PMP · Scope · 4 lessons · about 44 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

How scope will be managed has to be set out first in a plan; what the scope is has to be written up as a description everyone agrees to. This chapter focuses on two related processes in the Scope performance domain (with Elicit and Analyze Requirements in between). Plan Scope Management produces the scope management plan and the requirements management plan, which set out "how to manage." Define Scope selects from the requirements documentation the requirements that will actually be built and produces the project scope statement, which says "what is in and what is out"; the process objective also includes identifying quality requirements and how compliance with them will be demonstrated. The statement then goes through Develop Scope Structure and, together with the WBS and the WBS dictionary, becomes the scope baseline.

The core judgment in this chapter comes down to two sentences: the plan governs the method and the statement governs the content; requirements are collected, scope is selected. The scope statement is a common exam topic: where acceptance criteria are written, where exclusions are written, and what to check first when scope is disputed.

Lessons in this chapter

How to study this chapter

First tell "plans" from "documents." The scope management plan and the requirements management plan set out how to do things; the scope statement and the requirements documentation record content. In multiple-choice questions, a question about "how, and by what procedure" often points to a plan, while a question about "what are the deliverables, what are the acceptance criteria, what is not being done" often points to the statement. Then memorize the four components of the statement and where the two key items live: acceptance criteria and exclusions are both in the scope statement. Finally, master the tools and techniques of Define Scope and their signal words, especially facilitation: when key stakeholders disagree about the boundary, use it to reach consensus. For adaptive questions, do not apply the predictive habit of "fix the scope before work begins"; scope becomes clear step by step at the start of each iteration, driven by the backlog.

Chapter map

Plan Scope Management ──→ Scope management plan (how to manage: define, develop, monitor, control, validate)

  • → Requirements management plan (how to manage requirements)

Define Scope ──→ Project scope statement

  • Project scope description · Deliverables
  • Acceptance criteria · Project exclusions
  • (also updates the requirements documentation; the objective includes identifying quality requirements and how compliance will be demonstrated)

Project charter → Requirements documentation → Scope statement (progressive elaboration)

Predictive: scope statement + WBS + WBS dictionary = scope baseline (adaptive: set at the start of each iteration from the requirements prioritized by expected delivery value)

Lesson 1

Plan Scope Management: The Scope Management Plan and the Requirements Management Plan

Lesson video

Lesson overview

How scope will be managed has to be set out first in a plan; what the scope is has to be written up as a description everyone agrees to. These two jobs belong to two different processes: Plan Scope Management produces the scope management plan, and Define Scope produces the project scope statement. This lesson covers the first. What it sets out is "how to do it," not "what to do." That is the heart of this lesson and the point most often confused on the exam: when a multiple-choice question offers both the "scope management plan" and the "scope statement," one governs the method and the other governs the content. The following lessons cover Define Scope and the scope statement.

Objective, inputs and outputs of Plan Scope Management

The objective of Plan Scope Management is to create a scope management plan. It defines how the project will be delivered by establishing all of the work required to complete the project and eliminating work that will not add value. Its key benefit is that guidance on scope management is provided to ensure that value is delivered to stakeholders. The plan should be defined, developed, monitored, validated and controlled based on the project life cycle.

The inputs to the process include the project charter, the project management plan, requirements documentation, the risk register, the stakeholder register, enterprise environmental factors and organizational process assets. Common tools include expert judgment, data gathering (interviews, focus groups, questionnaires and surveys), data analysis, and test and inspection planning. The output is project management plan updates, chiefly the scope management plan and the requirements management plan. Adaptive projects do this too. The objective is the same, ensuring that value is delivered; the approach is simply more iterative and collaborative than in predictive projects.

What each of the two plans covers

The scope management plan describes how the scope will be defined, developed, monitored, controlled and validated. Its components include at least four processes: the process for preparing a project scope statement; the process that enables the creation of the WBS from the detailed project scope statement; the process that establishes how the scope baseline will be approved and maintained; and the process that specifies how formal acceptance of the completed project deliverables will be obtained. It can be formal or informal and broadly framed or highly detailed, based on the needs of the project.

The requirements management plan describes how project and product requirements will be analyzed, documented and managed. It covers how requirements activities will be planned, tracked and reported; how configuration management will be done; how requirements will be prioritized; which metrics will be used and why; and the traceability structure that reflects the requirement attributes (covered in the previous chapter).

