Net Present Value and Value Evaluation

PMP · Finance · 3 lessons · about 37 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

A project is an investment made to create value. The earlier chapters dealt with how money is spent and managed; this chapter answers “is this money worth spending?” PMBOK 8 lists value definition and value maximization as key concepts of the Finance performance domain: organizations often measure project success with metrics such as return on investment, internal rate of return, payback period or return on assets, and value can also be social or environmental value, or intangible value such as customer satisfaction and innovation. The chapter has three lessons. First, present value, discounting and net present value, the most important calculation. Second, internal rate of return, payback period, return on investment and benefit-cost ratio, with what each means and the selection criterion for each. Third, the seven types of cost, with the emphasis on sunk cost and opportunity cost. The exam focuses on understanding meaning and making decisions.

By the end of this chapter you should be able to do the following. Use the formula to discount future money to present value, calculate the net present value of a multi-year project and decide whether it is financially acceptable. When comparing mutually exclusive projects, know that the default choice is the one with the largest positive NPV. State the meaning and selection criterion of internal rate of return, return on investment, benefit-cost ratio and static payback period, and calculate a static payback period. Distinguish direct from indirect, fixed from variable, and sunk from opportunity cost, and ignore sunk cost in decisions. Understand that value is more than profit.

Lessons in this chapter

Chapter map

Present value PV = FV ÷ (1 + r)ⁿ  
NPV = Σ (t = 1…n) CFt ÷ (1 + r)ᵗ − I0 (I0 is the initial investment); NPV > 0 is usually accepted; among mutually exclusive options choose the largest positive value  
IRR: the discount rate that makes NPV = 0; larger is better       ROI: net return as a proportion of the investment (this lesson commonly uses the average annual basis); larger is better  
Static payback period: includes construction when there are no inflows during it and payback is measured from project start; shorter is better            BCR: benefits ÷ costs; accept if greater than 1  
Cost types: direct / indirect, fixed / variable, life cycle, sunk (excluded from decisions), opportunity (value of the option given up)  

How the exam tests this

Calculation questions concentrate on present value, static payback period and opportunity cost, each taking one or two steps. The core of the scenario questions is “which metric supports which decision”: to compare the value of several investment paths, use net present value; to find the average annual return as a share of the investment, use return on investment; to ask how long until the money is recovered, use payback period; for continue-or-stop decisions, do not look at the money already invested. PMBOK 8 also stresses the many faces of value, so expect questions that distinguish “is it financially worthwhile?” from “is it worth doing given its overall value?”

Study tips and practice

  • Present value uses division, and you discount for as many years as there are; after calculating, check by multiplying back.
  • The static payback period starts accumulating from when the initial investment is made. If there is a construction period with no cash inflow and the starting point is the project start, the construction period counts in the payback period. Write out the cumulative value for each year, find the year it turns positive, then convert.
  • Remember that sunk cost does not enter decisions, and opportunity cost is the value of the best feasible alternative given up, not the difference.
  • This ends the whole Finance topic. Go back to the mind map and restate the four processes and how the chapters relate in your own words.

Lesson 1

Present Value, Discounting and Net Present Value (NPV)

Lesson video

Lesson overview

A project is an investment made to create value. Selecting projects, writing a business case and deciding whether a project is worth continuing usually require financial metrics to measure the return on investment (value can also be intangible, and where necessary non-financial measures such as regulatory compliance and social impact are used too). PMBOK 8 lists “value definition” as a key concept of the Finance performance domain: organizations use metrics such as return on investment, internal rate of return, payback period or return on assets to measure project success and alignment with organizational goals. This lesson starts from the most basic step: $1 today is not worth the same as $1 a year from now, so future money has to be converted into today's value. That is present value; discounting all of a project's cash flows and adding them up gives net present value. For these metrics the PMP exam focuses on understanding meaning and making decisions; when calculations appear, they are generally short, one- or two-step applications. The next lesson covers the other metrics. ECO: Process domain, Task 3 (Help ensure value-based delivery) and Task 6 (Plan and manage finance).

Present value and discounting

A dollar today is worth more than a dollar a year from now. This is the time value of money. Converting future money into today's value is called discounting; the converted value is the present value (PV), and the rate used is the discount rate.

FV is the amount received (or paid) at some future point, r is the discount rate, and n is the number of years. You discount for as many years as there are, and you must divide: the further away the money and the higher the discount rate, the smaller the present value. The discount rate usually reflects the cost of capital or the opportunity cost of giving up other investments.

