Quality
Control Charts
PMP · Quality · 3 lessons · about 40 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
When doing quality control, the project manager often has to answer two questions: is this process stable, and is what it produces acceptable? The control chart answers the first, and the specification limits answer the second. The two must not be confused. PMBOK 8 says control charts are used to determine whether or not a process is stable or has predictable performance. Control limits are calculated statistically and represent the natural variation of a stable process, which is different from specification limits, which are set by requirements. Control charts are not limited to manufacturing; they can also monitor cost and schedule variances, the frequency of scope changes and other management results.
This is the only chapter in the whole topic that has "read the chart and calculate" questions. The two out-of-control rules in common exam practice are one point outside the control limits and seven consecutive points on the same side of the mean. Combined with the specification limits, they produce two counterintuitive cases: "in control but nonconforming" and "out of control but conforming". The chapter gives the five-step chart-reading method used in exam practice, and following it will earn you reliable points.
Lessons in this chapter
- Lesson 1: What Control Charts Are For, and Control Limits Versus Specification Limits. Purpose; natural variation and special causes; how the two sets of limits differ; the mean ± 3 sigma and the calculation formulas.
- Lesson 2: Judging Out-of-Control Signals and Worked Chart-Reading Examples. The two out-of-control signals; what to do when a process is out of control; the five-step chart-reading method (common exam practice); complete examples of in control but nonconforming and out of control but conforming.
- Lesson 3: Control Charts in Projects. Worked examples with a cost variance chart and a scope change frequency chart; how control charts, cause-and-effect diagrams and Pareto charts divide the work; predictive versus adaptive projects.
How to study this chapter
First get clear where the two sets of limits come from: specification limits are set from requirements, and control limits are "calculated" from the process. Once that is clear, the chart-reading questions that follow will not get tangled. Then memorize the two out-of-control rules, and work three to five worked examples with the five-step method, writing down each time, in order, "check for points outside, check for seven in a row, decide whether in control, check the specification, compare widths", and the answer comes out naturally. The use of control charts in projects in the last lesson is more conceptual; just hold on to two points: "control charts are not limited to factories" and "each of the three tools handles one part of the job".
Chapter map
Control chart (is the process stable, is performance predictable)
- Control limits UCL/LCL (calculated statistically from process data; on a common three-sigma chart, written as mean ± 3σ)
- Specification limits USL/LSL (set by product or project requirements)
- Out of control: one point outside · 7 consecutive points on one side → find the cause, take corrective action
- Five steps to read a chart: check for points outside → check for seven in a row → decide in control or not → check the specification → compare limit widths
- In projects: cost variance · schedule variance · defect counts · frequency of scope changes
Chapter practice: use the chapter exercises, starting with the core questions and then the required questions.
Lesson 1
What Control Charts Are For, and Control Limits Versus Specification Limits
Lesson overview
When doing quality control, the project manager often has to answer two questions: is this process stable, and is what it produces acceptable? The control chart answers the first question and the specification limits answer the second. The names are similar and the meanings differ, which makes this the biggest source of confusion in the chapter. This lesson first covers what a control chart is and what it is used for, and then where the two sets of limits come from, who sets them and how they are calculated. The next lesson covers how to read the chart to judge that a process is out of control, and uses worked examples to tell "in control but nonconforming" apart from "out of control but conforming".
What a control chart is
PMBOK 8 says: control charts are used to determine whether or not a process is stable or has predictable performance. Upper and lower specification limits are based on the requirements and reflect the maximum and minimum values allowed. Upper and lower control limits are different from specification limits. The control limits are determined using standard statistical calculations and principles to ultimately establish the natural capability for a stable process. The project manager and appropriate stakeholders may use the statistically calculated control limits to identify the points at which corrective action will be taken to prevent performance that remains outside the control limits.
The method is to plot the measured values of the process point by point in time order, then draw the center line (the mean), the upper control limit (UCL) and the lower control limit (LCL), and watch how the points vary. In a production setting the control chart is one of the core tools of statistical process control (SPC). In a stable process the data usually vary randomly up and down around the mean within a fairly fixed range. That variation is built into the process and is called natural variation. When a point falls outside that range, or the points form a clearly non-random pattern, it is generally taken as an out-of-control signal that a special cause may be at work and needs to be investigated (even a stable process has a very small chance of a random point outside), and the process is no longer considered stable. The value of the control chart is that it makes such changes visible as early as possible.
A chart that has no limit lines and simply plots the trend over time is called a trend chart. It is used to see whether a metric is rising or falling over time, for example to verify whether an improvement is working. If code reviews started last month and the weekly defect rate is plotted over time, you can see whether things are moving in the right direction.
