What this chapter covers

The critical path method is the core of schedule calculation questions. You are given a network diagram with durations and asked for the total duration, the critical path, the early and late dates of a particular activity, and its total float and free float. It is the schedule network analysis technique used when developing the schedule, and it is typically applied in the fourth step, Adjust, to analyze and review the draft schedule. Its inputs are the network drawn with the precedence diagramming method and the estimated durations; its outputs, the critical path and the float, in turn become the basis for resource optimization and schedule compression decisions. The chapter starts from the concept of the critical path, works through a complete forward pass and backward pass example, and ends with the two kinds of float and the characteristics of the critical path.

By the end of this chapter you should be able to do the following. Explain how the critical path, the shortest project duration and the critical path method relate to one another. Find the critical path by listing paths, adding them up and taking the maximum. Use the forward and backward passes to calculate ES, EF, LS and LF, and check total float in two ways. Tell total float from free float and handle the delay of a non-critical activity. Judge whether the critical path shifts after a delay or after crashing.

Lessons in this chapter

Chapter map

Question to answerMethodResultLesson
How soon can the project finish?List the paths, add them up, take the longestCritical path, shortest durationLesson 1
What are the earliest and latest start dates of an activity?Forward pass, backward passES, EF, LS, LFLesson 2
How long can an activity be delayed?TF = LF − EF; FF = min(ES of successors) − EF − 1Total float, free floatLesson 3
What happens after a delay or crashing?Compare all paths againNew critical path, change in durationLesson 4

Study tips and practice

  • Practice listing paths and adding them up first, then the forward and backward passes. Check every calculation question in two ways until it becomes a habit.
  • For the “+1” and “−1” in the formulas, go by the starting point given in the question, and do not mix the two conventions within one question.
  • Total float and free float are high-frequency topics in scenario questions. Ask yourself first: is the delayed activity on the critical path, and is there enough float?
  • This chapter is closely tied to resource leveling and resource smoothing, to the critical chain method, and to the later chapter on crashing and fast tracking: the critical path and float are the basis for the judgments in all of them.

Lesson 1

The Critical Path and the Critical Path Method

Lesson video

Lesson overview

Once the network diagram is drawn and the durations are estimated, the first questions the project manager has to answer are these: what is the fastest the project can be finished, and which activities will hold up the whole project if they slip? The answer to both is the critical path. This lesson explains what the critical path and the critical path method are, how to find the critical path, and what judgments you can make once you have found it. It covers ECO: Process domain, Task 8 (Plan and manage schedule), specifically creating the project schedule. It sits at the start of the fourth step of developing the schedule, Adjust: the precedence diagramming method has provided the network and the duration estimates have provided the numbers, and this lesson uses them to answer the duration question. The next lesson uses the forward and backward passes to calculate the dates one by one.

The critical path and the critical path method

The critical path method (CPM) is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility (float) on the logical network paths within the schedule model. The critical path is the sequence of activities that determines the shortest possible duration to complete the project, which is to say the longest path through the network. The activities on it are called critical activities.

Start with an intuitive example. Before a new store opens, three independent things must be done: the fit-out takes 12 days, getting the business license takes 7 days, and recruiting and training staff takes 9 days. All three can start at the same time, so the whole preparation can take as little as 12 days, because the slowest item decides the end point. The license and the hiring can each start a few days late without moving the opening date, as long as they stay within their own extra time. That extra time is float, and the fit-out, which has no spare time, is the critical activity.

Remember two preconditions of the critical path method. First, it performs schedule network analysis: it looks only at the logical relationships between activities, durations, leads, lags and constraints, and it is done without regard to resource limitations. Second, the early and late dates it produces are not the actual project schedule; they define the time windows within which each activity may be executed.

How to do it: list the paths and add them up

The most reliable way to find the critical path by hand is to list every path from the start to the finish, add up the durations, and take the largest.

Worked example: a store-system launch project (days, FS relationships)

The activities: A requirements confirmation, 3 days, no predecessor; B back-end development, 8 days, predecessor A; C front-end development, 6 days, predecessor A; D data preparation, 5 days, predecessor A; E integration testing, 4 days, predecessors B and C; F staff training, 2 days, predecessor D; G go-live acceptance, 3 days, predecessors E and F.

Step 1: List all the paths and add them up.

PathCalculationLength
A-B-E-G3 + 8 + 4 + 318 days
A-C-E-G3 + 6 + 4 + 316 days
A-D-F-G3 + 5 + 2 + 313 days

Step 2: Take the longest. The critical path is A-B-E-G, and the shortest duration is 18 days. A-C-E-G is only 2 days shorter and is a near-critical path.

Step 3: Work out the total float of the other paths. The branches in this example are simple and have no extra constraints, so the difference in path lengths shows the branch float at a glance (an activity's total float should still be calculated from the forward and backward passes as LS − ES or LF − EF). The float of the path through C is 18 − 16 = 2 days; the path through D and F has 18 − 13 = 5 days, and D and F share those 5 days.

Step 4: Check. If C actually takes 9 days (3 more), A-C-E-G becomes 19 days, 1 day longer than the original critical path, so the project is 1 day late: the extra 3 days minus C's 2 days of float. If D takes 4 extra days, 4 is less than 5, so the project is not late.

This example also illustrates three rules for judging the critical path. When a critical activity (total float of zero) slips, and the network relationships and the other activities are unchanged and no remedial action is taken, the project finish date will usually move back by the same number of days. A non-critical activity that slips by no more than its total float does not affect the project. The portion beyond the float delays the project.

