Plan Communications Management

PMP · Stakeholders and Communication · 5 lessons · about 55 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Plan Communications Management is the process of planning how to communicate with the identified stakeholders, both inside and outside the team. It draws on the stakeholder register and the stakeholder engagement plan and produces the communications management plan, which is the starting point for Manage Communications and Monitor Communications later on. The exam questions here are highly formulaic, and the first job is to tell the question types apart. When a stakeholder's communication needs change, first analyze that stakeholder's information needs, then update the communications management plan through the applicable change mechanism. When agreed communication simply is not happening, first consult the plan and correct the execution. When a "new requirement" is really about scope or another area, handle it through that area and the Assess and Implement Changes process. Common exam practice: first classify the communication problem. If agreed communication was not carried out, consult the communications management plan and correct execution. If the stakeholder's needs are new or unclear, clarify them, then choose a suitable communication method and update the plan. A calculation also appears often: the number of communication channels, n(n-1)/2, which counts the potential one-to-one channels among n people. The n(n-1)/2 formula is common exam practice.

By the end of this chapter you should be able to do the following. State the inputs, tools and techniques, and outputs of Plan Communications Management, and explain what communication styles assessment, political awareness and cultural awareness are used for. Carry out a communication requirements analysis and calculate the number of communication channels correctly, telling "increases to" from "increases by". Distinguish communication technology, communication methods and communication skills, and tell push, pull and interactive communication apart. Use the basic, interactive and cross-cultural communication models to explain why "received" does not mean "understood". List what a communications management plan contains and know when to update it.

Lessons in this chapter

Chapter map

StepKey pointsIn one sentence
BasisStakeholder register, stakeholder engagement planFirst know whom you are communicating with, then plan how
AnalysisCommunication requirements analysis, channel countWhen needs change, analyze first; channels = n(n-1)/2
SelectionCommunication technology, methods, skillsTechnology is the tool or system; a method is a systematic way of transferring information (it can be classified by how information flows or by the main communication need); skills are the ability to provide, receive and elicit information
UnderstandingCommunication modelsAcknowledgment only means "received"; communication succeeds only when feedback matches the original message
ResultCommunications management planWhen communication goes wrong, check it first; when needs change, analyze them before updating it

Study tips and practice

  • Memorize the main line first: "when needs change, analyze the needs, then choose a suitable communication method and update the communications management plan, and then communicate according to the plan". Most scenario questions in this chapter are variations on it.
  • For channel calculations, build two habits: first count exactly who is included in n, and after calculating, check with the running-sum method.
  • For push, pull and interactive communication, decide by how the information flows, not by which software is used.
  • The next chapter, Manage and Monitor Communications, takes the plan into execution and checking.

Lesson 1

Plan Communications Management: Purpose, Inputs, Techniques and Outputs

Lesson video

Lesson overview

Who gets which project information, when, and by what means cannot be left to improvisation; it has to be worked out during planning. Plan Communications Management does exactly this, and its output is the communications management plan. This lesson covers the purpose of the process, how it connects to the stakeholder register and the stakeholder engagement plan, its inputs and its tools and techniques, and three frequently tested interpersonal skills: communication styles assessment, political awareness and cultural awareness. ECO: People domain, Task 4 (Engage stakeholders) and Task 8 (Plan and manage communication). The next four lessons cover communication requirements analysis, technology and methods, communication models and the contents of the plan.

What Plan Communications Management has to answer

PMBOK 8 defines the process this way: "The Plan Communications Management process involves the activities to plan how to communicate with the identified stakeholders, both inside and outside the team." It is not an isolated step. Communication planning overlaps with stakeholder identification, analysis, prioritization and engagement, and is closely aligned with the stakeholder engagement plan, which helps keep communication strategies consistent and aligned with stakeholder expectations.

Put in one sentence: based on "who the stakeholders are and what they want", decide "what information goes to whom, when and through which channel". Information can be classified from three angles: internal or external, sensitive or public, and general or detailed. Analyzing the stakeholders, their information needs and the categories of information provides the foundation for establishing the communication processes and plans for the project.

Among the seven processes of the Stakeholders Performance Domain, it comes after Identify Stakeholders and Plan Stakeholder Engagement and before Manage Communications and Monitor Communications. PMBOK 8 does not require the seven processes to run in a fixed order: Plan Stakeholder Engagement and Plan Communications Management sit side by side in the Planning Focus Area, and communication planning overlaps with stakeholder identification, analysis, prioritization and engagement, so the work can be iterative and overlapping. The usual line of thought is to identify the stakeholders and build the register first, then plan communication based on the stakeholders and their information needs. (Without a register you do not know whom to communicate with; without a plan, Manage Communications has nothing to follow.) Common exam practice: when a question asks "the register is built, what is the next step?", judge from the scenario whether information needs must be analyzed and the communications management plan developed or updated. The answer is usually this step, not sending a mass email or holding a meeting right away.

Inputs, tools and techniques, and outputs

ItemContent
InputsProject charter; resource management plan and stakeholder engagement plan; requirements documentation and stakeholder register; enterprise environmental factors; organizational process assets
Tools and techniquesExpert judgment; communication requirements analysis; communication technology; communication models; communication methods; interpersonal and team skills (communication styles assessment, political awareness, cultural awareness); data representation (stakeholder engagement assessment matrix); meetings
OutputsProject management plan updates (communications management plan, stakeholder engagement plan); project documents updates (project schedule, stakeholder register)
Figure 1 The cycle of the three communication processes

Two points matter when reading this table. First, two "subject documents" are among the inputs: the stakeholder register says who the stakeholders are, and the stakeholder engagement plan sets out the strategies and actions needed to promote their effective engagement; the communication plan has to serve that goal. Second, the project management plan updates in the outputs include the communications management plan itself, which becomes a component of the project management plan once planning is done. Communication arrangements may also reveal new stakeholders or new needs, so the register and the engagement plan may need updating too.

Three interpersonal skills: communication styles assessment, political awareness, cultural awareness

Communication styles assessment is "a technique used to assess communication styles and identify the preferred communication method, format, and content for planned communication activities. Often used with unsupportive stakeholders, this assessment may follow a stakeholder engagement assessment to identify gaps in stakeholder engagement that require additional tailored communication activities and artifacts."

Political awareness is recognizing, and being willing to work within, formal and informal power relationships; it helps the project manager plan communications according to the project environment and the organization's political environment. Cultural awareness is seeing the differences among individuals, groups and organizations and adjusting the communication strategy to those differences to reduce misunderstanding.

