Scope

Validate Scope

PMP · Scope · 4 lessons · about 41 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Validate Scope is the last process in the Scope performance domain: the customer or another stakeholder with acceptance authority formally accepts the deliverables that have been completed and verified. The process has two main objectives: checking the processes being used to achieve quality standards, and formalizing the acceptance of the deliverables. PMBOK 8 places verification in Monitor and Control Scope and acceptance in Validate Scope. They are different processes that follow one another: verify first, accept second.

The exam concentrates on four points. First, the difference between verification and acceptance, and their order. Second, the inputs of Validate Scope (verified deliverables) and its tools (inspection, customer talks and tests, process analysis, review meetings). Third, acceptance needs formal approval and a record (a signature where one is required), and when acceptance fails, the reason is recorded first and the matter is then handled in whatever way the project handles change. Fourth, adaptive projects rely on the definition of done, the definition of ready and the acceptance criteria of user stories. A common mistake is to treat “passed the quality check” as “ready for closure.” ECO: Process domain, Task 2 (Develop and manage project scope) and Task 10 (Manage project closure).

Lessons in this chapter

Chapter concept map

Monitor and Control Scope ──verify──▶ verified deliverables ──▶ Validate Scope ──accept──▶ accepted deliverables ──▶ closure Tools: inspection · customer talks and tests · process analysis · review meetings

  • If not accepted: record the reason → if a change is needed, follow change control → remedy → reverify

Adaptive: user story acceptance criteria (clear before development) + DoR (can we start?) + DoD (is it done?)

Lesson 1

Purpose and Position of Validate Scope: Verify First, Then Accept

Lesson video

Lesson overview

Validate Scope is one of the six processes in the Scope performance domain. It sits in the Monitoring and Controlling focus area and follows on from Monitor and Control Scope: once deliverables are done and verified as correct, the customer or another stakeholder with acceptance authority formally accepts them. This lesson covers three things: what the process is meant to achieve; how it connects with Monitor and Control Scope from the previous chapter, and what “verify first, accept second” means; and when it takes place on a predictive project. This is a highly tested distinction on the exam, where options often treat “quality check passed” as “ready to close.” This lesson is here to correct that mistake. ECO: Process domain, Task 2 (Develop and manage project scope) and Task 10 (Manage project closure).

The purpose of Validate Scope

PMBOK 8 says: “The Validate Scope process has two main objectives: checking the processes being used to achieve quality standards and formalizing the acceptance of the deliverables. This process helps ensure that deliverables meet established quality standards and that these deliverables gain formal acceptance from stakeholders. The key benefit of this process is that the scope is validated through an objective process to assure value and quality in the product, service, or result delivered. This process also increases the probability of acceptance of the product, service, or result delivered.”

Note the word “objective.” Acceptance does not rest on feelings or relationships but on checking, item by item, against acceptance criteria agreed in advance. On a predictive project these criteria are usually recorded in the project scope statement and can be added to the WBS dictionary as needed, and they may also appear in the requirements documentation, the project charter and related documents; on an adaptive project they are usually found in user stories, backlog items or the definition of done. With a clear basis, the customer and the team do not talk past each other.

Verification and acceptance: two steps in sequence

In Monitor and Control Scope, the project team checks internally whether deliverables are correct; this is called verification. In Validate Scope, the customer or a stakeholder with acceptance authority decides whether to accept; this is called acceptance. The output of the first is verified deliverables and the output of the second is accepted deliverables, and the output of the first is exactly the input of the second. The order cannot be reversed. If you go for acceptance without verification, the customer may spot the defects immediately; if verification passes but there is no acceptance, the deliverable cannot yet be treated as accepted by the customer.

Figure 1 From verification to acceptance
Monitor and Control ScopeValidate Scope
What it doesVerifies whether deliverables are correctFormally accepts deliverables
Who judgesThe project team, against quality standardsThe customer or a stakeholder with acceptance authority
OutputVerified deliverablesAccepted deliverables
On failureRecord the reason; remedy or correct through change controlRecord why acceptance was not given and assess the impact; raise a change request if a change is needed

So for a question such as “the project team has verified the deliverables through Monitor and Control Scope; what does the project manager do next?”, the answer is not to write the final report, not to close the project, and not to hand the system straight over to operations. It is Validate Scope: ask the customer or another stakeholder with acceptance authority to formally accept against the acceptance criteria. When a vendor declares that “all work in the contract scope is done,” the declaration is only a starting point. The project team first checks and confirms the deliverables through Monitor and Control Scope. Once verified deliverables exist, the project manager convenes stakeholders with acceptance authority to carry out Validate Scope, rather than marking a milestone whose completion condition is acceptance as complete or treating the sponsor's word alone as the end of the matter.

