Finance

Estimate Costs

PMP · Finance · 3 lessons · about 37 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

The upfront cost-estimating work covered in this chapter goes in two steps: set the rules first, then estimate item by item. Plan Financial Management defines how project revenues and expenses will be estimated, budgeted, managed, monitored and controlled, and produces the financial management plan and the funding strategy. Estimate Costs develops an approximation of the cost of the resources needed to complete project work. It answers "how much money does the project need?" and outputs the cost estimates and the basis of estimates, along with project document updates (for example updates to the assumption log, the lessons learned register and the risk register). This chapter covers the two processes together: first what the financial management plan says, where the money comes from, and how estimate accuracy narrows as the project progresses; then how to choose among four estimating methods; and finally why the basis of estimates is valuable and which factors make an estimate change.

By the end of this chapter you should be able to do the following. State what the financial management plan should and should not contain, tell accuracy from precision, and recognize control thresholds. List the common funding strategies and tell a funding strategy from a funding proposal. State the reference ranges and the right timing for the rough order of magnitude estimate and the definitive estimate (the names used in common exam practice). Choose analogous, parametric, bottom-up or multipoint estimating from the signals in a question, and calculate the triangular and beta distributions. Explain what the basis of estimates is for, list the factors that affect estimates, and respond correctly when an estimate is challenged or an omission is found.

Lessons in this chapter

Chapter map

Plan Financial Management -> financial management plan (rules: units of measure, accuracy, precision, control thresholds, rules of performance measurement, reporting formats)
                          -> funding strategy (where the money comes from); (Monitor and Control Finances also produces funding proposals: a dedicated funding request based on estimated costs, reserves and the business value proposition)  
Estimate Costs            -> accuracy (common exam reference values): rough order of magnitude -25% to +75% -> definitive estimate -5% to +10%
                          -> methods: analogous / parametric / bottom-up / multipoint (triangular / beta)
                          -> outputs: cost estimates + basis of estimates (plus project document updates)  
                          Influencing factors: schedule, risk, resources, quality; life cycle cost  

How the exam tests this

Questions in this chapter are mostly concept and scenario judgments, with very little calculation. Common formats include: "Which of the following is NOT part of the financial management plan?" (the answer is the option with specific amounts); an estimate range or "just started, little information" is given and the question asks for the estimate grade; a scenario is given and you pick the estimating method by its signal words; when the sponsor challenges an estimate, the answer is to retrieve and explain the basis of estimates; when asked how an omission should have been avoided, the answer is historical information and expert review; when an omission is found during execution, analyze the impact first and then handle it through the change control mechanism. Multipoint estimating occasionally tests a one-step calculation, so keep the triangular and beta distributions apart.

Study tips and practice

  • Write the signal words of the four estimating methods on a small card, and circle the signal words in the stem before choosing.
  • Work through the triangular and beta calculations twice each by hand, and remember that in the beta distribution (PERT) the most likely value has a weight of 4, while the triangular distribution weights all three equally.
  • This chapter connects closely to the next chapter, "Cost baseline and reserves": estimates may be presented at the activity level or in aggregate form, and only after they are aggregated, distributed over time and approved do they become the baseline (contingency reserve is included in the baseline in the common case, and PMBOK 8 also allows an organization to place it outside the baseline; management reserve is outside the baseline). Do not mix them up too early.
  • After the practice for this chapter, read through the table of financial management plan contents again until you can recite it without looking at your notes.

Lesson 1

The Financial Management Plan, Funding Strategies and Estimate Accuracy

Lesson video

Lesson overview

Financial management starts by setting the rules and then applying them: where does the money come from, how accurate must the estimates be, and how large a variance must be reported? The Finance performance domain in PMBOK 8 has four processes: Plan Financial Management, Estimate Costs, Develop Budget, and Monitor and Control Finances. This lesson covers the starting point of the first two: the financial management plan and funding strategy produced by Plan Financial Management, and the units and accuracy you need to settle before estimating costs. The next two lessons cover estimating methods and the basis of estimates. ECO: Process domain, Task 6 (Plan and manage finance), covering analyzing financial needs and planning financial reporting.

Plan Financial Management: set the rules first

Plan Financial Management is the process of defining how the project revenues and expenses will be estimated, budgeted, managed, monitored, and controlled. It is performed once up front or at predefined points in the project. It has two main outputs: the financial management plan and the funding strategy. PMBOK 8 places this work in the Finance performance domain, which covers, besides cost, where the money comes from, financial constraints, and how the value the project creates is measured.

