Responsibility Assignment Matrix and RACI

PMP · Resources and Team · 3 lessons · about 35 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

The first process in the Resources performance domain is Plan Resource Management, the process of defining how to estimate, acquire, lead, and utilize physical, virtual, or team resources. It answers three questions: how resource arrangements are determined, who is responsible for each piece of work, and where these arrangements are written down and how they are carried out. (Which resources the project needs, and how many, is answered by the later Estimate Resources process.) The chapter has three lessons. The first covers what the process does, the three kinds of resources, the three hierarchical charts (WBS, OBS and RBS), and the four terms role, authority, responsibility and competence. The second covers the tool the exam tests most, the responsibility assignment matrix and RACI. The third covers what is in the resource management plan and how to use it when roles are unclear, skills are missing or rules are disputed.

In the exam, scenarios such as “members do not know their responsibilities”, “people pass the buck”, “several people assign work to the same member” and “a skill gap is found during planning” usually have their answer in the tools and documents of these three lessons. If responsibilities are already clear and members still pass the buck, you also have to bring in processes such as Lead the Team.

Lessons in this chapter

Chapter map

Plan Resource Management

  • Resources: team · physical · virtual (Acquire Resources covers all three; Monitor and Control Resourcing covers physical and virtual resources; external resources can be obtained through procurement, see Lesson 1)
  • Hierarchical charts: WBS (deliverables) · OBS (departments) · RBS (resource categories and types); text-oriented formats
  • Responsibility assignment matrix: RACI (responsible · accountable · consulted · informed), one A per activity
  • Output: resource management plan (identification of resources, acquiring resources, roles and responsibilities, project organization chart, project team resource management, training, team development, resource control, recognition plan; PMBOK 8 lists nine contents, which may include but are not limited to these, including “project team resource management”) + team charter

For practice on this chapter, use the chapter exercises; do the core questions first, then the required ones.

Lesson 1

Plan Resource Management: Resource Types, Hierarchical Charts and Roles and Responsibilities

Lesson video

Lesson overview

The first process in the Resources performance domain is Plan Resource Management. It answers three questions: how resources are estimated, acquired, led and utilized, who is responsible for each piece of work, and where these arrangements are written down and how they are carried out. This lesson begins with what the process does and what kinds of resources there are. It then covers the three hierarchical charts and text-oriented formats, and finally the four terms role, authority, responsibility and competence, together with how management style changes. The root of exam scenarios such as “members do not know what they should do” and “nobody noticed the skill gap” is here. The next lesson covers the tool the exam tests most, the responsibility assignment matrix and RACI.

What Plan Resource Management does

PMBOK 8 defines Plan Resource Management as the process of defining how to estimate, acquire, lead, and utilize physical, virtual, or team resources. Its key benefit is that it “establishes the approach and level of management effort needed to manage project resources based on the type and complexity of the project.” “This process is performed once or at predefined points in the project. Resource planning is used to determine and identify an approach to ensuring that sufficient resources are available for the successful completion of the project. Effective resource planning should consider and plan for the availability of—or competition for—scarce resources.” The specific tools and techniques include the responsibility assignment matrix, organizational theory, green human resource management, resource-based view, and SWOT analysis.

There are three kinds of resources: team resources, meaning the project team members; physical resources, such as equipment, materials, facilities and supplies; and virtual resources, such as software, testing environments and licenses. In PMBOK 8, Acquire Resources covers team, physical and virtual resources, while Monitor and Control Resourcing covers physical and virtual resources (team performance is managed in Lead the Team). Internal resources are acquired (assigned) from functional or resource managers, and external resources are obtained through partnerships, joint ventures or procurement processes (see Plan Sourcing Strategy and Appendix X4 on procurement). That is why the resource manager (“an individual with management authority over one or more resources”) and the project manager are two different roles: the project manager leads the team, internal resources are usually assigned by functional or resource managers, and whether the project team has direct control over resource selection depends on the organizational structure and governance arrangements.

