Quality
Quality Planning and Assurance
PMP · Quality · 6 lessons · about 1 h 11 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Quality is not something you inspect only when the project ends. It is something you set standards for during planning and build into the processes. PMBOK 8 does not split quality management into three processes for planning quality management, managing quality and controlling quality. It first sets down the principle "Embed Quality Into Processes and Deliverables" among the project management principles, and then places the actual work in three places. The quality requirements and the quality management plan are established in Define Scope. Process quality is the job of Manage Quality Assurance. The measurement and verification of deliverable quality sit in Monitor and Control Scope. Older materials and some question stems still use the earlier process names; this chapter points out the correspondence where it helps, and the exam points have not changed.
This is the core chapter of the quality topic. The questions concentrate on four types: classifying work (assurance or control), choosing a tool (audit, checklist, flowchart and so on), "what should the project manager do?" scenarios (find the cause first, communicate first, do not lower the standard), and quality practices in adaptive environments.
Lessons in this chapter
- Lesson 1: What Quality Means: Embed Quality Into Processes and Deliverables. PMBOK 8's definition of quality and its nine dimensions, and why quality activities come first (prevention first, shift-left); quality matters as much as cost and schedule.
- Lesson 2: Quality Management Plan and Quality Metrics. The six contents of the plan; what makes a metric measurable; requirements drive standards; what to do when metrics lack data or coverage falls short during execution.
- Lesson 3: Quality Assurance vs. Quality Control. The official distinction; where each sits in Manage Quality Assurance and Monitor and Control Scope; a three-step classification method (common exam practice).
- Lesson 4: Manage Quality Assurance. Quality audits, checklists, flowcharts, affinity diagrams, problem-solving and process improvement; what to do after an audit.
- Lesson 5: Quality Reports, Quality Control Measurements and Quality Practices in Adaptive Environments. The two quality records; predictive versus adaptive practice; definition of done, automated testing and whole-team responsibility.
- Lesson 6: Grade vs. Quality; Corrective Actions, Preventive Actions and Defect Repairs. Low grade is not low quality; the differences among the three kinds of action and their procedure; the order of response when a major defect is found.
Chapter map
Quality (degree to which inherent characteristics meet or exceed target objectives; nine dimensions)
- Planning: Define Scope → quality requirements and standards → quality management plan + quality metrics
- Quality assurance (process) → Manage Quality Assurance → audits · checklists · cause-and-effect diagrams · flowcharts · process improvement → quality reports
- Quality control (deliverables) → Monitor and Control Scope → inspections · testing · root cause analysis → verified deliverables · quality control measurements
- Problem found → corrective actions · preventive actions · defect repairs (change requests)
Adaptive: definition of done · automated testing · continuous integration · whole-team responsibility
The practice entry for this chapter is chapter practice. Start with the core questions, then do the must-do questions.
Lesson 1
What Quality Means: Embed Quality Into Processes and Deliverables
Lesson overview
Quality is where the whole topic starts. PMBOK 8 does not split quality management into three separate processes for planning, assurance and control. It first sets down a principle, Embed Quality Into Processes and Deliverables, and then places the quality work in Manage Quality Assurance, Define Scope and Monitor and Control Scope. This lesson covers the definition of quality, the dimensions used to measure it, why quality work should be done early, and the judgment the exam uses most: quality matters as much as cost and schedule, and prevention beats inspection after the fact. The next lesson covers the quality management plan and quality metrics, and the third lesson covers how to tell quality assurance from quality control.
What quality is
PMBOK 8 defines quality this way: "Quality is the degree to which a set of inherent characteristics of a project deliverable or process helps to meet or exceed the project's target objectives." Embedding quality means being able to "satisfy customers and stakeholders' stated or implied needs as a matter of course, at or above target levels of efficiency."
Read the definition in four pieces. "A set of" tells you quality is not a single measure: an electric scooter has braking distance, but also range, water resistance and noise. "Inherent characteristics" are the identifiable attributes a deliverable or process has by itself; the degree to which they meet or exceed the target objectives is the quality. "Stated or implied needs" is a reminder that you must meet what the contract says and also what is obviously expected but not written down, such as a fitness band whose battery should not die after half a day on one charge. "Degree" means quality can be measured; it is not a two-position switch between "good" and "bad".
Quality has two layers of requirements. Deliverables must meet acceptance criteria and satisfy stakeholder expectations, and processes must be appropriate and as effective as possible. So quality covers both the thing you make and the way you make it. PMBOK 8 says the quality of the deliverable and of the processes used to achieve it "are measured by conformance to acceptance criteria, the definition of done (DoD), fitness for use, and overall efficiency."
Quality can also be viewed through nine dimensions, which apply to both deliverables and processes. The table gives PMBOK 8's own question for each dimension:
| Dimension | The question it asks |
|---|---|
| Performance | Do the deliverables or processes function as intended by the project team and other stakeholders? |
| Conformity | Are the deliverables and processes aligned with specifications and fit for use? |
| Reliability | Do the deliverables and processes maintain the consistency necessary to meet or exceed desired outcomes? |
| Resilience | Can the deliverables and supporting processes cope with unforeseen failures and recover quickly? |
| Satisfaction | Do the deliverables and processes elicit valuable feedback from customers and/or end users, including usability and user experience? |
| Uniformity | Do the deliverables and processes demonstrate parity across similar outputs or workflows? |
| Efficiency | Are the deliverables and processes optimized to produce the greatest output with the least input? |
| Sustainability | Do the deliverables and processes contribute positively to economic, social, and environmental outcomes? |
| Compliance | Do the deliverables and processes comply with regulatory requirements and relevant industry standards, as well as organizational standards? |
The exam does not ask you to memorize every detail of each dimension, but remember one conclusion: quality is not the same as "no defects". A fully featured, defect-free system that customers find awkward to use fails on the satisfaction dimension. A product built exactly to specification that breaks environmental regulations fails on compliance.
Why quality activities come first
PMBOK 8 explains that the objective of quality activities is to move the deliverables to the point of delivery without unnecessary delays and to minimize rework and material waste through the early detection and prevention of defects. The objective is the same whether the requirements are well defined up front or are progressively elaborated and delivered incrementally.
This is the core logic the exam relies on: prevention is cheaper than finding defects afterward. The later a defect is found, the more it costs to fix. For the schedule, PMBOK 8 suggests reviewing scheduling practices and artifacts for completeness and correctness; integrating product quality reviews as scheduled milestones; and practicing a "shift-left" approach, where quality practices are prioritized as early in the project life cycle as possible. For finance, embedding quality helps control costs by preventing rework and reducing waste. For resources, you need qualified people and suitable tools. For risk, you manage quality-related risks proactively.
Here is a contrast. Suppose the housing mold for an access-control panel is designed with tolerances that are too tight. No number of extra inspectors at the factory will turn out good parts, because the problem is in the design itself. If the factory had joined the design review and the tolerances had been set to a reasonable range, there would be far less inspecting to do later. You get quality by building it in through design and process, not by inspecting it in.
Good quality management also brings further benefits: less rework, scrap and customer complaints, higher team morale, and a smaller negative impact on the environment, including avoiding the unnecessary consumption of resources and emissions that rework causes.
How it is carried out in planning
PMBOK 8 places quality planning in the Define Scope process. That process describes the project scope, product and value to be delivered, and also produces the quality management plan. It identifies the quality requirements and standards for the deliverables and determines how the project will show that those requirements have been met. On predictive projects this is done at the start; on adaptive and hybrid projects it is done at the start of each iteration.
For a scenario question about "what to do about quality", you can think through these steps in order:
- First find out what the quality requirements are: the quality requirements in the requirements documentation, and the acceptance criteria for each deliverable in the project scope statement.
- Then check whether they are written into the quality management plan: standards, objectives, roles and activities.
- Then check whether execution follows the plan: whether the processes comply (quality assurance, in Manage Quality Assurance) and whether the deliverables are acceptable (quality control, in Monitor and Control Scope).
- When you find a problem, find the cause before you fix it. Do not "solve" it by lowering the standard.
Example: it meets the standard, but the customer is unhappy
A community group-buying app project is intended in part for older residents. It is built to the requirements document and passes three rounds of testing. At the pre-launch demo, the customer's representative frowns and says, "It takes five taps to place an order. Older users will never manage this." The requirements document says nothing about the number of steps, but because older residents are intended users, usability for them is an implied need. The right move for the project manager is to find the gap between the customer's real expectation and the current quality standard, turn that gap into a measurable quality metric (for example, ordering in no more than three steps), and then decide how to adjust. Showing the test report and saying "we have already met the standard" is not the answer.
