Stakeholders and Communication
Stakeholder Engagement
PMP · Stakeholders and Communication · 5 lessons · about 55 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Identification and analysis answered “who are they and what do they care about?” This chapter answers “how do we get them involved in the project in the right way?” It follows the order of the processes. Plan Stakeholder Engagement produces the engagement plan and uses the stakeholder engagement assessment matrix to compare each person's current and desired engagement level. Manage Stakeholder Engagement carries out the plan by communicating and collaborating, and uses interpersonal skills to handle concerns and conflict. Aligning and managing expectations is what ECO People domain Tasks 5 and 6 require, and it lands mainly in Manage Stakeholder Engagement. Finally, Monitor Stakeholder Engagement checks how well engagement is working and adjusts strategies and plans when it finds a gap.
Scenario questions come in endless variety, yet the answer is often the same action: first find out what the other person wants, then communicate to align, and if scope has to change, go through change control.
Lessons in this chapter
- Lesson 1: Planning stakeholder engagement and the stakeholder engagement plan. Purpose, inputs and techniques; strategies tailored to individuals or groups of stakeholders (a common exam term: “one strategy per person”); root cause analysis to find out why someone resists; what the plan contains and why it is sensitive (common exam practice).
- Lesson 2: The stakeholder engagement assessment matrix: five engagement levels and the C–D gap. Unaware, resistant, neutral, supportive, leading; C for current, D for desired; the difference between supportive and leading.
- Lesson 3: Managing stakeholder engagement: follow the plan, and use interpersonal skills for concerns and conflict. Four kinds of activity; the five conflict resolution techniques; negotiation, ground rules and the sponsor.
- Lesson 4: Aligning and managing stakeholder expectations: dissatisfaction, conflict and out-of-scope requests. The two ECO tasks; clarify first, check the basis, then align, and go through change control if scope must change; common scenarios.
- Lesson 5: Monitoring stakeholder engagement: assess results, adjust strategy and plan. Re-comparing with the assessment matrix; what to do when someone cannot be reached or engagement drops; telling planning, managing and monitoring apart.
Chapter map
Plan engagement ──► Engagement plan (current/desired engagement levels, strategies; may contain sensitive information, and common exam practice is to control access and distribution according to content and organizational requirements)
- Assessment matrix: unaware · resistant · neutral · supportive · leading (C current, D desired)
Manage engagement ──► Execute the plan: gain support · manage expectations · address concerns · reach agreement
- Five conflict techniques: withdraw/avoid · smooth/accommodate · compromise/reconcile · force/direct · collaborate/problem-solve
Expectations: clarify first → check the basis → align → change if needed → record and update
Monitor engagement ──► Re-compare C and D → adjust strategy → update the engagement plan and communications management plan
Lesson 1
Planning Stakeholder Engagement and the Stakeholder Engagement Plan
Lesson overview
The list of stakeholders is done, and each person has been analyzed and classified. The next question is how to get these people involved in the project in the right way. That is Plan Stakeholder Engagement. According to the PMBOK 8 inputs and outputs diagram, its formal output is project management plan updates, specifically creating or updating the stakeholder engagement plan within them; in common exam practice this is shortened to “the output is the stakeholder engagement plan.” This lesson covers the purpose, inputs and techniques of the process, what goes into the plan, and when confidentiality measures may be needed. It corresponds to the step before ECO People domain Task 4 (Engage stakeholders), “execute the stakeholder engagement plan”: you need a plan first. The next lesson covers its most important tool, the stakeholder engagement assessment matrix.
What Plan Stakeholder Engagement does
“Plan Stakeholder Engagement is the process of developing strategies to engage identified project stakeholders based on their needs, expectations, interests, requirements, and potential impact on the project. The key benefit of this process is that it provides an actionable plan to interact effectively with stakeholders.” It is performed periodically throughout the project as needed; it is not something you write once at kickoff and put away.
The results of the previous three lessons become the basis for action here. The register says who they are, analysis and classification say what they care about and how closely to manage them, and engagement planning answers “for each person, what exactly do we do?” Common exam practice sums it up in one phrase: “one strategy per person.” Among opponents, someone worried about the schedule and someone worried about noise need different approaches.
Inputs and techniques
Four inputs deserve attention. The resource management plan includes the roles and responsibilities of team members and other stakeholders. The communications management plan is an input to this process and is also updated continuously as project needs and status change. The risk management plan includes the risk appetite of key stakeholders and the corresponding risk thresholds, which helps in choosing the most suitable combination of engagement strategies. The stakeholder register provides the list, classifications and other information. Others include the project charter, assumption log, change log, issue log, project schedule, risk register and agreements.
| Category | Technique | Purpose |
|---|---|---|
| Data gathering | Benchmarking | Compare with comparable organizations or projects to identify good practices and ideas for improvement |
| Data analysis | Assumption and constraint analysis | Work through current assumptions and constraints so that engagement strategies are tailored realistically |
| Data analysis | Root cause analysis | Find the cause of a person's current engagement level so you can choose strategies to raise it |
| Decision-making | Prioritization/ranking | Needed when there are many stakeholders, they change often or the relationships are complex. PMBOK 8 notes that stakeholders with the most interest and the highest influence are often prioritized at the top of the list; the exact ranking rules should still be tailored to the project |
| Data representation | Mind mapping | Consolidate ideas into a single map that reflects commonality and differences in understanding and generates new ideas |
| Data representation | Stakeholder engagement assessment matrix | Compare current and desired engagement levels |
| Other | Expert judgment, meetings |
Root cause analysis deserves the most attention: only by understanding why someone resists can you choose a more targeted strategy. If the worry is extra workload, talk to him with a plan that lightens the load; if the worry is being sidelined, talk to him about taking part in decisions.
The stakeholder engagement plan
The formal output of planning is project management plan updates, specifically creating or updating the stakeholder engagement plan (one of the components of the project management plan). PMBOK 8 defines it this way: “The stakeholder engagement plan is a component of the program or project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in program or project decision-making and execution. The plan can be formal or informal and highly detailed or broadly framed, based on the needs of the project and the expectations of stakeholders. The stakeholder engagement plan may include but is not limited to specific strategies or approaches for engaging with individuals or groups of stakeholders.”
That is the PMBOK 8 definition of the engagement plan. Common exam practice: besides the information in the register, plans often state the current and desired engagement levels of key stakeholders; the scope and impact of stakeholder changes; and the relationships among stakeholders and the overlaps and intersections that may arise.
The plan may contain sensitive information. Common exam practice is to protect assessments of and strategies for particular people when disclosure could damage relationships, using precautions such as limiting access. PMBOK 8 notes that the sensitivity and confidentiality of information may call for additional security measures; in practice you can limit access according to how sensitive the information is and what the organization requires.
