What this chapter covers

The team charter is one of the outputs of Plan Resource Management. The team develops it itself, or at least contributes fully to it, and it records what everyone has agreed about “how we work together.” This chapter addresses two kinds of problem: the team charter addresses behavior and collaboration issues such as late arrival at meetings, disagreement about how decisions are made and new members not knowing the rules; the shared-vision material addresses differences in how team members and key stakeholders understand the project's goals. The chapter has three lessons. Lesson 1 covers what the team charter is for, its six common contents (which can be tailored and supplemented to suit the project) and who develops it, and explains how it relates to team agreements and to the project charter. Lesson 2 covers how ground rules are set and the order of action when someone breaks them. Lesson 3 covers the team-level common vision, roles and expectations, and how to start a new team, support a remote team, or integrate a new member.

Project authorization is covered under the project charter; this chapter focuses on aligning and carrying out the project vision at team level, including building consensus on that vision with key stakeholders. In the ECO this chapter maps to three tasks: Develop a common vision, Manage conflicts and Lead the project team.

Lessons in this chapter

Chapter map

Team charter (an output of Plan Resource Management)

  • Contents: team values · communication guidelines · decision-making criteria and processes · conflict resolution processes · meeting guidelines · team agreements
  • Ground rules: expectations about acceptable behavior → prevent conflict → violation: talk privately → update the rules → formal procedure
  • Opening order (common exam practice, can be iterative or parallel): vision and objectives → roles and responsibilities → ground rules → assign tasks
  • Development and updates: team develops it or contributes to it · reviewed and updated periodically · reviewed again when membership changes, to help new members fit in

(Team agreements: the term used in the Standard's “Build an Empowered Culture” principle; project charter: authorizes the project and is a separate document)

Lesson 1

Team Charter and Team Agreements: Purpose, Contents and Who Develops It

Lesson video

Lesson overview

The team charter deals with “how we work together”: what to do about late arrivals at meetings, how to decide when opinions differ, and what to do when new people do not know the rules. It is an output of Plan Resource Management, alongside the resource management plan (a component of the project management plan). This lesson covers the purpose of the team charter, its six contents, why the team should develop it or contribute to it, and how it relates to the project charter and to team agreements. The next lesson covers the part of the charter that questions use most often: ground rules, and what to do when someone breaks them.

What the team charter is

The team charter is a document that establishes the values, agreements and operating guidelines for the team. It sets clear expectations regarding acceptable behavior by project team members. Early commitment to clear guidelines decreases misunderstandings and increases productivity. Discussing areas such as codes of conduct, communication, decision-making and meeting etiquette also allows team members to discover the values that are important to one another.

An analogy from sports: before a match, players need to settle who covers which position, how to call for a pass and how to cover for each other after a mistake. If the rules are not shared, the players start arguing halfway through the game. The team charter does the same for work: it settles questions of “how we cooperate” before work begins, so there is something to refer to when friction does appear.

The six contents

The team charter may include, but is not limited to, the following: team values, communication guidelines, decision-making criteria and processes, conflict resolution processes, meeting guidelines and team agreements. Each one answers a common kind of friction:

ContentFriction it addressesExample wording
Team valuesInconsistent standards of workBe honest with the customer; report problems the same day
Communication guidelinesMissed information, slow repliesPhone for urgent matters; reply to everything else within one working day
Decision-making criteria and processesRepeated argumentsIf a technical disagreement has no consensus after ten minutes, the technical lead decides
Conflict resolution processesTension that builds upThe people involved talk privately first; if that fails, the project manager helps
Meeting guidelinesInefficient meetingsAgenda sent a day ahead, start on time, no longer than 45 minutes
Team agreementsOther commitments that never get put into practiceCore working hours, naming convention for shared files
The six contents of the team charter

Worked example

The team charter of a hospital information system upgrade project contains these items: Wednesday afternoon is online time for everyone, and no other meetings are scheduled then; requirement-change proposals are first discussed in the team chat, and any proposal formally submitted is recorded promptly in the change log with its current status; in meetings, people listen to the end before rebutting. These three correspond to team agreements, decision-making criteria and meeting guidelines. With them, a new test engineer knows on day one how to work with the team and does not need to find out by trial and error.