Worked examples
Example 1: someone wants to cancel the quality management plan during planning to save cost
On a company's mobile payment app development project, a team member thinks the tasks are simple and quality control is unnecessary. The project manager notices that dropping the quality management plan would also lower costs, and cost matters a great deal to the client. What should the project manager do?
Show answer and explanation
Correct answer: D
A team member feels the task is simple and quality control is unnecessary, and dropping the quality management plan would also save money, which matters a great deal to the client. The question asks how the project manager should respond; in essence, whether a quality plan can be abandoned just to cut cost.
Quality matters as much as cost and schedule and cannot be given up to save money. PMBOK 8 requires quality to be embedded in processes and deliverables, and the quality management plan sets out the quality standards, objectives, roles and responsibilities and quality activities as the basis for preventing defects and reducing rework. Dropping the plan looks like a saving but may add the later cost of defects, rework and customer complaints. “The task is simple” is only a personal judgment and cannot replace a plan. So the project manager should develop the quality management plan. The answer is D.
Why the other options are wrong
- A. Starting work with no quality management plan gives up prevention outright. Logging it as a risk and moving the budget saved into management reserve accepts the problem instead of solving it, and management reserve is not meant for this purpose.
- B. Enough team experience is a subjective judgment, and management's verbal confirmation cannot replace a plan. Quality activities are ensured by plans and processes, not by individual experience.
- C. Postponing inspection until an external audit after acceptance finds defects after the fact, when rework costs more. “Cutting the budget accordingly” also has no basis.
Key takeaway Do not unilaterally cancel agreed quality activities just to save cost or hit a date. If a trade-off is truly needed, assess the impact and decide through governance and change control procedures. Have a quality management plan: prevention beats inspection after the fact.
Variation If the end of an iteration is near and the team skips code review to hurry, the answer is the same: restate the definition of done and agree on ways of working that do not sacrifice quality. Do not condone it, and do not lower the definition of done.
Something wrong with this question?
Example 2: all tests passed, but the customer is still unhappy
A software project has passed all its quality tests and meets the established quality standards, but the client's representative is still not satisfied. What should the project manager do?
Show answer and explanation
Correct answer: A
The software has passed all quality tests and meets the established standards, but the client's representative is still not satisfied. The question asks what the project manager should do; the key is that there may be a gap between the established standards and the client's expectations.
PMBOK 8 says quality should satisfy customers' and stakeholders' stated or implied needs as a matter of course. Passing the tests shows only that the work meets the “written-down standard”. If the client is still unhappy, it may mean that some implied need was never written into the standard. So first verify the gap between the client's expectations and the quality standards, find out where it lies, and then decide whether to adjust the standards, add metrics or improve the way of working. You can think of the process in two steps: first find the gap against the client's real expectations; and if a requirement, acceptance criterion or baseline really must change, assess the impact and submit a change request, and once it is approved update the quality management plan with measurable quality metrics. Otherwise the next test will “pass” in the same way and the client will be just as unhappy. The answer is A.
Why the other options are wrong
- B. Showing the test report proves only that the work was done to the standard. It does not answer the client's dissatisfaction and does not find the gap.
- C. Reworking everything without knowing which expectation is unmet wastes resources and may not address the client's real concern.
- D. Asking for sign-off before discussing the dissatisfaction avoids the problem. The basis for acceptance is still unclear, and it may damage the client relationship.
Key takeaway Meeting the standard does not mean the client is satisfied. Verify the gap between expectations and the standard first.
Variation If the stem said that a feature the client explicitly asked for, already written into the approved requirements or acceptance criteria, was not built, that would be a failure to meet the acceptance criteria and you would rework it to the standard. If the request was never part of the approved scope, assess it and use change control. This question does not state the specific source of the dissatisfaction, so first verify the gap.
Something wrong with this question?
Common traps
Common trap
- Quality is not "no defects": the nine dimensions also include satisfaction, efficiency, sustainability and compliance.
- Meeting the established standard does not mean the customer is satisfied. The standard may not cover every implied need, so find the gap first rather than just showing the test report.
- When someone proposes canceling quality activities to save cost or time, the project manager should not go along. Explain the consequences to the person proposing it and aim for the agreed, appropriate level of quality. Do not lower quality standards on your own to hit a date or save money (common exam practice: answer as "quality matters as much as cost and schedule"). If a trade-off really is needed, assess the impact on quality, cost and schedule and decide through governance and change control procedures.
- When a team cuts corners near the end of an iteration, the response is to restate the definition of done and agree on ways of working that do not sacrifice quality. It is not to lower the definition of done, and it is not to work overtime.
- PMBOK 8 has no separate "Plan Quality Management" or "Control Quality" process. When older materials and some question stems still use those two names, read them as the quality management plan and the quality control activities within Monitor and Control Scope.
Key takeaways
- Quality is the degree to which a set of inherent characteristics of a deliverable or process helps to meet or exceed the project's target objectives, including stated or implied needs.
- Quality requirements have two layers: deliverables meet acceptance criteria, and processes are appropriate and as effective as possible.
- The nine dimensions are Performance, Conformity, Reliability, Resilience, Satisfaction, Uniformity, Efficiency, Sustainability and Compliance.
- The objective of quality activities is early detection and prevention of defects, reducing rework and waste. "Shift-left" means moving quality work as early as possible.
- Quality requirements and standards are identified in Define Scope, and the quality management plan is also produced there.
- Aim for the agreed, appropriate level of quality, and never lower quality standards on your own for cost or schedule. If a trade-off is truly needed, assess the impact and decide through governance and change control procedures (common exam practice: quality matters as much as cost and schedule).
Lesson 2
Quality Management Plan and Quality Metrics
Lesson overview
The previous lesson said quality must be planned early. This lesson answers where the result of that planning is written down and what form it takes: it goes in the quality management plan, and quality metrics turn the quality objectives into numbers you can measure. The exam usually asks three kinds of questions here: what the plan should contain; what makes a metric measurable; and what to do when the plan does not match the customer's requirements or stakeholders' expectations, or when nobody tracks the metrics during execution. ECO: Process domain, Task 7 (Plan and optimize quality of products/deliverables), covering planning quality processes and tools and executing the quality management plan.
What the quality management plan contains
The quality management plan is a component of the program or project management plan. It describes how an organization's policies, procedures and guidelines will be implemented to achieve the quality objectives, and it describes the activities and resources the project management team needs to achieve the quality objectives set for the project. It may be formal or informal, detailed or broadly framed; the style and level of detail depend on the requirements of the project. The plan should be reviewed early in the project to ensure that decisions are based on accurate information. The benefits of this review may include a sharper focus on the project's value proposition, reductions in cost, and less frequent schedule overruns caused by rework.
The quality management plan may include, but is not limited to, the following components:
- Quality standards that will be used by the project;
- Quality objectives of the project;
- Quality roles and responsibilities;
- Project deliverables and processes subject to quality reviews;
- Quality control and quality management activities planned for the project; and
- Quality tools and methodologies to be employed, alongside detailed procedures for handling nonconformance and continuous improvement.
The plan is an input to several later processes. Cost estimating refers to it so that the cost of quality activities is included. Monitor and Control Scope uses it to decide how quality control is carried out. Manage Quality Assurance turns it into executable activities. The plan is not an activity itself: it does not detect defects and does not guarantee quality by itself. Quality comes from executing it.
Where standards come from is a common exam point. Quality requirements are recorded and refined in the requirements documentation (the project charter may already hold high-level requirements and success criteria). Once they reach the project scope statement, every deliverable has acceptance criteria, and the quality management plan turns these requirements into standards, activities, roles and tools. So requirements drive standards, not the other way around. When a quality standard in the plan conflicts with the customer's requirements, first find out why they differ, and resolve it by negotiation in light of the customer's requirements and the applicable organizational policies, regulations, contracts and industry standards. If an approved requirement, standard or plan has to change, handle it through the change mechanism (common exam practice: requirements drive standards, so when the stem gives no other conditions, choose to confirm with the customer and let the requirements prevail). Quality standards and acceptance expectations must also be explained to stakeholders and their understanding confirmed. Otherwise the disagreement surfaces only at acceptance, when the rework has already happened.
Quality metrics: turning objectives into numbers
Quality metrics specifically describe project or product attributes and how the Manage Quality Assurance process will verify compliance with them. PMBOK 8 gives these examples: percentage of tasks completed on time, cost performance measured by a cost performance index (CPI), failure rates, number of defects identified per day, total downtime per month, errors found per line of code, customer satisfaction scores, and percentage of requirements covered by the test plan as a measure of test coverage.
