PMP Cheat Sheet: Finance

The key points and common traps of 16 lessons in 5 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.

Mind map of Finance
Tap the map to enlarge

Estimate Costs

Formulas

Cost Estimate: Beta Distribution (PERT) Expected ValueO optimistic, M most likely, P pessimistic estimate; use the beta distribution when the question does not name a distribution (common exam practice); when it says "triangular distribution" or "simple average" use (O+M+P)/3
Cost Estimate: Triangular Distribution Expected ValueA simple arithmetic mean; the common formula given in PMBOK 8
Cost Estimate: Standard Deviation and ±1σ IntervalCommon exam practice: the standard deviation of the beta distribution is taken as (P − O) ÷ 6, not divided by 3; E ± σ is a one-standard-deviation interval around the expected value, not the full range of the estimate (the full range is O to P); only under a normal approximation does E ± σ cover about 68%. For example, O=40, M=52, P=82: E = 55, σ = 7, E ± σ = 48–62, while the full estimate range is 40–82

Lesson 1: The Financial Management Plan, Funding Strategies and Estimate Accuracy

Key takeaways

  • The four processes of the PMBOK 8 Finance performance domain: Plan Financial Management, Estimate Costs, Develop Budget, and Monitor and Control Finances.
  • Outputs of Plan Financial Management: the financial management plan (the rules for managing money) and the funding strategy (where the money comes from). Funding proposals come from Monitor and Control Finances and are used to request the needed funds from internal or external funding sources; certain phases may submit specific funding requests to cover the approved budget of that phase.
  • A control threshold is the maximum variance allowed before action is taken, and it determines when action must be taken.
  • Accuracy increases as information increases. Rough order of magnitude −25% to +75% and definitive estimate −5% to +10% are common exam grade names and reference ranges; the more information, the narrower the range.
  • Stem signal: "just started, little information, want a rough number" means a rough order of magnitude estimate (common exam practice).

Common traps

  • The financial management plan states rules (units, accuracy, precision, thresholds, measurement rules, reporting formats) and does not state specific amounts; how much each phase needs and when it is disbursed are funding requirements, derived from the cost baseline.
  • Accuracy is "how far off", and precision is "to which digit it is written".
  • The range is asymmetric: for a rough order of magnitude estimate (the common exam name) it is −25% to +75%, so the upper limit is wider than the lower.
  • Estimates become more accurate later, but an early estimate is still required: give a range and explain to stakeholders that it is a range.
  • An estimate is not itself a baseline. The cost baseline is formed only after estimates are aggregated, distributed over time and approved. Contingency reserve is included in the cost baseline in the common case (PMBOK 8 also lets an organization place it outside the baseline by preference), and management reserve is not part of the cost baseline.

Lesson 2: Estimating Methods: Analogous, Parametric, Bottom-Up and Multipoint

Key takeaways

  • Analogous: refer to a similar project; early, fast, generally less accurate. Parametric: statistical relationship, unit price × quantity. Bottom-up: aggregate work packages, usually more accurate but time-consuming. Multipoint estimating: three values, handles uncertainty.
  • Triangular distribution E = (O + M + P) ÷ 3; beta distribution E = (O + 4M + P) ÷ 6, σ = (P − O) ÷ 6.
  • The PMBOK 8 commonly used formula is the triangular distribution; common exam practice: when the stem does not state a distribution, use the beta distribution (PERT), and when it says "triangular distribution" or "simple average", use the triangular distribution.
  • Adaptive projects use story points, planning poker and T-shirt sizing for relative estimating, and velocity cannot be compared across teams.
  • Estimating is progressively elaborated; numbers given early should be marked with a range or their uncertainty and explained to stakeholders.

