Free PMP practice questions with answers and full explanations: 1,000 questions, open to everyone with no sign-up. The full bank holds 2,876 questions, organized by chapter of the study guide. Want a whole paper first? Take the free PMP practice test (8 tests).
Try 25 free PMP practice questions, no sign-up
Pick an answer first, then open the explanation: why the right answer is right and why each other option is wrong.
Three months after an online education company’s learning platform goes live, the project manager finds that an interactive Q&A feature, which passed acceptance, is hardly used. What should the project manager do?
Show answer and explanation
Correct answer: D
Three months after the learning platform goes live, an interactive Q&A feature that passed acceptance is hardly used. What should the project manager do?
Deliverables are used to produce outcomes, outcomes create benefits, and benefits create value. A feature that has been delivered but is not used means the chain has broken at the outcome link, and there is a gap between the outcome and the expected value. While the reason is unknown, first investigate why the feature is not used and assess how large the gap is, then decide how to improve. The signal in this type of question is “accepted but not used”: acceptance shows that delivery met requirements, while usage shows whether an outcome was produced, so turn to investigating the outcome rather than going back to check the delivery process. The answer is D.
Why the other options are wrong
- A. Acceptance shows only that the work was done to requirements, not that it has value. Delivering a deliverable is not the same as creating value, and “no further follow-up” ignores value.
- B. Adding more interactive features while the reason is unknown only increases investment. It may not solve the lack of use and may amplify waste.
- C. Pausing other work and reworking everything without knowing the cause may fix the wrong thing. Investigate first, then decide whether rework is needed.
Key takeaway Delivering a deliverable does not mean value has been realized. When something is not used, find the cause first and assess the value gap.
Variation If the investigation finds that the entry point is buried too deep and users cannot find it, a low-cost remedy such as better guidance and training may be more appropriate than rework.
Something wrong with this question?
In its annual review, a group evaluates a completed customer portal project. In judging whether the project outcomes were successful, what is the MOST central criterion?
Show answer and explanation
Correct answer: C
A group evaluates a completed customer portal project in its annual review. The question is the most central criterion for judging whether the project outcomes were successful.
Project success requires evaluating two dimensions, outcomes and management, and both matter. Of the two, the success of project outcomes is critical to the targeted business value. Here the question asks whether the outcomes were successful, so the most central criterion is whether the project delivered the intended business value and aligns with the organization’s strategy. On time and on budget belong to the management dimension and show only whether execution was efficient. A way to remember it: when judging outcomes, ask whether value was realized; only when judging whether execution was efficient do you look at cost, scope, time and quality. The answer is C.
Why the other options are wrong
- A. Finishing within the planned duration and budget reflects only the success of the management process. It cannot stand in for whether value was realized.
- B. Projects almost always encounter risk events. Whether any occurred does not show whether value was realized.
- D. Change is a normal part of a project. Zero changes is neither realistic nor a criterion of success.
Key takeaway Whether project outcomes succeeded depends mainly on whether the intended business value was realized and aligned with strategy. On time and on budget belong to the management dimension, and both dimensions need to be assessed.
Variation If the question were about whether the project management process succeeded, the answer would become adherence to constraints such as cost, scope, time and quality.
Something wrong with this question?
A convenience retail chain's store management system upgrade project has entered planning. Before preparing the project management plan, the project manager sorts out the enterprise environmental factors and organizational process assets that affect the project. Which of the following statements about them are true? (Select 3)
Show answer and explanation
Correct answer: BCF
The project is in planning. You must decide which of six statements about the two kinds of influencing factors are true. The core is “which are enterprise environmental factors, which are organizational process assets, and can they be controlled?”
Enterprise environmental factors are conditions not directly influenced by the project team that impact, constrain or direct the project, and their source can be inside or outside the organization; internal ones include organizational culture, structure and governance, employee capability and so on. Organizational process assets are the organization's own processes, policies, procedures and knowledge repositories, including the lessons learned and historical information of earlier projects. So B (employee capability is an internal enterprise environmental factor), C (lessons learned are organizational process assets) and F (the source can be inside or outside) are correct. The answer is B, C and F.
Why the other options are wrong
- A. Organizational structure falls under “organizational culture, structure and governance,” an internal enterprise environmental factor. A restructuring is a change in an environmental condition, not a change in organizational process assets.
- D. The two kinds are inputs of a different nature, and there is nothing to support that enterprise environmental factors always affect a project more than organizational process assets. The degree of effect depends on the particular project and cannot be generalized.
- E. The characteristic of enterprise environmental factors is that the project team cannot directly control them and has to take them into account during the project, with the legal, policy and other mandatory constraints among them to be obeyed. What the team can draw on, and in part update, are organizational process assets.
Key takeaway Enterprise environmental factors: not directly controllable by the team, to be considered in planning, from inside or outside. Organizational process assets: from the organization itself; knowledge repositories are updated throughout the project, while policies, processes and procedures change only under organizational procedures.
Variation If the stem were changed to “select the statements that are NOT true,” the answer would become A, D and E. If one more option were added, “organizational process assets come from inside the organization and their knowledge repositories can be updated,” it would be true. In multiple-response questions, judge each option separately against the definitions and not by overall impression.
Something wrong with this question?
A project manager is assigned to develop warehouse scheduling software for a logistics company. Another business unit of the company did a similar project that was later stopped because its performance was too poor, and its lessons learned were archived in the organizational knowledge repository. The project manager is worried about how this project will turn out and wants to take action in advance to make sure it succeeds. What should the project manager do?