Scope management planRequirements management plan
What it coversHow scope will be defined, developed, monitored, controlled and validatedHow requirements will be analyzed, documented and managed
Specific contentProcesses for preparing the statement, creating the WBS, establishing and maintaining the baseline, and formal acceptancePlanning, tracking and reporting of activities, configuration management, prioritization, metrics, traceability structure
What is not in itNo scope (scope is in the scope baseline)No requirements (requirements are in the requirements documentation)

Which plans contain no actual content

There is a rule of thumb that is common exam practice: if "scope management plan" is among the options and the question asks about specific scope or specific requirements, it is generally not the answer, because the plan contains no scope. The same reasoning applies to the other plans that describe only "how." Remember it as: the scope management plan contains no scope, the schedule management plan contains no schedule, the financial management plan contains no costs, and the risk management plan contains no risks. Plans for other areas, such as quality, resources, communications and stakeholders, often contain both the method and specific content. For example, the quality management plan holds both the quality standards and the methods for controlling quality. So where is the scope itself? In the scope baseline. In a predictive project the scope baseline is made up of the scope statement, the WBS and the WBS dictionary together; in an adaptive project the scope baseline is set at the start of each iteration based on the value expected from the delivery and aligned with the prioritized requirements.

Using the plans: what to do when part of the plan is missing

The scope management plan should cover all five stages: define, develop, monitor, control and validate. Suppose you find that the plan explains only how to prepare the scope statement and create the WBS, with nothing on how to monitor and control scope or how to handle scope changes. You should add those processes and update the scope management plan. Do not stuff the change-handling method into the scope statement (it records the scope itself), do not rely on the change control board to rule case by case on the spot, and do not copy it into the requirements management plan (which covers requirements).

Here is one more distinction. The procedure for formally accepting completed deliverables is in the scope management plan; the conditions a deliverable must meet to be accepted are in the acceptance criteria of the scope statement. The procedure belongs to the plan, and the conditions belong to the statement.

Example: the scope management plan of the campus parcel locker project

After consulting the sponsor, the student union representative and the locker supplier, the project manager wrote a three-page plan. The scope statement is drafted by the project manager and approved by the sponsor. The WBS is decomposed to work packages under the deliverables and reviewed by each team lead. The scope baseline is maintained by the change control board, and any change that adds or removes deliverables must first be assessed for its impact on schedule and cost. Acceptance is carried out with the student union representative and the logistics office present together, checking item by item against the acceptance criteria in the scope statement, and ending with a formal signature. The plan does not say which modules to build; that is for the scope statement and the WBS.

Worked examples

Example 1 Concept: which document defines how deliverables are accepted

Question 1Example

PMLyceum's membership points platform project has been authorized by a project charter and formally launched. The project manager is convening the main stakeholders to prepare a document that sets out the procedure by which completed deliverables will be formally accepted. What is this document?

Show answer and explanation

Correct answer: B

The project charter is approved and the project manager is convening the main stakeholders to prepare a document. The question is which document sets out “the procedure by which completed deliverables are formally accepted,” that is, a plan that sets out the method rather than a document that records specific content.

The scope management plan describes how the scope will be defined, developed, monitored, controlled and validated, and it includes the process that specifies how formal acceptance of the completed project deliverables will be obtained. The document in the stem is meant to set out the acceptance procedure, so the answer is the scope management plan. A simple rule helps: the procedure belongs to the plan, and the conditions belong to the statement. The answer is B.

Why the other options are wrong

  • A. The scope statement holds the acceptance criteria for each deliverable, that is, the conditions the deliverable must meet before it can be accepted. It does not set out the procedure by which acceptance is carried out.
  • C. The requirements management plan sets out how requirements are analyzed, documented and managed. It governs requirements, not the acceptance of deliverables.
  • D. The work breakdown structure is a hierarchical decomposition of project work, used to organize and assign work. It does not set out an acceptance procedure.

Key takeaway The scope management plan sets out “how to manage,” including the process for formally accepting deliverables; the acceptance criteria themselves are written in the scope statement.

Variation If the stem were changed to “what conditions each deliverable must meet to count as acceptable,” the answer would become the acceptance criteria in the scope statement.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: the scope management plan is missing the monitoring and control part

Question 2Example

During planning, the project manager finds that the scope management plan covers only how to prepare the scope statement and create the WBS, and says nothing about how to monitor and control scope or how to handle scope changes. What should the project manager do?

Show answer and explanation

Correct answer: B

In the planning phase of a predictive project, the scope management plan covers only how to prepare the scope statement and create the WBS, and lacks monitoring, controlling and change handling for scope. The question asks how to remedy this.

