Resources and Team
Estimate Resources and Acquire Resources
PMP · Resources and Team · 4 lessons · about 39 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
The Resources performance domain has two adjacent processes: Estimate Resources answers “what do we need and how much,” and Acquire Resources answers “how do we get it.” Once you have the resources, you also need to use them evenly across the project and release them promptly when they are finished. The chapter has four lessons. Lesson 1 covers the inputs to Estimate Resources, the four main estimating tools and the three core outputs, and introduces the project document updates. Lesson 2 covers collaborative negotiation when acquiring resources, preassignment and multicriteria decision analysis. Lesson 3 covers the three core resource documents produced by Acquire Resources (plus change requests and the various updates), and the approach for handling resource shortages or changes: establish the facts first, then negotiate, and only then change. Lesson 4 covers resource leveling, skills matching, single points of dependency and timely release.
The two process names follow PMBOK 8: Estimate Resources and Acquire Resources. Acquire Resources here applies to team, physical and virtual resources; external resources are obtained through partners, joint ventures or procurement. Plan Sourcing Strategy (deciding between internal and external resources) belongs to the Governance performance domain, and this chapter discusses it mainly in Lesson 2, to show how it divides the work with Acquire Resources.
Lessons in this chapter
- Lesson 1: Estimate Resources: requirements, basis and the resource breakdown structure. The resource calendar; bottom-up, analogous and parametric estimating and alternative analysis; resource requirements, basis of estimates and resource breakdown structure; when there is a gap, do an alternative analysis first.
- Lesson 2: Acquire Resources: negotiate first, preassignment and multicriteria decision analysis. Collaborative negotiation, escalation when needed, and recruiting under the sourcing strategy (when external resources are needed, follow the procurement process; see Plan Sourcing Strategy); the three situations for preassignment; criteria, weights, scoring and weighted totals.
- Lesson 3: Outputs of Acquire Resources: assignments, team assignments, resource calendars and handling resource changes. The three core resource documents and the other updates; when a member is tied up, go to the functional manager; ways to acquire capability that is missing; conditions for using alternative resources.
- Lesson 4: Resource optimization and release: balance workload, match skills, release on time. Resource leveling and resource smoothing; the resource histogram; removing single points of dependency; releasing resources promptly when done.
Chapter map
Estimate Resources: resource management plan · schedule management plan · scope baseline · activity list · resource calendars …
- Tools: bottom-up · analogous · parametric · alternative analysis
- Outputs: resource requirements · basis of estimates · resource breakdown structure
Acquire Resources: negotiate → escalate through governance if beyond your authority; recruit under the sourcing strategy, and handle external resources through procurement (common exam practice: negotiate → escalate → recruit or procure; conditions in the stem take priority)
- Preassignment · multicriteria decision analysis (criteria, weights, scoring)
- Outputs: physical or virtual resource assignments · project team assignments · resource calendars
When a resource problem arises: establish the facts → negotiate → change
Resource optimization: balance workload · match skills · release on time
Lesson 1
Estimate Resources: Requirements, Basis and the Resource Breakdown Structure
Lesson overview
Plan Resource Management settled the approach; Estimate Resources has to answer the specific questions: what resources does the project need, how many, and when? It follows closely on schedule and cost: the activity list decides what is needed, the resource calendar decides when it can be used, and the estimates in turn affect schedule and cost. This lesson covers the inputs to Estimate Resources, the four estimating tools and the outputs (three core results plus project document updates), and what to do when requirements and available resources do not match. The next lesson covers how to get these resources.
What Estimate Resources does
The key benefit of this process is that it identifies the type, quantity and characteristics of resources required to complete the project. It also helps anticipate potential resource shortages or surpluses, allowing for proactive adjustments, and enhances the ability to manage resource allocation and usage risks. The process is performed once or at predefined points in the project, and is closely related to the Schedule performance domain; it must also be coordinated with cost estimating, so that resource estimates stay consistent with the budget and financial constraints. What is estimated covers team resources and the type and quantities of physical or virtual resources.
The main inputs are the resource management plan, the schedule management plan and the scope baseline, plus activity attributes, the activity list, the assumption log, cost estimates, resource calendars and the risk register. The activity list shows which activities need resources, the activity attributes provide resource information for each activity, and the risk register points out which risks will affect the choice and availability of resources. The resource calendar is the easiest to overlook. It identifies the working days and shifts during which each specific resource is available, including the start and end of normal business hours, weekends and public holidays, and it specifies when and for how long a resource will be available. It may also reflect experience, skill level and geographical location. If a senior engineer is on vacation for a week, you cannot schedule work for that week, and if test equipment is free only in a certain month, you need to know that in advance; both depend on the calendar.