First get the positioning right: the financial management plan answers "how do we manage money", not "how much money is it". It is the same kind of document as the scope management plan and the schedule management plan: it records rules, formats and methods, while the specific amounts are recorded, by purpose, in artifacts such as the cost estimates, the cost baseline and the project funding requirements. Content that is a rule belongs in the plan; specific cost figures and funding schedules do not. When an exam question asks "which of the following is NOT part of the financial management plan", decide by this rule.

ContentDescription
Units of measureThe unit used to measure each resource, for example labor in staff days, materials in tons or kilometers
Level of accuracyThe acceptable range for activity cost estimates, such as ±10%, which may include an amount for contingencies
Level of precisionTo what digit the estimate is rounded, depending on the scope of the activities and the size of the project
Control thresholdsThe maximum cost variance allowed before action is taken, often expressed as a percentage deviation from the baseline
Rules of performance measurementHow earned value management and other performance measurement methods are to be used
Reporting formatsThe formats and frequency of the various cost reports
Additional detailsStrategic funding choices, the procedure for fluctuations in currency exchange rates, and the procedure for recording project costs

Accuracy and precision are the most easily confused. Accuracy asks "how far may the estimate be from the true value", and precision asks "to which digit is the number written". An activity estimated at "$18,600" has very high precision, but if it actually cost $25,000, its accuracy was poor. "±10%" in a stem means accuracy; "rounded to the nearest thousand" means precision. A control threshold is the maximum variance allowed before action is taken: it defines how large a variance has to be before action is required, while whether to escalate also depends on project governance and authority rules. You will use it again in the lesson on Monitor and Control Finances.

Funding strategies and funding proposals

A project's money may come from inside the performing organization or from outside, and one project may use several approaches. Any single approach or combination of approaches can be considered a funding strategy. There are seven common ones:

  • Fixed or reallocated internal budgets: paid for by a department's annual budget, or by moving in surplus funds from other budgets or from lower-priority initiatives.
  • Lump sum: the entire budget, reserves included, is allocated at once.
  • Incremental disbursement: funds are secured and allocated in several increments, specific to individual phases or key milestones.
  • External investment: individual or institutional investors provide capital, often in exchange for interest in long-term ownership or operations, which suits early-stage or innovative projects.
  • Governmental or nongovernmental organization (NGO) grants: dedicated funding, provided the project aligns with the grantor's objectives.
  • Crowdfunding: small contributions from a large number of individuals, particularly effective for projects with strong community appeal.
  • Client contract: the performing organization delivers as a vendor to a customer and is paid under the contract.

The Monitor and Control Finances process may also produce funding proposals (they are not an output of Plan Financial Management). Projects often require dedicated funding efforts before or after the project starts, and certain phases may require specific funding requests to cover the approved budgets of that phase. In these cases, estimated costs and reserves are calculated as part of a business value proposition, and the value proposition is then used to request the needed funds from the appropriate internal or external funding source. The distinction is simple: the funding strategy settles "where the money comes from"; the project funding requirements state when and how much funding is needed (derived from the cost baseline); a funding proposal uses the approved budget and the business value proposition to ask the funding source for those funds. PMBOK 8 also stresses that project managers are often asked to lead or support funding efforts before or during a project, so you need to manage costs and also be able to explain why the project deserves the funding.

Units and accuracy of estimates

Cost estimates are usually expressed in currency units. Sometimes effort is first estimated in non-monetary units such as staff days, which removes the effect of currency fluctuations and eases comparison, and converted into money at unit rates when the budget is prepared, so that unit price changes do not disturb the effort estimate. What is estimated is all the resources that will be charged to the project: labor, materials, equipment, services and facilities, as well as special items such as inflation allowances, financing costs and contingency costs.

The accuracy of an estimate improves as the project progresses; this is progressive elaboration. Right at the start, there is little scope and little detail, so only a wide range can be given; as requirements, design and supplier quotes become clear, the range narrows.

Figure 1 Cost estimate ranges narrow as the project progresses

The financial management plan sets the acceptable range for cost estimates, and accuracy increases as information increases. The grade names and ranges in the table below are common exam practice; actual ranges are set by the organization and the financial management plan:

Estimate type (common exam name)Accuracy range (common exam reference values)When it applies
Rough order of magnitude (ROM)−25% to +75%Initiation, very little information
Definitive estimate−5% to +10%Sufficient information, a precise number is needed

Example: using the range

A pharmacy chain wants to migrate its store inventory system to a new platform. At initiation the team has only a one-page requirements document and gives a rough order of magnitude estimate of $80,000.

