PMP · Quality · 2 lessons · about 26 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Cost of quality (CoQ) converts two things into money: the prevention and appraisal spent to make the product meet requirements, and the internal and external failure paid for when it was not done well. PMBOK 8 lists it as one of the data analysis tools, used when estimating costs, and notes that there is an optimal cost of quality: beyond that point, investing in additional prevention and appraisal is neither beneficial nor cost-effective. The ECO's Process domain Task 7, "Plan and optimize quality of products/deliverables", also lists "manage cost of quality (CoQ) and sustainability" explicitly.

The chapter has two stable question types. In the first, you are given an item of cost and must decide which category it belongs to. In the second, quality activities are over budget, the cost of quality is high or rework costs are rising, and you must decide what the project manager does. For the second type, read the stem. Common exam practice: when rework or defects rise, analyze the root cause first. When you must choose among quality investment options, then compare costs and benefits. When a budget variance occurs, analyze the variance and handle it through governance and change procedures. Do not cut the budget outright, and do not just add more testing.

Lessons in this chapter

How to study this chapter

First use Figure 5-3 to fix the four categories and the typical items of each in memory. Then classify with the three questions: conforms or not, who found it, built right or checked. Do that well and a classification question needs almost nothing else memorized. For trade-off questions, remember one sequence of actions: first analyze the structure of the cost of quality, then compare the cost and benefit of the specific approaches, and finally adjust the investment. The worked examples do not require formulas; you only need to classify and add, and to use "reduction in failure costs minus extra spending" to test whether something pays off. After this chapter you will find it easier to understand why corrective action taken on process problems found in an audit should lower the cost of quality and raise the sponsor's or customer's acceptance of the project's product.

Chapter map

Cost of quality = prevention + appraisal + internal failure + external failure

  • Cost of conformance (during the project, to avoid failures): prevention + appraisal
  • Cost of nonconformance (during and after the project, to deal with failures): internal failure (found by the team) + external failure (found by the customer)

Optimal cost of quality: the balance point between investment and failure losses

  • Review the overall structure → cost of quality
  • Judge whether an activity or option is worth it → cost-benefit analysis

The practice entry for this chapter is chapter practice. Start with the core questions, then do the must-do questions.

Lesson 1

The Four Categories of Cost of Quality, and Cost of Conformance vs. Nonconformance

Lesson video

Lesson overview

Cost of quality (CoQ) answers one question: how much money was spent to make the product meet requirements, and how much was lost because it was not done right? It converts both the quality activities and the consequences of failure into money. It is a data analysis technique commonly used when estimating costs, and it corresponds directly to the item "Manage cost of quality (CoQ) and sustainability" within ECO: Process domain, Task 7 (Plan and optimize quality of products/deliverables). This lesson covers the four categories of cost and the two larger groups they form. The next lesson covers how to balance prevention spending against failure losses, with a full worked example. The exam point in this lesson comes down to one thing: given an item of cost, decide which category it belongs to.

The four categories

PMBOK 8 defines cost of quality this way: "The cost of quality includes all costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements." The cost of quality associated with a project consists of one or more of the following costs:

  • Prevention costs. Costs related to the prevention of poor quality in products, deliverables, or services of the specific project.
  • Appraisal costs. Costs related to evaluating, measuring, auditing, and testing products, deliverables, or services of a specific project.
  • Failure costs (internal/external). Costs related to nonconformance of products, deliverables, or services based on the needs or expectations of the stakeholders.

Figure 5-3 lists typical items for each category. Memorize them and you can answer nearly every classification question on the exam:

Figure 1: The four categories of cost of quality and the two groups
CategoryTypical items (Figure 5-3)Who finds it / when it occurs
Prevention costsTraining, document processes, equipment, time to do it rightDuring the project, spent to avoid failures
Appraisal costsTesting, destructive testing loss, inspectionsDuring the project, spent to avoid failures
Internal failure costsRework, scrapFailures found by the project
External failure costsLiabilities, warranty work, lost businessFailures found by the customer, often after the project is complete

The difference between internal and external failure depends on who finds the failure: internal failure costs arise from failures found by the project, and external failure costs from failures found by the customer. Common exam practice often illustrates this as a defect found before delivery versus after delivery, but who finds it is the deciding distinction. The same defect is an internal failure if project staff find it before delivery and rework it, and an external failure if the customer finds it after delivery and demands warranty work or compensation. External failure is often the most expensive: besides recalls and compensation, you may lose the customer and future business, which is why spending on prevention is usually worthwhile.