Show answer and explanation
Correct answer: C
In this project the project manager wants to learn from a similar project's failure within the organization, and the question is what measure the project manager should take.
The reasons a similar project failed are recorded in the lessons learned in the organizational knowledge repository, which is an organizational process asset. Reviewing those lessons learned directly shows the problems to avoid and lets them be prevented in this project's planning, which meets the requirement to “take action in advance and make sure of success” and also reflects the pattern that when you meet a similar project you first consult the organizational process assets. The answer is C.
Why the other options are wrong
- A. Assessing risks and adding outside experts first does not use the ready-made internal experience, costs more, and, with the specific causes of the failure not yet understood, is hard to aim correctly.
- B. That a similar project failed does not mean this one will, and urging the sponsor to terminate is a premature, negative step when the information is still insufficient.
- D. Doing no prevention and adding resources only when problems appear is reactive and does not achieve the aim of “taking action in advance.”
Key takeaway When you see a similar project, first review its lessons learned, and then decide whether other measures are needed.
Variation If the company had no similar project and the project manager lacked experience of the kind, first go to experienced experts or the PMO for advice and also consult outside material; if the similar project had been a success, you would likewise first review its lessons learned and then tailor them for this project.
Something wrong with this question?
A project manager has just been assigned to Phase 2 of an IoT gateway project. A defect appears during implementation, and the original engineering team has been moved to other projects, so nobody knows how to fix it. The customer points out that a similar defect once held up the project's schedule. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
The project is in Phase 2, a defect has occurred and the original team has left. You must decide the project manager's first action.
The defect has already occurred, the original engineering team has been reassigned, and nobody knows how to fix it. Whether the original team left a record of how it dealt with the defect has to be checked first in the organizational process assets (lessons learned, historical information, the defect repository). Consult them first to find out how it was handled before, and only then can you judge whether to extend the schedule, find resources or take other measures. The customer's mention that a similar defect appeared before is a further sign that the historical records probably already hold an answer. The answer is A.
Why the other options are wrong
- B. At this point nothing is known about the defect, so the situation must first be understood and its impact assessed. If the schedule baseline needs to change, a change request must then follow the change management plan, receive authorization, and be reflected in the relevant plans before implementation; the schedule cannot simply be extended first.
- C. The defect has already occurred, so it is an issue, not a risk. Updating the risk management plan does not fix it and is not the first step.
- D. Finding resources with relevant knowledge is something to do when necessary, but it should not come first before the earlier records have been consulted.
Key takeaway When you take over a project and meet a problem nobody knows how to handle, first consult the organizational process assets (lessons learned, defect records) and then decide whether to extend the schedule or find people.
Variation If, after consulting, you find there are no records at all, the next step is to look for resources with the relevant knowledge. And once the defect is fixed, add the handling to the defect repository for later projects to use.
Something wrong with this question?
A project manager receives a project to develop a sports social app. The product’s features must be determined step by step based on continuous user feedback, and there is no ready-made technical solution to refer to for how these features will be implemented. Which development approach should the project manager recommend?
Show answer and explanation
Correct answer: D
The features of a sports social app must be determined step by step from continuous user feedback, and no ready-made technical solution exists for implementing them. You must decide which approach to recommend.
Judge with the Stacey matrix (common exam practice): requirements uncertainty on the vertical axis is high and technology uncertainty on the horizontal axis is also high, so the project falls in the complex zone, where adaptive approaches fit best. The two signals map to the two axes: “features determined step by step from continuous user feedback” is requirements uncertainty, and “no ready-made technical solution” is technology uncertainty. An adaptive approach should therefore be used, determining the features and how to implement them gradually through iterations and feedback. The answer is D.
Why the other options are wrong
- A. A predictive approach suits the simple zone, where both requirements and technology are clear. When both are uncertain, locking the plan up front only causes repeated rework.
- B. The stem gives no condition requiring predictive components, phases, or governance mechanisms to be kept; both requirements and technical solution must become clear through feedback and exploration, so D matches more directly than B.
- C. Incremental delivery within a predictive approach requires the overall scope to be well understood and planned up front. Here the features are determined gradually through feedback, so the premise is absent.
Key takeaway When both requirements and technology are uncertain (the complex zone of the Stacey matrix), choose an adaptive approach.
Variation If requirements were clear but the technology had some uncertainty, the project might fall in the complicated zone, and you would still choose iteration, increment, hybrid, or another suitable approach according to the degree of technical uncertainty. If both were clear, it is the simple zone and predictive applies.
Something wrong with this question?
You take over a smart-home device development project that has been running for about six months under a predictive approach. The team is discussing the previously approved scope: even though the change control procedure is strict, requirements keep changing. What should you do?
Show answer and explanation
Correct answer: A
You take over a development project that has run for half a year. The change control procedure is strict, yet requirements still change continuously. What should you do?
Strict change control is a means of dealing with change. If it is already strict and requirements still keep changing, tightening the process alone will not solve the problem, and the current predictive approach may not match the project’s uncertainty: when a project with highly uncertain requirements uses an approach that depends on stable requirements up front, a large volume of change will usually result. You should consider adjusting the development approach, for example moving to an adaptive or hybrid approach, so the project can adapt to continuously changing requirements. The answer is A.