  • Lower limit: 80 × (1 − 25%) = $60,000. Upper limit: 80 × (1 + 75%) = $140,000. The true cost may fall anywhere between $60,000 and $140,000.
  • Once the detailed design and supplier quotes are in hand, the team gives a definitive estimate of $96,000, and the range narrows to 96 × 0.95 = $91,200 up to 96 × 1.10 = $105,600.
  • What management receives at initiation is an order of magnitude, not a commitment.

The signal for this point on the exam is: the project has just started, there is no similar past project, the scope is uncertain, and leadership wants a high-level budget number. Analogous estimating needs a similar project, parametric estimating needs historical data, and bottom-up estimating needs detailed information; none of the three is available at this point, and when information is insufficient you can usually produce only a rough order of magnitude estimate (ROM is a grade of accuracy; when there is no similar project or historical data, the specific technique relies mainly on expert judgment, and only once a similar project or historical data exists can analogous or parametric estimating be used). Common exam practice: when the question asks about the estimate grade, choose ROM; when it asks about the estimating technique, decide from conditions such as the available historical material. Hold on to the three conditions "just started", "insufficient information" and "uncertain scope".

Worked examples

Example 1 Core question type: what belongs in the financial management plan

Question 1Example

The project manager of an e-commerce company is drafting the financial management plan, and the team disagrees about what the plan should contain. Which of the following is NOT usually specified in the financial management plan?

Show answer and explanation

Correct answer: C

The project manager is drafting the financial management plan and the team disagrees about its contents. The task is to find the item that is not part of the financial management plan.

The financial management plan answers “how do we manage money”, and records the rules for estimating, budgeting and monitoring: units of measure, accuracy, precision, control thresholds, rules of performance measurement, reporting formats and so on. Rule-type content belongs in the plan, while specific amounts and disbursement dates do not. The financial management plan sets out the methods and rules for managing finances and funding strategies, and does not record the specific amounts and arrival dates for each phase; those figures and timings are derived from the cost baseline and the funding requirements. Option C is about the specific amounts and arrival dates for each phase, so C is not part of the financial management plan. The answer is C.

Why the other options are wrong

  • A. Control thresholds determine how large a variance must be before action is required. They are standard content of the plan, so they belong in it, and this is not the answer.
  • B. Accuracy (the acceptable range) and precision (the digit to which values are rounded) are both written in the plan, so they belong in it, and this is not the answer.
  • D. How to use earned value management and other performance measurement methods is also among the rules of performance measurement in the plan, so it belongs in it, and this is not the answer.

Key takeaway The financial management plan states rules, not specific amounts or disbursement dates.

Variation If the option read “the acceptable range for activity cost estimates is ±10%”, that is accuracy and belongs in the plan; if it read “$80,000 of funding is needed in the third quarter”, it is still a specific amount and does not belong in the plan.

Something wrong with this question?

Report an issue with this question

Example 2 Calculation and judgment: deciding the estimate grade from the range

Question 2Example

A consulting firm's project manager reports to the sponsor and executives at mid-project. The cost report gives a point estimate of $480,000 with an estimate range of $460,000 to $500,000. What level of estimate is this?

Show answer and explanation

Correct answer: C

The project is at mid-stage, and the cost report gives an estimate range of $460,000 to $500,000. The question asks which level of estimate this is.

The estimate grade is judged by the width of the range and the amount of information. A rough order of magnitude estimate is about −25% to +75% and is used early, when little information exists; a definitive estimate is about −5% to +10% and is used once information is sufficient (rough order of magnitude and definitive estimate are common exam grade names and the ranges are common exam reference values, all common exam practice). Here the point estimate is $480,000, and the range is about $20,000 above and below it, roughly ±4%, which falls within the definitive estimate range, and by mid-project information is already fairly complete. The answer is C.

  1. Point estimate = $480,000; lower limit $460,000, upper limit $500,000, each $20,000 away
  2. Deviation ÷ point estimate = 20,000 ÷ 480,000 ≈ 4.2%, a very narrow range
  3. For comparison: a rough order of magnitude estimate would be 480,000 × 0.75 to 480,000 × 1.75 = $360,000 to $840,000, far wider than the range in the question
  4. Check: a definitive estimate of −5% to +10% corresponds to $456,000 to $528,000, and the range in the question lies within it, so choose the definitive estimate

Why the other options are wrong

  • A. Rolling wave planning is a way of elaborating progressively as the project advances. It is not an estimate grade distinguished by accuracy.
  • B. A rough order of magnitude estimate centered on $480,000 would cover about $360,000 to $840,000, far wider than the range in the report.
  • D. Analogous estimating is a method that refers to similar past projects. It is not an estimate grade.