Common traps

  • Analogous estimating is fast but generally less accurate, parametric estimating depends on data quality, and bottom-up estimating is usually more accurate but the most time-consuming. Do not confuse "more accurate" with "fastest".
  • Analogous estimating is a top-down, gross-value approach that can be applied to an entire project or to part of one. Do not switch to "expert judgment" just because expert judgment was used.
  • When a multipoint estimating question does not state the distribution: the commonly used formula in PMBOK 8 is the triangular distribution (O + M + P) ÷ 3; common exam practice is to use the beta distribution/PERT (O + 4M + P) ÷ 6 when the stem does not specify a distribution; when the stem says "triangular distribution" or "simple average", use the triangular distribution.
  • The standard deviation of the beta distribution is (P − O) ÷ 6, not divided by 3.
  • Story points measure relative size, not hours, and story points from different teams cannot be compared.

Lesson 3: Cost Estimates, the Basis of Estimates and Influencing Factors

Key takeaways

  • The two outputs of Estimate Costs: the cost estimates and the basis of estimates; the basis of estimates records the assumptions, constraints and range.
  • When a number is challenged, respond with historical information, lessons learned and the basis of estimates.
  • Factors that affect estimates: schedule, risk, resources and quality, plus make-or-buy decisions.
  • PMBOK 8 stresses life cycle cost: when pushing project cost down, look beyond near-term spending and evaluate the effect on use, maintenance cost and life cycle value.
  • Avoid omissions by consulting similar projects and having experts review beforehand, not by patching afterward and not by over-reserving.

Common traps

  • Cost estimates can be presented at the activity level or in aggregate form; Develop Budget aggregates the estimated costs of activities or work packages and establishes the approved cost baseline.
  • The basis of estimates is not an optional attachment: an estimate without a basis is hard to get approved and cannot be defended when challenged.
  • Schedule, risk, resources and quality all change cost; a change in duration may change time-accumulating financing costs, overhead and so on.
  • Reserves deal with uncertainty and cannot replace a complete estimate. Known required work belongs in the estimate and must not be deliberately left for reserves to cover.
  • An estimate is not a baseline. The cost baseline is formed only after estimates are aggregated, allocated over time periods and approved. Management reserve is not part of the cost baseline; contingency reserve is included in the cost baseline in the common case, and PMBOK 8 also allows an organization to place it outside the baseline by preference.

Cost Baseline and Reserves

Formulas

Cost BaselineThe common case with reserves managed implicitly (default in exams): the cost baseline contains contingency reserve and not management reserve; how reserves are included depends on the financial management plan and organizational policy
Project BudgetWith reserves managed implicitly; when management reserve is used the baseline rises and the reserve falls, so the total budget is unchanged; do not add contingency reserve to the baseline again (double counting)
Total Funding RequirementTotal funding requirements are derived from the cost baseline; funds are usually released in increments and may be uneven

Lesson 1: Cost Aggregation and the Cost Baseline: What Is in the Budget

Key takeaways

  • Develop Budget aggregates the estimated costs of individual activities or work packages to establish an authorized cost baseline.
  • Aggregation route: activity → work package → control account → project. With reserves managed implicitly, contingency reserve is included at the levels the plan specifies; with reserves managed explicitly, reserves are listed separately.
  • Under common exam practice (reserves managed implicitly): cost baseline = work package cost estimates + contingency reserve; project budget = cost baseline + management reserve.
  • The cost baseline is time-phased, can be changed only through change control, and when plotted cumulatively is an S-curve.
  • PMBOK 8 describes two scenarios: reserves managed implicitly (the baseline includes contingency reserve) and reserves managed explicitly (the baseline includes neither reserve). Default to the first.

Common traps

  • Under common exam practice (reserves managed implicitly), the cost baseline contains contingency reserve and not management reserve, and project budget = cost baseline + management reserve (this equation does not apply when reserves are managed explicitly). Do not add contingency reserve on top of the baseline and call that the budget; that double counts it.
  • After work package estimates are aggregated, the result is not yet a cost baseline until it is time-phased, includes contingency reserve (when managed implicitly) and is approved.
  • A control account is a management control point containing two or more work packages; a planning package sits below the control account and above the work package.
  • The cost baseline can be changed only through formal change control procedures; you cannot change it just because you want to.
  • Past projects can serve as a reference, but you cannot apply an old project's total to the current one. Access to cost data and authority to approve the budget are set by organizational policy, governance arrangements and the financial management plan; once cost estimates are aggregated and time-phased, an authorized governance body approves them to form the baseline.

