Earned Value Management

PMP · Finance · 4 lessons · about 49 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Earned value management (EVM) is the core tool of the Monitor and Control Finances process. It integrates the scope baseline, cost baseline and schedule baseline into the performance measurement baseline, and then uses one measure, the budgeted value of the work actually completed, to compare against both the plan and actual spending. It answers two questions: is the project ahead of or behind schedule, and is it under or over budget? The chapter has four steps. First, you learn the four basic values: budget at completion, planned value, earned value and actual cost. Second, you subtract to get schedule variance and cost variance. Third, you divide to get performance indices and read the project's status. Fourth, you learn the order of action a project manager follows once a variance is found. The first three steps are calculation and the fourth is scenario judgment, and the exam tests both kinds of questions.

By the end of this chapter you should be able to do the following. State what BAC, PV, EV and AC each mean and find them from the facts in a question. Use SV = EV − PV and CV = EV − AC to judge schedule and cost, and work back from a variance to EV and AC. Use SPI = EV ÷ PV and CPI = EV ÷ AC to read the four possible statuses, and understand how the overall SPI differs from the critical path. When a variance appears, act in this order: analyze the cause, compare with the control threshold, correct within your authority, raise a change request if a baseline must change, and communicate.

Lessons in this chapter

Chapter map

BAC (total budget)  PV (how much was planned)  EV (how much was actually done, valued at budget)  AC (how much was actually spent)  
Schedule: SV = EV − PV; SPI = EV ÷ PV   |   Cost: CV = EV − AC; CPI = EV ÷ AC
> 0 / > 1 favorable; = 0 / = 1 on plan; < 0 / < 1 unfavorable  
On finding a variance: analyze the cause → compare with the control threshold → correct within your authority → raise a change request if a baseline must change → communicate and forecast  

How the exam tests this

The pattern for calculation questions is fixed. First identify the BAC, the planned percent complete, the actual percent complete and the actual spending given in the stem, and use them to determine PV, EV and AC. If a value is missing, work it back from the variance or index the question gives. Then calculate the variance or index and judge the status. Common variations include giving only the percent complete, giving only a variance, measuring in story points, giving a critical path SPI, and giving a point in time after the project has finished. The pattern for scenario questions is also fixed. When a variance or trend appears, the first step is to analyze the cause. An overrun that has already crossed the threshold is an issue and goes in the issue log. To change a baseline, go through change control first. Practice both patterns until they are routine and this chapter becomes dependable points.

Study tips and practice

  • Memorize the four definitions and the two “always first” rules: EV is always first in the variance formulas and always the numerator in the index formulas.
  • In every calculation question, write out the three numbers PV, EV and AC, and then check that SPI × PV = EV and CPI × AC = EV.
  • For scenario questions, ask yourself first: has the variance already occurred, or is it only a trend? Has it crossed the threshold? Is my authority enough?
  • After this chapter, continue to the chapter on estimate at completion; it is the forecasting extension of this one.

Lesson 1

Earned Value Basics: BAC, PV, EV and AC

Lesson video

Lesson overview

The core tool for monitoring finances is earned value management (EVM). It uses one yardstick to measure scope, schedule and cost together: it takes the budgeted value of the work completed and compares it, on one side, with the plan and, on the other, with actual spending. It answers two questions: is the project ahead of or behind schedule, and is it under or over budget? Every EVM calculation rests on four numbers: budget at completion (BAC), planned value (PV), earned value (EV) and actual cost (AC). The first step on any question is to find these four numbers. This lesson covers only how the four values are defined and found; variances and indices come in the next two lessons, and forecasting in the next chapter. ECO: Process domain, Task 6 (Plan and manage finance), covering planning how expenditures will be tracked across the project life cycle and monitoring financial variances.

What the four values are

Earned value management integrates the scope baseline with the cost baseline and schedule baseline to form the performance measurement baseline. EVM develops and monitors three key dimensions for each work package and control account: planned value, earned value and actual cost. Add the budget total for the whole project and you have the four values.

AbbreviationNameMeaning
BACBudget at completionThe sum of all budgets established for the work to be performed; the total value of the cost baseline, not including management reserve
PVPlanned valueThe authorized budget assigned to scheduled work: the budgeted value of the work planned to be completed to a point in time
EVEarned valueThe measure of work performed expressed in terms of the budget authorized for that work: the budgeted value of the work actually completed to a point in time
ACActual costThe realized cost incurred for the work performed on an activity during a specific time period: the money actually spent on the work completed to a point in time

In simplified problems with a single unit of measure, where costs are taken at actual unit prices, “quantity of work × unit price” shows the relationship among the three at a glance. (The formal definition of AC is the realized cost incurred for the work performed during a specific time period; quantity × actual unit price is only a simplification.)

  • PV and EV both use the budgeted unit price. The difference is the quantity of work: PV is “how much should be done by now” and EV is “how much has actually been done”.
  • EV and AC both correspond to the quantity of work actually completed. The difference is the unit price: EV is valued at budget and AC at what was actually spent.
  • PV is cumulative: the cumulative PV at the planned completion date equals BAC (the incremental planned values of the individual periods add up to BAC; do not add up the cumulative PV figures at each point in time). When EV = BAC, all the work has been completed.

In older textbooks these three values are also called BCWS (PV), BCWP (EV) and ACWP (AC), which occasionally appear in questions. In adaptive projects, effort can be expressed through story points. When story points are used, PV is the amount of story points estimated for the user stories planned until a certain date (usually the end of the iteration), EV represents the story points estimated for the user stories that are considered done at the end of the same iteration, and AC is related to the costs for the team working on the user stories during the iteration.

How to remember and find them

The easiest way to remember them is to ask what information each one depends on. PV is read from the time-phased performance measurement baseline: look at which work was planned to be completed by the data date and what authorized budget it carries, and you know how much work should be done and how much it should be worth. (Only in simple problems where the plan is spread evenly can you estimate it in proportion to elapsed time.) EV depends on how much work was actually completed, converted at the authorized budget for that work: it is not affected by what was spent, and it ignores what the plan says; it looks only at how much work is really done, valued at the budgeted unit price. AC depends on actual spending: you must look in the books. The three values answer three different questions, and no single one can tell you whether a project is doing well. They must be used in pairs: EV against PV shows schedule, and EV against AC shows cost.