Why the other options are wrong
- B. Change requests must still be evaluated through the Assess and Implement Changes process. Rejecting all of them is neither reasonable nor able to meet the reality of continuously changing requirements.
- C. The stem already says change control is strict. Tightening it further only makes it harder for real requirements to get in and does not solve the fundamental mismatch between the approach and the requirements.
- D. Accepting every change unconditionally would hit scope, cost, and schedule, and it does not conform to proper change management either.
Key takeaway However strict change control is, it cannot stop requirements from changing; what needs adjusting is the development approach, not blocking the changes.
Variation If the requirements were actually stable and only certain stakeholders kept asking for additions, the problem would be stakeholder management and you should hold to change control. Whether to adjust the approach depends on whether requirement change is the norm for the project.
Something wrong with this question?
At the weekly meeting of PMLyceum’s logistics route optimization project, nearly every team reports that “everything is fine”. In follow-up conversations after the meeting, the project manager learns that two tasks are clearly behind schedule, and that members did not want to say so in the meeting because they feared being singled out and criticized. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
At the weekly meeting every team says “everything is fine”, yet after the meeting two tasks turn out to be late, and members feared being singled out. The question asks what the project manager should do first, and it turns on the accountable leader creating a psychologically safe environment.
The signal is “did not want to say so in the meeting, feared being singled out and criticized”: the root of the concealment is a lack of psychological safety, not a lack of checking. An accountable leader leads by example and fosters an environment where people can speak freely and report problems frankly without fear of retaliation, so that problems surface early and are solved together. Change the environment first, and only then will the information be true. The answer is A.
Why the other options are wrong
- B. Daily written statuses with item-by-item checking only add monitoring burden. Members can still polish their reports, and the root problem, that people are afraid to speak, is untouched.
- C. Having the owners fix things privately leaves the team’s habit of reporting only good news unchanged, and the problem is still not seen and solved by the team together.
- D. Naming people and threatening their reviews makes members more afraid of exposing problems and strengthens the motive to conceal. It is the opposite of psychological safety.
Key takeaway The earlier a problem surfaces the better. First make it safe for members to tell the truth, and only then talk about checking and performance reviews.
Variation If the same scenario were changed to “every score in the risk register is low”, the answer is still to build a culture of candid risk reporting. If asked about the purpose of creating psychological safety, the answer is to let members speak and report problems frankly without fear of retaliation.
Something wrong with this question?
On PMLyceum’s supply chain system upgrade project, the project manager notices that developers who find a risk are reluctant to report it, fearing they will be held responsible, and the problem is usually exposed passively only after it blows up. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
On the supply chain system upgrade project, developers who find a risk do not want to report it and the problem is exposed only after it erupts. The question asks what to do first, and the basis for the judgment is the trust and psychological safety requirements in Build an Empowered Culture.
The key signal is “fearing they will be held responsible”: the members are not failing to report because of ability, but because of a lack of trust and safety. An empowered culture requires an environment that promotes trust, so the project manager first creates an atmosphere of psychological safety and sets up a reporting channel that does not assign blame to individuals, so that risks are spoken about while they are still small. The answer is A.
Why the other options are wrong
- B. Cutting ratings and naming names is punishment. Members will fear exposing problems even more, and the concealment will only get deeper.
- C. Surprise spot checks are a monitoring measure. They do nothing to remove members’ worries and in fact damage trust.
- D. Handing a cultural problem inside the team to functional managers is passing the buck. For emotional and attitude issues like this, the project manager should first talk with the people and improve the environment personally.
Key takeaway When members hide problems, first solve whether they dare to speak, not punishment, monitoring or handing it off.
Variation If the scenario were “the team does not dare try new methods for fear of failure”, the answer becomes allowing small-scale experiments and lowering the cost of failure. If it were “a new member is interrupted in meetings”, it becomes setting a team agreement and inclusive rules for discussion.
Something wrong with this question?
Several batches of room-control panels for a hotel chain's smart-room project are produced at an overseas factory. The project manager is told that the first batch of panels will arrive late. Installing these panels is on the critical path, and the delay will cause the project to miss a milestone. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
On a hotel chain's smart-room project, the first batch of panels from an overseas factory will arrive late. Installing them is on the critical path, and the delay will make the project miss a milestone. What should the project manager do first?
The delay has been confirmed, so a current condition now exists that will affect the milestone; manage it as an issue rather than as an uncertain risk. Because the issue comes from an external factory, the project manager first confirms the cause, actual impact and feasible alternatives with the factory. With those facts established, the project manager logs the issue and develops an action plan to reduce the impact on the milestone. The answer is A.
Why the other options are wrong
- B. The lessons learned register can be updated during the project, but when an issue has just appeared the priority is to log, assess and address it; revisions to the project management plan must also follow the applicable change process.
- C. Rescheduling that touches the baseline requires assessment and the applicable change-control process. Timely notice to relevant stakeholders may be appropriate, but that does not make unilateral rescheduling the first action.
- D. Assigning blame is a retrospective commercial action. It does nothing to protect the milestone now, so it is not the first thing to do.
Key takeaway A confirmed external delay is an issue: first verify the cause, impact and alternatives with the external factory, then log and address it rather than putting it in the risk register or submitting a change first.
Variation If the stem said “the supplier says the first batch may be late,” it has not happened and is a risk: record it in the risk register and assess it; once the delay is confirmed it becomes an issue.
Something wrong with this question?
