold, the first step is to correct the estimates and the basis of estimates for the affected activities.

Key takeaway Proficiency affects duration. In estimating, include the learning curve and update the basis of estimates.

Variation If the activity were a 24-hour stress test and the team wanted to add people to shorten it, the duration is set by the nature of the work and adding people will not shorten it. If the resource calendar shows members can give only 3 days a week, you must also re-estimate using their productive time.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • "Adding people always speeds things up" is wrong. If the stem says new resources need training, communication costs rise or resources are already saturated, lean toward the answer that efficiency falls and duration does not necessarily shorten.
  • Effort is not duration. 120 labor hours could be 5 days or 15 days, depending on how many people are assigned and how many productive hours they have.
  • Estimate inputs come from the person or group most familiar with the activity. The project manager does not set them alone, and a sponsor's approval does not make them right.
  • When experts' numbers differ widely, do not simply average them and do not simply escalate. Have them explain their reasons and re-estimate.
  • The learning curve, resource availability and risk are all factors to consider in estimating. When you find something missing, adjust the estimates of the affected activities and update the basis of estimates. Do not add one block of padding at the end.

Key takeaways

Key point

  • What you estimate: effort (labor hours) is converted into duration (work periods). Use productive hours and the resource calendar when converting.
  • Inputs come from the person or group most familiar with the activity. Estimates made by temporary staff should be reviewed with the team that will do the work.
  • Large disagreement among experts: in wideband Delphi, experts estimate individually, discuss the extreme values after each round and re-estimate until the numbers converge.
  • Influencing factors: the law of diminishing returns, number of resources, advances in technology and cognitive bias (including team members' motivation). Adding people does not always shorten the schedule.
  • Parkinson's law and student syndrome are common exam terms. They show that spare time gets used up.

Lesson 2

Analogous, Parametric and Bottom-Up Estimating

Lesson video

Lesson overview

There are a few basic ways to estimate duration, and almost every exam asks "which one fits this situation?" This lesson puts the three basic techniques side by side (analogous estimating, parametric estimating and bottom-up estimating), adds expert judgment, the Delphi technique and relative estimating in agile settings, and ends with a table that maps keywords to techniques. Multipoint estimating has its own chapter later. Analogous, parametric, bottom-up and multipoint methods can equally be used to estimate cost; the only difference is whether you are estimating time or money.

The three basic techniques

Analogous estimating is a technique for estimating the duration, cost or required resources for an activity or a project using historical data from a similar activity or project. It uses parameters from a previous, similar project, such as duration, budget or size, as the basis for estimating the same parameter for the current one. It is a gross value estimating approach that relies on historical data and expert judgment, and is sometimes adjusted for known differences in project complexity. Compared with other techniques it is generally less costly and less time-consuming, but it can also be less accurate. It is reliable only when the earlier activities are similar in substance to the current ones and the people doing the estimating have the necessary expertise. It can be applied to a whole project or to segments of a project, and it is frequently used early on when there is limited detailed information.

Parametric estimating uses a statistical relationship between historical data and project parameters to build an algorithm, for example "quantity × labor hours per unit". Its accuracy depends on the quality of the model and the underlying data, so you need reliable historical data and quantifiable parameters. Bottom-up estimating estimates the duration, cost or required resources by aggregating the estimates of lower-level components of the work: you break the work into smaller components, estimate each one and roll them up level by level. It usually takes more time, but when decomposition and the underlying data are good it can give higher accuracy, so it suits cases where the scope has been decomposed and higher accuracy is needed (common exam practice: remember it as "most accurate, slowest"). When an activity's duration cannot be estimated with a reasonable degree of confidence, you can also decompose the work within the activity, estimate the details and then aggregate.

Calculation example: one estimate for an office network with each of the three techniques

A company has taken on an office network installation. The three examples below estimate different things and the numbers cannot be compared directly: analogous estimating estimates the duration of the whole project, while parametric and bottom-up estimating cover only one item of work, "floor cabling".

  • Analogous (object: the whole project): a similar network project last year took 90 days. This time the floor structure is more complex, and the team judges the complexity to be about 20% higher, so the estimate is 90 × 1.2 = 108 days. It is fast, but the basis is only one "similar project".
  • Parametric (object: floor cabling): 4,200 meters of network cable will be laid, and historical data show an average of 70 meters per person-day. With 6 people assigned, total effort is 4,200 ÷ 70 = 60 person-days, and duration is 60 ÷ 6 = 10 days. Check: 6 people × 10 days × 70 meters = 4,200 meters. If the historical data came from an open-plan office and this floor has many partitions, the parameter has to be adjusted first.
  • Bottom-up (object: the same "floor cabling" item): break the work package "floor cabling" into laying out 3 days, pulling through conduit 4 days, termination 2 days and testing 1 day, in sequence, for a total of 10 days. Estimating item by item and then aggregating is usually more accurate, but it needs a complete decomposition first.

