Schedule
Crashing vs. Fast Tracking
PMP · Schedule · 3 lessons · about 34 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
When the schedule slips, or the sponsor asks for an earlier finish, the project manager has to shorten the duration without cutting scope. Schedule compression offers two common techniques: crashing and fast tracking. Both are applied on the critical path, but they cost different things. Crashing shortens the schedule mainly by adding resources, and may increase cost and/or risk. Fast tracking shortens the schedule by overlapping activities, which mainly adds rework and risk and may also increase cost. These two concepts are high-frequency scenario-question topics, and the key is to read which constraints the stem gives: can the logical relationships change, and can resources and budget be added? The chapter also covers compression with multiple paths and the crash cost slope.
By the end of this chapter you should be able to do the following. State the preconditions for schedule compression and how it relates to negative float. Compare crashing options using the cost slope. State when fast tracking applies and what risks it carries. Compress correctly when there are several critical paths. Choose between crashing and fast tracking from the conditions in a question.
Lessons in this chapter
- Lesson 1: Schedule compression basics and crashing. Do not reduce scope, compress the critical path, and re-analyze after compressing; crashing adds resources to shorten the schedule for the least incremental cost; a cost slope example.
- Lesson 2: Fast tracking, and a worked comparison with crashing. Turn sequential activities into parallel ones, review discretionary dependencies closely, and confirm the overlap really shortens the critical path; a comparison table; a step-by-step multi-path compression example with a check.
- Lesson 3: Choosing in exam questions: crashing or fast tracking. Two signals, four typical question types, the link to cost and schedule performance data, and the answering order used in common exam practice.
Chapter map
| Condition in the stem | Choice |
|---|---|
| Budget may be increased, or extra resources are available, and adding resources to a critical path activity can shorten it | Crashing (when the incremental cost and risk are acceptable) |
| No extra resources, cost cannot increase, and there are discretionary dependencies that can be adjusted | Evaluate fast tracking (confirm the activities can run in parallel and that this shortens the critical path; assess rework, risk and cost) |
| Logical relationships cannot change, but extra resources are available | Crashing |
| Still behind after crashing | Re-analyze the critical path and the remaining room to compress; evaluate more crashing, fast tracking, or a combination |
| Multiple critical paths | Every one must be compressed by enough days |
Study tips and practice
- Practice the cost slope calculation from Lesson 1 first, then the multi-path compression in Lesson 2, and find the critical path again at every step.
- Practice the decision flow in Lesson 3 until it is automatic: two signals, and you can pick the answer in ten seconds.
- Redoing the critical path analysis after compression is a requirement in both calculation and scenario questions.
- This chapter is closely tied to the chapters on the critical path method and on resource leveling and resource smoothing, so you can alternate between them.
Lesson 1
Schedule Compression Basics and Crashing
Lesson overview
When the schedule is behind, or the sponsor asks for an earlier finish, the project manager has to shorten the duration without cutting scope. PMBOK 8 gives two common techniques, crashing and fast tracking, together called schedule compression. This lesson first covers the preconditions for schedule compression and how it relates to negative float, and then covers crashing: adding resources, for the least incremental cost, and only useful on critical path activities that can actually be shortened. A cost slope shows which activity is the cheapest one to crash first. Fast tracking and the comparison of the two techniques are in the next lesson, and how to choose in exam questions is in the third lesson. ECO: Process domain, Task 8 (Plan and manage schedule).
Schedule compression and its preconditions
Schedule compression is a technique used to shorten the schedule duration without reducing the project scope. It is used to meet schedule constraints, imposed dates or other schedule objectives. Negative float analysis is a helpful companion technique: the critical path is the path with the least float, and when a constraint or imposed date is violated, total float can become negative. In that case, first analyze why the float is negative, and consider measures such as schedule compression to restore the schedule objective (adjusting the constraint is another option worth evaluating). The activities you compress must be on the critical path; compressing a non-critical activity does not shorten the total duration. After compressing, redo the critical path analysis to catch any new critical path.