Common trap

Here PV means “present value”, which has the same abbreviation as “planned value” in earned value management but a completely different meaning. Read the context: where a discount rate and a number of years appear, it is present value.

Worked example: which payment option is worth more

A customer offers two ways to pay: $100,000 in one payment a year from now, or $118,000 in one payment three years from now. The discount rate is 8% per year.

  • Present value of option 1: 100,000 ÷ 1.08 ≈ $92,593.
  • Present value of option 2: 118,000 ÷ 1.08³ = 118,000 ÷ 1.2597 ≈ $93,672.
  • Option 2 looks like $18,000 more, but discounted to today it is only about $1,080 more than option 1. If the discount rate rises to 10%, option 1 is worth 100,000 ÷ 1.10 ≈ $90,909 and option 2 is worth 118,000 ÷ 1.331 ≈ $88,655, so option 2 is now lower. The higher the discount rate, the more the later money loses.
  • Check: 93,672 × 1.08³ ≈ 118,000, matching the given amount.

Net present value (NPV)

Net present value is the sum of the discounted net cash flows of each period (cash inflows positive, cash outflows negative). When the initial investment is the only cash outflow and later periods have only net inflows, it can be written as “the sum of the present values of each year's net cash inflow, minus the initial investment”:

This general form also applies to projects with later additional investment, maintenance costs or decommissioning costs. The common simplified form is:

is the net cash inflow in year t, is the initial investment (as a positive number), r is the discount rate and n is the number of years. Only when costs and benefits are discounted to the same point in time can they be compared on the same ruler. Figure 1 shows the process for a three-year project.

Figure 1: Discounted cash flows and net present value

Worked example: NPV of a three-year project

A store self-checkout upgrade project has an initial investment of $50,000. Net cash inflows in years 1, 2 and 3 are $22,000, $24,200 and $26,620, and the discount rate is 10%.

  • Year 1: 22,000 ÷ 1.1 = $20,000; year 2: 24,200 ÷ 1.21 = $20,000; year 3: 26,620 ÷ 1.331 = $20,000.
  • Total present value = 20,000 + 20,000 + 20,000 = $60,000.
  • NPV = 60,000 − 50,000 = +$10,000, which is greater than 0, so accept.
  • Check: if the discount rate rises to 20%, total present value = 22,000 ÷ 1.2 + 24,200 ÷ 1.44 + 26,620 ÷ 1.728 ≈ 18,333 + 16,806 + 15,405 ≈ 50,544 (calculated from unrounded values), so NPV ≈ +$544, almost 0. At a higher rate NPV turns negative, which means the project's internal rate of return is slightly above 20%.

Decision rules

  • NPV > 0: the project's returns exceed the cost of capital, so it can be accepted.
  • NPV < 0: when evaluated only on financial return, with no mandatory or other strategic value, the project is usually not financially viable and should be abandoned. PMBOK 8 notes that value can also show up as regulatory compliance, social impact, customer satisfaction and innovation, so whether to drop a project that is mandatory for compliance or has major strategic value also depends on organizational strategy and the other dimensions of value.
  • When choosing among mutually exclusive projects, choose the one with the largest positive NPV. NPV already accounts for the time value of money, so you need not consider the project's length again or divide by the number of years.
  • The NPV of the “do nothing” path can be taken as 0, and it is also a comparable alternative: when evaluating on financial return alone, if every option has a negative NPV, do not do the project.

Where NPV is used

Net present value is one of the financial metrics commonly used in cost-benefit analysis. PMBOK 8 says that cost-benefit analysis “is a financial analysis method used to determine the benefits provided by a project against its costs”, and that it compares the cost of an activity to the expected benefit; ROI, IRR and payback period are other value metrics that PMBOK 8 lists. Cost-benefit analysis compares the cost of a project (or an activity or alternative) with its expected benefit. It is usually part of the business case (common exam practice), and PMBOK 8 says the business case is typically developed and maintained by the sponsor. The project manager may not calculate NPV personally but must be able to read it and use it to support decisions: when several paths each have costs and benefits, estimate the costs and benefits of each path, discount them and compare the net present values. Do not compare only the rent, or only the payback period, and do not use a tool such as Kano analysis that ranks requirements. The same applies to investment choices such as make-or-buy. Earned value and performance indices are monitoring metrics used during execution and are not used to compare options that have not started. If the options carry probabilities, first use a decision tree to calculate the expected monetary value of each option and then compare them; see “decision tree analysis” in the Risk topic for the EMV calculation.