Resource requirements are determined from scope, work packages and activities (PMBOK 8: resource requirements identify the types and quantities of resources required for each work package or activity in a work package), and the schedule shows further when those resources are needed. So the inputs to Plan Resource Management are things such as the project charter, scope baseline, project schedule, requirements documentation, risk register and stakeholder register, and the outputs are the resource management plan and the team charter, with updates to the assumption log and risk register where needed. Skill gaps should be identified early in resource planning and reviewed and updated throughout the project with a skill matrix.

Worked example

On a store checkout system upgrade, the project manager compares the schedule during planning and finds that data migration will be needed in month 4, and nobody on the current staff has done it. At this point the project manager should write “data migration skills” into the resource requirements and arrange training or outside support in the resource management plan, instead of waiting until month 4 when the activity cannot start and then scrambling.

Hierarchical charts and text-oriented formats

Hierarchical charts are top-down breakdowns used to show positions, responsibilities or resources. The exam tests three, and they differ only in what they break down by.

ChartBroken down byQuestion it answers
Work breakdown structure (WBS)DeliverablesWhat is to be delivered
Organizational breakdown structure (OBS)Departments, units or teamsWhich department is responsible for which work packages
Resource breakdown structure (RBS)Resource categories and typesWhich resources are needed, and of what type

Per PMBOK 8, an OBS “is arranged according to an organization's existing departments, units, or teams, with the project activities or work packages listed under each department.” An RBS “is a hierarchical representation of resources by category and type. Examples of resource categories include but are not limited to labor, materials, equipment, and supplies. Resource types may include the skill level, grade level, required certifications, or other information as appropriate to the project.” The three charts describe the same project and differ only in what the breakdown is based on.

Figure 1 What the three hierarchical charts break down

Worked example

The WBS of a community elder-care service platform project has three work packages: platform development, home-visit service training and go-live acceptance. Hanging each work package under the responsible department, so that the technology department sees platform development, the operations department sees training and the quality department sees acceptance, gives an OBS. Sorting the resources needed by labor (back-end engineers, training instructors), equipment (servers, tablets) and materials (training manuals), and then by skill grade, gives an RBS.

Responsibilities can be drawn as charts and can also be written in a text-oriented format: responsibilities, authority and competence requirements listed role by role. A matrix is good for seeing at a glance who is involved in which activity, and text is good for spelling out what a role has to do in detail. PMBOK 8 introduces hierarchical charts, the responsibility assignment matrix and text-oriented formats separately, and all of them can be used to express resource roles or responsibility arrangements.

Role, authority, responsibility and competence

When the resource management plan states roles and responsibilities, four terms must be kept apart. Role is “the function assumed by, or assigned to, a person in the project”, such as business analyst or testing coordinator. Authority is “the right to apply project resources, make decisions, sign approvals, accept deliverables, and influence others to carry out the work of the project”, and “team members operate best when their individual levels of authority match their individual responsibilities.” Responsibility is “the assigned duties and work that a project team member is expected to perform in order to complete the project's activities.” Competence is “the skill and capacity required to complete assigned activities within the project constraints.” “When such mismatches are identified, proactive responses such as training, hiring, schedule changes, or scope changes are initiated.”

Resource management style should be adjusted to the situation. When the team knows this kind of project well, it can manage itself to a large degree, and for a completely new kind of project you give more oversight and a more directive style. A predictive project usually fixes its resource needs and plan at the start.

Key point

Plan Resource Management sets the method: how physical, virtual or team resources are estimated, acquired, led and utilized. The specific skills and resources needed are recorded in the resource requirements; consult the resource management plan for the approach to closing gaps and for project-level roles and responsibilities.

Worked examples

Example 1 A predictive project: when to identify skill gaps

Question 1Example

PMLyceum is upgrading the inventory system for its retail stores, using a predictive approach. The project is critical to the company, but during execution the project manager finds that nobody on the team has the specialized data migration skills required, so one deliverable cannot be produced. What should the project manager have done to avoid this?

Show answer and explanation

Correct answer: B

A predictive project is already in execution, but no one on the team knows data migration, so a deliverable cannot be produced. The question asks what should have been done to avoid this, which means looking back at what planning should have covered.

Planning should first identify the team resources and skills the work requires, using the approach set out in the resource management plan, and then decide on recruiting, training or procurement. A predictive project stresses planning up front, so the list of skills should be complete during planning: gaps then show up before work starts, and there is still time to train or add people. “Should have” and “avoid” in the stem point to an action taken beforehand, and identifying all skills during planning fits best. The answer is B.