Who develops it

The team charter works best when the team develops it or at least has an opportunity to contribute to it, and all project team members share responsibility for ensuring that the rules in it are followed. So the project manager does not write it alone and send it out, does not assign a senior member to draft it, and does not consider the job done by simply applying the organization's template. The process of taking part in the discussion itself builds consensus and commitment; people who did not take part can easily fall back on “I never agreed to that” and ignore the rules later.

The team charter can be reviewed and updated periodically, which keeps the team aware of the ground rules and helps new members get oriented and integrated. When the makeup of the team changes substantially, review and update it together with all the members instead of unilaterally announcing the old rules. The best time to develop it is when the team has just been formed and work is about to begin, for example at the project kickoff meeting.

How it differs from team agreements and the project charter

Team agreements appear in the Standard, in the principle Build an Empowered Culture: they are a set of behavioral parameters and working norms that are established by the project team and upheld through individual and team commitments. They should be created at the beginning of a project to determine the essential norms and practices that facilitate ongoing collaborative success. The Guide, under Plan Resource Management, covers the team charter, and lists team agreements among its contents. In both cases the team creates the norms for how members work together, but do not treat the two terms as interchangeable labels for one document. When a question uses one of these terms, answer according to that term's own definition; when you see descriptions such as “code of conduct” or “meeting etiquette,” think of the team charter first. The project charter is different. PMBOK 8 defines it as a document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities (the project manager is usually appointed and authorized by the sponsor). It governs the relationship between the project and the organization, not the behavior of members toward one another.

Worked examples

Example 1 A new team: how to develop an effective team charter

Question 1Example

A home appliance manufacturer's smart panel development project has just started. The members come from the engineering, purchasing and quality departments, and their cooperation is critical to the project's success. How should the project manager develop an effective team charter?

Show answer and explanation

Correct answer: B

A smart panel development project has just started. Members come from engineering, purchasing and quality, and their cooperation is critical to the project's success. The question is how to develop an “effective” team charter, so the key is the method of development.

The team charter works best when the team develops it or at least has an opportunity to contribute to it. The process of discussing values, roles and responsibilities, and working rules itself builds consensus and commitment, and members follow the rules willingly once they accept them. The kickoff meeting is a suitable occasion for a new team to discuss together, with the project manager facilitating. The stem stresses “effective” and “cooperation is critical,” so the answer is B.

Why the other options are wrong

  • A. A charter the project manager writes alone and then sends out expresses personal expectations. Members did not take part, so they will not feel it is “their own agreement.” Buy-in is low and compliance is not assured.
  • C. Handing the drafting to one senior member still shuts everyone else out and merely swaps one ghostwriter for another. The charter needs the participation of all members, not an announcement of the result to the team.
  • D. A template can be the starting point for discussion, but letting members change only the wording cannot replace the team discussing and reaching consensus together, and it does not reflect the cooperation between this project's three departments.

Key takeaway Have all members take part in developing the team charter, so that buy-in and compliance are assured.

Variation If “a new member joins and finds the charter no longer fits,” review and update it together with all members, rather than announcing the old rules one-way.

Something wrong with this question?

Report an issue with this question

Example 2 Members with very different styles: which document should be in place beforehand

Question 2Example

A new energy company recruited a group of highly skilled engineers from several cities for its battery management system development project. The members are spread across different cities and have very different work styles and practices; since the start of work, arguments have been constant and progress is slow. To avoid this situation, which document should the project manager have guided the team to develop beforehand?

Show answer and explanation

Correct answer: D

The engineers on a battery management system project come from several cities and have very different work styles and practices. Since the start of work there have been constant arguments and slow progress. The question asks which document the team should have been guided to develop beforehand to avoid this.

The root of the arguments is that members have no shared expectations of “how we work together.” The team charter records the team's values and the agreements and operating guidelines the team settled on. It spells out communication rules, decision-making methods, conflict handling, and meeting and discipline requirements in advance, and sets clear expectations for acceptable behavior; the earlier everyone commits to it, the fewer the misunderstandings. The signals in the stem are “differences in habits” and “beforehand.” The answer is D.