Consider a scenario. On a data analytics project, the senior engineers like to discuss data definitions in person, while the newly arrived junior analyst prefers to send text messages in the team chat, because replies can be reread and do not interrupt anyone. Both preferences have a good reason, and neither side is wrong. The project manager's correct move is to run a communication styles assessment first to find out what everyone prefers, then agree with the team on a communication arrangement that everyone accepts and write it into the communications management plan. Asking one side to give way to the other, or just setting up a single Q&A session, does not address the real issue, which is that preferences differ.

Judgment rules to apply when planning

  • Communication starts from the stakeholders' needs, not from the project manager's own habits.
  • Old communication templates and standard operating procedures among the organizational process assets can be used as references, but first assess whether they fit this project, then adapt them as needed and consult the stakeholders; do not copy them unchanged. If the organization expressly requires a procedure to be followed, follow it, and submit any proposed change as the organization requires.
  • When there are many stakeholders and the project manager has limited time, differentiate content and frequency by each party's concerns and set strategies by group, rather than sending everything to everyone.
  • For stakeholders who do not support the project, look at the engagement gap first, then run a communication styles assessment as needed.

Worked examples

Example 1 The next step after the register is built

Question 1Example

On a membership system upgrade project for a restaurant chain, the project manager has built the stakeholder register and is considering how to pass project information to the customer effectively. What should the project manager do next?

Show answer and explanation

Correct answer: D

The stakeholder register is built, and the project manager is thinking about how to get information to the customer. The question is what comes next after the register.

Plan Communications Management takes the stakeholder register and the stakeholder engagement plan as inputs and produces the communications management plan. The register identifies, assesses and classifies stakeholders, but it cannot replace an analysis of specific information needs (content, frequency, channel). So the next step is to build on the register and stakeholder analysis by carrying out a communication requirements analysis (supported by a communication styles assessment where needed), find out what each party needs, then set content, frequency and channel and develop the communications management plan. The sequence is analyze first, plan second, execute last. The answer is D.

Why the other options are wrong

  • A. One standard weekly meeting does not distinguish between audiences: it is too much for some and not enough for others. Analyze first, then set frequency and format.
  • B. A mass update is direct execution. It is not targeted, it risks information overload or missing key content, and there is no plan to follow.
  • C. Every project has different stakeholders. Past project materials can be a reference but cannot replace an analysis of this project's stakeholders.

Key takeaway In the scenario described, where the project manager is planning how to communicate, use the stakeholder register to analyze needs and develop the communications management plan before executing communications.

Variation If the communications management plan has already been approved, the next step is to carry out Manage Communications according to it. If someone has not received information, first consult the plan and determine why. Update the plan only if needs or communication arrangements have changed; if delivery merely failed, correct the execution problem under the existing plan.

Something wrong with this question?

Report an issue with this question

Example 2 Conflicting preferences call for a communication styles assessment

Question 2Example

The team on a data analytics project is mostly senior data engineers. Several of them tell the project manager that the newly arrived junior analyst always asks about data definition questions by typing in the team's instant messaging app, yet such questions can only be explained properly face to face. When the project manager asks the junior analyst, the analyst says that written answers can be reread and do not interrupt anyone's work. What should the project manager do?

Show answer and explanation

Correct answer: B

On this team the senior engineers prefer face-to-face discussion and the junior analyst prefers asking in writing, and each preference has its own reason. The project manager has to resolve the conflict of preferences at its root.

Communication styles assessment is a technique used in Plan Communications Management to identify stakeholders' preferred communication methods, formats and content. Both sides in the question give reasons: face to face makes the data definitions clear, while writing can be reread and does not interrupt others. Neither side is wrong, so the project manager should not favor one. The project manager should first find out the preferences, then agree with the team on an arrangement everyone accepts and write it into the communications management plan. That resolves the disagreement at its root. The answer is B.

Why the other options are wrong

  • A. This accommodates only the senior engineers and ignores the junior analyst's reasons (answers can be reread and do not interrupt others), so the disagreement remains as it was.
  • C. A fixed weekly session only standardizes the occasion. It does not establish anyone's preferences and does not settle the day-to-day conflict over face to face versus writing.
  • D. This swings the other way and accommodates only the junior analyst. It is equally one-sided and turns the arrangement into a unilateral order.

Key takeaway When members' communication preferences differ, use a communication styles assessment to find the preferences, then agree an arrangement together, without favoring either side.

Variation If the question changed to “a key stakeholder does not support the project and rarely replies to email,” you would first assess the engagement gap and then, as needed, run a communication styles assessment to find the stakeholder's preferred approach. An option saying “require everyone to use the same tool” is still not the answer.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The output of Plan Communications Management is the communications management plan, not a particular notice or meeting. When the scenario says the project manager is now planning how to communicate, analyze first and then plan; do not jump straight to "sending information".
  • Communication styles assessment looks at preferred methods, formats and content; it does not judge whether a person's personality is good or bad. It is often used with stakeholders who do not support the project.
  • Communication materials and standard operating procedures from past projects must be assessed for fit and then adapted; they cannot be applied directly. Where the organization has a mandatory requirement, follow the organization's rule.
  • Political awareness does not mean playing power games. It means recognizing formal and informal power relationships and working effectively within them.

Key takeaways

Key point

  • Plan Communications Management: plan how to communicate with the identified stakeholders, both inside and outside the team; the output is the communications management plan.
  • Inputs include the stakeholder register and the stakeholder engagement plan; communication planning has to align with the engagement plan.
  • Information can be classified as internal or external, sensitive or public, and general or detailed.
  • Communication styles assessment finds the methods, formats and content stakeholders prefer; political awareness and cultural awareness help adjust communication to the environment.
  • In a scenario like this lesson's, where the project manager is planning how to communicate, use the register to analyze information needs and develop the communications management plan before executing communications.

Lesson 2

Communication Requirements Analysis and the Number of Communication Channels

Lesson video

Lesson overview

When planning communication, the first step is to find out exactly what information each stakeholder needs; this is communication requirements analysis. The second step is to recognize that as the number of people grows, the number of communication channels multiplies; this is the channel calculation. This lesson contains both the most frequently tested scenario rule (when needs change, analyze first, then change the plan) and the calculation that regularly appears on the exam: n(n-1)/2. The second half walks through three complete worked calculations, each with a check. ECO: People domain, Task 4 (Engage stakeholders) and Task 8 (Plan and manage communication). The previous lesson covered Plan Communications Management as a whole; the next lesson covers communication technology and methods.

Communication requirements analysis

PMBOK 8 defines communication requirements analysis as "an analytical technique used to determine the information needs of the project stakeholders through interviews, workshops, the study of lessons learned from previous projects, etc." These requirements "are defined by combining the type and format of information needed with an analysis of the value of that information." The value part is the crucial one: more information is not better, and information that has no value to the recipient only creates distraction.

