Estimate at Completion

PMP · Finance · 2 lessons · about 25 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Earned value management tells us how the project is doing now. Forecasting answers the next question: if things continue like this, how much will it cost in the end and how long will it take? Earned value analysis is one of the data analysis techniques in Monitor and Control Finances. The EAC it produces is recorded in cost forecasts, duration forecasts feed into schedule forecasts, and the results are communicated to the relevant stakeholders. The chapter has two lessons. The first covers the four ways to calculate estimate at completion (EAC), and the estimate to complete (ETC) and variance at completion (VAC) that follow from it. The second covers the to-complete performance index (TCPI), which turns the question around: to finish within budget, how efficient must we be from now on? It then applies the same thinking to time to forecast the completion duration. EAC calculations do not appear often on the exam, but the assumption behind each formula is logical, and once you understand it you do not need to memorize anything.

By the end of this chapter you should be able to do the following. State that EAC = AC + ETC and choose one of the four methods according to whether the variance will continue and whether the remaining work has been re-estimated. Derive ETC and VAC from EAC and read the sign of VAC. Calculate TCPI against BAC or against an approved EAC, and read the gap between it and CPI. Forecast completion duration from SPI using a simplified linear method (common exam practice), only when the schedule is linear and the question explicitly asks you to extrapolate the current SPI; a real schedule forecast relies on the schedule model, the critical path and the remaining durations. When TCPI is much higher than the current CPI, weigh risk, time remaining and technical performance to assess whether BAC is still achievable; if it is clearly no longer viable, consider the forecasted EAC, and raise a change request if a baseline has to change. Once the forecasted EAC is approved, it can replace BAC in the TCPI calculation.

Lessons in this chapter

Chapter map

EAC = AC + ETC           ETC = EAC − AC           VAC = BAC − EAC  
Atypical: AC + (BAC − EV)   Typical: BAC ÷ CPI   Schedule and cost both matter: AC + (BAC − EV) ÷ (CPI × SPI)   Re-estimate: AC + new ETC  
TCPI = (BAC − EV) ÷ (BAC − AC); when the target is an approved EAC: (BAC − EV) ÷ (EAC − AC)  
Forecast total duration = time elapsed + (planned total duration − planned duration for the work completed) ÷ SPI  

How the exam tests this

Most questions are one- or two-step calculations: decide the situation first, then plug into the formula. If the stem says “one-time” or “isolated”, use atypical. If it says “continues at the current performance”, use typical. If it says “re-estimated”, add the new ETC. If it asks for ETC or VAC, convert one more step from EAC. TCPI often appears together with CPI, and the test point is whether you need a change. The trap in duration forecasting is using the wrong index: for duration, use SPI. Nearly every wrong option corresponds to a specific calculation mistake, so when you review, compare against the explanation and find which kind of mistake you make.

Study tips and practice

  • First unify the first three EAC formulas as “AC + remaining budget ÷ performance”, then remember that the performance term is 1, CPI or CPI × SPI.
  • Check every EAC against the sign of VAC: with the BAC ÷ CPI formula, CPI below 1 means EAC should be above BAC. If you assume the rest of the work will follow a new estimate or other performance, rely on the formula you chose and the new ETC.
  • Draw AC, ETC, EAC, BAC and VAC on a timeline, then answer which segment the question asks about.
  • After this chapter, go on to the chapter on net present value, which moves from monitoring to investment evaluation.

Lesson 1

Estimate at Completion (EAC): Four Methods, Plus ETC and VAC

Lesson video

Lesson overview

Earned value management tells us how the project is doing now; forecasting answers the question: if it continues like this, how much will it cost in the end? In Monitor and Control Finances, cost forecasts are made through earned value analysis and trend analysis. The EAC that results is recorded in cost forecasts and communicated to the sponsor and other relevant stakeholders. This lesson covers three quantities: estimate at completion (EAC), estimate to complete (ETC) and variance at completion (VAC). The focus is on the four methods of calculating EAC and how to decide from the stem which one to use. To put it in proportion: the meaning of SPI and CPI is a must-know foundation, while EAC calculations appear less often, so concentrate on the assumption behind each formula rather than memorizing. Make sure you have mastered BAC, PV, EV, AC, CPI and SPI from the previous chapter. ECO: Process domain, Task 6 (Plan and manage finance), covering anticipating future financial challenges.