Why the other options are wrong

  • A. The project management plan integrates the baselines and subsidiary plans and governs how the project is executed, monitored and closed. It does not set behavioral rules for members.
  • B. The risk management plan covers how risks are identified, analyzed and responded to. Even if disagreements among members become a risk, it is not what unifies behavior in advance.
  • C. The stakeholder engagement plan deals with strategies for engaging external and internal stakeholders and does not contain the working rules of members inside the project team.

Key takeaway When members' styles differ greatly and conflict is likely, align expectations in advance through the team charter.

Variation If the stem asked “which document formally authorizes the project and gives the project manager authority to apply organizational resources,” the answer would be the project charter; if it asked “what to do when you find nobody follows the communication guidelines,” go back to the team charter and renegotiate with the team.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The project manager drafts the charter alone and then sends it out. The members did not take part, so buy-in is low. The charter should be developed early by the team together, and the kickoff meeting can be one occasion for discussing and confirming it (PMBOK 8: the team charter works best when the team develops it or at least has an opportunity to contribute to it).
  • Using a template can be a starting point, but it cannot replace the process of the team discussing and reaching consensus together.
  • The team charter governs how members work together; the project charter authorizes the project and the project manager. Do not mix them up.
  • The risk management plan, the stakeholder engagement plan and the project management plan do not set behavioral rules for members.

Key takeaways

  1. The team charter establishes values, agreements and operating guidelines for the team, and is an output of Plan Resource Management.
  2. Contents: team values, communication guidelines, decision-making criteria and processes, conflict resolution processes, meeting guidelines and team agreements.
  3. It works best when the team develops it or contributes to it, and all members share responsibility for following it.
  4. It can be reviewed and updated periodically; when membership changes, review and update it together with all members.
  5. The team charter and team agreements govern members' behavior; the project charter authorizes the project. They are different things.
  6. When members have very different styles and are prone to conflict, align expectations in advance through the team charter.

Lesson 2

Ground Rules and Handling Violations: Prevent First, Correct in Order

Lesson video

Lesson overview

The most practical part of the team charter is the ground rules: when people start work, how meetings run, what to do when opinions differ, how quickly messages get answered. Exam questions about them are common and come in two forms: how to prevent disagreements in advance, and how to handle it when someone breaks a rule. This lesson first covers what ground rules are and how they are set, then the order for prevention and correction. The previous lesson covered the charter as a whole and the next covers vision and expectations at team level; together, the three lessons describe how a new team gets started.

What ground rules are

Ground rules are expectations regarding acceptable behavior by project team members, defined in the team charter. The PMBOK 8 glossary adds that they set the expected behavior for project team members and other stakeholders with regard to stakeholder engagement. In a team charter, the following are also commonly written as ground rules (common exam practice): core working hours, punctuality and speaking etiquette in meetings, how decisions and conflicts are escalated, and communication channels and reply times.

Ground rules should be set early, ideally when the team is first formed, and with everyone taking part. When team members' available hours do not line up, it is more effective to have the team agree on a block of core working hours in the charter than for the project manager to impose one unilaterally, ask some people to start earlier, or require everyone to start at the same moment. It increases the overlap in working time, and because everyone agreed to it, it is easier to follow.

Worked example

The members of a software maintenance team are in two different cities and each works their own usual hours. They overlap for less than an hour a day, and communication keeps breaking down. The project manager calls everyone together, and the team writes this into the team charter: 10:00 to 12:00 each day is core online time for everyone, and meetings are scheduled only in that window; questions outside core time are left in the team chat and answered before 10:00 the next day. The team agreed on the solution itself, so nobody feels that it was imposed.

