Stakeholders and Communication

Managing and Monitoring Communications

PMP · Stakeholders and Communication · 4 lessons · about 43 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Once the communications management plan is written, someone has to carry it out and check how well it works. Manage Communications belongs to the executing focus area and is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information. Monitor Communications belongs to the monitoring and controlling focus area and is the process of ensuring the information needs of the project and its stakeholders are met. The three communications processes (Plan Communications Management, Manage Communications and Monitor Communications) join end to end into a cycle. When a problem appears, you first assess the cause and the gap in information needs, then take corrective action based on the analysis, and, where necessary, update the relevant plans or raise a change request (common exam practice: when the question gives no other conditions, the usual order is to analyze the cause first, then update the communications management plan). The chapter also covers two practical topics: project reporting and reporting in agile settings, and how to tailor communication for virtual teams, multiple time zones and external stakeholders.

By the end of this chapter you should be able to do the following. State the purpose, inputs and outputs of Manage Communications and Monitor Communications. Tell communication skills from interpersonal and team skills, and use the communications management plan to handle “communication has gone wrong” scenarios. Adjust the level, format and detail of project reports to the audience, and explain red-amber-green status indicators and information radiators. Monitor communications against the plan, analyzing first and acting second. For scenarios involving international teams, time zones and external stakeholders, choose the action that fits the tailoring approach.

Lessons in this chapter

Chapter map

ProcessFocus areaIn one sentence
Plan Communications ManagementPlanningProduces the communications management plan (previous chapter)
Manage CommunicationsExecutingCollects, creates and distributes information according to the plan, and uses confirmation and feedback to make sure it has been understood correctly
Monitor CommunicationsMonitoring and controllingChecks whether information needs are met, analyzes the cause first, then updates the plan or raises a change request
TailoringThroughoutOrganizational culture, the product, AI, time zones, language, external stakeholders

Study tips and practice

  • Questions where communication has gone wrong (common exam practice): your first reaction is “follow or consult the communications management plan” and see whether anything was agreed and whether it was carried out. Next, analyze needs, environment and tools to find the root cause and the gap. Then revise the plan and collect feedback. Only last comes replacing people or escalating, and change requests are raised as needed.
  • For agile questions, hold on to “transparency”: information radiators, Kanban boards and burndown charts let stakeholders look for themselves.
  • When you practice the chapter questions, first jot down on scratch paper whether the question is about planning, executing or monitoring, and only then choose an answer.

Lesson 1

Manage Communications: Collecting, Creating and Distributing Information According to the Plan

Lesson video

Lesson overview

Once the communications management plan is written, someone has to put it into practice, and that is Manage Communications. It belongs to the executing focus area. The work is to collect, create and distribute information; for critical information or communication that requires a closed loop, confirm that the other party has received and understood it. This lesson covers the purpose and key benefit of the process, its inputs and outputs, communication skills and interpersonal and team skills, and the two judgments the exam tests most often: when communication goes wrong, go to the communications management plan first, and information sent is not the same as information known. ECO: People domain, Task 8 (Plan and manage communication). The previous chapter covered planning, the next lesson covers project reports and information sharing, and the one after covers Monitor Communications.

Purpose and key benefit

“The Manage Communications process involves setting up and conducting communications with stakeholders (e.g., sponsors, customers, end users, team members, managers, or executives), both inside and outside the team (e.g., external vendors). Manage Communications is the process of ensuring the timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and ultimate disposition of project information. The key benefit of this process is that it enables an efficient and effective information flow between the project team and stakeholders.”

Two points stand out in this passage. First, information has a long life cycle: from collection and creation, through storage and retrieval, to ultimate disposition, every stage is covered by Manage Communications. Second, the process identifies all aspects of effective communication, including the choice of appropriate technologies, methods and techniques, and it needs flexibility: when the needs of stakeholders or the project change, the methods and techniques must be adjusted too.

Inputs, tools and techniques, outputs

ItemContents
InputsResource management plan, communications management plan, stakeholder engagement plan; change log, issue log, lessons learned register, quality report, risk report, stakeholder register; work performance reports; enterprise environmental factors; organizational process assets
Tools and techniquesCommunication technology; communication methods; communication skills (communication competence, feedback, nonverbal communication, presentations); project management information system; project reporting; interpersonal and team skills (active listening, conflict management, cultural awareness, meeting management, networking, political awareness); meetings
OutputsProject communications; project management plan updates (communications management plan, stakeholder engagement plan); project document updates (issue log, lessons learned register, project schedule, risk register, stakeholder register); organizational process asset updates

The most important input is the communications management plan. It describes how, when and by whom information will be administered and disseminated, and Manage Communications carries it out. Work performance reports are “the physical or electronic representations of work performance information compiled in project documents, which are intended to generate decisions, actions, or awareness”, and they are circulated to stakeholders as defined in the communications management plan. Among the outputs, project communications “may include but are not limited to performance reports, deliverable status, schedule progress, cost incurred, presentations, and other information required by stakeholders.”