EAC: what has been spent plus what is still to be spent

The estimate at completion (EAC) is “the expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete”:

The budgeted value of the remaining work is BAC − EV. What the remaining work will cost depends on how efficiently the work will be done from now on. That gives four methods. The deciding questions are mainly these: is the original estimate still valid, will the current cost variance repeat, and will both cost and schedule affect the remaining work?

SituationBasis for choosingFormula
Atypical varianceThe current variance is a one-off and the remaining work will be done at the originally planned efficiency
Typical varianceThe current cost performance will continue
Schedule and cost both affectThe remaining work is affected by both CPI and SPI (for example, it must be finished by a fixed date)
Re-estimateThe original estimate is no longer valid and the remaining work is re-estimated bottom-up

The first three formulas share one structure: , where “performance” is 1, CPI or CPI × SPI. Once you see this you do not need to memorize: if efficiency matches the budget, divide by 1; if efficiency continues, divide by CPI; if efficiency is also affected by schedule, divide by the product of the two indices.

Signals in the stem decide which to use. “Isolated”, “the problem has been resolved” and “the rest will proceed as planned” point to atypical. “Continues at the current performance” and “this is expected to persist” point to typical. “The remaining work has been re-estimated” and “the original estimate was wrong” point to re-estimate: use AC plus the new ETC directly and do not use CPI again. When nothing is stated, treat the variance as typical, that is, BAC ÷ CPI (common exam practice).

Worked example: one data set, four forecasts

An outpatient registration system upgrade has BAC = $80,000 and a planned duration of 10 weeks. At the end of week 4, EV = $24,000, AC = $30,000, and 40% should have been complete, so PV = 80,000 × 40% = $32,000.

  • CPI = 24 ÷ 30 = 0.8; SPI = 24 ÷ 32 = 0.75.
  • Atypical: EAC = 30,000 + (80,000 − 24,000) = 30,000 + 56,000 = $86,000.
  • Typical: EAC = 80,000 ÷ 0.8 = $100,000. Check: 30,000 + 56,000 ÷ 0.8 = 30,000 + 70,000 = 100,000.
  • CPI × SPI: EAC = 30,000 + 56,000 ÷ (0.8 × 0.75) = 30,000 + 56,000 ÷ 0.6 ≈ $123,300.
  • Re-estimate: the team re-estimates the remaining work at $65,000, so EAC = 30,000 + 65,000 = $95,000.
  • Comparison: for the same project, different assumptions give forecasts from $86,000 to $123,300. The assumption matters more than the formula.

Worked example: re-estimating the remaining work

A website redesign has four tasks with budgets of $25,000, $40,000, $55,000 and $30,000. The first two are complete, with actual costs of $27,000 and $36,000. The team re-estimates the remaining two tasks at $58,000 and $28,000.

  • BAC = 25 + 40 + 55 + 30 = $150,000; AC = 27 + 36 = $63,000.
  • EAC = 63 + 58 + 28 = $149,000, slightly below BAC.
  • Check: the completed part saved 25 + 40 − 63 = $2,000. The remaining budget is 55 + 30 = 85 against a re-estimate of 86, which is $1,000 more. Net saving $1,000, consistent with $150,000 − $149,000 = $1,000.

ETC and VAC

The estimate to complete (ETC) is “the expected cost to finish all the remaining project work.” ; in the re-estimate situation, ETC comes directly from the new bottom-up estimate. The variance at completion (VAC) is “a projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion”: . VAC greater than 0 means the project is expected to come in under planned cost; equal to 0 means at planned cost; less than 0 means over planned cost, that is, an overrun.

The three quantities are easiest to see on a timeline. AC has already been incurred, ETC is still to be incurred, and together they make EAC; the difference between BAC and EAC is VAC. Figure 1 draws this relationship with the numbers from the typical case above.

Figure 1: Relationship of BAC, AC, ETC, EAC and VAC

In the typical case, ETC = 100,000 − 30,000 = $70,000, which can also be calculated directly as (80,000 − 24,000) ÷ 0.8 = 70,000. VAC = 80,000 − 100,000 = −$20,000, so a $20,000 overrun is expected. VAC is easily confused with CV: CV is the variance that has already occurred at this moment, while VAC is the forecast variance at completion. One looks at now, the other at the end point.

This is the value of trend analysis: you do not wait for the overrun to happen and then report it; you warn before completion and leave the team time to correct. When EAC exceeds BAC by a large amount and passes the threshold, the project manager records the forecast and communicates it to the relevant stakeholders, analyzes the cause and corrective options, and then, following the financial management plan and governance process, decides whether to raise a change request or escalate.