Prevention comes first

The main purpose of ground rules is to prevent conflict, not to eliminate every disagreement. When the way of interacting has been agreed in advance and members' expectations of each other match, there is less conflict. To prevent mutual blame caused by inconsistent ways of interacting, agree on interaction ground rules in advance; if the conflict comes from unclear role boundaries, also clarify roles and responsibilities. Consensus is usually reached through thorough discussion and participation. The team may also use collective decision-making techniques such as voting, as agreed in the charter (PMBOK 8 lists several different voting criteria). It should not normally be left to the project manager alone to decide; give priority to letting the team discuss together and reach a conclusion by the decision-making method the charter specifies. The discussion should be facilitated in a suitable way, so that everyone has a chance to give their view and a clear conclusion is reached.

To avoid disputes of the “I didn't know that rule existed” kind, make sure that the charter is developed with everyone's participation. Members who helped develop the rules understand them better and are usually more willing to accept and follow them, so handling a breach by the rules is less likely to cause argument afterward. Issuing the charter after the fact, asking members to sign it, or relying on the leader's charisma to carry people along are not the right remedies.

When a rule is broken

For discipline and behavior problems, go back to the team charter and the ground rules first. The ECO calls for an environment in which shared ground rules are followed and violations are managed and corrected. The handling sequence below is common exam practice: usually start by talking privately, finding out the reason and restating the rule, and then, depending on the nature of the violation and organizational policy, decide whether to update the charter, escalate or start a formal procedure. Where safety, harassment, illegal conduct or a serious compliance matter is involved, handle it immediately through the organization's procedures.

Common exam practice: when the stem gives no other conditions, the order is to talk privately with the person first, understand the reason, restate the rule and explain the consequences; if you find the rule itself no longer fits, the team renegotiates and updates the charter; if the person keeps ignoring reminders and the project is affected, then follow the organization's formal procedure. Do not criticize anyone in public, do not rush to escalate, and do not go around the team to set penalties unilaterally.

Order of action when a ground rule is violated

If a new member's behavior does not fit the team's norms, first help them learn and follow the charter; replacing them or disciplining them comes later. If members are unwilling to follow existing agreements, go back to the charter first and remind everyone of their responsibilities. What needs to change is the content of the charter, and the team decides that together; the project manager does not issue a separate prohibition.

Predictive, adaptive and hybrid approaches

All three approaches ask the same of ground rules: agree first, then follow. The difference lies in the rhythm of updates. A predictive project sets the rules when the team is formed and reviews them afterward as needed. In an adaptive project, agreeing working agreements before the first iteration and inspecting them in retrospectives as needed are agile practice and common exam practice; the team charter itself can be reviewed and updated periodically. Rules that helped stay, rules that exist only on paper go, and anything that needs adjusting is changed on the spot. In a hybrid project the team often has both predictive and adaptive members, so it is even more important to write both sides' rhythms, meeting schedules and decision-making methods into one charter at the very start, so that neither side follows its own habits while the other simply has to go along. In every approach, the rules in the charter should be testable: if nobody can say what “following it” looks like, the rule is too vague.

Worked examples

Example 1 Overlapping working time is too short: how to improve interaction

Question 1Example

On the operations project team of a software outsourcing company, each member has their own daily start time, and at times the overlap in working hours is very short. Interaction within the team has dropped and efficiency has fallen with it. What should the project manager do?

Show answer and explanation

Correct answer: A

On an operations project team, members each have their own start times and the overlap in working hours is sometimes very short, so interaction drops and efficiency falls. The question is what the project manager should do, based on how to handle working hours that do not line up.

The team charter records the ground rules the team has agreed on. Having the team discuss and agree a block of core working hours when everyone is on duty increases the overlap, and because everyone agreed to it, it is easier to follow. It is also consistent with the principle that ground rules should be set with everyone taking part. The answer is A.

Why the other options are wrong

  • B. Requiring those who start later to come in earlier means the project manager is unilaterally asking some people to adjust, without consulting everyone. It invites resistance; even if imposed as a ground rule, it would be less effective than one agreed by the team.
  • C. Assigning each member an overlap window and enforcing it is still a top-down arrangement. The team does not discuss it or reach consensus, so it is less effective than a schedule the team agrees itself.
  • D. Requiring everyone to start at the same moment ignores each member's circumstances. It is also imposed, and a one-size-fits-all rule does not improve the quality of collaboration.