Cost of conformance vs. cost of nonconformance

The four categories are grouped by nature into two larger groups. On the left of Figure 5-3 is the cost of conformance: money spent during the project to avoid failures, made up of prevention costs and appraisal costs. On the right is the cost of nonconformance: money spent during and after the project because of failures, made up of internal failure costs and external failure costs. "Conformance" here means that results satisfy the established quality requirements.

GroupIncludesWhen it occursNature
Cost of conformancePrevention costs, appraisal costsDuring the projectInvested on purpose to avoid failures
Cost of nonconformanceInternal failure costs, external failure costsDuring and after the projectSpent reactively to deal with failures

How to classify: three questions

When you meet an item of cost, ask three questions in order:

  1. Was the money spent to prevent or evaluate conformance to requirements, or was it caused directly by a nonconformance that has already been confirmed? The former is cost of conformance and the latter is cost of nonconformance. (Classification depends on the purpose and cause of the spending, not on timing: testing and inspection often take place after defects have already been created, but they are still appraisal costs.)
  2. If it is cost of nonconformance, who found the defect? If project staff found it, it is an internal failure; if the customer found it, it is an external failure.
  3. If it is cost of conformance, was it spent to "build it right" (training, documents, equipment, time) or to "find problems" (testing, inspection, audits)? The first is prevention and the second is appraisal.

There are two places where people often go wrong. Buying equipment is not the same as using it. If the stem says "purchase a machine used only for testing", the purpose of the spending is to evaluate conformance to requirements, so it is normally an appraisal cost. Equipment used to improve production or the process and to prevent defects is normally a prevention cost (Figure 5-3 lists general "equipment" as a prevention example). Common exam practice: look at the use the stem emphasizes; do not decide only by whether the item is "bought" or "used". Destructive testing damages the samples under test, and that loss is recorded as an appraisal cost, not a failure cost.

Example: classifying and totaling a list of costs

Here are the quality-related costs of a smart speaker project in this phase: (1) company-wide quality awareness training, $4,000; (2) writing and maintaining assembly work instructions, $3,000; (3) power consumption and sound quality testing before shipment, $11,000; (4) a destructive drop test on 20 units, with a prototype scrap loss of $2,000; (5) 150 units found with the wrong firmware version, reflashed as rework, $9,000; (6) one batch has already reached the distributor and is returned and compensated because of swollen batteries, $16,000.

Step by step:

  • Prevention costs: (1) + (2) = $4,000 + $3,000 = $7,000
  • Appraisal costs: (3) + (4) = $11,000 + $2,000 = $13,000 (the destructive testing loss is recorded as an appraisal cost)
  • Internal failure costs: (5) = $9,000 (rework found by the team itself)
  • External failure costs: (6) = $16,000 (returns and compensation found on the customer's side)
  • Cost of conformance = $7,000 + $13,000 = $20,000; cost of nonconformance = $9,000 + $16,000 = $25,000; total cost of quality = $45,000
  • Check: $7,000 + $13,000 + $9,000 + $16,000 = $45,000.

Reading the numbers: cost of conformance is only $20,000, and external failure alone is $16,000, more than the $9,000 of internal failure. Whether to add prevention or appraisal spending still depends on the number of defects, the trend in losses and a cost-benefit analysis of the added spending.

Worked examples

Example 1: the customer finds a defect after delivery. Which category is this cost?

Question 1Example

An industrial water pump project has delivered all the equipment to the client. A few weeks later the client writes that the pumps' flow rate fluctuates widely and is disrupting their production line. The project team has to pay to fix the problem. Which category of cost of quality does this cost belong to?

Show answer and explanation

Correct answer: C

All the industrial water pumps have been delivered, and a few weeks later the client writes that the flow rate fluctuates widely, and the team has to pay to fix it. The question asks which category of cost of quality this cost belongs to.