Example: designing an engagement strategy for a project kickoff meeting
On a store system upgrade project for a pharmacy chain, the project manager must announce at the kickoff meeting that the inventory module will go live in the second release. From the register, the project manager sees that the regional purchasing director has always regarded the inventory module as the point of the project: high power, high interest, and likely to object. The project manager does three things. First, root cause analysis shows that what the director cares about is “a lower out-of-stock rate.” Second, the project manager arranges a one-on-one meeting with him the day before the kickoff, first listening to his thoughts and then explaining the technical reason for the delay, and proposing that release 1 include an out-of-stock alert. Third, the director's current level, “Neutral” (confirmed in the pre-meeting conversation: he knows the project and neither supports nor opposes it), and his desired level, “Supportive,” go into the engagement plan. The rating rests on the result of the conversation: if it were confirmed that he resists the changes the project's work or outcomes might bring, he would be rated Resistant. At the kickoff meeting the director does not object on the spot and even adds the acceptance criteria for the out-of-stock alert.
Worked examples
Example 1 Foreseeing that a key person will object: what to do in advance
PMLyceum has taken on an 8-month store system upgrade project. At the project kickoff meeting, the project manager plans to announce that one data migration task will finish later than originally planned. That task is exactly what one key stakeholder values most about the project, and he is expected to object strongly. What should the project manager do to reduce the chance of a strong rejection at the kickoff meeting?
Show answer and explanation
Correct answer: B
The project kickoff meeting is coming up, and the project manager foresees that a key stakeholder will object strongly to the delay to be announced there. The question is how to lower the chance of rejection in advance.
Stakeholder engagement has to happen before a problem erupts. The signals in the stem are “is expected to object strongly” and “reduce the chance of a strong rejection at the kickoff meeting”: the goal is to defuse the disagreement, not to respond to a conflict. A private conversation before the meeting lets the project manager learn why this work matters to him and hear his views on scope and timing, so the disagreement is worked through beforehand and he is not blindsided at the meeting. The answer is B.
Why the other options are wrong
- A. The assessment matrix is only a tool for comparing current and desired engagement levels. It does not give him a chance to voice his views before the meeting, and it does nothing to ease his unhappiness about the delay.
- C. A written notice is one-way communication, and stating that the meeting will not reopen the discussion collects no feedback. The objection will simply surface later, at the meeting or after it, in a stronger form.
- D. Logging the risk and planning a response can be a supplementary step, but those actions do not engage him directly and do not do enough to reduce the chance of a strong objection at the kickoff meeting. The priority is to reach out, learn what he wants and resolve the disagreement beforehand.
Key takeaway When you foresee that a key stakeholder will object, communicate proactively before the meeting and listen; do not wait to deal with it in the room.
Variation If he has already rejected the delay on the spot at the meeting, the first step is to steady the room and promise a follow-up conversation afterward, then find out what he needs. Prevention and after-the-fact repair lead to different answers.
Something wrong with this question?
Example 2 A newly appointed high-power person: what to do after the assessment
While the project is under way, the client reorganizes, and a newly appointed operations director holds final decision authority over the project budget and acceptance. After analyzing the director with the team, the project manager records him in the stakeholder register and assesses his current engagement level as “Unaware” and his desired level as “Supportive.” What should the project manager do next?
Show answer and explanation
Correct answer: A
A newly appointed client operations director has final authority over the budget and acceptance. The team has assessed his current engagement level as “Unaware” and his desired level as “Supportive,” and you must decide the right next step.
Identifying, assessing, planning and executing come in order. The team has already identified and assessed him: current level Unaware, desired level Supportive, so the gap is clear. The next step is to bring him into the stakeholder engagement plan and set engagement strategies and actions for closing that gap, for example, first help him understand the project and its potential impacts, then win his support. Updating the engagement plan and developing a targeted strategy is the work of Plan Stakeholder Engagement. The answer is A.
Why the other options are wrong
- B. Showing credentials is an attempt to please him. It develops no strategy around his needs and expectations and does nothing of substance to win his support.
- C. Putting all the effort into one director neglects other stakeholders. Engagement has to cover every important stakeholder, with effort allocated by priority.
- D. Giving in to every request leads to scope creep. It is not an engagement strategy and does not manage his expectations.
Key takeaway For a new key stakeholder, once the desired level is assessed, update the engagement plan and develop a targeted strategy.
Variation If the team had not yet assessed his current level, they would first assess it through conversations and observation, then compare the gap, and only then develop a strategy.
Something wrong with this question?
Common traps
Common trap
- The engagement plan is not written once. New stakeholders, a change in a key person's attitude and a phase transition all mean going back to update it.
- The register focuses on recording people and their assessments and classifications; the plan focuses on strategies and actions. Do not needlessly write responses into the register, and do not needlessly copy the register into the plan; the engagement plan should center on strategies and actions and can refer to the relevant register information as needed.
- When you foresee that a key person will object, reach out proactively before the meeting and hear his views. Sending only a written notice, only logging a risk or only drawing the assessment matrix does not actually engage him.
- Putting all your effort on one high-power person neglects other important people. Engagement must cover all important parties, with effort allocated by priority.
- Giving in to every demand of a high-power person is not engagement and only brings scope creep.
Key takeaways
- Plan Stakeholder Engagement develops strategies for engaging stakeholders based on their needs, expectations and impact. Its formal output is project management plan updates, that is, creating or updating the stakeholder engagement plan.
- One strategy per person: use root cause analysis to find out why someone resists, then choose the strategy.
- Tools: assessment matrix, prioritization/ranking, assumption and constraint analysis, mind mapping, benchmarking.
- The plan contains current and desired engagement levels, the scope and impact of changes, and relationships among stakeholders; it may contain sensitive information (common exam practice), so limit its circulation according to the information's sensitivity and organizational requirements.
- When you foresee opposition, communicate proactively before the meeting. When a new key person appears, assess him, then update the plan and set a strategy.
Lesson 2
The Stakeholder Engagement Assessment Matrix: Five Engagement Levels and the C–D Gap
Lesson overview
How do you know what someone's attitude toward the project is now, and what you want it to become? The answer is the stakeholder engagement assessment matrix. It is the tool most often tested in Plan Stakeholder Engagement, and it is also the yardstick you compare against when monitoring stakeholder engagement. This lesson covers the five engagement levels, how to mark C and D, how to use the gap, and the difference between “supportive” and “leading.” The previous lesson covered the plan as a whole; the next covers how the plan is put into practice. ECO: People domain, Task 4 (Engage stakeholders).