Worked examples

Example 1 Calculation: a one-off overrun; find the estimate at completion

Question 1Example

A community elder-care platform development project has a budget at completion of $120,000 set in the project management plan. Actual cost to date is $75,000 and earned value is $60,000. The project manager's analysis concludes that the overrun is a one-time problem caused by rework on early requirements and that the remaining work can be completed at the originally budgeted efficiency. What is the forecast estimate at completion?

Show answer and explanation

Correct answer: B

BAC is $120,000, AC is $75,000 and EV is $60,000. The overrun is a one-time effect of requirements rework, and the remaining work will be done at the originally budgeted efficiency. Find EAC.

“One-time” and “at the originally budgeted efficiency” show that the variance will not continue, so this is an atypical variance. EAC = AC + (BAC − EV): the money already spent plus the budgeted value of the remaining work. The answer is B.

  1. Budgeted value of the remaining work = BAC − EV = 120 − 60 = $60,000
  2. EAC = AC + (BAC − EV) = 75 + 60 = $135,000
  3. VAC = BAC − EAC = 120 − 135 = −$15,000, so a $15,000 overrun is expected
  4. Check: the overrun already incurred is AC − EV = 75 − 60 = $15,000. After a one-time overrun it does not grow, which matches VAC, so the answer is B

Why the other options are wrong

  • A. $60,000 is only the budgeted value of the remaining work, BAC − EV, which is ETC. It leaves out the $75,000 already spent.
  • C. $150,000 = 120 ÷ 0.8 (CPI = 60 ÷ 75 = 0.8). That is the typical-variance calculation. The stem says the overrun is one-time, so you cannot assume the low efficiency continues.
  • D. $195,000 = 75 + 120. It adds the full budget again without deducting the budgeted value of the work already done.

Key takeaway If the variance is a one-time event, use EAC = AC + (BAC − EV).

Variation If the project manager judged that the low efficiency would continue, EAC = 120 ÷ 0.8 = $150,000 and VAC = −$30,000. If the remaining work were re-estimated at $70,000, EAC = 75 + 70 = $145,000.

Something wrong with this question?

Report an issue with this question

Example 2 Calculation: efficiency continues; find the estimate to complete

Question 2Example

An equipment installation project has a budget at completion of $90,000, current earned value of $36,000 and actual cost of $45,000. The project manager expects cost efficiency from now on to stay the same as it is now. What is the estimate to complete (ETC)?

Show answer and explanation

Correct answer: C

BAC is $90,000, EV is $36,000, AC is $45,000, and cost efficiency from now on will be the same as now. What must be calculated is how much more will be spent (ETC), not total cost.

Cost efficiency continues, so this is a typical variance, and the remaining work must be adjusted by the current CPI. First calculate CPI, then divide the remaining budget by CPI to get the money still to be spent. The answer is C.

  1. CPI = EV ÷ AC = 36 ÷ 45 = 0.8
  2. EAC = BAC ÷ CPI = 90 ÷ 0.8 = $112,500
  3. ETC = EAC − AC = 112,500 − 45,000 = $67,500
  4. Check: calculating directly, (BAC − EV) ÷ CPI = (90 − 36) ÷ 0.8 = $67,500. They agree, so the answer is C

Why the other options are wrong

  • A. $45,000 = BAC − AC is the budget at completion minus the money already spent. It is neither the budgeted value of the remaining work (BAC − EV = $54,000) nor adjusted for efficiency.
  • B. $54,000 = BAC − EV is the budgeted value of the remaining work. It equals ETC only when efficiency matches the budget, and here CPI is 0.8.
  • D. $112,500 is EAC, the total cost at completion. It does not deduct the $45,000 already spent.

Key takeaway ETC = EAC − AC; under a typical variance, ETC = (BAC − EV) ÷ CPI.

Variation If the variance were a one-time event, ETC = BAC − EV = $54,000. If the remaining work were re-estimated at $60,000, ETC is simply $60,000.

Something wrong with this question?

Report an issue with this question

Example 3 Scenario: reading the variance at completion

Question 3Example

A project has a budget at completion of $200,000, current earned value of $80,000 and actual cost of $100,000. The project manager reforecasts at the current cost efficiency and calculates a variance at completion of −$50,000. The sponsor asks what the latest forecast means. Which conclusion should the project manager report?

Show answer and explanation

Correct answer: A

BAC is $200,000, EV is $80,000 and AC is $100,000. Forecasting at the current cost efficiency gives a variance at completion VAC = −$50,000. What should be reported to the sponsor?