Why the other options are wrong

  • A. Training must be planned, but what to train depends on which skills are missing. Without the skills list there is nothing to base a training plan on. It is work that follows identifying skills, not the first thing to do.
  • C. Identifying skills as work proceeds leaves gaps to appear only in execution, which is exactly the failure in the stem: the skill is missing and the deliverable cannot be produced.
  • D. Identifying the required skills is planning work led by the project manager and team. The sponsor focuses on business objectives and authorization and does not know the specific technical skill requirements better than the project team, so passing it to the sponsor shirks the duty.

Key takeaway Skill gaps must be identified during planning by the project manager and the team, not found late during execution.

Variation If the gap had been found during planning, first assess its impact and the relevant constraints. Common exam practice is then to address the gap in the resource management plan and arrange training. On an adaptive project, reassess team skills and gaps before each iteration.

Something wrong with this question?

Report an issue with this question

Example 2 Two groups with overlapping responsibilities: which document to check first

Question 2Example

A retail system overhaul project has run into a problem: the work of the inventory synchronization group and the member data migration group partly overlaps, and it is unclear who is responsible for delivering that part, which is already affecting the project. The resource management plan lists each group's roles and responsibilities. What should the project manager do next?

Show answer and explanation

Correct answer: A

The work of the inventory synchronization group and the member data migration group partly overlaps, nobody knows who should deliver that part, and the project is already affected. The resource management plan lists each group's roles and responsibilities. The question is the project manager's next step, which centers on dividing responsibility between teams.

Who is responsible for what is written under “roles and responsibilities” in the resource management plan, which covers role, authority, responsibility and competence. When the two groups' responsibilities overlap, the project manager should consult the plan first. If it is clear, use it to clarify and coordinate execution; if the resource management plan must change, assess and obtain authorization for the change through the applicable change process before updating the plan, notifying the relevant parties, and implementing it. The answer is A.

Why the other options are wrong

  • B. The scope statement says what work is to be done and what is to be delivered. It does not say which group is responsible for which part, so it is the wrong basis for reorganizing teams.
  • C. The WBS breaks scope into work packages and shows what work exists, but it also does not say which group takes it on. It cannot say who owns the overlapping part.
  • D. The overview in the project management plan is not content designed for resource assignment. Resource arrangements are in its subsidiary plan, the resource management plan, which is more specific.

Key takeaway When responsibilities overlap between teams and it is unclear who is responsible, go back to the roles and responsibilities in the resource management plan, not the scope documents.

Variation If the question asked which tool clearly shows how each activity relates to people, the answer would become the responsibility assignment matrix. If it asked whom a new member reports to, the answer would be the project organization chart.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The resource management plan is a guide to “how to manage resources”, not a list of “which resources are needed”. The list comes from Estimate Resources.
  • Identifying skills is the project manager's work in the planning phase and cannot be pushed to the sponsor. Initial skill needs and gaps should be identified early, not deliberately put off until work has started. During the project the skill matrix keeps being updated, and new gaps are identified and closed in Lead the Team.
  • The scope statement and the WBS mainly say what work is to be done. The WBS can show high-level areas of responsibility, but who exactly is responsible should still be checked in the roles and responsibilities of the resource management plan and in the responsibility assignment matrix.
  • In this lesson focus on the three hierarchical charts the exam tests: the WBS breaks down by deliverables (it answers “what is delivered” and does not directly show who is responsible), the OBS by department, and the RBS by resource. PMBOK 8 also lists the value breakdown structure (VBS).

Key takeaways

  1. Plan Resource Management determines how resources are estimated, acquired, led and utilized, and outputs the resource management plan and the team charter.
  2. Resources fall into three kinds: team, physical and virtual. Acquire Resources covers all three; Monitor and Control Resourcing covers only physical and virtual resources (team members are handled in Lead the Team). External resources are obtained through partnerships, joint ventures or procurement.
  3. The WBS breaks down by deliverables, the OBS by department, and the RBS by resource category and type.
  4. Role is the position, authority is the right to decide, responsibility is the work to be done, and competence is the skill needed to do it.
  5. When competence is insufficient, train, hire, change the schedule or change the scope. Skill gaps are identified during planning.
  6. Management style is adjusted to the situation: when the team knows this kind of project well it can manage itself to a large degree, and for a completely new kind of project you give more oversight and a more directive style.