Key takeaway A range that is only a few percentage points wide with sufficient information is a definitive estimate; a very wide range with very little information is a rough order of magnitude estimate.

Variation If the report said “estimate $20,000; the actual may be between $15,000 and $35,000”, the range is −25% to +75% and it is a rough order of magnitude estimate.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The financial management plan states rules (units, accuracy, precision, thresholds, measurement rules, reporting formats) and does not state specific amounts; how much each phase needs and when it is disbursed are funding requirements, derived from the cost baseline.
  • Accuracy is "how far off", and precision is "to which digit it is written".
  • The range is asymmetric: for a rough order of magnitude estimate (the common exam name) it is −25% to +75%, so the upper limit is wider than the lower.
  • Estimates become more accurate later, but an early estimate is still required: give a range and explain to stakeholders that it is a range.
  • An estimate is not itself a baseline. The cost baseline is formed only after estimates are aggregated, distributed over time and approved. Contingency reserve is included in the cost baseline in the common case (PMBOK 8 also lets an organization place it outside the baseline by preference), and management reserve is not part of the cost baseline.

Key takeaways

Key point

  • The four processes of the PMBOK 8 Finance performance domain: Plan Financial Management, Estimate Costs, Develop Budget, and Monitor and Control Finances.
  • Outputs of Plan Financial Management: the financial management plan (the rules for managing money) and the funding strategy (where the money comes from). Funding proposals come from Monitor and Control Finances and are used to request the needed funds from internal or external funding sources; certain phases may submit specific funding requests to cover the approved budget of that phase.
  • A control threshold is the maximum variance allowed before action is taken, and it determines when action must be taken.
  • Accuracy increases as information increases. Rough order of magnitude −25% to +75% and definitive estimate −5% to +10% are common exam grade names and reference ranges; the more information, the narrower the range.
  • Stem signal: "just started, little information, want a rough number" means a rough order of magnitude estimate (common exam practice).

Lesson 2

Estimating Methods: Analogous, Parametric, Bottom-Up and Multipoint

Lesson video

Lesson overview

Cost estimating takes different shapes at different times: early on, you quote a number fast from experience; later, every work package has to be worked out, and activities with high uncertainty need their risk built in. Different situations use different methods, and almost every year the exam asks you to "read the stem and pick the method". This lesson explains how the four estimating methods work, their characteristics and when to use them, focuses on the two multipoint estimating formulas, and adds the relative estimating that adaptive projects use. ECO: Process domain, Task 6 (Plan and manage finance), analyzing the project's financial needs. The previous lesson covered accuracy ranges, and the next covers the outputs of estimating and the influencing factors.

Four estimating methods

Costs can be estimated in many ways. Expert judgment runs through all of them: asking experienced people for an estimate is itself expert judgment, and analogous estimating also contains an element of expert judgment. The exam mostly tests the differences among the four below.

MethodHow it worksCharacteristicsWhen to use
Analogous estimatingUse the actual cost of a similar past project to project the current oneTop-down, can be applied to a whole project or part of it; relies on expert judgment; quick, cheap, less accurateEarly in the project, when detailed information is insufficient and a result is needed quickly
Parametric estimatingBuild a model from the statistical relationship between historical data and other variables, such as "unit price × quantity"; regression analysis is a typical approachAccuracy depends on the quality of the model and the underlying dataReliable historical data and quantifiable parameters are available
Bottom-up estimatingEstimate each work package or activity first, then aggregate level by levelUsually higher accuracy, but time-consuming and costlierThe scope has been decomposed clearly and higher accuracy is needed
Multipoint estimatingCalculate from three values: optimistic, most likely and pessimisticTakes uncertainty and risk into accountThe item being estimated has considerable uncertainty

How do you remember them? Look at the signal words in the stem. "Based on similar past projects", "early", "very little information" and "need it fast" point to analogous estimating. "Statistical relationship", "parametric model" and "cost per data point" point to parametric estimating. "Aggregate by work package" and "need higher accuracy" point to bottom-up estimating. "Optimistic, pessimistic, most likely" and "high uncertainty" point to multipoint estimating. The difference among the four is essentially how much information is used: analogous uses only overall experience, parametric uses statistical regularities, bottom-up uses all the detail, and multipoint specifically handles uncertainty.

