Cheat sheet · free to read or print
PMP Cheat Sheet: Scope
The key points and common traps of 22 lessons in 6 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.
Requirements Elicitation
Lesson 1: Scope Performance Domain: Value, Quality and the Six Processes
- Goal of the Scope domain: capture all the work required to complete the project successfully and do no unnecessary work; quality belongs to it as well.
- Six processes: Plan Scope Management, Elicit and Analyze Requirements, Define Scope and Develop Scope Structure (planning); Monitor and Control Scope and Validate Scope (monitoring and controlling).
- Project scope is the work performed to deliver the product; product scope is the features, functions and characteristics of the product, service or result.
- The scope baseline is the approved version of the scope documents. In predictive projects it is made up of the project scope statement, the WBS and the WBS dictionary, and changes go through formal change control.
- Adaptive projects set the scope baseline at the start of each iteration, manage scope with a backlog, and the product owner approves changes flexibly.
- To develop and manage scope: reach agreement with stakeholders, decompose level by level, and control changes by procedure.
- Thinking the Scope domain only covers “what to build”. It also covers quality, and quality is an integral attribute of scope.
- Confusing project scope with product scope. The first is the work; the second is the features, functions and characteristics of the product.
- Treating requirements as scope. Requirements are needs that are collected and analyzed; scope is the product features and project work that are defined and approved on that basis. They are not like-for-like things whose quantities you can compare directly.
- Assuming adaptive projects have no scope baseline or no scope management. They manage scope too; the baseline is simply set at the start of each iteration and the product owner approves changes flexibly.
- Confusing Validate Scope with Monitor and Control Scope. The former is formal acceptance by the customer, the sponsor or another authorized stakeholder; the latter is internal monitoring and management of changes.
Lesson 2: Elicit and Analyze Requirements: Objectives, Inputs, Requirements Documentation and the Six Requirement Classes
- Elicit and Analyze Requirements defines and documents stakeholder requirements; its output is the requirements documentation (and, as common exam practice, the requirements traceability matrix).
- Before baselining, each requirement is unambiguous (measurable and testable), traceable, complete, consistent and accepted by key stakeholders.
- Six classes: business, stakeholder, solution (functional and nonfunctional), transition and readiness, project, and quality.
- Requirements documentation describes how individual requirements should meet the business needs of the project; the scope statement defines the approved project and product scope, major deliverables, acceptance criteria and explicit exclusions.
- To avoid “not what the customer wanted,” elicit and confirm requirements accurately up front.
- Adaptive projects collect requirements as user stories and keep ranking them in the backlog.
- Requirements documentation holds requirements (what is wanted), not scope (what will and will not be done). Requirements are recorded in the requirements documentation; scope is selected from them by the later Define Scope process and written into the project scope statement. Likewise, the requirements management plan contains no specific requirements, and the scope management plan contains no specific scope.
- Requirements are not scope. The requirements documentation collects all the requests; the scope statement decides which are done.
- The requirements management plan contains no requirements, and the scope management plan contains no scope.
- The requirements documentation is an output of Elicit and Analyze Requirements. “Where do requirements come from?” is asking about inputs (charter, business case, stakeholder register and so on).
- Words like “satisfying, convenient, fast” are not unambiguous and cannot go into the baseline. Before baselining, requirements must be unambiguous, traceable, complete, consistent and accepted.
- A quality requirement is a condition or criterion for validating a deliverable; it is not a functional requirement. Do not confuse acceptance criteria with functions.
Lesson 3: Requirements Elicitation Techniques: From Brainstorming to Prototypes and Facilitation
- Brainstorming for ideas, interviews for in-depth or sensitive information, focus groups for the attitudes of one type of person, questionnaires for reach and statistics, benchmarking for borrowing best practice.
- Document analysis, design thinking and meetings are also techniques PMBOK 8 lists.
- When you need early feedback on a working model to clarify the expected product, use a prototype (observation/conversation helps when users cannot describe current work; lack of experience is only a supporting condition). A storyboard is a kind of prototype, often used for user stories.
- For disagreement that needs consensus, use a facilitated workshop. JAD for software and QFD for manufacturing are common exam names.
- An affinity diagram groups ideas; a mind map draws the links between ideas with lines.