The scope management plan is supposed to set out how scope will be defined, developed, monitored, controlled and validated. If the monitoring and control parts are missing, add the Monitor and Control Scope process and the way changes are handled, and update the scope management plan, so that every later change has rules to follow. A problem with a plan is solved in the plan. The answer is B.

Why the other options are wrong

  • A. The scope statement records the scope itself (description, deliverables, acceptance criteria, exclusions). It does not set out how changes are handled.
  • C. The change control board approves individual changes, but how scope is monitored and controlled has to be set out in the plan in advance; it cannot rely entirely on ad hoc rulings.
  • D. The requirements management plan covers requirements activities, configuration management and the like. The processes for monitoring and controlling project scope belong in the scope management plan.

Key takeaway The scope management plan covers five stages: define, develop, monitor, control and validate. Whichever is missing, add it.

Variation If the stem said that “the requirements management plan lacks a provision on requirements prioritization,” you would likewise add it and update the requirements management plan, not write it into the scope management plan.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • "The scope management plan contains the project scope" is wrong: the plan sets out only the method, and the scope is in the scope baseline.
  • The scope management plan sets the acceptance procedure; the scope statement holds the acceptance criteria.
  • The requirements management plan covers analyzing, documenting and managing requirements; it does not cover monitoring and controlling scope.
  • The scope management plan is not a fixed template. It can be formal or informal, detailed or broadly framed, depending on the needs of the project.
  • Adaptive projects also have a scope management plan, only more iterative and collaborative. Do not read this as "agile does not need plans."

Key takeaways

  1. The output of Plan Scope Management is project management plan updates, specifically to the scope management plan and the requirements management plan; the objective is to define how the project will be delivered.
  2. Scope management plan: how scope will be defined, developed, monitored, controlled and validated; it includes four processes: preparing the statement, creating the WBS, establishing and maintaining the baseline, and formal acceptance.
  3. Requirements management plan: how requirements will be analyzed, documented and managed.
  4. The scope management plan contains no scope and the requirements management plan contains no requirements; remember the rule that the "how-only" plans hold no actual content.
  5. If the plan lacks monitoring and control, add those processes and update the scope management plan.
  6. Adaptive projects also plan scope management, with a more iterative and collaborative approach.

Lesson 2

Define Scope: Objective, Inputs, Tools and Techniques

Lesson video

Lesson overview

Once requirements have been collected and prioritized, a project is usually limited by time, budget and other constraints, so you have to decide which of the candidate requirements actually go into the project scope and write them up as a clear description. That is Define Scope. This lesson covers the objective, inputs and outputs of the process and six categories of tools and techniques. It also covers two commonly tested scenarios: what to do when key stakeholders each hold a different view of the scope boundary, and what to do when a project manager from a predictive background runs an agile project for the first time and the scope cannot be fully defined. The previous lesson covered how scope is managed; the next covers the core output of Define Scope, what the scope statement contains.

Objective, inputs and outputs of the process

The objective of Define Scope is to develop a detailed or high-level description of the project, the product and the value expected to be delivered, as well as a quality management plan. The process also identifies the quality requirements and standards for the deliverables, and determines how the project will demonstrate that the quality requirements are met. Its key benefit is that it helps ensure that the stakeholders and the project team understand the value that will be delivered through a product, service or result. In essence, the process selects from the requirements documentation the project requirements that will finally be included and then develops a detailed description of the project and its product.

The main inputs are the project charter (the elements in PMBOK 8 Table 4-1, such as the high-level project description, boundaries and key deliverables, and project approval requirements), the requirements documentation (which identifies the requirements to be included in scope), the assumption log, the project management plan, enterprise environmental factors and organizational process assets. The outputs are the project scope statement, and updates to the requirements documentation (these are the two outputs shown in PMBOK 8 Figure 2-16), because the result of the selection may feed back and change the status of requirements.

Six categories of tools and techniques

The tool categories listed in PMBOK 8 Figure 2-16 are expert judgment, decision-making, data analysis, decomposition, interpersonal and team skills (facilitation), and product analysis. Alternative analysis and multicriteria decision analysis, listed below with their category in parentheses, are common specific techniques within them.

  • Alternative analysis (data analysis): compare different ways of meeting the requirements and choose the most suitable one.
  • Multicriteria decision analysis (decision-making): use a decision matrix to rate alternatives against several criteria and rank them.
  • Facilitation (interpersonal and team skills): the ability to effectively guide a group event to a successful decision, solution or conclusion. In Define Scope it is often used to get key stakeholders to reach a consensus on the deliverables and on the boundaries of the project and the product (this is the application scenario, and also the signal to look for in questions).
  • Product analysis: asking questions about a product or service and forming answers to describe its use, characteristics and other relevant aspects, turning high-level product descriptions into meaningful deliverables. Example techniques are product breakdown, requirements analysis, systems analysis, systems engineering, value analysis and value engineering.
  • Expert judgment and decomposition.

