Quality

The PMP study guide for Quality: 4 chapters and 15 lessons, about 3 h 1 min of study. Every lesson has worked examples with the explanation folded until you open it. Read the topic guide first ↓

Topic video

Watch the free Quality videos in the PMP video course →

Chapters in this topic

Topic guide

What this topic covers

Quality management answers three questions: what counts as good quality, how to build quality into processes and deliverables, and how to investigate and fix it when something goes wrong. PMBOK 8 puts this among the project management principles: Embed Quality Into Processes and Deliverables. Quality is the degree to which a set of inherent characteristics of a project deliverable or process helps to meet or exceed the project's target objectives. The goal of quality activities is to detect and prevent defects early, reduce rework and waste, and deliver without unnecessary delay. After this topic you should be able to do the following. Write and read a quality management plan and quality metrics. Tell quality assurance from quality control, and say which process each falls in under PMBOK 8. Choose the right quality tool for a scenario (audits, checklists, cause-and-effect diagrams, Pareto charts, control charts and so on). Classify costs of quality and judge whether an investment is worthwhile. Read a control chart and decide whether a process is out of control and whether the product is acceptable.

Quality topic mind map

Where quality work belongs

Quality planning, process quality, and deliverable quality fall under the following processes:

Quality workProcessWhere this course covers it
Establish quality requirements, standards, and the quality management planDefine ScopeQuality Planning and Assurance, Lessons 1 and 2
Ensure processes meet stakeholder expectations through audits, checklists, problem-solving, and process improvementManage Quality AssuranceQuality Planning and Assurance, Lessons 3 and 4
Inspect, test, and measure deliverables, producing verified deliverables, quality reports, and quality control measurementsMonitor and Control ScopeQuality Planning and Assurance, Lessons 3 and 5

If a question asks about testing whether deliverables meet requirements, the focus is quality control. If it asks about auditing whether a process complies, the focus is quality assurance.

The four chapters and how they relate

ChapterIn one sentenceLessons
Quality Planning and AssuranceWhat quality is, how to write the plan, how to tell assurance from control, how assurance is done, how adaptive projects do it, grade and corrective actions6 lessons
Cost of QualityWhat it costs to do it right, what it costs when it is not done right, and how much investment is the right amount2 lessons
Cause-and-Effect and Pareto DiagramsFind the causes first, then set priorities; what each of the common quality tools answers4 lessons
Control ChartsWhether a process is stable and whether the product is acceptable; how to read the chart3 lessons

The four chapters form a line that moves from the broad to the specific. First you build the framework (Quality Planning and Assurance), then measure it in money (Cost of Quality), then analyze problems with tools (Cause-and-Effect and Pareto Diagrams), and finally monitor the process with a statistical chart (Control Charts). The first two chapters lean toward concepts and scenarios and the last two toward tools and chart reading. Control charts are where you do the most chart reading and calculating in the whole topic.

What the ECO and the exam ask

In the ECO, quality falls mainly under Process domain, Task 7 (Plan and optimize quality of products/deliverables): collect the quality requirements of project deliverables, plan quality processes and tools, execute the quality management plan, help ensure regulatory compliance, manage cost of quality (CoQ) and sustainability, conduct ongoing quality reviews, and implement continuous improvement. Of these four chapters, Quality Planning and Assurance is the most frequently tested. The question types fall roughly into four kinds:

  1. Classification questions: is this piece of work quality assurance or quality control; is this expense a prevention, appraisal or failure cost.
  2. Tool-selection questions: a need is given and you pick the right tool. Watch the verb in the stem: why, which to handle first, check item by item, is it stable.
  3. Scenario questions: "what should the project manager do?" The answer is often to find the cause first, analyze first, communicate first, and explain the risk, without lowering the standard or cutting quality.
  4. Chart-reading and calculation questions: judging whether a control chart is in control and whether the product is acceptable; totaling costs of quality.

How to study

Study the chapters in order, and read each chapter's overview first. Later material refers back to earlier concepts: cost of quality uses "prevention, appraisal and failure", cause-and-effect and Pareto diagrams use "root cause", and control charts use "quality control".

Master five distinctions, which come up in every chapter's questions: quality versus grade; quality assurance (process) versus quality control (deliverables); cost of conformance versus cost of nonconformance; cause-and-effect diagram (find causes) versus Pareto chart (set priorities); control limits (calculated from the process) versus specification limits (the customer's requirement).

Remember three default answers used in common exam practice. If defects appear or the product misses its target, do root cause analysis first. If someone wants to cancel quality activities to save cost or time, explain the risk and hold to quality. If you find a process is not compliant, audit first and compare against the plan to find the gap.

Work calculation questions step by step. For cost of quality, classify first and then total. For control charts, use the five-step chart-reading method. For each lesson's worked examples, try them yourself by the steps first, then check against the collapsed solution.

Common mistakes to watch for

  • Treating grade as quality: an intentionally selected lower grade that meets requirements is not necessarily a quality problem; failure to meet quality requirements is.
  • Separating quality assurance from quality control by "who does it" rather than by focus (process or deliverable).
  • Treating the quality management plan as an activity: it is a basis and does not detect defects.
  • Counting appraisal costs as failure costs, or counting prevention costs as costs of nonconformance.
  • Choosing a cause-and-effect diagram when the question asks "which to handle first", or a Pareto chart when it asks "why".
  • Mixing up control limits and specification limits, and forgetting that "in control does not mean acceptable".
  • When defects are many, raising a change or lowering the standard first, instead of doing root cause analysis first.