A software company's system development project hits a technical difficulty just after entering the planning phase, and the project manager asks a senior expert to share experience with the team. Which of the following are tacit knowledge? (Select 3.)
Show answer and explanation
Correct answer: ACE
The project is in the planning phase and a senior expert is asked to share experience with the team. You must pick all three tacit items out of five; the core is telling tacit from explicit.
Tacit knowledge is embedded in a person's mind and is highly personal, and it is hard to express in language or documents; it includes technical skills, experiences, insights and practical knowledge. Intuitive judgment about risk, practical experience built up over several projects and insight into the essence of a problem are all things that are hard to say, hard to write down in full and are often best shared through person-to-person interaction, so all three qualify. A useful check is to ask whether the knowledge depends heavily on personal experience, intuition and context and is hard to formalize completely or transfer directly; if so, it is usually tacit. So choose A, C and E.
Why the other options are wrong
- B. A cause-and-effect diagram expresses causes and effects in a figure. It is already in finished form and can be shared and stored directly, so it is explicit knowledge.
- D. A project analysis report is already written in words and data and can be passed to anyone as a document, so it is explicit knowledge.
Key takeaway Intuition, insight and practical experience are tacit knowledge; diagrams and reports, which can be put in writing, are explicit knowledge.
Variation If the options were changed to “an operating manual” and “an expert judging equipment condition from years of experience,” the first is explicit and the second is tacit. If the question asked how to share tacit knowledge, the answer would be mentoring, pairing and face-to-face interaction, not having the other person read documents.
Something wrong with this question?
A project manager is responsible for a complex project, and the team is communicating with stakeholders to reach a consensus on the project scope. Several key stakeholders hold different views on whether certain deliverables are in scope, and the project boundary and acceptance conditions remain unclear. To settle the detailed scope description, what should the project manager do?
Show answer and explanation
Correct answer: B
A complex project is defining scope. Several key stakeholders hold different views on whether certain deliverables are in scope, and the boundary and acceptance conditions cannot be settled. The question asks how to settle the detailed scope description.
One tool for Define Scope is facilitation: bring together key stakeholders with different expectations and expertise and, in a workshop, reconcile their differences so that they form a cross-functional consensus on the deliverables and on the boundaries of the project and product. The obstacle in the stem is exactly a disagreement over the boundary with no consensus. The answer is B.
Why the other options are wrong
- A. The scope has not been settled yet. Leaving the dispute to later change management avoids what needs doing now, and a change management plan cannot substitute for consensus on scope.
- C. The project is already in Define Scope. The problem is disagreement over where to draw the boundary, not requirements that were never elicited, so eliciting again does not resolve the disagreement.
- D. If the team settles scope unilaterally and then informs stakeholders, it will not win the consensus of key stakeholders, and the result is easily overturned later, causing disputes.
Key takeaway When stakeholders disagree on the scope boundary, use facilitation to reach consensus; it is a tool of Define Scope.
Variation If the stem were changed to “choose among several technical options by scoring them on cost, risk and duration,” the answer would be multicriteria decision analysis; “turning a high-level product description into specific deliverables” would be product analysis.
Something wrong with this question?
A hybrid project keeps adding base stations to a 4G network, and the schedule baseline includes a schedule contingency reserve for an identified delivery delay risk. At the end of the first month the team is behind target and the operator's revenue for the month has suffered. Stakeholders want to improve return on investment (ROI) quickly and ask the project manager to say when these base stations can be put into operation and start charging. What should the project manager do?
Show answer and explanation
Correct answer: C
A hybrid project keeps adding base stations to a 4G network, and the baseline includes a contingency reserve for an identified delivery delay risk. At the end of the first month the schedule is behind, and stakeholders want to know the date for going live and charging. What should the project manager do?
The contingency reserve within the baseline is time set aside for identified delay risks, and the project manager draws on it under the risk management plan and the authority established (common exam practice: no separate change control needed). The schedule is already behind, so do a reserve analysis first: how much has been used, how much is left, and whether what is left is enough to cover the later risks. Then reforecast the go-live date from that and explain it to stakeholders. If the remaining reserve cannot cover the later risks, the forecast date has to move back accordingly. The answer is C.
Why the other options are wrong
- A. Reporting business updates more often does not answer the go-live date question and does not improve the schedule.
- B. The project approach cannot be switched at will, and even changing to predictive would not automatically yield a reliable date. The problem is that the reserve has not been assessed.
- D. Redrawing the boundary between agile and predictive modules has no direct bearing on the schedule slip or on forecasting a date.
Key takeaway When the schedule is behind, do a reserve analysis first (how much contingency reserve has been used and how much is left), then forecast the date.
Variation If the stem said the event was an unidentified emergency and the contingency reserve was used up, you would go through the change control procedure to request management reserve. If asked who draws on the contingency reserve, the answer is the project manager, under the risk management plan and the authority established (common exam practice: no separate change control needed).
Something wrong with this question?
On a project, only one engineer can do Activity M and Activity N, and both activities are scheduled for Days 4 to 6, which creates a conflict. M is on the critical path and has zero total float, while N has 5 days of total float. Which two judgments are correct? (Choose 2.)
Show answer and explanation
Correct answer: BC
Only one engineer can do M and N, and both are scheduled for Days 4 to 6. M is on the critical path, and N has 5 days of total float. You must judge whom to delay first and which technique each choice is.