Worked examples

Example 1 Calculation: discount a payment received in three years to present value

Question 1Example

A software company agrees with a customer to receive a single project payment of $133,100 three years from now. The finance department uses a discount rate of 10% per year. What is the present value of this payment today?

Show answer and explanation

Correct answer: B

This is the most basic discounting calculation in the Finance performance domain: given a future amount, a discount rate and a number of years, find the value today.

Present value converts future money into today's value with PV = FV ÷ (1 + r)ⁿ. You discount for as many years as there are, and you must divide. At a discount rate of 10% per year, $133,100 received three years from now has a present value of exactly $100,000. The answer is B.

  1. Substitute into PV = FV ÷ (1 + r)ⁿ with FV = 133,100, r = 10% and n = 3
  2. (1 + 10%)³ = 1.1 × 1.1 × 1.1 = 1.331
  3. PV = 133,100 ÷ 1.331 = $100,000
  4. Check: 100,000 × 1.331 = 133,100, matching the payment in three years, so the answer is B

Why the other options are wrong

  • A. $93,170 = 133,100 × (1 − 3 × 10%) = 133,100 × 0.7. This subtracts the discount rate as simple interest instead of discounting year by year with compounding.
  • C. $121,000 = 133,100 ÷ 1.10 discounts for only one year and leaves out the other two years.
  • D. $177,156 = 133,100 × 1.331 turns the division into multiplication, producing a larger amount three years out. The direction is wrong.

Key takeaway Present value = future amount ÷ (1 + discount rate)ⁿ. Discount for as many years as there are, and always divide.

Variation If the discount rate were 8%, present value = 133,100 ÷ 1.08³ ≈ $105,659. If the $133,100 were received two years from now, present value = 133,100 ÷ 1.21 = $110,000.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: how to compare the value of several paths

Question 2Example

A fitness chain is considering expanding to one of three neighboring business districts. The project manager needs to explain to management the benefits of each of three paths: build a new club, lease an existing space, or not expand at all. What should the project manager do?

Show answer and explanation

Correct answer: C

The project is at the options-evaluation stage. You need to decide what method puts the value of the three paths (including not expanding) on the same basis for comparison.

Each path has its own cash outflows and inflows at different points in time. Only by discounting them to present value and computing net present value can costs and benefits be compared at the same point in time. The NPV of not expanding can be taken as 0, so it can be included too. The path with the largest positive NPV has the most value and directly supports management's decision. The answer is C.

Why the other options are wrong

  • A. Rent is only part of cost and applies only to the lease path. It includes no benefits and does not cover building or not expanding.
  • B. Payback period says only how long it takes to recover the investment. It does not reflect the size of benefits after payback or the time value of money, and here it also omits the “do not expand” path.
  • D. Kano analysis is a tool for prioritizing requirements and understanding customer satisfaction. It is not a financial method for comparing the value of investment options.

Key takeaway To compare the overall value of several investment options (including doing nothing), discount costs and benefits to a common basis and compare the net present values.

Variation If the NPVs of the three paths are +$120,000, +$80,000 and 0 (not expanding), choose the +$120,000 path; if all were negative, choose not to expand.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Present value uses division: PV = FV ÷ (1 + r)ⁿ. Multiplying by mistake makes the present value too large. Discount for as many years as there are, not just one.
  • Discounting is compounding. You cannot subtract the discount rate directly as simple interest (such as × (1 − n × r)).
  • NPV already includes the time value of money. When comparing, do not divide by the project's years again and do not deduct the initial investment a second time.
  • Among mutually exclusive projects, choose the one with the largest positive NPV; do not choose a project with a negative NPV.
  • Present value PV has the same abbreviation as planned value PV in earned value management but a different meaning.
  • Payback period and cost differences speak only to part of the picture; to compare the overall value of several paths, use NPV.

Key takeaways

Key point

  • Money has a time value; present value PV = FV ÷ (1 + r)ⁿ. Divide, and discount for as many years as there are.
  • NPV = the sum of the discounted net cash flows of each period; simplified form: the sum of the present values of each year's net cash inflow − the initial investment.
  • Evaluated on financial return alone, NPV > 0 is usually acceptable and NPV < 0 usually is not; when the project is mandatory for compliance or has significant strategic, social or other non-financial value, a broader judgment is needed; among mutually exclusive projects, choose the largest positive NPV.
  • NPV already contains the time value of money, so you need not consider the project's length again; the NPV of “do nothing” is 0.
  • Use NPV to compare the overall financial value of several investment paths (including make-or-buy); the core of cost-benefit analysis is comparing costs with expected benefits.