In practice, a usable metric normally answers four questions: what is measured, how it is measured, how often, and what value counts as acceptable. A one-time acceptance metric may not need a frequency. If any of the four is missing, it is often hard to tell during execution whether quality is on target. Here are two pairs showing the same idea written two ways:
| Wording | Problem |
|---|---|
| The page should load as fast as possible | There is no target value, so everyone has a different idea of "fast" |
| The home page loads within 2 seconds on a standard network, measured by sampling 50 loads each week, with a pass rate of at least 95% | It says what is measured (load time), how (sampling), how often (weekly) and what counts as acceptable (95%) |
| Learners feel good about the course | A subjective feeling that cannot be measured |
| After each course, the learner satisfaction score is at least 4.2 (out of 5) | It has a scale and a target value |
The planning stage must also settle how to test and inspect. PMBOK 8 says that during planning the project manager and the project team determine how to test or inspect the product, deliverable or service to meet the stakeholders' needs and expectations, as well as how to meet the goal for the product's performance and reliability. The tests and inspections depend on the industry and can include, for example, alpha and beta tests in software projects, strength tests in construction projects, inspection in manufacturing, and field tests and nondestructive tests in engineering. The planned testing and evaluation activities produce quality test and evaluation documents, which are used to identify errors and defects early in the project and reduce the cost of dealing with them later.
You can also use benchmarking when planning quality. Benchmarking is the comparison of actual or planned products, processes and practices to those of comparable organizations to identify good practices, generate ideas for improvement, and provide a basis for measuring performance. The benchmarked projects may exist within the performing organization or outside it, or can be within the same application area or another application area.
Using the plan during execution
A plan is not something you write and then leave on the shelf. Several typical execution situations all call for the same approach: go back to the plan and fill in what is missing.
- The quality objective says only "high quality": work with stakeholders to refine it into measurable metrics.
- Metrics are defined but nobody records data: assign someone to collect the data at the planned frequency and compare it with the target.
- Actual test coverage is 78% against a planned 95%: assess the requirements that are not covered and add the critical tests. Do not lower the metric to the current level.
- Quality problems keep occurring, and everyone assumes quality is the quality inspector's job alone: define each role's quality responsibilities in the plan, and make all team members jointly responsible.
- A senior manager worries about final quality: invite that person to review the quality management plan together, and explain the standards, the activities and how quality will be demonstrated.
Example: an outline of a concise quality management plan
Take a membership app project for a pharmacy chain. Its quality management plan contains roughly the following. Quality standards: follow the company's mobile app development standard and the personal data protection requirements. Quality objectives: no more than 3 severe defects in the first month after launch, and test coverage of at least 95% for core flows. Roles and responsibilities: the product manager confirms acceptance criteria, the test lead maintains the defect log, and every team member is responsible for the code they submit. Items under review: the requirements document, the interface design and the core transaction flow. Quality activities: a code review every week, a regression test every iteration, and one independent acceptance test before launch. Tools and nonconformance procedures: defect severity levels, repair deadlines and retest rules.
Worked examples
Example 1: a senior manager worries whether quality will be met
On a shared finance services platform project at PMLyceum, after a review meeting a vice president tells the project manager privately that she is not confident the final delivered quality will meet the target. The project is already in execution. What is the MOST appropriate thing for the project manager to do?
Show answer and explanation
Correct answer: B
The project is already in execution, and a vice president tells the project manager privately that she is not confident the final delivered quality will meet the target. The question asks for the most appropriate response.
The quality management plan sets out the quality standards the project uses, the quality objectives, roles and responsibilities, the deliverables and processes subject to review, and the quality activities and tools. Inviting the vice president to go through the plan together both confirms whether the quality requirements she cares about are covered and explains how the project will ensure quality by following the plan, which responds directly to her concern. In answering a manager's concern, the point is to let that person see that “there is a plan, there are standards and there is a path to carry them out”, not to rely on verbal assurance. The answer is B.
Why the other options are wrong
- A. The size of the backlog reflects only the amount of work. It cannot be used to infer a quality level, much less prove that quality is on target.
- C. User acceptance testing is only one part of quality activities. Asking her to sign off on that arrangement does not answer her concern about overall quality.
- D. Saying only that the standards were approved long ago does not explain how the project will achieve them. It does not dispel the doubt and looks evasive.
Key takeaway When a senior manager worries about quality, first invite that person to review the quality management plan together.
Variation If the concern comes from the client, you can also show the quality control measurements and quality reports. The plan explains “how we do it”, and the measurements show “what was actually achieved”.
Something wrong with this question?
Example 2: which is the best measurable quality metric
An online education platform project is defining its quality metrics. Which of the following is the BEST quantifiable quality metric?
Show answer and explanation
Correct answer: D
A project needs to define quality metrics for its quality management plan. The question asks which metric can be quantified and measured.
A quality metric must describe an attribute specifically and state how compliance will be verified. Whether a metric is usable depends mainly on four questions: what is measured, how it is measured, how often (a one-time acceptance metric may not need this), and what value counts as acceptable. “Total downtime per month does not exceed 4 hours” has a clear object, a monthly totaling basis and a target value. It can be measured directly during the project, and it matches the “total downtime per month” kind of metric PMBOK 8 lists. Conversely, any goal worded with “as … as possible”, “the more … the better” or “feel” has no target value and no measurement method, so you cannot tell whether it has been met, and it cannot serve as a basis in an audit. The answer is D.
Why the other options are wrong
- A. “Attractive and easy to use” has no number and no measurement method. It is a subjective impression, and you cannot tell whether it has been met.
- B. “As fast as possible” has no target value, so everyone has a different idea of what level counts as acceptable.
- C. “Feel good” is a subjective description. Unless a survey score and a target value are given, it cannot be measured.
Key takeaway A good metric has a number and a counting basis. “The more … the better” and “feel good” do not qualify.
Variation Rewrite C as “after each course, the learner satisfaction score is at least 4.2 (out of 5)” and it can be quantified. Rewrite B as “the home page loads within 2 seconds, with a weekly sampled pass rate of at least 95%” and it can be too.
Something wrong with this question?
Common traps
Common trap
- "As fast as possible", "as few as possible" and "feels good" are not measurable metrics. A metric needs a clear, verifiable test; where it can be quantified, state the target value and how it is counted.
- When a standard conflicts with the customer's requirements, first find out why, then negotiate with the requirements prevailing (subject to mandatory standards such as laws and contracts). Changing an approved requirement, standard or plan goes through change control. Do not simply lower the standard, and do not force the customer to accept a low one.
- A metric that is defined but never recorded is the same as no metric. Do not rely on impressions, or wait for the customer's acceptance to assess it.
- When coverage falls short, add tests for the critical requirements. Do not lower the metric, and do not push the testing responsibility onto the customer.
- The quality management plan is not a quality assurance activity itself, and it does not detect defects.
Key takeaways
- The quality management plan is a component of the project management plan, produced in Define Scope and reviewed early in the project.
- Its contents are quality standards, quality objectives, roles and responsibilities, items subject to quality reviews, quality activities, and tools, methodologies and nonconformance procedures.
- A quality metric must be measurable: what is measured, how, how often, and what value counts as acceptable.
- Requirements drive standards; standards and acceptance expectations must be communicated to stakeholders and confirmed.
- Planning also covers test and inspection planning, and benchmarking can help set the quality level.
- When metric data is missing or coverage falls short during execution, go back to the plan to collect more data and add tests. Do not lower the metric.
Lesson 3
Quality Assurance vs. Quality Control: The Difference and Where Each Sits in PMBOK 8
Lesson overview
The exam asks about this knowledge point in a very fixed way: you are given a piece of work and asked whether it is quality assurance or quality control, or you are asked where "finding defects" and "auditing the process" each belong. This lesson first covers the official distinction between the two, then shows which process each one sits in under PMBOK 8, because question stems sometimes use older process names. There is only one principle for telling them apart: look at the focus, which is either the process or the deliverable.
How the standard separates them
PMBOK 8 says: "Quality management is sometimes called quality assurance, although quality management has a broader meaning in non-project work. In contrast, project management differentiates quality assurance and quality control as two distinct efforts:
- Quality assurance is about using project processes effectively. This effort involves following and meeting standards to assure stakeholders that the project's final results will meet their needs, expectations, and requirements. Related concepts include regulations, compliance, and audits.
- Quality control is about creating project deliverables that meet defined specifications and thresholds. This effort involves defining the attributes of the value generated by a project and ensuring project deliverables achieve those attributes. Related concepts include product design, testing, and defects."
