What this chapter covers
Whether team members sit together or are spread across different cities or even different countries has a large effect on how the team must be managed. On the exam, whenever a stem mentions geographically dispersed members, different time zones, working from home or a distributed team, think of a virtual team, and think of communication first. The chapter has three lessons. Lesson 1 covers what colocation and virtual teams mean, and what each one gains and costs. Lesson 2 covers communication planning for virtual teams, time zones, trust, and the management of cross-cultural and diverse teams. Lesson 3 covers communication technology, choosing and using collaboration tools, and how to run remote meetings.
Virtual team scenario questions are common, and the usual answer follows one pattern: plan communication first, set up an online collaboration environment, let the team agree on meeting times and working conventions together, and, when feasible and useful, meet face to face at critical moments.
Lessons in this chapter
- Lesson 1: Colocation and virtual teams: meaning, advantages and disadvantages. The team room and osmotic communication; the seven things a virtual team makes possible, and its benefits; isolation and communication difficulty; how to choose in exam questions.
- Lesson 2: Virtual team communication, time zones, trust and cross-cultural management. Why communication planning matters more; overlapping hours, rotation, and minutes plus asynchronous participation; follow-the-sun and fishbowl windows (common exam terms); one-on-one conversations and informal online activities; discussing cultural differences openly.
- Lesson 3: Collaboration tools and remote work: equip the team first, then agree how to use the tools. Collaboration platforms and a team site; interactive and push communication; listen to needs first, then trial; when moving to remote work, provide tools before training; remote participation by experts.
Chapter map
How the team is organized
- Members together: colocation: team room · osmotic communication (can be temporary)
- Members apart: virtual team: bigger talent pool · lower cost · less travel / isolation · harder communication
- Communication planning: overlapping hours · rotation · minutes + asynchronous · follow-the-sun · fishbowl window
- Trust: one-on-one conversations · informal online activities · ongoing check-ins · team charter
- Cross-cultural: learn proactively · discuss openly · agree conventions together
- Tools: collaboration platform · team site · instant messaging · video conferencing · for a newly formed team with collaboration problems, at least one face-to-face meeting (a suggestion from a PMBOK 8 example; where conditions do not allow it, video conferencing stands in, which is common exam practice)
Lesson 1
Colocation and Virtual Teams: Meaning, Advantages and Disadvantages
Lesson overview
Whether team members sit together or are spread across different cities or even different countries has a large effect on how the team must be managed. On the exam, whenever a stem mentions geographically dispersed members, different time zones, working from home or a distributed team, think of a virtual team, and think of communication first. This lesson covers what colocation and virtual teams mean, what each one gains and costs, and how to choose between them in exam questions. The next lesson covers communication and trust in virtual teams, and the one after covers collaboration tools.
Colocation
Colocation is an organizational placement strategy where the project team members are physically located close to one another in order to improve communication, working relationships, and productivity. It involves placing many or all of the most active project team members in the same physical location to enhance their ability to perform as a team. Colocation can be temporary, such as at strategically important times during the project, or can continue for the entire project. Colocation strategies may include a team meeting room (often called a “war room” in exam questions), common places to post schedules, and other conveniences that enhance communication and a sense of community.
PMBOK 8 gives the benefits of colocation as better communication, better working relationships and higher productivity. Exam prep sums this up as “osmotic communication” (a common exam term): information flows naturally through a shared space, so you can look up and ask, you can settle things face to face, and in-person contact also makes it easier to build trust and reduce misunderstandings. A war room should seat members of the same project team, so that the information exchanged all the time is useful.
Virtual teams
Virtual teams are groups of people with a shared goal who fulfill their roles with little or no time spent meeting face to face. The availability of communication technologies such as email, audio conferencing, social media, web-based meetings, and videoconferencing has made virtual teams more feasible. The virtual team model makes it possible to do the following:
- Form teams of people from the same organization who live in widespread geographic areas;
- Add special expertise to a project team even though the expert is not in the same geographic area;
- Incorporate employees who work from home offices;
- Form teams of people who work different shifts, hours, or days;
- Include people with mobility limitations or disabilities;
- Move forward with projects that would have been held or canceled due to travel expenses; and
- Save the expense of offices and the physical equipment needed for employees.