Lesson 2

IRR, Payback Period, ROI and Benefit-Cost Ratio

Lesson video

Lesson overview

Net present value tells you “how much it is worth”, but management often wants to know other things as well: how high the rate of return is, how long it takes to recover the investment, and how much comes back for each dollar put in. Internal rate of return, payback period, return on investment and benefit-cost ratio answer these questions. They are usually used in cost-benefit analysis and written into the business case. This lesson sets out side by side the meaning, calculation, treatment of the time value of money and selection criterion of the four metrics, and explains that value is more than profit and how non-financial value enters decisions. The previous lesson covered present value and NPV, and the next covers cost types. This lesson supports ECO Process domain, Task 3 (Help ensure value-based delivery), including examining business value throughout the project and verifying that a measurement system for tracking benefits has been established.

The four metrics compared

MetricMeaningConsiders time value of money?Decision rule
Internal rate of return (IRR)The discount rate that makes NPV equal to 0; the implied rate of return of the project's cash flows, which can be compared with the organization's minimum required rate of returnYesLarger is better
Payback period (PP)The time needed to recover the initial investment from cumulative net cash inflows (common exam practice: use the static, undiscounted payback period; if the question says to discount, use discounted cash flows)NoShorter is better
Return on investment (ROI)In general net investment gain ÷ investment cost × 100%; common exam practice: average annual profit ÷ total investment × 100% (the period and annualization follow the question or the organization's definition)NoLarger is better
Benefit-cost ratio (BCR)Benefits ÷ investment (cost)Usually calculated with present valuesAccept only if greater than 1; larger is better

IRR and NPV are a pair: at a discount rate equal to the IRR, NPV is exactly 0. When a project's IRR is higher than the organization's minimum required rate of return (usually based on the cost of capital), the project is acceptable on that financial criterion. PMBOK 8 also mentions return on assets (ROA) and return on average capital employed (ROACE), metrics that gauge the organization's profitability relative to the money invested.

Worked example: static payback period

  • A project invests $90,000, has a 6-month construction period, and then earns net income of $5,000 per month. Recovery during the earning period takes 90 ÷ 5 = 18 months, so the payback period = 6 + 18 = 24 months. The construction period counts too: the payback period is measured from the project start date.
  • Another project invests $60,000, with net cash inflows over three years of $20,000, $25,000 and $30,000. Cumulative: $20,000 at the end of year 1, $45,000 at the end of year 2, $75,000 at the end of year 3. If year 3's cash flow occurs evenly through the year, the investment is recovered during year 3: payback period = 2 + (60 − 45) ÷ 30 = 2.5 years (if the cash flow occurs only at year end, the payback period is 3 years).
  • Check: at 2.5 years, cumulative inflow = 45 + 30 × 0.5 = $60,000, which equals the investment.

Worked example: ROI and BCR

A chain bakery invests $200,000 in a central kitchen, and expects cumulative profit of $150,000 over 5 years, with the present value of the discounted benefits totaling $260,000.

  • Average annual profit = 150,000 ÷ 5 = $30,000; ROI = 30,000 ÷ 200,000 × 100% = 15%.
  • BCR = 260,000 ÷ 200,000 = 1.3, greater than 1, so acceptable.
  • Check: NPV on a present value basis = 260,000 − 200,000 = $60,000, greater than 0, consistent with a BCR greater than 1. BCR > 1 and NPV > 0 are two ways of writing the same judgment.

How the metrics work together

These metrics are used within cost-benefit analysis. Cost-benefit analysis is a financial analysis method that compares the cost of a project (or an activity or alternative) with the expected benefit, used to judge the strengths and weaknesses of the alternatives and select the one with the best benefits, and it also helps the project manager decide whether an activity is cost-effective. It is usually part of the business case (common exam practice); PMBOK 8 says the business case is typically developed and maintained by the sponsor.

The metrics can rank projects differently, so first be clear about the decision constraint. The default exam rule is: when several mutually exclusive projects all have positive NPVs, choose the one with the largest NPV, because NPV directly states how much value is added, whereas IRR reflects a rate of return, not an amount. When funds are limited, select the portfolio with the largest total NPV within the budget constraint, for which BCR or the profitability index can serve as a reference. Look at IRR only when the question explicitly asks you to compare by the highest rate of return. The weakness of payback period is that it ignores benefits after recovery and ignores the time value of money; the weakness of ROI is that it ignores the time value of money.

