- Schedule Baseline and Monitoring the Schedule
Schedule
Schedule Baseline and Monitoring the Schedule
PMP · Schedule · 3 lessons · about 33 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
The schedule baseline is the accepted and approved version of the schedule model, with baseline start and finish dates; the project schedule remains a separate output of the schedule model. On a predictive project, schedule monitoring during execution usually compares actual or forecast progress against it. On an adaptive project, the focus is on comparing the total amount of work delivered and accepted with the amount expected to be complete for the same period, on watching velocity, and on reprioritizing the remaining work. This chapter finishes the outputs of schedule development (the schedule baseline and the project schedule) and covers the last process in the Schedule performance domain: Monitor and Control Schedule. It ties the earlier chapters together: which steps produce the baseline, what analysis to use after a deviation, and what process to follow when the baseline has to change. This is a frequently tested chapter, especially scenario questions on variance analysis and schedule changes, and the main line is "analyze first, then act".
By the end of this chapter you should be able to do the following. State the definition of the schedule baseline, what is required to change it, and how it relates to reserves. Tell milestone, summary and detailed schedules apart. State the inputs, tools and outputs of schedule monitoring, and the different focus for predictive and adaptive projects. Handle a schedule deviation in this order: analyze the cause, compare with the control threshold, go through change control if needed, then update and communicate.
Lessons in this chapter
- Lesson 1: The schedule baseline and the three forms of the project schedule. The baseline is the approved schedule model; on predictive projects a baseline change must go through the Assess and Implement Changes process, while adaptive projects handle it flexibly according to their governance and change mechanisms; how the baseline, reserves and the performance measurement baseline relate; what each of the three schedule forms is for; an example with reserves and the baseline.
- Lesson 2: Monitor and Control Schedule: inputs, tools, and the focus for predictive and adaptive projects. The definition and key benefit of the process, its tools and techniques, an example of schedule variance and schedule performance index, and keeping the schedule realistic.
- Lesson 3: Variance analysis and schedule changes. A four-step response to a deviation (common exam practice); two ways to handle a deviation inside and outside the control threshold; baseline updates; the typical "act first, analyze later" wrong options.
Chapter map
| Scenario | What to do | Lesson |
|---|---|---|
| The schedule is complete but not yet approved | Push for review; create the baseline only after approval | Lesson 1 |
| A change affects the baseline dates | Assess the impact; update the baseline after approval | Lessons 1 and 3 |
| Reporting to the customer or management | Milestone schedule or bar chart | Lesson 1 |
| Forecasting a future delay | Trend analysis | Lesson 2 |
| You find the project is behind | Analyze the cause first, then compare with the control threshold | Lesson 3 |
Study tips and practice
- On deviation scenario questions, look at the verbs in the options first: analyze, assess and discuss are the right starting points, while crashing straight away, changing first or reporting up usually skips the analysis.
- You should be able to recite the comparison points for the baseline (baseline versus project schedule, versus a draft, versus management reserve).
- Once you finish this chapter, the lessons in the schedule topic are complete. Go back and do the topic's mixed practice, focusing on critical path calculation and the choice of compression technique.
Lesson 1
The Schedule Baseline and the Three Forms of the Project Schedule
Lesson overview
Once the schedule has been developed and approved, it becomes the schedule baseline. On projects that use a schedule baseline, one of the main jobs of schedule monitoring is to compare actual dates with the approved baseline dates; adaptive projects also track progress through accepted work, velocity and the backlog. This lesson covers what the schedule baseline is, how it differs from the project schedule, what procedure a change must follow, and how it relates to reserves and the performance measurement baseline. It then covers the three forms of the project schedule, the milestone schedule, the summary schedule (bar chart) and the detailed schedule, and the schedule data. This is the final output of schedule development, and it is what the next lesson's monitoring compares against. ECO: Process domain, Task 8 (Plan and manage schedule), and Business Environment domain, Task 3 (Manage and control changes).