The benefits include the use of more skilled resources, reduced costs, less travel and relocation expenses, and the proximity of team members to suppliers, customers, or other key stakeholders. Saving the expense of offices and the physical equipment needed for employees is also one of the possibilities that PMBOK 8 lists for the virtual team model; saving commuting time is a common-sense addition. Virtual teams can use technology to create an online team environment where the team can store files, use conversation threads to discuss issues, and keep a team calendar. PMBOK 8 notes that remote and virtual teams face heightened challenges due to varying work styles, time zones, and the absence of in-person interaction, which can hinder collaboration and relationship building. Combining PMBOK 8 with common exam practice, the disadvantages are mainly in communication: members can feel isolated, an “us versus them” split can form, people are hard to reach, communication is less efficient, and there is less informal exchange.
Compare
| Colocation | Virtual team | |
|---|---|---|
| Approach | Members work in the same place | Members are dispersed and connected by technology |
| Advantages | Better communication (osmotic communication, a common exam term), trust builds quickly, strong cohesion | Larger talent pool, lower cost, less travel and relocation |
| Disadvantages | Limited by location, high relocation and travel cost | Isolation, communication difficulty, time zone and cultural differences |
| Key means | A team meeting room (a war room, a common exam term), face-to-face conversation | Communication planning, communication technology, regular meetings |
Worked example
A logistics startup is building a freight-dispatch app. Its developers and testers are spread across three cities, and the budget has no money for relocation or travel. The project manager forms a virtual team. She sets up a shared document library and a team calendar, agrees on a 15-minute online daily coordination meeting each morning, and uses instant messaging for day-to-day questions. When the project reaches a critical point, the requirements review, she asks to bring the members from the three cities together in one place for two days. Technology handles the routine and face-to-face meeting handles the key moments, which controls cost and also reduces misunderstandings.
How to choose in exam questions
Members are dispersed and there is no relocation or travel budget: form a virtual team and use communication technology to build an online team environment, rather than asking for extra funds to colocate. Online communication is causing misunderstandings and conditions allow it: use temporary colocation, so that face-to-face communication clears up the misunderstandings and strengthens the sense of team. A face-to-face meeting cannot be held: first use communication technology to move the meeting and the collaboration online, rather than subcontracting the work, postponing it, or only checking the risk register.
Worked examples
Example 1: Dispersed members and no relocation budget: what to do
A logistics startup has begun developing a freight-dispatch app. After the project charter is approved, the project manager starts acquiring resources and finds that the developers and testers needed are spread across several cities, while the budget includes no relocation or travel costs. What should the project manager do to make sure the project can be completed?
Show answer and explanation
Correct answer: C
The charter for the freight-dispatch app is approved and the project manager is acquiring resources. The developers and testers are spread across several cities, and the budget has no relocation or travel money. The question is how to get the project done under the constraints of “no relocation or travel budget, people in different places.”
Virtual teams are groups of people with a shared goal who fulfill their roles with little or no time spent meeting face to face. With modern communication technology, the team can store files online, discuss issues in conversation threads and keep a shared calendar. This saves travel and relocation costs and still lets the project use the right talent in other locations. When members are scattered and there is no relocation budget, forming a virtual team and creating an online team environment turns the constraint into a workable solution. The answer is C.
Why the other options are wrong
- A. The budget never included relocation money, and asking for more means a change request and change control, which costs time and money. The value of a virtual team is precisely that it avoids relocation and travel.
- B. A responsibility assignment matrix can clarify roles, but the main difficulty here is geographic dispersion and the resulting communication and collaboration needs; a matrix by itself does not provide a remote collaboration environment.
- D. Letting members work alone and deliver at milestones provides no shared online environment or communication routine, so collaboration and engagement are not assured. It is less complete than forming a virtual team.
Key takeaway When members are scattered and there is no relocation or travel budget, use a virtual team with an online team environment instead of paying to bring everyone together.
Variation If the stem said the budget was ample and the project had reached a critical stage, temporary colocation could be considered. If the question asked for the benefits of a virtual team, the answer would be more skilled resources, reduced costs, and less travel and relocation expense.
Something wrong with this question?