Why can't you compare PV and AC directly? Because they correspond to different amounts of work. Suppose that at some point the plan called for spending $40,000, and the project has also spent $40,000. The numbers are identical, but if only two thirds of the planned work is actually done, that $40,000 was too much to spend; if more work than planned has been done, it may have been too little. Without EV as the go-between, those two numbers cannot support any conclusion.

Quick practice: finding EV, PV and AC from the conditions

  • Budget $30,000, work 60% complete: EV = $30,000 × 60% = $18,000.
  • Planned at $30,000 and 10 days, with work and budget spread evenly over the 10 days, and today is day 4: PV = $30,000 × 4/10 = $12,000.
  • Planned at $24,000 and 6 days, with work and budget allocated evenly by day, and on the first day the crew completed two days' worth of work: 1/3 is complete, so EV = $24,000 × 1/3 = $8,000.
  • The plan is to lay 300 square meters of flooring with a budget of $30,000, and EV is $9,000: 30% is complete, so 90 square meters are laid.
  • The ledger shows $13,000 paid to date: AC = $13,000. AC has to come from the cost records; it cannot be derived from the percent complete alone.

Worked example: laying fiber-optic cable (see Figure 1)

A community broadband project plans to lay 400 meters of fiber in 8 weeks with a budget of $16,000, progressing evenly. At the end of week 4 a check shows 180 meters laid and actual spending of $9,000.

  • BAC = $16,000; budgeted unit price = $16,000 ÷ 400 = $40 per meter.
  • By the end of week 4 the plan called for 400 × 4/8 = 200 meters, so PV = 200 × $40 = $8,000.
  • 180 meters were actually laid, so EV = 180 × $40 = $7,200.
  • AC = $9,000 (from the books).
  • Check: EV of $7,200 is below PV of $8,000, so the project is behind schedule; EV of $7,200 is below AC of $9,000, so it is spending more and producing less.
Figure 1 The four basic earned value measures (fiber-optic example, end of week 4)

Three traps when finding values

When a question gives only the percent complete, EV = BAC × percent complete, not AC × percent complete. EV is value converted at the budget; it cannot be worked back from how much was spent.

When a question says the check is made on the planned completion date, PV equals BAC: according to the plan, everything should be done by then. Likewise, after the project is completed on plan, EV also equals BAC and does not keep growing over time: earned value is the budgeted value of the work completed, and once all the work is done it no longer rises, and it can never exceed the budget authorized for that component.

When a question gives only AC and the percent complete, with no information about timing, PV cannot be found, and such questions usually do not need PV. The unit prices in the stem, such as “budget per kilometer” or “budget per story”, are there to convert quantity of work into budgeted value.

Worked examples

Example 1 Calculation: earned value from distance completed

Question 1Example

A city greenway project covers 45 kilometers and has a budget of $9,000,000. It is planned to finish in 18 months. Every kilometer has the same amount of work and the same budget, and the budget is spread evenly over the 18 months. At the end of month 6, cumulative spending is $2,800,000 and 12 kilometers have been paved. The sponsor wants a status report that includes earned value. What earned value should be reported at this point?

Show answer and explanation

Correct answer: B

Work on this project is measured in kilometers. The question asks only for earned value (EV) at the end of month 6; the spending to date and the months elapsed are distractors.

Earned value equals the work actually completed multiplied by the budgeted unit price. Divide the total budget by the total length to get the budgeted price per kilometer, then multiply by the kilometers already paved. That gives the budgeted value of the work completed, regardless of how much was actually spent or how much was planned to be done. The answer is B.

  1. Budgeted unit price = $9,000,000 ÷ 45 = $200,000 per kilometer
  2. EV = 12 × $200,000 = $2,400,000
  3. Check: 12 ÷ 45 = 4/15 complete, and $9,000,000 × 4/15 = $2,400,000
  4. Compare: AC = $2,800,000 and PV = $9,000,000 × 6 ÷ 18 = $3,000,000. All three values differ; EV looks only at the work completed

Why the other options are wrong

  • A. $747,000 ≈ $2,800,000 × 12 ÷ 45. This multiplies actual cost by the percent complete. EV is value measured at the budget, so it cannot be derived from AC.
  • C. $2,800,000 is the actual cost (AC). It treats the money spent as the value of the work completed.
  • D. $3,000,000 = $9,000,000 × 6 ÷ 18. Calculated from elapsed time, this is the planned value (PV): what should have been done, not what was actually done.

Key takeaway EV is how much work was actually completed, valued at the budgeted unit price; PV is how much was planned; AC is how much was spent.

Variation If 30% of the work were complete, EV = $9,000,000 × 30% = $2,700,000. In this question, schedule variance is SV = EV − PV = $2,400,000 − $3,000,000 = −$600,000, and cost variance is CV = EV − AC = $2,400,000 − $2,800,000 = −$400,000.

Something wrong with this question?

Report an issue with this question

Example 2 Calculation: earned value after the planned completion date

Question 2Example

A logistics sorting-line upgrade project has a budget at completion of $48,000 and is planned to finish in 6 months. At the end of month 4, the project has spent $32,000, and both cost and schedule match the plan exactly. The project continues to follow the plan, which calls for completion at the end of month 6. What will the project's earned value (EV) be 3 months later, at the end of month 7?

Show answer and explanation

Correct answer: D

BAC is $48,000 and the plan is 6 months. At the end of month 4 cost and schedule both match the plan. The question asks for EV at the end of month 7.

If cost and schedule match the plan at the end of month 4, then EV = PV = AC = $32,000 and CPI = SPI = 1. On plan, the project finishes at the end of month 6, and at completion EV = BAC = $48,000. Earned value is the budgeted value of the work completed; once all the work is done it stops increasing. So at the end of month 7 it is still $48,000. The answer is D.