The schedule baseline
The schedule baseline is the approved version of a schedule model that can be changed using formal change control procedures and is used as the basis for comparison to actual results. The schedule baseline is accepted and approved by the appropriate stakeholders as the baseline for the schedule, with baseline start dates and baseline finish dates. During monitoring and controlling, the approved baseline dates are compared to the actual start and finish dates to determine if variances have occurred. The schedule baseline is a component of the project management plan.
Three key points:
- It is a baseline only once approved. A schedule that has been developed but not yet approved by stakeholders is only a draft. The project manager should push for the review and establish the baseline after approval. Do not save the draft as the baseline and let the team start work, and do not treat team agreement as a substitute for approval.
- It changes only through change control. Once the baseline is approved, changes go through the change control procedure. Change control is stricter on predictive projects; adaptive and agile projects are more flexible and may even have none.
- The baseline is not the project schedule. The baseline is the approved version, kept for comparison. The project schedule is the current output of the schedule model and is updated as work progresses.
Tie the contents of the baseline to reserves. Contingency reserve is time or money allocated in the schedule or cost baseline for known risks with active response strategies. It is used under the risk management plan and established authority; using it as planned does not usually change the baseline. Management reserve is not in the baseline; PMBOK 8 says it is typically released at the discretion of senior leadership or management (in some organizations, at the discretion of the project manager or project management team). Common exam practice: using management reserve requires a change request through change control, and it is merged into the baseline only after approval. The schedule baseline, together with the scope baseline and cost baseline, forms the performance measurement baseline, which earned value management uses to compare actual schedule and cost performance.
Example: how many days are really in the baseline
A project's activity estimates add up to a planned duration of 100 days. The identified risks need 8 days of contingency reserve, which, as is usual, is included in the schedule baseline, so the baseline duration is 108 days. Management holds another 6 days of management reserve outside the baseline.
Step 1: Baseline duration. 100 + 8 = 108 days, and the baseline finish date is calculated from 108 days.
Step 2: The project manager's authority. When an identified risk occurs, if the risk management plan and established authority allow it, the project manager may use the 8 days of contingency reserve already in the baseline, and the baseline does not change.
Step 3: Beyond the contingency reserve. If an unknown-unknown risk creates 6 days of unforeseen work, a request to use management reserve can be made under the governance arrangements (common exam practice: submit a change request through change control). Only when an approved change brings these 6 days into the plan does the schedule baseline move from 108 days to 114 days. An ordinary delay should first be analyzed and corrected with corrective action; it must not be covered automatically from management reserve.
Step 4: Check. 108 + 6 = 114, so the baseline includes this management reserve only when it becomes 114 days.
The three forms of the project schedule
The project schedule is an output of a schedule model that presents linked activities with planned dates, durations, milestones and resources. Each activity needs at least a planned start date and a planned finish date. There are three common forms of presentation, running roughly from least to most detail (common exam practice; which to use can be tailored to communication and management needs). The use described for "key external interfaces" in the table is likewise common exam practice:
| Milestone schedule | Summary schedule | Detailed schedule | |
|---|---|---|---|
| Also called | Milestone chart | Bar chart, Gantt chart | Project schedule network diagram (precedence diagramming method and others); a time-scaled one is a logic bar chart |
| Use | Planned start or finish dates of the major deliverables and key external interfaces, often used for high-level communication | Shows activity progress at a glance, which makes it easy to explain to management | Makes it easy to analyze the sequence relationships between activities |
The three forms use the same data and differ only in level of detail. A milestone schedule shows only points in time (diamond symbols). A summary bar chart uses horizontal bars for schedule activities and may also roll up summary activities or work packages. A detailed schedule breaks the work down into specific activities and shows the logical relationships between them.