The difference between smoothing and leveling lies in whether the delay goes beyond the float and whether the critical path is touched. Making N wait for M, so N runs from Day 7, delays N by 3 days, which does not exceed its 5 days of float, so the finish date and the critical path do not change; this is resource smoothing, and B is correct. Making M wait for N delays M, which has no float, by 3 days, so the finish date slips 3 days; this uses the critical path and is resource leveling, and C is correct. The answers are B and C.
- Option 1: M on Days 4-6, N on Days 7-9; N is delayed 3 days, 3 ≤ 5, the finish date is unchanged: smoothing
- Option 2: N on Days 4-6, M on Days 7-9; M is delayed 3 days and has no float, so the finish date slips 3 days: leveling
Why the other options are wrong
- A. M is on the critical path and has no float, so delaying it necessarily delays the finish date.
- D. Both techniques change start dates. The criterion is not whether dates change but whether the delay goes beyond float and touches the critical path; N's delay is within its float, so it is smoothing.
Key takeaway Delaying an activity within its available float to resolve a resource conflict is resource smoothing. If the adjustment instead delays a zero-float critical-path activity, it is resource leveling and affects the project duration.
Variation If N had only 2 days of total float, a 3-day delay would exceed it by 1 day; N's path would then become the new longest path and the finish date would slip 1 day, so it could only count as resource leveling.
Something wrong with this question?
A project manager is in charge of a showroom fit-out project and has signed an installment-payment contract with the customer. During execution the customer notifies the project manager that the next payment will be a month late and agrees to move the completion date back by a month; the schedule change has been approved through the formal change process. The project manager calculates that, at the current rate of spending, even counting management reserve, the funds will not last until the new payment date. What should the project manager do?
Show answer and explanation
Correct answer: B
During execution the customer delays a payment by a month, and the corresponding delay in completion has been approved through the formal change process. But at the current rate of spending, even with management reserve, the funds will not last until the new payment date.
The timing of funds arriving does not match planned expenditure, so you do funding limit reconciliation: adjust the schedule so that the rate of spending matches the pace at which funds arrive. Since the completion date can slip, release some resources and slow the pace to lower the rate of spending and last until the next payment date. The answer is B.
Why the other options are wrong
- A. Suspending and disbanding the team is too passive. The customer has only delayed a payment and has not terminated the contract, and reassembling the team later would be very costly.
- C. Lowering the quality standard would harm the deliverables. The project manager cannot lower quality standards unilaterally to save money; if quality requirements must be adjusted, it needs assessment and approval through the change process.
- D. The stem says that even counting management reserve the funds will not last until the new payment date, so keeping the current pace would still run dry. Management reserve is also not meant to bridge a payment delay.
Key takeaway When funds do not arrive in time, adjust the schedule and slow the rate of spending so that expenditure matches the arrival of funds. Slowing the pace adjusts the schedule and funding arrangements; if it affects an approved baseline, it still goes through change control.
Variation If the customer did not agree to delay completion, assess reducing scope, applying early for interim funding, or negotiating a change with the customer. If funds arrive early, you can speed up.
Something wrong with this question?
The project manager is sorting out this month's quality work. Which TWO of the following are quality control activities rather than quality assurance? (Choose 2.)
Show answer and explanation
Correct answer: BC
Some of the four options are aimed at the process and some at the deliverables, and you must pick the two that are quality control. Quality control and quality assurance both serve the quality objectives, and the key to telling them apart is the object each focuses on.
The test is the focus: quality control focuses on whether deliverables meet defined specifications and thresholds, and quality assurance focuses on whether processes are compliant and effective. B, “checking whether completed deliverables meet the quality metrics”, and C, “recording product defects found in testing”, are both aimed at deliverables and are quality control. The objects of A and D are processes, so they are quality assurance. In a multiple-response question, judge each option by its object, and do not pick an option just because it sounds “related to quality”. The answers are B and C.
Why the other options are wrong
- A. Auditing whether the team's process follows organizational standards focuses on the process. It is a quality audit and belongs to quality assurance.
- D. Summarizing good practices from a quality audit and spreading them uses the audit results to improve the process, which is the role of quality assurance.
Key takeaway Look at the focus: checking deliverables and recording defects are quality control; process audits and spreading good practices are quality assurance. Quality control answers “is the result acceptable?”, and quality assurance answers “is the way of working right, and can it be improved?”
Variation If an option said “draft the quality management plan”, that is quality management work in project planning. It is neither a quality assurance nor a quality control activity.
Something wrong with this question?
An agile team is developing online appointment software, and a newly joined developer asks when quality control should be performed. As the product owner, how should you answer?
Show answer and explanation
Correct answer: D
An agile team is developing online appointment software, and a new developer asks when quality control should be performed. The product owner has to answer. In essence the question is about the timing of quality activities on an agile project.
Agile projects stress building quality into the process: testing, review and integration go on continuously within every iteration, and the earlier a defect is found, the less trouble it causes. So quality control is not an activity at one fixed point, but something done throughout the development process, continuously. That is consistent with PMBOK 8's goal of detecting and preventing defects early and reducing rework. So the answer to “when is quality control done in agile?” is not one meeting or one milestone: it is done in every iteration, for every story and with every commit. The answer is D.
Why the other options are wrong
- A. Doing it in a block after the iteration ends finds defects late, makes rework more expensive and runs against the principle of prevention first.
- B. Doing it before the iteration review meeting covers a single point in time, which is too narrow.
- C. The retrospective is for summarizing experience and improving ways of working. It is not where quality control is carried out.