VAC = BAC − EAC measures the budget variance at completion. A negative VAC means EAC is above BAC: EAC = 200 + 50 = $250,000, so the project is expected to finish $50,000 over the budget at completion. This is a forecast of the end point, not a variance that has already occurred. The answer is A.

Why the other options are wrong

  • B. The variance to date is CV = EV − AC = 80 − 100 = −$20,000, only $20,000 overspent. VAC is a forecast for completion.
  • C. The sign is read backward: a positive VAC means an expected saving, and a negative VAC means an expected overrun.
  • D. The estimate to complete is ETC = EAC − AC = 250 − 100 = $150,000, not $50,000. The $50,000 is the expected total overrun.

Key takeaway VAC = BAC − EAC. A negative value means an overrun is expected at completion, not that one has already occurred.

Variation If VAC = +$30,000, then EAC = BAC − 30, a saving of $30,000 is expected. If asked about the variance to date, look at CV, not VAC.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Typical variance uses BAC ÷ CPI; atypical variance uses AC + (BAC − EV). First read the stem to decide whether the variance will continue.
  • If there is a “new estimate”, use AC plus the new ETC and do not divide by CPI again.
  • Do not confuse EAC with BAC: BAC is the approved total budget, while EAC is the total cost forecast from current performance.
  • ETC is what is still to be spent and equals EAC − AC. It is not EAC, and it is not BAC − AC.
  • VAC = BAC − EAC; a negative value means an overrun is expected at completion. It is a forecast, not the variance already incurred (that is CV).
  • With the typical-variance formula EAC = BAC ÷ CPI, CPI below 1 means an overrun and EAC should be above BAC; if you get an EAC below BAC, the direction is wrong. For other situations (re-estimate, CPI × SPI and so on) you still judge by the formula chosen.

Key takeaways

Key point

  • EAC = AC + ETC; ETC = EAC − AC; VAC = BAC − EAC.
  • Four methods: atypical AC + (BAC − EV); typical BAC ÷ CPI; CPI × SPI when both affect the work; re-estimate AC + new ETC.
  • Basis for choosing: whether the variance will repeat; with no statement, treat it as typical (common exam practice).
  • A negative VAC means an overrun is expected at completion; VAC looks at the end point, CV looks at now.
  • Three steps to solve: find BAC, EV and AC and compute the indices; decide the situation; plug into the formula, then convert to ETC or VAC as asked.

Lesson 2

To-Complete Performance Index (TCPI) and Forecasting Completion Duration

Lesson video

Lesson overview

EAC answers “how much will it cost in the end?” The to-complete performance index (TCPI) turns the question around: to finish the remaining work within a given budget, what cost efficiency must we achieve from now on, and is that realistic? It is a tool for judging whether a target is achievable. The second half of the lesson applies the earned value idea to time and uses the schedule performance index (SPI) to forecast how much longer the project needs. Neither part is hard; the difficulty is which quantity is in the numerator and which in the denominator. These questions come up with low probability, and when they do they usually test a single conversion step, so understanding the structure is enough. The previous lesson covered EAC, ETC and VAC, and the next chapter covers net present value and investment evaluation. ECO: Process domain, Task 6 (Plan and manage finance), covering monitoring financial variances.

TCPI: how efficient must the remaining money be

The to-complete performance index (TCPI) “is a measure of the cost performance that should be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.” The numerator is the budgeted value of the work still to be done, and the denominator is the money left. The denominator depends on the target:

TargetFormula
Still aiming at BAC (BAC is still viable)
BAC no longer viable; aiming at the approved EAC

How to remember it: CPI = EV ÷ AC; TCPI subtracts once from the numerator and once from the denominator: the numerator is BAC − EV and the denominator is BAC − AC (EAC − AC when the target is EAC).

Interpretation: TCPI is how much work, in dollars of budget, must be earned for every dollar spent from now on. A TCPI above 1 is hard to achieve: you must be more efficient than planned from now on, and the larger the value, the harder. A TCPI equal to 1 means finishing exactly with planned efficiency. A TCPI below 1 means you can finish even if future efficiency is below plan, which is relatively comfortable.

Worked example: is the target still realistic?

A digital showroom project has BAC = $140,000. So far EV = $50,000 and AC = $70,000.