Lesson 2: Contingency Reserve vs Management Reserve: Where the Money Comes From and Who Approves It

Key takeaways

  • Contingency reserve: identified risks (known-unknowns); inside the cost baseline in the common case; used by the project manager under the risk response plan; the baseline does not change.
  • Management reserve: unidentified risks (unknown-unknowns); outside the cost baseline; usually decided by senior management and needs a change request; once released it is added to the baseline.
  • Under the common budget structure used in this lesson (reserves managed implicitly, contingency reserve included in the cost baseline): project budget = cost baseline + management reserve; when management reserve is released, the baseline goes up, management reserve goes down, and the total budget is unchanged. PMBOK 8 also allows other structures, such as a cost baseline that contains neither reserve.
  • Contingency reserve can be set as a percentage, a fixed amount or by quantitative analysis; monitor it during execution through reserve analysis.
  • If an identified risk does not occur, unused contingency reserve can be released.

Common traps

  • When an identified risk occurs, use contingency reserve under the plan, with no change control procedure needed. When an unidentified risk occurs, a change request must be submitted before management reserve is released.
  • Under the common structure in which management reserve is included in the project budget and funding requirements, releasing it increases the cost baseline and reduces management reserve, while total project budget and funding requirements stay the same; other budget structures follow organizational governance rules.
  • New scope is not a use of management reserve; once a scope change is approved, update the baselines.
  • When an identified risk occurs, do not “re-plan the response”. The planning was done before the risk occurred, and now you are executing. You do not need to redo quantitative analysis either.
  • Common exam practice: unless the stem says otherwise, management reserve requires a change request. You cannot spend first and report afterward, and you cannot quietly fold the cost into another work package. The exception is when the stem states that the project manager has authority to release it.

Lesson 3: Project Funding Requirements, Funding Limit Reconciliation and Financing

Key takeaways

  • Total funding requirement = cost baseline + management reserve; funds may be released in increments and unevenly.
  • Cumulative expenditure plots as an S-curve and funding as a staircase; at no point may the staircase fall below the cumulative expenditure curve.
  • Funding limit reconciliation: reschedule work and place imposed dates so that the rate of spending matches the arrival of funds.
  • For external financing, check the accompanying requirements first; when a phase needs dedicated funds, submit a funding proposal and use the right approval channel.
  • When funding goes wrong: assess the impact of the gap and the alternatives first, then adjust the schedule, adjust scope or seek funds.

Common traps

  • A sufficient total budget does not mean there is enough money in every period; match the needs of each period with the time the funds arrive.
  • When funds do not match, what you adjust is the schedule and the rate of spending, not the cost baseline at will.
  • When funding goes wrong, the first step is to assess the impact of the gap and the alternatives, not to cut scope, pause or ask for money immediately.
  • Total funds required = cost baseline + management reserve; management reserve is outside the baseline but inside the funding requirements.
  • A funding proposal is a specific request for dedicated funds (common for a particular phase), while the funding strategy covers where the money comes from and how it is raised and released. Do not confuse them.

Lesson 4: Financial Constraints and Budgeting in Agile Environments

Key takeaways

  • Financial constraints: besides the budget, there are the type of funds (CapEx versus OpEx), budgets allocated by year that must be used within the year and cannot be carried over depending on organizational rules, and the source of personnel.
  • An agile project's budget can be allocated by quarter and revised quarterly; iterations flatten the expenditure curve.
  • When the budget is limited: rank the backlog by value with the product owner and deliver the greatest value within budget; when defining the first release scope, identify the minimum viable product.
  • Small projects should budget conservatively; government projects hold larger reserve buffers.
  • Stem signals: the budget is cut or about to run out and scope is adjustable. Prioritize first; do not ask for money first.