The two sets of limits
When you analyze a chart you may see two sets of horizontal lines at once (control limits belong to the control chart, and specification limits can be overlaid when needed, to judge conformance). The names are similar, but the meanings are entirely different:
| Specification limits (USL, LSL) | Control limits (UCL, LCL) | |
|---|---|---|
| Meaning | Upper and lower specification limits, reflecting the maximum and minimum values allowed | Upper and lower control limits, representing the natural variation of a stable process |
| Basis | Requirements: the customer contract, product design specifications, regulations or organizational standards | The process's own data, calculated with standard statistical methods |
| Who sets them | Set from the requirements, which may come from the customer contract, product design specifications, regulations or organizational standards; unrelated to how the process actually performs | Calculated from data; cannot be changed at will to look better |
| What they judge | Whether a single product conforms | Whether the process is stable |
| Going outside means | That product is a defective unit | The process may have a special cause and needs investigating |
The control limits are usually set 3 sigma above and below the process mean (0 sigma). ±3 sigma is used because in a simplified model where the data are approximately normal, about 99.7% of the points fall within that range. A point landing outside is very unlikely, so when it happens it deserves serious attention. The exam treats ±3 sigma as the standard practice. Sigma (σ) is the standard deviation of the process data and reflects how large the variation is.
How to calculate: two small formulas
Control limits from σ (in the simplified exam model used in this lesson: individual values, approximately normal, centered on the mean; PMBOK 8 requires only that limits be determined by standard statistical principles and calculations, and the formulas for different control charts depend on the statistic and the subgroup size): UCL = mean + 3σ, LCL = mean − 3σ. σ back from the limits: σ = (UCL − LCL) ÷ 6, or σ = (UCL − mean) ÷ 3.
Example: a bottled-drink filling line
The customer contract specifies a net content of 320 ml to 340 ml per bottle. Those are the specification limits. The quality inspector records data continuously while the line runs normally: mean 330 ml, standard deviation σ = 1.5 ml.
- UCL = 330 + 3 × 1.5 = 334.5 ml
- LCL = 330 − 3 × 1.5 = 325.5 ml
- Compare: the control limits of 325.5-334.5 ml fall inside the specification limits of 320-340 ml, so the process capability is sufficient.
Going the other way, if you know only that UCL = 334.5 ml and LCL = 325.5 ml, then σ = (334.5 − 325.5) ÷ 6 = 1.5 ml, and the mean = (334.5 + 325.5) ÷ 2 = 330 ml.
Conclusion: specification limits are set by requirements; control limits are "calculated" from the process.
If a question asks "what are the upper and lower control limits based on?", the answer is statistical calculation from the process's historical data. It is not the contract tolerance, not something the project manager sets according to the target, and not the acceptance standard value approved by the sponsor.
When to choose a control chart
When the stem stresses "prove the process is stable", "predictable performance" or "judge whether it is out of control", choose the control chart. When it stresses whether the product is within the "acceptable range", compare against the specification limits or acceptance criteria; if you need to prove both, display both and judge the control limits and the specification limits separately. To set priorities, choose the Pareto chart; to find causes, the cause-and-effect diagram; to look at correlation, the scatter diagram. For example, a customer doubts the quality of a deliverable, and the project manager wants to use process data to prove the production process is stable and that quality has always been in the acceptable range. Use a control chart. Draw the control limits next to the data: if all points are inside the limits and show no abnormal trend, that proves only that the process is in control. Then draw the specification limits as well; only when the measured values also all fall within the specification limits does it prove the quality is acceptable.
Worked examples
Example 1 Using process data to show a customer the process is stable and performance predictable
PMLyceum has taken on the development of an online booking platform. The team has completed the main deliverables and demonstrates them to all parties at a review meeting. The customer representative expresses concern about the quality of these deliverables. The project manager wants to use process data to show that the process that produced these deliverables is stable and its performance is predictable. Which tool should be used?
Show answer and explanation
Correct answer: C
The main deliverables of an online booking platform are complete, and the customer is concerned about quality at the review meeting. The project manager wants to use process data to show that the process that produced the deliverables is stable and its performance is predictable.
The stem asks to “show that the process is stable”. A control chart plots process data in time order and displays upper and lower control limits, to determine whether the process is stable and its performance predictable. If the points all fall within the limits with no abnormal pattern, it can show the customer that the process is in control and performance is predictable. Note that control limits reflect the natural variation range of the process and are not the same as specification limits. To show whether the output conforms, you must also compare it with the specification limits or acceptance criteria. The answer is C.
Why the other options are wrong
- A. A Pareto chart sorts by frequency from highest to lowest to find the “vital few”. It cannot show whether a process is stable.
- B. A cause-and-effect diagram sorts out the possible causes of a problem. It is a tool for finding causes, not for proving quality.
- D. A scatter diagram looks at whether two variables are related. It also cannot judge whether a process is stable.