Sources of information typically used to identify and define project communication requirements include:

  • stakeholder information and communication requirements from within the stakeholder register and stakeholder engagement plan;
  • the number of potential communication channels or paths, including one-to-one, one-to-many and many-to-many communications;
  • organizational charts;
  • project organization and stakeholder responsibilities, relationships and interdependencies;
  • the development approach;
  • the disciplines, departments and specialties involved in the project;
  • the logistics of how many persons will be involved with the project and at which locations;
  • internal information needs (for example, when communicating within organizations);
  • external information needs (for example, when communicating with the media, the public or contractors); and
  • legal requirements.

The scenarios the exam uses for this topic mostly follow the same pattern: a stakeholder complains that there is too little information, or too much, which disturbs their work; the sponsor is replaced; the customer's contact person is replaced; or senior management asks to see status earlier. If the problem is only that the information does not fit a current stakeholder's needs, the right move is first to talk with that stakeholder, run a communication requirements analysis to find out what is wanted, and then update the communications management plan accordingly. If the sponsor or the customer's contact person is replaced, first identify and analyze the new stakeholder and update the register, then run a communication requirements analysis and update the communications management plan and other related plans based on it. The options "just send a report", "take the team to visit the stakeholder" and "add one more arrangement to the plan" all skip the step of finding out what is needed, which is why they are not the best answer. When the communication problem stems from unclear or changed stakeholder needs, first communicate with the stakeholder and analyze the needs, then update the communications management plan; adjusting tools or escalating depends on the nature of the problem and the escalation process in the plan. (If the problem comes from a tool failure, an urgent risk, a compliance requirement or an escalation threshold already reached, switching tools or escalating may have to happen immediately.) Common exam practice: when the question gives no other conditions and only says that the information is not what someone wants, clarifying the need comes before changing tools or escalating.

Ways to classify communication activities

The plan has to distinguish the different kinds of communication activity. The classification and selection rules below are common exam practice. There are four common ways to classify. By direction: upward (to superiors and the sponsor), downward (to the team) and lateral (among peers, for example project managers consulting each other). By form: formal and informal. By medium: written and oral. By scope: internal and external. The usual selection rule is this: for anything involving contracts, changes, performance conclusions or anything that needs a record, use formal written communication; for day-to-day coordination, or a private reminder to an individual member about behavior, use informal oral communication, and do it in private wherever possible.

The number of communication channels

n(n-1)/2 is the common exam calculation for the number of potential channels, and it appears often on the exam. The more people there are, the faster the channels grow. Two people have one channel. Each of n people has to communicate with the other n−1 people, giving n×(n−1) "person to person" pairs in total; but A to B and B to A are the same channel counted twice, so divide by 2:

Here n is the number of communication participants as the question defines them. Whether it includes the project manager, the sponsor and so on depends on who the question says must be able to communicate with each other.

Figure 1 Communication channels among 4 and 5 people
Figure 2 Growth of communication channels with the number of people

Before solving this kind of question, check three things: (1) whether n includes the project manager, according to the headcount basis in the question; (2) whether the question asks "increases to" (the total after the change) or "increases by" (the amount of change); (3) when people leave and join, calculate the net headcount first and then apply the formula.

Calculation 1 Direct substitution, checked with the running-sum method

The core team of a data migration project: 1 project manager and 6 members, 7 people in all, and every two people have to communicate.

  • Step 1: n = 1 + 6 = 7.
  • Step 2: substitute into the formula: 7 × 6 ÷ 2 = 42 ÷ 2 = 21 channels.
  • Check: person 1 has 6 channels with the other 6; person 2 has 5 with the remaining people after them; then 4, 3, 2, 1. The total is 6+5+4+3+2+1 = 21, which agrees with the formula.

Calculation 2 The basis for n: who is counted

A project manager leads 8 members, and there are also a sponsor and a customer representative (2 people); all 11 are required to communicate directly with each other.

  • Step 1: count the people: n = 1 + 8 + 2 = 11 (the question explicitly requires everyone to be interconnected, so the sponsor and customer representative are counted).
  • Step 2: 11 × 10 ÷ 2 = 110 ÷ 2 = 55 channels.
  • Common mistake: counting only the 8 members gives 8×7÷2 = 28, which leaves out the project manager and the other two people.
  • Check: 10+9+8+…+1 = 55. Checking the increment: if one more member joins, channels become 12×11÷2 = 66, an increase of 11, exactly equal to the headcount before the new member joined. So the calculation is right.

Calculation 3 People leave and join: increases to versus increases by

A team of 6 including the project manager; during execution 2 people are reassigned and 5 new people join.

  • Step 1: original channels = 6 × 5 ÷ 2 = 15.
  • Step 2: net headcount = 6 − 2 + 5 = 9, and the new number of channels = 9 × 8 ÷ 2 = 36.
  • Step 3: channels increase to 36; they increase by 36 − 15 = 21.
  • Check: add the 3 net new people one at a time: from 6 to 7 people adds 6 channels, from 7 to 8 adds 7, from 8 to 9 adds 8, and 15 + 6 + 7 + 8 = 36, which agrees with the direct calculation.

Common trap

  • Writing n(n-1)/2 as n(n-1) and forgetting to divide by 2 (with 12 people, 132 is wrong; the answer is 66).
  • Using n² or n(n+1)/2: both are misremembered formulas.
  • "Increases to" asks for the total and "increases by" asks for the difference; both numbers will appear among the answer options, so read the question carefully.

Worked examples

Example 1 The change in the number of channels

Question 1Example

A project's stakeholders grow from 8 to 11 people, and the number of communication channels is calculated as n(n-1)/2. By how many channels does the number of communication channels increase?

Show answer and explanation

Correct answer: D

Stakeholders grow from 8 to 11 people, and the number of channels is calculated as n(n-1)/2. You are asked by how many channels the number increases, so the quantity needed is the change, not the new total.

The formula and the headcounts are given, so the key is reading the question: you need “by how many” the channels increase, which means subtracting the number before the change from the number after, not simply giving the new total. Calculate the two totals with the formula, then subtract. This formula is the common exam calculation. The result is 27, which shows that every 3 additional people add channels much faster than headcount. The answer is D.

  1. With 8 people: 8×(8−1)÷2 = 28 channels.
  2. With 11 people: 11×(11−1)÷2 = 55 channels.
  3. Increase in channels = 55 − 28 = 27.
  4. Check: each of the 3 new people connects to the original 8, 3×8 = 24 channels, plus 3×2÷2 = 3 channels among the 3 new people, 27 in all, which agrees.