When it happens: as deliverables are delivered, not only at the end

Validate Scope on a predictive project is not done once before closure after all the work is finished. In common exam practice, it is carried out periodically throughout the project as needed. When deliverables are delivered in phases and can be used independently, each batch is handed to the customer for acceptance as soon as it is completed and verified. A review at the end of a phase checks whether the expected outcomes or exit criteria have been met, and exit criteria can be tied to the acceptance criteria of the deliverables, so that the next phase begins only once they are met.

The benefit is finding problems early. If all acceptance is left to the end, any failure means the related deliverables must be reworked and overall delivery or closure may slip. So accept early and in batches. Before the project moves into closure, formal acceptance of the deliverables by the stakeholders with acceptance authority must be obtained, and the approval is recorded as the contract or the organization requires (with a signature where one is required); in the Manage project closure task, the ECO also requires obtaining stakeholder approval that the project is complete.

Worked examples

Example 1 After quality control passes, what comes next

Question 1Example

A project manager is implementing an inventory management system for a supermarket chain. Through Monitor and Control Scope, the project team has checked and confirmed that the system is correct, producing verified deliverables. What should the project manager do next?

Show answer and explanation

Correct answer: B

Through Monitor and Control Scope, the project team has checked and confirmed that the inventory management system is correct, producing verified deliverables. The question asks what the project manager does next.

The stem states that the project team checked and confirmed the system through Monitor and Control Scope, so verified deliverables have been produced; these are the input to Validate Scope. Before the system goes to the customer for use, the customer or another stakeholder with acceptance authority must formally accept it against the acceptance criteria, and a formal acceptance record is kept as the contract or the organization requires. The step after verification and before closure is Validate Scope. The answer is B.

Why the other options are wrong

  • A. The final report belongs to closure and makes sense only after the deliverables have been accepted.
  • C. The deliverables have not yet been formally accepted, so the project cannot move straight into closing the project or phase.
  • D. Handover to operations also comes after acceptance. Handing over before acceptance bypasses the customer's formal acceptance.

Key takeaway Passing a quality check is only verification; to hand over the deliverable, it still has to be accepted in Validate Scope.

Variation If the customer has already signed off acceptance, the next step is Close Project or Phase and handover. If testing finds defects, submit a change request for defect remedy; after approval and repair, the work is inspected and reverified through Monitor and Control Scope before it goes to Validate Scope.

Something wrong with this question?

Report an issue with this question

Example 2 The vendor declares scope complete and asks for approval

Question 2Example

A company outsources the redesign of its corporate website to a vendor and assigns a project manager to oversee it. After the vendor announces that all work within the contracted scope is complete, the project team checks and confirms the deliverables through Monitor and Control Scope. The contract states that the corresponding delivery milestone is complete only after formal acceptance. The vendor now asks for approval. How should the project manager respond?

Show answer and explanation

Correct answer: A

After the vendor reports completion, the project team checks and confirms the deliverables through Monitor and Control Scope; the contract states that the corresponding delivery milestone is complete only after formal acceptance. The vendor then asks for approval.

A vendor's announcement of completion is only a statement; it does not mean the deliverables have been accepted. The stem further states that the project team has checked and confirmed the deliverables through Monitor and Control Scope, producing verified deliverables. The project manager should next bring together stakeholders with acceptance authority to decide whether to accept them against the acceptance criteria, which is Validate Scope. The answer is A.

Why the other options are wrong

  • B. In this question the completion milestone is conditioned on acceptance. Updating the plan first assumes acceptance, and the plan drifts away from reality.
  • C. The vendor checking its own agreement cannot replace formal acceptance; the project manager should bring in stakeholders with acceptance authority to inspect the deliverables against the contract and the acceptance criteria and decide whether to accept them.
  • D. Relying on the sponsor's word without checking the deliverables against the acceptance criteria destroys the objectivity of acceptance and bypasses other stakeholders who have acceptance authority.

Key takeaway A vendor saying the work is done is only the starting point; approval comes from stakeholders validating scope against the acceptance criteria.

Variation If the deliverables were found to be inconsistent with the agreement before the vendor finished, the deviation would be dealt with first. If the check passes, obtain and record formal approval (and a signature where one is required).

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Passing a quality check is not acceptance. An internal check only shows the deliverables have been verified; before they are delivered for the customer's use, the customer or a stakeholder with acceptance authority must formally accept them.
  • Without formal acceptance, you cannot complete a closure or delivery milestone whose exit condition is acceptance (other milestones are judged by their own completion criteria), and you cannot hand the system straight over to operations.
  • If the sponsor merely says it is approved without the deliverables being checked against the acceptance criteria, acceptance loses its objectivity.
  • Validate Scope is not done only once at the very end. With phased delivery, each batch can be accepted once it is completed and verified.
  • Monitor and Control Scope is verification and Validate Scope is acceptance; reversing them is a classic wrong option.

