Identifying and Analyzing Stakeholders

PMP · Stakeholders and Communication · 4 lessons · about 44 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

The Stakeholders performance domain is about people. For a project to succeed, you first need to know who is connected with it, what they care about and which of them need the most attention. This chapter is the starting point of the whole topic. It first covers who stakeholders are and which seven processes make up the performance domain, then how the Identify Stakeholders step finds people and which people it finds. Next comes analysis, which turns the list into "what each person wants and which side they are on". Then mapping and classification, where models such as the power/interest grid decide how to spend your effort. Finally the register, which records everything above in one place and is kept up to date as people change.

Nearly all the questions in this chapter are scenario questions, and the common patterns are four: whether to include opponents, what to do right after identification, matching a person to a cell of the power/interest grid, and what to do and in what order when a new person appears.

Lessons in this chapter

Chapter map

Stakeholders performance domain (seven processes; initiating has only "Identify Stakeholders")

Identify Stakeholders

  • Inputs: project charter · business documents · agreements · other plans and logs
  • Data gathering: questionnaires and surveys · brainstorming · brainwriting
  • Analysis: position · role · stakes (interest, rights, ownership, knowledge, contribution) · expectations · attitude
  • Mapping: power/interest grid · cube · salience model · upward/downward/outward/sideward · prioritization
  • Outputs: stakeholder register (identification, assessment, classification), plus change requests, project management plan updates, project documents updates

New or replaced person: first register and analyze (update the stakeholder register) → update the stakeholder engagement plan → update the communications management plan as needed (the order of handling used in exam practice)

Chapter practice: do the "Identifying and analyzing stakeholders" topic in the chapter exercises, starting with the core questions.

Lesson 1

The Stakeholders Performance Domain and Identifying Stakeholders

Lesson video

Lesson overview

Until now the material has been mostly about work and money. From here on it is about people. The Stakeholders performance domain is about people: from finding out who is connected with the project to monitoring their engagement throughout the life cycle. This lesson first makes clear who stakeholders are and which seven processes the domain contains, and then covers the first step in the sequence: Identify Stakeholders. It corresponds to the first item, "identify stakeholders", of ECO: People domain, Task 4 (Engage stakeholders). Most of the exam scenarios in this lesson are of the kind "someone has been left out; what does the project manager do?" The next lesson covers the analysis that follows identification.

Who stakeholders are

A stakeholder is an individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a portfolio, program, or project. PMBOK 8 counts the project sponsor, team members, and all the people impacted by, or who feel they may be impacted by, the project. A project can have a small group of stakeholders or potentially millions of them. There may be different stakeholders in different phases of the project, and the influence, power, or interests of stakeholders may change as the project unfolds.

Effective stakeholder identification, analysis, and engagement includes stakeholders who are either internal or external to the organization, those who are supportive of the project, those who are neutral, and opponents, who are not supportive of the project. This is the most important sentence in the lesson: people who oppose the project are stakeholders too, and are often the ones who most need to be seen. PMBOK 8 also says the activities of identification, prioritization, and engagement should be reviewed and updated routinely, or at least when the project progresses through phases.

As for team members, by definition they are of course stakeholders. In exam stems, however, to tell the roles apart, team members are sometimes named separately and the others are called "stakeholders", such as the customer, the sponsor, managers of other departments, users, regulators and the public. Use the stem to judge the scope; do not exclude team members just because the word "stakeholders" has been used.

Where the seven processes sit

PMBOK 8 splits the work of the Stakeholders performance domain into seven processes: Identify Stakeholders, Plan Stakeholder Engagement, Plan Communications Management, Manage Stakeholder Engagement, Manage Communications, Monitor Stakeholder Engagement and Monitor Communications. They are spread across the four focus areas of initiating, planning, executing, and monitoring and controlling, and closing has no process of its own. Initiating has just one, Identify Stakeholders; the other six split into "engagement" and "communication" under planning, executing and monitoring and controlling. The four chapters of this topic cover, in turn, identifying and analyzing, engagement, planning communications and managing communications.

The seven processes of the Stakeholders performance domain

Identify Stakeholders: what it does

The Identify Stakeholders process involves selecting the individuals, groups, or organizations that have a stake in the project. The process includes identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success. The key benefit of this process is that it enables the project team to identify the appropriate focus for the engagement of each stakeholder or group of stakeholders.

This process is not done once and finished. The project environment keeps changing, and continuous stakeholder identification can work as a risk management strategy: the people who were not identified often become the source of later risks. So it is performed periodically throughout the project as needed, and whenever the sponsor changes, a phase changes, the organization is restructured, or someone joins or leaves, you should go back and do it again. The earlier the better, because the degree of stakeholder engagement directly affects success or failure.

Where to find people: inputs, data gathering and outputs

Among the inputs to identification, three point straight to "who the stakeholders are". The project charter lists the key stakeholders and sometimes states their responsibilities. Among the business documents, the business case gives the initial list of those affected by the project, and the benefits management plan identifies the individuals and groups who will benefit from the results. The parties to an agreement are all stakeholders, and may lead you to others. The other inputs include the communications management plan, the stakeholder engagement plan, the change log, the issue log, the requirements documentation, enterprise environmental factors and organizational process assets.