Communication skills

“Communication skills are a collection of skills to provide, receive, and elicit information from various sources. Communication skills can be oral, visual, or electronic. Oral communication skills include interaction, presentation, active listening, and meeting facilitation. Visual communication skills include data visualization and nonverbal communication. Electronic communication skills include electronic tools such as professional writing, crafting emails, texting, chatting, AI prompts, and similar activities.”

  • Communication competence: “a combination of tailored communication skills that considers factors such as clarity of purpose in key messages, effective relationships and information sharing, and leadership behaviors.”
  • Feedback: “information about reactions to communications, a deliverable, or a situation. Feedback supports interactive communication among the project manager, project team, and all other project stakeholders. Examples include coaching, mentoring, and negotiating.”
  • Nonverbal communication: body language that transmits meaning through gestures, tone of voice and facial expressions. Mirroring and eye contact are also important techniques. Team members should be aware of how they are expressing themselves, both through what they say and what they do not say.
  • Presentations: the formal delivery of information and/or documentation to stakeholders.

Interpersonal and team skills

Active listening involves techniques such as acknowledging, clarifying, confirming, understanding, and removing barriers that adversely affect understanding, and it can be used to reduce misunderstandings and other communication deviations with stakeholders. Conflict management starts from the fact that “conflict is inevitable in a project environment”, and “conflict should be addressed early and usually in private, using a direct, collaborative approach.” Cultural awareness is seeing the differences among individuals, groups and organizations and adjusting the communication strategy to them, which builds trust and respect. Meeting management means preparing and distributing an agenda that states the objectives, starting and finishing at the published time, ensuring the appropriate participants are invited and attend as scheduled, staying on topic, managing expectations, issues and conflicts during the meeting, and recording all actions along with the person responsible for completing each one. Networking is “the establishment of connections and relationships with other people from the same or other organizations for the purpose of exchanging information and developing contacts”, which helps solve problems, influence the actions of stakeholders and increase stakeholder support for the project. Political awareness helps the project manager plan communications based on the project environment and the organization's political environment.

Two exam judgments

First, when communication goes wrong, start with the communications management plan. Suppose the functional manager asks for a weekly email update and the sponsor asks for a weekly meeting to report performance. The two requests differ, and the communication problem could endanger project success. The project manager should not escalate straight away, nor patch things up one person at a time. The project manager follows the communications management plan so that each party is kept informed in a timely way as agreed. If a stakeholder's information needs or the original communication method really have changed, first analyze whether the change is necessary and what it affects, and then update the plan appropriately. A request outside the plan should not be taken in without analysis.

Second, sent is not the same as received, and certainly not the same as understood. The customer representative complains of not receiving the deliverable, while the team member says the delay was already announced by email. Email is push communication, and push communication “ensures that the information is distributed but does not ensure that it reaches or is understood by the intended audience.” What the project manager should do is confirm that the representative has received and knows about the delay, not ban members from contacting the customer, send the notice personally, or hand over a half-finished product.

Worked examples

Example 1 Different requests: check the plan first

Question 1Example

A project is in execution, and the communications management plan already documents each stakeholder's information needs. The functional manager reports not receiving the information needed and asks the project manager for a weekly email status update. The sponsor asks instead for a weekly meeting to report project performance. The project manager judges that if the communication problem is not resolved, the success of the project will be seriously threatened. What should the project manager do?

Show answer and explanation

Correct answer: D

The project is in execution and the communications management plan already documents each stakeholder's information needs. The functional manager wants weekly emails and the sponsor wants a weekly meeting. The two requests differ, and the communication problem could seriously threaten project success.

Manage Communications means collecting, creating and distributing information according to the communications management plan. When communication goes wrong, go back to the plan first: it records each stakeholder's information needs, frequency and method. The project manager keeps the functional manager and the sponsor informed in a timely way as the plan describes. If the plan does not match the two latest requests, the project manager should first analyze whether the change is necessary and what it affects, then update the plan appropriately under the applicable change control. The answer is D.

Why the other options are wrong

  • A. Communication is the project manager's own responsibility, and nothing suggests the problem is beyond the project manager's authority. Escalating immediately avoids that responsibility.
  • B. A communication model describes how information is encoded, transmitted, decoded and answered. It explains the transfer process but does not say what each stakeholder needs or how each should receive it.
  • C. Serving one party and ignoring the other has no basis. First check the plan to see what was agreed and whether it needs updating, rather than choosing between stakeholders on the spot.

Key takeaway When communication goes wrong during execution, look at the communications management plan first, then manage communications according to it.

Variation If the plan does not contain the functional manager's needs, first discuss those needs and then update the plan. If Monitor Communications finds the plan was not carried out, do the missed communication as planned and find out why.

Something wrong with this question?

Report an issue with this question

Example 2 The email was sent, but the customer says it never arrived

Question 2Example

A customer representative complains of not receiving an important deliverable that was agreed in the plan. The responsible team member says the representative was already told by email that delivery would be delayed. What should the project manager do to keep this from happening again?

Show answer and explanation

Correct answer: B

A customer representative complains of not receiving an important deliverable agreed in the plan, while the team member says an email already announced the delay. The question is how to keep this from happening again.