Developing the schedule also produces schedule data and the project calendars. Schedule data includes, at a minimum, the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints. It is often supplemented with resource histograms, alternative schedules (best case or worst case, before and after resource leveling, with or without imposed dates) and the schedule reserves applied. When a predictive project has to meet a stage-review requirement, it can set milestones in the schedule and arrange reviews; it does not need to switch to another approach.
Worked examples
Example 1 Scenario: a change alters the baseline finish date
PMLyceum takes on a predictive ERP implementation project. While reviewing a change request, the project manager finds that it would change the completion date in the schedule baseline. What should the project manager do?
Show answer and explanation
Correct answer: C
On a predictive ERP project, a change request under review would change the completion date in the schedule baseline. The question asks what the project manager should do.
Once approved, the schedule baseline can be changed only through formal change control procedures. The project manager must first assess the effect of the change on the schedule and obtain approval through the Assess and Implement Changes process; after approval, the change is carried into the schedule baseline. The core of this question is the sequence: assess the impact, submit the change, get it approved through the Assess and Implement Changes process, update the baseline. No step can be skipped, and any option that bypasses approval is wrong. The answer is C.
Why the other options are wrong
- A. The baseline can be modified only through formal change control. Changing first and filing afterward violates the procedure.
- B. Leaving the baseline as is and writing the new date only in a report means the change has not gone through assessment, approval and baseline update, so the handling is incomplete. The baseline should stay unchanged until approval and be updated after it.
- D. Crashing is one means of dealing with variances, but the change is already known to alter the date, so it should be assessed and put through the approval procedure; the team cannot be assumed to absorb it.
Key takeaway A change that affects the schedule baseline: assess first, get approval, then update the baseline.
Variation If the project uses Scrum, change control is more flexible, but the impact still has to be assessed and the Product Owner reorders the Product Backlog; other adaptive methods follow their own governance and change mechanisms.
Something wrong with this question?
Example 2 Concept check: a document for the customer that lists only the main dates
The project schedule is ready for approval. The project manager needs to prepare a document for the customer representative that lists only the planned dates of the main deliverables and key external interfaces. Which of the following should be prepared?
Show answer and explanation
Correct answer: D
The schedule is awaiting approval. The project manager must prepare a document for the customer representative listing only the planned dates of the main deliverables and key external interfaces.
The PMBOK 8 glossary defines the milestone schedule as a type of schedule that presents milestones with planned dates, and the Gantt chart as a bar chart of schedule information. Common exam practice divides the schedule by level of detail into milestone, summary and detailed forms; a milestone schedule marks only the planned dates of the main deliverables and key external interfaces, which suits reporting to a customer. For this kind of question, look at the purpose of the document and its reader first: for a customer who needs only the main dates, use milestones; for management tracking progress, use a bar chart; to show the relationships between activities, use a network diagram. The answer is D.
Why the other options are wrong
- A. A Gantt chart uses horizontal bars to show each activity's planned start, finish and duration. It is more detailed than a milestone schedule that lists only the main dates, and it is often used to track activity progress for management.
- B. A detailed schedule network diagram shows the detailed logical relationships between activities. It is not a report that gives a customer the main dates.
- C. A work breakdown structure breaks the project scope down level by level by deliverable. It does not show planned dates.
Key takeaway Milestone schedule for the customer; bar chart for management; network diagram for activity relationships.
Variation If the customer wanted to see a bar for each work package's planned start and finish, use a Gantt chart (a bar chart of schedule information, per the PMBOK 8 glossary).
Something wrong with this question?
Common traps
Common trap
- The schedule baseline is not the project schedule. The baseline is the approved version, and changes to it go through change control; the project schedule is updated as work progresses.
- An unapproved draft cannot serve as the baseline. Establishing the baseline for the first time is approved by the sponsor or authorized stakeholders under the governance arrangements, and it is not a change to an existing baseline.
- For a scope change, evaluate its effect on the schedule and other baselines before approval. If it is approved and affects the approved schedule baseline, update the schedule baseline through the formal change control procedure; changing only the project schedule is not enough.