Example 2: Online communication is causing misunderstandings: how to lead
A newly assigned project manager leads an exterior design project for a home appliance maker. The designers are located in different cities. Communication over video and text often causes misunderstandings because people do not express themselves clearly, the team lacks a good collaborative atmosphere, and design quality is suffering. The company has agreed to bring members together in one location for short periods at critical stages. What should the project manager do?
Show answer and explanation
Correct answer: C
A newly assigned project manager leads an exterior design project whose designers are in different cities. Video and text communication keeps causing misunderstandings, the collaborative atmosphere is poor, and quality is affected. The company allows short-term gatherings at critical stages.
Colocation places the main team members in the same physical location to strengthen the team’s ability to perform, and it can be used only at strategically important times. The root of the problem is dispersed locations combined with poor online communication, and the company allows members to gather at critical stages. Bringing members together temporarily, so that face-to-face conversation clears up misunderstandings and builds a sense of team, is the most direct fix. The answer is C.
Why the other options are wrong
- A. Blaming and criticizing individuals does not address the root cause. The communication barrier comes from dispersed locations and the way people communicate online, and criticism will not improve the collaborative atmosphere.
- B. The problem is within the project manager’s own remit and can be addressed directly with team building and colocation. Passing it to the sponsor is not proactive and may not help.
- D. The misunderstandings arise from video and text communication in the first place. Using the same channels more often does not fix the root problem and does not build a sense of team.
Key takeaway When online communication is causing misunderstandings and conditions allow it, use temporary colocation so that face-to-face communication removes the misunderstandings and builds team spirit.
Variation If the stem said the company would not allow any form of colocation, the answer would change to building a collaboration platform and adding video meetings and one-on-one conversations. If the misunderstandings came from cultural differences, discuss them openly and agree shared working conventions.
Something wrong with this question?
Common traps
Common trap
- Colocation is not required, and longer is not better; it can be used only at critical times.
- The problems of a virtual team are mainly about communication, not ability. When members are dispersed, think communication first, not criticizing individuals or replacing people.
- Adding budget so that everyone can work in one place is often not the best answer; a virtual team is precisely what saves the relocation and travel.
- A war room should seat members of the same project team. Do not put unrelated people in it.
Key takeaways
- Colocation places members in close physical proximity and can be temporary or last the whole project.
- The benefits of colocation are better communication (osmotic communication, a common exam term) and quick trust building; a team meeting room (a war room, a common exam term) is a common practice.
- A virtual team has little or no face-to-face contact and is connected by communication technology.
- Virtual team benefits: more skilled resources, lower cost, less travel and relocation. Disadvantages: isolation and communication difficulty.
- When members are dispersed and there is no relocation budget, form a virtual team and set up an online team environment.
- When online communication is causing misunderstandings and conditions allow, colocate temporarily.
Lesson 2
Virtual Team Communication, Time Zones, Trust and Cross-Cultural Management
Lesson overview
When a virtual team runs into trouble, nine times out of ten the trouble is communication. Members in different time zones cannot find a time to meet; people who have never met misread each other’s messages again and again; and people from different backgrounds and cultures understand the same sentence differently. This lesson covers why communication planning matters more, how to handle time zones, how to build trust, and how to manage cross-cultural and diverse teams. The previous lesson covered what a virtual team is, and the next one covers specific collaboration tools and remote meetings.
Communication planning matters more
PMBOK 8 states: “Communication planning becomes increasingly important in a virtual team environment. Additional time may be needed to set clear expectations, facilitate communications, develop protocols for resolving conflicts, include people in decision-making, understand cultural differences, and share credit in successes.” Exam tip: when a stem shows the features of a virtual team, check first whether the communication planning fits (common exam practice: with no other conditions, think communication first). You must still judge from the specific symptoms whether the fix is to improve communication, hold team building, resolve conflict, assess needs or remove an obstacle. When forming a team across locations, first learn the communication needs and preferences of members in each place, and agree the communication methods with the team so that participation rises. PMBOK 8 bases communication planning on stakeholder analysis and on information needs and categories, and when choosing communication technology it adds factors such as urgency, availability and reliability, ease of use, time zones and cultural differences. So analyze communication needs and plan the methods first, then choose communication technology that every member can use, that is reliable, and that suits the time zones and cultural setting. When “communication technology” and “communications management plan” both appear among the options, choose according to the level the question asks about: if it asks how to plan, choose the communications management plan; if it asks what tool to use, choose communication technology.
