Critical Chain Method

PMP · Schedule · 2 lessons · about 22 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

A schedule network that has not been through resource optimization may contain resource conflicts, and resource leveling can change the critical path. PMBOK 8 first performs the critical path method's forward and backward passes without regard to resource limitations; subsequent resource loading and leveling can change the critical path, and in critical chain project management that resource-loaded and resource-leveled critical path is called the critical chain. In addition, the duration estimate of each activity often hides its own “insurance time”. The critical chain method addresses these problems: it builds resource constraints into the critical path, takes the scattered safety margin out of the activities and pools it into buffers placed at key positions on the path, and during execution uses the buffer protection index to monitor whether the finish date is safe. This chapter is short and the exam does not test it directly very often. The key points are how it differs from the critical path method, where the two kinds of buffer go, and how the buffer protection index differs from the schedule performance index.

By the end of this chapter you should be able to do the following. State the definition of the critical chain method and how the critical chain relates to the critical path. Say where the project buffer and the feeding buffer each go (the latter is a common exam term). Explain that buffers replace, and are not added to, task-level safety time. Say what the buffer protection index compares and how it differs from the schedule performance index. Compare the critical chain method with the critical path method.

Lessons in this chapter

Chapter map

KeywordPoints toLesson
Resource constraints; resource-loaded and resource-leveled critical pathCritical chainLesson 1
End of the critical chainProject buffer, protects the finish dateLesson 1
Where a non-critical chain merges into the critical chainFeeding bufferLesson 1
Percentage of buffer remaining vs. percentage of critical chain remainingBuffer protection indexLesson 2
Adding people, overtimeCrashing, not the critical chain methodLesson 2

Study tips and practice

  • Hold on to three words: resource constraints, buffer, safety margin.
  • A buffer replaces safety time; it is not an extra on top of it.
  • Make a comparison table of the BPI and the SPI, and memorize the use and the comparison object of each.
  • The critical chain method is neither schedule compression nor resource smoothing; be able to rule it out when it appears among the options.

Lesson 1

The Critical Chain Method and Buffers

Lesson video

Lesson overview

A critical path worked out from logical relationships and durations alone may change once resource constraints are considered, because resource leveling can change the critical path. (PMBOK 8 calls for a resource-loaded and resource-leveled critical path in both the critical path method and critical chain project management.) In addition, each activity's estimate often hides its own “insurance time”. The critical chain method addresses exactly these problems: it puts resource constraints into the determination of the critical path, takes the scattered insurance time out, pools it into buffers, and places them at key positions on the schedule path. This lesson covers the definition of the critical chain method, how the critical chain relates to the critical path, and where the project buffer and the feeding buffer go and how they replace task-level insurance time. The critical chain method is not tested heavily, but the concepts are concentrated, and three words earn you the points: resource constraints, buffer, safety margin. It covers ECO: Process domain, Task 8 (Plan and manage schedule).

The definition of the critical chain method

The critical chain method is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. It builds on the critical path method and goes further, considering resource allocation, how resource conflicts are handled, and the effect of uncertainty in activity durations on the critical path.

PMBOK 8 states plainly that, when identifying the longest path or chain of tasks in a project schedule, “the resource-loaded and resource-leveled critical path” and “the critical chain” are synonymous. In other words, the resource-constrained critical path is the critical chain. For example, design and commissioning can logically start at the same time, but both need the same process expert, so they can only be done one after the other. This “resource-driven sequence” has to be counted into the longest chain, and what you get is the critical chain, which may not be the same path as the one calculated from logic alone.

In common exam practice, the critical chain method does two things on top of the critical path method: first, the duration of each activity no longer contains a safety margin, and second, the safety margin is pooled into a buffer placed at particular positions on the path. PMBOK 8 itself summarizes it more briefly: the two methods have nearly identical scheduling logic, and the only meaningful difference in the logic is that the critical chain method also calculates the percentage of the project buffer remaining and compares it with the percentage of the critical chain remaining (see the next lesson). The two statements come from different angles and do not contradict each other. Everything else works as in the critical path method: you still consider durations, logical relationships and whether resources can be in place, activity by activity.