Expert judgment is judgment provided based upon expertise in an application area, discipline, industry and so on, as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education, knowledge, skill, experience or training. When you are unsure which requirements to include or how to describe them, you can ask experts and key stakeholders for input. Common exam practice: if an expert can be on site only briefly, the first step is to meet the expert and explain the specific difficulty the team faces, so that they can pinpoint why the scope is unclear, and then carry out the follow-up work accordingly; do not first have the expert read a large pile of documents.

When working questions, translate these tools and techniques into signals. "The boundary is disputed and consensus is needed" means facilitation. "Several alternatives, several criteria, scoring needed" means multicriteria decision analysis. "Turn a high-level product description into specific deliverables" means product analysis. "Compare ways of implementing" means alternative analysis. "Unsure which requirements to include or how to describe them" means expert judgment. "Divide scope and deliverables into smaller, more manageable parts" means decomposition.

Define Scope is iterative

Define Scope can be carried out more than once. When some part of the requirements cannot be finalized for the time being and no detailed description can be written, there is no need to stop and wait. You can first give a higher-level scope description, elaborate it progressively as you learn more about the project, and update the scope statement and requirements documentation when necessary. PMBOK 8 states the timing this way: the description may be done at the beginning of the project for predictive approaches, or at the beginning of each iteration for adaptive and hybrid approaches.

Define Scope in predictive vs. adaptive approaches

  • Predictive: describe the scope at the beginning of the project and structure the deliverables in the WBS.
  • Adaptive and hybrid: the scope can be described at the beginning of each iteration. Adaptive projects define deliverables progressively through a backlog. In a hybrid project, the iterative part can be elaborated through a backlog and the predictive part structured in a WBS, depending on how the hybrid is set up. Scope is usually kept at a high level, often represented by a product roadmap with its releases.

So a project manager from a predictive background who takes over an agile project should not spend a long time before starting trying to fix the scope firmly, should not first seek the product owner's partial approval as a scope baseline, and should not submit a change request to return to predictive just because they are uncomfortable with progressively clarified scope. The correct approach is to refine and settle the backlog items for the current iteration at the start of each iteration, then deliver the iteration, and let the overall scope become clearer step by step through the backlog.

Example: three departments disagree about "deliverables"

In an e-commerce platform redesign, the heads of sales, customer service and logistics each had a view on "whether the order lookup page should show shipment tracking" and "whether customer service tickets are in this release," and the boundary stayed undecided. The project manager cannot have the team draw the line unilaterally, and should not push the dispute onto a later change. She runs a facilitated workshop. First she has all three sides state their own goals, then goes through the requirements documentation item by item: which items decide business value and which are only "nice to have." In the meeting they agree to include "tracking display" and to list "customer service tickets" in the exclusions. The consensus is reached and recorded on the spot, and then written into the scope statement.

Worked examples

Example 1 Scenario: key stakeholders disagree about the scope boundary

Question 1Example

A project manager is responsible for a complex project, and the team is communicating with stakeholders to reach a consensus on the project scope. Several key stakeholders hold different views on whether certain deliverables are in scope, and the project boundary and acceptance conditions remain unclear. To settle the detailed scope description, what should the project manager do?

Show answer and explanation

Correct answer: B

A complex project is defining scope. Several key stakeholders hold different views on whether certain deliverables are in scope, and the boundary and acceptance conditions cannot be settled. The question asks how to settle the detailed scope description.

One tool for Define Scope is facilitation: bring together key stakeholders with different expectations and expertise and, in a workshop, reconcile their differences so that they form a cross-functional consensus on the deliverables and on the boundaries of the project and product. The obstacle in the stem is exactly a disagreement over the boundary with no consensus. The answer is B.

Why the other options are wrong

  • A. The scope has not been settled yet. Leaving the dispute to later change management avoids what needs doing now, and a change management plan cannot substitute for consensus on scope.
  • C. The project is already in Define Scope. The problem is disagreement over where to draw the boundary, not requirements that were never elicited, so eliciting again does not resolve the disagreement.
  • D. If the team settles scope unilaterally and then informs stakeholders, it will not win the consensus of key stakeholders, and the result is easily overturned later, causing disputes.

Key takeaway When stakeholders disagree on the scope boundary, use facilitation to reach consensus; it is a tool of Define Scope.