Worked example: choosing among three mutually exclusive projects

Three mutually exclusive projects, same discount rate. A: NPV $18,000, IRR 12%, payback 3 years. B: NPV $25,000, IRR 10%, payback 4 years. C: NPV −$3,000, IRR 6%, payback 6 years.

  • C has a negative NPV and is excluded immediately.
  • Between A and B, choose B, which has the larger NPV. Choose A, with the higher internal rate of return, only if the question explicitly says to choose by the highest IRR, or A for its shorter payback only if the question asks for the fastest recovery. If the question says only that funds are limited, first rule out any project whose initial investment is over the budget; for independent projects, pick the feasible combination with the largest total NPV under the budget. You cannot decide on IRR alone.
  • Check: B's NPV of $25,000 exceeds A's $18,000 and adds more value, so B is the default choice.

Value is more than profit

Value is more than profit. PMBOK 8 says value can be tangible or intangible: at the financial level it is profit, at the social level it is value for people, and at the environmental level it is value for the planet. Customer satisfaction and innovation are examples of intangible value. Sometimes a project does not bring value by itself because it is a component of a program, and the value will be realized in the future. Sometimes spending more on a particular project is acceptable because value is measured by the outcome being available on a given date. So a project with a negative NPV but large social value may still be approved in public welfare and public service fields. When you meet such a question, first be clear whether it asks “is it financially worthwhile?” or “is it worth doing considering overall value?”

Value maximization means that the Finance performance domain is not only about cost; it also aligns with strategy, uses clear indicators of success and considers dimensions such as social impact, customer satisfaction and innovation.

During execution, the project manager also keeps checking value. If an update of the cost-benefit analysis shows that the expected value has become very limited, report it to the sponsor and stakeholders and assess whether to continue. At closing, if a key member asks for the actual return on investment and other business value, the project manager should verify the realized benefits and metrics against the benefits management plan rather than relying on subjective impressions.

Worked examples

Example 1 Calculation: the static payback period must include the construction period

Question 1Example

A company is evaluating an internal platform project. It requires an investment of $150,000 and has an 8-month delivery period. From month 9 onward it is expected to bring in a net cash inflow of $25,000 per month. Calculated as a static payback period (counted from the start of the project), what is the project's payback period in months?

Show answer and explanation

Correct answer: B

This question involves calculating a static payback period. The key is that the payback period is counted from the start of the project, not from the day income begins.

The static payback period is the time needed to recover the initial investment from the project's net cash inflows, without discounting. Cash inflows start only in month 9, so the payback period must include the first 8 months of the delivery period, plus the number of months needed after cash inflows begin to recover the $150,000. The answer is B.

  1. Time to recover the investment after income begins = 150,000 ÷ 25,000 = 6 months
  2. Add the 8-month delivery period before income begins
  3. Payback period = 8 + 6 = 14 months
  4. Check: cumulative income at the end of month 14 = 6 × 25,000 = $150,000, equal to the investment, so the answer is B

Why the other options are wrong

  • A. 6 months counts only the recovery time after income begins and leaves out the first 8 months of delivery.
  • C. 8 months is only the delivery period. At that point the project has just begun to produce income and recovery of the investment has not yet started.
  • D. 15 months double counts a month, for example counting month 9 as a separate month and then adding the 6 months of recovery. In fact months 9 through 14 are themselves exactly those 6 months of income.

Key takeaway When there are no inflows during construction and payback is measured from project start, static payback period = construction period + investment ÷ net cash inflow per period.

Variation If the delivery period were cut to 5 months, payback = 5 + 6 = 11 months. If monthly net cash inflow fell to $20,000, payback = 8 + 150,000 ÷ 20,000 = 15.5 months.

Something wrong with this question?

Report an issue with this question

Example 2 Concept: which metric is average annual return as a share of total investment

Question 2Example

An environmental nonprofit is launching a community recycling project, and the project manager is helping the sponsor prepare the business case. To show the sponsor that the investment is reasonable, a metric is needed that shows how high the average annual net benefit (average annual profit) the project creates is as a proportion of total investment. Which metric should be used?