  • CPI = 50 ÷ 70 ≈ 0.71.
  • Targeting BAC: TCPI = (140 − 50) ÷ (140 − 70) = 90 ÷ 70 ≈ 1.29.
  • Interpretation: so far each dollar spent has earned only $0.71 of work, but the money left demands $1.29 of work per dollar spent. Jumping from 0.71 to 1.29 is almost unrealistic, so you should consider BAC to be no longer viable.
  • Management approves a new target of EAC = $190,000: TCPI = 90 ÷ (190 − 70) = 90 ÷ 120 = 0.75. This means that if efficiency stays above 0.75 from now on, the new target is met. The earlier 0.71 is still slightly lower, so correction must continue.
  • Check: read TCPI together with CPI. When TCPI is higher than CPI, the larger the gap, the more cost performance must improve relative to the current level, and the more doubtful the target. If TCPI is not higher than CPI, there is no need to demand a large improvement on this basis.

Handling logic: if TCPI is far above 1 and actual cost performance has not improved for a long time, the original budget is no longer realistic. The project manager should assess whether finishing within the original budget is still feasible. If it is not, forecast, record and communicate a new EAC; once the people with authority endorse it, it becomes the new target. If the cost baseline must also be modified, raise a change request and approve it through change control. You should not push through with overtime, release management reserve on your own to cover the gap, or keep watching and hope things improve. PMBOK 8 also states that if it becomes obvious that BAC is no longer viable, the project manager should consider the forecasted EAC, and once approved, the EAC may replace BAC in the TCPI calculation.

Forecasting completion duration with performance indices

What follows is a simplified linear method (common exam practice), which assumes planned work and budgeted value are spread evenly over the planned duration, so percent complete equals percent of budgeted value. It applies the earned value idea to time by replacing dollars with time. In general you should take PV from the schedule baseline, or use earned schedule, and forecast the duration from the schedule model, the critical path and the remaining durations. The idea: time already used is like “AC”, the planned duration of the work completed is like “EV”, and then you divide by schedule performance.

There are three common cases. If later schedule performance stays at the current level, SPI is the current value. If it improves after resources are added, SPI is the new value given in the question. If the remaining work proceeds as originally planned, SPI is 1. If later performance “stays at the current level”, the formula reduces to: forecast total duration = planned total duration ÷ SPI.

Worked example: three cases for forecasting duration

A data migration task is planned for 24 days, and planned work and budgeted value are spread evenly across the 24 days (on day 10, 10/24 ≈ 41.67% should be complete). At the end of day 10 you check and find 30% complete.

  • Planned duration for the work completed = 24 × 30% = 7.2 days; remaining planned duration = 24 − 7.2 = 16.8 days.
  • Current SPI = EV ÷ PV = 30% ÷ (10 ÷ 24) = 7.2 ÷ 10 = 0.72.
  • Performance continues: forecast total duration = 10 + 16.8 ÷ 0.72 = 10 + 23.3 ≈ 33.3 days, which also equals 24 ÷ 0.72 ≈ 33.3 days.
  • Remaining work proceeds as planned: 10 + 16.8 = 26.8 days.
  • More people are added and schedule performance on the remaining work rises to 1.2: 10 + 16.8 ÷ 1.2 = 10 + 14 = 24 days, exactly recovering the plan.

Note that when the question asks about duration you use SPI, not CPI. An SPI below 1 means the project is behind and the duration should get longer, so you divide the planned duration by SPI rather than multiplying.

Worked examples

Example 1 Scenario: TCPI is far above CPI; what do you do

Question 1Example

A project is in mid-execution, with a budget at completion of $500,000. The budgeted value of the work completed is $150,000 and actual cost is $250,000. For the past several months the team's cost performance index has held steady at about 0.6, with no sign of improvement. The project manager calculates that to finish within the original budget, the to-complete performance index for the remaining work is 1.4. What is the most appropriate action for the project manager?

Show answer and explanation

Correct answer: A

The project is in mid-execution: BAC is $500,000, EV is $150,000, AC is $250,000, CPI has been steady at about 0.6, and the TCPI needed to finish within the original budget is 1.4.

TCPI is how much work must be completed for every dollar spent from now on. ($500,000 − $150,000) ÷ ($500,000 − $250,000) = 1.4, but actual performance has been only 0.6, and more than doubling it overnight is almost unrealistic. The appropriate action is to assess first whether finishing within the original budget is feasible. If it is not, reforecast EAC and have someone with authority approve it as the new target; if the cost baseline must change, raise a change request. In that case TCPI is calculated as (BAC − EV) ÷ (EAC − AC). The answer is A.