Email is push communication. It proves that information was sent, not that it was received or understood. The representative claims not to have known, so the communication loop was never closed. To prevent a repeat, confirm that the stakeholder has received and understood the delay, and resend or change the method when confirmation is missing. The answer is B.

Why the other options are wrong

  • A. Whether members may contact the customer directly is not the issue. Whoever sends the message, the receiver's awareness must be confirmed, and banning direct contact does not solve that.
  • C. Delivering a partial product changes what is delivered. It has nothing to do with the communication problem of announcing the delay, and the customer still does not know which part will be delivered when.
  • D. Whether a member or the project manager sends the notice, receipt and correct understanding still have to be confirmed. Changing the sender does not close the loop and does not prevent the problem at its source.

Key takeaway Sent is not delivered. For critical information or communication that requires a closed loop, confirm that the other party knows. The communications management plan should specify how receipt will be confirmed when needed, especially for push communication.

Variation If the member explained the delay in person, still verify through the listener's paraphrase or explicit confirmation that it was received and understood; telling someone face to face does not by itself guarantee this will not happen again. If the email went to a whole customer department, still confirm that the specific person responsible knows.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Manage Communications is carried out according to the communications management plan, not by sending information at random. When needs or methods change, analyze first and then update the plan appropriately. A request outside the plan should not be taken in without analysis.
  • A meeting is a form of interactive communication and one of the tools and techniques. Do not equate “holding a meeting” with Manage Communications itself.
  • Communication skills (what a person can do) are not the same as communication technology (the tools).
  • Feedback supports interactive communication; it is not a one-way notice. Sending an email does not mean communication is complete.

Key takeaways

Key point

  • Manage Communications: ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and ultimate disposition of project information.
  • Inputs include the communications management plan and work performance reports; the outputs are project communications, plus updates to the communications management plan, the stakeholder engagement plan and others.
  • Communication skills fall into three kinds: oral, visual and electronic. Feedback and nonverbal communication are the points to focus on.
  • Active listening, conflict management, cultural awareness, meeting management, networking and political awareness are the common interpersonal skills.
  • When communication goes wrong, follow the communications management plan first. For critical push communication or communication that requires a closed loop, confirm that the other party has received and understood it.

Lesson 2

Project Reports, Meetings and Information Sharing: Including Reporting in Agile Settings

Lesson video

Lesson overview

The most routine work in Manage Communications is writing reports, holding meetings and sharing information inside and outside the team. This lesson begins with project reports and work performance reports: how to adjust level, format and detail for different audiences, and how to use red-amber-green status indicators without misleading anyone. It then covers meeting management and information sharing inside the team. Finally it covers agile and hybrid environments, where status is displayed openly on information radiators, and where, when reporting to management and to people unfamiliar with agile, you explain rather than avoid. ECO: People domain, Task 6 (Manage stakeholder expectations) and Task 8 (Plan and manage communication). Reports and information sharing are both ways of letting others see progress.

Project reports

“Project reporting is the act of collecting and distributing project information. Project information is distributed to many groups of stakeholders and should be adapted to provide information at an appropriate level, format, and detail for each type of stakeholder. The format may range from a simple communication to more elaborate custom reports and presentations. Information may be prepared regularly or on an exception basis.”

Several practices follow from this. For executives, provide a summary that highlights key indicators and exceptions; for an operations team, provide details and operating steps. The same data can be split into a summary version and a detailed version and provided to each audience as needed. The form of a report should help the reader grasp the information faster and make decisions more easily.

Work performance reports are “the physical or electronic representations of work performance information compiled in project documents, which are intended to generate decisions, actions, or awareness.” They are sent to stakeholders according to the communications management plan, and they are an input to Manage Communications.

Writing a status report: red-amber-green indicators and candor

“Dashboards often include information displayed as stoplight charts (also known as red–amber–green [RAG] charts), bar charts, pie charts, and control charts. A text explanation can be used for any measures that are outside the established thresholds.” The meaning of red, amber and green should be agreed in writing, for example green meaning within the threshold, amber meaning close to the threshold and needing attention, and red meaning the threshold has been exceeded, together with a note, so that different people do not read the colors differently.

A status report should be complete and also forward-looking. Imagine a warehouse system project originally planned for 10 months and extended to 14. At month 8 the cost savings are already above target, but some of the features planned to be live by then are not. In reporting to stakeholders, you cannot say only that “the features were not completed on schedule”, you cannot wait until everything is finished, and you cannot just send a progress email. You explain the benefits already realized, the benefits expected from the features still to go live, and the action plan to close the gap, so that the audience understands the true state of cost and schedule and can form a judgment from it.

Meetings and information sharing inside the team

Meeting management works like this: prepare and distribute an agenda stating the objectives; start and finish at the published time; invite the appropriate participants and make sure they attend; stay on topic and bring discussion back when it drifts; manage expectations, issues and conflicts during the meeting; and record all actions along with the individual who has responsibility for completing each action. After the meeting, confirm key communications in writing and file them, which is a good way to leave a record.