There are two kinds of data gathering. Questionnaires and surveys suit situations with many people who are spread widely; brainstorming asks a group of people for input. Brainwriting is one of the brainstorming techniques: first everyone writes down their own ideas, then they are shared and discussed as a group. It can be done in person or online, and it keeps the loudest voice from steering the whole room. After identification come stakeholder analysis and mapping, which are the content of the next two lessons.

The core output is the stakeholder register. The others are change requests, and updates to the project management plan (requirements management plan, communications management plan, risk management plan, stakeholder engagement plan) and to project documents (assumption log, issue log, risk register).

Example: finding the people for a district library's lending system

A district library is upgrading its lending system. The project manager opens the project charter and sees that the library director is the sponsor and the head of the information center is responsible for the technology. The business case says "reduce readers' waiting time in line", which brings readers and the circulation desk staff to mind. The agreement with the software vendor adds the vendor's project manager and the on-site engineer to the list. Then comes a brainstorming session, where a librarian points out that older readers in the community cannot use the self-service kiosks and the neighborhood office often borrows books in bulk. The list grows from the initial 6 individuals and groups to 8. The neighborhood office appeared in none of the documents and was added through the brainstorming.

Worked examples

Example 1 Scope of coverage: should opponents be included

Question 1Example

A city plans to build a new waste-to-energy incineration plant, which once built will reduce dependence on external waste treatment facilities. The project manager has the support of several district leaders, but some resident representatives and some people in the city argue that the project should be halted and replaced with a program of waste sorting and recycling. Which stakeholders should the project manager include in the stakeholder engagement plan?

Show answer and explanation

Correct answer: D

On a waste-to-energy plant project in a city, the district leaders support it, while resident representatives and some others oppose it. The question asks which stakeholders the engagement plan should include.

A stakeholder is an individual, group or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a portfolio, program, or project. Identification and engagement must cover those inside and outside the organization, including supporters, neutrals and opponents. The stem sets support and opposition side by side, and the key is “do not pick and choose”: the criterion for inclusion is whether they may affect, be affected by, or perceive themselves to be affected by the project, regardless of their attitude and regardless of who designated them. The resident representatives and others who want the project halted are on the list as well. So the plan should cover all the identified stakeholders who may affect, be affected by, or perceive themselves to be affected by the project. The answer is D.

Why the other options are wrong

  • A. Stakeholders are defined by their relationship to the project, not designated by the sponsor. Choosing people only by the sponsor's wishes leaves out those the sponsor did not think of or does not want to face.
  • B. Supporters only leaves out the neutrals and the opponents. Later resistance often comes from opponents who were not managed, and supporters' support also needs to be maintained.
  • C. Opponents only is equally incomplete. Supporters and neutrals also need to be engaged and communicated with, or their support will drain away over time.

Key takeaway The engagement plan does not pick and choose: every identified stakeholder who may affect, be affected by, or perceive themselves to be affected by the project must be considered, and opponents in particular must not be left out.

Variation Including only high-power stakeholders would be just as incomplete: residents and users with low power and high interest also have to be managed, only with a different intensity. Only when the question asks “who to manage closely” do you answer by layering on power and interest.

Something wrong with this question?

Report an issue with this question

Example 2 All the work conforms, yet the product is not accepted

Question 2Example

A software company is developing a scheduling system for internal use. Preparation was thorough and a very high quality measurement standard was set. The project is progressing according to the project management plan, the product quality measurements all meet those standards, schedule and cost match the baselines, scope is being developed strictly to the scope baseline, and everything else is also as planned. At this point the project manager is told that the product cannot pass acceptance and the project may be terminated. What is the most likely cause?

Show answer and explanation

Correct answer: C

On an internal scheduling system project, schedule, cost, scope and quality measurements all match the baselines, yet the project manager is told the product cannot pass acceptance and the project may be terminated. The most likely cause has to be judged.

The stem rules out the internal causes one by one: the quality standard was set high, the stem also says the quality measurements met the standard, and schedule, cost and scope show no deviations. The work was done exactly to plan and the result was still rejected, which shows the plan itself left something out. The most common omission is a key stakeholder who was not identified, whose requirements never entered the requirements documentation or scope, so the product naturally does not match. People who were not identified often become the source of later risks, so the answer is C.

Why the other options are wrong

  • A. The stem makes clear the quality standard was high and the quality measurements met it, so quality is not the cause.
  • B. A sponsor withdrawing support could indeed end a project, but the direct trigger in the stem is that the product cannot be accepted, and nothing points to the sponsor's attitude.
  • D. The stem does not show the team meeting an insurmountable technical obstacle; on the contrary it shows the planned scope and the set quality standards were achieved. That cannot explain “completed to plan yet cannot be accepted” the way a missed key stakeholder and their requirements can.