How it is used under different development approaches

Predictive projects usually define a fairly complete timeline up front (rolling wave planning can refine it step by step when information is lacking), and the critical path method is the main network analysis tool. Adaptive projects usually use timeboxed schedules built on short iterations, and may also use flow-based schedules; they do not usually calculate a critical path activity by activity. In a hybrid project, the high-level schedule lists milestones using predictive techniques; suitable sub-project streams can use the critical path method, and the rest use Kanban or iterations.

Worked examples

Example 1 Calculation: find the critical path and shortest duration from a network diagram

Question 1ExampleSelect 2

The activities, durations (in weeks) and predecessors of a system upgrade project are shown in the diagram. The project has no externally imposed finish date. Select the critical path and the shortest project duration. (Choose 2.)

Network diagram of seven activities, durations in weeks. A (8 weeks) and B (6 weeks) have no predecessor; C (5 weeks) and D (9 weeks) follow A; E (13 weeks) follows B; F (4 weeks) follows C and D; G (3 weeks) follows E and F.

Show answer and explanation

Correct answer: AD

The stem gives a network diagram with durations in weeks and no externally imposed finish date. You must select both the critical path and the shortest duration, and the two answers must correspond to the same path.

The critical path is the path with the longest sum of durations, and its length is the shortest project duration. List all three paths from start to finish and add them up. The longest is A-D-F-G at 24 weeks, so the critical path is option D and the shortest duration is option A. The answers are A and D.

  1. List the paths and add them: A-C-F-G = 8 + 5 + 4 + 3 = 20 weeks; A-D-F-G = 8 + 9 + 4 + 3 = 24 weeks; B-E-G = 6 + 13 + 3 = 22 weeks
  2. Take the maximum, 24 weeks: the critical path is A-D-F-G
  3. Check: the next-longest path, B-E-G, is 22 weeks, 2 weeks shorter than the critical path. It is a near-critical path; B and E each have 2 weeks of total float, while G is also on the critical path and has 0

Why the other options are wrong

  • B. A-C-F-G is only 20 weeks, the shortest of the three paths. This takes the shortest path for the critical path.
  • C. B-E-G is 22 weeks, a near-critical path only 2 weeks shorter than the critical path. It is easy to choose by mistake because it has few activities and one long one.
  • E. 22 weeks is the length of B-E-G. This takes the length of the second-longest path as the project duration.
  • F. 20 weeks is the length of the shortest path, A-C-F-G. The shortest duration is set by the longest path, not by the shortest.

Key takeaway The critical path is the longest path and the shortest duration is its length; the two answers must correspond to the same path.

Variation If Activity D were shortened to 6 weeks, A-D-F-G would become 21 weeks, B-E-G's 22 weeks would be the longest, the critical path would shift to B-E-G, and the shortest duration would be 22 weeks.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: how to determine the delivery date

Question 2Example

A bank has engaged PMLyceum to carry out an information-security remediation project. Several of the client's stakeholders want the project manager to commit to a firm delivery date. The project has many internal and external dependencies, plus several milestones that must be met within fixed time windows. What should the project manager do FIRST to determine the shortest project duration as the basis for the committed delivery date?

Show answer and explanation

Correct answer: C

The project has many dependencies and milestones fixed to time windows. The question specifically asks for the shortest project duration as an analytical basis for the committed delivery date.

The shortest project duration is set by the longest path in the network, which is the critical path. Integrate the activities into a network according to their logic, find the critical path, and add its length to the start date. That gives the earliest finish date without regard to resource limits, which is the basis for the delivery date you commit to; the fixed windows, calendars and resource constraints still have to be checked in the schedule analysis. “Many dependencies and fixed milestones” in the stem is the cue to do network analysis. The answer is C.

Why the other options are wrong

  • A. The work breakdown structure answers “what is the work” by decomposing it into deliverables. It contains no sequence or durations, so it cannot yield a delivery date.
  • B. The schedule baseline is the approved schedule model. It is the result of schedule analysis, not a method for arriving at dates; the analysis comes first and the baseline after.
  • D. Resource availability determines whether activities can be performed on time, but looking at resources alone cannot give the overall duration, nor does it show how dependencies affect the dates.

Key takeaway To answer “when is the earliest the project can be delivered?”, find the critical path.

Variation To identify which activities could start a few days later without affecting the delivery date, you look at the total float of each activity, which still starts from the critical path analysis.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The critical path is the path with the longest sum of durations, regardless of the number of activities; the single longest activity is not necessarily on the critical path.
  • The shortest duration equals the length of the longest path. “Shortest” and “longest” describe the same thing, so do not let the wording confuse you.
  • To decide whether something is critical, look at whether its total float is zero (or the least, when constraints apply), not at the number of its successors.
  • The critical path method does not consider resources. The dates it produces are windows, not an approved schedule.

Key takeaways

Key point

  • The critical path is the longest path in the network and determines the shortest project duration.
  • The critical path method performs schedule network analysis without regard to resource limitations, and determines the float of each path at the same time.
  • To find the critical path by hand: list all the paths, add each one up and take the maximum. In a simple network with no extra constraints, the difference in path lengths shows the float of a branch at a glance; the total float of an activity is still calculated as LS − ES or LF − EF.
  • With no extra constraints, with network relationships and other activities unchanged and with no remedial action, a delay on a critical activity usually pushes back the project finish date by the same amount (with constraints or network changes, redo the schedule network analysis); only the part of a non-critical activity's delay that exceeds its total float delays the project.
  • Predictive projects mainly use the critical path method; adaptive projects usually use iteration timeboxes or flow-based schedules and generally do not calculate a critical path activity by activity; hybrid projects use both in layers.