When you are told something like "finish one month earlier", the right steps are these. First review the critical path and assess which activities can be crashed and which can be run in parallel, comparing the schedule, cost and risk impact of each option. If the compression measures you are considering would change the approved plan, a baseline or the authorized scope, submit a change request and implement it only after change control approves it. If the measures fall within existing authority and tolerances, take corrective action as planned. PMBOK 8 requires that any change to the schedule baseline or agreed-upon schedule of a predictive project go through the Assess and Implement Changes process and follow integrated change control. Cutting scope directly, skipping quality inspections, simply extending the deadline, or editing the schedule directly are not the first choice.
Crashing
Crashing is a schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources. Examples include approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Crashing works only for activities on the critical path where additional resources will shorten the activity's duration. Crashing does not always produce a viable alternative and may result in increased risk and/or cost.
Some activities do not get faster when you add resources, for example a 24-hour stress test, or work where the team is already saturated and extra people only add coordination cost. Such activities cannot be crashed. So the outcome of crashing is: it may increase cost and/or risk, and whether the duration actually shortens depends on whether the activity can be shortened by adding resources.
How to do it: use the cost slope to pick what to crash first
Crashing is done "for the least incremental cost". In practice you compare cost slopes: how much extra each day of shortening costs.
Example: choosing the cheapest critical path activities to crash
A data-center cutover project has three activities on its critical path, with the data below (days and dollars). To keep the calculation simple, assume no other path becomes critical during compression:
| Activity | Normal duration | Normal cost | Crash duration | Crash cost | Maximum compression |
|---|---|---|---|---|---|
| Cabling | 10 | $20,000 | 6 | $26,000 | 4 days |
| Rack installation | 8 | $12,000 | 6 | $15,000 | 2 days |
| Integration testing | 6 | $9,000 | 5 | $10,800 | 1 day |
Step 1: Calculate the slopes. Cabling: ($26,000 − $20,000) ÷ (10 − 6) = $1,500 per day. Rack installation: ($15,000 − $12,000) ÷ (8 − 6) = $1,500 per day. Integration testing: ($10,800 − $9,000) ÷ (6 − 5) = $1,800 per day.
Step 2: Compress by 5 days, lowest slope first. Cabling and rack installation tie at $1,500 per day. Use cabling to its limit, 4 days ($6,000), then rack installation for 1 day ($1,500). That is 5 days of compression for an added $7,500.
Step 3: Check. If you used integration testing for 1 day, rack installation for 2 days and cabling for 2 days instead: $1,800 + $3,000 + $3,000 = $7,800, which is more than $7,500. So $7,500 is the lowest-cost plan here. Under the assumption above, the path shortens by 5 days. In practice, recalculate the critical path after each stage of compression; if another path becomes critical, include its activities in the comparison and choose the plan again.
Worked examples
Example 1 Scenario: asked to finish one month early
PMLyceum is taking on its first warehouse management system project, and the team has no prior experience in this industry. Halfway through the project, a key stakeholder tells the project manager that because of a newly issued industry regulation, the project must finish one month earlier than planned. What should the project manager do to meet this requirement?
Show answer and explanation
Correct answer: B
The project is halfway through, and a key stakeholder wants it to finish one month earlier than planned because of a new regulation. The question is what approach achieves that.
The finish date must come earlier without reducing scope, so the answer is schedule compression. The first step is to review the critical path, because only compressing critical path activities can shorten the total duration. Then assess which activities can be crashed and which can be run in parallel. After compressing, redo the critical path analysis, because compressing the critical path may turn a near-critical path into the new critical path. The answer is B.
Why the other options are wrong
- A. Schedule reserve is time set aside for uncertainty. Adding reserve only makes the plan longer; it does not shorten the actual duration.
- C. The work breakdown structure decomposes scope, so reviewing it will not shorten the duration. The schedule baseline is approved and cannot simply be updated; it must go through change control.
- D. A reward scheme may raise motivation, but it is not a schedule compression technique and cannot guarantee finishing one month earlier.
Key takeaway When asked to finish early: look at the critical path first, then compress with crashing or fast tracking, and changing a baseline goes through change control. Recheck the critical path before and after compressing, because a near-critical path may become the new critical path.
Variation Once the compression plan changes the approved schedule baseline or the finish date, submit a change request and handle it through the formal Assess and Implement Changes process. If every compression option is used up and the date still cannot be met, negotiate an adjusted baseline or scope with stakeholders.
Something wrong with this question?