Key takeaway When all the work conforms but the product is not accepted, first suspect that a key stakeholder was not identified and their requirements were not collected.

Variation If the schedule were badly behind and costs overrun, the answer would turn to technical difficulty or resource problems. When the signal changes from “everything matches the baseline” to “deviations appear”, the cause changes with it.

Something wrong with this question?

Report an issue with this question

Example 3 The customer says to ignore the opposing group

Question 3Example

A viaduct section of a city rail transit project is under construction, and a residents' rights group along the route questions whether the project is necessary. The customer tells the project manager to ignore the group, on the grounds that they do not support the project. What should the project manager do next?

Show answer and explanation

Correct answer: B

During construction of a rail transit viaduct, a residents' rights group along the route questions the project's necessity, and the customer says to ignore them. The question asks what the project manager should do next.

Groups affected by the project or who perceive themselves to be affected are stakeholders, and opponents are no exception, so “they do not support the project” is not a reason to ignore them. Identifying stakeholders continues throughout the project, so a group that appears during construction is added as soon as it is found. The project manager should add the group to the stakeholder register, analyze their potential impact on the project, and then set an engagement strategy accordingly. The customer funds the project and their view matters, but it cannot replace the project manager's responsibility to identify and manage stakeholders. The answer is B.

Why the other options are wrong

  • A. Having the customer tell the group about progress and the completion date is one-way information. The project manager has not yet identified the group as stakeholders or learned why they question the project, and a progress update does not address their concern about whether the project is necessary. Identify and analyze first; that decides who should engage them and how.
  • C. The customer funding the project does not mean other stakeholders can be dropped. The project manager is responsible for the smooth delivery of the project and cannot disregard possible resistance because of a customer instruction.
  • D. Telling the team to ignore all the group's correspondence gives up on analyzing and managing this group, and the problem is left to grow into a bigger conflict later.

Key takeaway A group that opposes the project is also a stakeholder: first register them and analyze their impact, and do not ignore anyone just because they do not support the project.

Variation If the group said it would complain to the media, then after registering and analyzing them, raise their priority, set a targeted communication strategy and report this risk to the sponsor.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Stakeholders are not only people with a say. People who are affected but have no decision power (such as residents or end users) are stakeholders too, and they are the easiest to miss.
  • The people you analyze and engage include opponents. If you focus only on supporters, you will be interrupted later by sudden resistance.
  • A customer or sponsor saying "ignore them" does not cancel a group's status as stakeholders: first register them, analyze their impact, and then decide how to engage them.
  • Identification is not a one-time job. When a new group or a new manager appears mid-project, add them to the register right away, analyze their interests, influence and involvement at the same time, and then update the engagement plan accordingly.
  • When every baseline is normal but the product is rejected, use the clues in the stem to check the requirements and acceptance criteria, the quality of the product, and whether stakeholders were identified and engaged (PMBOK 8 stresses collecting end-user feedback continuously and verifying and validating iteratively, to lower the risk that the product does not deliver its intended utility). Common exam practice: when all the metrics match the plan and the product is still rejected, the first suspicion is often that a key stakeholder was not identified, rather than quality or technology; if the stem gives other clues, follow them.

Key takeaways

  1. A stakeholder is an individual, group or organization that can affect the project, be affected by it, or perceive itself to be affected; supporters, neutrals and opponents all count.
  2. The Stakeholders performance domain has seven processes; initiating has only Identify Stakeholders, and the other six belong to planning, executing and monitoring and controlling.
  3. Identification must cover those inside and outside the organization, the earlier the better, and be repeated periodically, at least once at phase transitions.
  4. Sources for finding people: the project charter, business documents and agreements, plus questionnaires and surveys, brainstorming and brainwriting.
  5. The output is the stakeholder register, along with change requests and updates to related plans and documents.
  6. When every baseline is normal and the product is rejected, and the stem hints at users who were missed or whose needs were not taken in, first suspect that a key stakeholder was missed (common exam practice).

Lesson 2

Stakeholder Analysis: What Information to Collect and the Five Kinds of Stakes

Lesson video

Lesson overview

Having the list is not enough; knowing only "who" is not enough. This lesson covers stakeholder analysis, which means finding out what each person cares about, what they want and which side they are on. Identification and analysis are not two independent processes in sequence. The Identify Stakeholders process itself includes analyzing and documenting their interests, involvement, interdependencies, influence and potential impact on project success; stakeholder analysis is a core piece of work (a tool and technique) within that process. After you have found the potential stakeholders, you analyze and record this information further, and once you have enough, you use it to plan stakeholder engagement and communication. Stems often ask "what is the next step after identification?" and "how do you find out someone's motive and expectations?" The last lesson covered how to find people; the next covers how to classify them after the analysis.

What the analysis collects

The result of stakeholder analysis is a list of stakeholders and relevant information about each of them: their position in the organization, their role on the project, their "stakes", their expectations, their attitude (their level of support for the project), and their interest in information about the project. What initial identification gives you is mainly names and identities; analysis adds "motive" and "stance", and this information decides how you engage them later.