Put side by side, they make the following comparison:
| Quality assurance | Quality control | |
|---|---|---|
| Focus | The process: whether work follows the standards and how effective it is | The deliverable: whether what was made meets the specification |
| Typical question | Is the process compliant? Where is it inefficient? | Is this component acceptable? How many defects are there? |
| Related concepts | Regulations, compliance, audits | Product design, testing, defects |
| Common activities | Quality audits, checklists, cause-and-effect diagrams, flowcharts, process improvement | Inspections, testing/product evaluations, variance analysis, root cause analysis |
The rule of thumb (common exam practice): if the question is "is the way of working right?", it is quality assurance; if it is "is the thing acceptable?", it is quality control. Do not separate them by who does the work. An audit can be done by an external team and an inspection can be done by the project team, but that is not the basis for the distinction. The same tester who checks the process today is doing assurance, and tomorrow, testing the product, is doing control.
Where they sit in PMBOK 8
PMBOK 8 says: "Quality management is relevant during project execution. There are two ways in which quality should be addressed in a project. The first is during the construction of the project management process, which provides process quality assurance and value delivery throughout the project. The second is during deliverable construction and should be addressed through scope management and control." At that point, "quality should be focused on ensuring that deliverables are being produced according to the agreed-upon requirements set in the scope baseline." For adaptive approaches, the scope baseline may be called prioritized requirements or the Sprint Backlog.
Mapped to processes:
- Quality assurance: Manage Quality Assurance. Its outputs are quality reports, change requests, and updates to the project management plan and project documents.
- Quality control: no longer a separate process. Quality control activities sit in Monitor and Control Scope. That process measures the quality and value of the deliverables and ensures they meet the specified quality requirements, and its outputs are quality reports, verified deliverables, change requests and quality control measurements. Its tools include data analysis (variance analysis, trend analysis, root cause analysis), performance reviews, audits and inspections, testing/product evaluations and data representations. In Monitor and Control Scope, inspections and testing/product evaluations are aimed mainly at deliverables. For audits, judge by the object: a quality audit (checking whether the process complies) belongs to Manage Quality Assurance.
Earlier editions of the standard split quality management into three processes, Plan Quality Management, Manage Quality and Control Quality, and many study materials and older questions still use those names. PMBOK 8 has no "Plan Quality Management" or "Control Quality" process: the quality management plan is produced in Define Scope, and the quality control activities are part of Monitor and Control Scope. When you meet the older names, do not worry. What is tested has not changed: read "Control Quality" as inspecting, testing and measuring the deliverables.
Monitor and Control Scope and Validate Scope are two connected steps. In Monitor and Control Scope you verify that the deliverables are correct, and the result is verified deliverables. These become an input to Validate Scope, where the customer or the stakeholder with authority to accept formally accepts them. Validate Scope "has two main objectives: checking the processes being used to achieve quality standards and formalizing the acceptance of the deliverables." The two cannot replace each other: the team's own verification passing does not mean the customer has accepted.
How to decide: three-step classification
When a question asks "what kind of quality work is this?", the common exam practice is to work through these three steps:
- Find the object. Is what is being examined a work activity, a process or the way it is carried out (process), or a component, feature or product (deliverable)? If a document is itself the thing to be delivered (such as a design document or a report), treat it as a deliverable.
- Find the action. Auditing, checking steps against a list, improving a process and sharing good practices are assurance. Inspecting, testing, measuring, logging defects and comparing against specifications are control.
- Finally, check whether the activity is quality work at all. Producing the quality management plan for the first time normally belongs to Define Scope, and identifying stakeholders belongs to the Stakeholder performance domain. Neither can be classed as quality assurance or quality control by its name alone.
Example: classifying five pieces of work
During the testing phase of a logistics dispatch platform project, these things happen in one week: (1) comparing test results with the acceptance criteria item by item; (2) organizing an internal audit to check whether quality activities are being carried out as planned; (3) logging the defects found in testing and tracking them to repair; (4) summarizing the good practices found in the audit and spreading them to other projects; (5) producing the quality management plan for the first time at the start of the project.
Classification: (1) and (3) are quality control, because the object is the deliverable. (2) and (4) are quality assurance, because the object is the process. (5) is planning work that belongs in Define Scope, and is in neither category.
Worked examples
Example 1: inspecting completed software components finds too many defects
While inspecting completed software components, the project manager finds noticeably more defects than before. Which of the following work produced this finding?
Show answer and explanation
Correct answer: C
The project manager inspects completed software components and finds noticeably more defects than before. The question asks which work this finding came from.
The key information in the stem is “inspecting completed software components” and “finding defects”: the object is a deliverable and the action is inspection. Quality control is about creating project deliverables that meet defined specifications and thresholds, and its related concepts are product design, testing and defects. Inspection and testing of this kind fall under Monitor and Control Scope. First ask whether the thing being examined is a process or a deliverable, then see whether the verb is auditing or checking steps, or inspecting, testing and recording defects. The answer is C.
Why the other options are wrong
- A. Quality assurance is concerned with whether project processes are compliant and effective, and its method is to audit the process, not to inspect deliverables for defects.
- B. The quality management plan is a component of the project management plan. It sets out standards, activities and roles; it is not an activity itself and does not detect defects.
- D. Monitor Risks tracks identified risks and newly emerging risks. It does not find defects by inspecting deliverables.
Key takeaway Inspecting deliverables and finding defects is quality control. Auditing whether the process is compliant is quality assurance.
Variation If “inspecting completed components” is changed to “reviewing whether project activities follow the organization's procedures”, the answer becomes quality assurance (audit).
Something wrong with this question?
Example 2: pick two activities that are quality control, not quality assurance
The project manager is sorting out this month's quality work. Which TWO of the following are quality control activities rather than quality assurance? (Choose 2.)
Show answer and explanation
Correct answer: BC
Some of the four options are aimed at the process and some at the deliverables, and you must pick the two that are quality control. Quality control and quality assurance both serve the quality objectives, and the key to telling them apart is the object each focuses on.
The test is the focus: quality control focuses on whether deliverables meet defined specifications and thresholds, and quality assurance focuses on whether processes are compliant and effective. B, “checking whether completed deliverables meet the quality metrics”, and C, “recording product defects found in testing”, are both aimed at deliverables and are quality control. The objects of A and D are processes, so they are quality assurance. In a multiple-response question, judge each option by its object, and do not pick an option just because it sounds “related to quality”. The answers are B and C.
Why the other options are wrong
- A. Auditing whether the team's process follows organizational standards focuses on the process. It is a quality audit and belongs to quality assurance.
- D. Summarizing good practices from a quality audit and spreading them uses the audit results to improve the process, which is the role of quality assurance.
Key takeaway Look at the focus: checking deliverables and recording defects are quality control; process audits and spreading good practices are quality assurance. Quality control answers “is the result acceptable?”, and quality assurance answers “is the way of working right, and can it be improved?”
Variation If an option said “draft the quality management plan”, that is quality management work in project planning. It is neither a quality assurance nor a quality control activity.
Something wrong with this question?
Common traps
Common trap
- Separate them by focus, not by who does the work. An audit done by an external team is still quality assurance, and an inspection done by the project team is still quality control.
- The quality management plan is neither quality assurance nor quality control. It is only the basis for both.
- An audit checks whether the process complies; it is not a test of the product. Testing and inspection are aimed at deliverables.
- Quality control is not the same as Validate Scope. The former verifies that deliverables are correct and conform to quality requirements, and the latter is formal acceptance by the stakeholder with authority to accept.
- In PMBOK 8 the quality control activities are in Monitor and Control Scope. Monitor Risks and Monitor and Control Project Performance are not where you inspect deliverables for defects.
Key takeaways
- Quality assurance focuses on whether processes are compliant and effective. Quality control focuses on whether deliverables meet defined specifications and thresholds.
- Rule of thumb (common exam practice): "is the way of working right?" is assurance, and "is the thing acceptable?" is control.
- Quality assurance corresponds to Manage Quality Assurance. Quality control activities are part of Monitor and Control Scope, whose outputs include verified deliverables and quality control measurements.
- PMBOK 8 has no separate Plan Quality Management or Control Quality process. When you meet the older names, read them as the activity itself.
- Verified deliverables are an input to Validate Scope, and the team's own verification does not replace customer acceptance.