- Exam tip (common exam practice): start with the signals in the situation: number of people, geography, confidentiality, interaction, industry, and whether there is prior experience.
- When customers find it hard to state their requirements in words alone, a prototype is usually more direct than interviews alone; interviews can still be used alongside it to probe and clarify. Expert judgment is judgment based on expertise, experience or training, and the experts may come from inside or outside the organization, but it cannot replace users' own feedback on what they need. The Delphi technique is mainly used to collect experts' opinions anonymously and bring them gradually together. A judgment the exam often asks for: the customer cannot articulate the needs and they must be clarified through hands-on experience, so choose the prototype.
- Disagreement that needs consensus: facilitation. A large number of ideas: brainstorming. Scoring and choosing among several alternatives: only then multicriteria decision analysis (see the next lesson).
- The software industry often maps to joint application design and manufacturing to quality function deployment (common exam practice). The real basis for the choice is always “competing requirements need consensus, so facilitation”; the industry is only a supporting clue, and you must also look at the purpose of the workshop: JAD focuses on working together to clarify system requirements, while QFD focuses on turning customer needs into technical requirements and ranking them.
- Interviews versus focus groups: an interview is an in-depth conversation with one person or a few and suits sensitive information; a focus group is an interactive discussion among a group of similar people.
- Questionnaires and surveys collect information in writing in one direction, with no interaction, so they cannot resolve a disagreement that has already appeared.
- An affinity diagram mainly groups a large number of ideas for analysis; a mind map can organize and show the links between ideas, and PMBOK 8 also lists it among the brainstorming techniques, where it can consolidate ideas and generate new ones.
Lesson 4: Decision Methods and Prioritizing Requirements: Voting, Multicriteria Analysis, MoSCoW and User Stories
- Group decisions: unanimity, majority (more than 50%), plurality, autocratic, and multicriteria decision analysis (weight first, then score).
- The nominal group has everyone put forward ideas first and then discuss and rank; Delphi is anonymous and multi-round, with opinions gradually converging.
- Prioritization/ranking can apply to stakeholder requirements or to stakeholders themselves; requirements are usually ranked by value, cost of delay and similar criteria, and stakeholders usually by interest and influence.
- The four MoSCoW tiers: must have, should have (important but can be postponed), could have, will not have; others are the 100-point method, cost of delay and Kano analysis.
- Adaptive: user stories go into the backlog. Two ranking approaches that are common exam practice: relative weighting looks at benefit plus loss from absence, and virtual currency votes with handed-out “money”.
- INVEST (common exam practice) has six characteristics for checking user stories; items at the top are detailed and items further down are rough.
- The basis for ranking is value and stakeholders' interest and influence, not who is loudest. Once criteria are agreed, the group can also rank collectively with methods such as the 100-point method (virtual currency is an agile practice).
- When requirements contradict each other, first rank them and assess value and feasibility, then obtain approval. Do not first remove all the conflicting requirements, and do not rush to submit a schedule-extension change request.
- Delphi makes expert opinions converge; it is not one of the elicitation techniques from the previous lesson. The nominal group ranks by voting but does not require anonymity or multiple rounds.
- Do not mix up the four names: relative weighting (benefit plus loss from absence), MoSCoW (four tiers), Kano (satisfaction) and virtual currency (voting with handed-out money). Relative weighting and virtual currency are agile practice and common exam practice.
- In INVEST, “Testable” requires a specific description. A story that is too large is mainly a “Small” problem, not an “Independent” problem; only if it cannot be estimated because it is too large do you also check “Estimable”.
Requirements Traceability Matrix
Lesson 1: Requirements Traceability Matrix: Definition, Purposes, Columns and Attributes
- The requirements traceability matrix is a grid that links each requirement to its origin, its objectives and the deliverable that satisfies it.
- Four purposes: each requirement adds business value; requirements can be tracked throughout the life cycle; every approved requirement is delivered; it provides a structure for product scope changes.
- Columns: ID, requirements description, business objectives, project objectives, WBS deliverables, design, development, test strategy and test scenarios.
- Attributes: source, rationale, owner, priority, version, status and status date; stability, complexity and acceptance criteria can be added.