Lesson 2

The Responsibility Assignment Matrix and RACI: One Accountable Person per Activity

Lesson video

Lesson overview

“The same person is given work by three people”, “both people say that job is not theirs”, “when something goes wrong, nobody follows up”: questions like these appear in almost every set of practice exams, and the answer is often the same tool, the responsibility assignment matrix. This lesson covers what it is, what each of the four RACI letters stands for, why each activity may have only one accountable person, and how questions are worded. It is the core tool of Plan Resource Management from the previous lesson, and it is also the basis for “first check whether responsibility is clear” in conflict management and Lead the Team later.

What a responsibility assignment matrix is

“A responsibility assignment matrix is a grid that shows the project resources assigned to each work package. The matrix is used to illustrate the connections between work packages, or activities, and project team members.” Activities go down one side and people or groups across the other, and each cell says what responsibility that person has for that activity. “On larger projects, a responsibility assignment matrix can be developed at various levels. For example, a high-level matrix can define the responsibilities of a project team, group, or unit within each component of the WBS. A lower-level matrix can be used within the group to designate roles, responsibilities, and levels of authority for specific activities.”

The grid has three uses. Each row is an activity and each column is a person (or group). Reading across a row, you see all the people associated with that activity. Reading down a column, you see all the activities associated with that person. And overall, the format “ensures that there is only one person accountable for any one task to avoid confusion about who is ultimately in charge or has authority for the work.” So when a question asks “which of the following is NOT a function of a responsibility assignment matrix”, any option about schedule, cost or risk prioritization is not.

The four RACI letters

A RACI matrix is the most commonly used responsibility assignment matrix. The four letters stand for responsible, accountable, consulted and informed.

LetterMeaningHow to tell
R: ResponsibleThe person who actually does the workWho is doing the work
A: AccountableThe person who makes the final call and answers for the resultWhom to go to when something goes wrong
C: ConsultedThe person who provides opinions or expertiseWhom to ask before doing it
I: InformedThe person who needs to be told of progress and resultsWhom to notify when it is done
Figure 1 A sample RACI matrix

There is one iron rule for reading this matrix: each activity has only one A. There may be several Rs, a person may hold different letters on different activities, and one person may even be both A and R on the same activity, but the one who makes the final call can only be one person. If everyone is responsible, no one is. “A RACI matrix is a useful tool to ensure the clear assignment of roles and responsibilities when the team consists of internal and external resources.” The project manager can also select other options, such as “lead” and “resource” designations, as appropriate for the project.

Worked example

On a charging-station installation project for a residential community, take the activity “apply to the property manager for a construction permit”. The project manager is accountable (A), the business specialist is responsible (R), the property manager and legal counsel are consulted (C), and the sponsor is informed (I). If the business specialist and the project manager's assistant each think the job belongs to the other, responsibility is unclear, and the team should go back to the matrix to confirm who is R and who is the one and only A.

How to build a RACI

Building one is not complicated, and it takes four steps. Step one: take the work packages from the WBS (or the activities from the schedule-related documents) and list them down the left column. Step two: list the individuals or groups involved across the header. Step three: fill in the letters row by row, setting the single A for each row first, then the Rs, then adding Cs and Is. Step four: check each person's column. If someone has a large number of As or Rs, that may be a sign to check that person's load further against resource calendars, resource requirements and workload (a RACI itself carries no information on workload or duration). A column with very few entries also needs further checking and cannot be taken as proof that the resource is idle. If a row has no A or has two As, go back and correct it. After publication, return to the matrix to update it whenever a new member joins or responsibilities change.