Common traps

  • Capital expenditure buys assets and is depreciated; operational expenditure is the ongoing cost of day-to-day business and is expensed in the period. When told to use “only the operating budget”, change a purchase into a lease.
  • When the budget is allocated by year and cannot be carried over (depending on organizational rules), do not rush to spend at year end.
  • When the budget of an adaptive project is tight: first adjust backlog priorities and reduce scope. Do not ask for more budget first, cut evenly across the board, or blindly remove people.
  • When a budget is cut, re-rank the backlog with the product owner by value, dependencies and risk to deliver the greatest value within budget; if you need to define the first release scope, then identify and prioritize the MVP. Do not compress scope and schedule proportionally.
  • Predictive projects measure variance against the cost baseline; an agile project's budget can be revised quarterly, but it still needs traceable expenditure records.

Earned Value Management

Formulas

Budget at CompletionThe total value of all planned work, i.e. the cost baseline, not including management reserve; the cumulative PV at the planned completion date equals BAC
Planned ValueThe budgeted value of the work scheduled to be complete as of the status date (usually the data date), read from the time-phased baseline; common exam practice: for simplified questions with evenly spread work and a single unit of measure, PV = planned quantity of work × budgeted unit rate (for example 200 m planned at a budgeted $40/m gives PV = $8,000)
Earned ValueThe value of the work actually completed as of the status date, measured by the budget authorized for that work, regardless of actual cost; common exam practice (when percent complete is weighted by budget): EV = actual quantity of work × budgeted unit rate = BAC × percent complete (for example BAC $300,000 and 60% complete gives EV = $180,000)
Actual CostThe cost actually incurred for the work completed as of the status date; take it from the cost records, not from percent complete; common exam practice: for simplified questions with a single unit of measure and costs taken at actual unit rates, AC = actual quantity of work × actual unit rate (for example 180 m at $50/m gives AC = $9,000)
Schedule Variance> 0 ahead of schedule, < 0 behind schedule
Cost Variance> 0 under budget, < 0 over budget
Schedule Performance Index> 1 ahead of schedule, < 1 behind schedule
Cost Performance Index> 1 under budget, < 1 over budget

Lesson 1: Earned Value Basics: BAC, PV, EV and AC

Key takeaways

  • The four values: BAC budget at completion, PV planned value, EV earned value, AC actual cost.
  • PV = planned quantity of work × budgeted unit price; EV = actual quantity of work × budgeted unit price; AC is the cost actually incurred and recorded (in simplified problems with a single unit of measure and costs at actual unit prices, AC = actual quantity of work × actual unit price).
  • Memory aid: PV from the schedule, EV from progress, AC from the books.
  • Comparison rule: EV against PV shows schedule, and EV against AC shows cost.
  • EV = BAC means all the work is complete and EV does not rise after that; on the planned completion date PV = BAC.

Common traps

  • EV is the budgeted value of the work actually completed. It is not how much was spent (that is AC), and not how much was planned (that is PV).
  • With only the percent complete, EV = BAC × percent complete. Do not multiply AC.
  • On the planned completion date PV = BAC; after all the work is complete, EV = BAC and does not increase any further.
  • BAC does not include management reserve; it is the total value of the cost baseline.
  • PV and AC cannot be compared directly, because they correspond to different amounts of work. The comparison must go through EV.
  • “PV” is also the abbreviation for present value in finance, which has nothing to do with planned value in EVM. Look for a discount rate and a number of years to tell them apart.

Lesson 2: Variance Analysis: Schedule Variance (SV) and Cost Variance (CV)

Key takeaways

  • SV = EV − PV: above 0 is ahead, 0 is on plan, below 0 is behind.
  • CV = EV − AC: above 0 is under budget, 0 is on budget, below 0 is over budget.
  • When only variances are given: EV = PV + SV and AC = EV − CV.
  • For adaptive projects, convert story points to budget: PV and EV come from the stories planned and the stories actually delivered.
  • Variances can be converted into percentages for comparison with the control threshold.