- When you see "link every requirement to an objective" or "prevent omissions," choose the requirements traceability matrix.
- The requirements traceability matrix is not the requirements documentation: the documentation lists requirements, and the matrix links them.
- The matrix is not the scope statement: the scope statement covers scope and acceptance criteria, and the matrix shows where each requirement lands and whether it has been tested.
- The matrix's "test strategy and test scenarios" column links requirements to testing. A defect report exists only after tests are run; it is not a document produced when eliciting requirements.
- The change log only records changes. To check whether each requirement has been delivered, look at the matrix.
- The project charter provides a high-level project description, boundaries, major deliverables, project objectives and similar information. It does not link each requirement to an objective one by one, so it cannot replace the matrix.
Lesson 2: Requirements Management Plan, and Using the Matrix for Change and Acceptance
- The requirements management plan describes how requirements will be analyzed, documented and managed: planning, tracking and reporting of activities, configuration management, prioritization, metrics and the traceability structure.
- The requirements management plan contains no actual requirements; it differs from the scope management plan, the configuration management plan and the change management plan.
- When a requirement changes, do impact analysis along the matrix. A predictive project then goes through change control; an adaptive project adjusts the backlog under governance rules. Update the documents and the matrix as well.
- At acceptance, check item by item: is there a deliverable, is there a test strategy and test scenarios, and is the status completed?
- When the customer says a requirement was not implemented, check the matrix first. If an approved requirement has no record, add it immediately, verify the underlying artifacts and complete valid trace links; address real gaps through change control and the quality plan.
- The scope management plan contains no scope, and the requirements management plan contains no requirements: both plans cover only how things are managed.
- The configuration management plan governs versions and the change management plan governs how changes are handled; neither is the basis for "how requirements are analyzed, documented and managed."
- When the customer says a requirement was not done: verify against the matrix first, then decide whether to build it or go through change control. Do not agree straight away, and do not judge from memory or experience.
- An approved requirement cannot be put on hold just because "the customer did not mention it." In a predictive project, once the scope baseline is set, adding or dropping requirements goes through change control. In an adaptive project, the product owner usually handles it by managing the backlog, reprioritizing and iteration planning, following the established governance rules.
- The structure of the matrix is defined by the requirements management plan; it is not a table made up on the spot.
Project Scope Statement
Lesson 1: Plan Scope Management: The Scope Management Plan and the Requirements Management Plan
- The output of Plan Scope Management is project management plan updates, specifically to the scope management plan and the requirements management plan; the objective is to define how the project will be delivered.
- Scope management plan: how scope will be defined, developed, monitored, controlled and validated; it includes four processes: preparing the statement, creating the WBS, establishing and maintaining the baseline, and formal acceptance.
- Requirements management plan: how requirements will be analyzed, documented and managed.
- The scope management plan contains no scope and the requirements management plan contains no requirements; remember the rule that the "how-only" plans hold no actual content.
- If the plan lacks monitoring and control, add those processes and update the scope management plan.
- Adaptive projects also plan scope management, with a more iterative and collaborative approach.
- "The scope management plan contains the project scope" is wrong: the plan sets out only the method, and the scope is in the scope baseline.
- The scope management plan sets the acceptance procedure; the scope statement holds the acceptance criteria.
- The requirements management plan covers analyzing, documenting and managing requirements; it does not cover monitoring and controlling scope.
- The scope management plan is not a fixed template. It can be formal or informal, detailed or broadly framed, depending on the needs of the project.
- Adaptive projects also have a scope management plan, only more iterative and collaborative. Do not read this as "agile does not need plans."
Lesson 2: Define Scope: Objective, Inputs, Tools and Techniques
- Define Scope: select from the requirements documentation the requirements that will finally be built, write a detailed description of the project and product, and develop a quality management plan.
- Inputs: the charter, requirements documentation, assumption log, project management plan and so on; outputs: the scope statement and updated requirements documentation.
- Tools and techniques: expert judgment, decision-making, data analysis, decomposition, facilitation and product analysis (alternative analysis and multicriteria decision analysis are common specific techniques).
- When the boundary is disputed and consensus is needed, use facilitation; when an expert is on site only briefly, first have the expert understand the difficulty.