Four estimating tools
| Tool | How it works | Strength | Limitation |
|---|---|---|---|
| Bottom-up estimating | Break the activity into smaller tasks, estimate each and add them up | Fine detail, accurate | Takes time |
| Analogous estimating | Use historical data from a similar project to estimate the current one | Quick and cheap | Rough; suited to when detailed information is limited |
| Parametric estimating | Calculate from a statistical relationship between historical data and variables, such as quantity of work multiplied by hours per unit | Quantifiable, reusable | Depends on data quality |
| Alternative analysis | Compare different resource combinations, such as a few senior people versus many junior people | Finds the balance between cost and schedule | Needs several options to be compared |
There are also expert judgment, project management information systems, meetings and interviews. PMBOK 8 also mentions artificial intelligence, predictive analytics, virtual reality, augmented reality, optimization techniques such as branch and bound and genetic algorithms, and quantitative estimating models such as the constructive cost model (COCOMO). The exam concentrates on the traditional techniques above; for the newer tools it is enough to know their names and uses.
Worked example
A renovation project for an older residential complex needs to estimate how much labor “exterior wall insulation” will take. Bottom-up: break it into four tasks (erecting scaffolding, preparing the base layer, bonding the insulation boards, finishing the surface), estimate person-days for each and add them, giving 180 person-days. Analogous: last year's similar complex actually took 160 person-days, and adding 10% for the larger area gives 176 person-days. The two figures are close, which suggests the estimate is fairly credible; if they differed greatly, you would go back to look for the reason, and you would record the basis.
Three outputs
The outputs of Estimate Resources are resource requirements, basis of estimates, the resource breakdown structure and project document updates; the first three are the core results, explained below. Resource requirements identify the types and quantities of resources required for each work package or activity (the specific working days, shifts and durations when a resource is available come mainly from the resource calendar; the resource requirements documentation may also record the assumptions made in determining availability), and they are passed to schedule development and cost estimating. The basis of estimates is the supporting documentation that explains clearly and completely how the resource estimates were derived, for example “extrapolated from the person-days of the last two similar modules, plus 20% for new requirements.” The resource breakdown structure (RBS) is a hierarchical representation of resources by category and type, which helps with acquiring, managing and reporting resources. Project document updates carry the new information found during estimating into the relevant documents, such as activity attributes, the assumption log, the lessons learned register and the risk register.
Key point
Estimating resources comes down to three things: when they are available (the resource calendar), whether they have the skills needed, and what they will cost. When there is a gap between requirements and available resources, do an alternative analysis first, comparing ways to fill the gap such as internal reassignment, external procurement, leasing or outsourcing, and then plan how to acquire the resources; do not cut scope first, and do not simply wait.
Worked examples
Example 1 A gap between the requirements list and available resources: what to do
A logistics company's warehouse system upgrade project is in the planning stage. The project manager compares the resource requirements list with the people and equipment available to assign and finds an obvious gap between them. What should the project manager do?
Show answer and explanation
Correct answer: A
The warehouse system upgrade project is in planning. The resource requirements list is done, and compared with the people and equipment available to assign there is an obvious gap. The question asks what the project manager should do; the point is the first step after a gap appears.
After Estimate Resources produces the resource requirements, if available resources fall short, you should first do an alternative analysis, comparing the cost and impact of ways to fill the gap such as internal reassignment, external procurement, leasing and outsourcing, and then plan acquisition accordingly, staying consistent with the resource management plan and other documents. A gap can be addressed with options at the planning stage, so the project manager should first come up with an analysis rather than give up the objective. The answer is A.
Why the other options are wrong
- B. Handing the gap straight to the sponsor to decide means no analysis was done first. The project manager should first propose ways to fill the gap and their impacts, then ask for support with evidence, rather than throw the problem over as it is.
- C. Cutting scope changes the project objectives. It is a choice to consider only after other options prove infeasible and it has been agreed with stakeholders; it is not the first reaction to finding a gap.
- D. Postponing the start does not fill the gap. It is just waiting, and it affects overall schedule and cost, so it does not count as a solution.
Key takeaway When there is a gap between requirements and available resources, do an alternative analysis and plan how to acquire them; do not cut scope or just wait.
Variation If the stem adds that “the cost of the options to fill the gap exceeds the approved budget,” the next step becomes communicating with the sponsor and, if necessary, submitting a change request; if only a certain skill is missing, consider training first.
Something wrong with this question?
Example 2 What kinds of information you need when estimating resources
The project manager of a city light show project is estimating resources and needs to collect information on each person and piece of equipment so that the resource plan can be carried out. Which set of information is MOST critical?