Buffers: safety margin pooled together

In traditional estimating, each activity tends to carry a little insurance time of its own. The critical chain method takes this insurance time out of the activities, uses statistical methods to work out how long the buffer should be, and places it as pooled safety margin at selected positions on the path, to absorb the shocks of tight resources and various uncertainties. PMBOK 8 describes critical chain project management (CCPM) as a set of techniques used to promote fast execution and high due-date performance by aggregating task-level (or sprint-level) variability to a project buffer, and then allocating the project buffer only when and where needed in order to protect the project due date. The buffer here is in lieu of task-level buffers, not in addition to them.

Why pool it? When each activity carries its own insurance time, its owner will unconsciously use all of it, and time saved on an earlier activity does not get passed on to later ones; by the time an activity actually runs into trouble, its insurance has long since been spent. This corresponds to what estimating discussions call Parkinson's law and student syndrome. If you take the insurance back and pool it, people work to the tight time that contains no insurance, and the buffer is drawn on only where problems arise.

Buffers have two kinds of positions (“feeding buffer” and this division into two kinds of positions are common exam practice for CCPM):

Figure 1 The critical chain method: critical chain, project buffer and feeding buffers
  • Project buffer: placed at the end of the critical chain, it protects the project finish date.
  • Feeding buffer: placed where a non-critical chain merges into the critical chain, it lets delays on the non-critical chain be absorbed first, so they do not hit the critical chain directly.

Worked example: pooling scattered insurance time

The critical chain has 4 sequential activities, each with 5 days of pure working time. The traditional approach adds 2 days of insurance to each activity, so each is estimated at 7 days.

Step 1: The traditional estimate. 4 × 7 = 28 days, of which 8 days are insurance scattered across the activities.

Step 2: The critical chain approach. Schedule each activity at 5 days, with no safety margin, for 20 days in all. Then place a project buffer at the end of the critical chain. The length of the buffer is determined by statistical methods (one common approach is the square root of the sum of the squares of the activities' insurance times, that is, √(2² × 4) = 4 days; this is a supplementary note and the exam does not require you to calculate it). Take 4 days in this example, for a planned total of 24 days.

Step 3: Compare. 24 days is tighter than 28 days. It is unlikely that all four activities would use up their insurance, so the pooled buffer can be shorter than the sum of the separate insurance times (8 days). The price is that the 4-day buffer is shared by the whole project, and whichever activity slips first starts consuming the buffer first.

Step 4: The feeding buffer. If there is also a non-critical chain of 3 activities that merges before the third critical activity starts, place a feeding buffer (for example 3 days) at the merge point, and delays on this chain consume it first.

Worked examples

Example 1 Concept: what is the longest path that is resource-loaded and resource-leveled called?

Question 1Example

On a factory production-line relocation project, the design and commissioning activities can logically start at the same time, but both need the same process expert. After the team re-sequences the schedule to account for the resource conflict, the longest path in the schedule changes. In the critical chain method, what is this longest path, which is resource-loaded and resource-leveled, called?

Show answer and explanation

Correct answer: C

The schedule is analyzed with the critical chain method. Design and commissioning can start together but share one process expert. After re-sequencing, the longest path has changed. The question asks what this path is called.

PMBOK 8 explains that the critical chain method uses nearly identical scheduling logic to the critical path method; both are based on critical path analysis and call for a resource-loaded and resource-leveled critical path, and critical chain project management additionally manages uncertainty by aggregating it into buffers. The longest path that is resource-loaded and resource-leveled is synonymous with the resource-constrained critical path and with the critical chain. The stem describes exactly the longest path obtained after the resource conflict is taken into account. A memory aid: when you see “resource conflict” or “resource constraint” together with “longest path”, think critical chain; when you see “buffer”, think project buffer or feeding buffer, which are buffers, not paths. The answer is C.

Why the other options are wrong

  • A. The project buffer is a buffer placed at the end of the critical chain to protect the finish date. It is not a path.
  • B. The feeding buffer is a buffer placed where a non-critical chain joins the critical chain. It is not a path either.
  • D. The longest path based only on logic and durations, without resource constraints, is just the preliminary result before resource loading and leveling. What the question asks you to identify is the longest path after the resource conflict has been taken into account and the resources leveled, which corresponds to the critical chain.