Lesson 4
Manage Quality Assurance: Audits, Checklists, Problem-Solving and Process Improvement
Lesson overview
Manage Quality Assurance is the only process in PMBOK 8 named for quality, and it is the core knowledge point of this topic. It is concerned with the process: whether the project is being run to the organization's and the project's standards, where it is inefficient, and why performance is poor. On the exam it often shows up as a tool-selection question: you suspect the team did not follow procedure, so what do you use; you want to avoid omissions, so what do you use; you want to find inspection points, so what do you use. This lesson explains the purpose of the process, its tools and how to handle what it turns up, all in one place. Cause-and-effect diagrams, Pareto charts, control charts and the like are covered in detail in the next two chapters. ECO: Process domain, Task 7 (Plan and optimize quality of products/deliverables).
Purpose and tools of the process
PMBOK 8 defines Manage Quality Assurance as "the process of ensuring project processes are performed in a manner consistent with stakeholder expectations. This process involves translating the project management plan into executable activities that incorporate the organization's standards, regulations, and policies. The key benefit of this process is that it increases the probability of meeting the project objectives as well as identifies ineffective processes and causes of poor project performance. This process is performed throughout the project."
Its inputs are mainly the project management plan (including the quality management plan), all project documents, and the policies, procedures and regulations in the organizational process assets. Its tools are audits, checklists, data representation (affinity diagrams, cause-and-effect diagrams, flowcharts), decision-making, problem-solving and process improvement. Its outputs are quality reports, change requests, and updates to the project management plan and project documents.
Quality audits
"An audit is a structured, independent process used to determine if project activities comply with organizational and project policies, processes, and procedures." "A quality audit is usually conducted by a team external to the project, such as the organization's internal audit department, project management office (PMO), or an auditor external to the organization." Its objectives may include, but are not limited to:
- Identifying all good practices being implemented;
- Identifying all nonconformities, gaps, and shortcomings;
- Sharing good practices introduced or implemented in similar projects in the organization and/or industry;
- Proactively offering assistance in a positive manner to improve the implementation of processes to help raise team productivity;
- Highlighting contributions of each audit in the lessons learned repository of the organization.
In addition, "subsequent efforts to correct any deficiencies should result in a reduced cost of quality and an increase in sponsor or customer acceptance of the project's product." Quality audits may be scheduled or random, and may be conducted by internal or external auditors. They can also confirm the implementation of approved change requests, including updates, corrective actions, defect repairs and preventive actions.
Capture it in one sentence: an audit examines the process, not the product. The auditor goes through records, procedures and approval documents to see whether the team did things by the rules; the auditor does not test whether a part works. So the answer to each of these common scenarios is a quality audit:
- An external team independently reviews project activities and processes for problems.
- The PMO checks whether activities comply with the organization's procedures, policies and processes.
- A team rushing to finish under an incentive scheme is suspected of dropping required compliance steps and you need to investigate; or you want to show the customer that the change requests approved last month have all been implemented.
Other tools and techniques
A checklist is "a list of items, actions, or points to be considered." Checklists "are often used as reminders and are developed based on historical information and knowledge accumulated from similar projects and other sources of information." A checklist can also be used to ensure that a project or task is ready to start; such a checklist is also called "definition of ready" or "full kit". Two common uses on the exam are confirming that a prescribed series of steps has all been carried out, and confirming that every item on a requirements list has been met (common exam practice). The core function is to prevent omissions. When a question asks you to check item by item with nothing left out, choose the checklist.
A flowchart is a visual representation that maps out the sequence of steps and branching possibilities within a process; flowcharts are also known as process maps. PMBOK 8 says they help identify what can be improved. Seeing from the mapped steps which stage tends to produce defects and where inspection points belong is common exam practice. An affinity diagram shows large numbers of ideas classified into groups for review and analysis, and it can also organize potential causes of defects into groups. The cause-and-effect diagram traces the root cause of a result and has its own chapter later.
Problem-solving entails finding solutions for issues or challenges. "Effective and systematic problem-solving is a fundamental element in quality assurance and quality improvement." Problem-solving methods generally include these actions:
- Define the problem,
- Identify the root cause,
- Generate possible solutions,
- Choose the best solution,
- Implement the solution, and
- Verify solution effectiveness.
Process improvement "refers to the systematic approach of enhancing the efficiency and effectiveness of a process within an organization. This approach involves analyzing current processes, identifying areas for improvement, and implementing changes to achieve better performance, quality, and customer satisfaction. The ultimate goal of process improvement is to optimize operations, reduce waste, and increase value for both the organization and its customers." Continuous improvement can use approaches such as plan-do-check-act (PDCA), Lean, Total Quality Management, Six Sigma, Five Focusing Steps (5FS), and similar methods.
How to choose: find the tool from the scenario
| Signal in the question | Choose |
|---|---|
| You suspect procedure was not followed, the process is not compliant, or you need to verify that changes were implemented | Quality audit |
| You must confirm item by item that steps were done and requirements met, with nothing missed | Checklist |
| You want to see the order of steps, find stages prone to defects, or place inspection points | Flowchart |
| A pile of defect causes needs to be grouped | Affinity diagram |
| Why a problem happened, asking "why" layer by layer | Cause-and-effect diagram |
| A problem keeps recurring and you need to define it, find the cause, choose a solution and verify | Problem-solving |
| The process itself is inefficient and you want to optimize it systematically | Process improvement |
What to do after an audit is a different kind of exam point. The common exam practice is this: treat the audit result as a lead, check the process against the quality management plan, and find the gaps and their causes. Then decide whether to complete the documents, change the process or change the plan, and verify after the fix. For example, suppose a quality audit finds that the project's defect logging and escalation practice does not match the organization's prescribed procedure. You should first analyze why they differ and then correct the practice so that it complies with the procedure. You should not ask to revise the organization's procedure to fit current practice, hand the audit conclusion to the customer to deal with, or run another round of product testing in place of corrective action.
Example: what an audit finds and how it is handled
A smart door lock project uses a predictive approach. A PMO spot check finds that the third and fourth firmware batches have no code review records and that regression testing was only half done. The project manager first compares the facts with the quality management plan to find the cause of the gap (rushing the schedule, or too few reviewers). Next, the project manager raises a change request aimed at the cause under the change management plan, for example making review a release condition for each firmware batch and reviewing and testing the two batches already released after the fact. Once the change is approved, the quality management plan and related documents are updated, stakeholders are told and the change is carried out; the finding is also recorded in the lessons learned register.
Worked examples
Example 1: an external team independently reviews activities and processes. What is it using?
A membership system upgrade project for a retail chain has mostly completed its deliverables, but yesterday's testing still found some defects. After the project manager reports to the sponsor, the sponsor hires an external team to review the project's activities and processes to determine whether something is wrong in quality management. Which tool or technique is this?
Show answer and explanation
Correct answer: D
The project is close to completion, but testing still found defects. The sponsor hires an external team to review the project's activities and processes to determine whether something is wrong in quality management. The question asks which tool or technique this is.
“External team” and “reviewing activities and processes” are the key signals. A quality audit is a structured, independent process used to verify that project activities follow the organization's and the project's policies, processes and procedures, and it is usually conducted by a team external to the project. It is a tool of Manage Quality Assurance. Its object is the process, not the deliverable. Similar signal words include “independent”, “not part of the project team” and “check whether established procedures were followed”, all of which point to a quality audit. The answer is D.
Why the other options are wrong
- A. Statistical sampling takes part of a population as samples to inspect. The stem describes an independent compliance review of activities and processes by an external team, which is a quality audit.
- B. Data analysis is a family of techniques for organizing and evaluating data and information. It is not an independent review of whether activities and processes comply.
- C. Inspection examines whether deliverables meet standards, while what the stem has reviewed is the process, not the deliverables.
Key takeaway An independent review of activities and processes by an external team to check compliance is a quality audit.
Variation If the task were to check whether completed software modules meet the acceptance criteria, the answer would be inspection (deliverable verification, in Monitor and Control Scope), not a quality audit.
Something wrong with this question?
Example 2: you suspect the team dropped compliance steps to rush the schedule. How do you investigate?
The project sponsor promises an additional bonus if the project is delivered three weeks ahead of plan. Motivated, the team rushes the schedule all the way. The project manager suspects the team may have skipped the compliance check steps that must be carried out, and wants to verify whether the team has followed the prescribed process. What should be used?
Show answer and explanation
Correct answer: B
The sponsor promises a bonus for delivering three weeks early, and the team rushes. The project manager suspects the team may have skipped compliance check steps that must be carried out, and wants to verify whether the prescribed process was followed.
What needs verifying is whether the team followed the prescribed compliance process, not tracing the cause of a known problem. To investigate “did they do it as prescribed?”, use a quality audit: it checks in a structured, independent way whether project activities follow policies, processes and procedures, and finds noncompliant practices and gaps. The audit results give the basis for later correction, problem-solving and process improvement, so it is the first step in investigating compliance. After the audit, you can use a cause-and-effect diagram or problem-solving to find out why and how to fix it. So at this point the choice is B.