Key takeaway In agile, quality activities run continuously through the whole development process, not at a single point in time.
Variation If asked “who is responsible for quality?”, the answer is that the whole team shares responsibility. If asked “how do we make sure every story meets the standard?”, the answer is the definition of done.
Something wrong with this question?
A chain logistics company has used its warehouse management system for ten years and decides to upgrade it, appointing an experienced project manager to lead the project. During the first round of identifying stakeholders, the project manager finds that the warehouse manager and the dispatch manager believe the current system is good enough and worry that the upgrade will slow their teams' work. What should the project manager do next?
Show answer and explanation
Correct answer: A
A warehouse management system upgrade project is at the stage of identifying stakeholders. The warehouse manager and the dispatch manager think the current system is good enough and worry that the upgrade will slow operations. You must decide the next step.
The two managers' opposition comes from worry about work efficiency. This is a concern to be addressed, not a formal change requirement. One of the activities in Manage Stakeholder Engagement is addressing concerns and managing expectations, which uses communication and interpersonal skills (listening, influencing, negotiation, conflict management). First hear what worries them, then explain how the upgrade will protect operating efficiency, and win their support. The answer is A.
Why the other options are wrong
- B. Escalating before communicating directly with the people involved tends to sharpen the conflict. Stakeholders' concerns should first be handled by the project manager through communication.
- C. Monitoring evaluates how effective existing engagement efforts are. No engagement action has been taken yet, so there is nothing to monitor.
- D. The two managers have expressed worries, not asked for a change to the scope. Going through change control does not answer why they do not support the project.
Key takeaway When stakeholders withhold support out of worry, first use interpersonal skills to address their concerns; do not escalate, run change procedures or only monitor.
Variation If the two managers made it explicit that “we will agree only if an interface function is added,” that is a specific scope request, which should be assessed and submitted as a change request through integrated change control.
Something wrong with this question?
A newly assigned project manager leads an exterior design project for a home appliance maker. The designers are located in different cities. Communication over video and text often causes misunderstandings because people do not express themselves clearly, the team lacks a good collaborative atmosphere, and design quality is suffering. The company has agreed to bring members together in one location for short periods at critical stages. What should the project manager do?
Show answer and explanation
Correct answer: C
A newly assigned project manager leads an exterior design project whose designers are in different cities. Video and text communication keeps causing misunderstandings, the collaborative atmosphere is poor, and quality is affected. The company allows short-term gatherings at critical stages.
Colocation places the main team members in the same physical location to strengthen the team’s ability to perform, and it can be used only at strategically important times. The root of the problem is dispersed locations combined with poor online communication, and the company allows members to gather at critical stages. Bringing members together temporarily, so that face-to-face conversation clears up misunderstandings and builds a sense of team, is the most direct fix. The answer is C.
Why the other options are wrong
- A. Blaming and criticizing individuals does not address the root cause. The communication barrier comes from dispersed locations and the way people communicate online, and criticism will not improve the collaborative atmosphere.
- B. The problem is within the project manager’s own remit and can be addressed directly with team building and colocation. Passing it to the sponsor is not proactive and may not help.
- D. The misunderstandings arise from video and text communication in the first place. Using the same channels more often does not fix the root problem and does not build a sense of team.
Key takeaway When online communication is causing misunderstandings and conditions allow it, use temporary colocation so that face-to-face communication removes the misunderstandings and builds team spirit.
Variation If the stem said the company would not allow any form of colocation, the answer would change to building a collaboration platform and adding video meetings and one-on-one conversations. If the misunderstandings came from cultural differences, discuss them openly and agree shared working conventions.
Something wrong with this question?
In a probability and impact matrix, what is the most typical feature of an opportunity located in the high-priority area?
Show answer and explanation
Correct answer: D
Threats and opportunities are placed in the same probability and impact matrix. The question asks what characterizes an opportunity located in the high-priority area.
The matrix sets priority from predefined rules for combining probability and impact, and when numeric scoring is used the product of probability and impact can be calculated. For an opportunity, impact means the positive benefit if it occurs. High probability together with large positive impact is the most typical case of a high-priority opportunity, although the exact zones depend on the matrix the project uses. An opportunity with a high likelihood and a large benefit is both likely to occur and highly rewarding if it does, so it deserves priority attention. The answer is D.
Why the other options are wrong
- A. Low probability, large benefit: whether it falls in the high-priority area depends on the matrix definitions in the risk management plan, and it can be high priority when the product reaches the threshold, but that is not the “most typical” feature. The most typical case is large on both dimensions at once.
- B. High probability but a small benefit gives a product that is not high, so it usually falls in the medium or low priority area. It also does not satisfy “large on both dimensions”.
- C. What goes on the watch list are risks with both low probability and low impact, the opposite of “high priority”. A low-probability opportunity can reach a high-priority cell only if its impact is extremely large and the product reaches the threshold, which is not the most typical feature.
Key takeaway In the matrix, both opportunities and threats get their priority from the combination of probability and impact, and high probability with high impact is the most typical high-scoring case.
Variation If the question asked about a threat in the high-priority area, it would be high probability with a large negative impact, which needs a response arranged first. If it asked for the next step after finishing the register at identification, the answer is to assess probability and impact using the definitions in the plan.
Something wrong with this question?