Key takeaways

Key point

  • Validate Scope has two main objectives: checking the processes used to achieve quality standards, and formalizing acceptance of the deliverables.
  • Monitor and Control Scope verifies (the team checks internally whether deliverables are correct) and Validate Scope accepts (whether the customer accepts them). Verify first, accept second.
  • What goes into Validate Scope is verified deliverables, and what comes out is accepted deliverables.
  • Acceptance criteria are recorded in the project scope statement and can be added to the WBS dictionary and other documents as needed.
  • Validate Scope on a predictive project is carried out periodically as deliverables are delivered (common exam practice); before closure, formal acceptance must be obtained and the approval recorded (with a signature where required).

Lesson 2

Inputs and Tools of Validate Scope: What You Check Against and How

Lesson video

Lesson overview

The previous lesson covered where Validate Scope sits and why it exists. This lesson covers how it works: what acceptance relies on, which tools are commonly used, and what the project manager's first move is when the customer refuses to sign. The exam usually asks in two ways: directly which tool an activity belongs to among those of Validate Scope, or a scenario in which the customer and the team disagree on whether something meets the bar, asking for the next step. Learn the names of the inputs and tools exactly, and remember “check against the acceptance criteria first,” and you will earn those points. ECO: Process domain, Task 2 (Develop and manage project scope) and Task 10 (Manage project closure).

Inputs

The main input of Validate Scope is verified deliverables: completed deliverables that have been checked and confirmed for correctness through Monitor and Control Scope. The other inputs are the requirements documentation, the scope baseline, quality reports, work performance data and quality control measurements, plus enterprise environmental factors and organizational process assets.

Each input has its use. Verified deliverables are “what is being accepted.” The project scope statement and WBS dictionary in the scope baseline supply the acceptance criteria, which is “what to check against.” The requirements documentation describes the individual requirements and how they meet the project's business needs, providing a basis for checking the requirements. Quality reports and quality control measurements supply quality issues, measurement results and recommended corrective actions as data to support an objective acceptance against the acceptance criteria (they are not in themselves proof that the standard has been met; what shows that a deliverable has passed the Monitor and Control Scope check and been confirmed correct is the verified deliverables). “Accepted deliverables” is not among the inputs, since it is an output, and neither are change requests, which also appear on the output side.

Tools and techniques

The tools and techniques of Validate Scope are inspection, customer talks and tests, process analysis and review meetings, along with data gathering, data analysis and decision-making.

An inspection is the examination of a work product to determine if it conforms to documented standards. The results of inspections generally include measurements and may be conducted at any level. In Validate Scope it shows up as measuring, examining and confirming whether the work and deliverables meet the requirements and the product acceptance criteria, and it is often done jointly by the project team and the customer.

Customer talks and tests consist of the collaborative processes and activities involving direct interaction and feedback from customers during the development and testing phases of a project. These practices are integral to ensuring that the final product or service aligns with customer expectations and requirements. By engaging customers early and throughout the project life cycle, organizations can enhance transparency, build trust, and improve the overall quality of the deliverables. It is one of the tools PMBOK 8 lists for Validate Scope, alongside inspection and review meetings.

Process analysis identifies opportunities for process improvements and also examines problems, constraints, and non-value-added activities that occur during a process. It corresponds to the first objective of Validate Scope, checking the processes used to achieve quality standards, and not only the final product. A review meeting is a meeting held to review deliverables, in which the team and stakeholders discuss results against the standards and reach a conclusion on accepting or not accepting.

ToolIn one sentence
InspectionMeasure and examine deliverables against requirements and acceptance criteria
Customer talks and testsInteract directly with the customer during development and testing and take feedback at any time
Process analysisFind opportunities for process improvement; examine problems, constraints and non-value-added activities
Review meetingsMeetings held to review deliverables that reach a conclusion on acceptance

When the customer refuses to sign

Take a warehouse project in which, after delivery of handheld scanning terminals, the customer thinks scan success rate falls short of the contract requirement and will not sign for them, while the team thinks it has met the standard. Both sides are arguing the same question: do the deliverables actually meet the acceptance criteria? So the project manager's first step is to check against the acceptance criteria, going through the conditions that must be met before acceptance one by one and letting test data speak. That is “inspection” in Validate Scope.

Only after that check does the follow-up make sense. If the product really falls short, record the reason, do root cause analysis where needed, and rework or repair through change control. If it meets the standard, give the customer the inspection record and ask for a signature. The order cannot be reversed: reworking at the customer's request without finding out whether the product meets the standard may mean unnecessary rework and let scope grow at will; submitting a change request and asking for extra funds at the outset has no basis; and starting with root cause analysis comes before it is even confirmed that there is a problem.