Why the other options are wrong
- A. A cause-and-effect diagram analyzes the root cause of a known problem. Here you first need to verify whether the team followed the prescribed process, so it is too early to trace causes.
- C. A flowchart shows process steps and inspection points and helps in designing or improving a process, but it cannot reveal whether the team actually followed it.
- D. Process improvement is the systematic optimization that follows once inefficiency is found. At this point you suspect that what should have been done was not done, so check compliance first and talk about improvement afterward.
Key takeaway When you suspect the process was ignored or is noncompliant, investigate with a quality audit.
Variation If the audit finds the steps were skipped because there were too few reviewers, the next step is to repair the process with problem-solving or process improvement: the audit finds the gap, the cause-and-effect diagram finds the cause, and process improvement fixes the process.
Something wrong with this question?
Example 3: an audit finds that the defect escalation practice does not match the organization's procedure
A quality audit finds that the project's defect logging and escalation practice does not match the procedure the organization prescribes. What should the project manager do?
Show answer and explanation
Correct answer: A
A quality audit finds that the project's defect logging and escalation practice does not match the procedure the organization prescribes. The question asks what the project manager should do.
A quality audit checks whether project activities follow the organization's policies, processes and procedures, and here it has found a gap. The project manager should first analyze why the practices differ (people did not know, found it a nuisance, or the procedure itself does not fit), then correct the practice so it complies with the procedure, and record the finding as a lesson learned. One purpose of an audit is to identify nonconformities and promote process improvement, not to accommodate the status quo. So analyze the cause first, then correct the practice. The answer is A.
Why the other options are wrong
- B. The procedure is set by the organization. When the project's practice differs, the practice should be corrected. Asking to revise the organization's procedure to fit current practice puts the cart before the horse.
- C. Correcting audit findings is the responsibility of the project team and the project manager. Handing them to the client to decide shifts responsibility and does not serve the purpose of the audit.
- D. Additional product testing is aimed at deliverables, while the audit found a process problem. Testing cannot take the place of correcting the procedure.
Key takeaway When an audit finds a mismatch, first analyze the cause, then correct the practice so it complies with the procedure.
Variation If the analysis shows the procedure itself no longer suits the project, you can submit a revision proposal to the PMO as prescribed. But that is a conclusion reached after the analysis, not the first reaction.
Something wrong with this question?
Common traps
Common trap
- A quality audit checks whether the process follows policies, procedures and standards, so it is quality assurance. It is not testing of deliverables.
- A quality audit is usually conducted by a team external to the project. The project team's own review is not a quality audit.
- When you suspect "what should have been done was not done", audit first. Do not start with a cause-and-effect diagram (which finds causes) or with process improvement (which comes after you find inefficiency).
- When an audit finds noncompliance, do not just fill in documents to get by, do not change the quality management plan first, and do not revise the organization's procedure to fit the status quo. Find the gap and its cause first, then correct the practice.
- If someone suggests skipping internal quality checks and tests because the deadline is near, decline, explain the possible delay to the customer, and make sure the checks are completed.
Key takeaways
- Manage Quality Assurance ensures project processes are performed in a manner consistent with stakeholder expectations and identifies ineffective processes. It is performed throughout the project.
- Its tools are audits, checklists, data representation (affinity diagrams, cause-and-effect diagrams, flowcharts), decision-making, problem-solving and process improvement.
- A quality audit is structured and independent, usually conducted by an external team, and checks whether the process follows policies, processes and procedures. It can be scheduled or random.
- Checklists prevent omissions, flowcharts show steps and help place inspection points, and affinity diagrams group causes.
- Problem-solving has six steps: define the problem, identify the root cause, generate possible solutions, choose the best solution, implement it and verify its effectiveness.
- When an audit finds a problem, first compare against the plan to find the gap and its cause, then complete the documents or change the process, and verify that the fix works.
Lesson 5
Quality Reports, Quality Control Measurements and Quality Practices in Adaptive Environments
Lesson overview
The earlier lessons covered the plan, process audits and tools. This lesson covers the "records of results" of quality work and "how practice differs across life cycles". There are two documents: quality reports and quality control measurements. There is also one comparison. On predictive projects quality assurance is usually carried out formally; on adaptive projects it can be formal or informal depending on context, with quality embedded in every iteration and the whole team responsible; on both, quality assurance goes on throughout the project. ECO: Process domain, Task 7 (Plan and optimize quality of products/deliverables), covering executing the quality management plan, conducting ongoing quality reviews and implementing continuous improvement.
Two quality records
A quality report is a project document that includes quality management issues, recommendations for corrective actions, and a summary of findings from quality control activities. The quality report may include recommendations for any process, project and product improvements. It is a direct output of Manage Quality Assurance and of Monitor and Control Scope; Validate Scope may also update the quality reports through project document updates. What follows is common exam practice: a quality report may take the form of charts, figures or a written statement, and its purpose is to prompt corrective action by the processes and departments concerned. Some customers care about it especially and ask for it weekly or monthly. If the plan sets a release frequency, issue it on time, because a late report makes stakeholders lose confidence in the quality status.
Quality control measurements "are the documented results of the Manage Quality Assurance process activities. The measurements should be captured in the format specified in the quality management plan." They are also one of the outputs of Monitor and Control Scope. If an exam question asks for "the main output of Manage Quality Assurance", choose the quality reports. Quality control measurements record the actual measured results of quality activities and can show the quality level a deliverable actually reached. So when a customer doubts the quality, the project manager is more convincing using the quality control measurements than showing good samples from earlier batches, a few samples pulled from this batch, or the tolerances and control limits on their own. Samples represent only individual items, tolerances state only the requirement, and control limits state only the natural variation of the process. Only the record shows "what was actually achieved".
Data only matters if it is used. Defect counts and rework rates that sit in a report, never analyzed and never used to improve, are wasted. If groups record in different formats, unify the format as the plan says. When measurement results do not match the metrics, the first step is to review and analyze the warning (convening the relevant stakeholders if necessary) to understand its nature and impact, and only then decide on corrections or changes. Do not raise a change request first, and do not park it in the backlog.
Predictive vs. adaptive
PMBOK 8 says that "in predictive projects, quality assurance is usually performed in a formal capacity, under the expectation that strong process quality will minimize variances in an otherwise stable project." In agile or adaptive projects, "quality assurance can be performed formally or informally, based on the context." Quality assurance tasks "may be performed by the project management team, an external entity, or both."
On an adaptive project the scope baseline may be called prioritized requirements or the Sprint Backlog, and quality is measured by whether those requirements can be delivered as agreed. A team can use regular review meetings such as the retrospective, together with issues, threats, quality metrics and stakeholder feedback, to judge whether it needs to tailor its practices further. If deliverable quality is poor, analyze the root cause, improve the process and strengthen feedback and quality assurance where needed. Do not just add one more verification step.
The objective is unchanged: detect and prevent defects early and reduce rework and waste. What changes is the timing. Quality is not checked in a lump at the end of an iteration or of the project; it is done continuously within each iteration. These are some commonly used practices (continuous integration, test-driven development, pairing and similar are common exam practice):
- Definition of done: "The DoD is a checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use." In adaptive projects it is "a shared understanding of the specific criteria that should be met before a piece of work (e.g., a user story, feature, or increment) is considered complete and ready for release to the next stage or the customer." It differs from the acceptance criteria for a specific backlog item. It is the team's shared quality floor and must not be lowered to hurry a delivery.
- Automated testing and continuous integration: every commit is built and regression-tested automatically, so problems show up the same day instead of erupting all at once at a final integration.
- Test-driven development and pairing: write the test before the code; two people write together and review each other as they go.
- Technical excellence: an Agile Manifesto principle reads "Continuous attention to technical excellence and good design enhances agility." Refactoring and coding standards both serve it.
- Frequent reviews and usability testing: have stakeholders join product reviews often, and let real users try the product while the team watches. That is how problems surface before delivery.
- Slice user stories smaller: if testing is squeezed into the last two days of the iteration, slice the stories smaller and test each one as it is built, so testing spreads naturally across the whole iteration.
Quality belongs to the whole team: a self-organizing team finds problems itself and improves its own process. It does not wait for a quality coach to check each iteration item by item, and it does not rely on a manager's orders. AI tools can help generate test cases and organize defects, which speeds work up. But whether the cases cover the critical scenarios and whether the expected results are correct must be confirmed by team review, and the responsibility does not pass to the tool.