Key takeaway To prove that a process is stable and its performance predictable, use a control chart.
Variation If a point were outside the limits and the customer questioned the quality, the process may be out of control, so find the cause first instead of continuing to use the chart to claim stability.
Something wrong with this question?
Example 2 When you draw a control chart, what are the upper and lower control limits based on
The quality team on a part production line is drawing a control chart for part dimensions, and the customer contract gives tolerance requirements for the dimensions. When drawing it, what should the upper and lower control limits be based on?
Show answer and explanation
Correct answer: B
The quality team is drawing a control chart for part dimensions. They have both process data and the tolerance requirements from the customer contract. The question asks what the upper and lower control limits should be based on.
Control limits are calculated from the process's own data using standard statistical principles, are usually set 3 sigma above and below the mean, and represent the natural variation range of a stable process. It is the specification limits that are determined by customer requirements. So when you answer, look at “what is it based on”: limits calculated from process data are control limits, and limits given by customer or design requirements are specification limits. Therefore the answer is the process's historical data, calculated statistically: B.
Why the other options are wrong
- A. The contract tolerance is the customer's requirement for the product, and it corresponds to the upper and lower specification limits (USL, LSL), not control limits.
- C. The project manager can set quality objectives, but control limits cannot be set subjectively from objectives. They reflect the actual variation of the process, not the level one hopes to reach.
- D. Acceptance criteria approved by the sponsor are likewise requirements for the result and relate to specification limits. They do not determine control limits.
Key takeaway Control limits are calculated from process data, and specification limits are set by customer or design requirements. They are not the same thing.
Variation If the control limits use the mean-centered ±3σ convention, then with UCL 334.5 and LCL 325.5, σ = (334.5 − 325.5) ÷ 6 = 1.5 and the mean = (334.5 + 325.5) ÷ 2 = 330; the calculation never uses the specification limits.
Something wrong with this question?
Common traps
Common trap
- Specification limits are set by requirements (for example the customer contract, product design specifications, regulations or organizational standards), and control limits are calculated from the process. If a question asks what the control limits are based on, the answer is process data, not contract tolerance.
- Specification limits are usually outside the control limits, but not necessarily: when the process varies too much, the control limits can be wider than the specification limits (see the example in the next lesson).
- "Maximum and minimum acceptable values" should make you think of specification limits; "natural variation range" should make you think of control limits.
- A control chart judges process stability. It is not the tool for finding causes (cause-and-effect diagram), setting priorities (Pareto chart) or looking at correlation (scatter diagram).
- A trend chart has no control limits and only shows the direction of a metric over time; it can be used to verify whether an improvement is working.
Key takeaways
- A control chart determines whether a process is stable and whether its performance is predictable; in a production setting it is one of the core tools of statistical process control (SPC).
- A stable process varies randomly around the mean (natural variation). A point outside the limits or a clearly non-random pattern suggests a possible special cause; investigate and judge whether the process is still stable.
- Specification limits (USL, LSL) are set by requirements and judge whether a single product conforms. Control limits (UCL, LCL) are calculated from process data and judge whether the process is stable.
- Control limits are usually the mean ± 3 sigma: UCL = mean + 3σ, and σ = (UCL − LCL) ÷ 6.
- A chart with no limits that shows only the trend is a trend chart, and it can be used to verify whether an improvement is working.
Lesson 2
Judging Out-of-Control Signals and Worked Chart-Reading Examples: In Control but Nonconforming, Out of Control but Conforming
Lesson overview
Once the control chart is drawn, how do you read it? This lesson covers two things. One is how to judge that a process is out of control and what the project manager should do afterward. The other is how to read the control limits and the specification limits together to reach the two counterintuitive conclusions "in control but nonconforming" and "out of control but conforming". The second is the heart of the chart-reading calculation questions, and this lesson gives a fixed five-step method and two complete worked examples. Follow the steps and you will not be led astray by the distractor options.
How to judge that a process is out of control
"Out of control" means the distribution of the points shows that a special cause is affecting the process. Common exam practice uses two judgment rules:
- One point outside. If even one point falls outside the control limits, above or below, the process is out of control.
- Seven in a row. If 7 consecutive points fall on the same side of the mean, all above or all below, the process is out of control even if every point is still inside the control limits.
The reasoning for the second rule is that under random variation the points should, over time, be distributed on both sides of the mean. Seven in a row on the same side are unlikely to result from random variation alone, so they are treated as a signal that the mean may have shifted or another non-random change may have occurred. Its job is to give a warning before a point actually breaks through a control limit. (The seven-point rule is a commonly used exam rule.) PMBOK 8 says the project manager and appropriate stakeholders may use the statistically calculated control limits to identify the points at which corrective action will be taken to prevent performance that remains outside the control limits.