Show answer and explanation
Correct answer: B
The project manager of a light show project is estimating resources and needs to collect information on each person and piece of equipment so that the resource plan works in practice. The question asks which set of information is most critical, and the core is what you need to know in order to estimate resources.
Estimating resources answers three questions: when the resource is available and for how long (the resource calendar), whether it has the skills or experience needed, and what it will cost to use. Resource cost affects the choice in terms of both quantity and skill level, and these three kinds of information directly decide whether the plan can be carried out. The answer is B.
Why the other options are wrong
- A. Contract templates and payment terms belong to procurement management and are needed only after it is decided that a resource will be bought externally.
- C. Reporting relationships and performance appraisal belong to team management. Compared with resource calendars, skill requirements and usage costs, they are not the most critical information in estimating resources.
- D. Storage locations and approval procedures are execution-level details that can be arranged after the resources are settled. They are not core information for estimating resources.
Key takeaway Estimating resources comes down to three things: when they are available, whether they have the skills, and what they cost.
Variation If the stem asked “what are the outputs of estimating resources,” the answer would be resource requirements, basis of estimates, the resource breakdown structure and project document updates; if it asked which method to use “for a quick estimate when detailed information is limited,” that is analogous estimating.
Something wrong with this question?
Common traps
Common trap
- On finding a gap, the project manager should first analyze it and propose ways to fill it, and then ask the sponsor for support with evidence. Handing the gap straight to the sponsor passes the analysis work to someone else.
- Cutting scope or delaying the start are options for after the gap cannot be closed by resource measures; they are not the first reaction.
- Resource estimates and cost estimates must stay consistent, and cost is one of the factors that affect the choice of resources.
- Estimate Resources produces “what is needed and how much,” not “who will do it”; the specific people are decided in Acquire Resources.
Key takeaways
- Estimate Resources identifies the type, quantity and characteristics of resources, predicts shortages or surpluses, and is performed once or at predefined points.
- Inputs: resource management plan, schedule management plan, scope baseline, activity list, activity attributes, resource calendars, risk register and others.
- Tools: bottom-up, analogous and parametric estimating, and alternative analysis.
- Outputs: resource requirements, basis of estimates, resource breakdown structure, and project document updates (activity attributes, assumption log, lessons learned register, risk register and others).
- The resource calendar shows when and for how long a resource is available.
- When requirements and available resources do not match, PMBOK 8 lists alternative analysis as a tool of Estimate Resources. Common exam practice: usually analyze feasible ways to fill the gap first, then plan acquisition in line with the sourcing strategy; tailor the exact order to the situation.
Lesson 2
Acquire Resources: Negotiate First, Preassignment and Multicriteria Decision Analysis
Lesson overview
Estimate Resources tells us what is needed; Acquire Resources has to get it: it outlines and guides the selection of resources and assigns them to their respective activities. Acquire Resources here applies to team, physical and virtual resources; external resources are obtained separately, through partners, joint ventures or procurement. This lesson covers the inputs to Acquire Resources, how to approach a situation where you cannot get the people you need, preassignment, and how to choose when there is more than one candidate, using multicriteria decision analysis. Negotiation skills themselves are left to the next chapter.
What Acquire Resources does
The key benefit of this process is that it outlines and guides the selection of resources and assigns them to their respective activities. Based on the activity list, it obtains the team, physical or virtual resources needed to complete the project work, and it is performed periodically throughout the project as needed. By the time planning is done, the WBS and activities are settled and there is a rough idea of who will do each activity, but that does not mean those people can simply start: internal resources are assigned by functional managers or resource managers, so the project manager has to negotiate, and external resources are obtained through partners, joint ventures or procurement.
Failure to acquire the necessary resources may affect the schedule, budget, customer satisfaction and quality while increasing risk; insufficient resources or capabilities decrease the probability of success and, in a worst-case scenario, could result in project cancellation. So the project manager should collaborate fully, negotiate effectively and influence those who are able to provide the resources. The main inputs are the resource management plan, the procurement management plan, the cost baseline, the project schedule, resource calendars, resource requirements and the stakeholder register: the plans say when people are needed, the resource requirements say how many, the resource calendars say when they are free, and the stakeholder register says whom to talk to.
Three steps for getting people
PMBOK 8 requires that the project manager or project team collaborate, effectively negotiate and influence others who are able to provide the required team, physical or virtual resources. Failure to acquire resources may affect the schedule, budget, customer satisfaction and quality while increasing risk. If resources are not available, alternative resources, perhaps with different competencies, features or costs, may be used, but risks must be acknowledged and legal, regulatory, mandatory or other specific criteria must not be violated. In practice (common exam practice), when acquiring resources you negotiate with the appropriate resource owners according to the resource management plan and the sourcing strategy, escalate through governance any matter that exceeds the project manager's authority, and carry out recruiting, partnering or procurement according to the established sourcing strategy and organizational procedures.