Why the other options are wrong

  • A. This is the increase in headcount, 11 − 8 = 3, treated as the increase in channels. The number of channels grows with the square of headcount, not linearly.
  • B. This is the original number of channels with 8 people, 8×7÷2 = 28. It counts only the total before the change, without calculating the total after or subtracting.
  • C. This is the total with 11 people, 11×10÷2 = 55, that is, “increase to” 55. It does not subtract the original 28, answering “increase to” instead of “increase by.”

Key takeaway Calculate the channel counts before and after, then subtract; “increase by” needs the subtraction, “increase to” does not.

Variation If it asked “from 5 to 9 people, by how many do the channels increase,” the answer is 9×8÷2 − 5×4÷2 = 36 − 10 = 26. If it asked “increase to how many,” the answer is 36.

Something wrong with this question?

Report an issue with this question

Example 2 The change in channels after staff changes

Question 2Example

The core team of a cross-border e-commerce platform redesign project has 4 people including the project manager. Halfway through execution, 1 member is reassigned to another project, and then 3 new members join. What happens to the number of potential communication channels within the core team?

Show answer and explanation

Correct answer: C

The team has 4 people including the project manager; 1 leaves and 3 join, so people both leave and join. You must judge how the communication channels change, telling “increase to” from “increase by.”

First calculate the net headcount, then apply n(n-1)/2, and finally subtract the earlier number from the later. Calculate once before and once after the change; the numbers among the options are intermediate results or typical mistakes in this process, so be clear whether the total or the increment is asked for. Only C is correct as worded: the increase is 15 - 6 = 9. The total after the change is 15, but “Increase to 15” is not offered; B writes 15 as an increase. The answer is C.

  1. Before the change: n = 4, channels = 4×3÷2 = 6
  2. Headcount after the change: 4 − 1 + 3 = 6
  3. After the change: n = 6, channels = 6×5÷2 = 15
  4. Change: 15 − 6 = 9, so channels increase by 9 (increase to 15)
  5. Check: going from 4 to 6 people adds 4 channels and then 5, 9 in all

Why the other options are wrong

  • A. 6 is the number of channels before the change (and also happens to be the headcount after it). This treats a headcount or the original channel count as the result of the change.
  • B. 15 is the total number of channels after the change; it should be described as “increase to 15.” The option says “increase by,” which would also require subtracting the original 6.
  • D. 36 = 6×6, which squares n instead of calculating n(n-1)/2.

Key takeaway Calculate the headcount after the net change first, then apply n(n-1)/2, and keep “increase to” and “increase by” apart.

Variation If, after 1 person leaves and 3 join, the question asked “increase to how many,” the answer would be 15. If 2 leave and 1 joins, n = 3 and there are 3 channels, a decrease of 3.

Something wrong with this question?

Report an issue with this question

Example 3 The sponsor is replaced: what to do first

Question 3Example

During execution of a smart warehouse system integration project, the company is acquired by a large enterprise, and the project sponsor is now a vice president from the acquirer. The project manager has already identified and analyzed the new sponsor and updated the relevant assessment information in the stakeholder register. The new sponsor wants to learn the project status and plans to hold a project review meeting. What should the project manager do?

Show answer and explanation

Correct answer: B

During execution the company is acquired and the sponsor is replaced by the acquirer's vice president. The project manager has identified and analyzed the new sponsor and updated the relevant assessment information in the stakeholder register. The new sponsor wants to understand the status and plans a review meeting. The question asks what the project manager should do.

A change of sponsor means a stakeholder's needs may have changed, and the existing communication arrangements may not suit the new person. Before the review meeting, first carry out a communication requirements analysis to find out the type, format and frequency of information the new sponsor needs, then update the communications management plan so later communication meets those requirements. This is the standard pattern: when needs change, analyze first, then update the plan, then choose the method. The answer is B.

Why the other options are wrong

  • A. Sending the performance report directly, without confirming the format and content the new sponsor wants, may not give the sponsor what is needed.
  • C. Introducing team members has no direct bearing on understanding project status and is not what the new sponsor needs right now.
  • D. The issue log is a project document for recording and tracking issues. What the new sponsor needs now is the overall status and the information needed for decisions, not a raw list of issues. It also cannot replace first analyzing communication needs and updating the communications management plan.

Key takeaway When a stakeholder's information needs or communication preferences may have changed, first run a communication requirements analysis, then update the communications management plan, and only then send information or hold meetings.

Variation If it changed to “the customer's liaison is replaced and is cold toward the project,” and the cause is that report content, format or frequency do not meet the person's needs, the answer is again to analyze communication requirements first. If the cause is mainly insufficient engagement, first analyze and develop the matching stakeholder engagement strategy. If “a new external stakeholder was added,” add that stakeholder to the stakeholder register and analyze the stakeholder's influence, needs, and expectations together before updating the relevant plans.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When needs change, first run a communication requirements analysis and find out what is wanted, then choose a suitable communication method accordingly and update the communications management plan, and communicate afterwards according to the updated plan; do not send a report or arrange a meeting straight away.
  • The number of communication channels depends only on the number of people taking part in the communication, not on the amount or frequency of information.
  • Communication requirements analysis asks about "the type and format, combined with the value of that information", not only "what the other party wants".
  • Upward, downward, lateral and external communication each have their own requirements, and a small group's needs cannot be met with a single one-size-fits-all report.

Key takeaways

Key point

  • Communication requirements analysis: determine the type and format of information stakeholders need and the value of that information; sources include interviews, workshops and lessons learned.
  • When stakeholders or their needs change: analyze the needs first, then choose a suitable communication method and update the communications management plan, then communicate according to the plan.
  • Number of communication channels = n(n-1)/2; first decide whether n includes the project manager, then tell "increases to" from "increases by".
  • Check: add up (n−1)+(n−2)+…+1, or use "one more person adds n channels".
  • Use formal written communication for important matters and private oral communication for individual reminders.

Lesson 3

Communication Technology and Communication Methods: Push, Pull and Interactive

Lesson video

Lesson overview

When planning communication you have to settle two things: which tools to use (communication technology) and how information will flow (communication methods). The exam likes the second one best: the question describes a practice and asks you to decide whether it is push, pull or interactive, or asks the reverse, "to achieve a certain purpose, which one should you choose?" This lesson first separates the three easily confused names, technology, methods and skills, then covers the five factors for choosing technology, then goes through the three types of method and the five major forms of communication, and ends with selection rules. ECO: People domain, Task 8 (Plan and manage communication). The previous lesson covered requirements analysis; the next covers communication models.

Technology, methods, skills: remember the three names separately

Communication technology includes specific tools, systems, computer programs and the like, used to transfer information among project stakeholders. Common methods for information exchange and collaboration include conversations, meetings, written documents, databases, social media and websites. A communication method is "a systematic procedure, technique, or process used to transfer information among project stakeholders"; it looks at the direction and manner in which information flows. Communication skills are "a collection of skills to provide, receive, and elicit information from various sources"; they are abilities a person has, such as listening, giving feedback and presenting (the first lesson of the Manage Communications chapter covers them in detail).