How the exam tests this

There are three kinds of scenarios. First, if the stem shows that work from several sources, passing the buck or crossing role boundaries is caused by unclear ownership, establish a responsibility assignment matrix or review it with the team. If the stem instead establishes overload, a competence gap or unauthorized work as the cause, address that cause. Second, a question asks “who is responsible for which piece of work”, which again means checking the matrix. Third, two functional managers each say a deliverable belongs to them. To settle the ownership of a specific activity or work package, check the matrix first. If the options do not include the matrix, or if the question asks how roles, authority, responsibility and competence are planned for the project as a whole, check the resource management plan (a high-level matrix can also define the responsibilities of a group or unit within each component, so read the options carefully). The rule of thumb: if the stem says “responsibility unclear”, “passing the buck” or “do not know who is responsible”, it is the responsibility assignment matrix. If it says “which resources are needed”, look at the outputs of Estimate Resources (resource requirements and the resource breakdown structure). The resource management plan provides guidance on how project resources are identified and quantified, acquired, allocated and monitored and can include roles and responsibilities, but the types and quantities of resources are recorded in the resource requirements.

Worked examples

Example 1 A new task has no decision maker: which tool

Question 1Example

A smart-campus project is proceeding according to the strategic plan, and the key milestones in the plan have been aligned with stakeholders. During execution, several new tasks within the approved scope and important dependencies appear, work stalls as a result, and the team cannot say who should decide and take action. What should the project manager do?

Show answer and explanation

Correct answer: A

The project is in execution and the key milestones are aligned. When new tasks and dependencies appear, work stalls and the team cannot say who decides and acts. The conflict is not about schedule or scope but about unclear ownership.

A RACI matrix uses four roles (responsible, accountable, consulted, informed) to tie each task to people, and it ensures each task has only one accountable person. Using it to settle responsibility for the new tasks makes clear who decides and who acts, and the stall clears. The key signal in the stem is “cannot say who should decide and take action”. The answer is A.

Why the other options are wrong

  • B. A Gantt chart shows the timing of activities and milestones and answers “when”, not “who is responsible and who decides”. The milestones were already aligned and are not the issue.
  • C. Having the sponsor name an owner for each task means the project manager gives up the lead on resource management and slows the response. A better approach is for the project manager to assign actively with the tool and ask the sponsor to confirm only if needed.
  • D. The WBS breaks down scope that has already been defined. It is not for identifying all requirements and cannot by itself guarantee none are missed, and it also does not assign responsibility or decision rights. Nobody deciding on new tasks is not a problem of scope omission.

Key takeaway When it is unclear who does the work and who makes the call, use a RACI matrix to assign responsibility to people, with one accountable person per task.

Variation If the question asked how to confirm every deliverable has been included in scope, the answer would become the WBS. If it asked how to show which department is responsible for which work packages, the answer is the organizational breakdown structure.

Something wrong with this question?

Report an issue with this question

Example 2 Tasks too heavy and people passing the buck: what to review first

Question 2Example

A membership system development project for a convenience store chain has been running for a while. Several members complain to the project manager that their workloads are too heavy and that resources are unevenly allocated. The project manager cannot add resources for now and also notices that several tasks have no clear owner and are repeatedly passed among members, each saying “that's your job”. What should the project manager do?

Show answer and explanation

Correct answer: D

Members complain of heavy workloads and uneven allocation, the project manager cannot add resources, and some members pass their tasks to others. Taken together, the two signals show that members are not clear about what each of them should do.

Passing tasks around is a typical sign of unclear responsibility, and being unable to add resources closes off the option of adding people. Reviewing the responsibility assignment matrix with the team lets you check task by task whether each has a clear accountable and responsible person and lets members confirm their own responsibilities, which cuts passing at the root. Whether workloads are out of balance should be dealt with after responsibilities are clear, by looking at each person's workload and availability. The answer is D.

Why the other options are wrong

  • A. The project manager should first review and clarify the existing responsibility assignments. If changing people or responsibilities exceeds the project manager's authority, the functional manager can then be consulted or the matter escalated. Immediate escalation does not first resolve the current lack of clear responsibility boundaries.
  • B. An even split looks fair, but tasks and members' skills differ, so equal is not reasonable. More importantly, responsibilities would remain unclear and passing would continue under any new split.
  • C. The resource breakdown structure divides resources by category and type for acquiring and reporting resources. It has nothing to do with how responsibilities are split among members.

Key takeaway When members pass tasks to each other, it signals unclear responsibility. First go back over the responsibility assignment matrix with the team.