Common exam practice: when the stem gives no other conditions, a common line of reasoning is “first negotiate with the resource owners (functional managers, other projects' project management teams, external organizations); if negotiation fails or the matter exceeds your authority, communicate upward and ask the sponsor to help; if that still fails, recruit or obtain external resources through the procurement process.” This is a rule of thumb for ordering the options in an exam question; in real work, the sourcing strategy and your authority still govern. If the stem says the sourcing strategy already specifies external procurement, or the problem clearly exceeds the project manager's authority, follow the conditions in the stem. When a question asks “who to negotiate with,” first think of the party who provides the resource; the sponsor can also be a party to negotiate with or to ask for support when the sponsor controls the resource or the problem exceeds the team's authority.
A related process is Plan Sourcing Strategy. It sits in the Governance performance domain and decides whether to use internal or external resources for different parts of a project, considering factors such as organizational culture, specialized skills, resource capacity, risk and the overall value proposition, and it documents the sourcing decisions, selection methods and contract types. It answers “should we outsource,” while Acquire Resources answers “how do the people and materials get in place.”
Preassignment
Preassignment means that when physical or team resources for a project are determined in advance, they are considered preassigned. There are three typical situations: specific people were committed in a competitive proposal, the project depends on the expertise of particular persons, or members have already been assigned in Initiating or in other processes. When the people have been fixed in advance, there is no need to compare and score candidates. A project charter that names a key specialist directly is a case of preassignment.
Multicriteria decision analysis
When there is more than one candidate, use multicriteria decision analysis. First establish evaluation criteria (common exam practice: commonly used criteria for selecting people include availability, cost, experience, ability, knowledge, skills, attitude and international factors). Before applying the criteria to the candidates, prioritize them and set weights. Then score each candidate against each criterion, multiply each score by its weight, add up the results and rank by total score.
Worked example
You are hiring a data analyst. Criteria and weights: experience 40%, availability 30%, cost 20%, communication 10%, each scored from 1 to 5 (the cheaper, the higher the score). Candidate A: experience 5, availability 2, cost 3, communication 4, total = 5×0.4 + 2×0.3 + 3×0.2 + 4×0.1 = 3.6. Candidate B: experience 3, availability 5, cost 4, communication 3, total = 3×0.4 + 5×0.3 + 4×0.2 + 3×0.1 = 3.8. B is slightly ahead. If the project values experience above all and the weights are changed to experience 60%, availability 10%, cost 20%, communication 10%, A scores 4.2 and B scores 3.4, and the conclusion reverses. This shows why the weights must be set before scoring: if you adjust the weights after seeing the results, the exercise loses its meaning.
Worked examples
Example 1 The charter names a key specialist: which approach is this
A smart agriculture project is developing its project management plan. The sponsor believes that the project's success depends on the guidance of an agronomy expert, and the project charter names a senior agronomist to join the project. Which of the following is this approach?
Show answer and explanation
Correct answer: B
A smart agriculture project is developing its project management plan. The sponsor believes success depends on an agronomy expert and has named a senior agronomist in the project charter. The question asks what this approach is, which requires distinguishing concepts related to acquiring resources.
Preassignment refers to project resources determined in advance. Typical situations include specific people committed in a competitive proposal, dependence on the expertise of particular persons, and team members already assigned in Initiating or another process before the initial resource management plan is completed. Here the sponsor directly named the person in the charter, and the project depends on that person's expertise, so it fits the description of preassignment. The answer is B.
Why the other options are wrong
- A. Physical resource assignments are an output of Acquire Resources that records materials, equipment, sites and other physical resources. They are about things, not people, and are not an approach.
- C. Multicriteria decision analysis is a technique for selecting people by weighted scoring against criteria, which requires comparing several candidates. Here the person was named directly, with no comparison.
- D. Project team assignments are also an output of Acquire Resources, recording team members and their roles and responsibilities. They are a result, not a way of naming people.
Key takeaway If the person was determined in advance (committed in a bid, specialized skills, named in the charter), it is preassignment.
Variation If the stem said “there are three candidates and they are scored and ranked on experience, availability and cost,” the answer would be multicriteria decision analysis; if it asked “where the preassigned person is recorded,” the answer is the project team assignments.
Something wrong with this question?
Example 2 The department assigns people and the project manager has no say: what to do
A retail group is forming a cross-departmental membership operations project team. Members are assigned by each department, and the project manager has no direct authority over who is chosen. What should the project manager do?