The five engagement levels
A stakeholder engagement assessment matrix is “a matrix that compares current and desired stakeholder engagement levels.” The engagement level can be classified as follows:
| Level | Meaning |
|---|---|
| Unaware | The stakeholder is unaware of the project and its potential impacts. |
| Resistant | The stakeholder is aware of the project and potential impacts but resistant to any changes that may occur as a result of the work or outcomes of the project. These stakeholders will be unsupportive of the work or outcomes of the project. |
| Neutral | The stakeholder is aware of the project but neither supportive nor unsupportive. |
| Supportive | The stakeholder is aware of the project and its potential impacts and supportive of the work and its outcomes. |
| Leading | The stakeholder is aware of the project and its potential impacts and actively engaged in ensuring that the project is a success. |
Think of the five levels as a ladder from “has never heard of it” to “actively pushing it forward.” What an unaware stakeholder lacks is information. With a resistant stakeholder, first analyze the reasons for the resistance, then communicate, negotiate or adjust to address his concerns. A neutral stakeholder is neither supportive nor unsupportive; a supportive one backs the work and its outcomes but is not necessarily actively engaged in ensuring success; a leading stakeholder is already on the project's side and putting in effort.
How to use it: C, D and the gap
The rows of the matrix are the stakeholders and the columns are the five levels. Mark the current level with C, and mark with D the desired level that the project team has assessed as essential to ensure project success. The gap between current and desired sets the level of communication needed to engage that person effectively, and closing the gap is an essential element of monitoring stakeholder engagement. When C and D fall in the same cell (show both markers in that cell), no further increase is needed.
Three points to keep in mind when using it. First, D is not necessarily “Leading”: for an approver who only has to sign off on schedule, “Supportive” is enough, and demanding “Leading” of him would be a waste. Second, judge the size of the gap together with power and interest: a low-power person two levels short is not necessarily more urgent than a high-power person one level short. Third, the assessment needs a basis: reach it through conversations, observation of attendance and feedback, not impressions.
Example: reading an assessment matrix
An online course-registration system project at a school has four stakeholders:
- Dean of academic affairs: C at Neutral, D at Supportive. One level apart. He needs to see how the system will reduce complaints during registration peaks.
- Student union president: C at Unaware, D at Supportive. Three levels apart (Resistant and Neutral lie between). What is missing is information, so arrange a system demonstration first.
- Grade-level head representative: C at Resistant, D at Neutral. One level apart. First find out the reason for the resistance, which is worry that teachers' control over timetabling will be weakened, and then discuss solutions.
- Principal: C and D both at Leading, so no gap; keep the current reporting rhythm.
The grade-level head representative's D is set only at “Neutral” because his power is limited and project success only requires that he not stand in the way; pushing him to “Leading” would go beyond what is necessary.
How the matrix works together with the grid
The two tools answer different questions and are often used together, in sequence. The power/interest grid answers “how closely should this person be managed?” and the assessment matrix answers “where is he now and where does he need to be?” Common exam practice: use the grid first to set priorities, then mark C and D for each key person. For example, if someone in the grid's “manage closely” quadrant already has C and D in the same cell, the current communication is enough and you simply maintain it. If someone in the “keep satisfied” quadrant has C at Resistant, close the gap first even though his interest is low, because he has the power to block the project. Finally, write the gaps and the matching actions into the engagement plan and look back at them during monitoring.
Telling supportive and leading apart
These two levels are the easiest to confuse. A supportive stakeholder understands and supports the project's work and its outcomes; a leading stakeholder goes further and is actively engaged in ensuring that the project is a success (committing resources, taking on responsibility). Engagement levels are not preset by role: a sponsor typically needs a higher desired level of engagement, but his current and desired levels should still be assessed separately in the context of the project and cannot be decided from his position alone. Common exam practice: if a question says an executive is highly concerned about success and commits to providing all the necessary resources, classify him as Leading, not Supportive. Words such as “commits resources,” “personally pushes” and “ensures success” point toward Leading.
Worked examples
Example 1 When someone resists, what to do first
A project manager is assigned to manage a portal website redesign project. Before execution begins, the project manager learns that one stakeholder does not support the project and is unwilling to attend the necessary project meetings, and is likely to resist project activities during execution. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
Before execution of a portal website redesign project, the project manager learns that a stakeholder does not support the project, is unwilling to attend the necessary meetings and is likely to resist during execution. You must decide what to do first.
The stem asks what to do “first.” When a stakeholder appears resistant, first speak with the stakeholder directly to understand the concerns and cause of the resistance. Then document the confirmed information in the stakeholder register, assess the current and desired engagement levels in the stakeholder engagement assessment matrix, and choose targeted engagement actions. Escalating or trying to persuade unilaterally first is premature. The answer is A.
Why the other options are wrong
- B. Ordinary problems do not go to the sponsor first. Moreover, the reported resistance has not yet been confirmed directly and its cause is unknown, so escalating is premature, and going to the sponsor is not the project manager's first move.
- C. The business case explains whether the project is worth doing, whereas his problem is attitude and participation. Just reading it will not reveal his reasons and will not resolve the resistance.
- D. Notifying senior management and asking them not to be influenced is avoidance rather than handling the issue, and it takes no action to engage this stakeholder.
Key takeaway When information indicates resistance, communicate directly with the stakeholder first to understand the concerns, then document the assessment and refine the engagement strategy.
Variation If the question asked what to do “after the assessment,” the answer would be to develop a targeted communication strategy, for example, first learn the root cause of the resistance and then arrange a meeting with him.
Something wrong with this question?
Example 2 How to tell whether engagement is at the right level
A project manager is running a multinational project with more than 120 stakeholders. The project manager's concern is whether stakeholder engagement is appropriate, and at the level needed, for successful delivery. What should the project manager do?
Show answer and explanation
Correct answer: B
A multinational project has more than 120 stakeholders, and the project manager wants to know whether the engagement needed for successful delivery is appropriate and at the right level. You must decide what the project manager should do.
Judging whether engagement is “appropriate and at the right level” is exactly what the stakeholder engagement assessment matrix is for: it sets each stakeholder's current level next to the level the project needs, so the gaps are plain to see and you can tell which people need more communication. With this many people, a matrix is more efficient than talking to each one. The answer is B.
Why the other options are wrong
- A. The stem presents no specific problem, so there is nothing to “work out solutions” for, and one-on-one conversations with more than 120 people are impractical. This does not answer the question.
- C. The issue log records issues that have already occurred and has nothing to do with assessing engagement levels. Going through every entry would waste effort.
- D. Assumption and constraint analysis is used when planning engagement to tailor strategies, whereas this question is about whether the current state is adequate. That calls for a comparison, not an analysis of assumptions.
Key takeaway To find out whether engagement levels are sufficient, use the stakeholder engagement assessment matrix to compare current and desired levels.
Variation If “one key person's engagement level is below what is needed, for unknown reasons,” you would first do a root cause analysis and then develop a strategy to raise the level.
Something wrong with this question?
Common traps
Common trap
- C is the current level and D is the desired level. Do not reverse them.
- “Resistant” and “Unaware” are different. A resistant stakeholder knows about the project and opposes it; an unaware stakeholder knows nothing about the project or its impacts, first needs the necessary information, and once informed can be judged on his attitude to see whether further engagement is needed.