  1. End of month 4: cost and schedule match the plan, so EV = PV = AC = $32,000 and CPI = SPI = 1
  2. On plan, the project finishes at the end of month 6: EV = BAC = $48,000
  3. The stem says the project continues to follow the plan, so it finishes at the end of month 6; EV therefore remains $48,000 at the end of month 7
  4. Check: EV cannot exceed BAC, and $48,000 ≤ $48,000 holds. The answer is D

Why the other options are wrong

  • A. $32,000 is EV at the end of month 4. It carries today's value forward as if no work were completed over the next 3 months.
  • B. Extrapolating $8,000 per month ($32,000 ÷ 4) over 7 months gives $56,000, but EV is a budgeted value and can never exceed the budget at completion of $48,000.
  • C. $16,000 = BAC − AC = $48,000 − $32,000. That is the remaining budget, not earned value.

Key takeaway Once the project actually completes as planned, EV equals BAC and does not rise merely because more time passes.

Variation For EV at the end of month 5, you would need the value of the work planned to be complete by then. If planned value is spread evenly over the 6 months, EV = $48,000 × 5 ÷ 6 = $40,000. If only 90% were complete at the end of month 6, EV = $48,000 × 90% = $43,200.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • EV is the budgeted value of the work actually completed. It is not how much was spent (that is AC), and not how much was planned (that is PV).
  • With only the percent complete, EV = BAC × percent complete. Do not multiply AC.
  • On the planned completion date PV = BAC; after all the work is complete, EV = BAC and does not increase any further.
  • BAC does not include management reserve; it is the total value of the cost baseline.
  • PV and AC cannot be compared directly, because they correspond to different amounts of work. The comparison must go through EV.
  • “PV” is also the abbreviation for present value in finance, which has nothing to do with planned value in EVM. Look for a discount rate and a number of years to tell them apart.

Key takeaways

Key point

  • The four values: BAC budget at completion, PV planned value, EV earned value, AC actual cost.
  • PV = planned quantity of work × budgeted unit price; EV = actual quantity of work × budgeted unit price; AC is the cost actually incurred and recorded (in simplified problems with a single unit of measure and costs at actual unit prices, AC = actual quantity of work × actual unit price).
  • Memory aid: PV from the schedule, EV from progress, AC from the books.
  • Comparison rule: EV against PV shows schedule, and EV against AC shows cost.
  • EV = BAC means all the work is complete and EV does not rise after that; on the planned completion date PV = BAC.

Lesson 2

Variance Analysis: Schedule Variance (SV) and Cost Variance (CV)

Lesson video

Lesson overview

The previous lesson introduced BAC, PV, EV and AC. This lesson uses them for the first layer of analysis: variances. A variance is a dollar amount obtained by subtraction, and it tells you directly how many dollars the project has departed from the plan. Schedule variance (SV) looks at schedule and cost variance (CV) looks at cost. There are only two formulas, but there are plenty of test points: how to read the signs, how to translate words into PV, EV and AC, how to work back when only variances are given, and how to calculate with story points on an iterative project. The next lesson uses division to get the performance indices. ECO: Process domain, Task 6 (Plan and manage finance), covering monitoring of financial variances.

The two variance formulas

Key point

Schedule variance (SV) is a measure of schedule performance expressed as the difference between the earned value and the planned value. Positive means ahead of schedule, zero means on schedule and negative means behind schedule. Cost variance (CV) is the amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost. Positive means under planned cost, zero means on planned cost and negative means over planned cost. Both formulas give dollar amounts.

There is only one rule to remember: EV always comes first; in a variance formula it is the number you subtract from. A positive result is good news and a negative result is bad news. One more hint: the S in SV stands for Schedule, which concerns schedule and puts EV and PV together; the C in CV stands for Cost, which concerns cost and puts EV and AC together. The good news for schedule is being ahead and the good news for cost is saving money, and a positive variance means good news in both cases. Do not judge the direction by gut feeling; read the sign.

Worked example: week 3 of a bookstore renovation

By the end of week 3 of a bookstore renovation project, planned value PV = $8,000, earned value EV = $6,800 and actual cost AC = $6,200.

  • SV = $6,800 − $8,000 = −$1,200: behind schedule.
  • CV = $6,800 − $6,200 = +$600: under budget.
  • Check: AC is $1,800 below PV, but that difference means nothing. It mixes “less work done” with “less money spent”, which is why PV and AC must not be compared directly.

Translating words into PV, EV and AC

Many questions do not mention PV, EV or AC directly and describe them in words, so you must translate first. “The value of the work that should have been completed according to the plan” is PV; “the value of the work actually completed” is EV; “cumulative spending” or “actual spending” is AC; and “40% complete with a budget of $100,000” means EV = $40,000. Translate first, then apply the formulas; do not compare the sizes of the figures directly in the wording.

Worked example: taking over a project and judging its status

A pump station upgrade project has a planned duration of 30 months, and in month 15 you take over the project. The handoff materials say that, to date, the value of the work that should have been completed per the plan is $520,000, the value of the work actually completed is $480,000 and cumulative spending is $505,000.

  • Translate: PV = $520,000, EV = $480,000, AC = $505,000.
  • SV = $480,000 − $520,000 = −$40,000: behind schedule.
  • CV = $480,000 − $505,000 = −$25,000: over budget.
  • Conclusion: behind schedule and over budget. Check: if someone compared AC of $505,000 with PV of $520,000 and concluded that spending is below plan, that would be wrong.

Working back from variances, and using story points

Some questions give only variances and not EV or AC. Use the variance formulas to work back first, then continue the calculation: EV = PV + SV; AC = EV − CV.

Worked example: working back from variances

A project reports PV = $80,000, SV = −$5,000 and CV = +$2,000.

  • EV = PV + SV = $80,000 − $5,000 = $75,000.
  • AC = EV − CV = $75,000 − $2,000 = $73,000.
  • Check: SV = $75,000 − $80,000 = −$5,000 and CV = $75,000 − $73,000 = +$2,000, matching the givens. Conclusion: behind schedule, under budget.