Cost of quality has four categories: prevention, appraisal, internal failure and external failure. To tell whether a failure cost is internal or external, look at who found the nonconformance: internal failure costs arise when the project finds it, and external failure costs arise when the customer finds it. Here the client discovered the defect in use weeks after delivery and the team has to resolve it, so the loss is an external failure cost (warranty work, liabilities and lost business belong to the same category). External failure is often the most expensive: besides compensation and warranty work you may lose business, which is why prevention spending is usually worthwhile. The answer is C.

Why the other options are wrong

  • A. Internal failure costs are the rework and scrap that arise when project staff find defects. Here the client found the defect while using the equipment after delivery.
  • B. Prevention costs are investments made to prevent poor quality, such as training and documenting processes. The problem has already occurred, so this is not prevention.
  • D. Appraisal costs are what is spent on evaluating, measuring, auditing and testing the product. Only the cost of inspection and testing itself counts as appraisal. This question is about the cost of remedying a defect the client found, which is an external failure cost.

Key takeaway To tell internal from external failure, see who found the nonconformance: the project (internal) or the customer (external).

Variation If the same defect had been found by the quality inspector in the final inspection and reworked, the cost would be an internal failure cost, and the cost of the inspection itself would be an appraisal cost.

Something wrong with this question?

Report an issue with this question

Example 2: training and documenting processes. Which category, and which group?

Question 2Example

A cost of quality report divides project spending into two large groups, cost of conformance and cost of nonconformance. How should the training and process documentation the team carries out to improve process quality be classified?

Show answer and explanation

Correct answer: D

A cost of quality report divides spending into cost of conformance and cost of nonconformance. The question asks how the training and process documentation the team carries out to improve process quality should be classified.

Training and process documentation are investments made to prevent poor quality, so they are prevention costs. Prevention costs and appraisal costs together make up the cost of conformance, money spent during the project to avoid failures. The cost of nonconformance includes only internal and external failure. If you are unsure, remember this rule of thumb: building it right and checking it are cost of conformance, and what is paid because it was not built right is cost of nonconformance. The question asks you to get both the category (prevention) and the group (conformance) right. The answer is D.

Why the other options are wrong

  • A. Appraisal costs do belong to the cost of conformance, but training and process documentation are prevention activities, not appraisal activities.
  • B. Internal failure costs do belong to the cost of nonconformance, but training and process documentation are not rework or scrap after a failure.
  • C. The category is right but the group is wrong: prevention costs belong to the cost of conformance, and the cost of nonconformance contains only internal and external failure.

Key takeaway Cost of conformance = prevention + appraisal; cost of nonconformance = internal failure + external failure.

Variation Change “training” to “destructive testing loss” and the category becomes appraisal costs, with the group still cost of conformance. Change it to “warranty work” and it is an external failure cost, part of the cost of nonconformance.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Appraisal costs are not failure costs. Testing, inspection and audits are activities used to find nonconformance; their purpose is to find problems, so they are cost of conformance. Even if defects have already been created, those testing and inspection costs are still appraisal; only the rework and scrap after the defects are found count as internal failure.
  • Prevention costs belong to the cost of conformance, not the cost of nonconformance. "Prevention costs are failure costs" is wrong.
  • Rework and scrap are internal failure (found by project staff). Warranty work, compensation and lost business are external failure (found by the customer). When the stem mentions "returned by the customer" or "customer complaint", it usually means external failure.
  • The cost of the acceptance check before release is an appraisal cost; the rework cost after the check finds defects is internal failure cost.
  • Cost of nonconformance occurs both during and after the project; cost of conformance occurs only during the project.

Key takeaways

  1. Cost of quality includes all costs of prevention, appraisal and failure (internal and external).
  2. Prevention: training, document processes, equipment, time to do it right. Appraisal: testing, destructive testing loss, inspections. Internal failure: rework, scrap. External failure: liabilities, warranty work, lost business.
  3. Cost of conformance = prevention + appraisal, spent during the project to avoid failures. Cost of nonconformance = internal failure + external failure, spent during and after the project to deal with failures.
  4. Internal versus external depends on who finds the failure: found by the project is internal, found by the customer is external. Before versus after delivery is only the usual way exam questions illustrate it.
  5. The three classification questions: does it conform or not, who found it, was it done right or checked.