- The desired level is not necessarily “Leading.” The team sets it according to what project success requires, and it differs from person to person.
- The matrix and the strategies that go with it are generally used to develop and update the engagement plan, and where they are recorded can be tailored to the project. PMBOK 8 defines the stakeholder register as a project document that includes assessment and classification, so the register may also hold the relevant assessment information.
- The matrix compares engagement levels, not power and interest. Use the grid for classification and the matrix for engagement; do not mix them up.
Key takeaways
- The stakeholder engagement assessment matrix compares each person's current level (C) with the desired level (D).
- The five levels: unaware, resistant, neutral, supportive, leading.
- The gap determines the communication effort; C and D in the same cell means no increase is needed.
- Supportive is agreement; leading is full commitment to ensuring success. A sponsor typically needs a higher desired level of engagement, but whether he is Leading has to be assessed in context and cannot be decided from his position alone.
- To find out whether engagement is at the right level, compare with the assessment matrix. When you find resistance, first analyze the reason for it, record the gap between current and desired engagement in the matrix, and then develop targeted engagement measures.
Lesson 3
Managing Stakeholder Engagement: Follow the Plan, and Use Interpersonal Skills for Concerns and Conflict
Lesson overview
Once the plan is written, it has to be carried out in the executing focus area. That is Manage Stakeholder Engagement. This topic is tested often because it is the closest to everyday work: someone is worried, two people are in conflict, someone does not show up to meetings, so what does the project manager do? This lesson covers what the process does and which communication and interpersonal skills it uses, especially the five conflict resolution techniques and the principles that go with them. The previous lesson covered the assessment matrix; the next covers the thread of “expectations.”
What Manage Stakeholder Engagement does
“Manage Stakeholder Engagement is the process of communicating and working with stakeholders, which includes collaborating with sponsors to meet their needs and expectations, addressing any issues, and fostering appropriate sponsor involvement. The key benefit of this process is that it allows the project manager to increase support and minimize resistance from stakeholders. This process is performed throughout the project.”
Put plainly, it means doing what the engagement plan says: meeting the people who should be met, reporting to those who should be reported to, and explaining what should be explained. Planning decides “how to engage,” managing is “going and engaging,” and monitoring is “seeing how it worked.” The three processes easily serve as distractors for one another in questions; the way to tell them apart is in the last lesson of this chapter.
PMBOK 8 describes managing engagement as communicating and working with stakeholders, meeting needs and expectations, addressing issues and fostering appropriate involvement, with the key benefit of winning support and reducing resistance. Below, everyday activities are grouped into four kinds (a memory aid). Gain support: get stakeholders to buy in and take part. Manage expectations: align their expectations with what the project can actually do. Address concerns: resolve concerns before they turn into problems and resistance. Reach agreement: build consensus when views differ. The last three all depend on communication skills.
Inputs, tools and techniques, outputs
- Inputs: communications management plan, risk management plan, stakeholder engagement plan, change management plan; change log, issue log, lessons learned register, stakeholder register, risk register, status reports, project schedule; plus enterprise environmental factors, organizational process assets and other inputs tailored to the project. The engagement plan provides the specific strategies for engaging individuals or groups, and the register records information about each person.
- Tools and techniques: expert judgment; feedback (a communication skill); conflict management, cultural awareness, negotiation, observation/conversation and political awareness (interpersonal and team skills); ground rules; meetings.
- Outputs: change requests; project management plan updates (communications management plan, stakeholder engagement plan); project document updates (change log, issue log, lessons learned register, stakeholder register).
The results of engagement may mean that project scope or product scope needs to change, which is why change requests appear among the outputs. They should be reviewed and handled through the Assess and Implement Changes process and cannot be made directly; if they affect the project baselines, integrated change control actions should also be applied.
Interpersonal skills: conflict management and negotiation
PMBOK 8 stresses that conflict is inevitable. “Sources of conflict include scarce resources, scheduling priorities, and personal work styles.” The principles for handling it: “Conflict should be addressed early and usually in private, using a direct, collaborative approach.” Team members are initially responsible for resolving a conflict that becomes a negative factor, and if it escalates the project manager should help facilitate a satisfactory resolution; only “if disruptive conflict continues, formal procedures may be used, including disciplinary actions.”
Which approach to use depends on the factors PMBOK 8 lists: the importance and intensity of the conflict, time pressure for resolving it, the relative power of the people involved, the importance of maintaining a good relationship, and motivation to resolve the conflict on a long-term or short-term basis. There are “five general techniques for resolving conflict”:
| Technique | What it does | Result |
|---|---|---|
| Withdraw/avoid | Retreating from an actual or potential conflict situation; postponing the issue to be better prepared or to be resolved by others | The problem remains |
| Smooth/accommodate | Emphasizing areas of agreement rather than areas of difference; conceding one's position to the needs of others to maintain harmony and relationships | The relationship is kept; the problem is not necessarily solved |
| Compromise/reconcile | Searching for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict | Temporary or partial resolution; occasionally lose-lose |
| Force/direct | Pushing one's viewpoint at the expense of others; offering only win-lose solutions, usually enforced through a power position to resolve an emergency | Win-lose |
| Collaborate/problem-solve | Incorporating multiple viewpoints and insights from differing perspectives; requires a cooperative attitude and open dialogue | Can be win-win; typically leads to consensus and commitment |
When a question asks for “the most appropriate approach,” the answer is usually collaborate/problem-solve (common exam practice): bring both sides together, with the project manager acting as facilitator who drives the dialogue and helps reach a decision. Forcing is usually reserved for emergencies that call for quick loss-limiting or quick decisions where the relationship is secondary; withdrawing and smoothing generally only postpone or cool things down and do not remove the underlying disagreement, and they fit low-importance issues or cases where preserving the relationship matters most.
Negotiation is “a discussion aimed at reaching an agreement”; it is used to achieve support or agreement that supports the work of the project or its outcomes and to resolve conflicts within the team or with other stakeholders. Observation/conversation provides a direct way of viewing individuals in their environment to see how they perform their jobs or tasks and carry out processes, and is particularly helpful when the people who use the product have difficulty or are reluctant to articulate their requirements. Political awareness concerns the recognition of formal and informal power relationships and the willingness to operate within these structures. Cultural awareness is an understanding of the differences among individuals, groups and organizations and adapting the project's communication strategy in the context of these differences.
Ground rules and meetings
“Ground rules are expectations regarding acceptable behavior by project team members. Defined in the team charter, ground rules set the expected behavior for project team members and other stakeholders with regard to stakeholder engagement.” Examples are being punctual for meetings, taking turns to speak, and how to escalate differences of opinion. With rules in place, a lot of friction does not have to be resolved one case at a time by the project manager. Meetings are where the project manager communicates directly with stakeholders and makes decisions.