In short: technology is the tool, the method is the route, and skills are the ability. If a question asks "the handover process lacks a standard approach, what should be improved?", the answer is the communication method; if it asks "what tool should be used to publish this?", the answer is communication technology.

Five factors in choosing communication technology

FactorThe question to ask
Urgency of the need for informationHow fast must the information arrive, and do frequency and format vary by project phase?
Availability and reliability of technologyIs it compatible throughout the project, and available and accessible to all stakeholders?
Ease of useIs it suitable for project participants, with training arranged where needed?
Project environmentFace-to-face or virtual meetings, one time zone or several, multiple languages, any cultural differences?
Sensitivity and confidentiality of the informationIs sensitive or confidential content involved, what security measures are needed, and does the organization have a social media policy?

For example, on a project with high security requirements, even if instant messaging is the most convenient, confidential content must go through a controlled system; when the team is spread across several time zones, agree on response times for asynchronous messages instead of expecting someone to reply at any moment.

Three types of communication method

MethodHow it worksCharacteristicsCommon examples
Interactive communicationThe parties exchange information in real time, back and forthAllows clarification on the spot and a shared understanding; usually suited to cases that need real-time discussion or coordination of viewsFace-to-face meetings, video conferences, phone calls, instant messaging
Push communicationInformation is sent directly to specific recipientsEnsures the information is distributed but does not ensure that it reaches or is understood by the intended audienceLetters, memos, reports, emails, press releases
Pull communicationRecipients access the content themselves, subject to security proceduresSuited to large, complex information sets or to large audiencesWeb portals, intranet sites, eLearning courses, lessons learned databases, knowledge repositories

Three contrasting scenarios. After a headquarters review meeting, minutes are sent only to the key staff of the regional branches, and several branches still go off course: minutes are push communication, which only ensures that the information is sent, not that it is understood. To fix this at the root, have the key staff join by video or phone so points can be clarified on the spot, which is interactive communication. Members of an international project each need different lessons learned, so an intranet is built for them to search themselves: pull communication. A municipal engineering project opens a public web page to publish progress for residents: also pull, because recipients come and look for themselves.

Five major forms of communication

PMBOK 8 lists five major forms of communication, and the communications management plan should apply different approaches to them. Interpersonal communication is information exchanged between individuals, typically face-to-face. Small group communication occurs within groups of three to six people. Public communication occurs when a single speaker, or group of speakers, addresses a larger audience. Mass communication is an approach with minimal connection between the person or group sending the message and the large, sometimes anonymous, groups for whom the information is intended. Networks and social computing communication supports the emerging many-to-many communication trend, often through social computing technology and the media.

How to choose

  • The goal is "for everyone to understand and agree": use interactive communication, such as face-to-face or video meetings. If there is a dispute that must be settled the same day, immediately bring the parties together on a phone or video call.
  • The goal is "to send out formal information and leave a record": use push communication, but add a step to confirm receipt.
  • The audience is large, the information volume is high and you want recipients to take what they need: use pull communication.
  • When stakeholders' cultures, circumstances and preferences differ widely: do not use only one approach; use several according to each party's situation.
  • Methods should be decided by stakeholders' needs and written into the communications management plan, not by whatever the project manager is used to.

Worked examples

Example 1 What is missing besides the minutes: interactive communication

Question 1Example

A corporate group launches a cross-regional ERP rollout project at its headquarters, and each provincial branch sends a few key staff to take part. Because travel is restricted, these key staff can normally only read the minutes issued after headquarters review meetings, and as a result several branches' implementations have drifted from project requirements. To improve this at its root, which communication method should the project manager use?

Show answer and explanation

Correct answer: D

During execution of an ERP rollout project, branch key staff can only read the minutes issued after review meetings because travel is restricted, and implementations have drifted from requirements. The question asks which communication method fixes this at the root.

The root of the problem is that minutes are one-way, after-the-fact information, and there is no way to confirm that the other side has understood. Interactive communication is a real-time, multidirectional exchange of information that allows clarification on the spot and is the most effective method for getting everyone to a shared view. Having the key staff take part in the reviews by video or phone, exchanging and confirming points on the spot, is what resolves the gap in understanding. The answer is D.

Why the other options are wrong

  • A. Mass communication is a sender addressing a large, sometimes anonymous audience with minimal connection between them, so it hardly produces common understanding; it is a form of communication classified by scale, not a method at the level of push, pull and interactive.
  • B. Meeting minutes are themselves push communication, which only ensures that information is sent, not understood. That is the source of the problem, so continuing with push will not improve it.
  • C. Pull means the recipient fetches the content. The branches already have the minutes; what they lack is understanding of and alignment with the content, not a way to fetch it.

Key takeaway Push only sends; when parties need to reach consensus and a common understanding, use interactive communication.

Variation If the provincial key staff need to look up past review materials at any time, the answer becomes pull; if you only need to send one notice to designated people, the answer is push.

Something wrong with this question?

Report an issue with this question

Example 2 Let members search for themselves: pull communication

Question 2Example

The members of a multinational project come from several countries. After identifying communication needs, the project manager finds that each member needs different lessons learned, and so builds a company intranet that lets members search for them on their own. Which communication method has the project manager adopted?

Show answer and explanation

Correct answer: D

On a multinational project, the project manager finds after identifying communication needs that each member needs different lessons learned, and builds a company intranet for members to search on their own. Which communication method is this?

Communication methods are classified by how information flows into push, pull and interactive. Content on the intranet is looked up by recipients themselves rather than sent by a sender to specific people, which is the typical practice of pull communication, suited to large, complex information sets or large audiences. In the question, members are spread across countries and each needs different content, so pushing to each one individually would be inefficient and imprecise; letting members take what they need is the right fit. Lessons learned databases and knowledge repositories are of the same kind. The answer is D.

Why the other options are wrong

  • A. Push sends information directly to specific recipients; content on the intranet is looked up by members themselves, not sent.
  • B. Interactive communication is a real-time multidirectional exchange, and searching an intranet involves no real-time exchange.
  • C. By how information flows, the communication methods are push, pull and interactive; “portal communication” is not one of these three methods. A web portal is usually just a vehicle for pull communication.

Key takeaway An intranet, a knowledge repository or a public web page, anything the recipient accesses on their own, is pull communication.