Stakeholders' stakes may include but are not limited to a combination of the following, and one person often falls into several at once:

StakeMeaningExample
InterestA person or group can be affected by a decision related to the project or its outcomesA head nurse who will switch to new scheduling software
RightsLegal rights, such as occupational health and safety, or moral rights, such as protection of historical sites or environmental sustainabilityA nearby school demanding that noise meet standards
OwnershipA person or group has a legal title to an asset or a propertyThe owner of the construction land
KnowledgeThe person may have specialist knowledge, which can benefit the project through more effective delivery of project objectives, organizational outcomes, or knowledge of the power structures of the organizationA foreman with twenty years on the job
ContributionThe person may provide funds or other resources, including human resources, or offer support for the project in more intangible ways, such as advocacy in the form of promoting the objectives of the project or acting as a buffer between the project and the power structures of the organization and its politicsA vice president willing to speak for the project at board meetings

A memory aid: five words, "interest, rights, ownership, knowledge, contribution". The exam rarely asks you to recite the order. More often it gives you a person and asks which kind of stake it is, or the reverse, asks why a certain kind of person should also be included.

How to do the analysis

Analysis is not guessing while sitting in the office. You can go in this order:

  1. For each person on the list, first write down the identity information you already know: position, role and contact details.
  2. Judge which kinds of stake they hold and which part of the project's outcome they care about most.
  3. Find out their expectations and where their attitude toward the project falls: supportive, neutral or opposed.
  4. Assess what they can bring to the project, and what resistance they could cause it.
  5. Write the conclusions into the stakeholder register as the basis for classification and for setting engagement strategies.

Where does the information come from? The most direct way is to ask the person. For personal motives and real concerns, a one-on-one interview is usually better than a group email or a public meeting: it lowers the concerns the other person has about speaking openly, and the project manager can ask follow-up questions (information sensitivity, trust and organizational culture also affect how truthful the answers are, so cross-check with questionnaires, document analysis and other sources where needed). The business case, agreements and historical project data can give background and some clues about roles and expectations, but they are usually not enough to confirm a particular person's current motive and real attitude, which still needs to be verified.

Analysis has one more direct use: tailoring communication content. The exam content outline lists "analyze and tailor communication to stakeholder needs" as a separate item, meaning that for the same matter you tell the sponsor about benefits and risks, tell the user how to use it and tell the regulator about compliance, and you do not send one common message to everyone. This is also why planning communications management later draws on the register.

The conclusions of the analysis should include different treatment for different groups: people who care about the result need to be informed often, people who hold approval authority need to be communicated with early, and people who hold opposing views need to be understood as to why. That way, when you later draw up the engagement plan and the communications management plan, you can have "one strategy per person".

Example: analysis records for a hospital

A city hospital is launching a new inpatient scheduling system. The project manager analyzed four key stakeholders:

  • Director of nursing: the highest-ranking person in the department; stakes are interest and contribution; expects "fewer scheduling complaints"; supportive.
  • Night-shift nurse representative: front-line level; stake is interest; worried that shift-swap rules will become stricter; neutral leaning opposed.
  • Head of the IT department: stake is knowledge; expects clear interfaces and does not want to take the blame for operations; neutral.
  • The hospital's labor union: stake is rights, concerned whether working hours comply with regulations; attitude not yet expressed.

The night-shift representative's concern was drawn out in a one-on-one interview; at the open meeting she did not say a word.

Worked examples

Example 1 How to get information on a person's motives

Question 1Example

PMLyceum is implementing a membership system for a supermarket chain. The project manager is building the stakeholder register and is not sure of the motives of several customer-side leads. To get this information, what should the project manager do?

Show answer and explanation

Correct answer: B

On a supermarket chain's membership system project, the project manager is building the stakeholder register and is not sure of the motives of several customer-side leads, and needs to decide how to get this information.

Motives and expectations are information that stakeholder analysis has to collect, and the most reliable source is the person themselves. In a one-on-one conversation with no one else present, a lead is more willing to state real concerns, and the project manager can ask follow-up questions and observe their attitude. Public statements and written statements tend to be official in tone, and inferring from documents is even less reliable. The answer is B.

Why the other options are wrong

  • A. In a public setting such as a kickoff meeting, leads tend to hold back and will not easily state their real motives, and there is no way to ask follow-up questions one by one.
  • C. An email yields only a statement about the project objectives. It does not reveal personal motives and does not allow follow-up questions.
  • D. The business case states objectives at the project level. Inferring each person's motives from it is subjective guesswork and is unreliable.

Key takeaway If you are unsure of a stakeholder's motives, talk to the person one on one. A one-on-one conversation helps you understand motives and also supplies a basis for later communication methods and engagement strategies.

Variation If you need to learn the common needs of eighty users in a short time, one-on-one is impractical, so choose a questionnaire or focus group. One-on-one suits a small number of key people.