Variation If the stem said clearly that idle resources could be reassigned, consider moving idle resources to overloaded members (resource leveling is used only when resource conflicts must be solved by adjusting activity dates). If several people assign work to one member at the same time, the answer is again to use RACI to name a single accountable person.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • For conflict caused by unclear responsibility, the most fundamental remedy is to clarify roles and responsibilities. It is not to go to the functional manager first, replace people or split tasks evenly.
  • PMBOK 8 notes that the resource management plan may include “roles and responsibilities” (role, authority, responsibility, competence), while the responsibility assignment matrix shows the relationship between work packages or activities and team members. Common exam practice: if the stem asks who is responsible or accountable for a specific work package or activity, think of the responsibility assignment matrix first. If it asks how roles, responsibilities, authority and competence are planned for the project as a whole, think of the resource management plan, and judge by the context of the stem.
  • The responsibility assignment matrix clarifies the division of responsibility for work packages or activities. During planning it can first be built by role or group and refined to individuals once resources are known. To decide which resources are needed, look at the outputs of Estimate Resources (resource requirements and the resource breakdown structure). The resource management plan describes how resources are identified and quantified, acquired, allocated and monitored, and can include roles and responsibilities, while the specific types and quantities of resources are recorded in the resource requirements.
  • There can be only one A, but there can be several Rs. Do not read “accountable” as “does the work”.

Compare

Responsibility assignment matrixResource breakdown structureWork breakdown structure
AnswersWho is responsible for which activityWhich resources are neededWhat is to be delivered
FormGridHierarchical chartHierarchical chart

Key takeaways

  1. A responsibility assignment matrix shows the relationship between activities and team members and ensures that each task has only one accountable person.
  2. The four RACI letters: responsible (R), accountable (A), consulted (C), informed (I).
  3. Each activity has only one A, and there can be several Rs.
  4. When responsibility is unclear, people pass the buck or work is assigned from several sources, go back to the responsibility assignment matrix first.
  5. To determine which resources are needed, do not look at the matrix; look at the outputs of Estimate Resources (resource requirements and the resource breakdown structure). The resource management plan describes how project resources are identified and quantified, acquired, allocated and monitored, and can include roles and responsibilities. The specific resource types and quantities are recorded in the resource requirements.
  6. For a team of mixed internal and external people, RACI is especially useful for making the division of work clear.

Lesson 3

The Resource Management Plan: What It Contains and How to Use It

Lesson video

Lesson overview

The resource management plan is the most important output of Plan Resource Management and a component of the project management plan. When the team does not know how to get people, manage people or reward them, when a skill gap is found during planning, or when a labor agreement changes, the first reaction is to open this plan. This lesson covers its purpose and structure, what goes into the plan, and the usual ways the exam asks about it. The RACI from the last lesson is one way to present the roles and responsibilities in it, and the next chapter covers the other output of the same process, the team charter.

Purpose and structure

“A resource management plan is a component of the project management plan that describes how project resources are acquired, allocated, monitored, and controlled. The plan may be divided between the team management plan and the physical resource management plan according to the specifics of the project.” Think of it as the master guide on the resource side: it gives the approach for acquiring, developing, rewarding and releasing resources, while specific types and quantities are in the resource requirements, required timing is in the schedule and availability is in the resource calendars. A predictive project generally fixes it early on, and an adaptive project adjusts it on a rolling basis with each iteration.

What is in the plan

The resource management plan may include but is not limited to the following:

  • Identification of resources: methods for identifying and quantifying the team and physical resources needed.
  • Acquiring resources: guidance on how to acquire the team and physical resources for the project.
  • Roles and responsibilities: role, authority, responsibility and competence.
  • Project organization charts.
  • Project team resource management: guidance on how the project team resources should be defined, staffed, managed, and eventually released.
  • Training: training strategies for team members.
  • Team development: methods for developing the project team.
  • Resource control: methods for ensuring adequate physical resources are available as needed and that the acquisition of physical resources is optimized for project needs, including managing inventory, equipment and supplies throughout the project life cycle.
  • Recognition plan: a plan for which recognitions and rewards will be given to team members, and when.
Figure 1 Contents of the resource management plan

A project organization chart is “a graphical display of project team members and their reporting relationships. The chart can be formal or informal, highly detailed or broadly framed, based on the needs of the project.” It is a component of the plan and not a separate document. To find out whom a new member reports to, look there.