Variation If the project manager compiled the lessons learned each week and emailed them to every member, that would be push; if an online workshop were held for members to exchange ideas, that would be interactive.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Push communication only guarantees "sent", not "received and understood"; to confirm understanding you need feedback or interactive communication.
  • Email and reports are push; public web pages, intranets and knowledge repositories are pull; meetings, calls and video conferences are interactive.
  • By how information flows, communication methods fall roughly into three types: interactive, push and pull. (PMBOK 8 also lists five major forms of communication.) "Portal communication" and "broadcast communication" are not official categories; a web portal is usually a vehicle for pull communication.
  • Technology is the tool, a method is the way information flows, and skills are a person's ability; the three cannot be swapped.

Key takeaways

Key point

  • Communication technology is the tool, a communication method is the way information flows, and communication skills are a person's ability.
  • Choose technology by five factors: urgency, availability and reliability, ease of use, project environment, and sensitivity and confidentiality.
  • Interactive communication: real-time and multidirectional, best for reaching consensus. Push: ensures the information is sent, not that it is understood. Pull: the recipient takes it, suited to large amounts of information and large audiences.
  • Five main forms of communication: interpersonal, small group, public, mass, and networks and social computing communication.
  • Methods depend on stakeholder needs and are written into the communications management plan.

Lesson 4

Communication Models: Encode, Transmit, Decode and Feedback

Lesson video

Lesson overview

Why does an email go out, the recipient reply "received", and the work still go wrong? Communication models answer this kind of question: they break one act of communication into steps and show where each step can fail. PMBOK 8 gives three models, from the basic model that is only concerned with delivery, to the interactive model that stresses understanding, to the cross-cultural model that takes in emotion, culture and bias. This lesson covers the steps, the noise and the division of responsibility in the three models, and explains the difference between "acknowledging receipt" and "feedback", the detail most often tested on this topic. ECO: People domain, Task 8 (Plan and manage communication).

What a communication model is

A communication model is "a description, analogy, or schematic used to represent how the communication process will be performed for the project." It can represent the communication process in its most basic linear form (sender and receiver), in a more interactive form that adds the element of feedback (sender, receiver and feedback), or in a more complex model that incorporates the human elements of the sender(s) or receiver(s) and attempts to show the complexity of any communication that involves people.

Figure 1 Three communication models

The basic sender/receiver model

This model describes communication as a process with two parties, the sender and the receiver. It is concerned with ensuring that the message is delivered rather than understood. The sequence of steps is:

  • Encode. The message is coded into symbols, such as text, sound, or some other medium, for transmission (sending).
  • Transmit message. The message is sent via a communication channel. The transmission may be compromised by physical factors such as unfamiliar technology or inadequate infrastructure. Noise and other factors may be present and contribute to loss of information in transmission and/or reception of the message.
  • Decode. The data received is translated by the receiver back into a form useful to the receiver.

Every step in this model can go wrong. If the sender is vague, the encoding is unclear; if the email is caught in a spam folder, the transmission fails; if the receiver does not know the terminology, the decoding goes wrong. For important information whose understanding must be confirmed, plan an appropriate feedback or follow-up step in line with the communications management plan; do not treat “sent” as “understood.”

The interactive model: adding acknowledgment and feedback

The interactive model also describes communication as a process in which the sender and receiver both take part, but it recognizes the need to ensure that the message has been understood, and it brings in any noise, meaning any interference or barriers that might compromise understanding, such as the distraction of the receiver, variations in the perceptions of receivers, or lack of appropriate knowledge or interest. It adds two steps to the basic model:

  • Acknowledge. Upon receipt of a message, the receiver may signal (acknowledge) receipt of the message, but this does not necessarily mean agreement with or comprehension of the message; it means merely that it has been received.
  • Feedback/response. When the received message has been decoded and understood, the receiver encodes thoughts and ideas into a message and transmits this message to the original sender. If the sender perceives that the feedback matches the original message, the communication has been successful. In communication among people, feedback can be achieved through active listening.

Consider a scenario. A project manager emails the project management plan to the team members, and a member replies "received" right away and starts work. A few weeks later it turns out someone has been doing work outside the scope. "Received" is only an acknowledgment. If the member had replied with their understanding of the plan in their own words, the project manager could have spotted the gap. To avoid this kind of problem, have the receiver return their understanding so the sender can confirm it.

The cross-cultural model: human factors are noise too

In cross-cultural communication, making sure the message is correctly understood is a bigger challenge. Differences in communication styles can arise from differences in working methods, age, nationality, professional discipline, ethnicity, race or gender, and people from different cultures communicate using different languages and expect different processes and protocols. The cross-cultural model stresses that the sender's current emotional state, knowledge, background, personality, culture and biases influence the message itself and how it is transmitted; likewise, the receiver's emotional state, knowledge, background, personality, culture and biases influence how the message is received and interpreted, and contribute to the barriers or noise. The model can help develop communication strategies and plans for person-to-person or small-group-to-small-group communication; it is not useful for other communication artifacts such as emails, broadcast messages or social media.

What the sender and the receiver are each responsible for

The sender is responsible for the transmission of the message, ensuring the information being communicated is clear and complete, and confirming the message is correctly interpreted. The receiver is responsible for ensuring that the information is received in its entirety, interpreted correctly, and acknowledged or responded to appropriately. These components take place in an environment where there will likely be noise and other barriers to effective communication. Identify them and try to eliminate or reduce their interference with effective communication.

For a virtual team whose members come from different countries and have never worked together, when the project manager develops the communications management plan, first find out how cultural differences affect communication effectiveness, and then choose methods and tools accordingly. Pushing out emails in one direction, setting up a cloud folder or appointing a communication manager does not address this.

Worked examples

Example 1 "Received" does not mean understood

Question 1Example

A project manager emails the project management plan to team members, and a member replies “received” immediately on getting it and then starts executing. During execution the project manager finds someone doing work outside the scope, and an investigation confirms that the member misunderstood the plan. To prevent this kind of deviation, how should communication have been arranged beforehand?

Show answer and explanation

Correct answer: A

During execution, the project manager emails out the project management plan, a member replies “received” and starts executing, but the member misunderstood and did work outside the scope. The question asks how communication should have been arranged beforehand.

The interactive communication model adds “acknowledge” and “feedback” to the basic model's encode, transmit and decode. “Received” is only an acknowledgment of receipt and does not mean agreement or comprehension. Real feedback is the receiver decoding and understanding the message, then encoding their own thoughts and sending them back; communication succeeds when the sender perceives that the feedback matches the original message. Because the member did not send back their understanding, the deviation stayed hidden. So communication should have been arranged so that the member returns their understanding for the project manager to confirm. The answer is A.

Why the other options are wrong

  • B. The email already delivered the information, so the channel itself was not the problem, and changing the channel cannot guarantee understanding.
  • C. This is only decoding. The understanding is not sent back to the other side to confirm, so it may still be the member's own misunderstanding.
  • D. Collecting communication needs and selecting a delivery method addresses how information gets to people. Here the email arrived and the member replied that it was received; the problem is that understanding was not confirmed.