Sharing information inside a team depends on clear, consistent channels and agreements. When several groups work in parallel, hold regular meetings to share key information and anticipate problems. Keep the document repository updated continuously at the iteration cadence so it reflects the latest status. Set up a single information portal or directory to make access easy. The project manager should also remind each group lead to inform the project manager, as the plan requires, before sharing information with stakeholders, so that contradictory messages do not appear.

Agile and hybrid environments: information radiators

Agile and hybrid environments typically emphasize open, frequently updated status displays rather than relying only on lengthy reports. “An information radiator is a visible, physical display that provides information to the rest of the organization, enabling timely knowledge sharing. Information radiators may also be known as big visible charts. Information radiators are posted in a place where people can see the information easily, rather than having information in a scheduling or reporting tool. The information radiators should be easy to update and should be updated frequently. They are often “low tech and high touch” in that they are manually maintained rather than electronically generated.” They can show work completed, work remaining and risks. In lean environments, information radiators are known as visual controls. Kanban boards and burndown charts are commonly treated as typical forms of information radiators (common exam practice).

The benefit is transparency: stakeholders do not have to wait for a report or call a separate meeting, and can see progress themselves at any time. When a business owner wants a central place where stakeholders can check project progress themselves, the right move is to set up an online collaboration site or board; it gives stakeholders the same self-service transparency, especially in a distributed setting. The wrong moves are to write a detailed document for every iteration, hold one-on-one meetings one by one, or invite everyone to each daily coordination meeting.

When reporting to management and to people unfamiliar with agile, explain rather than avoid. After a transformation, senior leaders may still want the information in the old reports and dashboards, much of which no longer applies. The project manager should help them understand how the change affects the usefulness of certain reports and metrics, which still make sense and which no longer apply. Do not simply say “there are no reports in agile”, and do not make senior leaders learn it on their own first. For executives who worry that the team “does not document and does not report progress”, introduce the basics of agile and show progress with metrics such as burndown charts and velocity and with public information radiators.

Worked examples

Example 1 Behind schedule but ahead on benefits: how to report

Question 1Example

A project manager is leading a warehouse system project for a logistics company, with the goal of reducing operating costs. The project was planned for 10 months but has been extended to 14 months because of various problems during execution. At the end of month 8, the expected cost savings have been exceeded, but not all the features planned to be live by that date have gone live. How should the project manager report progress to stakeholders?

Show answer and explanation

Correct answer: B

During execution, a warehouse system project planned for 10 months has been extended to 14. At the end of month 8, cost savings are ahead of target, but some features that should be live by now are not. The question asks how to report progress to stakeholders.

Status communication should be complete and forward-looking: it lets stakeholders see that cost savings have been exceeded, honestly explains that some features are late, and says how the rest will be completed. Then they understand cost and schedule clearly and can form their own judgment. The answer is B.

Why the other options are wrong

  • A. Saying only that features were not completed on time leaves out the savings already achieved and any follow-up arrangements. The information is one-sided.
  • C. Waiting until the work is done to report leaves the sponsor uninformed for a long time, violates the requirement for timely communication, and may delay the project further.
  • D. A fixed monthly email of schedule and cost data may not respond to the immediate need to report progress, and it does not clearly cover the savings beyond target, the impact of the delayed features or the follow-up plan. Push email is not wrong in itself, but here it is less complete and less timely than B.

Key takeaway A status report must explain results, delays and the follow-up plan. It should not report only the gap, and it should not wait until the work is done.

Variation If costs were also over budget, report that honestly too and attach the response plan. If executives want a brief summary, tailor the report to the audience by highlighting key indicators and exceptions.

Something wrong with this question?

Report an issue with this question

Example 2 A business owner wants to check progress on a self-service basis

Question 2Example

The business owner of an agile team wants one central place where stakeholders can check project progress themselves. What should the agile practitioner recommend?

Show answer and explanation

Correct answer: C

On an agile project, the business owner wants a central place where stakeholders can check progress for themselves. The question asks what the agile practitioner should recommend.

Agile stresses transparency. An information radiator is a visible display placed where people can easily see it and easy to update, so stakeholders need not wait for reports or call separate meetings. An online collaboration site or board that shows progress in one place lets the business owner and other stakeholders look for themselves at any time. It works like an information radiator in a distributed setting: everyone can see progress in one place at any time. The answer is C.

Why the other options are wrong

  • A. Publishing only at the end of the iteration is not timely enough. A detailed document costs more to maintain and is less convenient for self-service than a continuously updated central board.
  • B. One-on-one meetings take up time person by person and are not a central place where everyone can check progress themselves.
  • D. The daily coordination meeting is a team synchronization, not an information entry point for stakeholders, and it leaves no place to look things up at any time.

Key takeaway For stakeholders to check progress themselves, build a central, open, always-available visual channel: a physical board, or an online collaboration board for distributed teams. Do not rely on one meeting or report at a time.

Variation If the team is co-located, the physical board can go up in the corridor. If the question asks about reporting to management unfamiliar with agile, besides the board also explain metrics such as burndown charts and velocity.

