Rolling Wave Planning and Developing the Schedule

PMP · Schedule · 2 lessons · about 24 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

This is the first chapter of the Schedule topic. It answers the question "where does the schedule start, and how do you get going?" You first need a schedule management plan, which sets out how the schedule will be built and managed. Then you move into the Develop Schedule process. PMBOK 8 folds defining activities, sequencing activities and estimating activity durations into this one process, and it is carried out in four steps: define activities, determine sequence, estimate effort and duration, and adjust. This chapter covers the ground rules and the first step: decomposing work packages into schedule activities, using rolling wave planning when information is limited, and producing the activity list, activity attributes and milestone list. The following chapters cover steps two, three and four in turn.

By the end of this chapter you should be able to do the following. List the main contents of a schedule management plan (the items this chapter stresses, plus links to organizational procedures, schedule maintenance and reporting formats) and know that it contains no specific dates. Recite the four steps of developing the schedule in order and tell which step a project is currently at. Distinguish decomposition of the WBS from decomposition when defining activities. Explain why rolling wave planning is detailed for the near term and high level for the future, and how it is used in predictive, adaptive and hybrid projects. Distinguish an activity, activity attributes and a milestone, and know that a milestone has zero duration.

Lessons in this chapter

Chapter map

Plan Schedule Management → schedule management plan (how to manage; no specific dates)

Develop Schedule

  • Step 1 Define activities ← scope baseline (WBS work packages) decomposition / rolling wave planning (detailed near term, high level later; planning packages) → activity list, activity attributes, milestone list (zero duration)
  • Step 2 Determine sequence → precedence diagramming method chapter
  • Step 3 Estimate effort and duration → estimating techniques and three-point estimating chapters
  • Step 4 Adjust → critical path method, resource optimization, critical chain method, schedule compression

How the exam tests this

Questions in this chapter are mostly "what is the next step?" questions and concept distinctions. Common forms include: what is missing from the schedule management plan; the scope baseline exists, so which step of developing the schedule comes first; which technique fits when information is limited, future details are unclear and there is a hard deadline; what is special about milestones, and what to do when a plan has no milestones; and what the output of defining activities is. Nearly all of these can be answered directly from the order of the four steps and the definition of rolling wave planning.

Study tips and practice

  • Line the four steps up in a row first, then see which step each question is at. "What is the next step?" questions then become a matter of matching.
  • Keep three things apart: the schedule management plan says how the schedule is developed and managed; the project schedule is an output of the schedule model; the schedule baseline is the approved version of the schedule model.
  • In chapter practice, watch for two keywords in rolling wave planning and milestone questions: "level of detail" and "zero duration".

Lesson 1

The Schedule Management Plan and the Four Steps of Developing the Schedule

Lesson video

Lesson overview

The Schedule topic answers the questions "when will the project finish, and when does each piece get done?" Before answering them you need ground rules: how the schedule will be built, how it will be managed, and how large a deviation must be acted on. Those rules are the schedule management plan. With the rules in place you can build the schedule. PMBOK 8 combines defining activities, sequencing activities and estimating activity durations in one process called Develop Schedule, carried out in four steps. This lesson explains these two things and their order. ECO: Process domain, Task 8 (Plan and manage schedule). The next three chapters expand steps two and three; step four, "adjust", is handled by the later chapters on the critical path method and related techniques.

The schedule management plan: decide "how to manage" first

Plan Schedule Management is the process of establishing policies, procedures and documentation for designing, developing, managing, performing and maintaining the schedule. Its key benefit is that it provides guidance and direction on how the project schedule will be managed throughout the project. The main inputs are the project charter, the project management plan, the development approach, enterprise environmental factors and organizational process assets. Common tools are expert judgment, alternative analysis and meetings. The output is project management plan updates, which include the schedule management plan.

The schedule management plan is the standard you follow when you later build the schedule and monitor variances. It says how to manage the schedule and contains no specific dates itself. A familiar exam reminder: the schedule management plan contains no schedule, just as the scope management plan contains no scope.