Example: network cabling for the same office building

  • Analogous: last year the company cabled a similar-sized office building in the same city for a total of $620,000. This building is slightly bigger, so adjust upward by 10% for an estimate of about $680,000. It takes a few minutes but is generally less accurate.
  • Parametric: historical data shows an all-in cost of about $480 per data point, and this building is designed with 1,300 data points: 1,300 × $480 = $624,000. If the unit price and the number of points are reliable, the result is more solid than the analogous one.
  • Bottom-up: estimate the work packages for cable, trays, racks, installation and commissioning one by one and add them up, giving $668,000. This takes the longest and is also the best documented.

Multipoint estimating

Multipoint estimating requires three values: optimistic (O), most likely (M) and pessimistic (P). PMBOK 8 calls it multipoint estimating: a method used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic and most likely estimates when there is uncertainty with the individual activity estimates. There are two ways to calculate it:

The triangular distribution is a simple arithmetic mean. The beta distribution is a weighted average in which the most likely value has the greatest weight. The beta distribution can also give a standard deviation: σ = (P − O) ÷ 6, which describes the spread of the estimate. The commonly used formula in PMBOK 8 is the triangular distribution (O+M+P)/3. Common exam practice: when the stem does not specify a distribution, use the beta distribution/PERT (O+4M+P)/6; when the stem explicitly says "triangular distribution" or "simple average", use the triangular distribution.

Example: the cost of racking equipment in a server room

For a server-room equipment installation task: optimistic $40,000, most likely $52,000, pessimistic $82,000.

  • Triangular distribution: E = (40 + 52 + 82) ÷ 3 = 174 ÷ 3 = $58,000.
  • Beta distribution: E = (40 + 4 × 52 + 82) ÷ 6 = 330 ÷ 6 = $55,000.
  • Standard deviation: σ = (82 − 40) ÷ 6 = $7,000, so 55 ± 7, that is, $48,000 to $62,000; if the question goes on to assume a normal approximation, the probability covered by the mean ±1σ is about 68%.
  • Check: the pessimistic value is farther from the most likely value, so the distribution is skewed to the right, and the triangular mean (58) is greater than the beta mean (55), as expected.

Estimating on adaptive projects

Estimating techniques commonly used on adaptive projects are story points, planning poker and T-shirt sizing. A story point is a unit for measuring all the work needed to complete a backlog item: the team picks a reference user story as the baseline and compares the other stories against it to estimate how many points each is; this is relative size estimation. Comparing sizes is usually more accurate and saves more time than predicting exact hours. Planning poker is based on wideband Delphi and works by consensus: everyone shows a card at the same time, the highest and lowest estimators explain their reasoning, and they play again until the estimates are close. Velocity is the number of story points a team completes in an iteration; it usually takes several iterations to stabilize, and because each team has a different reference story, story points cannot be compared across teams.

Other tools for estimating costs include alternative analysis, reserve analysis (setting aside contingency reserve for risk, covered in the next chapter), cost of quality, project management information systems, and decision-making techniques such as voting. Whatever the method, adaptive projects elaborate progressively: as new information appears, the team keeps refining the backlog and re-estimates the affected remaining work as needed; numbers given early should be marked with a range or their uncertainty and explained to stakeholders.

Worked examples

Example 1 Core question type: which method for a statistical relationship

Question 1Example

A project manager needs to estimate the development cost of a new mobile app. Based on years of accumulated data, the company has established a statistical relationship between the number of screens and the labor hours needed to develop each screen. Which estimating technique should be used to make use of this information?

Show answer and explanation

Correct answer: A

For the cost estimate of a new mobile app, the company's data accumulated over many years contains a statistical relationship between the number of screens and the labor hours per screen, and the question is which technique to use.

The deciding signals are “data accumulated over many years” and “statistical relationship”. Parametric estimating uses exactly the statistical relationship between historical data and variables to build a model (number of screens × hours per screen × hourly rate) and compute the cost; its accuracy depends on the quality of the model and the data. The answer is A.

Why the other options are wrong

  • B. Analogous estimating refers directly to historical data of a similar activity or project. It does not require building a statistical relationship among variables and would not compute from the number of screens.
  • C. Bottom-up estimating estimates each work package item by item and aggregates. It rests on the specific work content and not on a statistical relationship.
  • D. A rough order of magnitude estimate is a grade of accuracy (the exam reference range is −25% to +75%), not a technique that calculates from historical data.

Key takeaway When you see “statistical relationship, parametric model, unit price × quantity”, choose parametric estimating.