Other supporting methods, and agile settings

Expert judgment relies on opinions from experienced people and is often combined with analogous estimating. The Delphi technique is several rounds of anonymous expert estimates, with the results consolidated and fed back each round until opinions converge. Alternative analysis compares different ways of doing the work and weighs them to pick the best. Voting is a decision-making technique; common forms are unanimity, majority and plurality, and show of hands is often used in agile.

Adaptive projects commonly use story points, planning poker and T-shirt sizing, which give relative size rather than precise hours. In its list of techniques for duration estimating, PMBOK 8 names expert judgment, the Delphi technique, analogous estimating, parametric estimating, the program evaluation and review technique (PERT), bottom-up estimating, planning poker, story points and T-shirt sizing. Hybrid projects let different parts use techniques that suit them: the predictive part uses multipoint estimating and the adaptive part uses story points, and the two are integrated into the overall schedule through high-level milestones, deliverables and dependencies. Story points stay as the team's internal relative estimate and are not converted directly into days.

TechniqueKeywordsFeaturesSuits
Analogous estimatingRough, quick, similar project, early stageTop-down, low cost, lower accuracyLittle information and a quick answer needed
Parametric estimatingStatistical relationship, unit rate or labor hours × quantityDepends on model and data qualityReliable historical data and quantifiable parameters
Bottom-up estimatingRoll up level by level, most detailed, usually more accurate, takes longer (common exam practice: most accurate, slowest)Decompose first, then aggregateScope is clear and high accuracy is required
Multipoint estimatingUncertain, risky, optimistic/pessimistic/most likelyTakes uncertainty into accountA single activity is uncertain and there is no historical data

Worked examples

Example 1 Very different from past projects, so analogous will not work

Question 1Example

The implementation team at PMLyceum has always done retail system rollouts, and the project manager can estimate durations from how past projects were delivered. The company has now taken on an industrial IoT project that differs greatly from past projects, although the scope of work is clear and the WBS has been developed to the work package level. What should the project manager do next?

Show answer and explanation

Correct answer: C

The implementation team has always done retail system rollouts and can estimate durations from past projects. It has now taken on an industrial IoT project that differs greatly from them. What should the project manager do next?

Analogous estimating requires that the earlier activities be similar in substance to the current ones. The stem says the difference is large, so that premise fails and projecting from retail projects would carry a big error. Use the WBS: break the work into smaller tasks, estimate the duration of each one and roll them up level by level. That is bottom-up estimating, which usually gives higher accuracy. It has more basis than a single overall number and does not depend on dissimilar historical projects. The answer is C.

Why the other options are wrong

  • A. Scaling from retail projects is analogous estimating, but the stem says the difference is large, so its premise does not hold.
  • B. Expert judgment is an estimating technique recognized by PMBOK 8, but when the scope and the WBS are in place, giving only one overall figure and adjusting as you go is less well founded than estimating activity durations item by item.
  • D. Estimating the schedule is the responsibility of the project manager and team. Even if the PMO supplies a target date, it cannot replace activity duration estimates based on decomposition of the work.

Key takeaway When there are no comparable historical projects, decompose the work and estimate bottom-up.

Variation If the project had just started with very little information and the sponsor wanted only a rough number, use analogous estimating. If you have reliable historical unit rates and the quantity of work, use parametric estimating.

Something wrong with this question?

Report an issue with this question

Example 2 Which tool for an accurate estimate

Question 2Example

An e-commerce platform project at PMLyceum has entered its second phase, and the project manager has to give the sponsor accurate activity duration estimates. Enough detailed information is available that the activities can be decomposed into smaller tasks, estimated item by item and then aggregated. Which of the following estimating tools should the project manager use?

Show answer and explanation

Correct answer: A

An e-commerce platform project has entered its second phase and the project manager must give the sponsor accurate activity duration estimates. You must decide which estimating tool to use. The stem also gives the condition that the activities can be decomposed further and the information is detailed enough.

Bottom-up estimating breaks work into smaller components, estimates each item and then aggregates level by level. The stem says the activities can be decomposed further and the information is detailed enough, so estimating item by item and rolling up best fits the need for “accurate”, at the price of taking longer. As common exam practice, choose bottom-up when you need accuracy, but in practice you choose according to the available information, the quality of the model, the level of decomposition and the cost of estimating. Under these conditions the other options each have their own situations and none fits as well. The answer is A.