- The risk register and project calendars are project documents, not baselines. The baselines are the schedule, cost and scope baselines.
- A milestone schedule is often used for high-level communication, a bar chart shows activity timing at a glance, and a network diagram supports analysis of logical relationships. Choose the form by the stakeholders' information needs and do not swap them.
Key takeaways
Key point
- The schedule baseline is the schedule model approved by stakeholders, with baseline start and finish dates, used for comparison with actual results. It can be changed through formal change control procedures (usually stricter on predictive projects, more flexible on adaptive and agile projects, which may even have no formal procedure).
- Contingency reserve is included in the schedule or cost baseline and can be used within established authority. Management reserve is not in the baseline; PMBOK 8: typically released at the discretion of senior leadership or management; common exam practice: use goes through change control.
- The schedule, cost and scope baselines together form the performance measurement baseline.
- Three common forms: milestone (high-level communication), summary bar chart (timing at a glance), detailed schedule (network diagram, for analyzing logic).
- Schedule data includes milestones, activities, activity attributes, assumptions and constraints, and is often supplemented by resource histograms and alternative schedules.
Lesson 2
Monitor and Control Schedule: Inputs, Tools, and the Focus for Predictive and Adaptive Projects
Lesson overview
Once the schedule baseline is in place, the project moves into execution, and the Monitor and Control Schedule process has to run continuously: understand actual progress, update the schedule, manage changes, and keep the schedule realistic and executable. This lesson covers the definition and key benefit of Monitor and Control Schedule, its main inputs, tools and techniques and outputs, what predictive and adaptive projects each focus on, and how to handle scenarios such as a team that lacks confidence in the dates or schedule data that is inaccurate. It ties the techniques of earlier chapters together: the critical path method recalculates paths, resource optimization and schedule compression adjust the schedule, and earned value analysis measures variances. ECO: Process domain, Task 8 (Plan and manage schedule), which includes executing the schedule management plan, and Task 9 (Evaluate project status).
What Monitor and Control Schedule is
Monitor and Control Schedule is the process of monitoring the status of the project to update the project schedule and managing changes to the agreed-upon schedule. Updating the schedule requires knowing the actual or forecasted performance to date. The key benefit of this process is maintaining a realistic schedule throughout the duration of the project.
The main inputs, tools and techniques, and outputs can be summarized as follows:
| Category | Contents |
|---|---|
| Inputs | Project management plan (schedule management plan, scope baseline, performance measurement baseline, which integrates the scope, schedule and cost baselines), project documents (project schedule, schedule data, resource calendars, risk register, lessons learned register and others), work performance data, product backlog, enterprise environmental factors, organizational process assets |
| Tools and techniques | Data analysis (earned value analysis, burnup or burndown charts, performance reviews, trend analysis, variance analysis, what-if scenario analysis), critical path method, critical chain method, project management information system, resource optimization, leads and lags, schedule compression, velocity, daily coordination meeting, Sprint review, backlog refinement and others |
| Outputs | Work performance information, schedule forecasts, change requests, project management plan updates (schedule management plan, schedule baseline, cost baseline, performance measurement baseline), project document updates |
You can see that the techniques covered in the earlier chapters of this topic are all used again in monitoring. Earned value analysis supplies the variance figures: schedule variance SV = EV − PV and schedule performance index SPI = EV ÷ PV. Trend analysis uses the data so far to project what the schedule will do if the current trend continues, which answers "how much delay do we expect?" Schedule forecasts are estimates or predictions of conditions and events in the project's future based on information and knowledge available at the time the schedule is calculated; they are updated and reissued as work performance is obtained during execution.
Example: a schedule forecast from variance and trend
A project has a planned duration of 120 days. At day 60, planned value PV = $50,000 and earned value EV = $40,000.
Step 1: Schedule variance. SV = EV − PV = 40,000 − 50,000 = −$10,000. A negative value means behind schedule.