Worked examples

Example 1 What is the main input to Validate Scope

Question 1Example

A software module has completed verification of its deliverables (Monitor and Control Scope), and the project manager is preparing to arrange customer acceptance and is gathering the inputs that Validate Scope needs. Which of the following is a main input to this process?

Show answer and explanation

Correct answer: C

A software module has been verified, and the project manager is preparing customer acceptance and gathering the inputs Validate Scope needs. The question asks which is a main input.

The main input to Validate Scope is verified deliverables: completed deliverables that have been checked and confirmed for correctness through Monitor and Control Scope. Other inputs include project documents such as requirements documentation, the scope baseline, quality reports and work performance data, and quality control measurements. In the stem, the module has just finished verification, and that verified result is the input to Validate Scope. A way to approach this kind of question is to follow the arrows: the outputs of Monitor and Control Scope are the inputs to Validate Scope, while the outputs of Validate Scope are accepted deliverables, change requests and document updates. The answer is C.

Why the other options are wrong

  • A. Accepted deliverables are an output of Validate Scope, a result that exists only after acceptance is complete.
  • B. Change requests arise, for example, when deliverables are not accepted. They are an output, not an input.
  • D. The lessons learned register is updated after Validate Scope, so it belongs on the output side.

Key takeaway Validate Scope takes in verified deliverables; accepted deliverables come out.

Variation The output of Monitor and Control Scope is verified deliverables. When acceptance fails and a change is needed, a change request is produced as required.

Something wrong with this question?

Report an issue with this question

Example 2 The customer refuses to sign while the team thinks it has met the standard

Question 2Example

A children's smart-watch development project reaches customer validation. The customer believes location accuracy and fall-alert sensitivity fall short of requirements, refuses to sign the acceptance report and demands rework; the team believes the product already meets the standard. What should the project manager do?

Show answer and explanation

Correct answer: B

A children's smart-watch project is at customer validation. The customer says location accuracy and fall-alert sensitivity are below requirements and will not sign the acceptance report; the team thinks the product meets the standard.

The disagreement is whether the deliverables actually meet the acceptance criteria. So first check, item by item, whether each acceptance criterion is met, and use measurement data to judge whether the product really falls short; only then decide the follow-up action. That is the “inspection” approach in Validate Scope. Inspection should rest on the acceptance criteria agreed in advance and on measured data, not on impressions, and without giving way just because the customer is unhappy, which keeps acceptance objective. The answer is B.

Why the other options are wrong

  • A. Reworking to the customer's demand without checking the acceptance criteria may be unnecessary rework and lets scope grow at will.
  • C. A change request and extra funding need a basis, which comes only after it is confirmed that the product really does not conform and needs rework. Submitting now is premature.
  • D. Root cause analysis is done after it is confirmed that the product really does not meet requirements. At this point it is not even clear whether it meets the standard.

Key takeaway When the customer refuses to sign, first inspect against the acceptance criteria, then decide whether to rework, analyze or change.

Variation If the check confirms that location accuracy really is below the standard, record the reason, rework through change control and reverify. If it meets the standard, show the customer the inspection record and ask for a signature.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The input is verified deliverables, and the output is accepted deliverables; change requests and lessons learned updates are also on the output side.
  • Acceptance criteria are in the scope baseline (the scope statement and WBS dictionary); they are not decided verbally by the customer on the spot.
  • When the customer will not sign, check against the acceptance criteria first, not rework first, not ask for money first and not do root cause analysis first.
  • “Customer talks and tests” means interacting continuously with the customer during development and testing; a review meeting is a meeting held to review deliverables. Do not confuse them.

Key takeaways

Key point

  • Inputs: verified deliverables; requirements documentation, scope baseline, quality reports, work performance data and quality control measurements; and enterprise environmental factors and organizational process assets.
  • Tools: inspection, customer talks and tests, process analysis and review meetings, plus data gathering, data analysis and decision-making.
  • Customer talks and tests are collaborative activities with the customer during development and testing that gather feedback, improve transparency and build trust.
  • When the customer refuses to sign, check item by item against the acceptance criteria first, then decide whether to rework, analyze causes or go through change.

Lesson 3

Outputs of Validate Scope: Accepted Deliverables, Sign-Off and Handling Failed Acceptance

Lesson video

Lesson overview

This lesson covers the results of Validate Scope: what you get when acceptance passes, what to do when it does not, and how acceptance connects to closure. It is the richest lesson in scenarios on the exam: the customer refuses to sign, the customer uses acceptance to raise new requests, delivery happens with no written confirmation. The answer to every scenario falls on the same main line: acceptance needs a formal approval document (a signature where one is required); if it fails, record the reason first and then go through change control; closure comes after acceptance. ECO: Process domain, Task 10 (Manage project closure), Task 2 (Develop and manage project scope), and Business Environment domain, Task 3 (Manage and control changes).