Show answer and explanation
Correct answer: C
The members of a membership operations project team are assigned by departments, and the project manager has no direct decision on who is chosen. The question asks what the project manager should do; in essence, what to do when the resources are in someone else's hands.
A project manager does not necessarily have the authority to choose people directly. In that case you rely on negotiation and influence: negotiate with the functional managers, explain the project's needs and value, and secure qualified people. When the required resources are controlled by others, acquiring them commonly requires negotiation with parties such as functional managers, other project teams and external organizations. The answer is C.
Why the other options are wrong
- A. Ground rules belong to the team charter and govern how team members behave. They are not a way to obtain members.
- B. Team building targets the members who are already in place and aims to build cohesion and improve performance. It does not solve the problem of “people who are unsuitable or have not arrived.”
- D. Co-location changes how and where people work. It does not solve whether suitable people can be obtained; co-location is a team-building tool and has no effect on who is chosen.
Key takeaway When you have no say over who is chosen, negotiate with the functional managers to secure qualified people. Negotiation is not only about securing people; you also explain needs, timing and the impact on the functional manager's department, aiming for a win-win.
Variation If the functional manager still will not release people after negotiation, the next step is to communicate with the sponsor to coordinate; if nobody internal has this skill, then consider recruiting or procuring external resources.
Something wrong with this question?
Common traps
Common trap
- In multicriteria decision analysis, the criteria are prioritized and weighted first, and only then are the candidates scored; if you look at the people before setting the criteria, the result is biased.
- Acquiring resources is not the same as assigning them directly. Common exam practice: when the project manager has no authority to assign directly and the resources are not preassigned, you would normally negotiate with the functional manager or resource manager; if the stem clearly says the project manager has authority to assign, the resources are preassigned or the sourcing strategy says otherwise, follow the stem.
- Preassignment is a state that was determined in advance, not the result of scoring and selecting; the physical or virtual resource assignments and the project team assignments are outputs of Acquire Resources, not methods.
- Acquire Resources covers team, physical and virtual resources; external resources are obtained through partners, joint ventures or procurement, and in common exam practice this normally comes after internal negotiation.
Key takeaways
- Acquire Resources outlines and guides the selection of resources and assigns them to activities, and is performed periodically throughout the project as needed.
- When acquiring resources, negotiation is an important technique; the usual parties are functional managers, other project management teams and external organizations (common exam practice).
- Common exam practice: if negotiation fails, escalate to the sponsor, and if that still fails, recruit or procure; the conditions in the stem take priority.
- Preassignment: specific people committed in a competitive proposal, dependence on particular expertise, or already named in the charter.
- Multicriteria decision analysis: set the criteria, set the weights, score, then weight and rank.
- Plan Sourcing Strategy decides between internal and external resources and sits in the Governance performance domain.
Lesson 3
Outputs of Acquire Resources: Assignments, Team Assignments, Resource Calendars and Handling Resource Changes
Lesson overview
Once the resources are agreed, the outcome has to be recorded for later use in scheduling, cost and leading the team. Resources also often change after they arrive: key people get tied up, are absent, go on vacation or are reassigned. This lesson covers the three main outputs of Acquire Resources, and then the approach for handling resource shortages or changes: establish the facts first, then negotiate, and only then change. The previous lesson covered how to get people; the next covers how to use resources evenly.
Three main outputs
Acquire Resources has three main outputs:
| Output | What it records | Who uses it |
|---|---|---|
| Physical or virtual resource assignments | Materials, equipment, supplies and sites the project will use, and virtual resources such as software, test environments and licenses | Procurement, logistics, site management |
| Project team assignments | Team members and their roles and responsibilities on the project; the documentation may include a project team directory | Leading the team, communication |
| Resource calendars | On which days and shifts each resource is available, taking account of rest days and public holidays | Schedule development, resource leveling |
The resource calendar must honestly reflect vacations, training and local holidays, and scheduling is based on it. Members who take part part-time have scattered and changing availability; only if it is recorded in the resource calendar and kept up to date can the project manager know clearly who can take part when and for how long.
Acquire Resources may also produce change requests and updates to the resource management plan, cost baseline, project schedule, resource breakdown structure, resource requirements, risk register and stakeholder register, as well as to enterprise environmental factors (for example the availability of resources within the organization) and the lessons learned register.
Handling resource shortages or changes
When there is a resource problem, common exam practice is to “establish the facts first, then negotiate, and only then change.” A change request is raised only when the plan or a baseline really has to change.
- A key resource will be absent: first assess the actual impact on the schedule, then decide how to reassign.