PMBOK 8 pays special attention to the sponsor: “Sponsors are essential stakeholders who hold decision-making authority; secure human, material, or virtual resources; and ensure alignment with organizational strategy and project objectives.” Sponsors are typically involved in initiating the project and defining the project objectives and business case, approving the project charter and any changes to it, assigning and empowering the project manager, initiating a steering committee and being a member of it, approving the project management plan and any changes to it, ensuring the long-term benefits realization of project deliverables, proposing project termination, and authorizing project completion. An active sponsor is a critical success factor in achieving positive outcomes. The sponsor is often a senior executive, which calls for specific effort in understanding his needs and the ways of communication that fit him better.
Example: two directors fight over a feature
On a logistics company's dispatch platform project, the marketing director wants to add “customer self-service order changes,” while the operations director worries it will disrupt existing dispatching. The two argue their positions at the weekly meeting. The project manager neither takes a side on the spot nor escalates at once. After the meeting the project manager brings the two together and has each explain their concern first: marketing wants to shorten customer waiting time, and operations fears that order changes will upset routes that are already scheduled. The two agree on a solution: order changes will be open only for orders not yet dispatched. The project manager records this in the decision log and submits it for review as a change request. Three days later, both directors say at the change meeting that they accept it.
Worked examples
Example 1 A department manager objects out of worry: the next step
A chain logistics company has used its warehouse management system for ten years and decides to upgrade it, appointing an experienced project manager to lead the project. During the first round of identifying stakeholders, the project manager finds that the warehouse manager and the dispatch manager believe the current system is good enough and worry that the upgrade will slow their teams' work. What should the project manager do next?
Show answer and explanation
Correct answer: A
A warehouse management system upgrade project is at the stage of identifying stakeholders. The warehouse manager and the dispatch manager think the current system is good enough and worry that the upgrade will slow operations. You must decide the next step.
The two managers' opposition comes from worry about work efficiency. This is a concern to be addressed, not a formal change requirement. One of the activities in Manage Stakeholder Engagement is addressing concerns and managing expectations, which uses communication and interpersonal skills (listening, influencing, negotiation, conflict management). First hear what worries them, then explain how the upgrade will protect operating efficiency, and win their support. The answer is A.
Why the other options are wrong
- B. Escalating before communicating directly with the people involved tends to sharpen the conflict. Stakeholders' concerns should first be handled by the project manager through communication.
- C. Monitoring evaluates how effective existing engagement efforts are. No engagement action has been taken yet, so there is nothing to monitor.
- D. The two managers have expressed worries, not asked for a change to the scope. Going through change control does not answer why they do not support the project.
Key takeaway When stakeholders withhold support out of worry, first use interpersonal skills to address their concerns; do not escalate, run change procedures or only monitor.
Variation If the two managers made it explicit that “we will agree only if an interface function is added,” that is a specific scope request, which should be assessed and submitted as a change request through integrated change control.
Something wrong with this question?
Example 2 Two key people hold opposite views
A city bus travel app project is in the executing phase. Two key stakeholders disagree about the project scope: the marketing director insists on adding a coupon feature, which would expand the scope, while the operations director wants to keep the current arrangement unchanged. Both have explained their positions and reasons to the project manager, and the positions are mutually exclusive. What is the most appropriate next step for the project manager?
Show answer and explanation
Correct answer: B
A bus travel app project is in the executing phase. The marketing director insists on adding a coupon feature, and the operations director wants to keep the current arrangement. Both have explained their positions to the project manager, and the positions are mutually exclusive. You must decide the most appropriate next step.
Conflict between stakeholders should be handled early, directly and collaboratively. The two positions and reasons are already clear, so the project manager brings the two together in a meeting, acts as facilitator, and drives the dialogue toward agreement. This is collaborate/problem-solve: it incorporates both viewpoints and typically leads to consensus and commitment. Adding the coupon feature is a scope change, so once they agree it must go through the change control procedure rather than being settled outright in the meeting. Both are key stakeholders, which makes face-to-face facilitation all the more necessary. The answer is B.
Why the other options are wrong
- A. Escalation is a last resort; the project manager should first take the initiative to mediate. Escalating at the first sign of disagreement makes it look as if the project manager cannot resolve problems.
- C. Both positions are already clear, so separate conversations produce no new information and do not build consensus. Deciding the scope on his own bypasses change control and amounts to imposing a decision, which invites hostility.
- D. Leaving the two to arrange it themselves removes the project manager from the process. The discussion can drift or stall, and it does not show the project manager acting as a facilitator.
Key takeaway When stakeholders' views conflict, the project manager steps in and brings both sides together to solve the problem collaboratively, rather than hurrying to escalate or standing aside.
Variation If their disagreement involved cross-department resources and the project manager has no authority to decide, you would ask the sponsor to set priorities only after facilitation fails.
Something wrong with this question?
Common traps
Common trap
- Managing engagement is executing the plan: communicate where communication is due and report where reporting is due. Systematically adjusting strategy after assessing results belongs to Monitor Stakeholder Engagement; if handling an issue during execution requires changes to the plan, you can raise a change request and update the relevant plans, but first find out the cause.
- When a stakeholder objects out of worry, first handle his concerns with interpersonal skills; do not escalate first, do not go to change control first, and do not monitor first.
- When there is a disagreement with a stakeholder, communicate directly first, find the cause and discuss options together. Do not escalate to the sponsor first, and do not bypass the person concerned to consult the team.
- Conflict should be handled early and usually in private. Calling someone out in a public meeting may make him dig in harder, so conflict is generally handled in private.
- PMBOK 8 lists withdraw/avoid, smooth/accommodate, compromise/reconcile, force/direct and collaborate/problem-solve as conflict resolution techniques, each with its place: withdrawing and smoothing generally cannot remove the underlying disagreement, forcing mainly fits emergencies, and collaborate/problem-solve generally works best for long-term consensus (common exam practice: when asked for the “most appropriate,” think collaboration first).
Key takeaways
- Manage Stakeholder Engagement: communicate and collaborate according to the engagement plan, meet needs and expectations, address issues and foster appropriate involvement.
- Four kinds of activity (a memory aid): gain support, manage expectations, address concerns, reach agreement.
- Tools include conflict management, negotiation, observation/conversation, political awareness, cultural awareness, ground rules and meetings; outputs include change requests and updates to plans and documents.
- Conflict: early, private, direct, collaborative; of the five techniques, collaborate/problem-solve is generally best.
- The sponsor is a key stakeholder, and an active sponsor is a critical success factor.
Lesson 4
Aligning and Managing Stakeholder Expectations: Dissatisfaction, Conflict and Out-of-Scope Requests
Lesson overview
Questions on this topic map to two tasks in the ECO People domain: Task 5, Align stakeholder expectations, and Task 6, Manage stakeholder expectations. The scenarios vary endlessly: the client is unhappy with how the project is going, two directors' demands clash, the sponsor suddenly wants things faster, someone agrees to something and then does not cooperate. But the way to solve them is one and the same. This lesson sets out that approach: clarify the expectations first, then align them, and go through change control when needed. The previous lesson covered the tools for managing engagement; the next covers monitoring.