- Define Scope can be repeated: what cannot yet be written in detail is written at a high level first, then elaborated.
- Predictive projects can usually do it at the start of the project; adaptive and hybrid projects can do it at the start of each iteration, with scope becoming clearer step by step through the backlog.
- Define Scope selects from the requirements documentation. It does not accept every requirement as listed; there are usually more candidate requirements than the requirements finally included in scope.
- When the boundary is disputed, use facilitation to reach consensus. Do not first draw up a change management plan and leave the dispute for later, and do not let the team decide alone.
- Do not confuse facilitation (consensus needed), brainstorming (ideas needed) and multicriteria decision analysis (scoring several alternatives).
- An adaptive project does not require the scope to be fully settled before work starts, nor the product owner's partial approval before work starts to turn the scope into a baseline.
- Besides the scope statement, the outputs of Define Scope include updates to the requirements documentation. Identifying quality requirements and standards, and determining how compliance will be shown, are part of the process objective, but the outputs in Figure 2-16 list only the scope statement and the requirements documentation.
Lesson 3: The Project Scope Statement: Four Components, Acceptance Criteria and Exclusions
- The scope statement describes the project scope, major deliverables, assumptions and constraints, and covers both project scope and product scope.
- The detailed statement has four components: project scope description, deliverables, acceptance criteria and project exclusions.
- Acceptance criteria are in the scope statement; exclusions are in the scope statement and are used to manage expectations and reduce scope creep.
- The statement is the basis for judging whether a change request or additional work is within the project's boundaries.
- The quality management plan is also an objective of Define Scope; it describes how to show that quality requirements are met.
- Scope dispute: review the scope statement first, then decide whether to go through change control.
- Exclusions are written in the scope statement, not in the project charter or the scope management plan.
- Acceptance criteria: the scope statement contains or refers to them; detailed criteria for a specific WBS component may also be in the WBS dictionary; when a question asks only for deliverable criteria, the scope statement is usually the answer.
- In a scope dispute, check the statement first (especially the exclusions) to confirm whether the item is in scope, and only then talk about change. Do not build it straight away, and do not raise a change straight away.
- The quality management plan covers quality requirements and how to show they are met; it has nothing to do with disputes about whether something is in scope.
- Deliverables are not only the product itself; they also include ancillary results such as project management reports and documentation.
Lesson 4: Charter, Requirements Documentation and Scope Statement: Progressive Elaboration
- The charter, the requirements documentation and the scope statement are progressive elaborations: high-level, all requirements, selected scope.
- There are usually more candidate requirements collected than are finally included in scope; requirements are collected and scope is selected from them, so you cannot compare the two counts directly.
- The statement and the requirements documentation are linked in both directions: Define Scope may trigger an update to the requirements documentation.
- In a predictive project, the scope statement, WBS and WBS dictionary together make up the scope baseline.
- First collect the requirements, settle the scope and obtain appropriate approval and consensus under the governance arrangements, and only then create the WBS.
- Common exam practice: when the statement is not approved and the scope boundary is unclear, do not start work rashly; explain the risks to management first.
- The requirements documentation holds all collected requirements, and the scope statement holds the ones selected to be done; do not put every requirement straight into scope.
- The scope statement, the WBS and the WBS dictionary together make up the scope baseline; the statement is only one of the three.
- The charter gives only high-level boundaries and is not the detailed scope. Issuing the charter only means the project is authorized; whether conditions for reliable execution are in place depends on the governance arrangements and on whether the team has enough understanding of and confidence in the course of action.
- Once the scope baseline is set, new requirements can still come in, but they must be handled under the applicable change governance (formal change control in a predictive project). You cannot reject them all, and you cannot quietly accept them.
- When the statement is not approved, the project manager's correct move is to explain the risks to management; not to report it upward and leave it there, not to just comply, and not to walk away.
Work Breakdown Structure
Lesson 1: WBS Definition and Decomposition: Breaking All the Scope Down to Work Packages
- The WBS is a hierarchical decomposition of the total scope of work, and its lowest level is the work package; predictive and hybrid projects use a WBS, and adaptive projects use the product backlog as the counterpart.