Worked example

A restaurant chain upgrades its store system. The resource management plan provides guidance on how resources are identified, acquired, allocated and monitored. Specific needs, such as a development team of 6 people and 2 database engineers joining from month 3, are resource types and quantities recorded in the resource requirements; when they are needed is shown by the schedule or schedule data, and when a resource is available is found in the resource calendar. What the resource management plan holds are the matching arrangements: how the database engineers will be acquired; training in month 2 because interface testing skills are missing; equipment rented by the purchasing department in month 4 and returned within 2 weeks after use; a small reward for the whole team at each milestone. These correspond to acquiring resources, training, resource control and the recognition plan.

How the plan is used

The resource management plan is not something you write and then file away. It is used again and again at three points. During planning, you read it against the schedule: if a certain month needs a certain number of people and a certain skill, the plan must contain the matching acquisition and training arrangements. During execution, members joining or leaving, overlapping responsibilities and contract changes are analyzed and handled on its basis; when a configuration-controlled plan component must change, update it only after approval through the applicable process. During monitoring, actual use of physical or virtual resources is compared with the plan and corrective action is taken when deviations appear; team-member performance is tracked and managed through Lead the Team. So when a question asks “on what basis should this resource problem be handled”, the answer is mostly this plan. When it asks “what should be done first after a resource change”, the answer is to analyze the impact first. In a predictive project, where a plan component is under configuration control, the change goes through the formal change process, and the resource management plan is updated after approval. Baselines are not adjusted directly.

The “recognition plan” and “team development” in the plan also carry weight: what recognition or reward will be given, and when, can be written down in advance in the recognition plan instead of being decided off the cuff later, and the methods and timing of team development are likewise arranged here in one place, giving the later Lead the Team process something to work from.

How the exam tests this

Questions about this document usually take these forms:

  • A member is unclear about role and responsibilities, or responsibilities overlap between teams: first check the roles and responsibilities in the resource management plan.
  • There is disagreement about how resources are chosen or used: use the resource management plan as the basis (see the next paragraph); only disagreements about member behavior go back to the ground rules in the team charter.
  • A skill gap is found during planning: assess the impact and constraints first. If training can close the gap in time within the project constraints, arrange it in the plan; otherwise compare responses such as hiring, changing the schedule, or changing the scope.
  • A key role is missing: add it during resource planning and define its responsibilities.
  • A labor contract or resource rules change: first analyze the impact on the project and handle it through the established change process (in a predictive project, plan components under configuration control require a formal change request) and record the decision. Only if the change is approved and needs to be put into effect, update the resource management plan and other affected artifacts.
  • The resource plan and the schedule do not agree: they must be aligned, and any inconsistency found must be reconciled.

When there is disagreement about how resources are chosen and used, the plan is again the basis. Suppose the matrix has not yet named a lead, and the project manager and sponsor prefer different people. Do not look only at the organization chart. First confirm the resource selection method and decision authority from the resource management plan. If internal resources are controlled by a functional or resource manager, that manager should take part in coordinating or assigning them.

Worked examples

Example 1 A skill gap found during planning: the first step

Question 1Example

A store checkout system upgrade project has just been initiated. While planning, the project manager finds that several key members lack the skills needed for the core tasks late in the project. The assessment shows that training started now will close the gap before those tasks begin without breaching the schedule or cost constraints. What should the project manager do?

Show answer and explanation

Correct answer: D

The project has just been initiated and planning is under way. Comparing against the tasks, the project manager finds that several key members lack skills for late-stage core tasks. The assessment has confirmed that training can close the gap in time without breaching the schedule or cost constraints.

Skill gaps are something the resource management plan deals with: it states how resources are acquired and how people are trained. PMBOK 8 treats training, hiring, schedule changes and scope changes as parallel proactive responses. For a gap found during planning when training is feasible, common exam practice is to arrange adequate training in the resource management plan before replacing people or outsourcing. Among the choices, D best reflects that approach.