Time zones
Time zone differences cause two problems: meeting times are hard to find, and handoffs of information are delayed. The remedies are these. Find and share the overlapping hours when both sides work, and hold online meetings in those hours. Let the team discuss and agree the meeting times, with the leader’s role being to facilitate and not to command. Rotate the meeting times so members in every location take part fairly. When a time zone causes someone to be absent, make up for it with complete meeting minutes plus asynchronous participation, without penalizing the person who is absent or rearranging everything around one individual. Combine synchronous and asynchronous communication, and make the communication plan fit where members are located.
Two common ways of organizing the work are worth knowing (“follow the sun” and “fishbowl window” are common exam terms). In the follow-the-sun model, the team is spread across time zones; when one location finishes its day, another starts, and work passes like a baton from place to place, so someone is working twenty-four hours a day. It demands a lot of handoffs: handoff points must be clear and documentation complete. In the fishbowl window model, the video conferencing systems in each office stay on all the time, so everyone can see whether others are present or busy without scheduling anything. This lowers the cost of communication and strengthens the sense of belonging.
Building trust
When a virtual team lacks a sense of involvement, use one-on-one conversations and team building to build trust and belonging. Engagement is kept up through ongoing, planned check-ins and meetings, not by a one-time kickoff meeting. Team building matters even more for virtual teams, so arrange more informal online activities that give members a chance to talk informally and build trust. When communication is poor and trust is lacking, solve it systematically with regular video meetings plus a team charter. For a distributed team, try to build self-contained cross-functional sub-teams by region so that handoffs across regions are kept to a minimum (a common exam practice). When a remote member’s performance drops, first identify the specific obstacles and remove them one by one; when the cause is unclear, first learn what the member needs.
Cross-cultural and diverse teams
Members from different cultural backgrounds may think and express themselves differently, and the communication difficulty that language and cultural differences create is the first thing a geographically dispersed team has to consider. The Build an Empowered Culture principle in PMBOK 8 notes that “cultivating a team environment that honors diversity and seeks to harness it constructively fosters an atmosphere where conflicts can be managed efficiently.” In practice: learn about cultural differences proactively and discuss them openly, rather than avoiding them, merely recording them or breaking up the team. Help the team reach one shared understanding of the common goals so that everyone is aligned. Agree working methods, roles, and time zone and cultural conventions together with the team, rather than having the project manager announce them unilaterally. Frequent, low-cost online cultural exchange is often more practical than a one-time face-to-face event.
Conflict caused by cultural differences is resolved by understanding the differences and building common practices, not by avoiding it or forcing one culture on everyone. For a communication problem caused by cultural differences, have the people involved talk to each other directly (by video conference if needed) instead of relaying messages or simply asking one side to be tolerant. When a member asks to be moved off the team because of discomfort with colleagues, first talk to find out why and reaffirm inclusive practices, and do not rush to reassign the person or escalate.
Worked example
The development group of a cross-border e-commerce team is in Shanghai, and the subject matter expert is on the US east coast, twelve hours apart (counted on US Eastern daylight saving time; in winter the difference is thirteen hours). The project manager does not ask either side to work through the night. She agrees with the team to hold a 30-minute online meeting every Tuesday and Thursday at 8 p.m. Shanghai time, which is 8 a.m. for the expert. Minutes are written up the same day, and anyone who cannot attend gives written feedback within 24 hours. Every month the meeting times are swapped so that the two locations take turns bearing the inconvenient slot. Members have no complaints about the arrangement because they helped agree it.
Worked examples
Example 1: Shanghai and the US east coast are 12 hours apart: how to improve interaction
The development team on a cross-border e-commerce platform project is in Shanghai, and the subject matter expert is on the east coast of the United States, about 12 hours apart during daylight saving time. What can the project manager do to improve interaction between members at the two locations?
Show answer and explanation
Correct answer: D
The development team in Shanghai and the subject matter expert on the US east coast are about 12 hours apart, which is a virtual team communication problem. The question asks how to improve interaction between the two locations.