Common traps

  • SV = EV − PV and CV = EV − AC, with EV always first. Subtract the other way round and every sign is wrong.
  • Schedule compares EV with PV, and cost compares EV with AC. Do not compare AC directly with PV.
  • The basic results for SV and CV are dollar amounts. They can also be converted to variance percentages, but do not confuse them with the CPI and SPI of the next lesson.
  • SV = 0 does not necessarily mean the project was on time throughout. After the planned completion date, once all the scope is complete, EV = PV = BAC and SV is 0 (even if the project finished late). If a project finishes early, PV on the actual completion date is still below BAC and SV is positive, and late in the project SV loses its diagnostic value.
  • The words in the stem (should have been done by the plan, actually completed, cumulative spending) must first be translated into PV, EV and AC.

Lesson 3: Performance Indices: SPI and CPI, and Judging Project Status

Key takeaways

  • SPI = EV ÷ PV and CPI = EV ÷ AC; above 1 is favorable, below 1 is unfavorable and 1 is on plan.
  • Status: read schedule from SV / SPI and cost from CV / CPI. You should be able to read all four combinations.
  • Three steps for calculation questions (common exam practice): find BAC and the percentages; calculate PV, EV and AC; calculate the variance or index.
  • Checks: SPI × PV = EV and CPI × AC = EV.
  • Late in the project SPI tends toward 1. The overall SPI does not represent the critical path; when the critical path SPI is given, go by it.

Common traps

  • An index is a ratio: SPI = EV ÷ PV and CPI = EV ÷ AC, with EV the numerator in both. Do not swap numerator and denominator.
  • Judge schedule from EV and PV, and cost from EV and AC. The two judgments are independent; do not let one carry over into the other.
  • “45% complete, 42% of the budget spent”: if the two percentages are on the same basis, EV = 0.45 × BAC and AC = 0.42 × BAC, so CPI ≈ 1.07 and you can say costs are under budget. But without the planned percent complete you cannot tell whether the schedule is ahead or behind.
  • The overall SPI does not represent the critical path. With an SPI above 1, the critical path may still be behind.
  • Once all the scope is complete and the data date has reached or passed the baseline completion date, SV returns to zero and SPI equals 1. Do not conclude from that that there was no schedule problem.
  • A CPI of 0.8 means that for every $1 spent only $0.80 worth of work is produced; it does not mean an 80% overrun.

Lesson 4: What the Project Manager Does After Finding a Variance

Key takeaways

  • Monitor and Control Finances: monitor financial status, manage changes to the cost baseline and revenue forecasts, and ensure the project remains financially viable.
  • Order of action: analyze the cause, compare with the control threshold, correct within your authority, raise a change request if the baseline must change, then communicate and update the forecast.
  • Three analyses: variance analysis asks how far off, trend analysis asks what will happen, reserve analysis asks whether reserves are enough.
  • An overrun that has already occurred and crossed the threshold goes in the issue log first, with cause analysis started at once; a trend still developing is analyzed first.
  • Schedule behind: crashing works by adding resources and fast tracking by overlapping; when the budget is overrun, consider fast tracking first (common exam practice).

Common traps

  • When a variance appears, the first step is to analyze the cause, not to add funding, add resources, cut scope, or report it first. If an overrun has already crossed the threshold and is a fact, record it in the issue log first and start cause analysis at the same time.
  • Within the threshold, normally continue monitoring and correct within the project manager's authority when needed. Beyond the threshold, first take the measures the financial management plan prescribes; only if it also exceeds your authority or meets the escalation criteria do you escalate through the governance process.
  • The cost baseline can be changed only through formal change control. Record and analyze issues promptly; if a proposed action would change a controlled artifact or a baseline, raise a formal change request and, before approval, add a complete impact analysis of cost, schedule, risk and so on.
  • An overrun that has already occurred is an issue, recorded in the issue log. A risk is an uncertain event that has not yet occurred; do not register an overrun that has occurred as a new risk.
  • Capturing lessons learned is not the first thing to do. It can be recorded in step with the handling and completed after the issue is resolved.
  • Crashing adds resources and may increase cost and/or risk; fast tracking overlaps work and may increase rework and risk. When the budget is already overrun, fast tracking is usually the better fit (common exam practice).