- The provider has not confirmed that the resource will be in place: look at the resource management plan first, then decide whether to negotiate, escalate or change.
- A member is tied up by the functional department: first negotiate with the functional manager the member's time on this project and its priority.
- A resource is tied up by another project: first negotiate with that project's project manager or with the functional manager.
- To find out when someone is free: check the resource calendar; this is not a matter for negotiation.
When capability is insufficient, first assess the capability gap, then choose how to acquire it from reassignment, training, outsourcing and recruiting. If nobody internal really has it and external resources are needed, go back to the sourcing strategy and obtain them externally through the organization's procurement process (see Plan Sourcing Strategy in the Governance performance domain for the procurement process). For a short-term specialist need, consider borrowing a person or outsourcing in light of cost, availability, risk and the overall value proposition, and avoid taking on long-term staffing commitments without a long-term need; training time must be included in the plan. If the required resources cannot be acquired because of economic factors or assignment to other projects, the project manager or project team may be required to assign alternative resources, perhaps with different competencies, features or costs. Alternative resources are allowed if risks are acknowledged and legal, regulatory, mandatory or other specific criteria are not violated, and the consequences of the missing resources should be documented in the schedule, budget, risk, quality and training plans.
Worked example
An online course development project has two designers in the art group who can each commit only 50% of their time; the rest goes to poster work for their home department. The project manager records the two designers' available dates each week in the resource calendar and finds that in week 5 their home department is running a big promotion and both will be almost completely tied up. So he negotiates early with the functional manager: the course cover designs are completed two weeks early, and the manager is asked to keep at least one day per designer free in week 5. This respects the other department's business rhythm and also protects the project schedule.
Worked examples
Example 1 Part-time members: how to know clearly who is available when
A chain of training centers launches an online course development project. Members come from instructional design, art, technology and other departments, and the project takes up only part of their time; the rest of the time they work as scheduled by their home departments. The project manager wants to know clearly when each member can take part and for how long. What should be done?
Show answer and explanation
Correct answer: C
The members of an online course development project come from several departments, and the project takes only part of their time; the rest follows their home departments' schedules. The question asks how to know “clearly” when each member can take part and for how long, so the point is knowing availability.
A resource calendar records, resource by resource, the working days, shifts and leave, and shows when a team member is available and for how long. Part-time members' available time is scattered and changes, and only if it is recorded in the resource calendar and kept up to date can the project manager know it clearly, which also helps with scheduling and resource assignment. The answer is C.
Why the other options are wrong
- A. Having the sponsor negotiate hours addresses “whether the resource can be given.” It does not produce a record of available time that can be checked at any time.
- B. The team charter sets out values, how to communicate and decide, ground rules and so on. It is not a tool for recording members' available time.
- D. Verbal agreements with functional managers one by one produce no record and can change at any time, so the project manager still does not know who is available when.
Key takeaway To know who can work when, look at the resource calendar; negotiation can only secure resources and cannot replace a record.
Variation If the question asked “what to do when a member is tied up by another department and cannot attend,” negotiate hours with the functional manager; if it asked “what is the basis for scheduling,” the basis is likewise the resource calendar.
Something wrong with this question?
Example 2 A member misses the regular meeting: what should the project manager do
On a smart home development project, the project manager finds that a test engineer has repeatedly missed project meetings and learns that he has been busy with maintenance tasks assigned by his functional manager and has not been working on this project. What action should the project manager take?
Show answer and explanation
Correct answer: D
On a smart home project, a test engineer has repeatedly missed project meetings, and it turns out he has been doing maintenance tasks assigned by his functional manager. The question asks what action the project manager should take.
The member's time is being claimed by both the functional manager and the project. The root is a conflict in resource allocation, not the member's own attitude. The project manager should communicate and negotiate with the functional manager to clarify this member's hours and priority on the project, so that he can truly take part. The answer is D.
Why the other options are wrong
- A. Removing the member does not solve the project's need for this role. It may delay the schedule and would cause dissatisfaction in the team.
- B. A performance appraisal is an after-the-fact evaluation that cannot bring the member back to project work now, and responsibility does not lie with the member, so recording it in the appraisal would be unfair.
- C. Asking other members can only corroborate. The stem already explains why he is absent, and what is needed is direct communication with the functional manager, not further inquiry.
Key takeaway When a member is tied up by the functional manager, negotiate hours with the functional manager rather than dealing with the member personally.
Variation If the functional manager will not adjust the hours, communicate with the sponsor to coordinate; if the member truly cannot be spared, evaluate alternative resources or adjust the schedule.
Something wrong with this question?