Example 2 Concept: what adding resources to the critical path inevitably brings
After reviewing the project plan, the customer requires the planned duration to be cut to 60% of the original. The project manager decides to add resources to the tasks on the critical path. What is the most direct and most typical consequence of this decision?
Show answer and explanation
Correct answer: C
After reviewing the project plan, the customer requires the planned duration to be cut to 60% of the original, and the project manager adds resources to critical path tasks. The question asks for the most direct and most typical consequence of that decision.
Adding resources to critical path tasks is crashing. PMBOK 8 notes that crashing “may result in increased risk and/or cost”, and adding resources usually costs money, so increased cost is the most direct and most typical consequence. (If idle internal resources are used, the added cost may be small, but it is still the most reasonable of the four.) Whether the duration shortens depends on whether the activity can be made faster by resources, and coordination cost can offset the benefit, so “definitely shortens”, “lengthens instead” and “all become non-critical” are not the most direct and typical consequence of crashing. The answer is C.
Why the other options are wrong
- A. After compression the critical path may get shorter or even move to another path, but it will not make every critical activity non-critical, which is why you redo the critical path analysis.
- B. The communication and coordination cost of new people can indeed lengthen the duration instead, but that is a possibility, not a certainty.
- D. The duration does not necessarily shorten when resources are added; the nature of the activity and coordination cost both limit the effect. It is not absolute.
Key takeaway The most typical price of crashing is increased cost, and it does not guarantee a shorter duration.
Variation If the question asks “what risk may it bring”, then the coordination burden and quality risk from new people are both acceptable answers.
Something wrong with this question?
Common traps
Common trap
- Schedule compression does not reduce scope. Cutting scope or skipping quality inspections is not schedule compression.
- You compress activities on the critical path. Compressing a non-critical path does not shorten the total duration.
- "Add extra resources", "approve overtime" and "pay to expedite" all describe crashing. They are not the critical chain method and not resource leveling.
- Adding resources does not necessarily shorten the duration, because the coordination cost of new people can cancel the effect. Only critical path activities that can be shortened by adding resources are suitable for crashing, and crashing may increase cost and/or risk.
- When a variance appears, analyze first and compare options. If the option changes an approved baseline or authorization, go through change control; within authority and tolerances, take corrective action directly.
Key takeaways
Key point
- Schedule compression: shorten the schedule duration without reducing scope; redo the critical path analysis after compressing.
- When total float is negative, first analyze the cause and restore the schedule objective; you can compare schedule compression, adjusting the constraint and other options. When you use compression, the targets are critical path activities.
- Crashing: add resources to shorten the duration for the least incremental cost; it applies only to critical path activities that get faster when resources are added.
- Crash cost slope = (crash cost − normal cost) ÷ (normal duration − crash duration); crash the lowest slope first.
- Adding resources does not necessarily shorten the duration; only critical path activities that can be shortened by adding resources are suitable for crashing, and crashing may increase cost and/or risk.
Lesson 2
Fast Tracking, and a Worked Comparison with Crashing
Lesson overview
Crashing mainly trades cost for time, while fast tracking mainly trades risk for time (the two trade-offs are not mutually exclusive): activities that would run one after another are run at the same time. This lesson covers how fast tracking is done, when it applies and what it costs, puts the two techniques side by side in one table, and then works a multi-path compression example: after each step of compression you must find the critical path again, and when there are several critical paths they must be shortened together for the compression to count. Fast tracking requires a close review of discretionary dependencies, and mandatory dependencies must not be violated, which ties directly to the dependency types covered earlier. ECO: Process domain, Task 8 (Plan and manage schedule).
Fast tracking
Fast tracking is a schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration. An example is constructing the foundation of a building before completing all of the architectural drawings. Fast tracking may result in rework and increased risk. Fast tracking only works when activities can be overlapped to shorten the project duration on the critical path. Such overlapping requires increased coordination efforts between the activities concerned, potentially resulting in greater quality risk. Fast tracking may also increase project costs.
Fast tracking requires a close review of discretionary dependencies; mandatory dependencies must not be violated. So before deciding to fast track, go through the relevant dependencies one by one and see which are discretionary and whether they can be modified or removed. In practice, discretionary dependencies are often an order that grew out of habit, so they are the easiest to turn into parallel work, but the rework risk still has to be assessed. Adding a lead to a relationship is another way to achieve overlap.