Why the other options are wrong

  • B. Analogous estimating relies on historical data from similar projects. It is quick and cheap but less accurate, and suits the early stage when information is lacking.
  • C. The accuracy of parametric estimating depends on the quality of the model and the underlying data, so it is not necessarily better than item-by-item estimating.
  • D. Expert judgment is also a formal estimating technique, but its accuracy depends on the experts' experience and the information available. This question already meets the condition for decomposing further and aggregating item by item, so bottom-up estimating fits the stem better.

Key takeaway When activities can be decomposed further and you need accuracy, choose bottom-up (common exam practice); for speed, choose analogous.

Variation If “accurate” were changed to “the project has just started and a rough estimate is needed quickly”, the answer becomes analogous estimating. If it were changed to “high uncertainty and no historical data”, the answer is multipoint estimating.

Something wrong with this question?

Report an issue with this question

Example 3 How to combine two kinds of estimates in a hybrid project

Question 3Example

On a hybrid project, the predictive part is scheduled with multipoint estimating and the adaptive part is estimated in story points. The project manager must combine the two parts into one overall schedule. What should the project manager do?

Show answer and explanation

Correct answer: B

On a hybrid project the predictive part uses multipoint estimating and the adaptive part uses story points. How should the two parts be combined into one overall schedule?

A hybrid project lets different parts use techniques that suit them: multipoint estimating fits the predictive part and relative-size estimating such as story points fits the adaptive part. The project manager's job is not to force one technique but to agree on a common basis, for example the unit of time and how milestones and iterations correspond to the schedule, so that the two parts can be linked into one overall schedule. The answer is B.

Why the other options are wrong

  • A. A story point is a relative size, not a duration. Converting predictive activities into story points loses the time information and cannot support a predictive schedule.
  • C. An agile team estimates by iteration and relative size. Forcing it onto activity-by-activity multipoint estimating destroys the character of the method.
  • D. With no link there is no overall schedule, and the whole project cannot be reported to stakeholders.

Key takeaway In a hybrid project each part uses its own estimating technique, and a common basis is agreed to link them into one overall schedule.

Variation If an adaptive team wants to use velocity to forecast dates, first link story points to the iteration timebox. To set overall milestones, use high-level milestones to tie the two parts together.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • "Refer to similar past projects", "early in the project", "very little information", "needs to be quick": analogous estimating.
  • "Statistical relationship", "parametric model", "unit rate or labor hours times quantity": parametric estimating.
  • "Roll up from work packages level by level", "most accurate, slowest" (common exam practice): bottom-up estimating.
  • "Optimistic, pessimistic, most likely", "high uncertainty": multipoint estimating.
  • When the new project differs greatly from past projects, the premise of analogous estimating does not hold, and you should decompose the work and estimate item by item.
  • Analogous estimating involves some expert judgment, but "ask an experienced person to estimate" on its own is expert judgment, not analogous estimating.
  • A story point is a relative size, not a duration. You cannot simply convert it to days and enter it in a predictive network diagram.

Key takeaways

Key point

  • Analogous: uses historical data from a similar project; quick, cheap, less accurate; used early on.
  • Parametric: statistical relationship plus parameters; accuracy depends on the model and the data.
  • Bottom-up: decompose, estimate item by item, then roll up; usually takes longer and is more accurate (common exam practice: most accurate, slowest).
  • Multipoint estimating: uses three values to reflect uncertainty; covered in detail in the next chapter.
  • Adaptive projects use story points, planning poker and T-shirt sizing; hybrid projects use each technique where it fits, then agree on a common basis to link them.
  • The keywords in the stem decide the technique: similar project, statistical relationship, roll-up, uncertainty.

Lesson 3

Reserve Analysis and the Outputs of Duration Estimating

Lesson video

Lesson overview

Estimates can never be free of error, which raises two questions. Where you already know things may go wrong, how do you leave room in the schedule? And once you have an estimate, what must you deliver besides a single number? The first is reserve analysis, and the second is the duration estimate and the basis of estimates. This lesson also teaches you to read statements such as "2 weeks ± 2 days" and "a 15% probability of exceeding 3 weeks", and to compare two estimates by probability. Another way of handling reserve, pooling the safety time of individual activities, is the critical chain method, which comes in a later chapter.