Key takeaway The resource-constrained critical path is the critical chain.

Variation If asked what is placed at the end of the critical chain to protect the finish date, the answer is the project buffer; the buffer placed where a non-critical chain joins is the feeding buffer.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: what do you do with the insurance time scattered through the activities?

Question 2Example

A logistics-system upgrade project has moved from the critical path method to the critical chain method for its schedule. The project manager finds that every critical-chain activity estimate contains its own safety time, yet the plan has no project buffer to deal with uncertainty. What should the project manager do?

Show answer and explanation

Correct answer: D

The project has moved from the critical path method to the critical chain method for its schedule. Every critical-chain activity estimate contains its own safety time, but the plan has no project buffer.

The critical chain method calls for activity durations that contain no safety margin; the margin is taken out and pooled into buffers that protect the finish date, with a project buffer at the end of the critical chain. (A feeding buffer, placed where a non-critical chain joins the critical chain, is a common exam term in CCPM.) The buffer replaces task-level safety time; it is not added on top of it. PMBOK 8 stresses that the critical chain buffer is in lieu of task-level or sprint-level buffers, and not in addition to them, which is why the answer is D and not A. The answer is D.

Why the other options are wrong

  • A. The buffer replaces task-level safety time; it is not an extra layer on top. Doing both counts the safety time twice and stretches the plan.
  • B. With no buffer, there is no protection against resource limits and uncertainty, and any slip hits the finish date directly.
  • C. A small buffer after every activity is still scattered safety time, usable only by each owner. That is the opposite of a pooled buffer.

Key takeaway Safety margin is taken out of the activities and pooled into a buffer; the buffer replaces task-level safety time rather than adding to it.

Variation If 4 sequential activities were originally estimated at 7 days each (each including 2 days of safety time), take the safety out and schedule each at 5 days, 20 days in all; then add a 4-day project buffer according to the organization's buffer rule (an example only, not a fixed ratio), for a total of 24 days, tighter than the original 28.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • PMBOK 8: the resource-loaded and resource-leveled critical path is the critical chain; the two are synonymous. Common exam practice: when a question contrasts a critical path “scheduled only from logical relationships, with resources not yet considered” with the critical chain, answer “the critical chain considers resource constraints”; this treats the path before resource optimization as the point of comparison, and does not mean that the critical path method itself cannot consider resources.
  • A buffer is not added after every activity; it is placed in particular positions as a pool, and it replaces each activity's own insurance time rather than being added on top.
  • The project buffer protects the finish date, and the feeding buffer keeps the critical chain from being dragged down by non-critical chains. Do not mix up the positions.
  • The critical chain method is not schedule compression and not resource smoothing; adding people and overtime is crashing.

Key takeaways

Key point

  • The resource-loaded and resource-leveled critical path is the critical chain; critical chain project management adds pooled buffers and the buffer protection index (BPI; the next lesson covers what it compares and how to use it).
  • Activity durations contain no safety margin; the safety margin is pooled into buffers placed at particular positions on the schedule path.
  • The project buffer is at the end of the critical chain and protects the finish date; the feeding buffer is where a non-critical chain merges into the critical chain.
  • Buffers replace task-level insurance time; they are not added on top of it.

Lesson 2

Buffer Management, and Comparing the Critical Chain Method with the Critical Path Method

Lesson video

Lesson overview

Setting the buffers is only the first half. Buffer management answers how, during execution, you know whether the buffer is enough and whether the finish date is safe. For this PMBOK 8 provides a signal called the buffer protection index (BPI), and takes care to state that its use differs from that of the schedule performance index (SPI) in earned value management. This lesson covers buffer management and the BPI, then compares the critical chain method with the critical path method item by item, and finally clears up several concepts that are often confused with the critical chain method. It covers ECO: Process domain, Task 8 (Plan and manage schedule), specifically executing the schedule management plan and analyzing schedule variances.