Example: testing always gets squeezed into the last two days
On an online booking software team, testers are overwhelmed in the last two days of every iteration, and the verification report is always rushed. A new developer asks, "When does quality control happen?" The team's answer is: throughout the development process. The fix is to slice the big stories into small ones that take two or three days, test each one as soon as it is developed, and write into the definition of done that "code is reviewed and automated tests pass", so that anything short of that does not count as done. At the end of the iteration the team does only the final regression and the review demo, which is no longer the first time anything is tested.
Predictive vs. adaptive: the rhythm of quality activities
Predictive projects: quality assurance is usually carried out formally as planned. The timing and frequency of verifying deliverables are tailored to the quality management plan and the project context, and typically happen at planned checkpoints or during the work. They can be continuous, or they can be set by phase, milestone or batch. Adaptive projects: quality is embedded in every iteration, with continuous testing and continuous review, and the team improves itself. The completion criteria are written into the definition of done, the quality activities for the iteration are included in iteration planning, and the specific checking methods follow the quality management plan and the quality test and evaluation documents.
Worked examples
Example 1: quality control measurements do not match the metrics
After a batch of finished industrial sensors comes off the line, the team sends them to the quality inspection department as usual. The department immediately issues an important warning: the measured accuracy index does not match the quality metric. What should the project manager do?
Show answer and explanation
Correct answer: A
A batch of finished sensors is sent to the quality inspection department, which issues an important warning: the measured accuracy index does not match the quality metric. The question asks what the project manager should do.
Measurement results that disagree with the metrics are a quality problem that has already appeared, but its cause and impact are not yet clear. The first step is to convene the stakeholders to review and analyze the warning, to work out how large the deviation is, where it comes from and which deliverables it affects. Only on that basis can you decide on corrective action or a change request. A warning is not a conclusion: the quality inspection department has found a “phenomenon”, and the project manager has to turn that phenomenon into a judgment about cause and impact. Analyze first, then act. The answer is A.
Why the other options are wrong
- B. Submitting a change request before the cause, the impact and the remedy needed are known is premature. Analyze the warning first, then raise and evaluate any change under change governance.
- C. The warning already shows the problem is serious. Putting it in the backlog gives no sense of when it will be dealt with, and does not take the problem seriously enough.
- D. Logging in the issue log is only the starting point of recording and tracking. It cannot replace review, analysis and follow-up response, and it is not the key action the project manager takes first.
Key takeaway When quality measurement results disagree with the metrics, first convene stakeholders to review and analyze, then decide on correction or change.
Variation If the analysis confirms a design defect, only then do you submit a change request. If it is a measuring instrument error, calibrate the instrument first and no change is needed.
Something wrong with this question?
Example 2: how to convince the customer about quality
On a precision instrument manufacturing project, several batches of parts were returned by the client, who believes the parts are of poor quality and worries that their own products will be returned too. The project manager is confident quality is under control. How should the project manager communicate with the client so the client is convinced the project produces high-quality products?
Show answer and explanation
Correct answer: B
Several batches of parts were returned by the client, who doubts the parts' quality and worries their own products will be returned too. The project manager is confident quality is under control. The question asks how to convince the client that the project produces high-quality products.
Quality control measurements are the documented results of quality activities, recorded in the format the quality management plan specifies. They record actual results from inspection, testing and measurement activities and show “what was actually achieved” on the project. Showing them to the client is more complete and more convincing than scattered samples or a standard on its own. Quality control measurements can serve as a basis for communicating the quality status, so when you communicate quality to a client, data and records carry more weight than explanations. The answer is B.
Why the other options are wrong
- A. Good samples from earlier batches cannot prove the current product is acceptable, and the client's doubts concern recent batches.
- C. Tolerances state the specification requirement, and control limits state the statistical variation of the process. Explaining only those limits, without showing actual measurement results, does not prove the product meets requirements.
- D. A few physical samples pulled from this batch cover too little. They cannot prove the quality of all products and are not a complete measurement record.
Key takeaway To prove quality to a client, use the quality control measurements, not samples or a standard on its own.
Variation If the client asks “how will you ensure this in the future?”, show the quality management plan, explain the corrective-action recommendations in the quality reports, and describe how any approved corrective actions will improve the process.
Something wrong with this question?
Example 3: when quality control happens on an agile team
An agile team is developing online appointment software, and a newly joined developer asks when quality control should be performed. As the product owner, how should you answer?
Show answer and explanation
Correct answer: D
An agile team is developing online appointment software, and a new developer asks when quality control should be performed. The product owner has to answer. In essence the question is about the timing of quality activities on an agile project.
Agile projects stress building quality into the process: testing, review and integration go on continuously within every iteration, and the earlier a defect is found, the less trouble it causes. So quality control is not an activity at one fixed point, but something done throughout the development process, continuously. That is consistent with PMBOK 8's goal of detecting and preventing defects early and reducing rework. So the answer to “when is quality control done in agile?” is not one meeting or one milestone: it is done in every iteration, for every story and with every commit. The answer is D.
Why the other options are wrong
- A. Doing it in a block after the iteration ends finds defects late, makes rework more expensive and runs against the principle of prevention first.
- B. Doing it before the iteration review meeting covers a single point in time, which is too narrow.
- C. The retrospective is for summarizing experience and improving ways of working. It is not where quality control is carried out.
Key takeaway In agile, quality activities run continuously through the whole development process, not at a single point in time.
Variation If asked “who is responsible for quality?”, the answer is that the whole team shares responsibility. If asked “how do we make sure every story meets the standard?”, the answer is the definition of done.
Something wrong with this question?
Common traps
Common trap
- To prove quality to a customer, use the quality control measurements, not earlier samples, a single batch's samples or a standard on its own.
- When measurement results do not match the metrics, first convene stakeholders to review and analyze. Do not raise a change first, park it in the backlog, or have the quality department fill in the record afterward.
- Data that is stored but not used is not quality management. If recording formats differ, unify them as the plan says.
- Quality control in agile is not done in a lump after the iteration ends, and it is not done only in the retrospective. Quality control runs throughout the iteration; the iteration review can inspect the results and collect feedback, and the retrospective is mainly for reflecting on and improving the process.
- If the end of an iteration is near and testing is skipped to hit the date, restate the definition of done. Do not lower the definition of done.
- Test cases generated by AI must be reviewed and confirmed by the team, and the responsibility stays with the team.
Key takeaways
- A quality report contains quality management issues, recommendations for corrective actions and a summary of quality control findings, and may include improvement recommendations. Issue it at the planned frequency.
- Quality control measurements are the documented results of quality activities, in the format the plan specifies. Use them to prove quality to a customer.
- When measurement results and metrics disagree, review and analyze first, then decide on corrections or changes.
- Predictive projects usually carry out quality assurance formally; adaptive projects can do it formally or informally, with quality embedded in every iteration.
- Common adaptive practices: definition of done, automated testing and continuous integration, frequent reviews, smaller stories and technical excellence.
- The whole team shares responsibility for quality, and AI-assisted output must be reviewed by the team.
Lesson 6
Grade vs. Quality; Corrective Actions, Preventive Actions and Defect Repairs
Lesson overview
The last lesson of this chapter deals with two small exam points that are easy to overlook. The first is grade versus quality: a stem has someone say "this is the entry-level model, so lower quality doesn't matter", and you must decide how the project manager should respond. The second is what corrective actions, preventive actions and defect repairs each are and how they go through procedure once a quality problem has been found. The second point connects to the six problem-solving steps and to change control, and it is a frequent source of the right answer to "what should the project manager do?" scenario questions. ECO: Process domain, Task 7 (Plan and optimize quality of products/deliverables).
Grade is not quality
Grade is a classification of products that have the same use but different levels of features and specifications. For example, drills of the same type come as a home model and a professional jobsite model: the professional model has more torque, longer continuous running time and a higher price. Quality is the degree to which requirements are met, not how high-end the product is. A product with few features and a low grade has good quality as long as it consistently meets the requirements of its own grade. A product with many features that often breaks down is high grade and low quality. (Grade versus quality is a common exam term.)
Two judgments follow:
- Low grade is not a quality problem; low quality is. You cannot relax inspection because "it is the entry-level model". The entry-level model must meet its own requirements too.
- When you work through stakeholder needs and define the deliverables in planning, first be clear about the grade that is needed, and use that to set the product's features and quality requirements. If the grade is chosen wrongly, even the strictest quality management afterward is doing the wrong thing.