Lesson 2

Forward Pass and Backward Pass: The Seven-Box Node and a Step-by-Step Example

Lesson video

Lesson overview

You can find the critical path just by listing paths and adding them up, but the exam often asks for the early or late date of a particular activity, or for its total float, and for that you need the forward pass and the backward pass. This lesson first presents the seven-box node and six formulas, then works one complete example from start to finish and shows two ways to check it against each other. It builds on the critical path from the previous lesson and is the basis for the calculation of total float and free float in the next. It covers ECO: Process domain, Task 8 (Plan and manage schedule), specifically creating the project schedule.

The forward pass, the backward pass and the seven-box node

PMBOK 8 splits this calculation into two steps. The forward pass begins at the project start and calculates the earliest possible start (ES) and early finish (EF) dates for each activity. The backward pass begins at the project end and determines the latest allowable start (LS) and late finish (LF) dates for each activity without delaying the project. The difference between late and early dates yields the total float (TF), which indicates how much an activity can be delayed without affecting the project finish date. The critical path is the longest logical path that determines the shortest project duration; in an ordinary network with no externally imposed dates or other constraints, activities on the critical path usually have zero total float (PMBOK 8 notes that with constraints the total float on the critical path can also be positive or negative).

The seven-box node records all the numbers for an activity in one box:

ES early startDU durationEF early finish
Activity name or ID
LS late startTF total floatLF late finish

Using the convention that the project starts on Day 1, the formulas are:

ItemFormulaMemory aid
Early start ESForward pass takes the maximum
Early finish EF
Late finish LFBackward pass takes the minimum
Late start LS
Total float TF
Free float FFCovered in the next lesson

The “+1” and “−1” come from one convention: an activity that finishes by the end of Day 3 lets the next activity start as early as Day 4. PMBOK 8 notes that this is an accepted convention and that other accepted conventions may be used. Another approach often seen in exams counts the project start as Day 0, with each date being the point in time at the end of a day, and the formulas then have no ±1: ES = max(EF), EF = ES + DU, LF = min(LS). Both conventions give the same duration, critical path and float; only the way the dates are written differs by one day. In a question, go by the starting point and formulas the question gives, and do not mix the two in one question.

How to do it: a complete example

Worked example: a system cutover project (days; the project starts on Day 1)

A takes 4 days, no predecessor; B takes 6 days, predecessor A; C takes 3 days, predecessor A; D takes 5 days, predecessor B; E takes 4 days, predecessor C; F takes 3 days, predecessors D and E.

Step 1: Forward pass, left to right, to get ES and EF (take the largest EF among the predecessors, plus 1).
A: ES = 1, EF = 1 + 4 − 1 = 4. B: ES = 5, EF = 10. C: ES = 5, EF = 7. D: ES = 11, EF = 15. E: ES = 8, EF = 11. F has two predecessors; D's EF is 15 and E's is 11, so take 15: ES = 16, EF = 16 + 3 − 1 = 18. The shortest duration is 18 days.

Step 2: Backward pass, right to left, to get LF and LS (take the smallest LS among the successors, minus 1).
F: LF = 18, LS = 16. D: LF = 16 − 1 = 15, LS = 11. E: LF = 15, LS = 15 − 4 + 1 = 12. B: LF = 11 − 1 = 10, LS = 5. C: LF = 12 − 1 = 11, LS = 9. A has two successors; B's LS is 5 and C's is 9, so take 5: LF = 4, LS = 1.

Step 3: Total float TF = LF − EF.

ActivityESEFLSLFTFCritical
A14140Yes
B5105100Yes
C579114No
D111511150Yes
E81112154No
F161816180Yes

Step 4: Check in two ways. First, TF also equals LS − ES: for C it is 9 − 5 = 4 and for E it is 12 − 8 = 4, consistent with Step 3. Second, path lengths: A-B-D-F = 4 + 6 + 5 + 3 = 18 and A-C-E-F = 4 + 3 + 4 + 3 = 14, a difference of 4 days, exactly the total float of C and E; the activities with zero TF, A, B, D and F, are exactly the longest path.

Figure 1 Network diagram for the forward and backward pass example

Two small tricks for working through questions. On the forward pass, compare predecessor EFs and take the maximum only at a merge point; on the backward pass, compare successor LSs and take the minimum only at a split point. With a single predecessor or successor there is no comparison, but you still calculate the dates using the formulas. When there is no externally imposed finish date, the LF at the start of the backward pass is the project's earliest finish from the forward pass.

From working days to calendar dates

Durations are usually counted in working days. To convert them into calendar dates, you have to push the weekends and holidays through. For example, coding starts on a Monday and takes 3 working days, so it finishes Monday, Tuesday and Wednesday; unit testing then takes 2 days, finishing Thursday and Friday; nobody works on the weekend; and integration takes 3 days, finishing the following Monday through Wednesday. The three durations add up to 8 working days, but from the first Monday to the second Wednesday, 10 calendar days pass. Be clear whether the question asks for the “duration” or the “elapsed days”.

Worked examples

Example 1 Scenario calculation: working days and calendar dates

Question 1Example

A team is writing several modules. Coding starts on the 6th of this month (a Monday) and needs 3 working days. After development, 2 working days are reserved for unit testing, and integration can start only after testing is finished; integration needs 3 working days. The team does not work on weekends, no other holidays are considered, and everything goes smoothly. Which conclusion holds?

Show answer and explanation

Correct answer: B

The three activities follow one another, and the team does not work on weekends. You must convert working days into calendar dates and identify the logical relationship.

Development takes 3 working days and runs from Monday through Wednesday. Testing takes 2 working days and runs Thursday and Friday. There is no work on the weekend. Integration takes 3 working days and runs the following Monday through Wednesday. So integration finishes on the 15th, and from the 6th to the 15th is 10 calendar days. The sum of the durations is only 3 + 2 + 3 = 8 working days. The answer is B.