Acceptance passes: accepted deliverables

Accepted deliverables are the products, services, and capabilities that are created through a project and are validated by an appointed individual or a group of individuals against established criteria. When the relevant acceptance criteria are met, these deliverables are approved and accepted. The stakeholders with authority to approve deliverables should be involved early in the process and give feedback on the quality of deliverables, so that the team can assess quality and performance and recommend any necessary changes. Acceptance should be formally confirmed in line with the agreement and governance arrangements, leaving traceable evidence that the deliverables have been formally accepted. A signed approval document is a common form, but not the only one.

The signature has to come from someone with acceptance authority, which may be the customer, the sponsor or another authorized stakeholder, depending on the agreement and governance arrangements. The result of acceptance, pass or fail, is recorded and communicated to the relevant stakeholders. The reason is practical: without a written formal approval (commonly a signature), there is no proof of acceptance. Say a repair-request app is finished, but the customer's manager is on a business trip, and the project manager hands the package to the customer's liaison specialist with no written confirmation. On the payment date the customer says it never received or accepted the program, and the project manager has no evidence. Having a customer representative with acceptance authority sign to confirm in advance would have avoided it.

Acceptance fails

When a deliverable fails acceptance, first find out and record, against the acceptance criteria, why it was not accepted. Common exam practice is first to record the reason and assess the impact. If a change is needed, raise a change request under the change management plan, have the authorized person review and approve it, and only then implement the defect remedy or correction (PMBOK 8 lists change requests among the possible outputs of Validate Scope, which does not mean every rejection necessarily produces a change request). It is handled in whatever way the project's tailored change approach provides: a predictive project usually submits a formal change request, and an adaptive project usually records the item in the backlog and re-ranks it. After the remedy is done, the work returns to Monitor and Control Scope, where the modified deliverable is inspected and reverified, and then submitted for acceptance again.

When the question asks what to do “first,” the answer is the first step: find out why the customer will not accept and record it. Do not first draft a change request (with the reason unknown, you cannot say what is to be changed), do not directly update the project management plan (the change has not been approved), and do not have the team just start fixing it (defect repair is also a change). If the customer rejects the work because it deviates from an agreed style guide, the handling is the same: record the nonconformance and remedy it through change control. You cannot ask the customer to “sign first and discuss it later,” and you cannot update the scope statement first to fit.

Figure 1 Flow when acceptance passes and when it fails

Validate Scope also updates the quality reports, work performance information and requirements documentation, and produces lessons learned updates (relevant lessons can be recorded in the lessons learned register).

New requests raised at acceptance

In real projects, the customer often uses the acceptance step to raise new requests, even making them a condition of signing. The principle is to handle the two matters separately without waiting for one to finish before starting the other: request formal acceptance of the work that is complete and meets the criteria, while submitting the new request as a scope change. For example, on a municipal project to replace streetlights within an 8-kilometer radius, everything is complete and passes, but the customer's representative demands another kilometer before signing the closure report. The project manager obtains formal acceptance of the completed work and submits a change request for the extra kilometer, to be assessed through change control. Do not postpone acceptance to ask for more funds, do not ask an outside department to approve the expansion directly, and do not refuse to discuss it because it came too late.

Acceptance and closure

For a project that completes normally and delivers a result, formal acceptance is usually a necessary step before closing the project or phase. A project terminated early must still be closed as required, but without making acceptance of all deliverables a precondition. In the Manage project closure task, the ECO requires obtaining stakeholder approval that the project is complete and confirming that readiness for transition has been established. So when the team announces completion and the open issues are closed, the project manager's FIRST step is to ask the customer to accept against the acceptance criteria; final handover and closure normally follow acceptance. Lessons learned should be captured throughout the project, and benefits are measured on an ongoing basis in line with the benefits management plan and may continue after the project ends.

Once all deliverables have been formally accepted, closing out scope also includes collecting and reviewing the records of the project or phase and archiving project information for future use by the organization. The scope statement and requirements documentation are project documents and should be stored according to the organization's prescribed process. Archiving must not be skipped when a project is cancelled midway or time is tight.

Worked examples

Example 1 New scope requested at acceptance

Question 1Example

A signage replacement project for a coffee-shop chain covers replacing the signs of 10 stores in the city center. When all of them are done, the customer says it will not sign the project closure report unless an 11th store is added, because it fits the customer's new store-opening plan. What should the project manager do?

Show answer and explanation

Correct answer: A

All 10 store signs have been replaced. At acceptance the customer demands an 11th store and otherwise will not sign the project closure report.

The original scope is complete, so the project manager should ask the customer to formally accept that part against the agreed acceptance criteria; if the customer refuses to sign, record and handle the reason for the refusal (using contract dispute or escalation mechanisms if necessary). The 11th store is outside the scope baseline and is a scope change: record it as a change request, to be assessed and decided by the approver the project designates (the change control board where applicable). It need not wait until acceptance is finished. The two matters are handled separately and not tied to each other. The answer is A.