The specific output of this process is the schedule management plan, including information on project schedule development, release and iteration length, level of accuracy, units of measurement, links to organizational procedures, project schedule maintenance, control thresholds, rules of performance measurement, and reporting formats. Five of these are tested most often, and you should be able to give an example of each:

ContentExplanationExample
Release and iteration lengthHow long each release and iteration lasts in an adaptive project, fixed in advance; with fixed timeboxes, scope creep is easier to resistEach iteration is 2 weeks and each release is 3 iterations
Level of accuracyThe acceptable range for activity duration estimates, which may include an amount for contingenciesAn estimate may be "10 days ± 2 days"
Units of measureThe unit used to measure each type of resourceLabor in person-days, materials in tons
Control thresholdsHow large a deviation must be before action is required, usually written as a percentage deviation from the baselineA schedule variance of more than 10% of plan triggers corrective action
Rules of performance measurementThe rules used to measure schedule performance, such as earned value management (EVM)Percent complete is recorded with the "0/100" rule

The other items are how the schedule model is developed, the links to organizational procedures, how the schedule model is maintained, and the reporting formats. Control thresholds work the same way as for cost: a deviation within the threshold is handled by the project manager within their own authority; a deviation that reaches or exceeds the threshold is handled with the action the schedule management plan specifies, and whether to escalate depends on the project's governance and authority arrangements. The development approach is one of the inputs to Plan Schedule Management because it strongly affects how the schedule is planned: for example, detailed planning up front, or progressive elaboration as iterations proceed and information grows (predictive projects may also use rolling wave planning).

Developing the schedule: four steps

Develop Schedule is the process of analyzing sequences, durations, resource requirements and schedule constraints to create a schedule model for project execution and monitoring and controlling. The schedule model is used to determine the planned start and finish dates for project activities and milestones based on the best available information. Developing an acceptable project schedule is an iterative process: it may require the review and revision of duration estimates, resource estimates and schedule reserves to establish an approved project schedule that can serve as a baseline to track progress.

Figure 1: The four steps of developing the schedule
StepWhat you doWhat you getChapter in this course
1 Define activitiesDecompose work packages into activities that can be estimated and assignedActivity list, activity attributes, milestone listRolling wave planning (next lesson)
2 Determine sequenceDetermine the logical order and dependencies among activities, adding leads or lags where neededSchedule network diagramPrecedence diagramming method
3 Estimate effort and durationEstimate how many work periods each individual activity needs with the estimated resourcesDuration estimates and basis of estimatesEstimating techniques; three-point estimating
4 AdjustReview the draft schedule; if it is not acceptable, adjust its components and look for alternativesA schedule that can be approvedCritical path method, resource optimization, critical chain method, schedule compression

Step 4, "adjust", is not one technique but a family of them: the critical path method, resource optimization, the critical chain method, schedule compression, what-if analysis, simulation and others are all used in this step. Once a draft exists, team members also check whether the dates assigned to them conflict with resource calendars or with tasks on other projects, and decide whether resources need to be leveled before the schedule is approved as a baseline.

Scope work comes before the four steps. You first elicit and analyze requirements, define the scope and build the work breakdown structure (WBS), and only then start step 1. The reason is simple. In a predictive project, activities are normally drawn from the work packages at the lowest level of the WBS; in an adaptive project, activities can be progressively elaborated from the backlog and the scope of the current iteration. Duration, cost and resource estimates and risk analysis at the activity level can begin only once the activities have been listed, because they ask when this activity will be done, how much it will cost, who will do it and whether anything could go wrong with it. High-level planning and identification in these areas can start earlier.

PMBOK 8 adds a reminder: with project timelines continuously shrinking, and details still evolving, many predictive projects no longer build a detailed schedule up front. They outline the broad milestones and key activities first and then refine them as information increases. That is rolling wave planning, the subject of the next lesson.

Worked examples

Example 1 What is missing from the schedule management plan

Question 1Example

A project manager at a software company reviews a newly drafted schedule management plan. It specifies release timeframes and units of measure, but it does not say how schedule performance will be measured or how large a variance must be before action is taken. What should the project manager do?

Show answer and explanation

Correct answer: B

A schedule management plan has just been drafted. It already states release timeframes and units of measure, but it does not say how schedule performance is measured or how large a variance must be before action is taken. How should the gap be fixed?

The schedule management plan establishes the criteria for developing, monitoring and controlling the schedule. Typical contents include release and iteration length, level of accuracy, units of measure, control thresholds and rules of performance measurement. The stem already has two of these, and what is missing is exactly the rules of performance measurement (which rule is used to measure progress) and the control thresholds (how large a variance requires action). Both should be settled before the detailed schedule is built, so that later monitoring has rules to follow. They belong in the schedule management plan. The answer is B.