Estimate at Completion

Formulas

Estimate at Completion (basic identity)AC is the actual cost incurred to date and ETC is the expected cost of all the remaining authorized work; the four methods below differ only in how ETC is obtained
Estimate at Completion (atypical variance)The remaining work will be done at the originally planned rate
Estimate at Completion (typical variance)Current cost performance continues to the end
Estimate at Completion (cost and schedule performance both matter)The remaining work is affected by both cost and schedule performance
Estimate at Completion (new estimate)A bottom-up re-estimate of the remaining work
Estimate to CompleteThe cost still needed to finish the remaining work
Variance at Completion< 0 means a forecast overrun
To-Complete Performance Index (target: BAC)> 1 harder to achieve, < 1 easier to achieve
To-Complete Performance Index (target: EAC)Use when BAC is no longer achievable
Forecast Total Duration (simplified linear method)Common exam practice, a simplified linear method: it assumes planned work and budgeted value are spread evenly over the planned duration and that percent complete equals percent of budgeted value; when current performance continues, SPI takes the current value and the formula reduces to planned total duration ÷ SPI; when the remaining work follows the plan, SPI = 1. For example, 24 days planned, 30% complete on day 10: SPI = 7.2 ÷ 10 = 0.72, forecast total duration = 10 + 16.8 ÷ 0.72 ≈ 33.3 days; with the remaining work on plan it is 10 + 16.8 = 26.8 days

Lesson 1: Estimate at Completion (EAC): Four Methods, Plus ETC and VAC

Key takeaways

  • EAC = AC + ETC; ETC = EAC − AC; VAC = BAC − EAC.
  • Four methods: atypical AC + (BAC − EV); typical BAC ÷ CPI; CPI × SPI when both affect the work; re-estimate AC + new ETC.
  • Basis for choosing: whether the variance will repeat; with no statement, treat it as typical (common exam practice).
  • A negative VAC means an overrun is expected at completion; VAC looks at the end point, CV looks at now.
  • Three steps to solve: find BAC, EV and AC and compute the indices; decide the situation; plug into the formula, then convert to ETC or VAC as asked.

Common traps

  • Typical variance uses BAC ÷ CPI; atypical variance uses AC + (BAC − EV). First read the stem to decide whether the variance will continue.
  • If there is a “new estimate”, use AC plus the new ETC and do not divide by CPI again.
  • Do not confuse EAC with BAC: BAC is the approved total budget, while EAC is the total cost forecast from current performance.
  • ETC is what is still to be spent and equals EAC − AC. It is not EAC, and it is not BAC − AC.
  • VAC = BAC − EAC; a negative value means an overrun is expected at completion. It is a forecast, not the variance already incurred (that is CV).
  • With the typical-variance formula EAC = BAC ÷ CPI, CPI below 1 means an overrun and EAC should be above BAC; if you get an EAC below BAC, the direction is wrong. For other situations (re-estimate, CPI × SPI and so on) you still judge by the formula chosen.

Lesson 2: To-Complete Performance Index (TCPI) and Forecasting Completion Duration

Key takeaways

  • TCPI = (BAC − EV) ÷ (BAC − AC); when the target is EAC, the denominator becomes EAC − AC.
  • TCPI above 1 is harder to achieve, equal to 1 requires the planned efficiency, and below 1 is easier to achieve; read it together with CPI.
  • TCPI far above 1 with no improvement: assess whether the budget is still viable; if it is not, reforecast and use the approved EAC as the new target; go through change control only if the cost baseline must change.
  • Forecast total duration = time elapsed + (planned total duration − planned duration for the work completed) ÷ SPI.
  • Duration uses SPI and cost uses CPI; first decide what the question is asking.