Reserve analysis: contingency reserve and management reserve

When you estimate duration you can build in reserves to deal with uncertainty. There are two kinds, divided the same way as cost reserves:

Contingency reserveManagement reserve
What it addressesIdentified risks that have active response strategies, the "known-unknowns"Unforeseen work within the project scope, the "unknown-unknowns"
In the schedule baseline?Yes. It is a block of duration included in the schedule baselineNo, it is outside the baseline
Who can use itThe project manager, in line with the risk management plan and the authority established, with no separate change control needed (common exam practice)Usually at the discretion of senior leadership or management (some organizations authorize the project manager) and requested and approved according to the organization's governance; common exam practice: request it through the change control procedure

"Known-unknowns" are risks you can identify and anticipate in advance, for example a supplier's delivery might be a few days late, so you set aside a few days. "Unknown-unknowns" are unexpected events you cannot identify in advance and only know might exist. A contingency reserve can be provided at the level of a single activity or for the whole project. Unless the question says otherwise, treat the contingency reserve as inside the baseline and the management reserve as outside it.

Calculation example: how reserves enter the duration

The activity estimates for a server room renovation total 80 days (no reserve on the path). The risk register has three identified risks, and the team assesses them and sets aside an 8-day schedule contingency reserve. The organization has separately approved a 6-day management reserve to deal with the unforeseeable.

  • Schedule baseline = 80 + 8 = 88 days (including the contingency reserve).
  • The 6-day management reserve is outside the baseline, so the baseline still finishes on day 88 (counting the management reserve, the total authorized duration is at most 94 days). If it really had to be used, that would normally be at the discretion of senior leadership or management, with approval handled under the organization's rules (common exam practice: through the change control procedure).
  • During execution, an identified supplier delay risk occurs and uses 3 days: the project manager draws on the contingency reserve within their authority, leaving 5 days, and the finish forecast does not change.
  • A different case: if 6 days were used in the first month (rather than 3 in the previous point), the reserve analysis must be redone: does the remaining 2 days of contingency reserve cover the risks that have not yet occurred? Update the finish forecast accordingly.

When the schedule is behind, reserve analysis is also a monitoring tool: compare the reserve already used, the reserve remaining and the remaining risk, decide whether it is enough, and then reforecast the finish date.

Duration estimates and the basis of estimates

The output of estimating duration is a duration estimate: a quantitative assessment of the likely number of time periods required to complete an activity, phase or project. It does not include any lags, but it may include some indication of the range of possible results. For example:

  • "2 weeks ± 2 days": assuming a 5-day work week, the activity will take at least 8 days and not more than 12.
  • "A 15% probability of exceeding 3 weeks": there is a high probability, 85%, that the activity will take 3 weeks or less.

The other output is the basis of estimates. It should provide a clear and complete understanding of how the duration estimate was derived, including the data used, the assumptions and the constraints. An estimate needs a basis so that it can be approved, reviewed and later updated. All data and assumptions that support the estimate are documented for each activity. An estimate can be made at distinct levels, such as the control account, the work package or the activity.

Example: the client asks to "cut the duration by 20%"

The client has seen the estimates and asks for the total duration to be cut by 20%. If each estimate has a clear basis, the project manager does not have to cut the numbers mechanically. The reply is that it can be shortened, but only by reducing activities or scope accordingly, or by paying the price of schedule compression. Ask the client to say what they are willing to give up, and then recalculate. The basis of estimates is what makes the estimates stand up, so they are no longer numbers pulled out of the air.

Comparing two estimates by probability

When estimates carry probabilities, what you compare is the probability of finishing as planned: probability of finishing as planned = 1 − probability of delay. For example, project A has a 60% chance of a 10-day delay and otherwise finishes as planned; project B has a 35% chance of a 20-day delay and otherwise finishes as planned. Project A finishes as planned with probability 1 − 60% = 40% and project B with 1 − 35% = 65%, so B is more likely to be on time. Do not be misled by the number of delay days: A's delay is shorter, but a delay is more likely. Only if the question asks for the average delay do you multiply probability by days: A 0.6 × 10 = 6 days, B 0.35 × 20 = 7 days, and in that case A's average delay is smaller. The wording of the question changes the answer.

Worked examples

Example 1 The schedule is behind: use reserve analysis to forecast the go-live date

Question 1Example

A hybrid project keeps adding base stations to a 4G network, and the schedule baseline includes a schedule contingency reserve for an identified delivery delay risk. At the end of the first month the team is behind target and the operator's revenue for the month has suffered. Stakeholders want to improve return on investment (ROI) quickly and ask the project manager to say when these base stations can be put into operation and start charging. What should the project manager do?

Show answer and explanation

Correct answer: C

A hybrid project keeps adding base stations to a 4G network, and the baseline includes a contingency reserve for an identified delivery delay risk. At the end of the first month the schedule is behind, and stakeholders want to know the date for going live and charging. What should the project manager do?