Variation If it said “refer to the total cost of another similar app last year and raise it by 10%”, that is analogous estimating; if it said “estimate the development task of each screen item by item and add them up”, that is bottom-up estimating.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario judgment: time is short and a similar project exists

Question 2Example

A robot development project has a tight schedule, and the customer wants to see a prototype on site in three weeks. The sponsor asks the project manager to use the data of a similar earlier project to produce a rough budget as quickly as possible so a delivery plan can be agreed with the customer. What method should the project manager use to estimate cost?

Show answer and explanation

Correct answer: C

A robot development project has a tight schedule, and the sponsor asks for a rough budget as quickly as possible, using the data of a similar earlier project. The question asks which estimating method to use.

The stem gives three signals: refer to the data of a similar earlier project, as quickly as possible, and rough. These are the features of analogous estimating: it projects from historical data of a similar past activity or project, top-down, at low cost and high speed but with lower accuracy, and it suits situations where detailed information is insufficient and a result is needed quickly. The answer is C.

Why the other options are wrong

  • A. Bottom-up estimating is usually more accurate, but it requires estimating each work package and aggregating level by level, which takes longer and does not fit “as quickly as possible” and “rough”.
  • B. Multipoint estimating uses optimistic, pessimistic and most likely values to handle uncertainty. The stem stresses reference to a similar project and speed and does not mention uncertainty.
  • D. Expert judgment is a source of opinion that runs through all methods. The stem says explicitly to use the data of a similar project, and analogous estimating corresponds to that more directly.

Key takeaway “Refer to a similar project, fast, rough”: analogous estimating.

Variation If a historical regression model of cost per square meter against area existed, choose parametric estimating; if accuracy down to each work package were required and more time were acceptable, choose bottom-up estimating.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Analogous estimating is fast but generally less accurate, parametric estimating depends on data quality, and bottom-up estimating is usually more accurate but the most time-consuming. Do not confuse "more accurate" with "fastest".
  • Analogous estimating is a top-down, gross-value approach that can be applied to an entire project or to part of one. Do not switch to "expert judgment" just because expert judgment was used.
  • When a multipoint estimating question does not state the distribution: the commonly used formula in PMBOK 8 is the triangular distribution (O + M + P) ÷ 3; common exam practice is to use the beta distribution/PERT (O + 4M + P) ÷ 6 when the stem does not specify a distribution; when the stem says "triangular distribution" or "simple average", use the triangular distribution.
  • The standard deviation of the beta distribution is (P − O) ÷ 6, not divided by 3.
  • Story points measure relative size, not hours, and story points from different teams cannot be compared.

Key takeaways

Key point

  • Analogous: refer to a similar project; early, fast, generally less accurate. Parametric: statistical relationship, unit price × quantity. Bottom-up: aggregate work packages, usually more accurate but time-consuming. Multipoint estimating: three values, handles uncertainty.
  • Triangular distribution E = (O + M + P) ÷ 3; beta distribution E = (O + 4M + P) ÷ 6, σ = (P − O) ÷ 6.
  • The PMBOK 8 commonly used formula is the triangular distribution; common exam practice: when the stem does not state a distribution, use the beta distribution (PERT), and when it says "triangular distribution" or "simple average", use the triangular distribution.
  • Adaptive projects use story points, planning poker and T-shirt sizing for relative estimating, and velocity cannot be compared across teams.
  • Estimating is progressively elaborated; numbers given early should be marked with a range or their uncertainty and explained to stakeholders.

Lesson 3

Cost Estimates, the Basis of Estimates and Influencing Factors

Lesson video

Lesson overview

Coming up with a number is not hard. The hard part is having something to show when others ask "how did you get this number?" The Estimate Costs process has two core outputs: the cost estimates and the basis of estimates (PMBOK 8 also lists project document updates, such as updates to the assumption log, the lessons learned register and the risk register). This lesson covers what each of the two outputs is, why the basis of estimates is valuable, and which factors make an estimate larger or smaller: schedule, risk, resources and quality, as well as life cycle cost, which PMBOK 8 stresses in particular. Scenario questions often ask "what do you do when a number is challenged" and "how do you avoid omissions", and the answers are in this lesson. The first two lessons covered accuracy and methods; this lesson closes out cost estimating, and the next chapter moves on to Develop Budget. ECO: Process domain, Task 6 (Plan and manage finance).

Two outputs: cost estimates and the basis of estimates

Estimate Costs is the process of developing an approximation of the cost of resources needed to complete project work, and it answers how much money the project needs. It has two core outputs.

Cost estimates are a quantitative assessment of the likely costs for resources required to complete an activity, and they can be given at the activity level or in aggregate form: how much a particular purchase costs, how much the labor for an activity costs. The estimate must cover all resources that will be charged to the project, including labor, materials, equipment, services and facilities, as well as inflation allowances, financing costs and contingency costs.