Something wrong with this question?

Report an issue with this question

Example 3 Senior leaders still want the old reports after the move to agile

Question 3Example

A manufacturing company is moving several of its projects to an agile approach. After the transition, senior leaders still ask for the information that used to come from the old reports and dashboards, but much of it no longer applies. What should the project manager do?

Show answer and explanation

Correct answer: B

A company moves several projects to agile. Afterward, senior leaders still ask for the information in the old reports and dashboards, much of which no longer applies. The question asks what the project manager should do.

Senior leaders ask for the old information because they do not yet understand what the transition changes. The project manager should help them understand how the move to agile affects the usefulness of certain reports and metrics, which ones still mean something and which no longer apply, and show progress through information radiators, burndown charts and the like. This respects management's information needs and also wins their acceptance of the new way of reporting. The answer is B.

Why the other options are wrong

  • A. This overgeneralizes. Agile does have reports and dashboards, only in different forms and content. Flatly denying them will only make senior leaders more dissatisfied.
  • C. A self-managing team does not mean no reporting. Agile also requires transparent progress for stakeholders, so this claim is wrong and invites resistance.
  • D. Pushing the responsibility to learn onto senior leaders does not help them understand, communicates poorly, and is not the proactive approach expected of a project manager.

Key takeaway After a move to agile, reporting content changes. The project manager helps management understand the change instead of rejecting or avoiding it.

Variation If executives worry that the team is “not documenting and not reporting progress”, explain agile basics and show progress through metrics such as burndown charts and velocity and through public information radiators. If the question is whether to write one more weekly report, first let them look for themselves.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Reports adjust level, format and detail to the audience. Sending the same report to everyone does not meet the requirement.
  • A status report should be truthful, complete and forward-looking. Reporting only the gap, waiting until the work is done, or sending just one short note are all wrong.
  • When management wants more status information, do not simply write more reports. Let them see progress for themselves, and explain the agile basics behind the metrics.
  • An information radiator goes where people can easily see it and is easy to update. It is usually a manually maintained “low tech and high touch” tool, not an electronically generated report.

Key takeaways

Key point

  • Project reporting: collecting and distributing project information, adapted in level, format and detail to each type of stakeholder, and prepared regularly or on an exception basis.
  • The meaning of red-amber-green indicators should be stated in writing, and a text explanation can accompany any measure outside its threshold.
  • A status report should be truthful, complete and forward-looking; in this lesson's scenario, it should explain what has been achieved, the expected benefits of the unfinished features and the plan going forward.
  • Meetings need an agenda, a published start and finish time, and recorded actions with owners.
  • Information radiators are visible, physical, easy to update, and posted where people can see them. Agile reporting relies on transparency and self-service, and with management you explain the metrics.

Lesson 3

Monitor Communications: Checking Whether Information Needs Are Met

Lesson video

Lesson overview

After the communications management plan is running, you have to look back and check whether information went out as planned, whether the other party really received and understood it, and whether needs have changed. That is Monitor Communications, which belongs to the monitoring and controlling focus area. Exam questions on this topic follow a narrow pattern: the same problem comes up again, or someone is still unhappy although communication followed the plan, and the question asks what the project manager should do. This lesson covers the purpose, inputs and outputs of the process, how to compare plan with actual, the approach of analyzing first and acting second once a problem appears, and how the process divides the work with Monitor Stakeholder Engagement. ECO: People domain, Task 8 (Plan and manage communication) and Process domain, Task 9 (Evaluate project status), which includes communicating project status.

Definition, inputs and outputs

“Monitor Communications is the process of ensuring the information needs of the project and its stakeholders are met. The key benefit of this process is the optimal information flow as defined in the communications management plan and the stakeholder engagement plan. This process is performed throughout the project.”

ItemContents
InputsResource management plan, communications management plan, stakeholder engagement plan; issue log, lessons learned register, project communications; work performance data; enterprise environmental factors; organizational process assets
Tools and techniquesExpert judgment; project management information system; data representation (stakeholder engagement assessment matrix); interpersonal and team skills (observation/conversation); meetings
OutputsWork performance information; change requests; project management plan updates (communications management plan, stakeholder engagement plan); project document updates (issue log, lessons learned register, stakeholder register)

Note the input “project communications”. It is an output of Manage Communications and records what was actually sent, and Monitor Communications compares it with the communications management plan. Among the outputs, work performance information comes from the analysis of work performance data, and when a problem is found a change request may be raised, which can include a corrective action or a preventive action.

How to monitor: compare, find the gap, find the cause

The core of Monitor Communications is to compare plan with actual. The plan says what is sent to whom on which day, and the records show whether it was done and how well. For example, if the plan calls for an in-person briefing on Monday, an email on Wednesday and a status meeting on Friday, and Friday's meeting was not held, that is a deviation. Besides checking whether it was done, use observation and conversation to see whether it worked: whether the other party received it, understood it, and still has unmet needs. The stakeholder engagement assessment matrix can be used to compare what has been observed with the expected levels of engagement.