- The main technique of Develop Scope Structure is decomposition; the main outputs are the WBS and the WBS dictionary (adaptive projects also produce user stories and the product backlog), which in a predictive project, together with the project scope statement, make up the scope baseline.
- Five decomposition activities: identify the deliverables, set the structure, decompose level by level, assign codes, verify the degree of decomposition.
- The second level can be organized by phase or by major deliverable; outsourced parts can be included, with the seller developing a separate WBS; different deliverables can have different numbers of levels.
- Nodes are deliverables, not activities; all product work and project management work must be included.
- The WBS decomposes deliverables, not activities. An option that lists "every activity needed to complete the deliverables" in the WBS confuses the WBS with the activity list.
- Requirements are not scope, and they are not the WBS. Collecting requirements only records stakeholder expectations; it does not guarantee that all the work has been listed.
- When a deliverable is too big to hand out, decompose it first and then assign it. Do not add people first, and do not register a risk first.
- Project management work is also project work and belongs in the WBS.
Lesson 2: Work Packages, Planning Packages and Control Accounts: Where to Stop Decomposing
- A work package is the lowest level of the WBS; its cost and duration can be estimated and managed, and it also makes it easy to name a clearly responsible person.
- A control account is a management control point with two or more work packages; each work package belongs to a single control account.
- A planning package is below the control account and above the work package: known content, unknown detailed activities, used for rolling wave planning.
- The 100% rule must be followed (the WBS includes all product and project work, with nothing left out and nothing extra); assigning clear responsibility is an important management practice that can be reflected in the WBS dictionary and the responsibility assignment matrix; 80 hours and 4-6 levels are only rules of thumb.
- When departments draft WBS parts separately, use a review by everyone to remove duplicates and fill gaps; project management work belongs in the WBS too (represented by deliverables such as the project management plan and status reports).
- The work package is the lowest level of the WBS. Bigger is not better, and smaller is not better. Stop decomposing when its cost and duration can be estimated and managed and the level of detail is enough to exercise the control needed; clear responsibility can serve as a supporting consideration.
- Each work package belongs to only one control account; it cannot hang under two control accounts at once.
- A planning package is for the case of "content known, detailed activities unknown." Even if a rough budget or a high-level duration estimate already exists, it can remain a planning package, until the work is elaborated to the lowest level at which cost and duration can be estimated and managed and then forms work packages.
- 80 hours and 4-6 levels are only rules of thumb. Common exam practice: when a question asks which principles are "must follow" and these two are among the options, choose the 100% rule and the clear-responsibility principle.
- A responsibility assignment matrix can assign and clarify responsibility based on identified WBS components or activities, but it cannot replace a WBS review for removing duplicates.
Lesson 3: The WBS Dictionary and the Scope Baseline: How Predictive, Adaptive and Hybrid Projects Manage Scope
- The WBS dictionary provides detailed information for each WBS component, such as work description, resources required, quality requirements and acceptance criteria; most of it is created by other processes and added later.
- Scope baseline = project scope statement + WBS + WBS dictionary; in predictive projects it is changed through formal change control, and it is the basis for comparing actual results later.
- Adaptive projects use the product backlog; the baseline is set at the start of each iteration, and the product owner dynamically approves changes.
- Hybrid projects are managed part by part: the predictive part has a baseline and goes through change control, and the adaptive part uses a backlog.
- For a work package's description of work, resources required and acceptance criteria, look in the WBS dictionary. The WBS gives only the hierarchy and numbers, and the scope statement covers the whole project, not a single component.
- The scope baseline is a set of three things, not just the WBS, and it does not include the requirements documentation or the project charter.
- A hybrid project does not freeze a baseline for everything, and it does not use only a backlog for everything.
- Do not swap the methods: the part that needs a baseline and formal change control is the predictive part, and the part that can be adjusted dynamically is the adaptive part.
- The adaptive counterpart of the WBS is the product backlog, not the user story (a user story is only one entry in it).
Monitor and Control Scope and Scope Creep
Lesson 1: Monitor and Control Scope: Purpose, Inputs and Outputs
- Monitor and Control Scope is an ongoing process: it monitors and manages scope changes and measures the quality and value of deliverables so that scope and quality stay aligned with the scope baseline.