The contingency reserve within the baseline is time set aside for identified delay risks, and the project manager draws on it under the risk management plan and the authority established (common exam practice: no separate change control needed). The schedule is already behind, so do a reserve analysis first: how much has been used, how much is left, and whether what is left is enough to cover the later risks. Then reforecast the go-live date from that and explain it to stakeholders. If the remaining reserve cannot cover the later risks, the forecast date has to move back accordingly. The answer is C.

Why the other options are wrong

  • A. Reporting business updates more often does not answer the go-live date question and does not improve the schedule.
  • B. The project approach cannot be switched at will, and even changing to predictive would not automatically yield a reliable date. The problem is that the reserve has not been assessed.
  • D. Redrawing the boundary between agile and predictive modules has no direct bearing on the schedule slip or on forecasting a date.

Key takeaway When the schedule is behind, do a reserve analysis first (how much contingency reserve has been used and how much is left), then forecast the date.

Variation If the stem said the event was an unidentified emergency and the contingency reserve was used up, you would go through the change control procedure to request management reserve. If asked who draws on the contingency reserve, the answer is the project manager, under the risk management plan and the authority established (common exam practice: no separate change control needed).

Something wrong with this question?

Report an issue with this question

Example 2 Comparing two estimates with probabilities

Question 2Example

A program manager is managing two projects with the same planned duration. Project 1 has a 75% chance of a 15-day delay and otherwise finishes as planned. Project 2 has a 40% chance of a 25-day delay and otherwise finishes as planned. Based only on these two estimates, which project is more likely to finish within its planned duration?

Show answer and explanation

Correct answer: D

A program manager compares two projects with the same planned duration, each with a probability and number of days of delay, and asks which is more likely to finish as planned. The question is about the probability of being on time and does not look at the number of delay days.

The probability of finishing as planned = 1 − the probability of delay. Each project has only two outcomes, delay or on time, so work out each on-time probability and compare. Project 2's on-time probability is higher, so it is more likely to finish as planned. Whether the delay is 15 days or 25 days only affects the loss after a delay and does not affect the likelihood of being on time, so you cannot choose Project 1 just because its delay is shorter. The answer is D.

  1. Project 1 finishes as planned with probability 1 − 75% = 25%.
  2. Project 2 finishes as planned with probability 1 − 40% = 60%.
  3. Compare: 60% > 25%, so Project 2 is more likely to finish as planned.
  4. Check: for each project the probabilities of the two outcomes sum to 100% (Project 1: 75% + 25%; Project 2: 40% + 60%).

Why the other options are wrong

  • A. Choosing Project 1 only because its delay is shorter (15 days against 25) ignores that its probability of delay is as high as 75%.
  • B. The probabilities of delay differ, so the probabilities of finishing as planned differ as well. They cannot be the same.
  • C. The stem gives each project's probability of delay, so the on-time probability can be calculated. It is not undeterminable.

Key takeaway Probability of finishing as planned = 1 − probability of delay. Work out the probabilities first, then compare.

Variation If asked which has the smaller average delay in days, multiply probability by days: Project 1 is 0.75 × 15 = 11.25 days and Project 2 is 0.4 × 25 = 10 days, which is still Project 2. With a different set of numbers, the two questions could have different answers.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Contingency reserve is inside the baseline and is used by the project manager according to the risk management plan and the authority established, with no separate change control needed (common exam practice). Management reserve is outside the baseline and its use is usually at the discretion of senior leadership or management, and the common exam practice is to request it through change control. Do not swap their ownership and authority.
  • Contingency reserve answers identified risks and management reserve answers unknown-unknowns. Do not use management reserve to cover identified risks.
  • A duration estimate does not include lags. It may carry a range or a probability, but it must come with a basis of estimates.
  • For probability questions, first see what is asked: for "the probability of finishing as planned", use 1 minus the probability of delay; only for "the average delay" do you multiply probability by days.
  • When there is a clear basis of estimates, the answer to a demand to "just cut 20%" is not to cut the numbers mechanically but to discuss reducing scope or activities.

Key takeaways

Key point

  • Contingency reserve: for known-unknowns, inside the baseline, used by the project manager according to the risk management plan and the authority established, with no separate change control needed (common exam practice).
  • Management reserve: for unknown-unknowns, outside the baseline, and its use is usually decided by senior leadership or management (common exam practice: request it through change control).
  • When the schedule is behind, do a reserve analysis first: how much has been used, how much is left and whether it covers later risks. Then forecast the date.
  • A duration estimate does not include lags. It may carry a range (± days) or a probability, and it must come with a basis of estimates.
  • Probability of finishing as planned = 1 − probability of delay.

This chapter has 18 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.