Resources and Team

Negotiation

PMP · Resources and Team · 2 lessons · about 23 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Most of the resources a project manager needs do not belong to the project manager: people work for functional managers, experts are on other projects, and equipment has to be rented from outside. Getting them usually takes collaboration, negotiation and influence, and external resources may also be obtained through partners, joint ventures or the procurement process. Negotiation is a discussion aimed at reaching an agreement, used to achieve support or agreement and to resolve conflicts within the team or with other stakeholders. The chapter has two lessons. Lesson 1 covers the purpose of negotiation, three parties used in common exam practice (functional managers, other projects' management teams and external organizations), who leads, and the order of negotiation and escalation to the sponsor. Lesson 2 covers preparation before negotiating, techniques during negotiation, and how negotiation applies to acquiring resources, procurement contracts and conflict resolution.

On the exam, negotiation usually appears in scenarios such as resources being tied up, key people being pulled away and terms being discussed with a supplier. The answers have this in common: prepare first (when key people are pulled away, assess the impact on the project first), then negotiate, and use the value of the project to influence the other side. PMBOK 8 notes that escalation is often useful in hierarchical organizations, where decision-making authority includes people outside the project team or where higher-ranking individuals are better able to remove persistent obstacles; whether to escalate depends on authority and the established escalation criteria. Common exam practice: when the stem gives no other conditions, escalate only after negotiation fails.

Lessons in this chapter

Chapter map

Acquiring resources hits a block

  • Negotiation: functional managers · other projects' management teams · external organizations (goal: win-win) Prepare: objectives · bottom line · best alternative · the other side's interests · rank priorities first Conduct: focus on interests · conditional concessions · influence through value
  • If negotiation fails → escalate to the sponsor according to authority and escalation criteria (common exam practice)
  • If that still fails → use alternative resources, or recruit or procure external resources (per the sourcing strategy and authority)

Procurement disputes: alternative dispute resolution methods as specified in the contract (negotiation, mediation, arbitration, dispute review boards or expert determination) → litigation (the courts) only after all other means fail

Lesson 1

Purpose and Parties of Negotiation: Whom to Ask for Resources, with a Win-Win Goal

Lesson video

Lesson overview

Most of the resources a project manager needs do not belong to the project manager: people work for functional managers, experts are on other projects, and equipment may have to be rented from outside. Getting them depends on negotiation. This lesson covers what negotiation is, why it is the first choice when acquiring resources, the three parties in resource negotiations, who leads, and how it differs from escalating to the sponsor. The next lesson covers preparation, techniques, and specific applications to resources and procurement.

What negotiation is

Negotiation is a discussion aimed at reaching an agreement. It is used to achieve support or agreement that supports the work of the project or its outcomes and to resolve conflicts within the team or with other stakeholders. Negotiation among team members is used to reach consensus on project needs, and it can also build trust and harmony. In Acquire Resources, PMBOK 8 says that the project manager or project team should collaborate, effectively negotiate and influence others who are able to provide the required resources. So negotiation is both a tool and a skill.

When the resources are in another department's hands, the other side may not be willing to release them, and may not be able to. Giving orders alone often does not work; you have to negotiate so that the other side sees the value of the project. This is why, when acquiring resources, the ability to influence others is as important as political skill in the organization. When acquiring resources, you usually negotiate first (common exam practice; there is no fixed order, and alternative resources, recruiting or procurement are still chosen according to the sourcing strategy and authority). What negotiation aims for is a win-win result that achieves the project's objectives while benefiting both sides, not overpowering the other party.

Three parties to negotiate with

For resource negotiations, PMBOK 8 says the project manager or team should “collaborate, effectively negotiate, and influence” those who can provide the required resources; internal resources are assigned by functional managers or resource managers. The three parties below reflect common exam practice. The actual party depends on who owns or can coordinate the resource needed, and may also include resource managers, partners, suppliers and others:

PartyWhat you negotiateExample
Functional managersAssignment of internal people, so the project gets the most suitable resources within the required timeAsk the testing department to release a senior engineer
Other projects' management teamsSecuring scarce or special resources, or coordinating when a shared resource is usedStagger the periods an expert is used with another project
External organizationsTeam, physical or virtual resources that are not available internally, are scarce, certified or otherwise specialNegotiate expert support with a consulting firm
The three parties in resource negotiation

PMBOK 8 defines negotiation as a discussion held to achieve support or agreement, and it applies to interactions with stakeholders. The sponsor is itself an important stakeholder and may also be responsible for obtaining and providing resources, so you can negotiate with any stakeholder who can provide or coordinate resources, including the sponsor. When the problem goes beyond the project manager's authority or needs a higher-level decision or removal of an obstacle, escalate according to governance.