- The point is not to block change but to keep change under control after assessment.
- Inputs include the scope baseline, scope management plan, quality management plan, requirements documentation, quality metrics, approved change requests and deliverables.
- Outputs include verified deliverables, change requests, quality reports, quality control measurements and work performance information.
- Verify first, accept second: verified deliverables are an input to Validate Scope.
- Monitor and Control Scope does not forbid change, and it does not fold in new requests at will. It keeps change under control and keeps the baseline valid.
- The baseline is not redone uniformly at every phase. Only approved changes lead to a baseline update.
- The team checking internally whether deliverables are correct is Monitor and Control Scope; formal customer acceptance is Validate Scope. Do not jump ahead or reverse them.
- Manage Quality Assurance is about whether the project's processes are carried out to standard. It is not item-by-item inspection of completed deliverables.
Lesson 2: Scope Creep and Gold Plating: Two Ways Work Quietly Exceeds the Baseline
- Scope creep: the uncontrolled expansion to product or project scope without adjustments to time, cost and resources.
- Gold plating: the team adding out-of-scope content that nobody asked for. Both bypass change control, and both must be stopped.
- Prevention: project exclusions in the scope statement; timeboxing in adaptive life cycles; a scope management plan that states how scope is monitored and controlled and how the scope baseline is approved and maintained; a change management plan that states how changes are raised, recorded, assessed and approved, and how the change control board, its authority and the change control system work.
- Monitoring: the three percentage measures of scope creep, requirements stability and scope definition accuracy.
- When someone proposes adding a feature, first check whether it is within scope; until approved, do only the agreed scope.
- The key to scope creep is “uncontrolled”: an increase approved through change control is not creep.
- Gold plating does not earn extra credit. However valuable the idea, it cannot be done without change control, and customer satisfaction does not alter that.
- The project manager has no authority to approve new content outside the change control procedure, and consensus within the team cannot replace formal change control.
- The FIRST step is to check whether the idea is within scope, not to accept it at once, reject it at once or submit a change request at once.
- Management reserve deals with unforeseen work within scope. It is not for absorbing added scope.
Lesson 3: What to Do When You Find Out-of-Scope Work: Control First, Then Change
- Control first, then change (a common exam practice summary): record the situation, assess the impact, submit a change request, update the applicable baselines, plans, documents and change log after approval, communicate the decision and status, then implement the approved change and monitor the results.
- When an out-of-scope request arrives, FIRST assess its impact on scope, schedule, cost, resources, risk and so on, then let the person with authority decide.
- Whoever raises a change, use the mechanism appropriate to the approach: for a sponsor or customer, a predictive project suggests a formal change request, and an adaptive project records it in the product backlog, analyzes its impact and ranks it; for an externally mandated requirement, a predictive project or the baselined part of a hybrid project uses an internally submitted change request, while an adaptive project has the product owner add the requirement to the product backlog and rank it after impact analysis.
- If out-of-scope work is still under way, pause further work on it while assessing its impact; use change control to decide whether to keep or roll it back.
- Changes affect other performance domains and must be approved within the established governance structures.
- Out-of-scope requests land in change control: record the request, assess the impact, submit a change request, and update the baseline only after approval. Merely informing the sponsor, or quietly accepting, is not control.
- “FIRST” means analyze the impact: not reject first, not submit to the board first, and not look for alternatives first.
- Whoever raises the request, use the change mechanism appropriate to the approach. For requests from a sponsor or customer, a predictive project suggests that they submit a formal change request as required, and an adaptive project records the request in the product backlog, analyzes its impact and ranks it. A regulatory requirement is a compliance requirement imposed from outside: on a predictive project, or the baselined part of a hybrid project, the project manager records it, assesses its impact and submits a change request internally; on an adaptive project, the product owner adds it to the product backlog and ranks it after impact analysis.
- Doing the work first and completing the paperwork later reverses the order, and a change filed after the fact may not be approved.
- Do not use management reserve to absorb added scope. Management reserve covers unforeseen work within scope.
Lesson 4: Variance Analysis, Trend Analysis and Inspections: Tools for Monitoring Scope
- Variance analysis determines the cause and degree of difference between baseline and actual, and decides whether corrective or preventive action is needed.