In adaptive approaches, effort can be expressed through story points, and the planned and completed amounts are calculated from the story points assigned to each user story. To apply earned value you also need an agreed rule for converting story points into authorized budget. In the example below, each story is worth 5 story points and each story point is budgeted at $600. PV is the budget for the stories planned to be completed by a given date (usually the end of the iteration), EV is the budget for the stories delivered by the same point, and AC is what the team actually spent.

Worked example: variances on an iterative project

A repair-request mini-app project has 80 user stories, each worth 5 story points (400 points in total), with each story point budgeted at $600 (that is, $3,000 per story), to be completed in 4 iterations. At the end of iteration 2, the plan called for 200 points (40 stories), actual delivery was 180 points (36 stories), and cumulative actual spending is $118,000.

  • PV = 200 × $600 = $120,000; EV = 180 × $600 = $108,000; AC = $118,000.
  • SV = $108,000 − $120,000 = −$12,000: behind schedule. CV = $108,000 − $118,000 = −$10,000: over budget.
  • Check: BAC = 400 × $600 = $240,000. At half of the planned schedule, PV = $240,000 × 50% = $120,000, which agrees with the figure above.

Variances are sometimes also expressed as percentages. The common ones are CV ÷ EV and SV ÷ PV, used to compare against the control threshold in the financial management plan. For example, with CV = −$25,000 and EV = $225,000, the cost variance is about −11.1%, which is outside an agreed ±5% range.

Worked examples

Example 1 Calculation: PV, EV and AC given, find the schedule variance

Question 1Example

A trade-show booth construction project currently has planned value of $6,000, earned value of $5,100 and actual cost of $4,500. Which of the following correctly states the schedule variance?

Show answer and explanation

Correct answer: A

PV, EV and AC are all given. The question asks for the schedule variance (SV), not the cost variance.

Schedule variance is the difference between earned value and planned value: SV = EV − PV. The value of the work completed is lower than the value planned to be complete, so the project is behind schedule. AC is a distractor here; it is used only for the cost variance. The answer is A.

  1. SV = EV − PV = $5,100 − $6,000 = −$900
  2. SV is below 0, so the project is behind schedule
  3. For contrast: CV = EV − AC = $5,100 − $4,500 = +$600 is the cost variance and is irrelevant to this question
  4. Check: SPI = $5,100 ÷ $6,000 = 0.85, below 1, consistent with behind schedule

Why the other options are wrong

  • B. $5,100 − $4,500 = +$600 is the cost variance (CV), not the schedule variance that was asked for. It does not answer the question.
  • C. The numbers are right but the subtraction is reversed: $6,000 − $5,100 = +$900. In variance formulas EV always comes first, and a negative result means behind schedule.
  • D. −$1,500 = $4,500 − $6,000, which is AC minus PV. AC and PV correspond to different amounts of work and cannot be subtracted directly.

Key takeaway SV = EV − PV measures schedule and CV = EV − AC measures cost. EV always comes first.

Variation If the question asked for cost variance, CV = $5,100 − $4,500 = +$600, under budget. If EV were $6,600, SV = +$600, ahead of schedule.

Something wrong with this question?

Report an issue with this question

Example 2 Calculation: translate the words, then judge the status

Question 2Example

A smart-door-access installation project has a planned duration of 24 months. In month 12 the project manager is reassigned and you take over. The handoff materials show that, to date, the value of the work that should have been completed according to the plan is $420,000, the value of the work actually completed is $390,000, and cumulative spending is $410,000. What is your assessment of the project's current status?

Show answer and explanation

Correct answer: B

The project manager takes over a project in progress. The handoff materials give three figures in words; they must first be mapped to PV, EV and AC before judging status.

“The value of the work that should have been completed according to the plan” is PV = $420,000; “the value of the work actually completed” is EV = $390,000; “cumulative spending” is AC = $410,000. Schedule compares EV with PV and cost compares EV with AC, and the two judgments are independent: the project is behind schedule and over budget, meaning spending exceeds the value of the work completed and the project is behind schedule. The answer is B.

  1. Translate: PV = $420,000, EV = $390,000, AC = $410,000
  2. SV = EV − PV = $390,000 − $420,000 = −$30,000, behind schedule
  3. CV = EV − AC = $390,000 − $410,000 = −$20,000, over budget
  4. Check: SPI = $390,000 ÷ $420,000 ≈ 0.93 and CPI = $390,000 ÷ $410,000 ≈ 0.95, both below 1. The answer is B

Why the other options are wrong

  • A. This compares AC of $410,000 directly with PV of $420,000 and concludes that spending is below plan. Cost must be judged by comparing EV with AC.
  • C. This reads the schedule variance sign backwards (PV − EV = +$30,000) and concludes the project is ahead of schedule.
  • D. Both variance signs are reversed (PV − EV = +$30,000 and AC − EV = +$20,000), the opposite of the real situation.

Key takeaway Map the words to PV, EV and AC first, then compare EV with PV and with AC.

Variation If cumulative spending were $380,000, CV = $390,000 − $380,000 = +$10,000, under budget, and the status would become “behind schedule, under budget”.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • SV = EV − PV and CV = EV − AC, with EV always first. Subtract the other way round and every sign is wrong.
  • Schedule compares EV with PV, and cost compares EV with AC. Do not compare AC directly with PV.
  • The basic results for SV and CV are dollar amounts. They can also be converted to variance percentages, but do not confuse them with the CPI and SPI of the next lesson.
  • SV = 0 does not necessarily mean the project was on time throughout. After the planned completion date, once all the scope is complete, EV = PV = BAC and SV is 0 (even if the project finished late). If a project finishes early, PV on the actual completion date is still below BAC and SV is positive, and late in the project SV loses its diagnostic value.
  • The words in the stem (should have been done by the plan, actually completed, cumulative spending) must first be translated into PV, EV and AC.

Key takeaways

Key point

  • SV = EV − PV: above 0 is ahead, 0 is on plan, below 0 is behind.
  • CV = EV − AC: above 0 is under budget, 0 is on budget, below 0 is over budget.
  • When only variances are given: EV = PV + SV and AC = EV − CV.
  • For adaptive projects, convert story points to budget: PV and EV come from the stories planned and the stories actually delivered.
  • Variances can be converted into percentages for comparison with the control threshold.