Exam tip: when a question asks “who to negotiate with” and the options include resource owners such as the functional manager, normally choose the resource owner first; the sponsor and the program manager (escalation) come into play only when the question asks what to do “after negotiation fails” or when the matter is “beyond your authority.”

Who leads

Resource negotiations are usually conducted by the project manager or project team (the Acquire Resources section of PMBOK 8 says the project manager or project team should negotiate effectively). Procurement negotiation is different: the negotiation should be led by a member of the procurement team who has the authority to sign contracts, while the project manager and other members of the project management team may be present to provide assistance as needed. Procurement negotiation concludes with a signed contract document or other formal agreement that can be executed by both buyer and seller. PMBOK 8 also lists networking as a tool: establishing connections and relationships with other people from the same or other organizations for the purpose of exchanging information and developing contacts. It gives project managers and their teams access to informal organizations to solve problems, influence the actions of stakeholders and increase support for the project. The relationships you keep up in ordinary times often decide whether the other side is willing to sit down with you at negotiation time.

Worked example

A software company is organized functionally. The testing department manager for a warehouse system project does not know the project's prospects and has sent the engineers to another project, so verification work cannot start. The project manager does not ask the sponsor to give an order; instead she arranges a meeting with the manager. She first explains that the warehouse system is one of the company's priority projects this year, then shows that the verification delay will affect the customer's go-live date, and finally proposes that she needs only two engineers for three days each, with the rest of their time still belonging to the testing department. The manager sees the project's value to the whole company, and since his own department's business is not affected, he agrees.

Negotiation versus escalation: which comes first

Negotiation is not a cure-all, so you need to know where it fits. PMBOK 8 says the project manager or project team should collaborate, effectively negotiate and influence those who can provide the required resources. Negotiating first, and escalating through governance only when the matter exceeds your authority or a persistent obstacle needs higher-level handling, is common exam practice; alternative resources, recruiting or procurement are chosen according to the sourcing strategy, constraints and approved changes.

Common exam practice: when the stem gives no other conditions, the line of reasoning when you cannot get a resource is “negotiate with the other side first; if that fails, communicate with the sponsor to coordinate; if that still does not work, obtain external resources through recruiting or procurement.” Note the precondition of this line of reasoning: escalating directly without negotiating first is usually seen in scenario questions as failing in the project manager's responsibility, while continuing to delay after negotiation has clearly failed wastes schedule time. Words such as “first” or “first step” in a question usually point to negotiation; escalation comes in only with “after negotiation fails.” If the stem says the problem exceeds your authority, or the sourcing strategy already calls for external procurement, handle it according to the stem.

Worked examples

Example 1 Functional organization: a resource is diverted by the functional manager

Question 1Example

PMLyceum is a functional organization developing a warehouse management system. The functional manager of the testing department, who does not understand the project's business value, assigned the department's test engineers to support another project, so verification work on this project cannot start and the delivery date is in danger. What should the project manager do to resolve the problem?

Show answer and explanation

Correct answer: C

In a functional organization, the testing department's functional manager does not understand the project's business value and has assigned test engineers to support another project, so verification on this project cannot start. The question asks what to do to resolve the problem.

In a functional organization, people come under the functional manager, and the project manager secures resources through negotiation and influence, not orders. The manager moved the people because he does not understand the project's business value, so the most targeted approach is to negotiate with him directly, explain the project's value and the consequences of delay, and secure more people. Negotiation is the first choice when acquiring resources. The answer is C.

Why the other options are wrong

  • A. The sponsor can help obtain resources and resolve issues beyond the project management team's authority, but the project manager has not first negotiated with the functional manager who controls the assignment of people. Asking the sponsor at once to demand their return would damage the relationship and is not the first choice.
  • B. Contacting the test engineers directly and asking them to transfer goes around the functional manager. In a functional organization the project manager has no power to move a department's people, and where the engineers go is decided by the functional manager.
  • D. Changing the schedule baseline requires the change control procedure, and the project manager cannot push the date back alone. It also merely accepts that the resources are tied up and does not resolve the resource problem.

Key takeaway When resources are in the functional manager's hands, negotiate with him first and influence him with the project's value, rather than skipping a level or changing the baseline.

Variation If the stem added that “the functional manager still refuses after negotiation,” the next step is to communicate with the sponsor to coordinate; if the organization were a matrix, the thinking is the same and you still go to the functional manager first.