After an out-of-control signal, the project manager should find the cause and take corrective action. You may not let it go as chance variation, you may not loosen or recalculate the control limits on your own to put the points "back inside", you may not wait for the next round of data, and you certainly may not reduce sampling because of it. The control limits are calculated from the process's data in a stable state and reflect its natural capability; they are not there to accommodate the data.
The five-step chart-reading method
When you meet a chart-reading question, however the chart is drawn, the common exam practice is to go through the five steps below:
- Check whether any point is outside the control limits (above the UCL or below the LCL).
- Check whether 7 consecutive points fall on the same side of the mean.
- Draw the conclusion: is the process in control? If step 1 or step 2 holds, it is out of control. If neither holds, all you can say is that neither of these two out-of-control signals was found. (When a question tests only these two rules, treat the process as in control. A real chart should also be checked for trends, cycles and other non-random patterns.)
- Now look at the specification limits. Is any point beyond the upper or lower specification limit? If each point on the chart is the measured value of a single product, those beyond the specification limits are nonconforming units. If the points are statistics such as subgroup means, you have to judge from the original measurements whether individual units conform.
- Compare the widths of the two sets of limits. If the control limits are wider than the specification limits, the natural variation of the process is itself larger than what the customer allows. Even in control, it will produce defective units, and the process capability has to be improved. Only when the process is stable and the control limits lie inside the specification limits can you tentatively judge the process capability sufficient. When the process is out of control, deal with the special cause first and assess capability only after stability is restored.
The two judgments are independent of each other: whether it is in control depends on the control limits and the seven-point rule, and whether it conforms depends on the specification limits. One cannot substitute for the other. The four combinations:
| Combination | How the points look | Meaning | What the project manager should do |
|---|---|---|---|
| In control and conforming | Points are inside the control limits with no pattern, and inside the specification limits | The process is stable and the product conforms | Keep monitoring |
| In control but nonconforming | Points are inside the control limits, but some are beyond the specification limits | The process is stable but its capability is insufficient | Improve the process itself |
| Out of control but conforming | One point outside or seven in a row, and the product is still within specification | A special cause has appeared in the process | Find the cause and prevent it getting worse |
| Out of control and nonconforming | Out of control, and some points are beyond the specification limits | The process is unstable and the product also does not conform | Find the cause at once and deal with the nonconforming units |
Example 1: in control but nonconforming
A medical catheter has an outer-diameter specification of 4.90 mm to 5.10 mm. While the process runs stably, the mean is 5.00 mm and σ = 0.04 mm. In 20 sampled checks, the largest point is 5.11 mm and the smallest is 4.89 mm, with no 7 consecutive points on the same side.
- Step 1: UCL = 5.00 + 3 × 0.04 = 5.12 mm; LCL = 5.00 − 0.12 = 4.88 mm. 5.11 < 5.12 and 4.89 > 4.88, so no point is outside the control limits.
- Step 2: No 7 consecutive points on the same side of the mean.
- Step 3: Neither rule holds, so the process is in control.
- Step 4: The specification limits are 4.90-5.10 mm. 5.11 > 5.10 and 4.89 < 4.90, so those two units are nonconforming.
- Step 5: The control limits are 5.12 − 4.88 = 0.24 mm wide and the specification limits are 5.10 − 4.90 = 0.20 mm wide, so the control limits are wider and the process capability is insufficient. For the control limits to fit inside the specification limits you need 3σ ≤ 0.10, that is σ ≤ 0.10 ÷ 3 ≈ 0.0333 mm.
Conclusion: a stable process does not mean all products conform. Improve the process (change the equipment, change the method) to reduce σ, rather than adding inspection to pick out defective units. Address the common causes by improving the process, and decide according to the risk, the quality management plan and established procedures whether to pause production and isolate nonconforming units. But do not misjudge this as a special cause, and do not narrow the control limits to the specification limits.
Example 2: out of control but conforming
On a coffee capsule filling line, the net weight specification per portion is 5.5 g to 6.5 g. While it runs stably, the mean is 6.0 g, the upper control limit is 6.3 g and the lower control limit is 5.7 g. One day, the weights of 7 consecutive portions are 6.05, 6.10, 6.08, 6.12, 6.07, 6.15 and 6.09 g.
- Step 1: Assume the chart's control limits are the mean ± 3σ, so σ = (6.3 − 5.7) ÷ 6 = 0.1 g. All 7 points are within 5.7-6.3 g, so none is outside the limits.
- Step 2: All 7 points are above the mean of 6.0 g: 7 consecutive points on the same side. The rule holds.
- Step 3: Out of control.
- Step 4: The specification limits are 5.5-6.5 g and all 7 points are within them, so the product conforms.