Something wrong with this question?

Report an issue with this question

Example 2 The list is done: what is the next step

Question 2Example

After a brainstorming session, the project manager has a list of the project's main stakeholders. What should be done immediately after that?

Show answer and explanation

Correct answer: D

After a brainstorming session, the project manager has a list of the main stakeholders. The question asks what to do immediately next.

The brainstorming has just produced a preliminary list, and what follows is further analysis: assess each person's power, interest, expectations and attitude, classify them on that basis, and only then set engagement strategies. The signal in the stem is “the list has just been obtained”, with neither analysis nor classification done yet, so the next step is to assess each person's power and interest. The answer is D.

Why the other options are wrong

  • A. Monitoring is work that follows setting engagement strategies and starting engagement. At this point there is no analysis and nothing to monitor.
  • B. Reporting progress is communication and comes after analyzing and planning communication. It is not yet clear what information each person needs.
  • C. Putting people to work belongs to engagement, which comes after analysis, once strategies have been designed for different people. Putting everyone to work now has no basis and can easily cause resentment.

Key takeaway After forming a preliminary list, keep analyzing and classifying, and only then set strategies and engage them.

Variation If the analysis and classification are already done and the question asks what comes next, it is to plan stakeholder engagement: set strategies for each category of stakeholder.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Identification gives you the list; analysis gives you "what they want and which side they are on". Starting to report progress or putting people to work as soon as you have the list skips the analysis.
  • A stake is not the same as a high position. Affected residents and long-serving employees who hold knowledge also have stakes.
  • The business case mainly explains the project's economic feasibility, the reason for starting it, the costs, the benefits, how value is created and the success criteria. It usually cannot tell you directly someone's current motive; ask the person.
  • Silence in public is not agreement. A key person's real concerns often come out only in a private conversation.
  • Analysis is not a one-time job. People's attitudes change, and the conclusions need to be updated in the register as the project moves on.

Key takeaways

  1. The analysis has to pin down six things: position, role and stakes, plus expectations, attitude and what project information they want.
  2. The five common kinds of stake (PMBOK 8 says "may include but are not limited to"): interest, rights, ownership, knowledge and contribution, and a person can hold several.
  3. Analysis is core work within the Identify Stakeholders process. Common exam practice: when the stem asks "what is the next step after identification?", answer with analysis, then classification, then planning engagement.
  4. To learn a person's motives and real concerns, a one-on-one interview is usually the better fit, cross-checked with questionnaires, document analysis and other sources where needed.
  5. Write the conclusions of the analysis into the stakeholder register and update them as attitudes change.

Lesson 3

Stakeholder Mapping and Classification: the Power/Interest Grid and Other Models

Lesson video

Lesson overview

After the analysis, you have to decide "who to spend your effort on, and how much", and that means classifying the stakeholders. This lesson covers several commonly used mapping models: grid models such as the power/interest grid, the stakeholder cube, the salience model and directions of influence. The focus is on the power/interest grid, which is the most tested, and on which occasion each model suits. It corresponds to the "categorize stakeholders" item of ECO: People domain, Task 5 (Align stakeholder expectations). The last lesson covered analysis; the next covers the register.

Why map

Stakeholder mapping and representation is a method of categorizing stakeholders using various methods. Classification does two things: it assists the project team in building relationships with the identified project stakeholders, and when there are many stakeholders, it helps decide who to manage first and to what degree. A project's time and effort are limited. Spread your effort evenly over a hundred people and the few who matter most often end up not managed well.

Grid models: the power/interest grid

The power/interest grid, power/influence grid and impact/influence grid are all two-dimensional grids, and each supports a grouping of stakeholders according to their level of authority (power), level of concern about the project's outcomes (interest), ability to influence the outcomes of the project (influence), or ability to cause changes to the project's planning or execution (impact). These classification models are useful for small projects or projects with simple relationships between stakeholders and the project, or within the stakeholder community itself.

The power/interest grid is the one that appears most often on the exam. The four strategies below (manage closely, keep satisfied, keep informed, monitor) are common exam practice. PMBOK 8 says that grid models group stakeholders by dimensions such as power and interest:

Power/interest grid
CellPowerInterestStrategyPurpose
Manage closelyHighHighInvest the most effort and communicate closelyWin them over as a driver of the project
Keep satisfiedHighLowKeep them satisfied and communicate at a moderate levelKeep them from becoming a source of resistance
Keep informedLowHighInform them often and keep information flowingReassure them and hear their views
MonitorLowLowSpend the least effort but keep watchingNotice promptly when their position changes

The way to work a question is to judge the two dimensions first and then place the person: "has final say" and "can veto" mean high power; "very concerned about success or failure" and "directly uses the result" mean high interest. If both are high, manage closely; even if the person is opposed at the moment, you do not downgrade them but communicate with them proactively.