Key takeaway When working hours do not line up, have the team agree core working hours in the team charter rather than having the project manager designate them unilaterally.

Variation If the team spans several time zones with almost no overlap, agree in the charter on rotating meeting times and on how synchronous and asynchronous communication are used. The thinking is the same: the team decides together.

Something wrong with this question?

Report an issue with this question

Example 2 A member says they never saw the rules and rejects the penalty: how should this have been avoided

Question 2Example

A member missed a progress review meeting without requesting leave and was given a penalty under the ground rules. He and several other members say that this was the first time they had seen this rule and that they do not accept the penalty. What could the project manager have done to avoid this situation?

Show answer and explanation

Correct answer: D

A member missed a progress review meeting without leave and was penalized under the ground rules. He and other members say this was the first time they had seen the rule and refuse the penalty. The question asks what the project manager could “have done” to avoid this, so the key is a preventive measure.

When ground rules are developed jointly by the team, members know and accept their content, and handling a breach by the rules afterward is not likely to cause disputes. The heart of the stem is not that the rule is wrong but that members did not know it and did not take part. Making sure beforehand that the team charter is developed with the participation of all members would have avoided this. The answer is D.

Why the other options are wrong

  • A. Requiring everyone to express support for all decisions is unrealistic and is not the source of the dispute; the dispute arises from how the rule was made and how well it was known.
  • B. The project charter is a high-level document that authorizes the project and appoints the project manager. It does not set members' day-to-day behavioral norms, so having people sign it would not solve the team-rules problem.
  • C. Leadership style helps guide people, but to “avoid” this kind of dispute you need members to know and accept the rules beforehand, and charisma cannot replace participation.

Key takeaway The team charter works best when the team develops it or takes part in it; only when members know and accept the rules in advance can they be applied fairly afterward.

Variation If the rule exists and members accept it, but someone still breaks it, the order is a private conversation and restating the rule; if the rule does not fit, the team updates it; only if repeated reminders fail do you go to the formal procedure.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Members keep checking email in meetings and drift off topic. The cause is that there are no communication ground rules, and the remedy is to agree them through the team charter, not to replace people, escalate first or ban the behavior unilaterally.
  • The project manager unilaterally sets the core working hours without team discussion, and compliance suffers; let the team agree them itself.
  • The project charter authorizes the project and does not set members' day-to-day behavior; using it in place of the team charter does not solve behavior problems.
  • Common exam practice: the order for handling a violation is a private talk, restating the rule, updating the rule if necessary and only last a formal procedure; do not start with discipline or escalation. Serious or compliance-related incidents should be handled immediately through the organization's procedures.

Key takeaways

  1. Ground rules are expectations about acceptable member behavior, defined in the team charter.
  2. Set ground rules early with everyone taking part; consensus comes first from thorough discussion and participation, and voting or similar methods can be used as the team charter specifies.
  3. Their main purpose is to prevent conflict by agreeing how to interact in advance.
  4. When working hours do not line up, have the team agree core working hours in the charter.
  5. For a violation, talk privately and restate the rule first; if the rule does not fit, the team updates it; if reminders fail repeatedly, go to the formal procedure.
  6. To avoid “I never saw the rules” disputes, make sure beforehand that the charter is developed by everyone together.

Lesson 3

Shared Vision and Clear Expectations: The Opening Order for a New Team

Lesson video

Lesson overview

The team charter covers “how we work together,” but for the team to really get moving, everyone also needs to know why they are doing the work and what each person does. This lesson covers the team-level shared vision, the common aspects of team development, and how to make expectations clear for a new team, a remote team or a new member joining. It maps to two ECO tasks, Develop a common vision and Lead the project team. The purpose and objectives of the project as a whole are usually aligned through the project charter (on adaptive projects, the project charter can also take the form of a concise vision statement); here the focus is on aligning and carrying out the project vision at team level, and on making expectations clear inside the team.