Show answer and explanation

Correct answer: C

The project manager is helping the sponsor prepare the business case, and the question is which financial metric measures “average annual net benefit as a proportion of total investment”.

Return on investment measures the net return earned relative to the amount invested. The stem explicitly uses an annual-average basis: average annual net benefit (profit) ÷ total investment × 100%, which is exactly the ratio of average annual net benefit to the investment. The larger the value, the more average annual benefit each dollar invested brings back. This metric ignores the time value of money and is simple to use, so it suits explaining to the sponsor in a business case whether the investment is reasonable. The stem asks for a “proportion”, so the answer is C.

Why the other options are wrong

  • A. Total cost of ownership measures all costs of an asset over its whole period of use. It speaks only of cost and does not involve a benefit proportion.
  • B. Budget at completion (BAC) is the total budget for the project work, used to plan and monitor cost. It does not measure benefits.
  • D. Payback period measures how long it takes to recover the investment. It is a length of time, not the proportion of benefit to investment.

Key takeaway ROI measures the net return relative to the amount invested. On the annual-average basis it is average annual net benefit (profit) ÷ total investment, showing how much benefit each unit of investment brings; payback period measures time. ROI ignores the time value of money; when the time value matters, use NPV or IRR instead.

Variation If the stem asked “how long until all of the investment is recovered?”, the answer is payback period; if it asked “is the ratio of benefits to costs greater than 1?”, the answer is benefit-cost ratio.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The static payback period starts when the initial investment is made. If there are no inflows during construction and payback is measured from project start, include the construction period; common exam practice is to use the undiscounted static payback period.
  • Payback period measures a length of time and ROI measures a ratio. Do not mix them up. A short payback does not mean large overall value.
  • IRR is the discount rate that makes NPV equal to 0, and larger is better. To compare amounts, use NPV; choose by IRR only when the question explicitly asks to compare by highest internal rate of return.
  • BCR must be greater than 1 to be acceptable; equal to 1 is only break-even.
  • Total cost of ownership speaks of cost, and BAC is the total budget for the project work; neither measures a benefit ratio.
  • Value is not the same as profit; the answer to “is it financially worthwhile?” and “is it worth doing considering overall value?” can differ.

Key takeaways

Key point

MetricSelection criterionConsiders time value
NPVLarger is better among positive values; accept if NPV > 0Yes
IRRLarger is better; the discount rate at which NPV = 0Yes
ROILarger is better; net benefit ÷ investment (this lesson commonly uses average annual profit ÷ total investment)No
BCRAccept if greater than 1; larger is betterUsually present values
Static payback periodShorter is better; includes construction when there are no inflows during it and payback is measured from project startNo
  • These metrics are used within cost-benefit analysis, usually written into the business case (common exam practice); PMBOK 8 says the business case is typically developed and maintained by the sponsor.
  • Among mutually exclusive projects, default to the largest NPV; when funds are limited, maximize total NPV within the budget constraint, and BCR or the profitability index may serve as a reference; compare by IRR only when the question explicitly asks for the highest internal rate of return.
  • Value can be financial, social or environmental, and can also be intangible, such as customer satisfaction and innovation.

Lesson 3

Cost Types: Direct and Indirect, Fixed and Variable, Sunk Cost, Opportunity Cost and Life Cycle Cost

Lesson video

Lesson overview

The same sum of money plays different roles in different settings: whether it can be charged directly to a particular project, whether it rises and falls with the amount of work, whether money already spent still matters, and what is given up by choosing this option. These distinctions affect how costs are estimated and budgets built, and they directly affect decisions such as “continue or stop” and “choose A or B.” PMBOK 8 also stresses that every project decision may incur further costs for using, maintaining and supporting the result, so you must look at life cycle cost. This lesson sets out the seven cost types, with the emphasis on sunk cost and opportunity cost, the two concepts most often tested. The previous lesson covered value metrics. This lesson closes this chapter and the Finance topic. ECO: Process domain, Task 3 (Help ensure value-based delivery) and Task 6 (Plan and manage finance).