The project manager outsources a park landscaping job and gives the supplier construction drawings and a bill of quantities. During construction the supplier says it underestimated the quantities at the start, so its costs have run over, and asks the project manager to make up the difference. The contract has no cost-sharing or price-adjustment clause, and the project manager refuses. Which contract did the two parties most likely sign?
Show answer and explanation
Correct answer: B
The project is in construction with drawings and a quantity list in place, and the supplier asks for a higher price because of its own estimating error. The question asks which contract type this corresponds to.
The signal: the supplier says it underestimated the quantities and asks for the difference, and the project manager refuses. That means the price does not change because of the seller’s estimating error, and the cost overrun is the seller’s own to bear. This is a firm fixed-price contract. Under a fixed price incentive fee contract the contract must have a sharing ratio, and before the ceiling price the buyer shares by ratio the part above target cost, which does not fit “no cost-sharing clause at all”. Under time and materials and cost plus incentive fee contracts the buyer pays for the added cost, so a refusal would have no contractual basis. The answer is B.
Why the other options are wrong
- A. A time-and-materials contract settles on actual hours and materials, so the added work has to be paid for anyway and would not be refused.
- C. Under a cost plus incentive fee contract the buyer reimburses actual cost and has to pay more when cost rises, so refusing to make up the difference would have no contractual basis.
- D. A fixed price incentive fee contract has a sharing ratio above target cost, so the buyer shares the part above target cost by ratio and would not refuse it all. Only past the point of total assumption (where the price reaches the ceiling) does the whole overrun fall on the seller.
Key takeaway Refusing a price increase caused by the seller’s own estimating error corresponds to a firm fixed-price contract.
Variation If the contract allowed the price to be adjusted for rising material prices, it would be a fixed price with economic price adjustment contract and the seller’s request would have a basis; if the added work came from the buyer changing the scope, the seller could seek compensation through the change procedure.
Something wrong with this question?
An energy company plans to build a subsea power transmission line linking three coastal cities and hires a contractor for the construction. The detailed design of the work will not be finished until several months after the contract is signed, but the company requires the line to be in service within 30 months. The company does not intend to terminate the contract midway or to change the agreed scope of the line. The project manager wants the price mechanism to have the company and the contractor share risk so that the risk allocation between them is balanced. When planning the sourcing strategy or procurement strategy, which TWO contracting techniques should be considered? (Choose two.)
Show answer and explanation
Correct answer: AE
At signing the detailed design and implementation details are not settled and the schedule is limited. The company does not intend to terminate midway or adjust the scope. The question asks which contracting techniques keep risk balanced between buyer and seller (these techniques are common exam terms for adaptive projects).
The stem has three conditions: the detailed design is completed several months after signing (the design and implementation details are not settled), the date for entering service is fixed, and the aim is to balance risk between buyer and seller. Among the contracting techniques commonly used on adaptive projects (“fixed-price increments” and “graduated time and materials” are common exam terms), fixed-price increments cut the work into increments, each separately priced and paid after acceptance, so as the design becomes clear the two sides re-agree increment by increment, and neither has to bear all the uncertainty at once. Graduated time and materials has the two sides share financial risk: for early delivery the seller is paid a higher hourly rate, and for late delivery the rate is reduced, so both share the consequences of savings and delays. The answers are A and E.
Why the other options are wrong
- B. A firm fixed-price contract puts all the design change risk on the seller, but the detailed design is completed several months after signing and the design and implementation details are still uncertain, so the risk allocation clearly favors the buyer and cannot achieve the balance the stem asks for.
- C. In the stem the company does not intend to terminate midway. An early cancellation option mainly gives the buyer more flexibility to end early and protects the seller through a termination fee. It does not directly correspond to phased pricing or risk sharing in the price.
- D. In the stem the company does not intend to adjust the scope. A dynamic scope option lets the buyer swap scope by priority at milestones, which addresses scope flexibility and not risk sharing in price or rates.
Key takeaway To balance risk between buyer and seller use fixed-price increments and graduated time and materials: the first prices segment by segment by increment and the second adjusts the rate by how fast delivery is made.
Variation If the stem emphasized “the buyer wants maximum flexibility and may terminate at any time”, that would point to an early cancellation option; if it emphasized “scope is adjusted by priority”, to a dynamic scope option.
Something wrong with this question?
The agile team on an enterprise data dashboard project is in its third Sprint. The customer suddenly raises an urgent change: if it is not made, the value delivered to the customer will suffer, and if it is made, the Sprint Goal will be at risk. What should the team do next?
Show answer and explanation
Correct answer: B
In the third Sprint, the customer raises an urgent change: not making it harms the value delivered, and making it puts this Sprint's Sprint Goal at risk. The question is what the team should do next.
During a Sprint, no change may endanger the Sprint Goal, but as more is learned the Developers may negotiate the scope of the Sprint Backlog with the Product Owner. This change has a cost either way, so the team should work with the Product Owner to reassess its value, order and impact; the Developers can then update the Sprint Backlog while protecting the Sprint Goal. The answer is B.
Why the other options are wrong
- A. Putting it in the next Sprint means the change is not made now. The stem states that not making it harms the customer's value, so this does not meet the premise.
- C. Handing it to another team is passing the buck, and it does not assess the value or impact of the change.
- D. Agile stresses a sustainable pace. Taking on both the new requirement and the original work through overtime increases quality risk and is not the preferred way to resolve this conflict.
Key takeaway When an urgent change appears in the middle of a Sprint, the Product Owner and the team reassess priority and impact together.