Communication planning becomes more important in a virtual team environment. Choosing a suitable virtual communication method and then holding regular team meetings with it gives members at both locations a fixed, predictable channel for interaction. It takes the time difference into account and is both feasible and low in cost. The answer is D.
Why the other options are wrong
- A. With a 12-hour difference, having both sides work at the same time means one side works in the middle of the night, which harms rest and efficiency and is not realistic.
- B. Having the expert attend every scope planning review only involves him in one kind of meeting. It does little to improve day-to-day interaction between the two locations and does not solve the communication difficulty caused by the time difference.
- C. With great distance and a 12-hour difference, frequent face-to-face meetings are expensive and hard to arrange, and they defeat the purpose of having a virtual team.
Key takeaway With a large time difference and distance, first choose a virtual communication method, then schedule regular meetings that use it.
Variation If the stem asked about members missing meetings because of the time difference, the answer would be complete minutes plus asynchronous participation, with meeting times rotated. If the two sites had one hour of overlap, put the important conversations in the overlap.
Something wrong with this question?
Example 2: A cross-cultural virtual team: how to reduce the uncertainty caused by cultural differences
A project manager leads a geographically dispersed virtual team whose members come from different cultural backgrounds. What should the project manager do to avoid uncertainty for the project caused by cultural differences?
Show answer and explanation
Correct answer: D
A geographically dispersed virtual team has members from different cultural backgrounds, and the project manager wants to avoid uncertainty caused by cultural differences. The question asks for a suitable way to manage cultural differences proactively.
The most effective response to cultural differences is to learn about them proactively. First gather information on members’ cultural backgrounds, then have members discuss their working habits and work ethic so they better understand one another’s cultures and identify what needs to be considered at work. This reduces uncertainty, and it fits the attitude toward diversity in the Build an Empowered Culture principle. The answer is D.
Why the other options are wrong
- A. Requiring members to drop their cultural habits and adopt a “neutral” way of working is hard to do, consumes resources, and disregards respect for diverse cultures.
- B. Starting the project and just recording the uncertainty in the risk register to watch it takes no positive action. Cultural differences can be understood and managed proactively.
- C. Cultural differences can be dealt with, so there is no need to disband the team. And the resources needed for colocation may not be available in time either.
Key takeaway Learn about cultural differences proactively and discuss them openly, rather than avoiding them, only recording them, or breaking up the team.
Variation If the stem said cultural differences had already caused conflict, have the people involved talk directly and agree on working conventions together. If a member asks for a transfer because of discomfort, first talk with the member to understand the reasons, then consider other measures.
Something wrong with this question?
Common traps
Common trap
- With a time zone conflict, do not favor one side and do not escalate at once. Negotiate a time both sides can accept, and rotate.
- Conflicts in virtual teams often come from the communication mechanism. Understand the background first, then improve how the team communicates. Do not reassign people first.
- Cultural differences should be discussed openly and learned about proactively. Do not avoid them, do not just record them, and do not ask people to give up their cultural habits.
- A one-time kickoff meeting cannot replace ongoing, planned check-ins and meetings.
Key point
The order for virtual teams: first learn the needs and backgrounds of members in each location, then agree the communication methods, meeting times and cultural conventions together with the team. Day to day, communicate online and often. Whether to meet face to face at key points is decided by weighing cost, feasibility and everyone’s needs.
Key takeaways
- Communication planning matters more for virtual teams: spend more time setting expectations and establishing conflict resolution protocols.
- Time zones: find overlapping hours, have the team agree the meeting times and rotate them, and use minutes plus asynchronous participation for those who cannot attend.
- The follow-the-sun model works like a relay through handoffs; the fishbowl window model strengthens belonging through always-on video.
- Building trust: one-on-one conversations, informal online activities, and ongoing check-ins and meetings.
- Cross-cultural teams: learn proactively and discuss differences openly, and agree working methods and conventions together.
- Resolve cultural conflict by understanding differences and building common practices, not by avoiding it or forcing one culture on everyone.