Lesson 3

Performance Indices: SPI and CPI, and Judging Project Status

Lesson video

Lesson overview

A variance is a dollar amount; an index is a ratio. An index turns “how many dollars off” into “how efficient we are”, so projects of different sizes can be compared directly, and the forecasts of completion in the next chapter use these indices too. The exam asks for earned value skills at several levels. First, know what an SPI or CPI above, equal to or below 1 means, which handles most questions. Second, be able to do the simple calculations SPI = EV ÷ PV and CPI = EV ÷ AC. Third, start from a budget, a duration and a percent complete, find PV, EV and AC yourself and judge the status. This lesson follows those three levels and also explains two late-project spots where people often judge wrongly. The previous lesson covered variances, and the next covers what to do once a variance is found. ECO: Process domain, Task 6 (Plan and manage finance), covering monitoring of financial variances.

The two indices

Key point

The schedule performance index (SPI) is a measure of schedule efficiency expressed as the ratio of earned value to planned value. Above 1 means ahead of schedule, exactly 1 means on schedule and below 1 means behind schedule. The cost performance index (CPI) is a measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost. Above 1 means under planned cost, exactly 1 means on planned cost and below 1 means over planned cost. A CPI of 0.8 means that for every $1 spent, only $0.80 worth of work was completed.

As with variances, EV is always the numerator. S is schedule, divided by PV; C is cost, divided by AC. A positive variance and an index above 1 are both good news; a negative variance and an index below 1 are both bad news.

SV / SPICV / CPIProject status
> 0 / > 1> 0 / > 1Ahead of schedule, under budget
> 0 / > 1< 0 / < 1Ahead of schedule, over budget
< 0 / < 1> 0 / > 1Behind schedule, under budget
< 0 / < 1< 0 / < 1Behind schedule, over budget

Combinations of indices often have readable causes behind them. If both indices are below 1, performance is poor: the project is both behind and over budget. A CPI below 1 with an SPI above 1 means costs are over but the schedule is ahead, which is common when the schedule is bought with crashing. A CPI above 1 with an SPI below 1 means costs are under but the schedule is behind, which may be related to too few resources being put in, but first analyze the root cause and the critical path; if the schedule really must be compressed, then evaluate options such as crashing (which applies only to critical path activities and can increase cost and/or risk) and fast tracking. If both indices are above 1, the team may be performing well, or the baseline may contain too much slack. If both equal 1, plan and execution are in close agreement.

From the facts to a judgment: a fixed set of steps

Work calculation questions in three steps (common exam practice): find the BAC, the duration, the percent complete and the spending; calculate PV, EV and AC; then calculate the variance or index and judge. In simple questions where both the planned and the actual percent complete are measured on a budget-weighted basis, you can use PV = planned percent complete × BAC and EV = actual percent complete × BAC; in general, PV and EV should be calculated from the time-phased performance measurement baseline and the budgets of the individual work packages. AC is taken directly as cumulative spending.

Comprehensive example: the status of a data dashboard project

A data dashboard project has a BAC of $150,000 and is planned for 15 weeks, with work spread roughly evenly. At the end of week 9: 60% should be complete according to the plan, 54% is actually complete, and cumulative spending is $96,000.

  • PV = $150,000 × 60% = $90,000; EV = $150,000 × 54% = $81,000; AC = $96,000.
  • SV = $81,000 − $90,000 = −$9,000; CV = $81,000 − $96,000 = −$15,000.
  • SPI = $81,000 ÷ $90,000 = 0.90; CPI = $81,000 ÷ $96,000 ≈ 0.84.
  • Judgment: the schedule is about 10% behind, and for every $1 spent only $0.84 worth of work is produced: behind schedule and over budget.
  • Check: SPI × PV = 0.90 × $90,000 = $81,000 = EV; CPI × AC = 0.84 × $96,000 ≈ $81,000 = EV. Both indices recover EV.

Worked example: only the variances and PV are given

A project reports PV = $100,000, SV = −$8,000 and CV = +$4,000.

  • EV = $100,000 − $8,000 = $92,000; AC = $92,000 − $4,000 = $88,000.
  • SPI = $92,000 ÷ $100,000 = 0.92; CPI = $92,000 ÷ $88,000 ≈ 1.05.
  • Conclusion: behind schedule, under budget. The cause is still to be analyzed (it may be too few resources, so analyze the root cause and the critical path before deciding on a response).

On an adaptive project that applies earned value analysis, work can be expressed in story points (story points are only an optional unit), while AC is still measured as actual cost. Suppose an iteration planned to deliver 45 story points and actually delivered 36: SPI = 36 ÷ 45 = 0.8. The formula did not change on an iterative project; the work is simply measured in story points.

Two late-project spots where people often judge wrongly

First, once the baseline completion date has been reached or passed and all the scope is complete, EV = PV = BAC, so SV is 0 and SPI is 1, even if the project actually finished late. If a project finishes early, PV at the actual completion may still be below BAC. Late in a project, SV and SPI lose their diagnostic value, and you have to look at the schedule itself.

Second, SPI measures the amount of all the work completed and does not distinguish the critical path. An overall SPI above 1 does not stop activities on the critical path from running late, and it is the critical path that determines the duration. When a question gives both the critical path SPI and the overall SPI, go by the critical path: a critical path SPI below 1 means the duration is at risk. As common exam practice, when time to market is the key objective and CPI is above 1 while SPI is below 1, evaluate how to recover the schedule first. Consider the critical path, remaining funds, forecast at completion, reserves and spending authority before evaluating crashing or fast tracking.

Worked examples

Example 1 Calculation: judge budget and schedule from the budget and percent complete

Question 1Example

A project with a $900,000 budget is planned to finish in 18 months, with planned work and budget spread evenly over that period. At month 9, the project has completed 45% of the work and cumulative spending is $380,000. What are the project's current budget and schedule status?