Common traps
Common trap
- The resource calendar must honestly reflect vacations, training and local holidays, and scheduling is based on it; it answers “when is the resource available” and is not something to be negotiated.
- When resources are pulled away, first assess the impact on both sides and then negotiate formally; talk to the member before moving them, and when a member is absent, do not start with discipline or removal.
- When resources fall short, first clarify the need and seek support from stakeholders; do not start by logging a risk, changing a baseline or cutting scope.
- What you need to resolve is “who is taking up the member's time.” When the member is tied up by the functional department's work, you mainly negotiate with the functional manager; when tied up by another project, with that project manager or the functional manager. Negotiate primarily with whoever controls the competing allocation (the functional manager or the other project's project manager), while consulting the affected member as appropriate.
Key takeaways
- The three outputs of Acquire Resources: physical or virtual resource assignments, project team assignments and resource calendars.
- The resource calendar shows available dates and shifts and must honestly reflect vacations and training.
- When a resource problem arises: establish the facts first, then negotiate, and only then change.
- A member tied up by a functional department: negotiate hours and priority with the functional manager; a resource tied up by another project: negotiate with that project manager or the functional manager.
- When capability is insufficient, assess the gap first, then choose among reassignment, training, outsourcing or recruiting.
- If alternative resources may have to be used, risks must be acknowledged and legal, regulatory, mandatory or other specific criteria must not be violated.
Lesson 4
Resource Optimization and Release: Balance Workload, Match Skills, Release on Time
Lesson overview
Once the resource plan is done and people are in place, you often see this: one person is at full load for weeks while others wait for work; equipment arrives early but the site has not been handed over; a key expert goes on vacation and nobody can cover. This lesson is built around three resource management actions: balancing workload, matching skills and releasing on time (the resource optimization techniques in PMBOK 8 are resource leveling and resource smoothing), and how to deal with single points of dependency and shared resources. The first three lessons covered estimating, acquiring and the outputs; this one covers how to use resources well once you have them. Day-to-day monitoring and correction of physical and virtual resources continue in the chapter on monitoring resources, while team members' workload, skills matching and handover of cover are dealt with under leading the team.
Resource leveling and workload balancing
The resource optimization technique is a technique in which activity start and finish dates are adjusted to balance demand for resources with the available supply. Resource leveling, one of these techniques, adjusts the project schedule to optimize the allocation of resources and may affect the critical path. It can be used when shared or critically required resources are available only at certain times or in limited quantities, when resources are overallocated (a resource assigned to two or more activities during the same time period), or when there is a need to keep resource usage at a constant level. Available float is used for leveling resources, so the critical path may change. Resource smoothing uses only free and total float without affecting the critical path, so the completion date is not delayed.
The resource histogram shows resource demand over time and makes overloads and conflicts easy to see: compare the demand shown by the bar height with resource availability or a preset resource limit, and the weeks that exceed availability or show allocation conflicts are where balancing is needed. However good the resource plan is, it has to be considered together with the schedule, because leveling can change both the duration and the critical path.
Tasks and skills need to match, and a mismatch calls for reassignment: a member who is good at data analysis spends long periods tidying documents while a member who is good at testing is drawing interface sketches, which wastes capability and slows quality. If one person is overloaded and another idle, rebalance the work assignments and avoid depending on individuals. Long-term overtime is not sustainable; assess the workload and adjust the plan or bring in help. Assign more resources at demand peaks and fewer in troughs; acquire resources when they are needed, and if the timing is mismatched, adjust the acquisition time.
Worked example
On a venue construction project, the equipment rental company can deliver in June, but the venue will not be handed over until August; installation can start only after handover, and rent runs from the delivery date. If you accept delivery as offered, the equipment sits idle for two months and you pay two months of extra rent. The more sensible approach is to negotiate delivery for early August so that the acquisition time matches the time of need; it is not to take delivery early as a buffer, nor to force installation earlier just to put the equipment to use.
Single points of dependency and shared resources
When a key member's vacation or departure date is known, plan replacements and handover in advance to remove the single point of dependency. When several teams share a scarce expert, coordinate the schedule and manage the dependencies, for example by arranging a common review window rather than every team joining the queue whenever it likes. When resources are contested among several projects, agree priorities and allocation rules and use resources according to those rules. When a shared resource affects interdependent projects, assess availability first and then draw up a plan for adding resources.
Release on time
When resources have finished their work they should be released promptly so that other work in the organization can use them. For physical and virtual resources, the Monitor and Control Resourcing process in PMBOK 8 stresses that they should be assigned and released at the right time, right place and in the right amount, and released when no longer needed; team members are addressed in Lead the Team. Where idle time results from waiting for resources, reduce it by optimizing the schedule.