  1. Development: the 6th (Monday), 7th and 8th; it finishes on the 8th
  2. Testing: the 9th (Thursday) and 10th (Friday); the 11th and 12th are the weekend
  3. Integration: the 13th (Monday), 14th and 15th (Wednesday); it finishes on the 15th
  4. From the 6th to the 15th inclusive is 10 calendar days; the sum of the durations is 3 + 2 + 3 = 8 working days

Why the other options are wrong

  • A. Tuesday the 14th completes only the second day of integration. It is not done until Wednesday the 15th, so this misses the third day.
  • C. 10 is the number of calendar days. The durations add up to 8 working days, so this mixes up elapsed calendar days with duration.
  • D. “Integration can start only after testing is finished” is a finish-to-start relationship, not start-to-start.

Key takeaway Durations are counted in working days and must be pushed past weekends. When the next activity can start only after the previous one finishes, the relationship is finish-to-start.

Variation If the team also worked on weekends, development, testing and integration would run back to back and finish on the 13th, 8 calendar days in all, exactly the sum of the durations.

Something wrong with this question?

Report an issue with this question

Example 2 Calculation: total float and free float of E

Question 2Example

A data-center relocation project at PMLyceum has six activities (durations in days) and starts on Day 1: A takes 3 days and has no predecessor; B takes 5 days, predecessor A; C takes 4 days, predecessor A; D takes 6 days, predecessor B; E takes 2 days, predecessor C; F takes 4 days, predecessors D and E. Using the convention EF = ES + DU − 1, what are the total float and the free float of Activity E?

Network diagram of six activities, durations in days. A (3 days) has no predecessor; B (5 days) and C (4 days) follow A; D (6 days) follows B; E (2 days) follows C; F (4 days) follows D and E.
Show answer and explanation

Correct answer: D

The project starts on Day 1, and the stem fixes EF = ES + DU − 1. You must work through the forward and backward passes in full and then find total float and free float separately.

Do the forward pass, then the backward pass. E's total float is LF minus EF. Its free float is the early start of its successor F, minus E's early finish, minus 1. E and C share float on the same path, but E's successor F has to wait for D on the critical path. So both the total float and the free float of E are 5 days. The answer is D.

  1. Forward pass: A Days 1-3; B Days 4-8; C Days 4-7; D Days 9-14; E has ES = 7 + 1 = 8 and EF = 8 + 2 − 1 = 9; F takes the larger EF of D and E, 14, so ES = 15 and EF = 18
  2. Backward pass: F has LF = 18 and LS = 15; E has LF = 15 − 1 = 14 and LS = 14 − 2 + 1 = 13
  3. Total float of E = LF − EF = 14 − 9 = 5, which also equals LS − ES = 13 − 8 = 5
  4. Free float of E = ES of F − EF of E − 1 = 15 − 9 − 1 = 5
  5. Check: A-B-D-F = 18 days and A-C-E-F = 3 + 4 + 2 + 4 = 13 days, a difference of 5 days, consistent with the total float

Why the other options are wrong

  • A. This takes C's free float of 0 as E's. C's successor is E, so any move by C changes E's early start, and C's free float is 0. E's successor is F, whose early start is Day 15, so E's free float is 5.
  • B. This mixes two conventions in one question: ES is taken as 8 using +1, but EF is taken as ES + DU = 10, so 14 − 10 = 4 and 15 − 10 − 1 = 4. Both numbers come out 1 too small.
  • C. The total float is wrongly calculated as LF − ES = 14 − 8 = 6, which leaves out the duration. Total float is LF − EF or LS − ES.

Key takeaway Take the maximum on the forward pass and the minimum on the backward pass; TF = LF − EF = LS − ES, and FF looks only at the early start of the successors.

Variation If E's duration were changed to 4 days, E would run Days 8-11 with LF = 14, total float = 14 − 11 = 3, and free float = 15 − 11 − 1 = 3.

Something wrong with this question?

Report an issue with this question

Example 3 Calculation: where to take the maximum or minimum on the backward pass at merges and splits

Question 3Example

An order-system rework project at PMLyceum has six activities (durations in days) and starts on Day 1: A takes 3 days and has no predecessor; B takes 7 days, predecessor A; C takes 5 days, predecessor A; D takes 4 days, predecessor B; E takes 8 days, predecessor C; F takes 2 days, predecessors D and E. Using the convention LF = the minimum LS of the successors − 1, on which day is the late finish of Activity A?

Network diagram of six activities, durations in days. A (3 days) has no predecessor; B (7 days) and C (5 days) follow A; D (4 days) follows B; E (8 days) follows C; F (2 days) follows D and E.
Show answer and explanation

Correct answer: A

The project starts on Day 1. The question asks about only one step of the backward pass: how to take the late finish of A when A has two successors.

In the backward pass, when an activity has several successors, take the minimum of their late start dates and subtract 1. A's successors are B and C, so you must find the LS of each before you can take the smaller. A-C-E-F is the critical path and A is on it, so LF equals EF, Day 3. The answer is A.

  1. Forward pass: A Days 1-3; B Days 4-10; C Days 4-8; D Days 11-14; E Days 9-16; F has ES = 17 and EF = 18, so the duration is 18 days
  2. Backward pass: F has LS = 17; D has LF = 16 and LS = 13; E has LF = 16 and LS = 9; B has LF = 13 − 1 = 12 and LS = 6; C has LF = 9 − 1 = 8 and LS = 4
  3. A's successors are B (LS = 6) and C (LS = 4); take the smaller, 4, so LF = 4 − 1 = 3
  4. Check: A-C-E-F = 3 + 5 + 8 + 2 = 18, the critical path, so A has total float 0 and LF = EF = 3

Why the other options are wrong

  • B. This takes the smallest LS = 4 but forgets to subtract 1. If the next activity can start as late as Day 4, A has to finish on Day 3.
  • C. This takes the larger successor LS (B's 6) and subtracts 1. It is the error of “taking the maximum on the backward pass” and would let A finish later than C allows.
  • D. This takes B's late start, 6, directly as A's late finish. It takes the larger value and also forgets to subtract 1.