Show answer and explanation

Correct answer: C

PV, EV and AC are not given directly. Derive them from the budget, duration and percent complete, then judge budget and schedule separately.

Schedule compares EV with PV and cost compares EV with AC; the two judgments are independent. First calculate the three values: half the planned time has elapsed, so PV is $450,000; 45% is complete, so EV is $405,000; AC is $380,000. EV is below PV, so the project is behind schedule. EV is above AC, so the project is under budget. That is under budget and behind schedule. The answer is C.

  1. PV = $900,000 × 9 ÷ 18 = $450,000; EV = $900,000 × 45% = $405,000; AC = $380,000
  2. SV = $405,000 − $450,000 = −$45,000; SPI = $405,000 ÷ $450,000 = 0.90, behind schedule
  3. CV = $405,000 − $380,000 = +$25,000; CPI = $405,000 ÷ $380,000 ≈ 1.07, under budget
  4. Check: SPI × PV = 0.90 × $450,000 = $405,000 = EV; CPI × AC ≈ 1.066 × $380,000 ≈ $405,000 = EV. The answer is C

Why the other options are wrong

  • A. The cost judgment is right but the schedule judgment is wrong. This may come from comparing 45% complete with 42% spent ($380,000 ÷ $900,000) and concluding that more was done for less money. Schedule requires comparing EV with PV.
  • B. Both judgments are reversed: EV of $405,000 is above AC of $380,000, so the project is under budget, and EV is below PV of $450,000, so it is behind schedule.
  • D. The schedule judgment is right, but CV = +$25,000 means there is no overrun. The sign of CV has been read backwards.

Key takeaway Schedule compares EV with PV; cost compares EV with AC. The two judgments are independent.

Variation If cumulative spending were $430,000, CV = $405,000 − $430,000 = −$25,000, and the status becomes “over budget, behind schedule”, which is option D.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario judgment: the critical path SPI and the overall SPI disagree

Question 2Example

A market research project is midway through. A team member reports that the SPI on the critical path is 0.88, while the SPI for the project as a whole is 1.08. How should the project manager assess the project's schedule status?

Show answer and explanation

Correct answer: B

The project is midway through. The stem gives both the SPI on the critical path (0.88) and the SPI of the project as a whole (1.08), and asks for the schedule status.

The overall SPI measures the amount of all the work completed and does not distinguish whether the work is on the critical path. What determines the duration is the critical path, whose SPI is 0.88, below 1: the critical path is behind and the duration is at risk. Gains on non-critical paths cannot offset this. The answer is B.

Why the other options are wrong

  • A. The critical path SPI is below 1, so the schedule is not on plan, and certainly the duration is not risk-free. An overall SPI above 1 cannot hide this.
  • C. “The duration is at risk” is right, but “on schedule” is wrong: the critical path is already behind.
  • D. This is misled by the overall SPI of 1.08 and ignores the late critical path. Being ahead overall does not mean the duration is free of risk.

Key takeaway When both the critical path SPI and the overall SPI are given, focus on the critical path: late critical path activities point directly to a completion date risk, so look at the critical path SPI separately and judge the impact together with critical path analysis and schedule forecasts.

Variation If the critical path SPI were 1.05 and the overall SPI 0.90, critical path performance would currently be good, but you would still check the remaining schedule risk, whether float on non-critical activities has been used up, and whether the critical path has changed.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • An index is a ratio: SPI = EV ÷ PV and CPI = EV ÷ AC, with EV the numerator in both. Do not swap numerator and denominator.
  • Judge schedule from EV and PV, and cost from EV and AC. The two judgments are independent; do not let one carry over into the other.
  • “45% complete, 42% of the budget spent”: if the two percentages are on the same basis, EV = 0.45 × BAC and AC = 0.42 × BAC, so CPI ≈ 1.07 and you can say costs are under budget. But without the planned percent complete you cannot tell whether the schedule is ahead or behind.
  • The overall SPI does not represent the critical path. With an SPI above 1, the critical path may still be behind.
  • Once all the scope is complete and the data date has reached or passed the baseline completion date, SV returns to zero and SPI equals 1. Do not conclude from that that there was no schedule problem.
  • A CPI of 0.8 means that for every $1 spent only $0.80 worth of work is produced; it does not mean an 80% overrun.

Key takeaways

Key point

  • SPI = EV ÷ PV and CPI = EV ÷ AC; above 1 is favorable, below 1 is unfavorable and 1 is on plan.
  • Status: read schedule from SV / SPI and cost from CV / CPI. You should be able to read all four combinations.
  • Three steps for calculation questions (common exam practice): find BAC and the percentages; calculate PV, EV and AC; calculate the variance or index.
  • Checks: SPI × PV = EV and CPI × AC = EV.
  • Late in the project SPI tends toward 1. The overall SPI does not represent the critical path; when the critical path SPI is given, go by it.

Lesson 4

What the Project Manager Does After Finding a Variance

Lesson video

Lesson overview

Calculation is only a means. Scenario questions test the order of action once you have seen a variance. PMBOK 8 defines Monitor and Control Finances as the process of monitoring the project’s financial status, updating project finances, managing changes to the cost baseline and revenue forecasts, and ensuring that the project deliverables maintain their financial viability throughout the project life cycle. It also stresses that the value of financial measurements is not in the collection and dissemination of the data, but rather in the interactions about how to use the data to make value-adding, well-informed decisions and take appropriate actions. This lesson turns that idea into a sequence of actions: analyze first, then compare with the threshold, correct within your authority, go through change control when a baseline must change, and finally communicate. The previous lesson covered indices, and the next chapter uses indices to forecast. ECO: Process domain, Task 6 (Plan and manage finance), covering monitoring financial variances and working with the governance process.

The order of action: analyze first, then act

When you find a cost overrun or a schedule delay, work through the sequence below. (This order of action is common exam practice.)