Why the other options are wrong

  • A. A skill gap can be logged and tracked, but merely entering it in the issue log does not close it. In planning, first set out training and any needed resource acquisition in the resource management plan, so logging is not the first step.
  • B. Members lack only some skills, so replacing them during planning is hasty and adds cost. Consider whether training can solve it first, then whether anyone needs replacing.
  • C. The stem has not said that training is infeasible, and no make-or-buy analysis has been done, so outsourcing the core tasks directly is premature. If training cannot close the gap in time, then evaluate external resource options.

Key takeaway For a skill gap found during planning when training is feasible, common exam practice is to arrange training in the resource management plan before considering replacement or outsourcing.

Variation If the gap appears during execution and there is not enough time for training, then turn to borrowing staff, outsourcing or hiring. If the question asks what options exist when competence is lacking, the answer is training, hiring new members, schedule changes or scope changes.

Something wrong with this question?

Report an issue with this question

Example 2 Lead not yet named, opinions differ: which document is the basis

Question 2Example

On an enterprise ERP project, the lead for the “data migration” activity has not yet been set in the responsibility assignment matrix, and the sponsor and the project manager cannot agree: the project manager prefers member A, while the sponsor thinks member B is more experienced. The resource management plan already states each role's responsibilities and authority, including who decides on resource selection. What should the project manager do to resolve this disagreement over a resource decision?

Show answer and explanation

Correct answer: B

The lead for the “data migration” activity is not yet set in the responsibility assignment matrix, the project manager and the sponsor each have a candidate, and the resource management plan already states each role's responsibilities and authority, including who decides on resource selection. The question asks how to resolve the disagreement over this resource decision.

At heart the disagreement is about how resources are selected and who leads. The resource management plan states roles, responsibilities, authority and other content and is the common basis for the project manager and sponsor, so the project manager should handle the disagreement on that basis and give the decision a footing. The matrix does not yet cover this activity, so consulting it yields no conclusion. The answer is B.

Why the other options are wrong

  • A. An organization chart shows only the organization's levels and reporting relationships. It cannot say who chooses the lead for an activity or on what basis.
  • C. This activity's lead is exactly what is blank in the matrix, so looking there gives no answer. The matrix records the outcome once the disagreement is settled and is not the basis for settling it.
  • D. The functional manager controls staff assignment, whereas the dispute is about who leads within the project. The project manager should first handle it on the basis of the plan rather than hand the disagreement to the functional manager.

Key takeaway When there is disagreement about how resources are chosen and used, rely on the resource management plan, not the functional manager or the organization chart.

Variation If the stem said the matrix already names a lead but members do not accept it, review and confirm the matrix with the team. If a key person is being moved away by the functional manager, move to negotiating with the functional manager.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • To see team members and their reporting relationships, look at the project organization chart. It belongs to the resource management plan and is not a separate plan.
  • PMBOK 8 treats training, hiring new members, schedule changes and scope changes as parallel responses when competence is insufficient, and the impact and constraints should be assessed before choosing. On the exam, choose training in the resource management plan only when the stem establishes that training can close the gap in time within the project constraints. Otherwise assess the impact and constraints before comparing training, hiring, schedule changes, or scope changes.
  • To determine which resources are needed, look at the identification methods in the resource management plan and at the outputs of Estimate Resources. The responsibility assignment matrix shows the relationship between activities or work packages and people and is not used to show which resources are needed.
  • After the project management plan is issued, if a member asks about his role, the answer is in the roles and responsibilities in the plan and in the matrix, not in calling another meeting.

Key takeaways

  1. The resource management plan is a component of the project management plan and may be divided into a team management plan and a physical resource management plan.
  2. Its contents: identification of resources, acquiring resources, roles and responsibilities, project organization chart, project team resource management, training, team development, resource control, recognition plan.
  3. Roles and responsibilities contain four items: role, authority, responsibility and competence.
  4. For unclear roles, overlapping responsibilities and disagreements over resource selection, check the resource management plan first; for skill gaps, assess the impact and constraints first, then decide whether to arrange training in the plan; only disagreements about member behavior go back to the ground rules in the team charter.
  5. After a contract or rule change, analyze the impact and handle it through the established change process; update the resource management plan once the change is approved.
  6. The resource plan must be aligned with the schedule.

This chapter has 28 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.