Key takeaway On the backward pass, take the minimum LS of the successors and subtract 1; the activity just before a split is the one most often done the wrong way round.

Variation If C were shortened to 3 days, A-B-D-F and A-C-E-F would both be 16 days, both would be critical paths, and A's LF would still be Day 3.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The forward pass takes the maximum EF of the predecessors, and the backward pass takes the minimum LS of the successors. Reverse them and the whole diagram is wrong.
  • The backward pass starts from the last activity, whose LF is the shortest project duration (when there is no externally imposed finish date).
  • If you drop the “+1” or “−1”, or use EF = ES + DU − 1 for half a question and EF = ES + DU for the other half, your numbers will be off by 1.
  • TF = LF − EF and TF = LS − ES must always be equal, so you can use them to check each other. If they are not equal, one step is wrong.

Key takeaways

Key point

  • The forward pass calculates ES and EF, and the backward pass calculates LS and LF; the difference between late and early is the total float.
  • The formulas below assume that all dependencies are finish-to-start (FS) with no leads, lags or other date constraints. With the Day 1 start convention: ES = max(EF of predecessors) + 1, EF = ES + DU − 1, LF = min(LS of successors) − 1, LS = LF − DU + 1.
  • TF = LF − EF = LS − ES; in an ordinary network with no externally imposed date constraints, the activities with zero TF form the critical path.
  • Checking: in a case like this one, with two simple parallel paths, the difference in path lengths equals the total float of the activities on the non-critical branch; in a complex network, check against the results of the forward and backward passes.
  • The dates are time windows, not an approved schedule; working days must be converted into calendar dates.

Lesson 3

Total Float and Free Float

Lesson video

Lesson overview

Total float and free float are the most easily confused, and most often tested, points in the critical path method: what to do when a non-critical activity is delayed, whether the float is enough, and who gets to use it up. This lesson explains in one place the meaning, formula and sharing rule of the two kinds of float, how negative float and lags affect path lengths, and the order of handling for “activity delayed” scenario questions. It depends on the forward and backward passes in the previous lesson. It covers ECO: Process domain, Task 8 (Plan and manage schedule), specifically analyzing schedule variances, as well as the requirement in Task 9 (Evaluate project status) to assess current progress.

What the two kinds of float mean

PMBOK 8 defines the two as follows. On any network path, total float is the amount of time an activity can be delayed without delaying the project finish date or violating a constraint. Free float is the time an activity can be delayed without affecting the early start of its successor.

Total floatFree float
What it protectsThe project finish date (and constraints)The early start of the successor
FormulaTF = LF − EF = LS − ESFF = min(ES of successors) − EF − 1 (in this lesson, with consecutive day counting, FS relationships and no leads or lags; with other logical relationships or with leads and lags, adjust accordingly)
Whose it isCalculated per activity; activities in a simple serial chain may share the same stretch of slackA single activity; affects only its successors
SizeTF ≥ FF in an ordinary networkFF ≤ TF (not applicable when TF is negative)

When an activity has several successors, free float is measured against the earliest successor, which is why the formula takes the minimum of the ES values. The last activity of the project has no successor; its free float is usually calculated with the project completion milestone as its successor, and in an ordinary network without an extra finish-date constraint, its free float equals its total float.

How to do it: float is shared

Worked example: 1 day of shared float (days; Day 1 start)

P takes 5 days, no predecessor; Q takes 3 days, predecessor P; R takes 6 days, predecessor P; S takes 2 days, predecessor Q; T takes 4 days, predecessors R and S.

Step 1: Forward pass. P: Days 1 to 5. Q: 6 to 8. R: 6 to 11. S: 9 to 10. T takes R's 11, so it runs 12 to 15, for a duration of 15 days.

Step 2: Backward pass. T: LF = 15, LS = 12. S: LF = 11, LS = 10. R: LF = 11, LS = 6. Q: LF = 10 − 1 = 9, LS = 7. P: it has two successors, Q (LS = 7) and R (LS = 6); take 6, so LF = 5.

Step 3: Float. The critical path is P-R-T (5 + 6 + 4 = 15). Q's total float = 9 − 8 = 1, and S's total float = 11 − 10 = 1.

Step 4: Free float. Q: the ES of its successor S is 9, so 9 − 8 − 1 = 0. S: the ES of its successor T is 12, so 12 − 10 − 1 = 1.

Step 5: Interpretation and check. Q and S are on the same path and share 1 day of total float. If Q slips 1 day, S's early start moves to Day 10 and S's float is used up; Q's free float is 0, which means any move by Q squeezes its successor. If S slips 1 day, nothing else is affected, and its free float is 1. Check: path P-Q-S-T = 14 days, 1 day shorter than the 15-day critical path, consistent with the total float.

Key point

Total float is calculated per activity (in PMBOK 8: the amount of time an activity can be delayed without delaying the project finish date or violating a constraint). In a simple serial non-critical chain, activities may share the same stretch of schedule slack, and slack consumed by an earlier activity shrinks the room left for later ones to be delayed. Free float is also calculated per activity and measures how long the activity can be delayed without affecting the early start of its successor. Activities on the critical path usually have zero total float.