Example: five people on a community senior-care service platform project

  • The deputy director of the district civil affairs bureau: funds the project and approves acceptance, pays little attention to daily details, and normally listens only to quarterly reports. High power, low interest: keep satisfied.
  • The director of the nursing home: day-to-day operation after launch depends on this person, who is picky about functions and also has the power to veto acceptance. High power, high interest: manage closely.
  • The care workers' team leader: uses the platform every day to dispatch jobs but has no decision-making authority. Low power, high interest: keep informed.
  • A courier company's contact in another district: only occasionally delivers medicine for the elderly. Low power, low interest: monitor.
  • The property management office: for now it provides only one equipment room, but if the platform later connects to door access control, its position will rise and it will need to be reassessed.

The cube, the salience model and directions of influence

  • Stakeholder cube: a refinement of the grid models, combining the grid elements into a three-dimensional model. It improves the depiction of the stakeholder community as a multidimensional entity and assists with the development of communication strategies.
  • Salience model: describes classes of stakeholders based on assessments of three dimensions: power (level of authority or ability to influence the outcomes of the project), urgency (need for immediate attention, either time-constrained or relating to the stakeholders' high stakes in the outcome) and legitimacy (their involvement is appropriate). It is useful for large, complex communities of stakeholders or where there are complex networks of relationships within the community. It is also useful in determining the relative importance of the identified stakeholders. PMBOK 8 also mentions an adaptation that substitutes proximity for legitimacy, meaning stakeholders' direct involvement in the project activities, such as their physical proximity to the worksite or their direct contribution to project deliverables.
  • Directions of influence: upward (senior management of the performing organization or customer organization, the sponsor, and the steering committee); downward (the team or specialists contributing knowledge or skills in a temporary capacity); outward (stakeholder groups and their representatives outside the project team, such as suppliers, government departments, the public, end users and regulators); and sideward (the peers of the project manager, such as other project managers or middle managers who are in competition for scarce project resources or who collaborate with the project manager in sharing resources or information).
  • Prioritization: needed when there are many stakeholders, when the membership of the stakeholder community changes frequently, or when the relationships are complex. PMBOK 8 notes that the stakeholders with the greatest concern and influence are usually placed at the top of the list; the specific method of ranking can be tailored to the project context.
The four directions of influence of stakeholders

How do you choose a model? If the question gives two dimensions, use a grid. If it says the community is huge and the relationships complex, choose the salience model. If it says you want the full three-dimensional picture, choose the cube. If it says to classify by "position relative to the organization", choose directions of influence.

How to understand "influence" and "impact"

Note that in PMBOK 8, "influence" is the ability to influence the outcomes of the project, while the "ability to cause changes to the project's planning or execution" is another basis for grouping, called impact. Do not read "influence" as the degree of active participation in the project. If these dimensions appear on the exam, understand them as PMBOK 8 does.

Worked examples

Example 1 High power, high interest: how to manage

Question 1Example

A supermarket chain group launches a store inventory management system project, and the project charter has just been approved. In identifying stakeholders, the project manager finds that the group's president both cares a great deal about whether the project succeeds and holds final decision authority. According to the power/interest grid, how should the project manager manage the president?

Show answer and explanation

Correct answer: B

A supermarket chain group launches a store inventory management system project, and the charter has just been approved. The project manager finds the group's president both cares greatly about success and holds final decision authority. The question asks how to manage the president according to the power/interest grid.

Break down the stem first: “cares a great deal about whether the project succeeds” is high interest, and “holds final decision authority” is high power. High power and high interest fall in the “manage closely” cell of the grid (the four strategy names are a common exam term). Invest the most effort, communicate closely and manage the president's expectations. People in this cell can drive the project and can also bring it down, so you cannot skimp on communication. The answer is B.

Why the other options are wrong

  • A. Keep satisfied is for people with high power and low interest. The president's interest is high, and merely “keeping satisfied” would leave a highly concerned person without enough involvement.
  • C. Keep informed is for people with low power and high interest. The president has the highest power, and merely reporting progress without managing closely would let go of the person who most needs to be won over.
  • D. Monitor is for people with low power and low interest. The president is high on both, so just watching their moves would seriously underestimate their influence on success or failure.

Key takeaway High power and high interest mean manage closely; judge the two dimensions first and then place the person.

Variation If the president has high power but does not care about project details, place them in keep satisfied: ensure they do not become a roadblock at the approval stage, and give regular brief reports.

Something wrong with this question?

Report an issue with this question

Example 2 High power, high interest, yet opposed

Question 2Example

On a process renovation project at an auto parts plant, the project manager finds that the vice president of sales has great power and pays close attention to the project, yet states clearly that he opposes it. What should the project manager do?

Show answer and explanation

Correct answer: C

On a process renovation project at an auto parts plant, the vice president of sales has great power and pays close attention to the project but openly opposes it. The question asks for the right way for the project manager to respond.