Crashing compared with fast tracking
| Crashing | Fast tracking | |
|---|---|---|
| Method | Add resources (overtime, more people, expediting) | Turn sequential activities into activities that run at least partly in parallel |
| Cost | Cost and/or risk may increase | Rework and risk increase, and coordination effort and cost may also increase |
| Applies to | Critical path activities that can be shortened by adding resources | Critical path activities that can be overlapped; the logic must allow adjustment, so review discretionary dependencies closely |
| Extra budget | Usually needed | Common exam practice: usually does not depend on adding resources, but you take on rework and coordination risk. PMBOK 8 also notes that fast tracking may increase project costs |
| Precondition | Adding resources makes the activity faster | The logical relationships can be modified |
How to do it: single-path and multi-path examples
Example 1: the same 3 days of compression, done two ways
Solution design takes 6 days and development takes 9 days, done in sequence, for a total of 15 days.
- Crashing: add people to development so it shortens to 6 days, and the total becomes 6 + 6 = 12 days. The cost is the extra staffing expense.
- Fast tracking: development starts when design reaches day 3, so the two overlap by 3 days and the total is 6 + 9 − 3 = 12 days. No people are added, but development is built on a design that is not finalized, so rework is possible.
Example 2: multiple paths; at each step choose the lowest-cost activity or combination of activities that shortens all current critical paths
The network: A (5 days) is followed by two branches: A → B (7 days) → D (4 days), 16 days in total; and A → C (6 days) → D, 15 days in total. The target is to compress the duration to 13 days. The crash cost per day of compression and the maximum days available for each activity: A $2,500 (at most 2 days), B $1,200 (at most 2 days), C $1,800 (at most 3 days), D $3,000 (at most 1 day).
Step 1: Find the critical path. A-B-D is 16 days and is the critical path; A-C-D is 15 days. Only critical path activities can be compressed, and B is the cheapest of them. Compress B by 1 day for $1,200, and A-B-D becomes 15 days.
Step 2: Compare again. Both paths are now 15 days and both are critical. To help, you must shorten both at once, and there are three ways to do that: compress A (shortens both paths), $2,500; compress B and C by 1 day each, $1,200 + $1,800 = $3,000; compress D (shortens both paths), $3,000. Choose the cheapest, A, for $2,500. Both paths become 14 days, for a cumulative $3,700.
Step 3: Compress one more day. Making the same comparison, A can be compressed once more (the limit is 2 days) for $2,500, still the cheapest. Both paths become 13 days, for a cumulative $6,200, and the target is met.
Step 4: Check. Total cost = $1,200 + $2,500 × 2 = $6,200. Try some alternatives: B for 2 days plus D for 1 day plus C for 1 day costs $2,400 + $3,000 + $1,800 = $7,200; A for 1 day plus B for 2 days plus C for 1 day costs $2,500 + $2,400 + $1,800 = $6,700. Both are more than $6,200. If after Step 1 you kept compressing only B and left A-C-D alone, the duration would stop getting shorter.
Multi-path compression questions usually give the maximum crash for each activity and then ask which activities to crash. The answer has to deliver the required reduction on every critical path, not just on one.
Worked examples
Example 1 Scenario: the owner wants adjacent phases to run at the same time; what to do before approving
On a new plant construction project, the owner is worried that key milestones will be missed and insists that several consecutive construction phases be done at the same time to catch up. Before approving this change, which analysis should the project manager perform FIRST to decide which phases can overlap?
Show answer and explanation
Correct answer: A
On a new plant construction project, the owner worries about missing key milestones and insists that several consecutive construction phases be done at the same time. The question asks which analysis should be done first, before approving the change, to decide which phases can overlap.
Running phases in parallel is fast tracking. In fast tracking you review and adjust discretionary dependencies, and mandatory dependencies must not be violated, so before approval you first do a dependency analysis to see which phases can overlap. Cost and schedule impact only mean something once you know what can overlap. This is also the standard way fast tracking is tested: whenever activities overlap or phases run in parallel, the first step is to review the dependencies; mandatory dependencies cannot be violated and only discretionary dependencies can be adjusted. The answer is A.
Why the other options are wrong
- B. Fast tracking mainly carries rework risk, and the cost impact can be evaluated after it is confirmed that the phases can run in parallel. It is not the analysis that must be done first before approval.