- Step 5: The control limits are inside the specification limits, but the process has already shown an out-of-control signal (the mean may be shifting upward). At this stage it is not appropriate to claim that the process capability is sufficient; first find and deal with the special cause, and assess again once stability is restored.
Conclusion: all seven products now are conforming, so there is no need for rework for the moment. But the process has shown an out-of-control signal, and the cause must be found (for example a weighing sensor drifting or a change in material density), otherwise the risk that later products fall outside the specification limits rises. Seven points above the mean, however, are not enough to assert that the mean will keep shifting upward.
Worked examples
Example 1 One point falls outside the control limits and the rest are normal
A filling production line at PMLyceum is being monitored. The net content of the most recently sampled bottle falls outside the control limits on the control chart, and all the other points are within the limits. What should the project manager do?
Show answer and explanation
Correct answer: A
A filling line is being monitored, and the net content of the most recently sampled bottle falls outside the control limits on the control chart, with all the other points within the limits. The question asks what the project manager should do.
Control limits mark the range a stable process's natural variation can reach. As long as one point falls outside the limits, that is one of the cases of out of control, indicating that a special cause may exist, so judge the process out of control, look for the cause and take action. The judgment of out of control does not depend on whether the other points are normal. This is one of the ways to judge out of control; another is the “seven-point rule” used in exam practice, in which 7 consecutive points fall on the same side of the mean. The answer is A.
Why the other options are wrong
- B. The other points being within the limits cannot cancel the point outside; one point outside is enough for out of control.
- C. One point outside is already enough to establish out of control, and there is no need to wait for more data. Delay only lets the problem accumulate.
- D. A point outside the limits is beyond the range of natural variation and cannot be easily put down to chance. Chance fluctuation is usually inside the limits.
Key takeaway One point outside the control limits is out of control. Look for the cause first; do not let it pass as chance variation.
Variation If no point is outside but, under the seven-point rule used in exam practice, 7 consecutive points fall on the same side of the mean, it is also judged out of control; 6 consecutive points do not count yet.
Something wrong with this question?
Example 2 Chart reading and calculation: all points are inside the control limits, yet two points are beyond the specification limits
PMLyceum makes bolts for a piece of equipment, and the customer specifies that the length must be between 45 and 55 mm. The quality engineer takes 20 consecutive samples and draws the control chart (see figure): mean 50 mm, upper control limit 58 mm, lower control limit 42 mm. All data points are within the control limits, and there are no 7 consecutive points on the same side of the mean, but point 7 (56 mm) and point 11 (44 mm) are beyond the specification limits. How should the project manager interpret this?
Show answer and explanation
Correct answer: B
The bolt length specification is 45-55 mm, the control limits are 42-58 mm, and all points are within the control limits, but point 7 at 56 mm and point 11 at 44 mm are beyond the specification limits. The question asks how to interpret this.
The stem rules out the two common signals for a point beyond the control limits and 7 consecutive points on the same side of the mean (seven consecutive points on one side of the mean is treated as an out-of-control signal in common exam practice), and the chart shows no trend or other non-random pattern, so the process is stable and in control. But the control limits (42-58) are wider than the specification limits (45-55), which means the natural variation of the process is itself larger than the customer allows, so even an in-control process will still produce nonconforming units such as the 56 mm and 44 mm ones. Improve the process itself to reduce the variation, or negotiate the specification with the customer. The answer is B.
- Step 1, check for points outside: all points are within the control limits of 42-58 mm, so none is outside.
- Step 2, check for seven in a row: no 7 consecutive points on the same side of the mean of 50 mm.
- Step 3, conclude in control: neither out-of-control signal is present, so the process is in control.
- Step 4, check the specification limits of 45-55 mm: point 7 at 56 > 55 and point 11 at 44 < 45, so those two units are nonconforming.
- Step 5, compare widths: the control limits are 16 mm wide and the specification limits are 10 mm wide, so the control limits are wider and the natural variation exceeds what the customer allows.
- Conclusion: stable but with insufficient capability, so choose B.
Why the other options are wrong
- A. The bases for out of control are a point beyond the control limits, 7 consecutive points on one side and other non-random signals, not going beyond the specification limits. Both points beyond specification are within the control limits, so the process is not out of control and production need not be stopped.
- C. Looking only at the control limits would mislead you into thinking everything is normal. Points 7 and 11 are already beyond the specification limits, so the products do not conform.
- D. Control limits are calculated statistically and reflect the natural capability of the process. They cannot be narrowed artificially to suit the specification; the specification limits come from customer requirements.
Key takeaway In control means only that the process is stable; conformance depends on the specification limits. When the control limits are wider than the specification limits, even an in-control process produces defective units, and the process must be improved.
Variation If the control limits were 46-54 mm, inside the specification limits, the same two points at 56 and 44 would fall beyond the control limits and become out of control, and you would investigate special causes.