Lesson 2

Optimal Cost of Quality, Cost-Benefit Analysis and Using Cost of Quality

Lesson video

Lesson overview

Once you know the four categories of cost, the next question is how to use them. How much quality spending is the right amount? What do you trade off when quality activities run over budget? And when should you use cost of quality and when cost-benefit analysis, two similar-looking tools? The answer to almost every scenario question in this lesson is "analyze first, then trade off". The second half gives a complete worked example that calculates the cost of conformance, the cost of nonconformance and whether "adding more spending" pays off. ECO: Process domain, Task 7 (Plan and optimize quality of products/deliverables).

The optimal cost of quality

PMBOK 8 says: "The optimal CoQ is one that reflects the appropriate balance for investing in the cost of prevention and appraisal to avoid failure costs. Models show that there is an optimal quality cost for projects, where investing in additional prevention/appraisal costs is neither beneficial nor cost-effective."

This sentence has two layers. First, spending less on quality is not always better: if you spend less on prevention, failure costs rise even faster. Second, spending more is not always better either: beyond a certain point, each extra dollar buys a smaller and smaller drop in failure costs, and it stops paying off. So a project manager has no ready-made answer of "the higher the better" or "the lower the better", only "compare and trade off".

Another fact is that the later a defect is found, the more it costs to repair. PMBOK 8 says that early testing helps identify nonconformance problems and helps reduce the cost of fixing the nonconforming components, and that early detection and prevention of defects minimize rework and material waste. So when someone questions whether "too many test stages drive up cost", do not cut testing automatically. Explain that testing exists to detect defects early and lower future failure costs, then analyze each stage's cost, expected benefit and risk, and keep the testing whose early-detection benefit justifies its cost. Corrective action after a quality audit should likewise reduce the cost of quality and raise the sponsor's or customer's acceptance of the project's product.

Cost of quality analysis vs. cost-benefit analysis

Both tools deal with "is it worth it", but they answer different questions:

ToolThe question it answersTypical scenario
Cost of quality (analysis)How much do quality investment and failure losses come to in total, what is their structure, and is the spending balanced?Including the cost of quality activities when estimating costs; reviewing the structure when the cost of quality share is high or failure costs are rising
Cost-benefit analysisDo the benefits of one specific approach exceed its cost, and which alternative is better?Whether to add a test environment; whether to buy higher-spec inspection equipment; which quality approach pays off best within the given quality requirements, acceptance criteria and compliance constraints

PMBOK 8 describes cost-benefit analysis as "a financial analysis method used to determine the benefits provided by a project against its costs. The analysis is used to estimate the strengths and weaknesses of alternatives in order to determine the best alternative in terms of benefits provided."

One sentence tells them apart: to review the overall structure, use cost of quality; to judge whether one specific activity is worth it, use cost-benefit analysis. If the stem asks "should we add another round of testing", "is the pricier equipment worth it", or "what is the lowest acceptable standard between cost and quality", the answer is cost-benefit analysis. If it says "the cost of quality share is high" or "rework and scrap costs keep rising", first analyze the structure of the cost of quality.

How cost of quality is used in a project

Cost of quality shows up in a few places. It is one of the data analysis tools used when estimating costs, so that the cost of quality activities is included in the estimate. Correcting the deficiencies a quality audit identifies can reduce the cost of quality. The ECO expects the project manager to manage cost of quality and sustainability: embedding quality in processes also has environmental benefits, because it avoids the consumption of natural resources and the emissions that rework causes.

Collecting data without using it is the same as having none. If the four categories are totaled every month and nobody looks at them, the right thing is to analyze the data and optimize quality spending from it. When the cost of quality share is high, first see how much each of the four categories accounts for, find the unreasonable parts, and then adjust in a targeted way. Do not push the standard down to the minimum, and do not cut prevention and appraisal across the board. When rework and scrap costs keep rising, analyze where the failure costs come from and then act on the cause (usually by strengthening prevention), rather than just adding inspectors.

Worked example: is spending more on prevention worth it?

A data dashboard project originally plans the following cost of quality: prevention $6,000, appraisal $12,000, internal failure $18,000, external failure $24,000.

Step 1: the original cost of quality. Cost of conformance = $6,000 + $12,000 = $18,000; cost of nonconformance = $18,000 + $24,000 = $42,000; total $60,000.