- C. Crashing impact analysis addresses adding resources. The stem has phases running at the same time and no added resources.
- D. Schedule impact analysis is meaningful only after you know which activities can overlap, and deciding whether they can overlap starts with the dependencies.
Key takeaway Before fast tracking, do the dependency analysis: mandatory dependencies cannot be violated, and what can be adjusted are the discretionary dependencies.
Variation If the owner asked instead to add construction crews to save time, that would be crashing. First confirm that the activities are on the critical path and can actually be shortened by added resources, then assess the schedule, cost, and risk impacts.
Something wrong with this question?
Example 2 Scenario: still behind after two weeks of crashing
To deal with a delay, the project manager assigned extra people to the critical activities. Two weeks later the project is still behind the schedule, adding more people would now have very limited effect, and several activities on the critical path have discretionary dependencies that could be changed to run in parallel. How should the project manager get the project back on track?
Show answer and explanation
Correct answer: D
On a project, the project manager has already added people to critical activities, and two weeks later it is still behind. The question is how to get the project back on track.
There are two schedule compression techniques, crashing and fast tracking. Adding people is crashing. Two weeks later the project is still behind, and the stem says that adding more people would have limited effect. At the same time, the critical path has discretionary dependencies that can be changed to run in parallel, which meets PMBOK 8's condition for fast tracking, that activities can be performed in parallel to shorten the critical path. You should first re-analyze the critical path and the effect of the crashing, then develop a fast-tracking proposal for the activities that can overlap and assess the rework and coordination risk. If the proposal changes the approved schedule baseline or agreed-upon schedule, submit a change request and implement it only after approval. The answer is D.
Why the other options are wrong
- A. Crashing has already been applied, the project is still behind after two weeks, and further additions would have little effect. Continuing the same approach is not an improvement.
- B. Simply updating the project schedule will not recover the lost time. Moreover, if fast tracking changes the approved schedule baseline or agreed-upon schedule, a change request must first be submitted and approved through change control; the schedule cannot be updated directly.
- C. Resource leveling may change the critical path and usually lengthens the duration, so it does nothing to catch up on the schedule.
Key takeaway First see which kind of compression is feasible on the critical path: when adding resources has limited effect and the activities can run in parallel, use fast tracking.
Variation If the stem said all relevant dependencies were mandatory, fast tracking would be infeasible. You would assess other corrective or compression options and, if the target still could not be met, submit a change request and negotiate an adjusted date or other constraint with stakeholders.
Something wrong with this question?
Example 3 Calculation: two critical paths, which activities to crash
The figure below is the activity network diagram of a network upgrade project, showing the sequence and duration (in weeks) of each activity. The project manager is asked to shorten the project duration by 2 weeks. None of the activities can be fast tracked; activities P and T cannot be crashed, activity U can be crashed by at most 2 weeks, and each of the other activities can be crashed by at most 1 week. To meet the new duration requirement, which action should the project manager take?
Show answer and explanation
Correct answer: A
The network diagram has two paths, the duration must be shortened by 2 weeks, and the stem limits which activities can be crashed. The question is which activities to crash.
Both paths are critical, and the total duration must come down by 2 weeks, so each path must be shortened by 2 weeks; compressing only one is as good as compressing none. P and T cannot be crashed, so path 2 can only be shortened by crashing U by 2 weeks. On path 1, two of Q, R and S must be crashed by 1 week each, and the combination offered in the options is R and S. The answer is A.
- Path 1: P-Q-R-S = 2 + 3 + 2 + 2 = 9 weeks; path 2: P-T-U = 2 + 4 + 3 = 9 weeks; both are critical paths
- Path 2: T cannot be crashed, so crash U by 2 weeks, giving 7 weeks
- Path 1: crash R and S by 1 week each, giving 7 weeks
- Both paths are 7 weeks, the total duration is shortened by 2 weeks, and the target is met
Why the other options are wrong
- B. It includes T, which cannot be crashed, and it shortens path 1 by only 1 week (through R), leaving it at 8 weeks.
- C. Crashing only U brings path 2 down to 7 weeks, but path 1 is still 9 weeks, so the total duration does not change. Only one critical path was compressed.
- D. Crashing only R and S brings path 1 down to 7 weeks, but path 2 is still 9 weeks. It ignores the other critical path.