Step 2: Schedule performance index. SPI = EV ÷ PV = 40,000 ÷ 50,000 = 0.8. As of the data date, each unit of planned value has earned only 0.8 of a unit, so the project is behind its plan.
Step 3: Trend forecast. If the current trend continues, completion takes about 120 ÷ 0.8 = 150 days, about 30 days later than the baseline. This is a common trend extrapolation and is only an estimate.
Step 4: Next step. The numbers only say "behind"; they do not say "why". Do a cause analysis first, then see whether the variance has exceeded the control threshold, and decide whether to compress, optimize resources or submit a change request (next lesson).
What predictive and adaptive projects focus on
What each kind of project focuses on when monitoring the schedule
- Predictive: determining the status of the project schedule; influencing the factors that create schedule changes; reconsidering necessary schedule reserves; determining if the overall project schedule has changed; and managing the actual changes as they occur. A change to the baseline or agreed-upon schedule can be approved only through the Assess and Implement Changes process.
- Adaptive: determining the status of the schedule by comparing the total amount of work delivered and accepted against the estimates of work completed for the elapsed time cycle; conducting retrospectives to record lessons learned and improve processes; reprioritizing the remaining work plan (the backlog); determining the rate at which deliverables are produced, validated and accepted (velocity) in the given time per iteration (typically 2 weeks or 1 month); and managing the actual changes as they occur.
- For work that has been contracted, regular and milestone status updates, status reviews and walkthroughs are used to make sure the contractor's reports are accurate and complete and the schedule is under control.
When an adaptive project monitors the schedule, the emphasis is on measuring the amount of work delivered and accepted, not activities on a calendar. It can be counted in units that suit the team, such as story points or the number of work items, and shown with velocity and burnup or burndown charts.
Keeping the schedule realistic
Two kinds of scenario questions relate to this. One is that after the schedule is published, the team lacks confidence in the dates and nobody wants to commit. Estimates should come from the people most familiar with the activities, so the remedy is to review the estimates together with the team, work out a schedule everyone agrees with, and obtain their commitment. Forcing sign-off, padding the whole schedule with buffer, or having the sponsor apply pressure does not solve the problem. The other is that the progress data in the weekly report is inaccurate, for example completed activities still show as in progress. Then first verify and update the data, because every variance analysis rests on accurate data.
Worked examples
Example 1 Scenario: reporting an expected delay to the sponsor
An online education platform development project is in the execution stage. A personnel change at the top of a partner organization has put decisions on hold, and the project needs to speed up. The sponsor asks the project manager to report the expected delay. Which tool should the project manager use to prepare this report?
Show answer and explanation
Correct answer: D
In the execution stage, a personnel change at the top of a partner organization has put decisions on hold, and the sponsor asks for a report on the expected delay. The question asks which tool to use.
Trend analysis uses the performance data so far to project what the schedule will do if the current trend continues, so it is used to forecast a future delay and fits the request for the “expected delay”. Words such as “expected”, “likely” and “if things continue like this” are signals of forecasting and point to trend analysis and forecasting techniques, while “why” and “cause” point to root cause analysis. The output of trend analysis is a schedule forecast, which can be used directly to report to the sponsor how much later completion is expected, and to give a basis for deciding later whether to compress; that is exactly the “expected delay” the stem asks for. The answer is D.
Why the other options are wrong
- A. Root cause analysis finds the causes of problems that have already happened. It cannot predict whether later delays will occur.
- B. A quality report reflects quality problems and improvement recommendations. It has nothing to do with forecasting schedule delays.
- C. A milestone list gives milestones and their dates. It is planning information, and later delays cannot be worked out from it.
Key takeaway To predict whether later progress will slip: trend analysis; to find the cause of a problem that already happened: root cause analysis.
Variation If you needed to analyze “why the design phase used up so much time”, use root cause analysis, not trend analysis.
Something wrong with this question?