Vision and objectives at team level

A vision is a concise summary of the project's purpose that describes a realistic, attractive view of the future outcomes. A good vision is short and powerful and lets everyone see the same picture. PMBOK 8 lists “vision and objectives” first among the common aspects of team development: the vision and objectives are communicated throughout the project and are essential for understanding, and this includes referencing the intended outcomes when the project team makes decisions and solves problems. Communicate them repeatedly, not once at the kickoff meeting: state them at the start, bring them out for comparison when disagreements arise, and you can also post them where people often look.

The vision should not be drafted by the project manager alone and then announced. Who proposes and owns the vision depends on project governance (PMBOK 8: the sponsor, customer or product owner communicates the organization's vision, goals or expectations to the project management team and project team). The project management team should help the team and key stakeholders reach consensus, keep communicating the vision and keep it current, and follow progress throughout. Team members and key stakeholders draft it together and genuinely understand and accept the objectives in it. In adaptive projects, the product backlog is usually prepared by the product owner and contains requirements, features, epics and user stories, reflecting the overall scope and vision of the product.

Roles, responsibilities and team operations

The second common aspect of team development is roles and responsibilities: project managers should ensure that project team members understand and fulfill their roles and responsibilities. This effort may include identifying gaps in knowledge and skills and developing strategies to address those gaps through training, mentoring or coaching. The third aspect is project team operations: facilitating project team communication, problem-solving and the process of consensus building, which may include working with the project team to develop a project team charter and a set of operating guidelines or project team norms. PMBOK 8 also describes the characteristics of high-performing teams, such as open communication, shared understanding and shared ownership.

PMBOK 8 lists vision and objectives, roles and responsibilities, project team operations, guidance and growth as the common aspects of team development, and does not require that they be done in a fixed order. Common exam practice: when starting a new team, you usually give priority to aligning on vision, expectations, roles and responsibilities and ground rules, and only then assign tasks and discuss technical approaches; the actual order should be tailored to the project context. If the order is reversed, everyone starts work with their own understanding and overlaps and gaps soon appear. When role boundaries are blurry, the remedy is to clarify and confirm roles and responsibilities, not to avoid the issue and not to add another approval step.

Worked example

A pharmacy chain is building an e-commerce mini-app. The team members come from development, operations and customer service and do not know one another well. In the first week the project manager holds a half-day meeting. She starts with the goal of raising the share of online orders to 30%, then asks each person to say how they understand that goal. Next they confirm everyone's responsibilities against the responsibility matrix, and finally they agree reply times and the meeting schedule together. When tasks are assigned in week two, nobody asks “whose job is this?”

Remote teams, new members and deviations

A common problem with remote teams is that members do not fully understand the requirements and the quality of deliverables is uneven. If the unevenness comes from members understanding the requirements differently, use a team-wide meeting plus one-on-one conversations to establish clear objectives and expectations with the members, so that everyone is clear about their role, which also builds a sense of responsibility. If the cause is not yet clear, first analyze the root cause and then apply targeted quality assurance measures (PMBOK 8's tailoring advice for “the deliverables are poor quality”). Common exam practice: when the stem attributes poor quality to members understanding the requirements, objectives or expectations differently, choose the team-wide meeting plus one-on-one conversations; when the stem says only that quality is low and the cause is unknown, analyze the root cause first; when the stem clearly points to a tool, skill or process problem, handle it according to that cause. Time logs, taking turns reporting progress and peer reviews after the project ends cannot replace aligning on objectives up front.

When the team's understanding of objectives has drifted, realign on the vision, objectives and intended outcomes. When the team's behavior has drifted from the collaboration norms, restate behavioral expectations at team level according to the ground rules. When a new member joins, have them learn and accept the ground rules the team already has; the same applies to outsourced staff. When the team's makeup changes substantially, update the team charter together with all members instead of simply imposing the old rules on the changed team. When understanding of the objectives has drifted, clarify it early together with the sponsor and the team so that everyone is aligned.

Key point

The usual opening order for a team (common exam practice): make the vision and objectives clear, make roles and responsibilities clear, agree the ground rules together and write them into the team charter, and only then assign tasks.

Worked examples

Example 1 A remote team's work quality is poor: how to ensure quality

Question 1Example

A project manager at PMLyceum is responsible for a project whose members are spread across several countries. In past work with remote teams, the project manager found that the quality of work that members submit is often poor, and an investigation showed that the cause was that members understood the work requirements and objectives differently. For the project to deliver on time and with quality, what should the project manager do?