Figure 1 The communications management cycle

After a problem is found, common exam practice is to analyze first and then act. Analysis includes assessing whether the stakeholder's communication needs have changed, finding the gap against the current plan, and doing a root cause analysis. After analysis you decide on a corrective action. If the communications management plan or another controlled artifact must be changed, raise and process the change according to the development approach in use and the change management plan and configuration management plan, and update it once approved or confirmed. Making up a communication that was missed is a corrective action. The change request that results can contain corrective or preventive actions taken to make communication more effective and to meet information needs, and the plan component most likely to need updating is the communications management plan.

Division of work with Monitor Stakeholder Engagement

The two monitoring processes come as a pair. Monitor Stakeholder Engagement looks at people: it assesses the effectiveness of engagement efforts and adjusts the engagement strategies and plans. Monitor Communications looks at information: it confirms that the flow of information meets needs. The PMBOK 8 table of outcome checks also says, for “communications management is performed”, that the check is to “review the communications management plan periodically and tailor it appropriately based on the needs of stakeholders.”

Two typical scenarios

The same problem comes up again. An external expert reports being unable to open the knowledge base pages. The team replies that the client application needed for access has been upgraded and sends him the new version. Later, at an all-stakeholder meeting, he raises the same problem. The previous communication did not work: the team only sent software and never confirmed that he could use it. The project manager should first talk with him and find the specific sticking point (it could be installation, permissions, compatibility or the network), and then deal with the root cause. Only if it turns out he is unfamiliar with the new client application should training be given. Sending the installer again, suggesting the old version or bypassing the client application all repeat or avoid the earlier approach.

Communication followed the plan, but someone is still unhappy. On a supermarket inventory system upgrade, a key stakeholder complains that the performance variances in the reports make the project look out of control. The project manager has always provided status according to plan, and this stakeholder rarely attends the status meetings. Proving that the plan was followed is no answer. First assess his communication needs, find the gap against the current plan, and adjust the communications management plan if necessary, because the plan itself may not suit him, and the problem may not be only whether it was carried out.

Worked examples

Example 1 The same problem comes up a second time

Question 1Example

An external expert on a project reports being unable to open the project knowledge base pages and asks the team for help. The team replies that the client software needed for access has been upgraded and sends him the new version. Later, at an all-stakeholder meeting, he raises the same problem again. What should the project manager do?

Show answer and explanation

Correct answer: A

An external expert cannot open the knowledge base pages. The team replied that the client had been upgraded and sent the new version, yet at an all-stakeholder meeting he raised the same problem again. The project manager must deal with it, and this is the handling that follows a problem found in Monitor Communications.

When the same problem comes back, the previous communication did not work: the team only replied and sent software and did not find out where he was stuck. Monitor Communications calls for analyzing first and then acting, so the project manager should first talk with him to find the sticking point, and then provide support for that cause (for example, training on the new client if he turns out to be unfamiliar with it). That is what actually solves the problem. The answer is A.

Why the other options are wrong

  • B. Continuing with the old version avoids the problem without finding the sticking point or addressing why the communication fell short.
  • C. Sending the installer again repeats what was done last time. Without finding the sticking point, the cause stays and the problem will return.
  • D. Going around the client avoids the problem, does not fix the root of the failed communication, and adds extra work.

Key takeaway When the same problem returns, the last communication did not work. Find the sticking point instead of repeating the earlier action.

Variation If the expert says “I never receive the email”, check the distribution arrangements and mailbox settings. If he says “I cannot make sense of the report”, adjust the report format to his needs and update the communications management plan.

Something wrong with this question?

Report an issue with this question

Example 2 Communication followed the plan, but the stakeholder is still unhappy

Question 2Example

The sponsor of a chain-supermarket inventory system upgrade reports that a key stakeholder complains that the performance variances in the project manager's reports give the impression that the project is out of control. The project manager has always provided status according to the agreed communications management plan, and this stakeholder rarely attends the status reporting meetings. What should the project manager do FIRST?

Show answer and explanation

Correct answer: D

The sponsor relays that a key stakeholder complains that the performance variances make the project look out of control. The project manager has always given status according to plan, and this stakeholder rarely attends the status meetings. The question asks what to do first.

Monitor Communications confirms whether information needs are really met, not merely whether information was sent as planned. This stakeholder seldom attends, so the current channel may not suit them, and the plan itself needs checking. The project manager should first assess the stakeholder's communication needs, identify the gaps against the current plan, and adjust the communications management plan if needed, after which the project status can be clarified effectively. The answer is D.

Why the other options are wrong

  • A. The stem has not shown that the schedule really is behind or analyzed which activities could run in parallel. Fast-tracking rashly adds rework and risk and does nothing about the mismatch between needs and channel.
  • B. The stakeholder may not appear in a resource breakdown structure, and a complaint is no reason to have someone replaced. It is not an active attempt to solve the communication problem.
  • C. Proving to the sponsor that communications went out does not address the stakeholder's unmet need. It only defends the project manager.

Key takeaway If someone is dissatisfied even though communication followed the plan, assess their needs and find the gaps first, and adjust the plan if necessary.