Buffer management and the buffer protection index

Buffer management is the other half of critical chain project management. During execution, in addition to tracking the activities on the critical chain, you calculate the percentage of the project buffer remaining and compare it with the percentage of the critical chain remaining, which gives all project participants a “thumb on the pulse” signal of project schedule performance. PMBOK 8 calls this signal the buffer protection index (BPI). A further benefit is that it can be used to prioritize day-to-day tasks according to which ones will help protect the due dates of the projects most at risk of missing them, and this applies at the portfolio level as well.

Buffer protection index (BPI)Schedule performance index (SPI)
Comes fromCritical chain project managementEarned value management
What it comparesThe percentage of project buffer remaining with the percentage of critical chain remainingEarned value (EV) with planned value (PV)
What it is designed forProtecting the project due dateGauging how far the project may be from the schedule baseline

Worked example: reading the buffer signal

A project has a 60-day critical chain and a 10-day project buffer.

Step 1: Mid-project check. 30 days of work on the critical chain are finished, and the remaining 30 days are 50%. The buffer has used 3 days and has 7 days left, which is 70%.

Step 2: Compare. The buffer remaining (70%) is higher than the critical chain remaining (50%): the buffer is being consumed more slowly than the work is progressing, the finish date is protected, and you can leave things alone.

Step 3: Some time later. The critical chain has 30% remaining, but the buffer has only 20% left: the buffer is being consumed faster than the work is progressing. Be alert, start looking into the cause of the slippage, and take action if necessary.

Note. PMBOK 8 specifies only that the two percentages are compared; it gives no uniform formula or threshold. The “higher than / lower than” reading above is just an aid to understanding. Concentrate on what the BPI compares and what it is for; when a question gives data, you should still be able to calculate the two remaining percentages and compare them.

The difference between the BPI and the SPI is a test point: both are schedule signals, but the SPI looks at how far you are from the baseline (the ratio of EV to PV), while the BPI looks at whether the buffer can protect the finish date. If the question asks for “the indicator designed specifically to protect the finish date”, choose the BPI; if it asks for the “schedule performance index”, only then is it the SPI.

Comparing the critical chain method with the critical path method

Critical path methodCritical chain method
Longest pathThe longest path from logical relationships and durations (common exam practice: before resource optimization)The resource-loaded and resource-leveled critical path, that is, the critical chain
Activity durations (common exam practice)Estimates may include each activity's own safety timeNo safety margin
Handling uncertaintyThrough reserves and floatPooled into buffers: the project buffer (PMBOK 8) and the feeding buffer (a common exam term)
Signals during executionTotal float, SPIAlso has the buffer protection index

PMBOK 8 notes that the two methods use nearly identical scheduling logic, are both based on critical path analysis, and both call for a “resource-loaded and resource-leveled critical path”; the only meaningful difference in logic is that the critical chain method also calculates the percentage of the project buffer remaining and compares it with the percentage of the critical chain remaining.

The relationship between the critical chain method and resource optimization should also be kept clear. As defined, the critical path method calculates early and late dates from logic and durations alone, without regard to resource limitations; the resource-leveled result is the resource-loaded and resource-leveled critical path. In PMBOK 8 both methods call for a resource-loaded and resource-leveled critical path. In common exam practice, first working out the critical path from logic and only afterward resolving resource conflicts points to resource optimization, while building resource constraints into the determination of the “longest chain” from the start points to the critical chain method; the real difference in PMBOK 8 is still the comparison of the buffer percentages.

Concepts that are often confused

When a sponsor says “use the critical chain method to get the schedule back on track”, and the concrete action is to add people and approve overtime, those measures are actually crashing, which is schedule compression. The core of the critical chain method is resource constraints and buffers; it does not shorten the duration by adding resources. Nor is it resource smoothing: smoothing uses float to even out resource demand and has nothing to do with buffers.

Worked examples

Example 1 Concept: what does the BPI compare?

Question 1Example

A data-migration project uses critical chain project management. The project manager adds the buffer protection index (BPI) to the weekly report and explains to the sponsor what it means. Which two quantities does the BPI compare?

Show answer and explanation

Correct answer: A

A project uses critical chain project management, and the weekly report now includes the buffer protection index (BPI). The question asks which two quantities it compares.