What each of the two tasks covers
Task 5, “Align stakeholder expectations,” lists four items in the ECO: categorize stakeholders; identify stakeholder expectations; facilitate discussions to align expectations; and organize and act on mentoring opportunities. The idea is to classify first, then find out what each person wants, then help stakeholders reconcile differing expectations through discussion, and where needed organize and use mentoring opportunities to help stakeholders understand more and take part more capably.
Task 6, “Manage stakeholder expectations,” has three items as well: identify the expectations of internal and external customers; continually ensure that outcomes remain aligned with those expectations; and monitor customer satisfaction or expectations and respond as needed. “Customer” here is meant broadly, covering both the external customer who pays and the internal department that uses the results.
PMBOK 8 puts this under the key concept of stakeholder satisfaction: “Stakeholder satisfaction should be prioritized and integrated into the project objectives. The key to driving stakeholder satisfaction is maintaining a focus on continuous communication with all stakeholders, including customers, end users, managers, executives, and team members, to understand their needs and expectations, address issues as they occur, manage conflicting interests, and foster appropriate stakeholder engagement in project decisions and activities.”
A general order of handling
For questions where “expectations do not line up,” think through the order below, which is common exam practice.
- Clarify first; do not guess. If the client says he is dissatisfied, or several stakeholders say they are “uneasy,” ask them face to face what it actually is. Do not hold a team meeting to speculate, and do not change the plan first.
- Then check the basis. Compare against the engagement plan, scope statement, baselines and agreements to see whether the other party's expectations go beyond what has been approved.
- Then align. Resolve issues that information can settle by sharing data and facts. Where views differ, bring the stakeholders together to negotiate, and where necessary have the sponsor set the priorities.
- If scope has to change, go through change. A reasonable and worthwhile new request that requires changing a controlled document or baseline should, on predictive projects, go in as a change request and be assessed and approved before the plan is changed; on adaptive projects it is usually added to the backlog for impact analysis and prioritization. An unreasonable one gets an explanation of the project boundaries, without over-committing.
- Finally, record and update. Record the outcome: issues and action items go into the issue log; change requests and their status go into the change log; update the stakeholder engagement plan only when the engagement strategy changes, and the stakeholder register only when stakeholder information or assessments change, so that these two documents are not mechanically changed after every communication.
How to judge some common scenarios
Dissatisfied, but the work matches the plan exactly. There is no deviation in schedule, cost or quality, and the client is still unhappy. The problem may be a mismatch between his expectations and the plan itself, or something else. Variance analysis will not find it; first meet him to learn his expectations and concerns.
Success criteria or requirements conflict. Two directors make mutually exclusive requests. Go back to the engagement plan and the register first, look at the two people's power, interest and expectations, and then coordinate. Only if both are high-power and still cannot agree, or the issue involves cross-department priorities, work it out together with the sponsor.
Out-of-scope requests. An external partner raises additional conditions unrelated to the project, and the project manager is unwilling or unable to negotiate directly; the project manager still must not agree privately. First clarify the conditions with the partner who made the request, and check scope, agreements and authority. If a change is involved, submit a change request. If it exceeds the project manager's authority or meets the escalation criteria, escalate to the sponsor or the appropriate authorized body so that someone with authority decides, and record how it was handled in the issue log. A new request that requires changing approved documents, deliverables or baselines should go in as a change request; work already within the approved scope proceeds under the current plan.
Support has fallen, or someone refuses to take part. An expert is absent from meetings, or a director gives verbal support but will not release people. First communicate directly with the person and use the engagement plan as context to understand why support has fallen or participation has stopped; then respond to that cause. If an agreement or resource arrangement requires participation, use it to coordinate that participation. If the engagement strategy is not working, adjust the strategy.
The schedule is behind, but the client thinks it is almost done. Do not wait until go-live to say so. Report schedule problems promptly, explain the causes, the current and likely impacts and the proposed corrective actions, and state the downstream risks this creates, using data to align understanding.
Strained relations and repeated misunderstandings. Find out where the misunderstanding comes from and help the parties reach a common understanding. If the business side and the technical side cannot get on the same page, the project manager has to be the “translator,” saying the same thing in terms each side understands.
Earning trust and exerting influence
ECO Task 4 includes an item, “build trust and influence stakeholders to accomplish project objectives.” Trust comes from keeping commitments: if you promise a status report every week, do not cancel it several times in a row; do not overstate what you can do, and if something is beyond your ability, say so plainly instead of brushing it off. Influence comes from understanding the other person's interests: persuade with outcomes that matter to him, not by pulling rank. Observing, listening and asking questions will uncover the real problem better than explaining again and again.
Example: handling one “not satisfied”
In the sixth month of a factory equipment alert system project, the client's production supervisor says at the status meeting, “It's not smooth to use.” The project manager checks and confirms that what has been delivered conforms to the scope baseline, the schedule conforms to the schedule baseline, and the quality results meet the requirements. Instead of taking the topic back to the team, the project manager asks the supervisor the next day to come to the shop floor and demonstrate his daily operation. Twenty minutes of watching reveals that the supervisor is used to checking alerts on his phone, while the system was built only for computers. That need had never been written into the scope. The project manager formally submits a change request for “mobile viewing,” and after assessment and approval by the authorized body designated in the change management plan it is scheduled for phase two. The project manager records the outcome in the change log and tells the supervisor the conclusion and the date in person. The supervisor is satisfied with the outcome because he can see the path to a solution.
Worked examples
Example 1 An external merchant resists: what to do
A sports arena project is still in early planning, and its construction plan has not yet been approved; construction is expected to begin once approval is obtained. Merchants around the site worry that noise and dust during construction will hurt their business, and they feel resistant to the project. What should the project manager do?
Show answer and explanation
Correct answer: C
Construction of a sports arena is about to begin. Nearby merchants worry that noise and dust will hurt their business and resist the project. You must decide what the project manager should do.
When an external stakeholder has concerns, communicate early to learn their needs and expectations. Early in a project the cost of adjusting the plan is small; modestly optimizing work hours and dust control measures can often resolve the resistance and also win cooperation for the construction to come. Because the project is still in early planning and the construction plan has not yet been approved, there is still room to assess and optimize the plan before approval. For resistance from external stakeholders, the principle is to communicate early and adjust early, not to wait until the dispute becomes public and then repair it. The answer is C.
Why the other options are wrong
- A. Ignoring the resistance and waiting until it escalates into action costs much more, and it goes against the requirement to manage stakeholder expectations.
- B. The merchants are stakeholders the project has to manage. Passing the coordination to the owner means not taking on the responsibility for managing their engagement.