Key takeaway With several critical paths, every one must be compressed by enough; compressing only one is as good as compressing none.
Variation If U could be crashed by at most 1 week, path 2 could come down to only 8 weeks, so the total duration could be shortened by only 1 week and the 2-week requirement could not be met.
Something wrong with this question?
Common traps
Common trap
- "Activities that were sequential are now parallel" and "start the following activity earlier" describe fast tracking, not adding resources.
- Fast tracking requires a close review of discretionary dependencies, and mandatory dependencies must not be violated. You must also confirm that the overlap really shortens the critical path.
- The main risks of fast tracking are rework and quality problems, and it may also increase cost.
- With several critical paths, compressing only one is as good as compressing none: every current critical path must be compressed enough to meet the target duration.
- Redo the critical path analysis after compressing. A path that was near-critical may become the new critical path.
Key takeaways
Key point
- Fast tracking: turn sequential activities into activities that run at least partly in parallel; it may cause rework and increased risk, and needs more coordination.
- Before fast tracking, do the dependency analysis: review discretionary dependencies closely, and do not violate mandatory dependencies.
- Crashing mainly trades cost for time and fast tracking mainly trades risk for time; both may increase cost and risk.
- Multi-path compression: at each step choose the lowest-cost activity or combination that shortens all current critical paths, and compress together any new critical path that appears.
- When the schedule is behind, first analyze the variance and its root cause, then compare the cost, risk and feasibility of crashing, fast tracking and other corrective options. If the option affects the approved schedule baseline, submit and implement the approved change through the change control process.
Lesson 3
Choosing in Exam Questions: Crashing or Fast Tracking
Lesson overview
The two schedule compression techniques each have their own conditions for use, and the exam almost always tests them with scenario questions: the stem gives a set of constraints and asks you to decide whether to crash or fast track. The approach is very consistent. Look at two things: can the logical relationships change, and can resources and budget be added? This lesson turns those two signals into a decision flow (common exam practice), adds the link to cost and schedule performance data, explains why adaptive projects do not talk about compression, and lists four typical question types. This is a frequent exam topic. ECO: Process domain, Task 8 (Plan and manage schedule) and Task 9 (Evaluate project status).
Two signals: logical relationships, and resources and budget
When you read a question, ask two things in order.
First: can the logical relationships between activities change? If the stem says "the network diagram is fixed and the logic may not be changed" or "the dependencies are mandatory", fast tracking is ruled out, because fast tracking changes the logic and overlaps activities. If the stem says "many of the activities have discretionary dependencies" or "the adjacent phases can run at the same time", fast tracking is feasible.
Second: can resources and budget be increased? If the stem says "the budget can be increased", "idle staff are available", or "cost is no object", and adding resources to a critical path activity really would shorten its duration (PMBOK 8: crashing works only for activities on the critical path where additional resources will shorten the activity’s duration, and crashing does not always produce a viable alternative), crashing is a feasible choice. If the stem says "no extra resources", "there is not a cent for overtime", or "no additional cost will be accepted", crashing is ruled out. In that case, if the dependencies are discretionary and running in parallel would genuinely shorten the critical path, fast tracking is feasible (when the logic cannot change either, neither is feasible; see the table below).
| Condition in the stem | Choice | Reason |
|---|---|---|
| Critical path activities can be shortened by adding resources, and budget and approval allow it | Evaluate crashing | Trades the least incremental cost for time; it does not apply when there is only budget or idle resources but the activity is not on the critical path or extra resources would not help |
| No extra resources, cost cannot increase, dependencies are discretionary | Fast tracking | Usually needs no extra resources; you accept rework risk |
| Logical relationships cannot change, extra resources are available | Crashing | Fast tracking requires changing the logic |
| Logical relationships cannot change, no extra resources, and cost cannot increase | Neither is feasible | Negotiate with stakeholders and go through change control |
| Low risk tolerance, budget available | Compare the risks of the two; choose crashing when the fast tracking risk is unacceptable, crashing is feasible and its risk assessment is acceptable | Fast tracking brings rework and quality risk, and crashing may also increase risk and cost |
| Low risk, no budget, dependencies are discretionary | Fast tracking | The project can absorb rework |
The link to cost and schedule performance data
A cost performance index (CPI) greater than 1 means cost efficiency is good as of the measurement date (EV/AC is greater than 1). A schedule performance index (SPI) less than 1 means schedule efficiency is poor on an earned value basis. A good CPI does not by itself mean there is budget free to spend, so whether to crash still depends on checking the critical path, the effect of compression from added resources, the available budget and the approvals. In common exam practice, when the stem says cost performance is good, budget is available and the schedule is behind, lean toward crashing. Conversely, when CPI is less than 1 and management will not add budget, crashing is not feasible, and you can evaluate fast tracking or improving the efficiency of the existing staff; but fast tracking may still add cost through coordination and rework, so it cannot be assumed to be free.