Example 2 Scenario: the team is unwilling to commit to the dates
After the schedule of a customer service system upgrade project is published, the project manager finds that the development team lacks confidence in the delivery dates and nobody is willing to commit to them. What should the project manager do?
Show answer and explanation
Correct answer: A
The schedule has been published, the development team lacks confidence in the dates, and nobody is willing to commit.
Estimates should come from the team members who know the activities best, because only then is the schedule realistic and executable. The project manager should review the estimates together with the team, work out a feasible schedule, and let the team form its commitment through participation. The credibility of a schedule comes from participation: when the people who know the work best give and accept the estimates, someone owns the plan. Forced signatures, padding everything with buffer and pressure from above all avoid the root question of whether the estimates are realistic. Only by going back to the estimates and involving the team can the commitment truly take hold. The answer is A.
Why the other options are wrong
- B. A signature is a forced formal commitment, but the team still does not accept the plan itself, so the problem is not solved.
- C. Pushing everything back without analyzing the cause has no basis and may not meet the sponsor's expectations; if the dates are already approved, it may also require a baseline change.
- D. Pressure from the top down does not increase confidence, and dates the team does not accept still cannot be put into effect.
Key takeaway To get a real commitment to the schedule, work out a feasible schedule together with the team.
Variation If the review confirms the estimates are reasonable and the dates are still tight, the next step is to evaluate compression options rather than keep demanding commitment.
Something wrong with this question?
Common traps
Common trap
- Trend analysis predicts the future, while root cause analysis finds the causes of problems that have already happened. They answer different questions.
- A milestone list is planning information. You cannot project later delays from it.
- Monitoring the schedule is not just looking at whether you are behind: you have to update the schedule and manage changes.
- Adaptive projects usually do not use baseline dates of individual activities as the main basis for monitoring. They compare the amount of work delivered and accepted with what was expected for that time cycle, and watch velocity, while still monitoring necessary milestones and date commitments.
- Schedule performance means comparing actual results with the applicable plan basis, not a verbal summary: predictive projects usually compare against the schedule baseline or agreed-upon schedule, and adaptive projects compare the amount of work delivered and accepted with what was expected for that time cycle.
Key takeaways
Key point
- Monitor and Control Schedule: monitor the project status to update the schedule and manage changes to the agreed-upon schedule, keeping the schedule realistic and executable.
- Tools: earned value analysis, trend analysis, variance analysis, what-if scenario analysis, burnup or burndown charts, plus the critical path method, resource optimization and schedule compression.
- SV = EV − PV and SPI = EV ÷ PV; use trend analysis to predict the future.
- Predictive projects look at status, reserves and changes; adaptive projects look at the amount of work delivered, velocity and backlog priority.
- When the team lacks confidence: review the estimates with the team and get their commitment.
Lesson 3
Variance Analysis and Schedule Changes
Lesson overview
Monitoring finds that actual progress does not match the baseline: what happens next? This type of scenario question is heavily tested on the exam. There is only one main line of reasoning: analyze first, then act, compare with the control threshold before acting, and go through change control when the baseline has to change. This lesson expands that main line into four steps (common exam practice), and covers what variance analysis does, schedule forecasts, how to use control thresholds and schedule baseline updates, and explains which actions are the typical "act first, analyze later" mistakes. ECO: Process domain, Task 8 (Plan and manage schedule) and Task 9 (Evaluate project status), and Business Environment domain, Task 3 (Manage and control changes) and Task 4 (Remove impediments and manage issues).
Variance analysis and schedule forecasts
Variance analysis is a technique for determining the cause and degree of difference between the baseline and actual performance. It compares actual schedule with the baseline and answers "how far off, and why?" It works together with earned value analysis (SV, SPI), trend analysis (what the schedule will do if the current trend continues), what-if scenario analysis (what happens if a condition changes) and burnup or burndown charts (in adaptive projects, completed and remaining work over time). A schedule forecast is an estimate of the project's future conditions based on currently known information and performance trends, updated and reissued as work is executed. When the forecast finish date is later than the baseline, you can evaluate schedule compression measures such as crashing and fast tracking; resource optimization can be used to deal with a delay and also to resolve over-allocation and uneven resource supply and demand.