Something wrong with this question?
Example 3 Chart reading and calculation: all conform, but points 9 through 15 are 7 in a row above the mean
A packaging line at PMLyceum requires each bag to have a net weight of 238-262 g. The team leader samples one bag every hour and plots the weights on a control chart (see figure): mean 250 g, upper control limit 256 g, lower control limit 244 g. All 20 points are within both the control limits and the specification limits, but points 9 through 15 are 7 in a row above the mean. What should the project manager do next?
Show answer and explanation
Correct answer: D
The packaging line requires a net weight of 238-262 g per bag. The control chart has a mean of 250 g, an upper control limit of 256 g and a lower control limit of 244 g. All 20 points are within both the control limits and the specification limits, but points 9 through 15 are 7 in a row above the mean. The question asks what the project manager should do next.
In common exam practice, seven consecutive points on the same side of the mean is an out-of-control signal, even if no point goes beyond the control limits, so the process is judged out of control. At the same time, all 20 sampled points are within the specification limits, so the sampled units conform, and the stem shows no nonconforming products that would call for reworking the whole batch. But you do need to investigate and eliminate the abnormal cause (for example weighing equipment drift or a change in raw material), and correct it before the problem gets worse. Whether to stop production or expand inspection should be decided according to risk and established procedures. The answer is D.
- Step 1, check for points outside: the control limits are 244-256 g and all 20 points are inside them, so none is outside.
- Step 2, check for seven in a row: points 9 through 15, 7 points, are consecutively above the mean of 250 g, so the rule holds.
- Step 3, judgment: out of control.
- Step 4, check the specification limits of 238-262 g: all 20 sampled points are inside them, so the sampled units conform, and there is no sign of nonconforming products that would require reworking the whole batch.
- Conclusion: out of control but conforming; promptly find the cause and correct it, and decide whether to stop production according to risk and established procedures. Choose D.
Why the other options are wrong
- A. Conforming products do not mean the process is in control. Seven in a row on one side is already an out-of-control signal, and ignoring it would miss the chance for early correction.
- B. All 20 sampled units are within the specification limits, and the stem shows no nonconforming products needing rework, so you cannot demand an immediate stop and rework of everything on this basis. The response to out of control is to find the cause; whether to stop production or widen inspection afterward is decided by risk and established procedures.
- C. The purpose of the seven-point rule is to warn before a point goes beyond the limit. Waiting until a point is beyond the control limits is already too late.
Key takeaway Conformance of the product depends on the specification limits, and out of control depends on the control limits and the seven-point rule (exam practice). When a process is out of control but the product conforms, the cause must be found; whether to stop production or expand inspection is decided by risk and established procedures.
Variation If only 6 points were consecutively above the mean, it would not be out of control and you would keep monitoring; if one of the points reached 257 g, it would be beyond the upper control limit and judged out of control directly.
Something wrong with this question?
Common traps
Common trap
- Points inside the control limits do not mean the process is in control: seven in a row on the same side of the mean is also out of control.
- A point beyond the specification limits does not mean out of control. It means those units are nonconforming. The basis for out of control is a point beyond the control limits or seven in a row on one side.
- Out of control but the current products conform: you must find the cause and act in line with the quality management plan, and whether to stop production, isolate units or keep running under control is decided by the risk and the established procedures. In control but nonconforming: improve the process; do not go looking for special causes.
- When a question asks for the "next step", the answer lies in "analyze the cause and take action", not in "keep observing", "change the limits" or "reduce sampling".
- You cannot narrow the control limits to suit the specification; the control limits are calculated from process data.
Key takeaways
- This lesson focuses on two out-of-control signals used in common exam practice: one point outside the control limits, and 7 consecutive points on the same side of the mean. In practice you should also check for sustained trends, cycles and other non-random patterns.
- After an out-of-control signal, find the cause and take corrective action; do not loosen the limits, wait or reduce sampling.
- The five steps for reading a chart (common exam practice): check for points outside, check for seven in a row, decide in control or not, check the specification limits, compare the widths of the two sets of limits.
- Whether it is in control depends on the control limits, and whether it conforms depends on the specification limits. The two are independent.
- In control but nonconforming: improve the process capability. Out of control but conforming: the products are acceptable for now, but the special cause must be found; whether to stop production is decided by the quality management plan and the risk.
Lesson 3
Control Charts in Projects: Cost Variance, Scope Changes and Division of Work
Lesson overview
Some people assume the control chart belongs only to factories and plots part dimensions. Not so: control charts are used most frequently to track repetitive activities required for producing manufactured lots, but they may also be used to monitor cost and schedule variances, volume, frequency of scope changes, or other management results to help determine if the project management processes are in control. This lesson covers how to apply a control chart to project management metrics, how to calculate the limits from earlier data and judge later points, and how the control chart divides the work with the cause-and-effect diagram and the Pareto chart.