Negative float, constraints and lags

The total float of the critical path is usually zero, but constraints can change that. If a constraint sets the finish date later than the result of the forward pass, positive float can appear; if an imposed date is earlier than the logic and durations allow, there is negative float. In the example above, suppose the client requires completion by Day 14: T's LF becomes 14, and every activity on the critical path has total float of −1 day. Negative float means the current plan cannot meet the requirement, and acceleration strategies need to be analyzed and developed, which is the schedule compression covered in the later chapter on crashing and fast tracking.

When calculating path lengths, do not forget leads and lags. For example, A takes 5 days, after which one path runs through B (4 days) and then C (3 days) and another has D (3 days) with a 2-day lag after A, and both paths merge into E (4 days). The first path is 5 + 4 + 3 + 4 = 16 days; the second is 5 + 2 + 3 + 4 = 14 days, with the 2-day lag counted into the path. The second path has 2 days of total float. If D is then delayed by 4 days, its path becomes 18 days, longer than 16, and the project is delayed 2 days: the 4-day delay minus the 2 days of total float.

What to do first when an activity is delayed

When a non-critical activity is delayed, or a new dependency is added that pushes back the start of an activity, the order of handling that is common exam practice is this: first verify whether the activity's total float can absorb the delay; if it can, update the current schedule model and forecast and keep monitoring, with no need to spend money on crashing; any change to the schedule baseline still follows formal change control; if it cannot, assess the consequences according to the number of days of delay and apply measures such as compression. When an activity on the critical path is delayed, you must assess the effect on the finish date immediately. When you want to know how much flexibility the whole schedule has, you also use the float calculated by the critical path method.

Worked examples

Example 1 Scenario: a non-critical activity is delayed, and cost is constrained

Question 1Example

An impact assessment shows that a key resource, tied up by other priorities, cannot work on a non-critical activity. The activity may be delayed by three weeks, which may affect the related deliverable, and the other team members may become overloaded as a result. The project's main constraint is cost. What should the project manager do IMMEDIATELY?

Show answer and explanation

Correct answer: D

A non-critical activity may be delayed by three weeks and the project's main constraint is cost. The question asks which measure to take immediately.

The activity is not on the critical path, so whether it affects the finish date depends on its total float. If the float is at least three weeks, the delay will not hold up the project and no extra cost is needed, so first confirm whether the float is enough, then decide whether to act. With cost as the main constraint, any step that spends money first is inappropriate. This also fits the “analyze before acting” order: when you do not know whether float is enough, any step that spends money or cuts scope skips the analysis. The answer is D.

Why the other options are wrong

  • A. Hiring temporary staff adds cost, and cost is the main constraint. Spending money before you know whether the delay affects the finish date is not appropriate.
  • B. Reducing the delivery scope is a negative approach that must be negotiated with stakeholders, and it should not be the first thing considered before the impact is understood.
  • C. A resource calendar should reflect the actual availability of resources. Simply editing the calendar creates no resources and cannot prevent the delay; confirm the float first, then decide whether to adjust resource assignments or the schedule.

Key takeaway When cost is constrained and a non-critical activity is delayed, check the float first and do not rush to spend money.

Variation If the delayed activity were on the critical path, an ordinary network without extra date constraints would usually have no positive total float to use, and you would evaluate crashing or fast tracking while weighing the cost constraint.

Something wrong with this question?

Report an issue with this question

Example 2 Calculation: the effect of a critical activity's delay on duration and float

Question 2Example

A server-room renovation project at PMLyceum consists of six activities. All relationships between activities are finish-to-start, and the durations are shown in the diagram. Activity A starts immediately when the project starts. If Activity B starts 2 weeks later than planned, what will be the effect on the project?

Network diagram: after Activity A (3 weeks) the network splits into an upper path B (4 weeks) and D (5 weeks) and a lower path C (3 weeks) and E (4 weeks); both paths merge at Activity F (2 weeks). All arrows are finish-to-start.
Show answer and explanation

Correct answer: C

All relationships between activities are finish-to-start. B starts 2 weeks late, and you must judge the effect on the finish date, the critical path and float, which starts with finding the critical path.

Of the two paths, A-B-D-F is longer and is the critical path. B is on it, with total float 0, so the delay passes straight through to F. With B starting 2 weeks late, this path becomes 16 weeks while the other is still 12 weeks, so the finish date is pushed back 2 weeks and the critical path does not change. The answer is C.

  1. A-B-D-F = 3 + 4 + 5 + 2 = 14 weeks; A-C-E-F = 3 + 3 + 4 + 2 = 12 weeks; the critical path is A-B-D-F
  2. B starts 2 weeks late: A-B-D-F = 14 + 2 = 16 weeks; A-C-E-F is still 12 weeks
  3. The finish date moves back 16 − 14 = 2 weeks, and the longest path is still A-B-D-F
  4. Check: the float of the non-critical path is 14 − 12 = 2 weeks, which cannot absorb a delay on the critical path

Why the other options are wrong

  • A. B is on the critical path and has no total float. Its delay passes straight through to F, so the finish date cannot stay the same.
  • B. After the delay, A-B-D-F is 16 weeks and A-C-E-F is still 12 weeks. The longest path has not switched, so the critical path has not changed.
  • D. D is on the critical path and its total float stays at 0. B's delay only makes the critical path longer; it does not give D any float.

Key takeaway When there is no extra date constraint, the critical path has zero total float, and other conditions are unchanged, a delay on a critical-path activity usually pushes back the finish date by the same amount; a delay on a non-critical activity may be absorbed by total float.