Why the other options are wrong

  • B. A scope change first has to go through change control; it is not a matter of going straight to the sponsor for money. Holding off acceptance would also delay accepting the completed work.
  • C. A change must be approved through this project's change control process. The project manager cannot let a department of the customer approve an expansion of scope directly; skipping the process leaves the baseline uncontrolled.
  • D. A request cannot simply be turned into a new project because it came late. A change request is the proper route, decided by the approver the project designates (the change control board where applicable).

Key takeaway When new requests arise at acceptance, request acceptance of the completed work while sending the new request through change control; handle the two matters separately.

Variation If the customer asked instead for a fix to a defect where completed work deviates from the acceptance criteria, that is not added scope; record the reason and remedy the defect through change control.

Something wrong with this question?

Report an issue with this question

Example 2 Delivery with no written confirmation, and the customer denies accepting

Question 2Example

A property management company's repair-request app has been developed and the project manager is ready to deliver it. Hearing that the customer's manager is on a business trip, the project manager hands the program package to the customer's liaison specialist and asks for no written confirmation. On the agreed payment date the customer does not pay, saying it never received the program and has not accepted it. What should the project manager have done beforehand to avoid this problem?

Show answer and explanation

Correct answer: D

A repair-request app is finished. While the customer's manager is away, the project manager hands the package to a liaison specialist with no written confirmation. On the payment date, the customer says it never received or accepted the program.

Deliverables should be accepted by a customer representative with acceptance authority, against the acceptance criteria, confirmed in the formal way the contract or governance arrangements call for; among the ways listed here, a signature is the best protection against dispute. Had a customer representative with acceptance authority signed to confirm acceptance in advance, the project manager would hold proof of the customer's acceptance, and the customer could not deny it later. Note also that the signer must be someone with acceptance authority: a liaison specialist receiving the package is not acceptance, and only the signature of a customer representative with acceptance authority or that person's formally authorized delegate counts. The answer is D.

Why the other options are wrong

  • A. Whether the payment date is reasonable has nothing to do with the customer denying receipt. The problem is the lack of proof of acceptance.
  • B. The stem shows no sign of scope excess or gap, so tighter monitoring of product scope does not address an acceptance dispute.
  • C. The problem is that the project manager did not obtain a signature, not an authority issue that needs escalation to the sponsor.

Key takeaway Acceptance needs formal confirmation: at delivery, a customer representative with acceptance authority inspects against the acceptance criteria and confirms in the agreed formal way (here, a signature). A liaison specialist receiving the package is no substitute.

Variation If the customer refuses to accept, record the reasons and deal with the defects or the dispute; if the approved scope, a baseline or another controlled item needs to change, submit a change request as required. If the customer merely agreed verbally, still obtain the agreed formal confirmation afterward.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Acceptance should be formally confirmed by people with authority under the scope management plan, the agreement and the governance arrangements, with traceable evidence kept; a signed document is a common form but not the only one. Handing the package to a liaison person or a verbal agreement is normally not formal acceptance.
  • Failed acceptance: first record (find out) the reason, then handle it in the project's tailored way of handling change. When a change is needed, a predictive project submits a change request through change control, and an adaptive project updates and re-ranks the backlog. Do not start fixing before that, and do not ask the customer to sign first and discuss afterward.
  • New requests at acceptance must not be bundled with acceptance of work already done: request acceptance of what meets the criteria while placing the additions in a separate change request, and handle the two matters independently.
  • On a predictive project, change requests are assessed under the prescribed procedure and approved, deferred or rejected by the designated authority, and implemented only after approval; on an adaptive project, impact analysis and prioritization normally happen through the backlog. An unauthorized outside department, or a single department on the customer's side, cannot directly expand scope.
  • Formal acceptance should normally be obtained before final handover and closing the project. The final report and handover preparations can be drafted earlier, but the project cannot be declared closed before acceptance is complete; the exact order follows governance and tailoring.

Key takeaways

Key point

  • Accepted deliverables: products, services and capabilities confirmed by a designated person or team against established criteria and approved because they meet the acceptance criteria; acceptance is formally confirmed per the agreement and governance arrangements and recorded (with a signature where required).
  • Failed acceptance: record the reason and assess the impact first. If a change is needed, raise a change request under the change management plan, obtain authorized approval, implement the remedy or correction, then reverify and seek acceptance again.
  • New requests at acceptance: request acceptance of what is complete while putting the new request in a change request. Handle the two matters separately.
  • Validate Scope updates quality reports, work performance information and requirements documentation, and produces lessons learned updates (relevant lessons can be recorded in the lessons learned register).
  • Accept first, then hand over and close. Closure requires stakeholder approval that the project is complete, and project information is archived.