The seven cost types

TypeMeaningExample
Direct costsCosts that can be clearly charged to one particular projectWages and travel for staff dedicated to the project
Indirect costsCosts not specific to one project, shared among several projects or arising from the organization's general expensesOverhead, utilities, rent
Fixed costsCosts whose total does not change with output or workload over a given period and relevant range, and which may recur by periodPurchasing equipment, monthly equipment rental
Variable costsCosts that change in proportion to output or workloadRaw materials, labor paid by the hour, consumables
Life cycle costAll relevant costs of a product over its whole economic lifeDesign, production, operation and maintenance, disposal
Sunk costCost already incurred that cannot be recoveredMoney already invested in the project
Opportunity costThe benefit that another option could have brought, given up by choosing one optionThe benefit of project B given up by choosing project A

Cost types are usually tested by giving a scenario and asking you to decide which type it is. The keywords map as follows. If it can be clearly charged to one project, it is a direct cost. If several projects share it, it is an indirect cost. If it stays the same however much is made, it is a fixed cost. If the more you make the more you spend, it is a variable cost. If the money is spent and cannot be recovered, it is a sunk cost. If it is the benefit of the best alternative given up in order to choose this option, it is an opportunity cost.

Worked example: fixed and variable costs

An event printing project rents printing equipment at a fixed rent of $6,000 per month (fixed cost); each brochure printed uses $12 of paper and ink (variable cost).

  • Print 1,000: total cost = 6,000 + 12 × 1,000 = $18,000, or $18 each.
  • Print 3,000: total cost = 6,000 + 12 × 3,000 = $42,000, or $14 each.
  • Pattern: total cost rises with quantity, but the fixed cost is spread thinner and the cost per brochure falls; the variable cost per brochure stays the same.
  • Check: (42,000 − 18,000) ÷ (3,000 − 1,000) = 12, which equals the variable cost per brochure.

Indirect costs are usually allocated by some proportion. For example, if the company's office space rents for $60,000 a year and is allocated across three simultaneous projects by person-days, a project that uses 25% of the person-days is allocated $15,000, and that is its indirect cost. A temporary site cabin rented specifically for that project is a direct cost.

Sunk cost and opportunity cost

Sunk cost is cost that has already been incurred and cannot be recovered. Whether you continue or stop, it cannot be changed, so it should not be considered in a decision; look only at how much more must be invested and how much more can be earned. When a sponsor says “we have already put in several hundred thousand, and pulling back would waste it, so we must continue”, that is the sunk cost fallacy: using money already spent as the reason can let losses snowball.

Opportunity cost is the value of the best feasible alternative given up by choosing one option (here on an NPV basis). It is not the value of the option chosen, nor the difference between the two. If project A and project B are mutually exclusive and you choose A, the opportunity cost is B's net value (see the example below: B's net present value is 65 − 50 = $15,000).

Worked example: continue or drop a pilot

A company has already invested $80,000 in a pilot project. After evaluation it finds that finishing requires another $50,000, and once built it is expected to bring $40,000 of present value in benefits. If it switches to alternative project B, the same $50,000 is expected to bring $65,000 of present value in benefits.

  • The $80,000 already invested is a sunk cost. It cannot be recovered whether or not the pilot continues, so it is not considered in the decision.
  • Continue the pilot: 40 − 50 = −$10,000. Switch to B: 65 − 50 = +$15,000.
  • Choosing the pilot means giving up B's net gain of $15,000, and that is the opportunity cost of choosing the pilot.
  • Conclusion: drop the pilot and do B. You cannot continue just because “we've already spent $80,000”.
  • Check: if the sunk cost is included, the pilot is −$90,000 and B is −$65,000, and the gap between them is still $25,000. The sunk cost is the same for both options and does not affect the comparison.

Life cycle cost

PMBOK 8 says the primary source of project costs is the resources needed to complete the project activities, but every project decision may incur further costs related to using, maintaining and supporting the project's purpose to create value, which emphasizes the need for life cycle cost and maintenance considerations. For example, limiting the number of design reviews could reduce the cost of the project but increase the resulting product's operating costs. In decisions, consider the costs within the project together with the costs after delivery: buying a cheaper piece of equipment that uses more power and costs more to repair may turn out less worthwhile over three years than a slightly more expensive one.

The point in time at which cost is measured also affects what “how much was spent” means. Different stakeholders measure project costs in different ways and at different times. The cost of an acquired item may be measured when the acquisition decision is made or committed, when the order is placed, when the item is delivered, or when the actual cost is incurred or recorded for project accounting purposes. When you read a question, check which basis it uses.

When the benefits of an option carry probabilities, you can first calculate the expected monetary value (EMV) of each option and then compare them. Where there are several options or multi-stage branches, you can use decision tree analysis; see “decision tree analysis” in the Risk topic for how EMV is calculated.