Key takeaway “Received” does not equal “understood.” Having the receiver send back their own understanding is effective feedback.

Variation If the scenario were “the email went into a spam folder and the member never saw it,” the problem would be in transmission, and you would change channels or add a notice. If it were “the member saw it but did not want to listen,” that would be noise and the receiver's responsibility.

Something wrong with this question?

Report an issue with this question

Example 2 A cross-cultural virtual team: what to do first

Question 2Example

PMLyceum has put together a diverse international team that will collaborate virtually, and the members have never worked together before. The project manager is developing the communications management plan. For the plan to be effective, what should the project manager do first?

Show answer and explanation

Correct answer: B

During planning, the project manager is developing the communications management plan for an international virtual team that has not worked together before. The question asks what must be done first for the plan to be effective.

The communication model points out that the sender's and receiver's emotional state, knowledge, background, personality, culture and biases all affect how a message is expressed and understood and can create noise. For a multinational virtual team with no shared working history, cultural differences are a key consideration when developing the plan. So first work out how cultural differences affect communication effectiveness, then choose methods and tools accordingly; that is what cultural awareness calls for. The answer is B.

Why the other options are wrong

  • A. One-way push cannot confirm that the other side has understood, and helps little with an unfamiliar virtual team.
  • C. A cloud folder is just a place to store things. It does not touch the root problem of cultural differences, and it is not what should be done first.
  • D. A communications manager can help, but the project manager first has to understand cultural differences for the plan to stand on solid ground.

Key takeaway When developing a communication plan for a cross-cultural team, first study the cultural differences, then choose tools and methods.

Variation If the team were in one city with similar cultures, you would first run a communication requirements analysis. If the question said “members always just nod and never ask questions,” the answer would still be to consider cultural awareness and set up a feedback mechanism.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • "Acknowledging receipt" only says the message arrived; it does not mean agreement or understanding. Real feedback is the receiver understanding the message and then encoding it and sending it back.
  • The basic model is concerned with delivery, the interactive model with understanding, and the cross-cultural model adds the human factors of both sides.
  • Noise and other barriers may exist on both sides; identify them and try to eliminate or reduce their interference.
  • The cross-cultural model cannot be used to develop communication strategies for email, broadcast messages or social media.

Key takeaways

Key point

  • Basic model: encode, transmit message, decode; it is concerned only with delivery.
  • Interactive model: adds acknowledgment and feedback/response; it stresses being understood and requires managing noise.
  • Cross-cultural model: the emotions, knowledge, background, personality, culture and biases of both sender and receiver affect communication and can create barriers or noise.
  • The sender ensures the message is clear and complete and confirms it was understood; the receiver receives it in full, interprets it correctly and responds.
  • Receipt is not understanding; having the receiver send their understanding back is effective feedback.

Lesson 5

The Communications Management Plan: Contents, Use and Updates

Lesson video

Lesson overview

The tools from the first four lessons all end up in one document: the communications management plan. Exam questions on this topic are very focused. Whenever a scenario shows communication going wrong, someone not receiving information, or someone raising a new requirement, first decide whether the problem is a missing plan or a deviation in execution. If the plan has gaps, evaluate the need and update the plan (if no plan exists yet, develop one first). If the plan is simply not being followed, correct the execution. Then choose the action that fits the specific scenario. Common exam practice: questions of this kind often have "consult the communications management plan" or "update the communications management plan" as the answer, but first separate the two cases above. This lesson covers what the plan is, what it contains, what each item answers, when it must be updated, and how it differs between predictive and adaptive projects. ECO: People domain, Task 4 (Engage stakeholders), Task 6 (Manage stakeholder expectations) and Task 8 (Plan and manage communication).

What the plan is

The communications management plan is a component of the portfolio, program or project management plan that describes how, when and by whom information will be administered and disseminated. It describes how project communications will be planned, structured, implemented and monitored for effectiveness. It is paired with the stakeholder engagement plan: the engagement plan answers "which strategies and actions promote effective stakeholder engagement", and the communications management plan answers "how information should flow to support that goal".

The starting point of the plan is stakeholders' communication needs, and every person is different. Some leaders like email and do not respond when you talk to them in person; some will only listen in person; some prefer to read reports. PMBOK 8 calls for adjusting the level of detail of communication to each stakeholder's role; in practice, the higher the position, the leaner the material (common exam practice): a manager reads a few pages, a director reads one page, and the top executive may want only a few sentences. The form and content of the same message have to be tailored to the audience, and a poor choice can reduce communication effectiveness.

What the plan typically contains

The plan typically contains the following, which you can remember as "who, what, when, how, and how it is managed":

Question answeredPlan content
To whomStakeholder communication requirements; the persons or groups that will receive the information, including their needs, requirements and expectations
WhatThe information to be communicated, including language, format, content and level of detail; the reason for distributing that information
WhenThe timeframe and frequency for distribution of the required information and for receipt of acknowledgment or response, if applicable
By whomThe person responsible for communicating the information, and the person responsible for authorizing release of confidential information
HowThe methods or technologies used to convey the information, such as memos, emails, press releases or social media announcements; flowcharts of the information flow, workflows with possible sequence of authorization, a list of reports and meeting plans
How it is managedEscalation processes; resources allocated for communication activities, including time and budget; the method for updating and refining the plan as the project progresses; a glossary of common terminology; constraints derived from specific legislation or regulations, technologies, organizational policies and so on

A few items need special attention for how they show up on the exam. Sensitive information: the plan states who has the authority to approve release of confidential information, so if an engineer wants to talk about internal project data externally, first consult the plan to confirm who authorizes it; information can also be released in tiers by sensitivity and authority. Glossary of terminology: a common glossary gives the team a shared language; say "this work is on the critical path" and the listener knows its urgency without an explanation. In cross-department or cross-company communication, compile a glossary both sides use. Escalation process: it specifies in which circumstances to escalate and to whom; when management has requirements about escalation, consult the plan first. Timeframe: agree a reply cycle for asynchronous messages or emails so that team members are not left waiting on each other.

Figure 1 The cycle of communications management: the plan is the basis for execution and monitoring

How the plan is used and when it is updated

Once written, the plan is the basis for execution and monitoring. Manage Communications sends information according to it, and Monitor Communications checks actual practice against it. In the following situations, first identify whether the issue is execution of the existing plan or a new communication need, then proceed accordingly:

  • Someone has not received information, or complains of too little or too much: first check whether the plan includes that person's needs and whether the person is on the distribution list.
  • A stakeholder raises a new requirement, for example the sponsor wants status information before the status meeting: first communicate with the sponsor to understand the need, then choose a suitable communication method and update the plan, and then communicate according to the plan. Do not first agree to send emails or have the team report separately.
  • When a new stakeholder is identified, first register and analyze the stakeholder, then check and update the stakeholder engagement and communications management plans. When the sponsor or contact person is replaced, first understand that person's needs, then update the relevant plans with specific communication arrangements.
  • Outsourced parties, subcontractors, outside experts and the media communicate with the project: the plan should state the rules for external communication, for example a single designated external contact, and who attends external meetings.