Answering order (common exam practice) and what PMBOK 8 says
PMBOK 8 only describes how each of the two techniques is done, when it applies and what it costs. It does not give an order for which to choose first when no constraints are stated. There is no fixed priority order: first decide whether the stem is asking about a category of technique or a specific action. If it asks about the category, choose schedule compression; if it gives conditions such as resources, cost and dependencies, choose the specific technique that matches them; when the conditions are not sufficient, do not rank them mechanically (common exam practice).
Four typical question types
Type 1: it explicitly allows spending money. In a review meeting, a team member says integration testing needs three more days, and a senior manager says that even if the budget has to be increased, delivery must still match the baseline. Extra budget is allowed, the activity is on the critical path, and extra resources really would shorten it, so choose crashing.
Type 2: it explicitly does not allow spending money. A pipeline project is three weeks late, the company will not approve overtime pay or any other extra spending, and analysis shows that the critical path has activities with discretionary dependencies that can be overlapped. You can evaluate fast tracking. If the nature of the dependencies is not yet clear, first analyze the dependencies and the critical path, then draw a conclusion.
Type 3: the constraint is the logical relationships. The logic in the network diagram is fixed and may not be adjusted, and the company happens to have a pool of idle staff who can be added to critical path activities to shorten their durations. Choose crashing.
Type 4: the constraint is risk and sustainability. The project has strict requirements for both quality and schedule, fast tracking would very likely cause more quality problems, and overtime by the team is not sustainable and leads to fatigue. Neither fast tracking (high quality risk) nor relying on long-term overtime (unsustainable) is suitable. After comparing the risks, switch to bringing in more people or other resources, which is still crashing, provided that adding resources to critical path activities is effective. When you ask the company for additional resources, explain that they are needed to keep the project on schedule.
Adaptive projects and schedule monitoring
Many adaptive projects use fixed time-boxed iterations, and some use a continuous flow approach. To monitor the schedule, they reprioritize the backlog and use measures such as velocity to judge the pace of delivery, and they generally do not use compression terms such as crashing and fast tracking. Predictive projects can evaluate crashing or fast tracking, based on critical path analysis, while developing or monitoring the schedule: first use the critical path method to see how a delay affects the critical path, then decide which approach to use, and first make sure the resources are sufficient.
Worked examples
Example 1 Scenario: no extra resources, mostly discretionary dependencies
You have been assigned to manage an ERP implementation project for a restaurant chain, covering store, warehouse, finance and other modules. Your calculated forecast completion date is 2 months later than the desired date. After analyzing the schedule network diagram, you determine that many activities on the critical path have discretionary dependencies, and confirm that some can be overlapped to shorten the critical path. You request additional resources but are told none are available for the project. Assuming project risk is low, which of the following is the BEST course of action?
Show answer and explanation
Correct answer: C
The forecast completion is 2 months later than desired, the activities mostly have discretionary dependencies, the request for additional resources has been refused, and project risk is low. The question asks for the best course of action.
To shorten the duration without reducing scope, use schedule compression. Extra resources are not available, so crashing will not work. The activities mostly have discretionary dependencies and can be overlapped, and risk is low, so the project can bear the rework risk. So change some sequential activities to run in parallel, which is fast tracking. “No extra resources” rules out crashing, while “discretionary dependencies” and “low risk” together support fast tracking. If any of the three conditions were missing, the answer might differ, so match all three conditions before choosing. The answer is C.
Why the other options are wrong
- A. Compressing quality inspection sacrifices quality for time and is not a schedule compression technique.
- B. Reducing scope is not schedule compression, and scope should not be touched first when feasible compression options exist.