Why the other options are wrong

  • B. There is no basis for lifting cost performance from 0.6 to 1.4 by overtime. Overtime also pushes costs up, and the efficiency target itself is unrealistic.
  • C. Management reserve is outside the cost baseline and is usually released at the discretion of senior management (in some organizations the project manager or team may decide), following organizational rules. The problem with C is that it uses reserve to mask a known, persistent inefficiency and claims to hold the original budget without first assessing feasibility.
  • D. A TCPI well above 1 is already a clear warning, and cost performance has held at 0.6 for months with no sign of recovering on its own. Continuing to watch is inaction.

Key takeaway When TCPI is far above 1 and efficiency is not improving, assess the feasibility of the original budget, reforecast and use the approved EAC as the new target, and go through change control if a baseline must change.

Variation If management approves a new EAC = $650,000, then TCPI = 350 ÷ (650 − 250) = 0.875, below 1. However, it is still above the current CPI of 0.6, so substantial improvement is required; whether the target is realistic still depends on risk, time remaining, technical performance, and the ability to improve.

Something wrong with this question?

Report an issue with this question

Example 2 Calculation: performance stays unchanged; forecast the completion months

Question 2Example

A project has a planned duration of 10 months, a budget at completion of $40,000, actual cost of $14,000, earned value of $12,000 and planned value of $15,000. Assume planned value accumulates evenly over time and that future schedule performance stays at the current SPI level. How many months in total are expected to be needed to complete the project?

Show answer and explanation

Correct answer: D

The question is clear that what is to be forecast is completion time, not cost, so the schedule performance index (SPI) should be used.

For duration, use SPI. Under the linear simplifying assumption set in the stem (planned value accumulates evenly and SPI stays constant), forecast total duration = planned duration ÷ SPI. This is a simplified method that is common exam practice; on a real project you would forecast from the updated schedule model and the remaining durations. An SPI below 1 means behind schedule, so the duration should be longer than planned. The answer is D.

  1. SPI = EV ÷ PV = 12 ÷ 15 = 0.8
  2. Performance continues: forecast total duration = planned duration ÷ SPI = 10 ÷ 0.8 = 12.5 months
  3. Check: 12.5 × 0.8 = 10, equal to the planned duration, so they agree. BAC and AC are distractor figures. The answer is D

Why the other options are wrong

  • A. 10 × 0.8 = 8 multiplies in the wrong direction. An SPI below 1 means behind schedule, so the duration must get longer, not shorter.
  • B. 10.8 months adds only the lag already incurred, about 0.75 month (3 ÷ 40 × 10), to the planned duration, assuming no further lag, which does not match “performance stays unchanged”.
  • C. This uses CPI: 10 ÷ (12 ÷ 14) ≈ 11.7. CPI reflects cost efficiency; use SPI to forecast duration.

Key takeaway Use SPI, not CPI, to forecast completion duration; when performance continues, forecast total duration = planned duration ÷ SPI.

Variation If EV were exactly equal to PV ($15,000), SPI = 1 and the forecast total duration is still 10 months. If EV were only $10,000, SPI = 10 ÷ 15 ≈ 0.67 and the forecast total duration = 10 ÷ 0.67 = 15 months.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The numerator of TCPI is the budgeted value of the remaining work, BAC − EV, and the denominator is the money left. It is not the EV ÷ AC of CPI.
  • Whether the target is BAC or EAC depends on whether the stated budget is still viable. When the original BAC is clearly no longer viable and the forecasted EAC has been approved as the new management target, use the EAC version; if the question says a budget baseline was approved and updated, calculate with the updated BAC.
  • A TCPI above 1 is a warning, not “high efficiency”; the larger it is, the harder the work is to complete.
  • Forecast duration with SPI, not CPI. An SPI below 1 lengthens the duration, so divide by SPI.
  • “Schedule performance stays at the current level” differs from “the remaining work proceeds as planned”: in the first, SPI takes the current value; in the second, SPI is 1.

Key takeaways

Key point

  • TCPI = (BAC − EV) ÷ (BAC − AC); when the target is EAC, the denominator becomes EAC − AC.
  • TCPI above 1 is harder to achieve, equal to 1 requires the planned efficiency, and below 1 is easier to achieve; read it together with CPI.
  • TCPI far above 1 with no improvement: assess whether the budget is still viable; if it is not, reforecast and use the approved EAC as the new target; go through change control only if the cost baseline must change.
  • Forecast total duration = time elapsed + (planned total duration − planned duration for the work completed) ÷ SPI.
  • Duration uses SPI and cost uses CPI; first decide what the question is asking.

This chapter has 15 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.