The main triggers for an update are a change of project phase, a change in the stakeholder community, and problems found by monitoring communication effectiveness. The plan must be updated and refined as the project progresses, and methods should vary by person: for example, email for formal updates, instant messaging for quick questions, and also feedback loops, face-to-face meetings, or adjusting the level of detail to each stakeholder's role.

How predictive and adaptive projects differ

How detailed the plan is depends on tailoring. Complex projects with many stakeholders need a more elaborate communications management plan than smaller projects, where the communication channels are more limited. Adaptive projects need continuous feedback on features and user stories and typically use daily coordination meetings and dedicated real-time communication platforms, with more frequent and more informal information exchange. Predictive projects may rely more on written plans, periodic reports and phase reviews. In both cases the formality of communication and the level of detail of the plan should still be tailored to organizational culture, project complexity and the stakeholders. International projects should adopt inclusive communication strategies, such as multilingual updates and regular virtual forums, to ensure stakeholders from different cultural backgrounds can take part and give feedback.

Communications management plan: predictive vs. adaptive

  • Predictive: developed mainly during planning, stating frequency, format, owners and escalation paths, and updated after changes.
  • Adaptive: usually a lighter plan that is easy to adjust continuously, combined with daily coordination meetings, iteration review meetings and collaboration platforms; the plan adapts quickly to feedback, and its level of detail is still tailored to project complexity and stakeholders.
  • Common ground: both first learn what the stakeholders need, and both update the plan when needs change.

Worked examples

Example 1 Senior management asks to see status information earlier

Question 1Example

A project manager runs a port expansion project. All senior managers attended the phase 1 status meetings. After the project moves into phase 2, one senior manager asks to receive project status information before each status meeting. What should the project manager do?

Show answer and explanation

Correct answer: D

The port expansion project has entered phase 2, and a senior manager asks to get project status information before each status meeting. The question asks what the project manager should do.

“Receive status information before the meeting” is a new communication requirement. The communications management plan contains stakeholders' communication requirements, so when a requirement changes, first talk with the manager to learn what information is wanted, when and in what form, then choose a suitable communication method and update the communications management plan, and then carry it out according to the plan. If this step is skipped, choosing email, mass sending or having members report separately may not match the form and timing the manager really wants, and may also produce inconsistent figures. The answer is D.

Why the other options are wrong

  • A. “You can get it at the meeting” ignores the manager's new requirement and is a passive response.
  • B. Email is a specific method and should be decided after the need is understood; at this point it is not even clear what content the manager wants.
  • C. Having members send information separately also fixes the method before the need is clear and with no plan to rely on, and it would produce inconsistent figures.

Key takeaway When a communication need changes: first understand the need, then choose a communication method and update the communications management plan.

Variation If it changed to “a senior manager asks for the report to become a one-page summary,” the line of thought is the same: confirm the need first, then update the plan. If the request goes beyond the project's scope, evaluate it first and then decide whether to accept it.

Something wrong with this question?

Report an issue with this question

Example 2 The distribution list was missed: which document to update first

Question 2Example

At the latest project status meeting, a stakeholder who has long been in the stakeholder register says he did not receive the root cause analysis of an issue discussed at the meeting. The project manager confirms that the stakeholder's work requires this analysis and finds that the person is not on the report distribution list. What should the project manager do first?

Show answer and explanation

Correct answer: C

At a status meeting, a stakeholder already in the stakeholder register says he did not receive the root cause analysis of an issue. The project manager confirms that the stakeholder's work requires the analysis and finds he is not on the report distribution list. What should the project manager do “first”?

The communications management plan specifies how information is delivered, when and by whom, and also who receives it. He is in the register but not on the distribution list, which means the plan did not cover his needs. This is a communication problem, so first update the communications management plan to put him on the distribution list, then send him the material that was missed. The answer is C.

Why the other options are wrong

  • A. The stem does not involve risk. The problem is the distribution list, and the risk register cannot help.
  • B. Whether a change request is needed is set by the change management plan. Adding someone who needs the material to the distribution list only adjusts communication arrangements and does not touch the scope, schedule or cost baselines, so it is normally updated and recorded as the plan authorizes, without first submitting a change request; only if the communications management plan is under configuration control should it be handled under the change management plan.
  • D. He has long been in the register. What is missing is a communication arrangement, so the register does not need updating.

Key takeaway If someone who needs the material is missing from the distribution list, first update the communications management plan, then send the material that was missed.

Variation If he were not in the register at all, you would first register and analyze him, then check and update the stakeholder engagement and communications management plans. If he were on the distribution list and still did not receive the material, you would look into an execution problem.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The communications management plan records rules and arrangements, not the content of any one communication; it is a component of the project management plan, not a project document.
  • When someone misses information, first separate whether the plan did not provide for it or the plan was not followed. If the plan did not provide for it, update the plan; if the plan provided for it and it was not done, send it as the plan says.
  • Adding a stakeholder to the distribution list usually does not involve changing a baseline. Whether a change request is needed should follow the change management plan and the configuration management plan; if the plan is under configuration control, handle it through the formal change process. (PMBOK 8: a change request is a formal proposal to modify any document, deliverable or baseline.) The stakeholder register does not need updating either, unless the person is a newly identified stakeholder.
  • The stakeholder register, the stakeholder engagement plan and the communications management plan each handle one thing: who the stakeholders are, which strategies and actions promote their effective engagement, and how information is delivered. Do not mix them up.

Key takeaways

Key point

  • The communications management plan is a component of the project management plan that describes how, when and by whom information will be administered and disseminated, and how communication effectiveness will be monitored.
  • Its contents center on requirements, information, timeframe and frequency, responsible persons, methods or technologies, escalation processes, resources, the update method, a glossary and constraints.
  • Confidential information is released by the person the plan designates; for external communication, set the rules first.
  • When communication goes wrong or needs change, consult the plan and understand the needs first, then choose a suitable communication approach; if the existing plan does not cover the need, update it accordingly and then execute. When a new stakeholder is identified, first register and analyze the stakeholder, then check and update the stakeholder engagement and communications management plans.
  • Complex projects with many stakeholders need more detailed plans; adaptive projects communicate more often and more informally.

This chapter has 67 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.