Key point
The three resource management actions in this lesson are balancing workload, matching skills and releasing on time; the resource optimization techniques in schedule development are resource leveling and resource smoothing. When you find that assignments can be improved, proactively review the proposed reassignments; if they would affect an approved baseline or controlled plan component, obtain approval through change control before implementing them. Do not ignore an improvement opportunity merely because the plan has been approved.
Worked examples
Example 1 Equipment arrives early and the site is handed over late: how to adjust
An exhibition engineering company takes on a venue construction project. The equipment rental company can deliver in June, but the venue will not be handed over until August; installation can start only after handover, and the rental period runs from the delivery date. The project manager finds that the time of acquiring the equipment does not match the time it is needed. What should the project manager do?
Show answer and explanation
Correct answer: B
On a venue construction project, the rental company delivers equipment in June, but the venue is handed over only in August, installation can start only after handover, and rent runs from the delivery date. The equipment would sit idle for two months while rent is paid.
Resources should be acquired when they are needed and released when they are not, to avoid the waste of occupying them early. Installation cannot be moved earlier, so adjust the acquisition time for the equipment to match the delivery date to the installation need, which avoids paying extra rent and does not affect construction. The answer is B.
Why the other options are wrong
- A. Taking delivery early and treating the idle time as buffer means paying two extra months of rent, and this buffer is not something the project needs.
- C. Moving installation as a whole forward to June is impossible: the venue is not handed over until August, and installation can start only after the venue is ready.
- D. The quantity of equipment is determined by installation needs, and reducing it would affect construction. It would also still mean acquiring early and does not solve the timing mismatch.
Key takeaway Acquire resources when they are needed; when acquisition and demand do not match in time, adjust the acquisition time.
Variation If the venue is handed over early while the equipment arrives late, negotiate with the rental company for earlier delivery or look for substitute equipment; if idle equipment cannot be avoided, consider subleasing it or releasing it early.
Something wrong with this question?
Example 2 Reassigning tasks would finish earlier: what to do
A project manager has just taken over a development project for smart home devices. The WBS has been built and the activities assigned to members. He finds that some activities would be done faster if given to other members. If the current assignments are kept, the project is expected to be 3 weeks late. What should the project manager do?
Show answer and explanation
Correct answer: D
A project manager has just taken over a development project for smart home devices. The WBS is built and activities are assigned. He finds that some activities would be done faster by other members, and keeping the present assignments means a 3-week delay.
Some members can complete certain activities faster, which is an opportunity to improve the schedule. The project manager should proactively review the proposed reassignments; if they would affect an approved baseline or controlled plan component, submit a change request and obtain approval before implementing them. An approved plan does not mean it cannot be optimized. The answer is D.
Why the other options are wrong
- A. Leaving the original assignments untouched and crashing other activities fails to use a ready-made opportunity, and it brings extra cost or risk.
- B. Asking for overtime when a better arrangement exists trades the team's rest time for schedule. It is not sustainable and is not the best approach.
- C. “The plan has been approved so keep it as is” is a rigid reading. When you find an opportunity, use it through the change control procedure and do not turn a blind eye.
Key takeaway When task assignments can be improved, proactively review the proposed reassignments; if they affect an approved baseline or controlled plan component, obtain approval before implementing them.
Variation If the stem were changed to “a member on the critical path is overloaded,” consider resource leveling or adding resources; if the reassignment affects the cost baseline, a change request must be submitted before it is carried out.
Something wrong with this question?
Common traps
Common trap
- Resource leveling can change the critical path and the duration; resource smoothing uses only float and does not change the critical path. Do not mix them up.
- Resources that arrive early create idle costs; acquire resources when they are needed, and if the timing is mismatched, adjust the acquisition time rather than taking delivery early as a buffer.
- When you find that assignments can be improved, proactively review the proposed reassignments; if they affect an approved baseline or controlled plan component, obtain approval before implementing them. Do not ignore the opportunity because the plan was approved or rely on overtime to cope.
- The purpose of the resource histogram is to show resource demand over time and spot overloads, not to show cost trends.
Key takeaways
- Resource leveling balances resource supply and demand by adjusting the schedule and may affect the critical path; resource smoothing uses only float and does not affect the critical path.
- The resource histogram shows resource demand over time and is used to spot overloads.
- Tasks should match skills; when overload and idleness coexist, rebalance.
- Remove single points of dependency: plan cover and handover in advance; for shared resources, agree priorities and rules.
- Acquire resources when they are needed and release them promptly when done.
- When assignments can be improved, review the proposed reassignments; if they affect an approved baseline or controlled plan component, obtain approval through change control before implementing them.
This chapter has 43 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.