Variation If he attends every meeting yet still says he did not receive it, check the content and format of the information. If he is a newly added stakeholder, update the stakeholder register and analyze his needs together, then update the relevant plans.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Monitor Communications checks whether information needs have been met, not whether “I sent it”. Information sent according to plan can still fail to meet the need.
  • When a problem is found, analyze the cause first, then update the communications management plan or raise a change request. Do not start by changing tools, escalating or replacing people.
  • Monitor Communications looks at information flow, and Monitor Stakeholder Engagement looks at the level of engagement. Their inputs and outputs are similar, but their objects differ.
  • Repeating an approach that has already proved ineffective will not solve the problem.

Key takeaways

Key point

  • Monitor Communications: ensuring the information needs of the project and its stakeholders are met, performed throughout the project.
  • Inputs include the communications management plan and project communications; outputs are work performance information, change requests, and updates to the communications management plan and others.
  • Method: compare plan with actual, assess effectiveness through observation and conversation, and analyze before acting.
  • When the same problem recurs or someone is unhappy despite communication following the plan: assess the needs, find the gap or sticking point, and adjust the plan if necessary.
  • It pairs with Monitor Stakeholder Engagement: one looks at information, the other at people's engagement.

Lesson 4

Tailoring Communication and Common Scenarios: Virtual Teams, Time Zones and External Stakeholders

Lesson video

Lesson overview

The same communications management plan cannot be used as is on every project. The team may be spread over several countries, members may speak different languages, some stakeholders may be outside the organization, and some projects are agile. PMBOK 8 requires communication activities to be tailored to the project. This lesson begins with tailoring considerations and the three official examples. It then turns the kinds of communication scenarios that keep appearing in the exam into rules: virtual teams, time zones, cross-cultural settings, external stakeholders, and what to do first when communication barriers arise. ECO: People domain, Task 8 (Plan and manage communication).

Tailoring considerations

“Because each project is unique, activities and processes in the Stakeholders performance domain should be tailored.” Considerations related to communication include the following.

  • Organizational culture. “Flat organizations tend to rely on open communications and foster informal channels, whereas hierarchical organizations use more formal approaches. The entire communication and stakeholder engagement strategy should consider organizational culture in order to properly engage with stakeholders.”
  • Product. “Products that allow or require interactive, incremental, or event-exploratory approaches usually bring a specific framework for stakeholder interactions. For example, the software industry created common events (also known as ceremonies) such as product reviews, planning sessions, and project retrospectives, among others, to update and engage stakeholders.”
  • Large language models (LLMs) and artificial intelligence (AI). “The use of AI should be assessed for each project through a decision-making process to determine when AI can assist with tasks or provide more time for other valuable activities.” When AI is used to produce artifacts for communication with the sponsor, stakeholders, team and vendors, “proactive security and ethics measures should be considered, such as project managers engaging with the appropriate stakeholders (e.g., the cybersecurity team, if applicable), to understand if the risk of incorporating AI is acceptable for the organization.”

The three official examples are these. An agile project needs continuous feedback on features and user stories, so teams usually hold daily coordination meetings and use dedicated communication platforms for real-time collaboration and information sharing. A manufacturing project implementing a large-scale enterprise resource planning (ERP) system disseminates formal project updates through biweekly email newsletters and monthly town hall meetings to ensure alignment across hierarchical levels. A medium-sized global project requires inclusive communication strategies, so multilingual updates and monthly virtual forums help ensure engagement and feedback from stakeholders across different cultural backgrounds.

Virtual teams and time zones

When a team is spread across several countries and time zones and works in different languages, the risk of misunderstanding rises noticeably. Common exam practice is as follows.

  • Revise the communications management plan to take regional differences into account. Arrange meeting times, language and channels in one place. This is more systematic than any single training course or workshop.
  • Accommodate time zones. Hold meetings in the core overlap hours when everyone is working. Rotate synchronous meetings to share the inconvenience among time zones, and give those who miss a meeting the minutes. Use more asynchronous communication and agree on response times.
  • Use online tools to raise transparency. When an agile team is spread over several time zones, an online board lets every member see how feature development is going at any time. Each region first holds its local daily coordination meeting, followed by a short overall status meeting.
  • Keep channels reliable and secure. Use audio and video products with passwords for meetings, and choose tools that allow real-time communication.
  • Confirm understanding. Express things concisely and clearly, and confirm that key information has been understood.

Cultural differences also go into the plan. Cultural awareness is “an understanding of the differences among individuals, groups, and organizations and adapting the project's communication strategy in the context of these differences.” For example, a nod means agreement in some countries and disagreement in others. In some cultures members are reluctant to object in public, so you can set up an anonymous feedback channel outside meetings and talk with members one-on-one in private to learn their real concerns.

External stakeholders and outsourcing

External stakeholders (customers, suppliers, industry associations, the media, outsourced teams) are not under the project manager's direct command, so communication relies on agreement. In communication requirements analysis, PMBOK 8 lists external information needs (for example, when communicating with the media, the public or contractors) as one of the sources for identifying communication requirements. Common exam practice also includes agreeing the rules for communicating with the customer with the outsourcing lead, arranging for a local resource to help the technical lead communicate with the customer, and agreeing a single external point of contact.