- Trend analysis uses historical data to forecast and flags anomalies early; root cause analysis goes to the deepest cause; inspections examine work products against standards.
- A control chart judges whether a process is stable, and specification limits (from requirements) differ from control limits (from statistics).
- Process automation (including RPA) uses software to take on rule-based repetitive tasks.
- When a variance is found: analyze the cause first, then correct or go through change. Do not accommodate it, cover it up or privately alter the baseline.
- When a variance is found, analyze the cause first, then decide on corrective action, preventive action or change. Recording and reporting only inform people; they do not count as handling it.
- The baseline is the ruler. It cannot be altered to make a variance go away, and a scope baseline update needs change control.
- Control limits differ from specification limits: the former are calculated statistically from the process, and the latter come from requirements.
- Variance analysis looks at the present state and its causes; trend analysis looks at where things are heading. Do not mix them up.
Lesson 5: Scope Monitoring in Adaptive Environments: The Backlog and the Product Owner
- On an adaptive project, the scope baseline is defined at the start of each iteration according to expected value, and the product backlog carries the scope.
- The product owner usually approves changes dynamically, without a formal change control procedure. New requirements go into the backlog and are scheduled after assessment by priority, unless organizational governance, a contract or regulation requires otherwise.
- A predictive project records changes in a change log. An adaptive project looks at the rate of scope completion, the rate of adding new scope and how feedback is taken in.
- A rising remaining-work line on a burndown chart means more remaining work, so check the cause first; unassessed additions are the ones that count as creep.
- When a team member receives a request to adjust a requirement, talk with the product owner: do not accept it on one's own and do not turn it away across the board.
- Adaptive projects usually do not use a formal change control procedure like a predictive project; the product owner mostly approves changes dynamically (where organizational governance, a contract or regulation requires otherwise, approval follows those rules). Options that mention a “change control board” or “escalate to management” are mostly predictive practice.
- Adaptive work embraces change. It is neither refused across the board nor done at once in the current iteration. After assessment and ranking, items are selected at iteration planning.
- The project manager and the Scrum Master do not decide what goes into the backlog. That belongs to the product owner.
- A burndown line that flattens does not mean scope increased. A rising remaining-work line means remaining work grew and the cause must be checked first (new work, scope adjustment, an omission, re-estimation); only unassessed additions are a creep signal.
Validate Scope
Lesson 1: Purpose and Position of Validate Scope: Verify First, Then Accept
- Validate Scope has two main objectives: checking the processes used to achieve quality standards, and formalizing acceptance of the deliverables.
- Monitor and Control Scope verifies (the team checks internally whether deliverables are correct) and Validate Scope accepts (whether the customer accepts them). Verify first, accept second.
- What goes into Validate Scope is verified deliverables, and what comes out is accepted deliverables.
- Acceptance criteria are recorded in the project scope statement and can be added to the WBS dictionary and other documents as needed.
- Validate Scope on a predictive project is carried out periodically as deliverables are delivered (common exam practice); before closure, formal acceptance must be obtained and the approval recorded (with a signature where required).
- Passing a quality check is not acceptance. An internal check only shows the deliverables have been verified; before they are delivered for the customer's use, the customer or a stakeholder with acceptance authority must formally accept them.
- Without formal acceptance, you cannot complete a closure or delivery milestone whose exit condition is acceptance (other milestones are judged by their own completion criteria), and you cannot hand the system straight over to operations.
- If the sponsor merely says it is approved without the deliverables being checked against the acceptance criteria, acceptance loses its objectivity.
- Validate Scope is not done only once at the very end. With phased delivery, each batch can be accepted once it is completed and verified.
- Monitor and Control Scope is verification and Validate Scope is acceptance; reversing them is a classic wrong option.
Lesson 2: Inputs and Tools of Validate Scope: What You Check Against and How
- Inputs: verified deliverables; requirements documentation, scope baseline, quality reports, work performance data and quality control measurements; and enterprise environmental factors and organizational process assets.
- Tools: inspection, customer talks and tests, process analysis and review meetings, plus data gathering, data analysis and decision-making.
- Customer talks and tests are collaborative activities with the customer during development and testing that gather feedback, improve transparency and build trust.