Step 2: evaluate the new proposal. The team finds that most defects come from inconsistent understanding of requirements, and proposes spending an extra $8,000 on requirements review training and on setting up and training people on design standards and a review process. This is a prevention cost; the design review itself, which checks whether the design meets requirements, is an appraisal cost and is not in the $8,000. Internal failure is expected to fall by $9,000 and external failure by $12,000, a total reduction of $21,000.

Step 3: the cost of quality under the new proposal. Prevention = $6,000 + $8,000 = $14,000; appraisal $12,000; internal failure = $18,000 − $9,000 = $9,000; external failure = $24,000 − $12,000 = $12,000. Cost of conformance = $14,000 + $12,000 = $26,000; cost of nonconformance = $9,000 + $12,000 = $21,000; total $47,000. That is $60,000 − $47,000 = $13,000 less than before.

Step 4: check with cost and benefit. The benefit is the $21,000 reduction in failure costs and the cost is the extra $8,000 of prevention: net benefit = $21,000 − $8,000 = $13,000, matching step 3. Benefit-cost ratio = 21 ÷ 8 ≈ 2.6, which is above 1, so it is worth doing.

Step 5: what if you add more? Suppose another $8,000 goes into prevention but failure costs are expected to fall by only $6,000 more. Net benefit = $6,000 − $8,000 = −$2,000, and the cost of quality rises from $47,000 to $49,000, so it no longer pays off. The neighborhood of that turning point is what the optimal cost of quality means.

Predictive vs. adaptive

The classification of cost of quality applies to both kinds of project. Predictive projects usually put the cost of reviews, testing and audits into the cost estimate during planning. Adaptive projects build testing and review into every iteration, so the cost of quality activities is spread across the iterations. Either way the objective is the same: detect and prevent defects early and reduce rework and waste.

Worked examples

Example 1: the budget is tight. How do you decide the lowest acceptable quality standard?

Question 1Example

A custom furniture project has a very tight budget, and the client thinks the money should go into producing the finished product, not into quality management work. The project manager explains the importance of quality management to the client, and both sides agree to lower the quality requirements somewhat within an acceptable range. What should the project manager do to determine the lowest acceptable quality standard?

Show answer and explanation

Correct answer: C

A custom furniture project has a very tight budget, and the client thinks money should go into the finished product. After the project manager explains the importance of quality management, both sides agree to lower the quality requirements somewhat within an acceptable range. The question asks how to determine the lowest acceptable quality standard.

To trade quality investment against cost, you have to set the cost and expected benefit of different quality levels (alternative quality standards) side by side. That is cost-benefit analysis: it helps judge whether an option is cost-effective and picks the alternative with the best benefit. Doing it together with the client means both sides accept the lowest standard that results. In practice, list the cost and expected benefit of each quality level (less rework, higher satisfaction and so on), and, provided mandatory floors such as regulations, contracts and acceptance criteria are already met, choose with the client a quality level with a suitable cost-benefit balance. You cannot replace setting a quality standard by cutting quality activities at random, or the established standard may not be achieved. The answer is C.

Why the other options are wrong

  • A. Benchmarking provides what peers do, as a reference only, and it does not answer how to trade quality investment against cost.
  • B. The project manager's own experience alone lacks data, is hard to convince the client with, and does not guarantee a reasonable result.
  • D. Design of experiments is a technique for observing the effect of adjusting several factor combinations at once. It is not used to trade cost against quality.

Key takeaway To trade cost against quality, use cost-benefit analysis.

Variation If the stem asked “when the cost of quality share is high, what is the first step?”, you would first analyze the structure of the cost of quality (how much prevention, appraisal and failure each account for), not do a cost-benefit analysis.

Something wrong with this question?

Report an issue with this question

Example 2: rework and scrap costs have risen for three months in a row

Question 2Example

Monthly data on an injection-molded parts project shows rework and scrap costs rising for three months in a row. What should the project manager do?

Show answer and explanation

Correct answer: C

Monthly data on an injection-molded parts project shows rework and scrap costs rising for three months in a row. Rework and scrap are internal failure costs, and a sustained rise means too many defects are being produced. The question asks what the project manager should do.