  1. Analyze the cause before acting. The first step is to use variance analysis and trend analysis to find where the variance comes from, how large it is and whether it will persist, with root cause analysis where needed. Do not immediately add funding, add resources or cut scope.
  2. Compare with the control threshold. The financial management plan may specify variance thresholds for monitoring cost performance, to indicate an agreed-upon amount of variation to be allowed before some action should be taken; thresholds are typically expressed as percentage deviations from the baseline plan. If the variance is within the threshold, continue monitoring it; if the financial management plan or the analysis indicates that correction is needed, act within the project manager's authority. If it reaches or exceeds the threshold, take the actions the financial management plan prescribes; and if it also exceeds the project manager's authority or meets the escalation criteria, escalate through the governance process.
  3. Go through change control when a baseline must change. The cost baseline can be changed only through formal change control procedures. To add budget, draw on management reserve or adjust a baseline, submit a change request, which is approved, deferred or rejected by the people named in the change management plan or organizational procedures, with the change control board involved where applicable. Management reserve is typically released at the discretion of senior leadership or management (in some organizations the project manager or project management team has that discretion), and if using it requires adjusting the cost baseline, the baseline is updated through formal change control.
  4. Communicate and forecast. Combine work performance information and the revised forecast at completion (see the next chapter) into work performance reports, and report them to the sponsor and relevant stakeholders as the communications management plan prescribes.

When an overrun has already crossed the threshold and is a fact, the thing to do “first” is to record it in the issue log (so it is tracked) and start cause analysis at once. When a variance is only a trend that threatens to break through and has not yet crossed the threshold, analyze the cause first. The two statements do not conflict: recording and analyzing happen almost together, and both come before adding funding, raising a change request or capturing lessons learned. (This is common exam practice for the order of action.)

Here is a typical situation. A performance report shows CPI = 0.82 and SPI = 0.95, and the variance has exceeded the 10% control threshold set in the financial management plan, so you take the actions the financial management plan prescribes, escalating when it exceeds your authority or meets the escalation criteria. The order is as follows. First analyze where the variance comes from: a supplier price increase, or rework? If it is something you can handle within your delegated authority, take corrective action, such as adjusting resources or optimizing the process, and at the same time report the breach of the threshold as the financial management plan and governance process require. If you need additional budget, to draw on management reserve or to change the cost baseline, submit a change request under the change management plan and have it approved by the designated approvers (with the change control board participating or approving where applicable); using management reserve also has to follow the organization's authorization. At the same time update the forecast at completion and tell the sponsor the result. The wrong answer choices that are typically offered are “immediately ask the sponsor for additional budget” and “cut scope directly”; both skip analysis and authorization.

Worked example: has the variance crossed the threshold?

A cold-chain warehouse project has agreed with its sponsor that a cost variance within 8% is acceptable. After 4 months: EV = $310,000 and AC = $340,000.

  • CV = $310,000 − $340,000 = −$30,000; CPI = $310,000 ÷ $340,000 ≈ 0.91.
  • Cost variance percentage = CV ÷ EV = −$30,000 ÷ $310,000 ≈ −9.7%. The absolute value exceeds 8%, so the threshold is crossed.
  • The overrun has already happened, so it is an issue, not a risk: once you confirm the overrun has occurred, record it in the issue log so it is tracked, analyze the cause and develop measures at once, and submit a change request if needed. Do not rush to add budget or change the baseline before the impact analysis is complete.
  • Check: if AC were $330,000, CV = −$20,000 and −$20,000 ÷ $310,000 ≈ −6.5%, still within the threshold, so it is normally monitored; if the plan or analysis indicates that correction is needed, the project manager acts within their authority.

Three kinds of analysis, and telling issues from risks

Three kinds of data analysis are commonly used to monitor finances, and each answers a different question.

AnalysisQuestion it answersTypical use
Variance analysisHow far is actual performance from the baseline, and why?Calculate SV, CV, SPI and CPI; find the cause and degree of the variance
Trend analysisWhat will happen if the current trend continues?Forecast future outcomes from historical results; warn early of problems that may appear later and leave the team time to correct them
Reserve analysisAre the reserves still sufficient?Monitor the use of contingency reserve and management reserve; judge whether they are still needed, can be released or need to be increased

Telling risks from issues is another test point of this lesson. Suppose the cost curve is “heading to break through the baseline” but has not yet gone over. That is a developing variance, and the first step is to bring the team together to analyze actual costs and find causes, not to report it, raise a change or ask for help. If the cost variance has already crossed the control threshold, it is an issue that has already occurred: do root cause analysis to find where the overrun occurred, then develop a solution and judge whether the baseline should change and by how much. Do not register an overrun that has happened as a new risk: a risk is an uncertain event that has not yet occurred, and an overrun that has crossed the threshold goes in the issue log.

Two ways to compress a late schedule

Once the cause is understood and you have confirmed that the schedule must be recovered, two compression methods are commonly used.

  • Crashing: adding resources (overtime, extra people, expedited delivery) to shorten the duration for the least incremental cost. It works only for activities on the critical path where additional resources will shorten the activity's duration, and it may result in increased risk and/or cost. A CPI above 1 only means cost efficiency is favorable up to the data date; whether you can fund crashing also depends on remaining funds, the forecast at completion, reserves and the authority to use them.
  • Fast tracking: activities or phases normally done in sequence are performed in parallel for at least a portion of their duration. The price is possible rework, and risk goes up. It suits activities that can safely be partly overlapped and where overlapping will shorten the critical path; discretionary dependencies deserve particular review for whether they can be modified or removed, but they are not the only type of dependency that can be fast-tracked. When the budget is already overrun and no more money is allowed, fast tracking is usually the better fit than crashing. (Exam tip: this is common exam practice; you still have to look at the critical path and the risks.)

Differences between predictive and adaptive environments

  • A predictive project takes the cost baseline as its reference, calculates PV, EV and AC period by period, and measures variances against the baseline.
  • On an adaptive project the spending curve is flatter, and the budget can be allocated by quarter and revised each quarter (other phased approaches that suit the project's rhythm are also possible), so financial planning and control must be tailored accordingly. When the budget is nearly used up and the scope is not complete, first analyze the remaining budget, unfinished scope, expected value and forecast at completion. Under a fixed-budget constraint, then work with the product owner and other relevant stakeholders to reprioritize the backlog rather than adding money or people without analysis.
  • A hybrid project has both a baseline and iterations. In practice, calculate the measures separately and present them together; do not mix the figures of the two kinds of work.