Show answer and explanation

Correct answer: A

The project's members are spread across several countries, and in past work with remote teams the quality of submitted work was poor. The question is what the project manager should do for the project to deliver on time and with quality.

Quality is poor because members do not fully understand the requirements and objectives, and in a remote setting deviations are more likely. Establishing clear objectives with members through team meetings and one-on-one conversations lets each person understand the expectations and their own role, and also builds a sense of responsibility, which raises quality at the source. The answer is A.

Why the other options are wrong

  • B. Time records show how much time was spent. They can make management more efficient, but they do not ensure that the work meets requirements.
  • C. Taking turns to report progress solves information sharing, but the stem does not say information is opaque, so it does not target the quality problem.
  • D. Peer evaluations scheduled for the end of the project are an after-the-fact measure with no effect on quality during execution.

Key takeaway For remote teams to deliver quality, first make the shared objectives and expectations clear through team-wide and one-on-one communication.

Variation If the stem said remote members “understand the objectives but lack tools,” first provide the collaboration tools; if new members join, have them learn and accept the ground rules the team already has.

Something wrong with this question?

Report an issue with this question

Example 2 A newly formed team of strangers: what to do first

Question 2Example

A company has just formed a new project team whose members come from the engineering, marketing and operations departments and do not know one another. What should the project manager do FIRST?

Show answer and explanation

Correct answer: A

A company has formed a new project team whose members come from three departments and do not know one another. The question is what the project manager should do first, and the basis is the opening order for a new team.

Before a new team gets to work, the project manager should first state expectations at team level and work with members to define roles, responsibilities and collaboration rules. This is the foundation of leading the team: once everyone knows what each person does and how to work together, later division of work and technical work have a shared starting point. The signals in the stem are “newly formed,” “strangers” and “first.” The answer is A.

Why the other options are wrong

  • B. Sending out a task list before expectations and rules are made clear leaves members unsure of the division of work and how to collaborate, which leads to misunderstandings and overlaps.
  • C. A technical solution is of course needed, but having the project manager finish it alone and then announce it gives the team no part in it, and it is not the first thing a new team needs.
  • D. Waiting for obvious conflicts before stepping in is passive. The project manager should establish expectations and rules in advance to prevent conflicts, not wait for problems to occur.

Key takeaway A new team first clarifies expectations, roles, responsibilities and collaboration rules, and only then assigns tasks and discusses technical work.

Variation If the stem were changed to “the members have been working together for a while and overlaps and gaps have appeared,” go back to clarifying and confirming roles and responsibilities, using the responsibility assignment matrix if necessary.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • For a new team, assigning tasks first, working out the technical approach first or letting everyone “find their own way of working together” all go against the common exam practice of making expectations, roles and rules clear first.
  • The vision must be drafted and understood by the team and key stakeholders together; it is not announced by the project manager and not simply posted on the wall.
  • Time logs and progress reports are about monitoring. If a quality problem comes from differing understanding of requirements or objectives, align on objectives beforehand; for other quality problems, analyze the root cause first and take targeted action.
  • When a new member joins, have them learn and accept the existing rules; do not leave them to figure it out alone, and do not discipline first.

Key takeaways

  1. The common aspects of team development: vision and objectives, roles and responsibilities, project team operations, guidance and growth.
  2. The vision should be concise and attractive, communicated repeatedly throughout the project, and used as a reference when making decisions.
  3. Opening order for a new team (common exam practice, tailored to the situation): expectations, responsibilities, rules, then tasks.
  4. When a remote team's uneven quality comes from differing understanding of requirements or objectives, first establish common objectives through team-wide and one-on-one communication; if the cause is unclear, analyze the root cause first.
  5. When a new member joins, have them accept the existing ground rules; when the makeup changes substantially, review and update the charter together with all members.
  6. When role boundaries are blurry, clarify and confirm responsibilities; do not avoid the issue and do not add approvals.

This chapter has 23 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.