How to do it: analyze first, compare with the control threshold, and go through change control if needed
After a variance is found, the usual order of handling in exam practice is as follows (this is an order for answering questions):
- Analyze the cause first. Discuss and assess with the team what caused the delay, or run a root cause analysis, and find out which critical path activities are behind and why. Do not immediately add resources, cut scope or report upward.
- Compare with the control threshold. The schedule management plan sets the maximum schedule variance allowed before action is taken. If the variance is inside the threshold, keep monitoring as the schedule management plan says, and the project manager may use judgment within authority. When it reaches or exceeds the threshold, take the action the schedule management plan prescribes, and escalate through governance when it goes beyond the project manager's authority or meets established escalation criteria.
- If the baseline must change, go through change control. If a corrective action would change the schedule baseline, submit a change request, approved through the Assess and Implement Changes process. A schedule baseline update is a modification to the original schedule baseline. It is necessary when significant changes occur that affect the project's timing, and it should be formally integrated into the plan.
- Update and communicate. Update the project schedule and the schedule forecasts, and report to stakeholders.
Example: two ways to handle a deviation inside and outside the control threshold
A project's baseline duration is 120 days, and the schedule management plan sets the control threshold at ±5%, that is, ±6 days.
Case 1: trend analysis predicts completion 4 days later than the baseline. 4 is less than 6, so it is inside the threshold. The project manager first finds the cause and keeps monitoring as the schedule management plan says; if action is needed, the project manager takes corrective action within authority, for example crashing critical path activities. The baseline does not change.
Case 2: the forecast completion is 9 days later than the baseline. 9 is more than 6, so it exceeds the threshold. Take the action the schedule management plan prescribes, and escalate through governance when necessary (beyond the project manager's authority or meeting the escalation criteria). If the final decision is to resolve it by extending the duration, submit a change request and, once approved, update the schedule baseline to 129 days.
Check. 120 × 5% = 6 days; 4 < 6 and 9 > 6, so the two treatments match the two cases. After the baseline is updated, the next round of variance analysis uses 129 days as the new reference.
Example: which baseline is updated first after an approved change
After a project's baseline was approved and execution had begun, a stakeholder worried that business permit processing would run late. A subject matter expert suggested allowing a longer period for the permit activity, and the change control board approved it. The change alters the timing; the work content and cost are unchanged. So the first thing to update is the schedule baseline, not the scope baseline or the cost baseline. The risk register records risk information and can be updated afterward.
The common "act first, analyze later" mistakes
The wrong options in exam questions on handling a deviation tend to follow a pattern: crashing, adding resources or requesting contingency reserve before the cause is understood; adding float to the entire plan; reporting to the sponsor or senior management as soon as a deviation appears; changing the baseline first and filing the change request afterward; writing the new date only in the status report without assessing the impact or going through change procedures. The correct options are usually actions of the "understand first, then decide" kind, such as "discuss with the team and assess the causes", "run a root cause analysis", "identify the critical path and the lagging activities and find out why", and "review the project management plan and assess the impact of the delay". When a delay is expected but has not happened yet, also assess the impact first and do not crash in advance.
Worked examples
Example 1 Scenario: the design phase is badly overrun and the customer worries about overall delay
The design phase of a factory MES implementation project is taking far longer than planned, and the main stakeholders on the customer side worry that the whole project will be late. What should the project manager do?
Show answer and explanation
Correct answer: B
The design phase has used far more time than planned, the customer side worries that the whole project will be delayed, and the question asks what the project manager should do.