What a control chart can monitor
PMBOK 8 states that control charts can be used to monitor various types of output variables. Although used most frequently to track repetitive activities required for producing manufactured lots, control charts may also be used to monitor cost and schedule variances, volume, frequency of scope changes, or other management results to help determine if the project management processes are in control.
In a project, the metrics that can be drawn as a control chart include: cost variance and schedule variance each week; the number of defects found each day; the number of scope change requests each month; and the number of defects or the test pass rate in each iteration. PMBOK 8 lists control charts among the tools for Monitor and Control Resourcing, and quality control activities (including measuring the quality of deliverables) fall under monitoring scope, which shows that their use is not limited to product dimensions.
How to do it: from data to judgment
The method is the same as in the last lesson, except that the subject is now a management metric. There are five steps:
- Take data from a stable period (for example the first 12 to 15 periods of the project) and calculate the mean and the standard deviation σ.
- Control limits: the simplified approach used in common exam practice is UCL = mean + 3σ and LCL = mean − 3σ (a real project should calculate them according to the type of data, the type of control chart and the sample size). Note: calculate from stable-period data. When an abnormal signal appears, investigate the cause first. Remove that point from the sample used to estimate the limits and recalculate only after the special cause has been confirmed and documented and either eliminated or shown not to represent the current process. You cannot delete a point just because it looks abnormal.
- Plot the later data point by point in time order.
- Common exam practice uses two rules to judge out-of-control signals: one point outside the control limits, and 7 consecutive points on the same side of the mean (in a real project, follow the out-of-control detection rules your organization has adopted).
- Once the process is out of control, find the cause, correct it if necessary, and raise a change request if a change is needed.
Example 1: a cost variance control chart
On an inventory management system project, the mean weekly cost variance over the first 15 weeks is +$10,000 (this example records variance as actual cost minus planned cost, so a positive value means an overrun; that is the opposite sign convention to CV = EV − AC in earned value management, so do not mix them), and σ = $20,000.
- UCL = $10,000 + 3 × $20,000 = +$70,000; LCL = $10,000 − $60,000 = −$50,000.
- The variances in weeks 16 and 17 are +$25,000 and +$30,000. They are inside the limits and are not seven in a row, so they are normal.
- The variance in week 18 is +$85,000. $85,000 > $70,000, so it is above the upper control limit: out of control.
What to do: the project manager must investigate what happened in week 18 (did a supplier raise prices all at once? was there rework? unplanned overtime?), determine whether it is a special cause or a planning problem, and take corrective action if necessary. The point is not to wait until the variance is too big to recover from, and certainly not to raise the upper control limit to put the point "back inside".
Example 2: a scope change frequency control chart
A website redesign project uses a predictive approach. Over the first 12 months, the mean number of scope change requests per month is 6, with σ = 1.5.
- UCL = 6 + 3 × 1.5 = 10.5; LCL = 6 − 4.5 = 1.5.
- In month 13 there are 12. 12 > 10.5, so it is above the upper control limit: out of control.
- Suppose instead that in months 14 through 20 no month exceeded the upper limit, but 7 months in a row were above the mean of 6. That is also an out-of-control signal.
Reading: a stable change frequency means the scope management process is in control. A sudden spike or a run above the mean suggests something may be wrong with scope management, and you need to find out whether the requirements are unclear, communication is poor or control is too loose.
How the control chart, cause-and-effect diagram and Pareto chart divide the work
These three tools are often tested together, and each handles one part of the job: the control chart finds that "the process has a problem"; the cause-and-effect diagram finds "why"; and the Pareto chart decides "what to handle first". The typical order of use: the control chart gives an out-of-control signal, the team traces the causes with a cause-and-effect diagram and ranks them with a Pareto chart, and after the correction the control chart is used again to verify that the process has returned to stability. When the stem mentions "judge stability, predictable, out of control", choose the control chart. Whether the frequency of changes is stable is also a control chart question; where the changes mainly come from is a Pareto chart question; whether the number of changes is related to the duration is a scatter diagram question.
Predictive versus adaptive
Quality control on predictive projects may use sampling per batch or per phase, with control charts used to monitor the stability of cost and schedule variances and defects. Adaptive approaches may be iterative, incremental, or both; teams can track metrics such as defects and test pass rates by iteration, plotting them as trend charts or suitable control charts to assess stability and inform adjustments at the retrospective.
Worked examples
Example 1 In a cost variance control chart, week 18 is the first point above the upper control limit
A software project at PMLyceum has entered execution. The project manager plots weekly cost variance on a control chart, with control limits calculated statistically from the first 15 weeks of data. The point for week 18 is the first to be above the upper control limit, all other weeks are within the limits, and there are no 7 consecutive points on the same side of the mean. What should the project manager do?