Grade and quality compared
| Situation | Grade | Quality |
|---|---|---|
| Simple features, but consistently meets its own requirements | Low | High |
| Full features, but often breaks down | High | Low |
| High-end, and built to requirements | High | High |
Three kinds of action
When quality audits, testing or quality reports find a problem, three kinds of action are commonly used. PMBOK 8 mentions them in connection with change requests: "Change requests may include corrective actions, preventive actions, defect repairs, or updates that reflect modified or additional ideas or content." Here is how they differ:
- Corrective action: bring performance that has already deviated back onto the planned track. For example, adjust a work process or an inspection mechanism that has failed.
- Preventive action: reduce the likelihood of a future deviation before it occurs. For example, improve the process or add training.
- Defect repair: rework, repair or replace the defect that was found. (The PMBOK 8 glossary defines rework as the "action taken to bring a defective or nonconforming component into compliance with requirements or specifications.")
The distinction among the three is common exam practice.
On a predictive project, when an action touches controlled artifacts or baselines, the three normally go in as change requests, which are reviewed and dispositioned through the Assess and Implement Changes process and carried out only after approval. An adaptive project usually puts the change into the backlog, does an impact analysis and prioritizes it, without necessarily having a formal approval process. Any stakeholder may request a change. Common exam practice: if the contract already covers the matter and the project baselines are not affected, for example when the contract says the supplier replaces nonconforming material, the project manager can ask the supplier directly to replace it without waiting for the change process, and certainly should not stop all work "to get to the bottom of it".
What to do after finding a defect
Order the steps using PMBOK 8's six problem-solving steps: define the problem; identify the root cause; generate possible solutions; choose the best solution; implement the solution; and verify solution effectiveness. Applied to a quality problem, that gives:
- Confirm the problem and find the cause first. Run a quality investigation to find out whether the defect comes from design, procurement or assembly. If the defect already creates a safety or compliance risk, or may keep escaping to the customer, first contain it temporarily: isolate the affected product and hold releases while you investigate.
- Generate alternative solutions, assess their impact and choose the best one.
- Then start correction and repair. Rework, replace or repair, and submit a change request where a change is needed.
- Consider prevention at the same time. Change the process or add training so the problem does not recur.
- Verify that it worked. Retest and see whether the metrics are back in the normal range.
- Communicate throughout. If the customer is already affected, correct it quickly and be open about the situation and the progress of the repair. But communication and apology cannot replace correction.
Example: a safety defect found before shipment
In the final check before shipment, a shared electric scooter project finds a major defect in the battery compartment mounting structure, which could work loose while riding. The customer begins deploying the scooters in two weeks. The project manager does this. (1) Immediately isolate the affected scooters and hold releases, and start a quality investigation at the same time, using a cause-and-effect diagram to list possible causes (design tolerance, fastener batch, assembly torque) and checking them against data. (2) The investigation finds that one fastener batch is nonconforming, so the project manager proposes defect repair on the scooters already assembled: replace the fasteners and reinspect. The proposed defect repair and corrective action go through the change management plan as a change request, which is assessed for impact and approved by the authorized person or change control board before implementation. (3) Corrective action: quarantine fasteners from the same batch and restore the confirmed incoming inspection and release process, so that later performance returns to what the quality plan requires. (4) Preventive action: add torque sampling to the release check, and add incoming inspection and a qualification review for the supplier, so the same problem does not escape again. (5) Explain to the customer the defect, the status of the fix and the assurances in place before deployment.
A quality metric that keeps sliding calls for the same approach. Analyze why it is sliding first, then take corrective action to pull performance back to the plan. Do not lower the standard, do not keep only the metrics that look good, and do not just "keep watching".
Worked examples
Example 1: a major safety defect found before shipment, with the customer deploying in two weeks
In the final check before shipment, the team on a shared electric scooter project finds a major defect in the mounting structure of the battery compartment, a key component. The mounting could work loose while riding and poses a safety risk to users, and the client plans to begin deploying these scooters in two weeks. What should the project manager do?
Show answer and explanation
Correct answer: B
In the final check before shipment, a major defect in the battery compartment mounting structure is a fact, and the client will deploy in two weeks, so there is time pressure. The question asks what the project manager should do most urgently now.
The defect has already occurred, so first isolate the affected scooters immediately to prevent delivery of an unsafe product and investigate whether the cause lies in design, procurement, or assembly. Following PMBOK 8, the proposed defect repair and corrective action should be raised as change requests, assessed for impact under the change management plan, and submitted to the authorized person or change control board. After approval, update the relevant plans and logs, notify affected parties, implement the changes, and verify their effectiveness. Defect repair addresses the existing scooters, while corrective action addresses the process that produced the defect. Client communication should be timely and run in parallel with the investigation and change process, but it cannot replace action. The answer is B.
Why the other options are wrong
- A. The stem does not say that this defect is an identified risk, and there is no contingent response strategy (a common exam term: contingency plan) that can be triggered directly. Paying the cost up front neither controls the safety risk nor determines the right remedy. It skips steps.
- C. Communicating with the client is necessary and should be done promptly. But explaining the cause in person before the cause is known removes neither the safety hazard nor the client's worry. It should run alongside investigation and correction, not replace them.
- D. An apology letter is only an attitude. It contains no corrective action, the defect is still there, and in two weeks the scooters would still be delivered with a safety risk.
Key takeaway On finding a major defect, immediately prevent delivery of nonconforming products and investigate the cause. Submit defect repair and corrective action through change control, implement them after approval, and keep the client informed.
Variation If the defect had already been found by the client in use and affected operations, correct it as soon as possible and explain the situation and the progress of the repair to the client. Communication runs in parallel with correction, but communicating without correcting is still not enough.
Something wrong with this question?
Example 2: "an entry-level model is low grade, so its quality must be low too"
At a project meeting, a member argues that a low-end model is a low grade, so its quality must also be low, and on that basis relaxes inspection of that model. What should the project manager do?
Show answer and explanation
Correct answer: B
At a meeting, a member argues that a low-end model is a low grade, so its quality must also be low, and relaxes inspection of that model on that basis. The question asks what the project manager should do.
Grade is a classification of products with the same use but different tiers of functions and specifications (grade versus quality is a common exam term). Quality is how well the deliverable's inherent characteristics meet the requirements and target objectives. Low grade does not mean low quality: as long as a low-end model meets the requirements of its own grade, its quality is acceptable, so inspection must not be relaxed. The project manager should clarify the difference between the two and require that the low grade meet its requirements as well. The required grade and its specifications should be established from the requirements, while quality management ensures that the product at that grade meets those requirements. If the wrong grade is selected, it should be corrected through requirements and scope management. The answer is B.
Why the other options are wrong
- A. Equating low grade with low quality is a confusion of concepts. Agreeing with it and cutting inspection frequency would leave the low-end model short of the requirements it should meet.
- C. Raising the feature level changes the product's grade. It is a matter of scope and requirements and does not solve the problem of relaxed inspection.
- D. Not clarifying lets the mistaken practice continue, and waiting for problems to appear is remediation after the fact.
Key takeaway Grade is a classification by tier, and quality is the degree to which requirements are met. Low grade does not mean low quality.
Variation The reverse is equally wrong. If someone says “the high-end model has many features, so its quality must be high”: a high-grade product that does not meet its own requirements still has low quality.
Something wrong with this question?
Common traps
Common trap
- It is wrong to treat "low grade" as "low quality" and relax inspection. Low grade is not a quality problem; low quality is.
- When you find a defect, investigate the cause and correct it first. Do not start by assigning blame, writing an apology letter or drawing on contingency reserve.
- Corrective action addresses a deviation that has already happened, preventive action addresses future deviation, and defect repair is the repair or replacement of the defect itself.
- Raising the feature level of the entry-level model changes the grade. It is not the way to fix relaxed inspection.
- Common exam practice: for nonconforming material that the contract already says the supplier replaces, the project manager asks for replacement directly and does not need the change process.
Key takeaways
- Grade is a classification by level of features and specifications; quality is the degree to which requirements are met. Low grade does not mean low quality.
- In planning, first be clear about the grade that is needed, and set features and quality requirements from it.
- Corrective action brings deviating performance back to plan; preventive action prevents future deviation; defect repair repairs or replaces the defect.
- When any of the three requires changing controlled project documents, deliverables or baselines, submit a change request, assess it through Assess and Implement Changes, and implement it once approved. For replacement of nonconforming material that the contract already requires the supplier to provide, common exam practice is that the project manager may ask the supplier directly.
- On finding a major defect: find the cause first, then correct and repair, verify that it worked, and communicate honestly. Communication cannot replace correction.
This chapter has 70 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.