Why the other options are wrong

  • A. Waiting for a delay before discussing how to monitor turns the rules into an after-the-fact fix. The purpose of a schedule management plan is to set the criteria in advance.
  • C. The schedule baseline is the approved version of the schedule model and records planned dates for each activity. The allowed range of variance is a control threshold, usually written as a percentage deviation from the baseline parameters, not a number of days attached to each activity in the baseline.
  • D. Monitoring rules are one of the things the schedule needs before it is built, so they should be set before the detailed schedule. If they are left until execution, nothing guides the team when a variance appears.

Key takeaway The schedule management plan says how the schedule will be managed, and the rules of performance measurement and control thresholds must be set before the detailed schedule.

Variation If what is missing is the length of each iteration in an adaptive project, add that to the schedule management plan too. If a variance is within the threshold, continue monitoring it; if it reaches or exceeds the threshold, follow the response action specified in the schedule management plan.

Something wrong with this question?

Report an issue with this question

Example 2 Which step to start from

Question 2Example

The schedule management plan has been approved and the team has chosen its development approach. The project manager must develop the schedule for a new product release and already has the approved scope baseline. Where should she start?

Show answer and explanation

Correct answer: C

The schedule management plan is approved, the development approach has been chosen, and the approved scope baseline is in hand. The project manager must develop the schedule for a new product release. At which step does Develop Schedule begin?

Developing the schedule takes four steps, which proceed in this order (the whole is iterative and you can go back and revise): define activities, determine sequence, estimate effort and duration, and adjust. Each step builds on the previous one. Activities are drawn from the work packages at the lowest level of the WBS in the scope baseline, and without activities there is nothing to sequence or estimate. The scope baseline is approved, so step 1 is to decompose the work packages into activities and build the activity list. Only after that do you sequence. The answer is C.

Why the other options are wrong

  • A. Estimating is step 3. At this point the activities are not defined and the sequence is not set, so there is nothing to estimate.
  • B. Determining sequence is step 2 and takes the activity list as input. With no activities broken out, there is nothing to sequence, so you cannot start here.
  • D. Reviewing and adjusting is step 4. There is not even a draft schedule yet, let alone anything to adjust.

Key takeaway The four steps proceed in order and can be revisited. With a scope baseline in hand, start with defining activities.

Variation If the stem said “the activity list is complete but many precedence relationships are not yet worked out”, the next step is determining sequence. If it said “the network diagram is drawn but has no durations”, the next step is estimating effort and duration.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The schedule management plan says "how to manage" and contains no specific dates. Specific dates appear in the project schedule; the project schedule is an output of the schedule model; once approved, the schedule model becomes the schedule baseline.
  • The four steps generally proceed in this order, but Develop Schedule is an iterative process: you can go back and revise, and steps can overlap. When a question asks "what is the next step?", first work out which step the project has reached. With only an activity list, the next step is sequencing. With a network diagram but no durations, the next step is estimating. Only when the critical path has been calculated and resources conflict does resource optimization come in.
  • "Adjust" is the name for a group of techniques, not a single tool.
  • A deviation within the threshold is handled by the project manager within their authority. A deviation that reaches or exceeds the threshold is handled with the action the schedule management plan specifies, and if it goes beyond your authority you escalate through the governance process. Do not go to the sponsor at the first sign of any deviation.
  • Estimating is step 3, not step 1. Without defined activities you cannot estimate durations at the activity level, and without activity sequences and durations you cannot calculate the critical path.

Key takeaways

Key point

  • The schedule management plan states how the schedule is built and managed. It contains no specific schedule.
  • Five commonly tested contents: release and iteration length, level of accuracy, units of measure, control thresholds and rules of performance measurement.
  • The four steps of developing the schedule are define activities, determine sequence, estimate effort and duration, and adjust. They proceed in this order, but the whole is iterative and you may go back and revise.
  • PMBOK 8 folds defining activities, sequencing activities and estimating activity durations into Develop Schedule.
  • "Adjust" covers a group of techniques: the critical path method, resource optimization, the critical chain method, schedule compression, what-if analysis and others.

Lesson 2

Decomposition, Rolling Wave Planning, and the Activity and Milestone Lists

Lesson video

Lesson overview

The first step of developing the schedule is defining activities: breaking the lowest-level work packages of the WBS into specific actions that can be estimated and assigned. But early in a project the details of future work are often unclear, and forcing a breakdown only produces a wrong one. That is when you use rolling wave planning: decompose the near term in detail, keep the far term high level, and refine it as information grows. This lesson covers decomposition, rolling wave planning, and the three outputs of defining activities: the activity list, activity attributes and the milestone list. The previous lesson covered the four steps and this lesson is step 1; the next chapter covers step 2, sequencing. ECO: Process domain, Task 8 (Plan and manage schedule), which includes developing the schedule according to the chosen development approach and estimating project tasks (including milestones).