The basis of estimates is the supporting documentation that outlines the details used in establishing the project estimates, such as assumptions, constraints, levels of detail, ranges and confidence levels, and it should provide a clear and complete understanding of how an estimate was derived. It may include how the basis of estimate was developed, assumptions made, known constraints, the range of possible estimates (for example ±10%), the confidence level of the final estimate, and the individual project risks influencing the estimate. To make review, approval and later traceability possible, the cost estimates should be supported by a clear and complete basis of estimates.

The basis of estimates is often underrated. Imagine someone challenging a number six months later. Without the basis, you can only argue from memory; with it, you can check the assumptions and the range to determine whether the original estimate was flawed or the assumptions have changed. Then use the basis of estimates to verify the cause and update the estimate; if a cost baseline has already been established and the update would affect it, raise a change request. So when the sponsor has doubts about a number, the project manager's first reaction should be to produce the basis: historical information from similar projects last year, lessons learned, the method used and the assumptions, rather than redoing the work with a different estimating method or relying only on communication skills to persuade.

What affects estimates

Cost estimates do not stand alone; the other plans keep driving them to change. You can remember four aspects: schedule, risk, resources and quality.

  • Schedule: the duration of activities affects cost. Financing costs (interest) accumulate over the duration, overhead increases with duration, and material prices fluctuate with the seasons, so a change in duration can change cost.
  • Risk: risks affect cost. Responding to threats, buying insurance and setting aside contingency reserve usually require funds, and opportunity responses may also require investment and may bring cost savings or extra value. Contingency reserve should be determined from the probability, impact and overall exposure of the identified risks, using methods such as reserve analysis (it can be a percentage of the estimated cost, a fixed amount, or derived from quantitative analysis).
  • Resources: using one person or two on the same activity costs differently; cost estimating must be built on the resource requirements estimates.
  • Quality: stricter quality requirements may increase investment in prevention, equipment, inspection and testing while reducing failure costs such as rework, so the estimate should analyze the cost of quality comprehensively and look for a sensible balance. Raising the required pass rate from 95% to 99.9% usually increases prevention and appraisal spending noticeably.
  • In addition, make-or-buy decisions, work package estimates and the scope baseline are also inputs to estimating costs.

PMBOK 8 places special emphasis on life cycle cost. Every project decision may bring later costs of use, maintenance and support, and when estimating and comparing options you should consider the effect of those decisions on later use, maintenance and support costs; whether those costs are included in the project cost estimates depends on the project scope and the organization's financial boundaries. Limiting the number of design reviews can lower project cost but may raise the product's operating cost. This reminder often appears in "cost cutting" scenarios: when you compress project cost, ask what it means for life cycle value and later operations.

Example: the cost estimate for a customer appreciation event

A team is organizing a customer appreciation event: venue $9,000, catering $7,500, materials and decoration $2,500. The risk register has one identified risk: actual attendance may exceed the number registered, and $2,000 of contingency reserve is set aside for it.

  • Total activity cost: 9,000 + 7,500 + 2,500 = $19,000.
  • Add the contingency reserve: 19,000 + 2,000 = $21,000.
  • The basis of estimates must state the source of the unit prices for the venue and catering, the assumption that the estimate is based on the registered attendance, and the reason for the reserve for the attendance risk.
  • Check: if the schedule slips by a week and the venue charges $1,800 more rent for the extra week, the cost estimate must be updated to $22,800 at the same time, which is "schedule affects cost".

What to do when estimating goes wrong

Estimating scenario questions come in three common forms, and the reasoning differs for each.

First, a brand-new project with no historical data, where the customer nevertheless wants to see a preliminary estimate first. Give an estimate with a range, explain that it will be refined as information increases, and involve experts with relevant experience; you cannot refuse to estimate because "there is no data", and you cannot force out a number that looks precise.

Second, an estimate has been submitted and is challenged as too high. Let the basis speak: historical information, lessons learned, assumptions and ranges. First find out whether what is being challenged is the method, the data or the assumptions, and then respond to that.

Third, an omission is found during execution. Fix it afterward through a change; prevent it beforehand by referring to historical data and experience from similar projects when estimating and by inviting experts familiar with the technology to review. Reserves cannot replace a complete estimate: known required materials belong in the cost estimate and must not be deliberately left for contingency reserve to cover. If the possibility of an estimating omission is identified as a risk, manage it through the risk process.