Show answer and explanation
Correct answer: A
A software project has entered execution, and the project manager plots weekly cost variance on a control chart, with control limits calculated statistically from the first 15 weeks. The point for week 18 is the first above the upper control limit, all other weeks are within the limits, and there are no 7 consecutive points on one side.
Control charts are not limited to production batches; they can also monitor management results such as cost variance, schedule variance and scope change frequency. The control limits represent the natural variation range of a stable process, and the week 18 point beyond the upper control limit is an out-of-control signal, meaning a special cause may have appeared. The project manager should find the reason for the abnormal variance that week, take corrective action if necessary, and raise a change request if one is needed. When handling it, “find the cause”: first work out whether it is a special cause (for example a one-time supplier price increase) or a problem with the plan itself, and then decide whether to correct. The answer is A.
Why the other options are wrong
- B. A point beyond the control limit is unlikely under natural variation, so it is treated as an out-of-control signal and cannot simply be ignored.
- C. Control limits reflect the natural capability of the process and cannot be adjusted at will just to make a data point look “normal”.
- D. One point beyond the limit means only that an investigation is needed. It is not enough to judge the project a failure or to submit a request to terminate it.
Key takeaway A control chart can monitor management results such as cost and schedule variance; when a point is beyond the control limits, investigate the cause and correct as the situation requires.
Variation If week 18's variance were inside the limits but weeks 12 through 18 were 7 weeks in a row above the mean, that would also be out of control, and you would investigate why the variance has been high for so long.
Something wrong with this question?
Example 2 Counting scope change requests by month and judging whether the change frequency is stable
A website redesign project at PMLyceum uses a predictive approach. The project manager counts the number of scope change requests each month, wanting to know whether the change frequency stays stable over time, in order to judge whether the scope management process is in control. Someone on the team believes control charts apply only to batch production in manufacturing. Which of the following is the most suitable approach?
Show answer and explanation
Correct answer: C
A website redesign project uses a predictive approach, and the project manager counts scope change requests each month, wanting to know whether the change frequency is stable and whether the scope management process is in control. Someone on the team thinks control charts apply only to manufacturing.
A control chart is used to determine whether a process is stable or its performance predictable. It is used most often in batch production, but PMBOK 8 explicitly says it can also monitor management results such as the frequency of scope changes. Plot the monthly number of changes in time order between the control limits and see whether they fall inside the limits and whether any run stays high, and you can judge whether the change frequency is stable. When you answer, first look at what the stem asks you to judge, “stable or not”, and then pick from the tools the one that can answer that question. The answer is C.
Why the other options are wrong
- A. A Pareto chart sorts by frequency to find the “vital few”. It answers where the changes mainly come from, not whether the frequency is stable.
- B. A scatter diagram looks at the correlation between two variables and cannot judge whether the change frequency is stable over time.
- D. A histogram shows the shape of the distribution of data, has no time order and no control limits, and cannot judge whether a process is in control.
Key takeaway Control charts are not limited to manufacturing and can also monitor management results such as scope change frequency and cost and schedule variance.
Variation To find out which department the changes mainly come from, use a Pareto chart; to see whether the number of changes is related to the project duration, use a scatter diagram.
Something wrong with this question?
Common traps
Common trap
- Control charts are not just for batch production in manufacturing: management results such as cost variance, schedule variance and scope change frequency can all use them.
- A point outside the control limits is an out-of-control signal that is unlikely under natural variation, and it is not enough to declare the project a failure either. Find the cause first and correct if necessary.
- Do not adjust the limits just to make the points look "normal". The limits are calculated from stable-period data and do not include abnormal points.
- To see whether a frequency is stable, use the control chart; to see the share by source, the Pareto chart; to see causes, the cause-and-effect diagram; to see correlation, the scatter diagram.
- The control chart is a tool for discovering problems; it does not replace root cause analysis.
Key takeaways
- A control chart can monitor management results such as cost and schedule variances, volume and the frequency of scope changes, to judge whether the project management process is in control.
- Method: calculate the mean and σ from stable-period data to get the UCL and LCL, then plot the later data point by point.
- One point outside and seven in a row on one side are both out-of-control signals. After one, find the cause and correct if necessary. Do not adjust the limits at will to put an abnormal point back inside (removing a point and recalculating after a special cause has been confirmed and documented and either eliminated or shown not to represent the current process, or recalculating from new stable data after a systematic process change, are appropriate).
- Division of work: the control chart finds the problem, the cause-and-effect diagram finds the cause, the Pareto chart sets the priorities, and after the correction the control chart verifies the result.
- On adaptive projects you can plot the number of defects, the pass rate and similar metrics per iteration as a trend chart or control chart and use them in the retrospective.
This chapter has 14 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.