From work packages to activities: decomposition

Defining activities means identifying and documenting the specific actions to be performed to produce the project deliverables. A work package is the work at the lowest level of the WBS, for which cost, effort, duration and resources can be estimated and managed. It is usually broken down further into smaller activities, and the activities represent the effort needed to complete the work package. You need scope information, especially the project scope statement, WBS and WBS dictionary in the scope baseline: the WBS, deliverables, constraints and assumptions in them must all be considered explicitly when you define activities.

Decomposition means breaking the project scope and deliverables down into smaller, more manageable parts, level by level. In the WBS, what is decomposed is the project scope and the result is work packages. In defining activities, what is decomposed is a work package and the result is activities. The two decompositions sit at different levels: one makes clear what is to be delivered, the other identifies the specific actions needed to complete a work package. Owners, resources and durations are determined later in planning. Involving the team members who will do the work in the decomposition usually makes the result more accurate.

Example: the "order page" of a shop mini-app

The WBS has a work package called "order page". It represents a piece of work that can be assigned and managed, and its duration could be estimated at the work package level, but it is still coarse and normally needs to be decomposed into specific activities so it can be sequenced and assigned in more detail. The team breaks it into four activities: design the page prototype, write the front-end code, integrate the payment interface, and test the ordering flow. Each activity is a verb plus an object, can be given an owner, and can be estimated on its own. The "operations dashboard" in the same WBS will not start until the next phase and its requirements are not yet clear, so it is not broken down yet and stays as a planning package.

Rolling wave planning: detailed near term, high level later

Rolling wave planning is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level. This progressive elaboration allows work to exist at various levels of detail, depending on the project life cycle stage. Early on, when information is less defined, work packages are outlined at a high level. As more information becomes available, these packages are decomposed into detailed activities.

Figure 1: Rolling wave planning: detailed near term, high level later

In the plan, rolling wave planning is progressive elaboration at work: near-term work is planned in detail, far-term work is outlined at a higher level first, and it is broken down further as information grows. A "planning package" here means a piece of work not yet broken down to activities: it has a name and a rough scope, its work content is known, but detailed schedule activities have not yet been determined, and it will be decomposed when the details are clear. A planning package sits below the control account and above the work package, and is later refined into work packages. The following two points are common exam practice: rolling wave planning is also commonly used for release planning in agile or predictive projects; and with each roll, the team typically goes back and does four things: refine the planning packages in the near-term window into work packages, decompose the work packages into activities, update the activity list, and update the schedule and related estimates.

How the three types of project use it

  • Predictive: the schedule is defined early, planned and sequenced in detail, a baseline is established and approved, and changes go through a formal procedure. Rolling wave planning is used for the parts of the far future that cannot yet be broken down.
  • Adaptive: the schedule is more flexible, the project is split into iterations, and planning horizons are short. Release planning is itself rolling: near-term iterations are detailed and later releases get only a rough scope.
  • Hybrid: the high-level schedule uses predictive techniques to list the key milestones and deliverables, and the sub-project streams below it follow adaptive or predictive approaches according to their own characteristics.

The activity list, activity attributes and the milestone list

Defining activities produces three artifacts: the activity list, activity attributes and the milestone list. When you use rolling wave planning or agile methods, the activity list is updated regularly because newly decomposed activities keep being added.

An activity list is a documented tabulation of schedule activities that shows the activity description, activity identifier and a sufficiently detailed scope of work description so project team members understand what work is to be performed. Its core columns are activity ID, name, description and a scope statement of sufficient detail. When the project needs it, extra fields such as the owner and notes can be added after resources are assigned. Activity attributes extend the description of each activity. At the start they typically include the unique activity identifier, the WBS identifier, the deliverable identifier and the activity label or name; later they gradually add predecessor and successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints and assumptions. Activity attributes are both an input to developing the schedule and one of the project documents consulted when estimating resources.

A milestone list identifies all of the project milestones and indicates whether each milestone is mandatory, such as one required by contract, or optional, such as one based on historical information. A milestone is a significant point or event in the project. Like an activity it has attributes such as a name and an ID, but it has zero duration: it marks a single point in time and consumes no time. Putting key milestones into the plan gives the sponsor and the team checkpoints to compare against.