When a variance appears, analyze the cause first and then decide what to do. A root cause analysis workshop can establish why the design phase is slow, so corrective action can address the real problem. The common pattern in variance scenario questions is to find the cause first and then act; here only root cause analysis meets the “analyze first” test, and the other three all act before the cause is understood. Any measure taken before the cause is found may spend cost on something that is not the problem. Once the cause is found, use the control threshold to decide whether action is required and the project's governance and authority limits to decide whether to escalate, and go through change control if necessary. The answer is B.
Why the other options are wrong
- A. Crashing without knowing why the work is slow easily causes quality problems or new risks.
- C. Adding float does not solve a delay that has already happened, and the cause has not been identified.
- D. Contingency reserve is for identified risks, and the stem does not say this delay is an identified risk.
Key takeaway After a variance appears, analyze the cause first; do not go straight to crashing, adding reserve or adding resources.
Variation If the analysis finds that the cause is a shortage of resources on the critical path, then consider crashing; if the variance exceeds the control threshold, action is required, and it goes up through governance if it is beyond your authority.
Something wrong with this question?
Example 2 Scenario: which document to update first after an approved change
A coffee chain is opening its first store in Southeast Asia. After the schedule baseline was approved and the project entered execution, a stakeholder worried that local business permit processing would be delayed. A subject matter expert reviewed this and recommended allowing more time for the permit activity, and the change control board approved the recommendation. Which document should the project manager update FIRST to record this change?
Show answer and explanation
Correct answer: C
On a predictive project, the schedule baseline is approved and the project is in execution. The change control board has approved an adjustment that allows more time for the business permit activity. The question asks which document to update first.
The change allocates more time to the permit activity, so what it changes directly is the schedule. When an approved change affects a baseline, the schedule baseline is updated so that it matches the approved plan. For questions of the type “a change was approved, what is updated first”, look at what kind of content the change alters: timing maps to the schedule baseline, work content to the scope baseline, and funding to the cost baseline. Note also that a baseline update must be formally integrated into the project management plan, and changing only the project schedule is not enough; approval comes first and the update after it, and the updated baseline becomes the new reference for later variance analysis. The answer is C.
Why the other options are wrong
- A. The work content has not changed, only the timing, so the scope baseline is unaffected.
- B. The risk register records risks, but here the change has been approved and what needs recording is the change in timing. Risk information can be updated afterward but is not the first document to update.
- D. The stem mentions no change in cost, so the cost baseline should not be the first thing updated.
Key takeaway An approved change that alters the timing: update the schedule baseline.
Variation If the change also added a paid expedited service, the cost baseline would have to be updated at the same time.
Something wrong with this question?
Common traps
Common trap
- When a deviation appears, analyze the cause first. Do not immediately crash, add resources, cut scope or request reserves.
- A deviation within the control threshold is handled under the schedule management plan and authority; at or beyond the threshold, take the action the plan prescribes and escalate if it goes beyond your authority.
- To change the schedule baseline, you must submit a change request and update it only after approval. You cannot change first and file afterward.
- A baseline update must be formally integrated into the project management plan; changing only the project schedule is not enough.
- When an expected delay has not happened yet, review the plan and assess the impact first rather than crashing directly.
- Whether a deviation affects the finish date depends on its effect on the critical path, total float and near-critical paths: first find the lagging activities on the critical path; a deviation on a non-critical path that exceeds its total float will also delay completion.
Key takeaways
Key point
- The four steps for handling a deviation (common exam practice): analyze the cause first, compare with the control threshold, go through change control if the baseline must change, and finally update and communicate.
- A deviation inside the threshold is monitored as planned and handled within authority; beyond it, take the action the schedule management plan prescribes and escalate if necessary.
- A schedule baseline update modifies the original baseline, and once a significant change that affects the schedule is approved it must be formally integrated into the plan.
- An approved change that alters the timing updates the schedule baseline first.
- When the schedule forecast is later than the baseline, you can use it to evaluate responses such as schedule compression; resource optimization can also resolve resource supply and demand, over-allocation or uneven use.
This chapter has 24 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.