The vice president has high power and high interest, so he falls in the “manage closely” cell (the four strategy names are a common exam term). His opposition does not change the cell he is in; it shows that he needs even more active management. The project manager should communicate proactively, find out why he objects, try to win his support and tailor the engagement approach within the manager's authority; any proposed change affecting approved scope or baselines must go through change control. Leaving a high-power opponent alone will make him a roadblock on approvals and resources. The answer is C.

Why the other options are wrong

  • A. Monitor is for people with low power and low interest. The vice president is high on both, and watching only when necessary would let his opposition keep festering.
  • B. Keep satisfied is for people with high power and low interest. The vice president's interest is high and he is opposing, so without proactive communication you cannot find out and resolve his concerns.
  • D. Keep informed is for people with low power and high interest. Passive reporting while waiting for him to state his position is far from enough for a high-power opponent.

Key takeaway For a high-power, high-interest opponent, manage actively and closely and win his support.

Variation If the vice president had high power but did not care about the project and merely held a veto at approval, he would fall in keep satisfied: keep up moderate communication so he does not become a roadblock.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • People with high power and low interest are the easiest to overlook, yet they may hold approval authority. The purpose of "keep satisfied" is to keep them from becoming a source of resistance.
  • People with low power and low interest need only the least effort (monitor), but keep watching them, because their position may change as the project moves on.
  • A person with high power and high interest who is opposed still belongs to "manage closely". Communicate with them proactively instead of dropping them to monitor.
  • "Keep informed" fits low power and high interest. For a person with high power, merely reporting progress is not enough.
  • Classification is not permanent: after a phase change or a change of people, place them in the grid again and update the register.

Key takeaways

  1. Mapping is for classifying, and it decides who gets your effort.
  2. Power/interest grid: high-high is manage closely, high power low interest is keep satisfied, low power high interest is keep informed, low-low is monitor.
  3. Grid models suit simple situations; the cube is three-dimensional; the salience model (power, urgency, legitimacy) suits large, complex communities.
  4. Directions of influence: upward, downward, outward, sideward.
  5. When there are many stakeholders or they change frequently, prioritize (PMBOK 8 notes that the stakeholders with the greatest concern and influence are usually placed at the top of the list).

Lesson 4

The Stakeholder Register: What to Record and What to Do When a New Person Appears

Lesson video

Lesson overview

The results of identification, analysis and classification all land in one document: the stakeholder register. It is the starting point for the engagement and communication work that follows. The scenario questions on this topic are numerous, and almost all follow the same pattern: in the middle of the project a new stakeholder pops up, or an existing stakeholder is replaced, and the question asks "what should the project manager do?" This lesson covers what is in the register, how it divides the work with the engagement plan, and the order of handling when a new person appears.

What the register records

The stakeholder register is a project document that contains information about project stakeholders, including an assessment and classification of project stakeholders; it is the main output of the Identify Stakeholders process. The register holds at least three kinds of information:

CategoryContent
Identification informationName, organizational position, location and contact details, and role on the project
Assessment informationMajor requirements, expectations, potential for influencing project outcomes, and the phase of the project life cycle where the stakeholder has the most influence or impact
ClassificationInternal/external; impact/influence/power/interest; upward/downward/outward/sideward; or any other classification model chosen by the project manager

The register in actual use is often a table with one row per person or per type of person. For example: "Section chief at a district health bureau, point of contact, cares about data security and acceptance timing, high power, high interest, support level 4". The support level is expressed on a scale of a few levels, and the project team defines the scale.

The register and the engagement plan divide the work differently

First separate the two documents. The register focuses on "who this person is, how much power and interest they have, and their attitude"; response measures are normally not its focus. How to engage them belongs primarily in the stakeholder engagement plan. PMBOK 8 describes the engagement plan in terms of "strategies and actions". Common exam practice: the current and desired engagement levels (from the stakeholder engagement assessment matrix) go together with the strategies in the stakeholder engagement plan; the register holds who the person is and the assessment and classification. This differs from the risk register, which has risk responses built in.

So by common exam practice, if a question asks "where are engagement levels and response strategies recorded?", the answer is the engagement plan. If it asks "who are the people and what are their power and interest?", the answer is the register. The two documents are linked: the engagement plan and the communications management plan both take input from the register, so when the register changes, both plans have to be checked.

When to update, and what to do when a new person appears

The register is a living document. The project manager should review it routinely throughout the project as needed (at least as the project moves through phases), and update it whenever a new stakeholder joins, someone leaves, or someone's power, interest or attitude changes. When a new stakeholder appears during execution, the order of handling used in exam practice is:

  1. First enter them in the register and analyze them: who they are, how much power and interest they have, what information they need and what their attitude is.
  2. Then decide from that how to engage them: update the stakeholder engagement plan, setting their current and desired engagement levels and the strategy.
  3. If they need to receive project information, update the communications management plan, stating the content, frequency and method of communication.
  4. After that, carry it out according to the plan and check the results when monitoring.

The most important thing in the order is "analyze first, then update the plans". If you copy the newcomer on every email without analyzing, you cannot tell what they really need; if you refuse on the grounds that "you are not in the plan", you are treating the plan as a dead document that cannot be changed. Likewise, when an existing stakeholder is replaced, the successor cannot be assumed to fit the predecessor's classification; analyze them again and then update the register.