Buffer management compares the percentage of project buffer remaining with the percentage of critical chain remaining, and this real-time signal is the buffer protection index (BPI). Its purpose is to protect the project finish date. When “critical chain project management” and “BPI” appear together in a question, think of the buffer, not the indices of earned value management. Its use is to give all participants a real-time signal of whether the finish date is safe. The answer is A.

Why the other options are wrong

  • B. EV compared with PV is the schedule performance index (SPI) of earned value management, which measures how far the project is from the schedule baseline.
  • C. Actual cost compared with earned value is a cost comparison used for cost performance and has nothing to do with buffers.
  • D. Buffer length against the sum of safety times is not what the BPI compares, and it is not a buffer-monitoring signal.

Key takeaway The BPI compares the percentage of project buffer remaining with the percentage of critical chain remaining, to protect the finish date.

Variation If only 20% of the buffer is left while 30% of the critical chain remains, the buffer is being consumed faster than the work is progressing, and you should look into the cause; the exam tests only what is compared, not the arithmetic.

Something wrong with this question?

Report an issue with this question

Example 2 Discrimination: two teams schedule with different methods

Question 2Example

Two teams at a consulting firm schedule the same project with different methods: Team A uses the critical path method and Team B uses the critical chain method. Which of the following is a difference between the two?

Show answer and explanation

Correct answer: B

Two teams schedule the same project with different methods: A uses the critical path method and B uses the critical chain method. The question asks how the two differ.

PMBOK 8 explains that critical chain project management aggregates task-level (or sprint-level) variability into a project buffer and allocates that buffer only when and where needed to protect the due date. It uses nearly identical scheduling logic to the critical path method, and both are based on critical path analysis calling for a resource-loaded and resource-leveled critical path. The only meaningful difference in logic is that critical chain project management also calculates the percentage of the project buffer remaining and compares it with the percentage of the critical chain remaining, producing the “buffer protection index” and giving all participants a real-time signal of schedule performance. Option B describes exactly this difference. The answer is B.

Why the other options are wrong

  • A. This does not match PMBOK 8: both methods call for a resource-loaded and resource-leveled critical path, so you cannot say that Team A ignores resources or that Team B does.
  • C. Critical chain project management uses nearly the same scheduling logic as the critical path method and still uses the logical relationships between activities; it does not sequence by resource availability alone.
  • D. The scheduling logic of the two methods is nearly identical, but critical chain project management monitors progress with a project buffer and the buffer protection index, so the way of monitoring is different, not exactly the same.

Key takeaway The difference between critical chain project management and the critical path method: safety is pooled into a project buffer and progress is monitored with the buffer protection index.

Variation If the question instead asked how the buffer protection index differs from the schedule performance index (SPI), the answer is that the former protects the due date and the latter measures how far the project is from the schedule baseline.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The BPI protects the finish date, and the SPI measures how far you are from the baseline. Their uses are different; do not swap them.
  • The BPI compares the percentage of buffer remaining with the percentage of critical chain remaining; it is not EV against PV, nor EV against AC.
  • PMBOK 8: both methods call for building a resource-loaded and resource-leveled critical path; in the context of identifying the longest path or chain of tasks in the schedule, that critical path is synonymous with the critical chain. Common exam practice: when a question contrasts “a path built only from logical relationships” with the critical chain, choose “the critical chain considers resource constraints”.
  • Adding resources and approving overtime is crashing, not the critical chain method.

Key takeaways

Key point

  • Buffer management: during execution, compare the percentage of project buffer remaining with the percentage of critical chain remaining; the signal is called the buffer protection index (BPI).
  • The BPI protects the finish date; the SPI (the ratio of EV to PV) gauges how far the project is from the schedule baseline.
  • Critical chain project management pools uncertainty into buffers, and durations contain no safety margin; compared with a path scheduled only by logic, it highlights resource constraints (in PMBOK 8 both methods call for a resource-leveled critical path).
  • The logic of the two methods is nearly identical; the real difference is whether the percentage of buffer remaining is calculated.
  • The critical chain method is neither crashing nor resource smoothing.

This chapter has 8 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.