Common traps

  • The numerator of TCPI is the budgeted value of the remaining work, BAC − EV, and the denominator is the money left. It is not the EV ÷ AC of CPI.
  • Whether the target is BAC or EAC depends on whether the stated budget is still viable. When the original BAC is clearly no longer viable and the forecasted EAC has been approved as the new management target, use the EAC version; if the question says a budget baseline was approved and updated, calculate with the updated BAC.
  • A TCPI above 1 is a warning, not “high efficiency”; the larger it is, the harder the work is to complete.
  • Forecast duration with SPI, not CPI. An SPI below 1 lengthens the duration, so divide by SPI.
  • “Schedule performance stays at the current level” differs from “the remaining work proceeds as planned”: in the first, SPI takes the current value; in the second, SPI is 1.

Net Present Value and Value Evaluation

Formulas

Present ValueFV is the future amount, r the discount rate, n the number of years
Net Present ValueCFt is the net cash inflow in year t, I0 the initial investment (a positive number), r the discount rate, n the number of years; NPV > 0 is acceptable, choose the largest positive value; if later outflows such as added investment exist, use NPV = Σ[t=0..n] CFt/(1+r)^t with CF0 negative
Internal Rate of ReturnThe discount rate at which NPV equals zero, with signed cash flows (CF0 is the initial investment, negative); compare it with the organization’s required rate of return, and above it the project is acceptable on this financial criterion; it normally has to be solved by trial or software; for mutually exclusive projects choose the largest NPV by default, and look at IRR only when the question asks to compare by the highest rate of return
Payback Period (undiscounted)I0 is the initial investment; T0 is the construction period (add it only when there are no inflows during it and payback is measured from project start); CF is the equal net inflow per period; N is the number of full periods after which cumulative inflows have not yet recovered the investment, and CFN+1 is the inflow of the period in which it is recovered (assumed to arise evenly within the period); shorter is better; ignores the time value of money; the undiscounted payback period is common exam practice, and when the question says discounted, use discounted cash flows. For example, investment $900,000, 6-month construction, then $50,000 net per month: PP = 6 + 900 ÷ 50 = 24 months; investment $600,000 with inflows of $200,000, $250,000 and $300,000: PP = 2 + (600 − 450) ÷ 300 = 2.5 years
Return on InvestmentNet investment gain = benefits − investment cost; higher is better; ignores the time value of money. Common exam practice (use only when the question gives this convention; period and annualization follow the question or the organization’s definition): ROI = average annual profit ÷ total investment × 100%. For example, investment $2,000,000 and cumulative 5-year profit $1,500,000: by the general definition (treating the profit as the net gain) period ROI = 1,500 ÷ 2,000 = 75%; by average annual profit = 300 ÷ 2,000 = 15% per year
Benefit-Cost RatioCompare benefits and costs after bringing them to the same point in time; when the question already gives comparable benefit and cost amounts, use them directly; > 1 is acceptable, higher is better (BCR > 1 and NPV > 0 are the same judgment). For example, present value of benefits $2,600,000 and investment $2,000,000: BCR = 1.3

Lesson 1: Present Value, Discounting and Net Present Value (NPV)

Key takeaways

  • Money has a time value; present value PV = FV ÷ (1 + r)ⁿ. Divide, and discount for as many years as there are.
  • NPV = the sum of the discounted net cash flows of each period; simplified form: the sum of the present values of each year's net cash inflow − the initial investment.
  • Evaluated on financial return alone, NPV > 0 is usually acceptable and NPV < 0 usually is not; when the project is mandatory for compliance or has significant strategic, social or other non-financial value, a broader judgment is needed; among mutually exclusive projects, choose the largest positive NPV.
  • NPV already contains the time value of money, so you need not consider the project's length again; the NPV of “do nothing” is 0.
  • Use NPV to compare the overall financial value of several investment paths (including make-or-buy); the core of cost-benefit analysis is comparing costs with expected benefits.