Example: handling a change of personnel

Halfway through an upgrade project for a logistics and warehousing system, the customer's business lead was moved to another project, and the new lead who took over had never been involved with this one. The project manager did not simply treat the newcomer as a copy of the predecessor. She arranged an interview to learn what the person cared about and their attitude toward the project, then created a new row in the register with the power, interest and expectations, and changed the engagement level and strategy for that position in the engagement plan. The former lead was kept in the register but marked as reassigned. A few weeks later at a regular meeting, the new lead asked for a briefing every two weeks, and the project manager added that item to the communications management plan right away.

Worked examples

Example 1 Communication missed the user lead: which document to check

Question 1Example

Early in a real estate company's customer management system project, the requirements document keeps failing to get approved. On checking, it turns out that a user department head was not included in the requirements-gathering communication. Which of the following documents may have omissions or be out of date?

Show answer and explanation

Correct answer: C

Early in a real estate company's customer management system project, the requirements document has not been approved. On checking, a user department head was not included in the requirements-gathering communication, and the question asks which document may have omissions or be out of date.

Who the project communicates with and who takes part depend on the stakeholder register, which records the identity, assessment and classification of all identified stakeholders. That the requirements communication left out the user department head suggests the register may not have listed this head, or was not updated in time as the organization changed. So you should check the stakeholder register. The answer is C.

Why the other options are wrong

  • A. Business documents (the business case and the benefits management plan) give only an initial list of affected individuals and groups. They are not the documents that maintain the communication audience. When a communication audience misses someone, check whether the register has an omission or is out of date.
  • B. The risk register records risks and responses. It is not the document that lists stakeholders and determines who to communicate with.
  • D. The project charter lists only key stakeholders. It is not the basis for the full list, and it would not be judged out of date because one user department head was missed.

Key takeaway When communication leaves someone out, first check whether the stakeholder register has an omission or is out of date.

Variation If a stakeholder's communication frequency does not match their needs, check the communications management plan, not the register.

Something wrong with this question?

Report an issue with this question

Example 2 A new department manager asks to be included in communication

Question 2Example

During project execution, the company sets up a new data analytics department, and its manager asks to be included in the project's regular communication and reporting. What should the project manager do?

Show answer and explanation

Correct answer: B

During project execution, the company sets up a new data analytics department, and its manager asks to join the project's regular communication and reporting. The question asks what the project manager should do.

The new department manager is a newly added stakeholder, and the appearance of this person shows that the list and the plans need updating. The correct order is to enter the manager in the stakeholder register while carrying out stakeholder analysis, find out what information the manager needs and how deeply to be involved, and then update the communications management plan accordingly, stating the content, frequency and method of communication. Also check the stakeholder engagement plan and update it if needed. That manages the manager's expectations and also avoids information overload. The answer is B.

Why the other options are wrong

  • A. Having the manager take part in all communication without analysis means you cannot tell what information the manager really needs, and it goes against the principle of communicating as needed.
  • C. The communications management plan is not a dead document that cannot be changed. When a new stakeholder and new needs appear, it should be updated. Using the plan as an excuse to refuse is wrong.
  • D. Communication is the project manager's responsibility. Pushing this manager to the steering committee and the project management office amounts to avoiding the problem.

Key takeaway When a new stakeholder appears, register and analyze them first and then update the communications management plan.

Variation If the newcomer is a senior executive with major impact, register and analyze them first, clarify their desired engagement level, then update the engagement plan and the communications management plan as needed.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The register normally does not emphasize response measures; strategies and actions belong primarily in the engagement plan. Common exam practice: engagement levels (unaware, resistant, neutral, supportive, leading) are recorded together with the strategies in the engagement plan. When a question asks "where are the strategies written?", answer the engagement plan.
  • When a new person appears, first enter them in the register and analyze them, then update the engagement plan and the communications management plan. Do not first copy them on every email, and do not refuse on the grounds that they are not in the plan.
  • When communication missed someone, first suspect whether the register has an omission or is out of date, not the business case or the risk register.
  • The project charter lists only key stakeholders. It is not the full list and cannot replace the register.
  • After updating the register, do not forget to go back and check the engagement plan and the communications management plan.

Key takeaways

  1. The register holds three kinds of information: identification, assessment and classification, and it is the main output of Identify Stakeholders.
  2. The register focuses on people and their assessment; common exam practice is to write strategies and the current and desired engagement levels in the stakeholder engagement plan.
  3. When people change or attitudes change, update the register; review it at phase transitions and update it when the information has changed.
  4. A new stakeholder: first register and analyze them, then update the engagement plan and the communications management plan.
  5. When communication left someone out: if the person left out is a stakeholder who has not yet been identified or whose registered information is out of date, check and update the register; if the person is already in the register but was not included among the recipients of information, check and update the communications management plan.

This chapter has 57 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.