Rising failure costs show that defects are not being prevented and may not be detected early enough. First analyze where the failure costs come from (which kind of defect, which operation), then optimize preventive measures or take other targeted corrective action based on the causes, cutting defects at the source. The idea of the optimal cost of quality is to find a balance among prevention, appraisal and failure, not to squeeze one item or rely only on more inspection. That also explains why “more inspection” is not a cure-all: inspection can only stop defects before they leave the plant, while prevention makes fewer defects occur in the first place. The answer is C.

Why the other options are wrong

  • A. Inspection is an appraisal cost, and cutting it lets defects be found later, so failure costs will only go higher.
  • B. Continuing with the original process and putting the rework cost into next period's budget does not address why defects are produced, and failure costs will keep accumulating.
  • D. Adding finished-product inspectors only intercepts some of the defects. Defects are still being produced, and rework and scrap do not fall. Adding inspection alone is not the best approach.

Key takeaway When failure costs rise, analyze their source first, then optimize preventive measures based on the causes. Do not rely only on more inspection.

Variation If the data show external failure costs (customer returns) rising while internal failure is very low, the final inspection is not stopping defects, and you need to review the appraisal stage as well.

Something wrong with this question?

Report an issue with this question

Example 3: the four categories of cost of quality are totaled but nobody uses them

Question 3Example

An e-commerce system project has been totaling the cost of quality data for the four categories (prevention, appraisal, internal failure and external failure) every month, but nobody has been using it. What should the project manager do?

Show answer and explanation

Correct answer: A

An e-commerce system project has been totaling the cost of quality data for the four categories every month, but nobody has been using it. The question asks what the project manager should do.

The value of cost of quality lies in using it: analyze the share of each of the four categories, judge whether prevention, appraisal and failure costs are balanced, and then adjust quality spending accordingly. Data that is only collected and never analyzed neither lowers cost nor improves quality. The analysis covers each category's share, the trend over time and the largest single items, and then adjusts prevention and appraisal spending in light of the idea of the optimal cost of quality. So analyze the cost of quality data and optimize quality spending accordingly. The answer is A.

Why the other options are wrong

  • B. Continuing to collect and filing it until closure means storing it without using it, and quality cannot be improved.
  • C. Reducing the totaling frequency cuts the information available for decisions and does not address the problem of nobody using it.
  • D. Cost of quality is project cost management information. The project manager may delegate analysis work but should ensure the data is used and must not hand all project decision accountability to the quality department.

Key takeaway Cost of quality data must be analyzed and used to optimize prevention and appraisal spending.

Variation If the analysis finds that external failure takes a very high share while prevention is very low, analyze the causes and cost-benefit balance before making targeted changes to prevention or appraisal spending. If prevention and appraisal are already very high and failure costs are very low, compare the marginal benefit to determine whether spending is excessive.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Prevention and appraisal spending is neither "the lower the better" nor "the higher the better". While meeting the quality requirements, strike the best balance between cost of conformance and cost of nonconformance and keep the total cost of quality as low as you can.
  • When quality activities run over budget, compare the cost and benefit of each item before deciding. Do not cut everything by the same proportion, and do not add budget without analysis.
  • For unproven claims such as "the higher-spec option saves money" or "one more round of testing is safer", do a cost-benefit analysis first. Do not adopt them outright and do not reject them outright.
  • When the cost of quality share is high, analyze the structure and then optimize. Do not lower the standard, do not cut only prevention and appraisal, and do not just add testing.
  • Cost-benefit analysis is for one specific approach or alternative; cost of quality is for reviewing the structure of overall quality spending.

Key takeaways

  1. There is an optimal cost of quality: beyond it, adding more prevention/appraisal spending is neither beneficial nor cost-effective.
  2. The later a defect is found, the more it costs: early testing and early prevention lower the cost of fixing, and reduce rework and waste.
  3. To judge whether one specific quality activity or alternative is worth it, use cost-benefit analysis; to review the structure of quality spending, use cost of quality.
  4. When quality activities run over budget, compare cost and benefit and trade off. When the cost is high, analyze the structure first, then optimize.
  5. Worked-example approach: classify first, then total the cost of conformance and the cost of nonconformance and add them. Check whether it pays off with "reduction in failure costs minus extra spending".
  6. Cost of quality data must be analyzed and used to optimize prevention and appraisal spending.

This chapter has 15 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.