Something wrong with this question?

Report an issue with this question

Example 2 An expert leaves: how to fill the resource first

Question 2Example

A company hires a project manager for an innovative product project, with a team made up of internally assigned core staff and external experts. During execution, an industry expert assigned from a functional department resigns for personal reasons, and his departure will slow the project. What should the project manager do to prevent the departure from delaying the schedule?

Show answer and explanation

Correct answer: D

On an innovative product project, the team consists of internally assigned core staff and external experts. During execution, an industry expert assigned from a functional department resigns and his departure will slow the project. The question asks what to do to prevent a schedule delay, and the core is filling the resource gap.

To prevent a schedule delay, the gap has to be filled, that is, the resource has to be acquired again. This expert was assigned from a functional department, so filling the gap depends on negotiation: discuss with the functional manager and ask him to provide or recommend a person of comparable caliber (for an external resource, go through the procurement department or the supplier), adding an expert of equal level. The answer is D.

Why the other options are wrong

  • A. Crashing compresses the schedule, making up for the loss with more effort from others, but what is missing is an expert whom others cannot necessarily replace, and it adds cost and risk.
  • B. Adding people means first negotiating with the party that provides the resource, and this expert came from a functional department. Pushing a problem you should first tackle yourself to the sponsor is slow and passive; the sponsor needs to step in only when the matter exceeds the project manager's authority.
  • C. Cutting lower-priority features reduces scope and does not add a resource, nor does it guarantee that the expert's departure will have no effect on the schedule. It also needs CCB approval, which takes time.

Key takeaway After a key person leaves, fill the resource gap first by negotiating with the functional manager, and only then consider crashing or cutting scope.

Variation If the expert had been hired externally under a contract, go to the procurement department or the original supplier to replace him; if nobody of the same level exists inside the organization, evaluate training existing members or external recruiting.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When the resource is in the functional manager's hands, negotiate with that manager first. Do not skip a level to the sponsor, contact the member directly or change the baseline.
  • The common parties are functional managers, other projects' management teams and external organizations (common exam practice). Asking the sponsor for help is escalation when the matter exceeds your authority, but you can also negotiate when the sponsor controls the resource (exam tip: when asked for the “party to negotiate with,” choose the resource owner first).
  • Negotiation aims for a win-win. Pulling rank and persuading with business value are two ways of pressing your case, and the latter is more effective.
  • Resource negotiations are usually conducted by the project manager or project team (PMBOK 8: negotiate effectively); procurement negotiations are led by a procurement team member with authority to sign contracts.

Key takeaways

  1. Negotiation is a discussion aimed at reaching an agreement, used to achieve support, reach consensus and resolve conflicts.
  2. When acquiring resources, negotiate first; the goal is a win-win.
  3. Parties: functional managers, other projects' management teams, external organizations (common exam practice).
  4. Asking the sponsor for help when the matter exceeds your authority is escalation; common exam practice: escalate only after negotiation fails.
  5. Resource negotiations are usually conducted by the project manager or project team; procurement negotiations are led by a procurement team member with authority to sign contracts.
  6. Networking helps the project manager influence stakeholders and build support for the project.

Lesson 2

Preparing for Negotiation, Techniques, and Applications to Resources and Procurement

Lesson video

Lesson overview

Knowing whom to negotiate with is not enough; you also need to know how. Negotiation is not “we'll see when we meet”: beforehand you need to be clear about your objectives and bottom line, during the talks you focus on the other side's interests and not on positions, and concessions need a rhythm. This lesson covers preparation and techniques, and then how negotiation applies in three settings: acquiring resources, procurement contracts and negotiating conflicts. The previous lesson covered the parties and purpose; together the two lessons cover the main ways negotiation is tested on the exam.

Four things to be clear about before negotiating

In preparation, be clear about at least four things (common exam practice). First, your own objectives: what you want most, what you must get and what you can give up. Second, your bottom line: the terms below which you will not accept. Third, your best alternative, that is, your best fallback if negotiation fails: with a fallback you negotiate from strength and know when to stop. Fourth, the other side's interests and constraints: why they hesitate, whether they are short of people themselves or fear that their department's work will suffer.