- When the customer refuses to sign, check item by item against the acceptance criteria first, then decide whether to rework, analyze causes or go through change.
- The input is verified deliverables, and the output is accepted deliverables; change requests and lessons learned updates are also on the output side.
- Acceptance criteria are in the scope baseline (the scope statement and WBS dictionary); they are not decided verbally by the customer on the spot.
- When the customer will not sign, check against the acceptance criteria first, not rework first, not ask for money first and not do root cause analysis first.
- “Customer talks and tests” means interacting continuously with the customer during development and testing; a review meeting is a meeting held to review deliverables. Do not confuse them.
Lesson 3: Outputs of Validate Scope: Accepted Deliverables, Sign-Off and Handling Failed Acceptance
- Accepted deliverables: products, services and capabilities confirmed by a designated person or team against established criteria and approved because they meet the acceptance criteria; acceptance is formally confirmed per the agreement and governance arrangements and recorded (with a signature where required).
- Failed acceptance: record the reason and assess the impact first. If a change is needed, raise a change request under the change management plan, obtain authorized approval, implement the remedy or correction, then reverify and seek acceptance again.
- New requests at acceptance: request acceptance of what is complete while putting the new request in a change request. Handle the two matters separately.
- Validate Scope updates quality reports, work performance information and requirements documentation, and produces lessons learned updates (relevant lessons can be recorded in the lessons learned register).
- Accept first, then hand over and close. Closure requires stakeholder approval that the project is complete, and project information is archived.
- Acceptance should be formally confirmed by people with authority under the scope management plan, the agreement and the governance arrangements, with traceable evidence kept; a signed document is a common form but not the only one. Handing the package to a liaison person or a verbal agreement is normally not formal acceptance.
- Failed acceptance: first record (find out) the reason, then handle it in the project's tailored way of handling change. When a change is needed, a predictive project submits a change request through change control, and an adaptive project updates and re-ranks the backlog. Do not start fixing before that, and do not ask the customer to sign first and discuss afterward.
- New requests at acceptance must not be bundled with acceptance of work already done: request acceptance of what meets the criteria while placing the additions in a separate change request, and handle the two matters independently.
- On a predictive project, change requests are assessed under the prescribed procedure and approved, deferred or rejected by the designated authority, and implemented only after approval; on an adaptive project, impact analysis and prioritization normally happen through the backlog. An unauthorized outside department, or a single department on the customer's side, cannot directly expand scope.
- Formal acceptance should normally be obtained before final handover and closing the project. The final report and handover preparations can be drafted earlier, but the project cannot be declared closed before acceptance is complete; the exact order follows governance and tailoring.
Lesson 4: Acceptance in Adaptive Environments: Definition of Done, Definition of Ready and Acceptance Criteria
- Definition of done (DoD): a checklist of all criteria that must be met for something to be considered ready for customer use; in common exam practice, it is used to carry non-functional requirements.
- A user story carries its own acceptance criteria, clarified with the item at iteration planning and set before development at the latest.
- Definition of ready (DoR): the conditions that must be met before work starts, also called a “full kit”; the DoD governs whether work is done and the DoR governs whether it can start.
- A gap in expectations, or stories that do not get done, is usually because the acceptance criteria were not made clear in advance.
- Adaptive acceptance continues with the iterations: at close of an iteration, confirm that the acceptance criteria are all met and the deliverables have been reviewed and accepted by stakeholders.
- Acceptance criteria must be clear and reviewed before development, and that is exactly what the definition of ready checks (the DoR checklist only confirms that “acceptance criteria are clear”).
- PMBOK 8: the DoD is a checklist of all criteria that must be met. Common exam practice: general testing, quality and compliance requirements that every increment shares go into the DoD, while the acceptance conditions of a specific feature go in the story's own acceptance criteria.
- The definition of done is a baseline shared by the whole team. It is not one expert's or one department's review.
- Acceptance criteria are not added after the demo, and they are not an excuse for the customer “deliberately setting obstacles”; a gap in expectations is usually a sign that the standard was not made clear.
- Adaptive does not mean no acceptance: acceptance continues with the iterations, based on the DoD and the stories' acceptance criteria.