When barriers arise, what to do first

Suppose an expert on a virtual team keeps failing to cooperate and collaboration is repeatedly blocked, or communication inside the team is poor and information does not keep up. The order for these scenarios is as follows (common exam practice). First compare with the communications management plan to see whether the delivery of information, the methods and the channels were agreed and whether they were carried out. Next analyze communication needs, environment and tools to find the root cause of the barrier. Then revise the plan and collect members' feedback on communication regularly, discussing improvements together. Only last do you consider replacing people or escalating. “Consult the communications management plan” and “analyze communication needs, environment and tools” can each be worded as “first” in a question, so read the stem to see which step it asks for.

Worked examples

Example 1 How can an international team reduce misunderstandings

Question 1Example

The resource management plan has been completed. Team members are spread across four countries, span multiple time zones, and work in different languages. The project manager wants the team to run smoothly and to reduce the harm that misunderstandings arising from this could do to the project. What should the project manager do?

Show answer and explanation

Correct answer: A

The resource management plan is complete. Team members are spread across four countries, several time zones and different working languages, and the project manager wants the team to run smoothly and to limit the damage misunderstandings could do.

Time zones, languages and cultural differences all affect communication. The communications management plan is the document that says how communication is planned, carried out and monitored. Writing the regional differences into it and arranging meeting times, language and channels in one place is how misunderstandings are reduced systematically, and it is exactly what tailoring communication to the project means. The answer is A.

Why the other options are wrong

  • B. A management training course has no direct bearing on communication differences and does not reduce misunderstanding.
  • C. A cultural awareness workshop can improve understanding, but it does not solve the scheduling problems of time zones and language. It handles only part of the issue.
  • D. The political environment is only one aspect of the differences. Discussing it strays from the point and does not address time zones or language.

Key takeaway For teams spread across regions, time zones and languages, revising the communications management plan to arrange things in one place is more complete than any single training.

Variation If the stem said only that members do not understand each other's cultures, a cultural awareness activity would fit better. If the question is how to set meeting times, choose the core overlap hours when everyone is working and provide minutes for those who miss it.

Something wrong with this question?

Report an issue with this question

Example 2 An agile team across time zones

Question 2Example

The agile team of a large platform software project is spread across several time zones, and communication among team members is especially important. As an agile coach, how should you help the team communicate successfully?

Show answer and explanation

Correct answer: C

The agile team of a large platform software project is spread across several time zones, and communication among members is particularly important. The question asks how the agile coach should help the team communicate successfully.

An agile team in different time zones should use online collaboration tools to promote transparent, thorough communication. An online board lets all members see the progress of feature development at any time, regardless of time zone and without relying on live meetings, which is typical remote collaboration practice. Agile values transparency, and putting progress where everyone can see it reduces misunderstanding better than daily emails. The answer is C.

Why the other options are wrong

  • A. Daily emailed reports are not absolutely unusable, but the information is scattered and one-way, with less transparency and collaboration than a shared online board.
  • B. Splitting deliverables by time zone guarantees communication only within each region. The communication problem for the whole team remains.
  • D. Building in some overlapping working hours can support synchronous communication, but asking each member to shift their own hours puts the burden on individuals and gives the team no shared view of progress. An online board gives all members continuous access to the same progress information across time zones, so C fits better.

Key takeaway For an agile team across time zones, use collaboration tools such as an online board for transparent communication.

Variation If the question is how to schedule synchronous meetings, choose the core overlap hours when everyone is working and rotate the inconvenience among time zones. If the question is how new members keep up, rely on the board, minutes and asynchronous communication.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When you meet a communication problem, do not start by changing tools, sending emails, escalating or replacing members. First check whether the communications management plan covers it and, if needed, update it after analyzing the needs.
  • For problems across time zones and languages, revising the communications management plan to arrange things in one place is more complete than holding a single training course or workshop.
  • An agile team's communication relies on transparent shared information, with real-time collaboration where useful, rather than relying only on daily emailed reports.
  • Before AI generates communication material, assess whether that is appropriate and consider security and ethics. It is not simply “use it if you want to”.

Key takeaways

Key point

  • Communication varies by project: organizational culture, the product and the use of AI are all tailoring considerations.
  • The three official examples: daily coordination meetings and real-time platforms on an agile project; biweekly email newsletters and monthly town halls on a manufacturing project; multilingual updates and monthly virtual forums on a global project.
  • For teams spread over locations, time zones and languages: revise the communications management plan, accommodate time zones, raise transparency with online boards or collaboration tools, and confirm understanding.
  • External stakeholders: build their information needs into the plan (PMBOK 8); agreeing rules and contacts for external communication is common exam practice.
  • When barriers arise (common exam practice): compare with the communications management plan first, then analyze needs, environment and tools to find the root cause, then revise. Do not replace people or escalate first.

This chapter has 61 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.