Preparation also has an internal step: before negotiating, clarify priorities with stakeholders and rank your objectives, so that you can protect your core interests when you compromise. If you decide only halfway through the talks what matters, you are making concessions in a hurry under pressure. If during negotiation a proposal emerges that may affect documents, deliverables or baselines, a change request can be raised and evaluated through the process (PMBOK 8: a change request is a formal proposal to modify any document, deliverable or baseline, and any stakeholder may submit one); a baseline must not be modified directly without approval. Common exam practice: first communicate and clarify the proposal and assess its impact; once it becomes a change proposal requiring formal review, raise a change request under the change management plan, and do not implement it or modify a baseline before approval. Whether negotiation precedes the change request depends on the scenario.

Conduct during negotiation

The following reflect common exam practice. Focus on interests and do not get stuck on positions. A position is “this person cannot be given to you”; an interest is “if he leaves, nobody can pick up my deliverables this month.” Only by understanding the interest can you find a solution that suits both sides, such as letting the other side keep part of the person's time, or having the project supply staff to cover. When assigning people runs into resistance, first understand the reasons behind the functional manager's attitude, then discuss solutions. Make concessions with conditions and at a measured pace: in stages, in exchange, with each concession matched by a concession from the other side, and without showing all your cards at once. Influencing the other side through the project's business value is more effective than pressing with authority.

Preparing for and conducting a negotiation

Worked example

A project needs a senior test engineer for three days a week, and the functional manager says his department has a release coming. The project manager does not say “the project matters more.” She first asks when the release is, then proposes: two days a week for the first two weeks, rising to three days after his department ships; and in the meantime the project team will write a regression test script for his department. The other side's interest (shipping on time) and the project's interest (having senior people) are both taken care of.

Applications in resources and procurement

When acquiring resources: in a matrix organization, if a key person is pulled away and the impact is already clear, negotiate with the functional manager to get the person back; if the impact is not yet known, assess it first, then negotiate or consider other options; to win people from other projects, negotiate with the functional manager on the basis of project value; for internal resources, the first step is to negotiate with the functional manager (common exam practice; PMBOK 8 notes that internal resources are assigned by functional managers or resource managers, and that external resources can be obtained through partners, joint ventures or the procurement process, with the source decided according to the resource management plan, availability and the sourcing strategy); when there is disagreement with a department over adding people, use negotiation and conflict management skills, and in common exam practice outside hiring comes after internal negotiation, though if the established strategy prefers internal resources, consider outside hiring or procurement under the sourcing strategy only when internal resources are unavailable; when a key member is pulled away, first establish the impact if it is not already clear, then communicate it and negotiate a solution, with escalation and blame coming later; when a shared person is contested by several projects, resolve the conflict in priorities by continuing to communicate with the other projects' stakeholders.

In procurement: procurement negotiation clarifies the structure, rights and obligations of the parties and other terms of the purchases so that mutual agreement can be reached prior to signing a contract, and the final document language reflects all agreements reached. When a disagreement or claim arises in procurement, you generally first use direct negotiation (the PMBOK 8 appendix on procurement lists negotiation, direct discussion without third-party intervention, as one type of alternative dispute resolution, ADR); if that does not resolve it, then use methods that bring in a third party as the contract specifies, such as mediation, arbitration or a dispute review board; litigation is normally the last option, when all other means are exhausted. For acquiring resources, common exam practice is similar: negotiate, escalate, then recruit externally; but the actual order of negotiation, escalation and external acquisition depends on the governance structure, authority, urgency, the resource management plan and organizational policy.

In negotiating conflicts: negotiation is also one means of conflict management. When the parties in conflict each give up something to reach a solution, that is compromise; when both sides work together to find a solution that benefits everyone, that is collaborating (problem solving), which is usually the first choice. When a resource conflict arises, such as two functional managers competing for the same member's time, the project manager negotiating directly with both functional managers to agree on the time the person will commit that both can accept is more effective than escalating or handing it to a subordinate.

Worked examples

Example 1 Negotiating with a key supplier: how to protect core interests

Question 1Example

A project manager is preparing to negotiate a supply agreement with a key supplier. The situation is complex, neither side can get everything it wants, and compromise may be needed to avoid schedule delays, cost overruns and reputational damage. To obtain an outcome that benefits the project, what should the project manager do?

Show answer and explanation

Correct answer: B

A project manager is preparing to negotiate a supply agreement with a key supplier. The situation is complex, neither side can have everything it wants, and compromise may be needed. The question is about the preparation needed to obtain an outcome that benefits the project.

To compromise in a negotiation, you must know in advance which interests you cannot give up and which you can. So before the negotiation, analyze priorities with stakeholders, rank the objectives by importance, and separate the bottom line, the expectations and the parts you can concede. Then you can make concessions on a reasoned basis and protect the project's core interests, avoiding schedule delay and cost overruns. The answer is B.