- D. Recommending cancellation because of concerns is an overreaction and not the project manager's natural first response.
Key takeaway When stakeholders resist, listen early and adjust early; that costs the least.
Variation If the merchants have already blocked the gate to stop construction, first steady the scene and meet with their representatives before resuming negotiation. The later the timing, the fewer the options.
Something wrong with this question?
Example 2 All the work meets the standard but the client is still dissatisfied: what to do first
At the sixth-month status meeting of a production line customization project, the client representative says bluntly that he is very dissatisfied with the project's performance. Right after the meeting, the project manager goes back and checks: the charter and the project management plan are approved, all activities are proceeding strictly as planned, there are no schedule or cost variances, and all quality tests have passed. What should the project manager do FIRST?
Show answer and explanation
Correct answer: C
In a production line customization project, schedule, cost and quality all match the plan, yet at the sixth-month status meeting the client representative says bluntly he is very dissatisfied. You must decide what to do first.
The stem asks what to do “first.” The work matches the plan and quality is up to standard, so the problem may lie in a mismatch between the client's expectations and the plan itself, not in execution variances. The only reliable way to find out what the client is unhappy about is to ask him in person, and then decide whether an adjustment is needed. Ask first, then act. This is also the basic approach to managing stakeholder expectations: rely on direct communication with the person, not on guesswork. The answer is C.
Why the other options are wrong
- A. What the client thinks can only be learned from the client. An internal team discussion is speculation and yields no real information.
- B. The stem already says there is no variance between actual and planned, so variance analysis cannot uncover why the client is dissatisfied.
- D. Revising the plan without knowing why the client is dissatisfied has no basis, would likely change it in the wrong direction and would cause scope creep.
Key takeaway When work follows the plan and quality is up to standard but the client is still unhappy, first meet him to understand his expectations, and only then talk about adjustments.
Variation If variance analysis showed the schedule four weeks behind and the client was unhappy about that, you would first investigate the cause of the variance and set corrective actions, while keeping the client informed.
Something wrong with this question?
Common traps
Common trap
- When there is dissatisfaction, ask first. Do not speculate in the team first, do not run variance analysis first, and above all do not change the plan first.
- When stakeholders have concerns, communicate early, because the cost of adjusting early is lowest. Do not wait until it escalates into action, do not pass it to the owner or the sponsor, and certainly do not recommend canceling the project.
- A reasonable new request goes through change. An unreasonable one gets an explanation of the boundaries; do not agree to it for the sake of the relationship.
- When stakeholders conflict with one another, the project manager coordinates first. Only when cross-department priorities cannot be settled or the matter exceeds his authority is the sponsor asked to decide.
- Expectation management is continuous. Check against expectations after every communication and every change.
Key takeaways
- Task 5, align expectations: categorize, define expectations, facilitate discussion to reach agreement. Task 6, manage expectations: identify expectations, continually align outcomes, monitor satisfaction.
- The order of handling: clarify first, then check the basis, then align, go through change if scope must change, and finally record and update.
- If the client is dissatisfied but the work matches the plan, first meet him to clarify his expectations.
- Do not agree privately to an out-of-scope request: clarify it first and check scope and authority; if a change is needed, go through a change request; escalate to the sponsor, and record it, only when it exceeds the project manager's authority or meets the escalation criteria. A new request that requires changing an approved document, deliverable or baseline is handled under the applicable change mechanism; work already within the approved scope proceeds under the current plan.
- Report schedule slippage ahead of time and align with data; earn trust by keeping commitments.
Lesson 5
Monitoring Stakeholder Engagement: Assess Results, Adjust Strategy and Plan
Lesson overview
The engagement work has been done, so how is it working? Monitor Stakeholder Engagement is the project's regular check-up: it watches whether stakeholders' support has changed and adjusts the strategy when it finds a deviation. In the exam, scenario questions for this lesson are almost all of the type “someone cannot be reached, is not taking part or has lost support,” asking what the project manager should do. The direction of the answer is consistent: go back to the engagement plan, find the cause, and change the strategy. This lesson covers how the process works and gives a way to tell planning, managing and monitoring apart. The previous lesson covered expectations; this is the last lesson of the chapter.
What Monitor Stakeholder Engagement does
“The Monitor Stakeholder Engagement process involves assessing the effectiveness of stakeholder engagement efforts, identifying necessary adjustments to improve relationships, and refining strategies or plans to better meet stakeholder participation needs. The key benefit of this process is that it maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes. This process is performed throughout the project.”
It follows Manage Stakeholder Engagement: managing is “doing it,” and monitoring is “seeing how well it was done.” Monitoring focuses on whether the engagement work is effective and whether a gap remains between each stakeholder's current and desired engagement. If there is a gap or circumstances change, the strategy may need adjusting; if actual engagement does not match the plan, review and revise the engagement plan; if everything is as expected, carry on. Monitoring cannot rely on the register alone: also watch work performance data, change activity and the outputs of other processes, and look at engagement within the project as a whole.
Inputs, techniques and outputs
| Item | Content |
|---|---|
| Inputs | Resource management plan, communications management plan, stakeholder engagement plan; issue log, lessons learned register, project communications, risk register, stakeholder register; work performance data; enterprise environmental factors, organizational process assets |
| Data analysis | Alternative analysis, root cause analysis, stakeholder analysis |
| Decision-making | Multicriteria decision analysis, voting |
| Data representation | Stakeholder engagement assessment matrix |
| Communication skills | Feedback, presentations |
| Meetings | Used to discuss and assess stakeholder engagement |
| Interpersonal and team skills | Active listening, cultural awareness, leadership, networking, political awareness |
| Outputs | Work performance information; change requests; project management plan updates (resource management plan, communications management plan, stakeholder engagement plan); project document updates (issue log, lessons learned register, risk register, stakeholder register) |
When monitoring, use the stakeholder engagement assessment matrix to compare current and desired levels again, and if a gap remains, act. Where needed, produce change requests, which can include the corrective and preventive actions needed to improve current engagement levels. The plans that need adjusting are chiefly the stakeholder engagement plan and the communications management plan.
How to tell whether engagement is working
PMBOK 8 gives several ways to check. Collect feedback from stakeholders through interviews or surveys, perform periodic alignment with stakeholders regarding project objectives, and check indicators such as the Net Promoter Score (NPS). Review the project's issue log, risk register and stakeholder register to confirm that risk responses are identified and successfully implemented. Review the number of change requests to requirements and collect feedback on increments, to see whether stakeholders agree with the project objectives.
Counting attendance at meetings is not enough, because showing up is not the same as being committed. Also record changes in each person's attitude, whether feedback gets followed up, and whether promised actions were done. In practice, adaptive projects often collect comments after every iteration review, and predictive projects often rely on monthly reports and phase reviews (common exam practice).