Common traps

  • Here PV means “present value”, which has the same abbreviation as “planned value” in earned value management but a completely different meaning. Read the context: where a discount rate and a number of years appear, it is present value.
  • Present value uses division: PV = FV ÷ (1 + r)ⁿ. Multiplying by mistake makes the present value too large. Discount for as many years as there are, not just one.
  • Discounting is compounding. You cannot subtract the discount rate directly as simple interest (such as × (1 − n × r)).
  • NPV already includes the time value of money. When comparing, do not divide by the project's years again and do not deduct the initial investment a second time.
  • Among mutually exclusive projects, choose the one with the largest positive NPV; do not choose a project with a negative NPV.
  • Present value PV has the same abbreviation as planned value PV in earned value management but a different meaning.
  • Payback period and cost differences speak only to part of the picture; to compare the overall value of several paths, use NPV.

Lesson 2: IRR, Payback Period, ROI and Benefit-Cost Ratio

Key takeaways

  • | Metric | Selection criterion | Considers time value |
  • |---|---|---|
  • | NPV | Larger is better among positive values; accept if NPV > 0 | Yes |
  • | IRR | Larger is better; the discount rate at which NPV = 0 | Yes |
  • | ROI | Larger is better; net benefit ÷ investment (this lesson commonly uses average annual profit ÷ total investment) | No |
  • | BCR | Accept if greater than 1; larger is better | Usually present values |
  • | Static payback period | Shorter is better; includes construction when there are no inflows during it and payback is measured from project start | No |
  • These metrics are used within cost-benefit analysis, usually written into the business case (common exam practice); PMBOK 8 says the business case is typically developed and maintained by the sponsor.
  • Among mutually exclusive projects, default to the largest NPV; when funds are limited, maximize total NPV within the budget constraint, and BCR or the profitability index may serve as a reference; compare by IRR only when the question explicitly asks for the highest internal rate of return.
  • Value can be financial, social or environmental, and can also be intangible, such as customer satisfaction and innovation.

Common traps

  • The static payback period starts when the initial investment is made. If there are no inflows during construction and payback is measured from project start, include the construction period; common exam practice is to use the undiscounted static payback period.
  • Payback period measures a length of time and ROI measures a ratio. Do not mix them up. A short payback does not mean large overall value.
  • IRR is the discount rate that makes NPV equal to 0, and larger is better. To compare amounts, use NPV; choose by IRR only when the question explicitly asks to compare by highest internal rate of return.
  • BCR must be greater than 1 to be acceptable; equal to 1 is only break-even.
  • Total cost of ownership speaks of cost, and BAC is the total budget for the project work; neither measures a benefit ratio.
  • Value is not the same as profit; the answer to “is it financially worthwhile?” and “is it worth doing considering overall value?” can differ.

Lesson 3: Cost Types: Direct and Indirect, Fixed and Variable, Sunk Cost, Opportunity Cost and Life Cycle Cost

Key takeaways

  • Seven cost types: direct, indirect, fixed, variable, life cycle, sunk and opportunity.
  • Sunk cost does not enter decisions; opportunity cost is the value of the option given up.
  • Total cost = fixed cost + variable cost per unit × quantity; the larger the quantity, the thinner the fixed cost per unit is spread, so the cost per unit falls.
  • Life cycle cost: in decisions, look at costs before and after delivery together.
  • When an option carries probabilities, calculate EMV first and then compare; NPV greater than 0 is financially acceptable on that criterion, and among mutually exclusive options choose the largest.

Common traps

  • When deciding whether to continue a project that has run into trouble, ignore sunk cost and look only at future investment and benefit.
  • Opportunity cost is the value of the option given up. It is not the benefit of the option chosen, not the difference between the benefits of the two options, and certainly not their sum.
  • Direct costs can be charged to a particular project; indirect costs are shared among projects, such as overhead and rent; fixed costs do not change with the workload, and variable costs do.
  • Do not push down project cost at the expense of raising usage and maintenance costs; look at life cycle cost.
  • Going over budget does not mean you must stop the project immediately, nor that you must finish at any price; look at whether the future value justifies continuing.