Why the other options are wrong

  • A. Revealing priorities midway means doing the preparation at the negotiating table. It invites hasty concessions under pressure and exposes your hand.
  • C. Setting objectives before negotiating is fine, but fixing them and following them strictly in the negotiation removes the room to concede and to adapt, particularly when the situation is complex.
  • D. Adjusting your priorities at any time as the negotiation develops lacks internal consensus, is high risk and is easily exploited by the other side. This should be done before negotiating.

Key takeaway Before negotiating, clarify priorities with stakeholders and rank your objectives, so that you can protect your core interests when you compromise.

Variation If the stem asked “what to do when negotiations reach a deadlock,” the approach is to go back to the parties' interests and look for a win-win solution or concessions in stages; if the negotiation fails, consider the best alternative.

Something wrong with this question?

Report an issue with this question

Example 2 Matrix organization: a key person is pulled away, what to do first

Question 2Example

A project manager is responsible for a project delivered to a strategic customer. While verifying resource availability in a matrix organization, the project manager finds that a key person has already been moved to another project inside the company and confirms that this will jeopardize the planned project start. What action should the project manager take NEXT?

Show answer and explanation

Correct answer: B

The organization is a matrix, and the project is delivered to a strategic customer. While verifying resource availability, the project manager finds that a key person has already been moved to another project in the company and confirms that this will jeopardize the planned project start. The question asks what the project manager should do next.

In a matrix organization, the project manager usually needs to negotiate with the functional manager who has the authority to manage or assign the person; the specific authority depends on the type of matrix and the governance arrangements. On finding that a key person has been moved, the project manager should proactively acquire the resource, and the first step is to negotiate with his functional manager to try to get him back, explaining how important this person is to a strategic customer's project. Consider other options only if negotiation fails. The answer is B.

Why the other options are wrong

  • A. When there is a resource problem, you first have to resolve the resource problem, not directly push back the project start. Pushing back means giving up the initiative and would affect the strategic customer.
  • C. The authority of a project management office depends on the organization's governance arrangements. The stem does not say it has the authority to assign this person, and in a matrix organization the functional manager is usually the first party to negotiate with; asking the PMO to reassign him is not the best choice.
  • D. Merely recording that the person has been moved in the risk register is passive recording. It takes no step to acquire the resource, and the problem remains.

Key takeaway When a key person in a matrix organization is pulled away, negotiate with the functional manager to get him back first, and put other options later.

Variation If after negotiation the functional manager cannot release him, communicate with the sponsor to coordinate or evaluate alternative resources; if the person pulled away was an external person, contact the supplier or the procurement department.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When a scarce resource is contested by several projects, apply the organization's governance and portfolio priority criteria, weighing value, strategic alignment, schedule, budget, risk and dependencies; it is not a matter of whoever outranks the others (common exam practice: when the stem gives no other conditions, compare the projects' business benefits first, then look at budget and schedule).
  • When the other side simply has no time, first negotiate a workable arrangement with that person; do not go around them and do not rush to escalate.
  • Do not change the baseline directly; usually you first communicate and clarify the proposal, and once it becomes a change proposal that needs formal review, raise a change request, and do not implement it or change the baseline before approval; whether to negotiate first depends on the situation in the stem (common exam practice).
  • Showing all your cards, changing priorities on the fly and refusing to flex on a fixed objective are all poor preparation; rank your priorities in advance, and have a bottom line while leaving room to move.

Key point

The order in negotiating: prepare first (objectives, bottom line, alternatives), then understand the other side's interests, influence through value and not authority, and make concessions in stages and in exchange; usually negotiate directly first, and escalate through the governance structure when that fails, the matter exceeds your authority or the situation is urgent; for procurement disputes, also use alternative dispute resolution methods such as mediation and arbitration as the contract specifies.

Key takeaways

  1. Before negotiating, be clear about your own objectives, bottom line, best alternative and the other side's interests.
  2. Before negotiating, clarify priorities with stakeholders and rank your objectives.
  3. Focus on interests, not positions; make concessions with conditions and at a measured pace; influence the other side through value.
  4. When a key person is pulled away and the impact is already clear, negotiate with the functional manager next (common exam practice); if the impact is not yet known, assess it first.
  5. Procurement disputes: negotiate first (which is itself ADR), then use third-party methods such as mediation and arbitration if unresolved; litigation is the last option.
  6. Negotiating conflicts: collaborating (problem solving) is usually the first choice, and compromise is each side giving up something.

This chapter has 21 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.