Worked examples

Example 1 Calculation: choose A, give up B; what is the opportunity cost

Question 1Example

A manufacturer can pursue only one of Project A and Project B. Project A has a net present value of $42,000 and Project B has a net present value of $58,000. Management ultimately decides to do Project A. What is the opportunity cost of this decision?

Show answer and explanation

Correct answer: B

Only one of two projects can be chosen, and management has chosen Project A. You must work out the value given up by choosing A, which is the opportunity cost.

Opportunity cost is the value the option given up could have brought. Choosing Project A means giving up Project B, whose net present value is $58,000, so the opportunity cost is $58,000. A's own net present value is the benefit of the option chosen, not the opportunity cost. The answer is B.

  1. Option chosen: Project A, NPV $42,000
  2. Option given up: Project B, NPV $58,000
  3. Opportunity cost = value of the option given up = $58,000
  4. Compare: 58 − 42 = $16,000 is only the difference between the two benefits, not the opportunity cost. The opportunity cost of $58,000 exceeds the $42,000 benefit of the project chosen, so the answer is B

Why the other options are wrong

  • A. $42,000 is the net present value of Project A, the option chosen. It is the benefit of the option selected, not the one given up.
  • C. $16,000 = 58 − 42 is the difference between the benefits of the two projects, which does not equal the value of the project given up.
  • D. $100,000 = 42 + 58 adds the values of the chosen and the abandoned options together, which has no meaning.

Key takeaway Opportunity cost is the value of the option given up, not the value of the option chosen and not the difference between the two.

Variation If management chose Project B instead, the opportunity cost would become A's $42,000. If there were three projects and only one could be chosen, the opportunity cost is that of the highest-value project among those abandoned.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: can “we've already invested several hundred thousand” be a reason

Question 2Example

At a phase gate review, the sponsor says, “We have already invested several hundred thousand dollars in this project, and pulling out now would mean wasting it. We have to continue.” How should the project manager view the role of the “money already invested” in this decision?

Show answer and explanation

Correct answer: A

At a phase gate review of whether to continue, the sponsor gives money already spent as the reason. You must judge whether the money already invested should be considered in the decision.

Money already spent that cannot be recovered is sunk cost, and it cannot be changed whether the project continues or is terminated. Incremental financial analysis therefore compares only future costs and benefits; the phase gate also considers business documents, strategic alignment, risks, and entry and exit criteria. Money already invested should not be a basis for the decision. The answer is A.

Why the other options are wrong

  • B. This is the classic sunk cost fallacy. Using money already spent as the reason to continue can let losses snowball.
  • C. Exceeding the budget calls for change control or reassessment, but it does not mean the project must be terminated immediately. Look at whether future value justifies continuing.
  • D. After a project is started and approved, if its value no longer exists, termination is just as reasonable a choice. There is no rule that it must be carried through.

Key takeaway Sunk cost does not enter the incremental financial analysis of whether to continue or terminate; that analysis compares only future relevant costs and benefits, and NPV can help the judgment; a phase gate must also weigh business documents, strategic alignment, risk and entry and exit criteria.

Variation If the assessment shows that investing a further $50,000 is expected to bring $80,000 of present value in benefits, then with other conditions equal and judging only on financial value, continue; if it would bring only $30,000, terminate, however much was invested before.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When deciding whether to continue a project that has run into trouble, ignore sunk cost and look only at future investment and benefit.
  • Opportunity cost is the value of the option given up. It is not the benefit of the option chosen, not the difference between the benefits of the two options, and certainly not their sum.
  • Direct costs can be charged to a particular project; indirect costs are shared among projects, such as overhead and rent; fixed costs do not change with the workload, and variable costs do.
  • Do not push down project cost at the expense of raising usage and maintenance costs; look at life cycle cost.
  • Going over budget does not mean you must stop the project immediately, nor that you must finish at any price; look at whether the future value justifies continuing.

Key takeaways

Key point

  • Seven cost types: direct, indirect, fixed, variable, life cycle, sunk and opportunity.
  • Sunk cost does not enter decisions; opportunity cost is the value of the option given up.
  • Total cost = fixed cost + variable cost per unit × quantity; the larger the quantity, the thinner the fixed cost per unit is spread, so the cost per unit falls.
  • Life cycle cost: in decisions, look at costs before and after delivery together.
  • When an option carries probabilities, calculate EMV first and then compare; NPV greater than 0 is financially acceptable on that criterion, and among mutually exclusive options choose the largest.

This chapter has 23 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.