What to do once a deviation is found
Common exam practice is to handle it in this order. First check the engagement plan to see what the original strategy and the current and desired levels were. Then use root cause analysis to find why things changed: were his concerns never addressed, is the way of communicating wrong, or has his own situation changed? Then determine what adjustment is needed. In a predictive environment, if it affects a controlled plan, assess the impact, submit a change request under the change management plan, obtain authorization, and only then update the plan, notify stakeholders and implement it. In an adaptive environment, assess and prioritize the change through backlog management and the established decision authority. Finally, update the register if stakeholder information or assessments changed, and keep monitoring.
Example: the finance department keeps missing meetings
On a home appliance maker's new product planning project, in the third week of the planning phase the finance department's representative has missed four meetings in a row. The project manager checks the engagement plan: the finance manager is currently “Neutral,” the desired level is “Supportive,” and the strategy is a monthly briefing. A monthly briefing is clearly not enough. The project manager asks a colleague close to the finance manager and learns that finance is worried that new product pricing will drag down the gross margin and that nobody has explained the cost basis to them. So the project manager proposes a new strategy: book half an hour every two weeks and go over the numbers with a cost estimate sheet. If the engagement plan and communications management plan are under formal change control, the project manager first assesses the impact and obtains the required approval under the change management plan, then updates the plans, notifies the relevant stakeholders and implements the strategy; finance's concerns go into the issue log and the stakeholder register; and if new requirements arise, a change request is raised, and the requirements document is updated after analysis and approval. Two weeks later, the finance representative appears at the review meeting.
Telling the three processes apart
| Process | Focus area | In one sentence | Signals in the question |
|---|---|---|---|
| Plan Stakeholder Engagement | Planning | Develop strategies and produce the engagement plan | “Develop,” “prepare,” “how to engage,” “first comparison of current and desired levels” |
| Manage Stakeholder Engagement | Executing | Communicate and collaborate per the plan, address concerns and conflict | “Someone is worried,” “disagreement arises,” “need to gain support” |
| Monitor Stakeholder Engagement | Monitoring and controlling | Check results, adjust strategy and plan | “Engagement dropping,” “cannot be reached,” “results unsatisfactory,” “compare current and desired levels again” (the assessment matrix is used in both planning and monitoring, so it is not a signal exclusive to planning) |
Worked examples
Example 1 A key person cannot be reached and gives no feedback
During the executing phase of an education cloud platform project, the project manager finds it hard to reach several key stakeholders and hard to get their feedback on the deliverables. What should the project manager do?
Show answer and explanation
Correct answer: B
During the executing phase of an education cloud platform project, several key stakeholders are hard to reach and it is hard to get their feedback on deliverables. You must decide what the project manager should do.
The stakeholder engagement plan sets out the strategies for engaging them. Being unreachable and giving no feedback is a signal of insufficient engagement, but the stem does not yet establish the cause. First analyze factors such as availability, concerns and communication methods, and then adjust the engagement strategy accordingly; if a controlled plan must be updated, follow the change management plan for the required approval. The answer is B.
Why the other options are wrong
- A. This problem lies within the project manager's responsibility, so there is no need to trouble the sponsor first. Having the sponsor step in is an ineffective escalation made before any adjustment of strategy.
- C. Sending a feedback form template only lowers the hurdle for filling it out; it does not identify why these stakeholders are hard to reach and provide no feedback.
- D. Passively waiting for them to make contact takes no step to adjust strategy for the lack of engagement. First analyze the cause and then revise the engagement plan.
Key takeaway When monitoring finds insufficient engagement, go back to the engagement plan and adjust the strategy.
Variation If these people are highly engaged but their feedback contradicts one another, turn to conflict management and bring them together to reconcile it.
Something wrong with this question?
Example 2 A department's representative never attends meetings
A home appliance company is planning a new product. During planning, a stakeholder from the finance department never attends project meetings and shows no interest in the product design. What should the project manager do?
Show answer and explanation
Correct answer: D
A home appliance company is planning a new product. During planning, a finance department stakeholder never attends project meetings and has no interest in the product design. You must decide what the project manager should do.
A finance department that never attends meetings and has no interest in the design is not necessarily a problem: appropriate engagement does not mean attending every meeting. The key is to confirm whether the department's needed level of engagement, information needs and the timing of its involvement have already been arranged in the engagement plan and communication strategy, so first review the engagement plan and the communication strategy; if actual engagement is below the needed level, then adjust the strategy. The stem says only that he does not attend and has no interest. It does not say that requirements were missed or that the register is wrong, so changing requirements or the register would not address the issue. The answer is D.
Why the other options are wrong
- A. The project manager can handle this kind of issue and need not escalate first, and escalating would not answer why the department is not taking part.
- B. The problem is non-participation, not the requirements or the register. Reviewing the requirements and updating the register does not touch the cause.
- C. Compelling attendance is only a means, and the department's needed level of engagement has not been confirmed first. Without reviewing the engagement plan and communication strategy, forcing attendance is neither how engagement is done nor likely to produce real participation.
Key takeaway When a stakeholder's engagement is low, first review the engagement plan and communication strategy to confirm the level of engagement he needs.
Variation If the department did attend meetings but its views were ignored, first go back and check whether its needs were collected and included, and then assess whether the engagement plan and the way of communicating need updating.
Something wrong with this question?
Common traps
Common trap
- When several people who used to support the project become neutral or even opposed, first check against the stakeholder engagement plan (use the assessment matrix to compare current and desired engagement, together with the strategies in the engagement plan and the assessment information in the register), analyze the deviation, and then adjust the strategy; do not change the register classifications first, and do not call an all-hands meeting to force agreement.
- If a department manager is merely “unsure” about the direction and scope of the plan and has not clearly asked for changes, do a stakeholder analysis first to understand the concerns; do not go straight to a change request.
- When a high-power, high-interest key stakeholder objects at a meeting, communicate with him immediately, find out what he wants and seek consensus; do not ignore him, do not remove him from the list, and do not ask the sponsor to step in right away.
- Insufficient engagement is a signal that needs checking: first confirm whether actual engagement is below the required level, then review the engagement plan and communication strategy, analyze the causes, and decide whether to adjust the strategy; having the sponsor step in or sending a feedback template does not touch the causes.
- Monitoring cannot look only at meeting attendance; look at attitudes and feedback.
Key takeaways
- Monitor Stakeholder Engagement: assess the effectiveness of engagement efforts, identify adjustments, and refine the strategy or plan, throughout the project.
- The core is using the stakeholder engagement assessment matrix to compare current and desired levels again.
- Outputs include work performance information, change requests (corrective and preventive actions), and updates to the engagement plan, communications management plan and others.
- When engagement drops or someone cannot be reached: go back to the engagement plan, find the cause, adjust the strategy.
- Telling the processes apart: develop strategy, execute the plan, check and adjust.
This chapter has 75 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.