Worked examples

Example 1 Limited information and a hard deadline: which technique

Question 1Example

A company has taken on a technical support project for the broadcast of a sports event. It must be finished before the opening ceremony in 5 months, and all it has so far is a high-level project vision; requirements have not been detailed. Which scheduling technique should the project manager use?

Show answer and explanation

Correct answer: D

A technical support project for a sports broadcast must be finished before the opening ceremony in five months, a fixed deadline. All the team has is a high-level vision and requirements have not been detailed. Which scheduling technique should be used?

The stem gives two signals: only a high-level vision (limited information) and a deadline that cannot move (no time to wait). When information is incomplete, forcing detailed activities will produce a wrong breakdown, and waiting until everything is clear means missing the deadline. Rolling wave planning addresses this planning problem. The near-term work that is clear is planned in detail, the far-term work stays at a higher level, and it is decomposed and the plan revised as more information becomes available. The answer is D.

Why the other options are wrong

  • A. What-if analysis assesses how different scenarios affect the schedule. It helps identify risks, but it does not replace the progressive elaboration of future work provided by rolling wave planning.
  • B. Building a detailed WBS and a complete schedule first can only be done once the requirements are clear. It takes a long time up front and is the worst choice for a project with a hard deadline.
  • C. The critical path method needs a usable network of activities or higher-level schedule elements and their logical relationships. The stem does not yet provide enough information for a reliable network, and CPM does not solve the problem that far-term work cannot yet be broken down.

Key takeaway When information is limited and you cannot wait, use rolling wave planning: detailed near term, high level later, refined as you go.

Variation If the requirements were fully frozen and all activities could be listed, you would not need rolling wave planning and could go straight to the network diagram and the critical path. If requirements have not yet been detailed, the corresponding approach is near-term iterations in detail and later releases at rough scope only.

Something wrong with this question?

Report an issue with this question

Example 2 Why does a milestone have no duration

Question 2Example

The project manager presents a milestone schedule to management. Someone asks why none of the milestones has a duration. How should the project manager explain it?

Show answer and explanation

Correct answer: A

The project manager presents a milestone schedule and someone asks why no milestone has a duration. The scenario does not depend on the development approach. What matters is the nature of a milestone.

A milestone is a significant point or event in the project. Like an activity it has attributes such as a name and an ID, but it marks only a single point in time and consumes no time, so its duration is zero. It is activities, not milestones, that have duration and consume resources. This is how the project manager should explain it to management: a milestone is by nature a point in time, so its duration is zero. The time is consumed by the activities before and after it, and the milestone marks the point reached when those activities are complete. The answer is A.

Why the other options are wrong

  • B. The durations of preceding activities belong to the activities. A milestone does not accumulate duration. Saying it “equals the sum of the activities before it” treats a point as a span of time.
  • C. Zero duration is what defines a milestone. All milestones are the same, whether or not they are on the critical path.
  • D. Zero duration comes from the definition, not from being “not yet estimated”, and nothing needs to be added after resources are confirmed. Estimating a duration for a milestone is itself a mistake.

Key takeaway A milestone is a point in time with zero duration. It is not an activity.

Variation If asked what else a milestone list must state, the answer is whether each milestone is mandatory (for example, required by contract) or optional (for example, based on historical information). Changing a critical activity to zero duration to “treat it as a milestone” is wrong, because it erases real work.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When the stem says "limited information", "future details are unclear" or "detailed for the near term, high level for the future", choose rolling wave planning. Do not define every activity in full all at once.
  • Rolling wave planning does not mean "do not plan yet". Future work does have a plan, only at a lower level of detail, and the activity list and schedule must be updated regularly as the project moves on.
  • The two "decompositions" are different. WBS decomposition breaks the project scope into work packages; decomposition in defining activities breaks work packages into activities.
  • A milestone is not an activity. You cannot estimate a duration for it, and you cannot turn a real critical activity into a zero-duration activity just to "treat it as a milestone".
  • A milestone must be marked mandatory or optional. A delivery date set by contract is a mandatory milestone.

Key takeaways

Key point

  • Defining activities decomposes work packages into activities. The scope baseline (WBS, WBS dictionary and so on) is the most important source of scope information.
  • Rolling wave planning is progressive elaboration applied to the plan: detailed near term, high level later, refined as information grows.
  • A planning package has a name and a rough scope and is not yet decomposed into activities.
  • The activity list lists all activities, activity attributes are enriched step by step, and the milestone list marks each milestone as mandatory or optional.
  • A milestone is a point in time with zero duration. It is not an activity.

This chapter has 19 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.