Lesson 3
Collaboration Tools and Remote Work: Equip the Team First, Then Agree How to Use the Tools
Lesson overview
Once members are dispersed, what keeps the team feeling “as if we were together”? Communication technology: video conferencing, shared portals, instant messaging and collaboration platforms. Whether the tools are chosen appropriately and used effectively has a significant effect on how a remote team performs. This lesson covers communication technology and the collaboration environment, the principles for choosing and using tools, and how to make remote meetings work. The first two lessons covered what a virtual team is and how it communicates, and this one comes down to tools and practice.
Communication technology and the collaboration environment
Communication technology includes specific tools, systems, computer programs, etc., used to transfer information among project stakeholders. Common methods used for information exchange and collaboration include conversations, meetings, written documents, databases, social media, and websites; videoconferencing, audio conferencing, email and instant messaging are common examples. According to common exam practice, communication technology builds a harmonious environment for a colocated team and promotes better mutual understanding in a virtual team. In its example of a newly formed virtual team that may encounter collaboration issues, PMBOK 8 suggests: setting up collaboration sites where the team can work together, which let the team store files, use conversation threads to discuss issues and keep a team calendar; having a project team site to keep all relevant project and project team information available; using audio, video and virtual conferencing capabilities for meetings; using technology to maintain ongoing contact, such as messaging and texting; scheduling time to get to know remote project team members; having at least one face-to-face meeting to establish relationships; and creating a team charter and defining ways of working.
Communication methods fall into three kinds: interactive, push and pull. Interactive communication occurs between two or more parties performing a multidirectional exchange of information in real time, through video conferences, instant messaging, phone calls and in-person meetings. Push communication is sent or distributed directly to specific recipients, such as emails and reports. “This method ensures that the information is distributed but does not ensure that it reaches or is understood by the intended audience.” Pull communication is used for large, complex information sets or large audiences; recipients access the content at their own discretion, as with web portals, intranet sites, eLearning courses, lessons learned databases and knowledge repositories. So one-way emails and logs cannot replace interactive communication, and a remote team needs a collaboration environment to support day-to-day communication, not meetings alone.
Choosing and using tools
The tools must fit the team’s needs. Collaboration tools are themselves project resources, so when they are inadequate, assess the need and provide suitable tools. Before choosing, listen to the team’s needs: do not default to the old tools and do not chase the newest ones. If people disagree about a new tool, let the team try it first and then evaluate it, deciding on facts rather than authority. When a team moves to remote work, first make sure the tools are in place and that training lets members use them, and only then talk about more budget or a smaller scope. If a communication tool is unavailable to some members, switch to one everyone can use rather than adjusting the people.
When a virtual team performs poorly, first assess the team’s performance and analyze the root cause (PMBOK 8: use the overall team performance assessment to identify the training, coaching, mentoring, assistance or changes required). If the cause is confirmed to be inadequate tool capability or communication channels, then train members, strengthen contact and provide suitable tools, rather than replacing people outright or going back to colocation. When collaboration is poor, assess the state of collaboration first, then provide the matching technology and equipment. For technical problems, find the root cause first rather than changing tools or working around them straight away.
Making remote meetings work
For a virtual meeting to be productive, give participants the information they need before it, use turn-taking to make sure everyone takes part, and choose the communication method to suit where members are. A distributed Scrum team can use virtual meetings day to day and, when feasible and useful, come together at key moments. When the budget does not allow travel, use video conferencing with screen sharing in place of face-to-face meetings, and you can still get user feedback. When an expert cannot get to the site, letting the expert take part remotely through video conferencing and similar technology is a way to protect both time and quality.
Worked example
On a regional government digital services project, a time-boxed commissioning activity had to be done on site and needed professional guidance from an expert at a foreign vendor, but entry restrictions kept the expert away. The project manager neither waited nor hastily trained the team. Instead she set up cameras and screen sharing at the commissioning site and asked the expert to guide the work online. The on-site engineers followed his instructions, and the session was recorded for later reference. The activity finished on time, and the team retained access to the expert’s knowledge despite the distance.
Worked examples
Example 1: The expert cannot get to the site: how to help the team finish on time
A key regional government digital services project is in the Executing focus area. One time-boxed activity needs the expertise and guidance of a foreign vendor’s expert to complete commissioning, and the team can handle the on-site work. Because of entry restrictions, the expert cannot come, the activity cannot be done without his expertise, and the team is looking for a way to finish on schedule. How should the project manager help the team?