Lesson 4

Acceptance in Adaptive Environments: Definition of Done, Definition of Ready and Acceptance Criteria

Lesson video

Lesson overview

Acceptance on a predictive project relies on the acceptance criteria in the scope baseline and takes place after batches of deliverables are complete. The rhythm on an adaptive project is different: with incremental methods such as Scrum, every iteration produces a usable increment, acceptance happens continuously with the iterations, and the basis for judging “is it done?” is the definition of done and each user story's own acceptance criteria. This is the lesson of the chapter most often tested, almost always in scenario questions. It comes down to three concepts, the definition of done (DoD), the definition of ready (DoR) and acceptance criteria, and when each comes into play. ECO: Process domain, Task 2 (Develop and manage project scope) and Task 7 (Plan and optimize quality of products/deliverables).

Definition of done (DoD)

The definition of done (DoD) is a checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use. In projects using an adaptive approach, a DoD is a shared understanding of the specific criteria that should be met before a piece of work (e.g., a user story, feature, or increment) is considered complete and ready for release to the next stage or the customer. In common exam practice, typical items are: code reviewed, tests passed, documentation updated, defects resolved.

The DoD is a baseline shared by the whole team and applies to every increment, so in common exam practice it carries the non-functional requirements. For example, an online consultation platform must meet concurrent-user capacity and patient privacy requirements, and the product owner worries that they will not be carried out. Write these requirements as checkable items in the DoD, so every increment must meet them to count as done, and the requirements are assured. Handing them to the operations department, bringing in one expert to review, or leaving them for the next planning meeting does not build the requirements into the workflow.

Acceptance criteria and user stories

A user story is a brief, textual description of an outcome from a specific stakeholder perspective, and is a promise for a conversation to clarify details. A typical user story should describe the user or stakeholder's role, who benefits from the feature (role), what the stakeholder needs to accomplish (goal), and the benefit to the stakeholder (motivation). The acceptance criteria in a user story should focus on the specific functionalities and end-user expectations that should be fulfilled. Each story carries its own acceptance criteria, which say what the feature must look like to be right.

When should acceptance criteria be set? Before development (common exam practice: at the latest at iteration planning), clarified together with the backlog item. Setting them after the work is done, at the demo or even at the retrospective, is too late. If the team has many questions about stories and the stories end up not completed, the most likely cause is that acceptance criteria were not made clear when the stories were discussed at iteration planning. If the customer tries the feature and says “it is not what we expected” while the team thinks it is fine, most likely the story did not state its acceptance criteria and each side relied on its own understanding. If stakeholders keep complaining at iteration demos that features were not delivered as requested, invite them into backlog refinement so that acceptance criteria are confirmed together before development starts.

Definition of ready (DoR)

The definition of ready (DoR) is a checklist of the conditions that must be met before a task or feature is started; PMBOK 8 also calls it a “full kit.” It helps the team have a clear, shared understanding of a task or feature before starting, which reduces rework. In common exam practice, typical items are: the description is clear and explicit; feasibility study and risk assessment are done; the needed resources are arranged; requirements, goals and acceptance criteria are clear; and the relevant stakeholders agree about the task or feature. As a common exam practice, the higher an item ranks in the backlog, the clearer and more specific it should be and the more it should meet the definition of ready, which in turn supports a more accurate estimate.

Figure 1 Definition of ready before work starts, definition of done when it ends
Definition of ready (DoR)Definition of done (DoD)
What it governsWhether a piece of work can startWhether a piece of work counts as done
Typical contentClearly described, resources arranged, acceptance criteria definedCode reviewed, tests passed, documentation updated, defects resolved
Timing (common exam practice)Around iteration planningBefore the iteration review

How acceptance continues

An adaptive project takes meeting the definition of done as the sign that work is finished, and drives acceptance of deliverables through continuing review and feedback (being done is not the same as formal acceptance). Velocity is a measure of a team's productivity rate at which the deliverables are produced, validated and accepted within a predefined interval. Whether stakeholders accept and are satisfied can be measured through interviews, observation and end-user feedback, and the levels of complaints and returns may also be used to indicate satisfaction. At the close of an iteration or release, confirm that prioritized backlog items are finished and that all acceptance criteria are met, and ensure that all deliverables have been reviewed and accepted by stakeholders.

A hybrid project takes care of both sides: the parts managed predictively can be formally accepted against the scope baseline, and the parts managed adaptively are reviewed and accepted continuously through the iterations; the exact arrangement depends on how the project is tailored. Predictive acceptance rests on the acceptance criteria in the scope baseline; adaptive acceptance rests on the definition of done and the stories' acceptance criteria, with continuing feedback from each iteration and scope refined step by step.