Variation If the delay were on C, starting 2 weeks late, A-C-E-F would become 14 weeks, exactly equal to the critical path. It would use up the 2 weeks of float, the finish date would not change, and both paths would be critical.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • A large total float does not mean you can delay at will: in a simple serial chain, activities share the same stretch of slack, so once the earlier activity uses it, the later one has none.
  • In an ordinary network calculation without negative total float, free float ≤ total float; this relationship cannot be applied when total float is negative; and an activity that has float can still have zero free float when its successor starts right after it.
  • Negative float means the current plan cannot meet a constraint. It is a signal to analyze and develop acceleration strategies, of which schedule compression is one option, not a sign of being “very comfortable”.
  • Delaying a non-critical activity is not always harmless: the project bears the part of the delay that exceeds the total float.
  • Include leads and lags when you calculate path lengths.

Key takeaways

Key point

  • Total float: the maximum delay that does not delay the finish date, TF = LF − EF = LS − ES; activities in a simple serial chain share the slack.
  • Free float: the maximum delay that does not delay the early start of the successor, FF = min(ES of successors) − EF − 1 (in this lesson, for networks with consecutive day counting, FS relationships and no leads or lags; with other logical relationships or with leads and lags, adjust accordingly).
  • In a network without negative total float, FF is no greater than TF (see Common traps for the negative-float case); with no extra finish-date constraint, the FF of the last activity usually equals its TF.
  • When an imposed date is earlier than the plan allows, negative float appears; first analyze the cause and develop acceleration strategies: consider schedule compression, or adjust logical relationships, leads and lags, and constraints that can be negotiated.
  • When a non-critical activity is delayed, first verify whether the total float is enough, then decide whether to act.

Lesson 4

Characteristics of the Critical Path: Multiple Paths and Path Shifts

Lesson video

Lesson overview

The critical path is not fixed once it is calculated. As the project is executed, activities slip, the team crashes, resources are adjusted, and the critical path can change to another path at any time, or even be several paths at once. This lesson sets out the characteristics of the critical path: there can be several, total float need not be zero, near-critical paths carry risk, what the project manager does after a path shift, and how predictive, adaptive and hybrid projects each use it. It closes the chapter and prepares the ground for the later resource optimization and schedule compression. It covers ECO: Process domain, Task 8 (Plan and manage schedule), specifically analyzing schedule variances, and the related requirement in ECO: Business Environment domain, Task 4 (Remove impediments and manage issues).

Some characteristics of the critical path

  • In an ordinary network with no extra date constraints, the critical path is usually the path with the longest duration and the least total float; more generally, the sequence of activities that determines the shortest project duration and has the least total float is the critical path. Activities on non-critical paths do not affect the duration as long as their delay stays within their own total float.
  • Activities on the critical path usually have zero total float, but not necessarily: a constraint that sets the finish date later than the result of the forward pass gives positive float, and an earlier one gives negative float.
  • There can be several critical paths: when several paths are equally long, each one is a critical path. The more activities you have to watch at the same time, the greater the risk.
  • A path with small total float whose length is close to that of the critical path is a near-critical path (some sources call it a sub-critical path). The closer it is to the critical path, the more easily one or two delayed activities can turn it into the new critical path. PMBOK 8 notes that many software tools allow users to define how criticality is measured.
  • The critical path method does not consider resource limits, so the schedule it produces may not be feasible and should be combined with resource optimization.

Bringing total float to zero or to a positive value may require adjustments to activity durations, logical relationships, leads, lags or constraints. PMBOK 8 also gives a measure related to the critical path called critical path drag: the amount of time that an activity on the critical path is adding to the project duration; alternatively, it is the maximum amount of time that one can shorten the activity before it is no longer on the critical path or before its duration becomes zero. This measure shows the theoretical maximum effect of each critical path activity on the duration. When choosing what to compress, you must also consider whether the activity can be compressed, the incremental cost and the risk (PMBOK 8 gives only the definition of this measure and does not make it a separate selection criterion).

How to do it: reanalyze after a delay or compression

Any event that changes a duration requires you to compare all the paths again; you cannot look only at the original one.

Worked example: the critical path shifts after crashing (days)

A warehouse renovation project has three paths: Path 1 is 20 days, Path 2 is 18 days and Path 3 is 15 days. Assume the paths share no activities other than their start and finish milestones, and that Paths 1 and 2 each contain enough crashable duration.

Step 1: The current state. The critical path is Path 1, with a shortest duration of 20 days; Path 2 has 2 days of float and Path 3 has 5 days.

Step 2: Crash activities on Path 1 by 4 days. Path 1 becomes 16 days.

Step 3: Compare again. The longest is now Path 2, at 18 days. The duration shortens by only 2 days (20 − 18), not 4, because Path 2 has become the new critical path. The extra 2 days of compression on Path 1 (taking it down to 16 days) buy no further reduction in project duration, so their crashing cost did not buy schedule shortening.

Step 4: What to do next. To keep compressing, you can first crash on Path 2 alone, by at most 2 more days (down to 16 days, tying with Path 1 as a critical path); after that, any further shortening has to compress both critical paths at the same time. Management focus shifts to Path 2 as well.

Check. Calculate the three paths again: 16, 18, 15. The maximum is 18, consistent with Step 3.

A delay works the same way. When an activity on the critical path is delayed, with total float of zero and other conditions unchanged, the project is usually delayed by the same number of days (if the critical path has positive total float because of a constraint, deduct the float that can be used first). When a delay on a non-critical path exceeds its total float, that path becomes longer than the original critical path and becomes the new critical path, and the project is delayed by the amount of the excess. After each change, the project manager reruns the critical path analysis, updates the schedule model, and shifts the focus of monitoring and resources to the new critical path.