Show answer and explanation
Correct answer: B
A digital government project is in the Executing focus area. A time-boxed commissioning activity needs the expertise and guidance of a foreign vendor’s expert, and the team can do the on-site work. Entry restrictions keep the expert away, and without his expertise the activity cannot be done. The question asks how the project manager should help the team.
What the activity needs is the expert’s knowledge and guidance. The expert cannot come on site and the activity cannot wait, so the most direct approach is to bring the expert into the team through communication technology: set up a video conference and let the expert guide the team online through the commissioning. This obtains the expert’s knowledge without being affected by the entry restrictions and protects both time and quality. The answer is B.
Why the other options are wrong
- A. It is uncertain when the restrictions will be lifted, and the activity is time-boxed, so waiting indefinitely would drag down the overall schedule.
- C. Training the team to expert-level commissioning skills would take a long time and extra money, which is not realistic under a time limit.
- D. A lessons learned repository might help, but searching takes time and may turn up no similar approach. It is less reliable than having the expert guide the team remotely.
Key takeaway When an expert cannot be on site, having the expert take part remotely through video conferencing or similar technology protects both time and quality.
Variation If the stem said the expert could not use video tools, first make sure a tool is available, replacing it if necessary with one everyone can use. If the activity were not time-boxed, waiting for the expert to arrive could also be considered.
Something wrong with this question?
Example 2: A global team starts virtually: how to get members committed
A global team is about to launch a cross-border e-commerce platform overhaul project. Travel is not feasible for team members, so most will take part virtually. What should the project manager do to get team members truly committed to the project?
Show answer and explanation
Correct answer: D
A global team is about to start a cross-border e-commerce platform overhaul. Travel is not feasible, so most members will participate virtually. The question asks how to get members truly committed to the project.
When the team works virtually most of the time, the key is to let members communicate in real time, share information and work together. A virtual collaboration environment brings video conferencing, instant messaging, file sharing and joint editing into one place. It can support daily collaboration throughout the project, information is open and transparent, and members find it easier to commit. The answer is D.
Why the other options are wrong
- A. One-on-one meetings only improve communication between the project manager and one member at a time, and members still lack collaboration with one another.
- B. Asking HR for team-building advice is only one part of planning, and advice by itself does not get members involved right away.
- C. A weekly meeting helps, but it is infrequent and interaction happens only at the meeting, so it cannot support members’ daily real-time communication and collaboration.
Key takeaway A virtual team relies on a collaboration environment (video conferencing, chat, document sharing) to support daily communication, not meetings alone.
Variation If the stem said the team already had a collaboration environment but engagement was low, strengthen one-on-one conversations and informal online activities. If one member cannot use a particular tool, switch to a tool everyone can use.
Something wrong with this question?
Common traps
Common trap
- When a virtual team performs poorly, first assess team performance and analyze the root cause. If the cause is confirmed to be tools or communication channels, then train members, provide the tools and strengthen contact, rather than replacing people outright or going back to colocation.
- When people disagree about a new tool, have the team try it and decide on the facts. Do not default to the old tool, and do not let the project manager or sponsor simply decide.
- One-on-one meetings only improve communication between the project manager and an individual, and a weekly meeting only provides interaction while the meeting is on. Neither replaces a collaboration environment that can support day-to-day communication.
- One-way emails and logs are not interactive communication. Remote teams should combine real-time interaction with asynchronous collaboration as needed.
Key takeaways
- Communication technology means the tools, systems or computer programs used to transfer information among project stakeholders. Common methods include conversations, meetings, written documents, databases, social media and websites; videoconferencing, email and instant messaging are common examples.
- A newly formed virtual team that runs into collaboration problems can set up a collaboration platform and a team site and use instant messaging to stay in contact; where conditions allow, schedule at least one face-to-face meeting and create a team charter.
- Collaboration tools are project resources: listen to the team’s needs first, then trial the tool and evaluate it.
- When moving to remote work, first make sure the tools exist and that people are trained to use them, then talk about budget or scope.
- Remote meetings: give information beforehand, take turns speaking, and choose the communication method to suit where members are.
- When an expert cannot get to the site, use video conferencing or similar technology to let the expert take part remotely.
This chapter has 39 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.