Worked examples

Example 1 Scenario judgment: an overrun trend appears; what do you do first?

Question 1Example

A project's cost curve shows a trend toward breaking through the cost baseline, but the project has not actually gone over yet. To manage the budget well, what should the project manager do FIRST?

Show answer and explanation

Correct answer: A

The project is in execution and monitoring. The cost curve shows a trend toward breaking through the cost baseline, but no actual overrun has occurred yet. The first step in managing the budget must be identified.

A trend is not yet an overrun that has happened, and neither its cause nor its size is known. After a variance or trend appears, the first step is analysis: compare against actual costs to find where the variance comes from, how large it is and whether it will persist. Only then can you decide whether to correct, prevent, or change the baseline. So first convene the team, analyze actual costs and find the cause. The answer is A.

Why the other options are wrong

  • B. The overrun is only a trend, and its cause and size have not been established. Announcing an outcome to stakeholders now is neither accurate nor calm; notify them after analysis and a forecast are available.
  • C. Adding budget means changing the baseline, which goes through change control. Asking for money before the cause is understood means you do not know how much to ask for, or whether to ask at all.
  • D. When a trend appears, the project manager first acts within their authority under the financial management plan. The sponsor is brought in only when the matter exceeds that authority, meets escalation criteria, or needs a governance decision.

Key takeaway When a cost variance or trend appears, analyze the cause first, and only then talk about notification, change requests or asking for help.

Variation If cumulative cost has already exceeded the control threshold, the overrun has become an issue: analyze the variance and its root cause promptly, record and handle it according to the governance arrangements, and take corrective action or submit a change request if needed.

Something wrong with this question?

Report an issue with this question

Example 2 Calculation and scenario: what do you record first for an overrun that has crossed the threshold?

Question 2Example

A project manager is in charge of building a cold-storage warehouse center. Because the construction involves many uncertainties, the sponsor and the project manager agreed that a cost variance within 5% is acceptable. After 3 months of execution, the team's data show an actual cost (AC) of $250,000 and an earned value (EV) of $225,000. What should the project manager do FIRST?

Show answer and explanation

Correct answer: D

The sponsor agreed that a cost variance within 5% is acceptable. AC is $250,000 and EV is $225,000. First judge whether the variance crosses the threshold, then decide what to do first.

CPI = $225,000 ÷ $250,000 = 0.9 and CV = −$25,000, about −11.1% of EV, beyond the agreed 5%. The overrun has already happened, so it is an issue, not a risk. When an issue occurs, first record it in the issue log (so it is tracked) and carry out cause analysis; then develop measures and, if needed, submit a change request. The answer is D.

  1. CPI = EV ÷ AC = $225,000 ÷ $250,000 = 0.9
  2. CV = EV − AC = $225,000 − $250,000 = −$25,000
  3. Variance percentage = CV ÷ EV = −$25,000 ÷ $225,000 ≈ −11.1%; the absolute value exceeds 5%, so the threshold is crossed
  4. Check: if AC were $235,000, CV = −$10,000 and −$10,000 ÷ $225,000 ≈ −4.4%, within the threshold. Here it is crossed, so record it in the issue log first. The answer is D

Why the other options are wrong

  • A. The first action now is to log the issue and analyze its cause so it can be tracked and handled promptly. Lessons learned can be captured while analysis and handling go on, and with the cause not yet known there is not yet a complete lesson to record. So A is not the first action.
  • B. A change request comes after the issue has been recorded, its cause analyzed and a solution determined. It is a later step.
  • C. A risk is an uncertain event that has not yet occurred. The overrun has already happened, so it is handled as an issue and recorded in the issue log, not the risk register.

Key takeaway Calculate first whether the variance crosses the agreed threshold. An overrun that has crossed it is an issue, and it is recorded in the issue log first.

Variation If AC were $235,000, CV = −$10,000, about −4.4%, which is within 5%, so the project manager would normally continue monitoring and correct within their authority if the plan or analysis indicated that action was needed. If the agreed threshold were 12%, the project would also be within the threshold.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When a variance appears, the first step is to analyze the cause, not to add funding, add resources, cut scope, or report it first. If an overrun has already crossed the threshold and is a fact, record it in the issue log first and start cause analysis at the same time.
  • Within the threshold, normally continue monitoring and correct within the project manager's authority when needed. Beyond the threshold, first take the measures the financial management plan prescribes; only if it also exceeds your authority or meets the escalation criteria do you escalate through the governance process.
  • The cost baseline can be changed only through formal change control. Record and analyze issues promptly; if a proposed action would change a controlled artifact or a baseline, raise a formal change request and, before approval, add a complete impact analysis of cost, schedule, risk and so on.
  • An overrun that has already occurred is an issue, recorded in the issue log. A risk is an uncertain event that has not yet occurred; do not register an overrun that has occurred as a new risk.
  • Capturing lessons learned is not the first thing to do. It can be recorded in step with the handling and completed after the issue is resolved.
  • Crashing adds resources and may increase cost and/or risk; fast tracking overlaps work and may increase rework and risk. When the budget is already overrun, fast tracking is usually the better fit (common exam practice).

Key takeaways

Key point

  • Monitor and Control Finances: monitor financial status, manage changes to the cost baseline and revenue forecasts, and ensure the project remains financially viable.
  • Order of action: analyze the cause, compare with the control threshold, correct within your authority, raise a change request if the baseline must change, then communicate and update the forecast.
  • Three analyses: variance analysis asks how far off, trend analysis asks what will happen, reserve analysis asks whether reserves are enough.
  • An overrun that has already occurred and crossed the threshold goes in the issue log first, with cause analysis started at once; a trend still developing is analyzed first.
  • Schedule behind: crashing works by adding resources and fast tracking by overlapping; when the budget is overrun, consider fast tracking first (common exam practice).

This chapter has 49 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.