Variation If the team finds that a new task takes too long and this Sprint cannot finish it, so that features must be cut or a whole story dropped, it likewise talks with the Product Owner, and does not decide by itself or turn to stakeholders or the Scrum Master.
Something wrong with this question?
The project manager has an AI tool forecast the estimate at completion (EAC) from earned value data and plans to compare it with the EAC calculated by formula. Compared with a formula calculation, what needs the MOST extra attention when using an AI forecast?
Show answer and explanation
Correct answer: B
In a project, the project manager has AI forecast the estimate at completion (EAC) from earned value data and will compare it with the EAC calculated by formula. The question asks what needs the most extra attention with an AI forecast compared with a formula calculation.
The key is what an AI forecast requires beyond a formula calculation. A formula calculation also depends on accurate, consistent inputs, but its method is fixed. An AI forecast also depends on training data and model assumptions, and its output may be inaccurate or biased, and PMBOK 8 stresses that information obtained from AI should be checked and validated. So you must examine both the input data and the model assumptions and also validate the forecast output, comparing it with the formula result. The answer is B.
Why the other options are wrong
- A. The style and colors of a chart affect only presentation, not whether the forecast is reliable.
- C. Choosing an EAC formula is a consideration in formula calculation, not an extra point for AI forecasts. The particular risk of an AI forecast lies in its data and model inputs.
- D. Converting currency units at exchange rates is a routine check in any cost calculation and is not specific to AI.
Key takeaway An AI forecast is not black-box truth: examine the input data and model assumptions, and check and validate the output.
Variation If the AI result differs greatly from the formula, the next step is still to check the input data and model assumptions first, not to accept or reject it outright. If asked which strategy level this application belongs to, the answer is assistance (predictive analytics for planning).
Something wrong with this question?
A hospital appointment system project uses a predictive approach. A team member responsible for interface development has twice failed to finish tasks on time, and as a result a milestone was missed. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
This is a predictive project. A team member responsible for interface development has twice missed task deadlines, causing a missed milestone, and the stem does not give the reason. The question asks what to do FIRST. With no ready-made process step, an analysis action should come first.
The signal is that the cause is unknown. When the cause is unclear, the project manager first talks privately with the person involved to learn why the tasks were not finished on time. Only then can you tell whether the problem lies with skills, with resources or with the task itself, and decide what to do. Analyze and communicate first, then act. The answer is D.
Why the other options are wrong
- A. Demanding an explanation in front of the whole team holds him to account before the cause is known and damages team relationships. Find out in private first.
- B. Reporting to the functional manager and asking for a performance action before finding out the cause escalates first and investigates afterwards, which is the wrong order.
- C. Changing the schedule baseline requires change control, and the project manager has no authority to push it back directly. Also, with the cause of the delay unknown, you cannot tell whether the schedule really needs to change.
Key takeaway When the cause is unknown, find it out first, and do so in private. Do not hold someone to account in public, do not escalate straight away and do not change the baseline directly.
Variation If it were confirmed that his time had been pulled away, the next step would be to assess the impact and coordinate resources. If the question asked what should have been done beforehand, the answer would be to define roles, responsibilities and communication rules during planning.
Something wrong with this question?
Keep going: practice by chapter below. 1,000 free questions with explanations, and a free account saves your progress.
What is free and what a paid pass adds
| No account | Free account | Paid pass | |
|---|---|---|---|
| Questions | 1,000 free questions | All 2,876 | All 2,876 |
| Explanations | Full, on every free question | Full on free questions; on the rest, only right or wrong and a link to the study guide | Full, on every question |
| Daily limit | 30 new questions a day | 30 new questions a day | None |
| Progress | Saved on this device | Saved to your account | Saved to your account |
| Wrong-answer lists, bookmarks | On this device | Included | Included |
| Custom sets by topic, chapter or knowledge point | Free questions | Free questions | Whole bank |
| Full mock exams | Not included | Mock 1 (180 questions), retakes allowed | All 10 |
| Video course | 320 videos, free with an account | 320 videos, free | 320 videos, free |
| Contact hours certificate | Not included | Not included | 35 hours: all 320 videos plus the end-of-course quiz |
| Price | $0 | $0 | 30 days $19.99; 90 days $29.99; 180 days $39.99 |
PMP practice questions: common questions
Are these PMP practice questions free?
Yes. 1,000 questions across all themes are open to everyone with no sign-up, and each has a full explanation. A free account lets you answer any of the 2,876 questions in the bank. Either way, the limit is 30 new questions a day. On the questions beyond the free ones you see whether your answer was right; the correct answer and the explanation come with a paid pass.
Do they follow the current exam outline?
Yes. The questions are grouped by the chapters of the study guide, which follows the current PMP Exam Content Outline, and each one tests a knowledge point of its chapter.
What are Core questions?
Core questions are 515 representative questions, about two per lesson, chosen from the questions beyond the free ones. They cover different points of each lesson, so they make the quickest first pass: do these first. To practice Core questions only, choose "Core questions — do these first" above the chapter list, or use the Core button to open the next chapter with Core questions left.
What does a paid pass add?
The correct answer and a full explanation on every question, including why each wrong option is wrong, no daily limit, and custom sets drawn from the whole bank. Wrong-answer lists, bookmarks and practice by chapter are free.
Is there a daily limit?
Yes, without a paid pass: 30 new questions a day, whether you are signed out (the 1,000 free questions) or on a free account (the whole bank). A paid pass has no limit.