Worked examples

Example 1 How to carry out non-functional requirements

Question 1Example

A team is developing an online consultation platform, and the system must meet non-functional requirements such as concurrent-user capacity and patient privacy protection. The product owner worries that these requirements will not be carried out and asks the project manager how to guarantee them. What should the project manager do?

Show answer and explanation

Correct answer: C

On an adaptive project, an online consultation platform must meet non-functional requirements such as concurrent-user capacity and patient privacy protection. The product owner worries they will not be carried out and asks how to guarantee them.

The definition of done (DoD) is a checklist of all criteria a deliverable must meet to be considered ready for customer use, and every increment must satisfy it to count as done. If non-functional requirements are written as checkable items in the DoD, they reach every iteration's delivery and gain force and assurance. The DoD suits non-functional requirements because it applies uniformly to every user story, feature or increment and does not depend on any individual's review. The answer is C.

Why the other options are wrong

  • A. Leaving it to the operations department splits responsibility and delays feedback, so it cannot ensure every increment meets the requirement.
  • B. One expert reviewing acceptance criteria can hardly cover every increment and does not build the requirement into the team's workflow.
  • D. Leaving it for the next iteration planning meeting merely discusses it; there is no force behind it and the product owner's worry remains.

Key takeaway Non-functional requirements reach every increment through the definition of done.

Variation If the question asked which checklist sets the preconditions for starting a piece of work, the answer would be the definition of ready; if it asked about a story's specific functional expectations, the answer would be the user story's acceptance criteria.

Something wrong with this question?

Report an issue with this question

Example 2 Many questions about the user stories, and they were not completed

Question 2Example

The software department of a manufacturer is moving from waterfall to agile, and its first agile project is an internal expense-reimbursement system. During the iteration, the developers have many questions about the user stories to be built, and those stories ultimately do not get completed successfully. What is the most likely cause?

Show answer and explanation

Correct answer: B

A department new to agile builds an internal expense-reimbursement system. During the iteration the developers have many questions about the user stories, and those stories do not get completed successfully. The question asks for the most likely cause.

The developers have many questions because they lack a shared understanding of what “done right” looks like. Acceptance criteria should be clarified when stories are discussed at iteration planning, and at the latest before development begins. If they were not clarified at that time, the developers have no basis for judging, and stories easily fail. Working backward from the symptom of “many questions” points to criteria that were not made clear before development; in common exam practice, the most likely cause is that the acceptance criteria were not clarified at iteration planning. The answer is B.

Why the other options are wrong

  • A. The customer side supplying acceptance criteria is normal practice. It helps clarify expectations and would not leave developers with questions.
  • C. Adaptive projects do not require a detailed requirements specification to be finished up front, so not finishing it is not the main cause of failed stories.
  • D. Writing acceptance test cases in advance is a good way to make the acceptance criteria clear first; it helps people understand the story and is not a cause of failure.

Key takeaway Before a user story enters an iteration, clarify its acceptance criteria along with the story.

Variation If the customer tries the feature and says it is not what was expected while the team thinks it is fine, the most likely cause is likewise that the story never stated its acceptance criteria.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Acceptance criteria must be clear and reviewed before development, and that is exactly what the definition of ready checks (the DoR checklist only confirms that “acceptance criteria are clear”).
  • PMBOK 8: the DoD is a checklist of all criteria that must be met. Common exam practice: general testing, quality and compliance requirements that every increment shares go into the DoD, while the acceptance conditions of a specific feature go in the story's own acceptance criteria.
  • The definition of done is a baseline shared by the whole team. It is not one expert's or one department's review.
  • Acceptance criteria are not added after the demo, and they are not an excuse for the customer “deliberately setting obstacles”; a gap in expectations is usually a sign that the standard was not made clear.
  • Adaptive does not mean no acceptance: acceptance continues with the iterations, based on the DoD and the stories' acceptance criteria.

Validate Scope under predictive versus adaptive approaches

  • Predictive: based on the acceptance criteria in the scope baseline, the stakeholders with authority formally accept the deliverables of a phase or batch, and the result of approval is recorded as the organization requires.
  • Adaptive: based on the definition of done and the stories' acceptance criteria, feedback is gathered continuously with the iterations, and scope is refined step by step.

Key takeaways

Key point

  • Definition of done (DoD): a checklist of all criteria that must be met for something to be considered ready for customer use; in common exam practice, it is used to carry non-functional requirements.
  • A user story carries its own acceptance criteria, clarified with the item at iteration planning and set before development at the latest.
  • Definition of ready (DoR): the conditions that must be met before work starts, also called a “full kit”; the DoD governs whether work is done and the DoR governs whether it can start.
  • A gap in expectations, or stories that do not get done, is usually because the acceptance criteria were not made clear in advance.
  • Adaptive acceptance continues with the iterations: at close of an iteration, confirm that the acceptance criteria are all met and the deliverables have been reviewed and accepted by stakeholders.

This chapter has 40 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.