- D. Resource leveling deals with resource constraints or overallocation, may change the critical path and often lengthens the duration. It is not a compression technique that can move the completion date 2 months earlier.
Key takeaway No extra resources, discretionary dependencies, low risk: fast tracking. Fast tracking requires activities that can be overlapped; because it may increase rework and risk, assess the risk tolerance before using it.
Variation If the company approved additional budget and analysis confirmed that added resources would shorten critical-path activity durations, crashing would also be feasible. Compare its cost and risk with fast tracking; with ample budget and sensitivity to risk, lean toward crashing.
Something wrong with this question?
Example 2 Scenario: extra budget allowed, still must deliver on the baseline
In a project review meeting, the team member responsible for integration testing tells the project manager that this critical path activity will take three days longer than planned, and that adding resources could shorten its duration. A senior manager says that even if the budget must be increased, a way must be found to deliver the project on the baseline plan. Which method should the project manager use to meet this requirement?
Show answer and explanation
Correct answer: A
Integration testing will take three days longer than planned, and a senior manager requires delivery on the baseline plan even if the budget must be increased. The project manager must choose the schedule compression method that meets this requirement and also fits the condition that the budget can be increased.
Delivering within the original baseline calls for schedule compression. The two techniques are crashing and fast tracking. The activity is on the critical path and adding resources can shorten its duration, which is the precondition for crashing. The stem also explicitly allows an increase in budget, and crashing trades cost for time, so the available facts directly support crashing. “Even if the budget must be increased, deliver on the baseline” removes the cost constraint while keeping the date fixed, which points to crashing, which trades cost for time, rather than fast tracking, which takes on rework risk. The answer is A.
Why the other options are wrong
- B. Fast tracking requires activities that can be overlapped to shorten the critical path. The stem does not establish that condition, so fast tracking is not supported by the available facts.
- C. The critical chain method manages uncertainty by accounting for resource constraints and setting project buffers, and it does not itself shorten this activity's duration. The stem does not say the project uses the critical chain method; what it does give are the three conditions for crashing (a critical path activity, added resources that work, and an increase in budget allowed).
- D. Leads and lags are time adjustments applied to the logical relationships between activities: a lead overlaps activities, with an effect similar to fast tracking and its rework risk, and a lag delays the following activity. The stem does not say there are leads or lags to adjust, and with budget available you should prefer shortening the testing activity itself by crashing.
Key takeaway When the stem confirms that adding resources to a critical path activity shortens it and increased cost is allowed, crashing is a supported choice. When resources cannot or should not be added but the dependencies allow parallel work, then consider fast tracking after assessing rework, quality, risk and cost impact.
Variation If the senior manager had said “not a cent more can be added”, the answer would become fast tracking, provided the dependencies allow parallel work, and you would assess the rework, quality and cost impact.
Something wrong with this question?
Common traps
Common trap
- "Add extra resources", "approve overtime" and "pay to expedite" describe crashing; "turn sequential activities into parallel ones" describes fast tracking.
- Do not choose crashing every time you see "speed up the schedule". First check whether there is budget and whether the logical relationships can change.
- Resource leveling may change the critical path and may lengthen the project duration, and compressing quality inspections or cutting scope is not schedule compression. Eliminate them when they appear as options.
- Monte Carlo analysis, earned value analysis and the critical chain method are not compression techniques.
- There is no fixed "schedule compression > crashing > fast tracking" order: first decide whether the stem asks about a category or a specific action, then match the conditions (common exam practice).
Key takeaways
Key point
- Two signals: can the logical relationships change, and can resources and budget be added (then confirm the activity is on the critical path and that compression really works).
- Budget can be increased, extra resources are available, and a critical path activity gets faster when resources are added: crashing. No extra resources, cost cannot increase, dependencies are discretionary and the overlap would shorten the critical path: evaluate fast tracking (it may still add cost and rework risk).
- The logical relationships are fixed: you cannot fast track, so crash if resources are available.
- CPI greater than 1 and SPI less than 1: cost efficiency is good while the schedule is behind; in common exam practice, when budget is authorized and critical path activities can be shortened by adding resources, lean toward crashing.
- Compression does not cut scope or quality; adaptive projects rely on reprioritizing the backlog and on velocity.
This chapter has 36 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.