Under different development approaches

Predictive projects: the schedule is defined up front, with a complete timeline that has clear milestones, dependencies and a critical path, and the critical path method is the main network analysis tool. Adaptive projects: the schedule is usually timeboxed by iteration, and critical path analysis is generally not done activity by activity within an iteration; impediment lists and the daily coordination meeting bring problems to the surface. Hybrid projects: the high-level schedule lists milestones using predictive techniques, some sub-project streams use the critical path method, and others use Kanban or iterations. When the schedule of a hybrid project deteriorates, you also first decide which impediments affect the critical path and deal with those first.

Worked examples

Example 1 Scenario: most impediments are cleared, but the schedule keeps deteriorating

Question 1Example

A hybrid project at PMLyceum has entered execution, and the project manager and team have started holding a daily coordination meeting. So far the project manager has resolved 75% of the impediments the team reported, but the schedule variance is still growing day by day with no sign of improving. What should the project manager do to keep the schedule from deteriorating further?

Show answer and explanation

Correct answer: C

A hybrid project is in execution, with a daily coordination meeting to surface impediments. 75% of the impediments have been cleared, yet the schedule variance still widens day by day. The question asks how to keep it from deteriorating further.

That most impediments have been cleared while the schedule variance keeps growing suggests turning your limited effort to the bottlenecks that affect the finish date. A delay on the critical path pushes back the finish date directly, so among the options given, rank the impediments by their effect on the critical path and deal first with those that affect it; you should still monitor the float of non-critical activities and analyze whether there are other sources of variance. The general approach in this kind of question is that, with limited resources and effort, you put them where they directly affect the finish date; impediments on non-critical paths can be handled later as long as the float is enough. The answer is C.

Why the other options are wrong

  • A. The stem does not say the daily coordination meetings are run badly. Sending the agenda in advance would not make impediment handling more targeted and would not solve the variance.
  • B. Quality problems can cause rework that delays the schedule, but the stem gives no hint of any quality problem. Focusing on the critical path is more direct.
  • D. The stem does not mention any lack of skills. Developing skills takes time to pay off and does not address the direct cause of the deterioration.

Key takeaway With limited resources, first resolve the impediments that would delay the critical path rather than spreading effort evenly.

Variation If all the impediments were on non-critical paths with ample float, that would only mean the finish date is not yet affected; if the schedule variance kept growing, you would analyze the root cause further.

Something wrong with this question?

Report an issue with this question

Example 2 Calculation: the length of the critical path after a delay

Question 2Example

A renovation project has seven activities, and all of the logical relationships are finish-to-start. Activity 1 starts first and takes 3 weeks. After it finishes, Activities 2, 4 and 5 can start at the same time, taking 4, 6 and 8 weeks respectively. Activity 3 follows Activity 2 directly and takes 3 weeks; Activity 6 follows Activity 4 directly and takes 4 weeks; Activity 7 can start only after Activities 3, 5 and 6 are all finished and takes 2 weeks. Activity 3 has now taken 4 weeks longer than planned. What is the length of the critical path now?

Show answer and explanation

Correct answer: C

All logical relationships are finish-to-start. Activity 3 has overrun by 4 weeks, which may shift the critical path, so the three paths must be compared again.

First list the three paths and add them up to find the critical path before the delay, then include Activity 3's overrun and compare again. After the delay, 1-2-3-7 is longer than the original critical path and becomes the new critical path, with a length of 16 weeks. The answer is C.

  1. Before the delay: 1-2-3-7 = 3 + 4 + 3 + 2 = 12 weeks; 1-4-6-7 = 3 + 6 + 4 + 2 = 15 weeks (critical path); 1-5-7 = 3 + 8 + 2 = 13 weeks
  2. Activity 3 goes from 3 weeks to 7 weeks: 1-2-3-7 = 3 + 4 + 7 + 2 = 16 weeks
  3. Take the maximum again: max(16, 15, 13) = 16 weeks, and the critical path shifts to 1-2-3-7
  4. Check: 16 − 15 = 1 week, so the finish date is 1 week later than originally planned

Why the other options are wrong

  • A. 15 weeks is the length of 1-4-6-7, the critical path before the delay. It misses that after Activity 3's overrun, 1-2-3-7 has become longer.
  • B. 12 weeks is the length of 1-2-3-7 before the delay. It does not include the overrun.
  • D. 13 weeks is the length of path 1-5-7, which is neither the longest before the delay nor the longest after it.

Key takeaway After an activity slips, compare all the paths again, because the critical path may shift.

Variation If Activity 3 had overrun by only 2 weeks, 1-2-3-7 would be 14 weeks, still less than 15 weeks. The critical path would not change, and this path's total float would drop from 3 weeks to 1 week.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The total float of activities on the critical path is “usually” zero, not “always”; with constraints it can be positive or negative.
  • The closer a near-critical path is to the critical path, the more dangerous it is; you cannot ignore it just because it is “not critical”.
  • After the critical path is compressed, the reduction in duration is limited by the next-longest path, and the extra money spent does not necessarily buy time.
  • A shift of the critical path is not a failure. Do not mechanically keep using the old list of critical activities, and do not immediately undo the crashing; reanalyze the paths, then decide to keep or adjust the crashing according to the schedule objective, incremental cost and risk.
  • The critical path method deals only with path constraints; resource conflicts have to be resolved through resource optimization.

Key takeaways

Key point

  • There can be several critical paths; total float is usually zero and can be positive or negative when constraints apply.
  • The closer a near-critical path is to the critical path, the greater the schedule risk.
  • Delays, crashing and resource adjustments can all shift the critical path, after which the critical path analysis must be done again.
  • If you compress only the current critical path and the other paths are unchanged, the reduction available before the path shifts is no more than its difference from the next-longest path; after the shift, reanalyze and compress the new critical path.
  • Predictive projects use the critical path method; adaptive projects use iteration timeboxes or flow-based schedules; hybrid projects use them in layers.

This chapter has 34 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.