Worked examples

Example 1 Scenario judgment: the sponsor challenges the estimate

Question 1Example

A project is very similar to one completed last year. The project manager asked the expert group from the previous project to produce a cost estimate using multipoint estimating and submitted it for approval to a newly appointed sponsor. The sponsor finds the number higher than expected and is worried about it. What should the project manager do?

Show answer and explanation

Correct answer: A

An expert group produced a cost estimate with multipoint estimating and submitted it for approval. The new sponsor finds the number high and is worried, and the project manager has to respond properly.

The sponsor is worried about the number itself, and the new project is very similar to last year's. What can answer the sponsor is the basis: pull up last year's historical information and lessons learned and explain how the new estimate was derived and how it compares with the historical data, so the number has a source and a comparison. The basis of estimates is the supporting documentation that lets the approver see how the number was derived, so let the basis do the talking. The answer is A.

Why the other options are wrong

  • B. Organizational process assets cannot tell you whether this estimate already includes contingency reserve; even if it does, you would still have to review the basis of estimates and the reserve analysis to show the number is reasonable, so that check alone does not answer the sponsor's concern.
  • C. Re-estimating bottom-up is a change of method, and the number is not necessarily lower; what the sponsor questions is not the method, and doing so also dismisses the expert group's work.
  • D. Relying on communication and negotiation alone without producing the basis does not solve the real problem. An estimate has to be defended with its basis, not with persuasion.

Key takeaway When an estimate is challenged, speak with historical information and the basis of estimates.

Variation If the sponsor questions the “unit price assumption for materials”, show the sources of the unit prices and the quote records; if the sponsor questions the “contingency reserve percentage”, show the risk register and the reserve analysis.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario judgment: how to avoid budget omissions in advance

Question 2Example

A company's server room renovation project is being implemented. The equipment engineer tells the project manager that, because of a technical misjudgment, several required materials were not included in the budget. How should the project manager have avoided this?

Show answer and explanation

Correct answer: B

The server room renovation is under way, and the equipment engineer says that a technical misjudgment left out required materials. The question asks how this should have been avoided, a judgment about prevention beforehand.

The wording “should have” points to a measure taken beforehand. The root of an omission is that the estimating stage did not identify all the materials and costs needed. When developing the estimate, referring to the experience and historical data of similar past projects helps identify materials and costs that were previously required and, among the given options, best reduces omissions at the source. The answer is B.

Why the other options are wrong

  • A. The sponsor is responsible for funding approval and high-level support and does not check materials detail, so cannot prevent an omission caused by a technical misjudgment.
  • C. Known required materials belong in the cost estimate, and excess reserves cannot substitute for complete estimating. Moreover, “coping with all uncertainty” is both unrealistic and ties up too much funding.
  • D. Updating the budget before the next phase is a remedy after the fact and does not meet the requirement of avoiding the problem in advance.

Key takeaway Avoid omissions by consulting historical data and similar projects beforehand, not by patching afterward and not by over-reserving.

Variation If the stem asked “what do you do after finding an omission”, the answer would become assess the impact and go through change control; if it asked “how can you confirm the estimate is complete”, check item by item against the WBS and have experts review it.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Cost estimates can be presented at the activity level or in aggregate form; Develop Budget aggregates the estimated costs of activities or work packages and establishes the approved cost baseline.
  • The basis of estimates is not an optional attachment: an estimate without a basis is hard to get approved and cannot be defended when challenged.
  • Schedule, risk, resources and quality all change cost; a change in duration may change time-accumulating financing costs, overhead and so on.
  • Reserves deal with uncertainty and cannot replace a complete estimate. Known required work belongs in the estimate and must not be deliberately left for reserves to cover.
  • An estimate is not a baseline. The cost baseline is formed only after estimates are aggregated, allocated over time periods and approved. Management reserve is not part of the cost baseline; contingency reserve is included in the cost baseline in the common case, and PMBOK 8 also allows an organization to place it outside the baseline by preference.

Key takeaways

Key point

  • The two outputs of Estimate Costs: the cost estimates and the basis of estimates; the basis of estimates records the assumptions, constraints and range.
  • When a number is challenged, respond with historical information, lessons learned and the basis of estimates.
  • Factors that affect estimates: schedule, risk, resources and quality, plus make-or-buy decisions.
  • PMBOK 8 stresses life cycle cost: when pushing project cost down, look beyond near-term spending and evaluate the effect on use, maintenance cost and life cycle value.
  • Avoid omissions by consulting similar projects and having experts review beforehand, not by patching afterward and not by over-reserving.

This chapter has 41 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.