Variation If the stem were changed to “choose among several technical options by scoring them on cost, risk and duration,” the answer would be multicriteria decision analysis; “turning a high-level product description into specific deliverables” would be product analysis.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: a predictive manager runs an agile project for the first time

Question 2Example

An experienced predictive project manager is running an agile project for the first time. Because uncertainty is high, he finds it hard to define the project scope completely in advance and has already spent a long time on it. What should the project manager do?

Show answer and explanation

Correct answer: D

An adaptive (agile) project, and a manager from a predictive background applying his habit of defining the scope completely in advance, having already spent a long time on it. The question asks what to do.

An adaptive project describes scope at the beginning of each iteration. Deliverables become clearer step by step through a backlog, and the scope is usually kept at a high level, often represented by a product roadmap with its releases. So a project with high uncertainty should not fix its scope at the outset; it should start delivering iterations and let the scope become clear and be adjusted step by step through the backlog. The answer is D.

Why the other options are wrong

  • A. Switching to a predictive approach goes against the project's high uncertainty, and it cannot be solved by a single change request.
  • B. Meeting every day to fix the scope wastes time and runs against iterative elaboration in adaptive projects; the scope may change again the next day.
  • C. An adaptive project does not require a fixed, complete scope baseline approved before work starts: the baseline is set at the start of each iteration according to the prioritized requirements, and changes are dynamically approved by the product owner rather than through formal change control.

Key takeaway In an adaptive project the scope becomes clear step by step through the backlog; it does not need to be settled in one go before work starts.

Variation For the same problem in a predictive project, the scope should be defined completely at the start of the project and the deliverables organized through a WBS; once the baseline is formed, changes go only through change control.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Define Scope selects from the requirements documentation. It does not accept every requirement as listed; there are usually more candidate requirements than the requirements finally included in scope.
  • When the boundary is disputed, use facilitation to reach consensus. Do not first draw up a change management plan and leave the dispute for later, and do not let the team decide alone.
  • Do not confuse facilitation (consensus needed), brainstorming (ideas needed) and multicriteria decision analysis (scoring several alternatives).
  • An adaptive project does not require the scope to be fully settled before work starts, nor the product owner's partial approval before work starts to turn the scope into a baseline.
  • Besides the scope statement, the outputs of Define Scope include updates to the requirements documentation. Identifying quality requirements and standards, and determining how compliance will be shown, are part of the process objective, but the outputs in Figure 2-16 list only the scope statement and the requirements documentation.

Key takeaways

  1. Define Scope: select from the requirements documentation the requirements that will finally be built, write a detailed description of the project and product, and develop a quality management plan.
  2. Inputs: the charter, requirements documentation, assumption log, project management plan and so on; outputs: the scope statement and updated requirements documentation.
  3. Tools and techniques: expert judgment, decision-making, data analysis, decomposition, facilitation and product analysis (alternative analysis and multicriteria decision analysis are common specific techniques).
  4. When the boundary is disputed and consensus is needed, use facilitation; when an expert is on site only briefly, first have the expert understand the difficulty.
  5. Define Scope can be repeated: what cannot yet be written in detail is written at a high level first, then elaborated.
  6. Predictive projects can usually do it at the start of the project; adaptive and hybrid projects can do it at the start of each iteration, with scope becoming clearer step by step through the backlog.

Lesson 3

The Project Scope Statement: Four Components, Acceptance Criteria and Exclusions

Lesson video

Lesson overview

The scope statement is one of the most-asked-about documents in the scope topic. Where are the acceptance criteria? Where is "what we are not doing" written? What do you rely on when the customer says "this should have been included"? These are common exam points. This lesson covers what the statement is, its four main components, and the two places you must remember: acceptance criteria and exclusions. The previous lesson covered the Define Scope process; the next covers how the statement relates to the charter and the requirements documentation.

What the statement is

The project scope statement is the description of the project scope, major deliverables, assumptions and constraints. It documents the entire scope, including the project and product scope. It describes the project's deliverables in detail and provides a common understanding of the project scope among project stakeholders. It has three uses: it enables the project team to perform more detailed planning; it guides the project team's work during execution; and it provides the baseline for evaluating whether requests for changes or additional work are contained within or outside the project's boundaries.

The last use is the one most often needed on the exam. When there is a dispute about whether a demand is within scope, open the statement first. Do not raise a change first, and do not revise the plan first.

The four components of the detailed statement

ComponentDescription
Project scope descriptionProgressively elaborates the characteristics of the product, service or result described in the project charter and requirements documentation
DeliverablesAny unique and verifiable product, result or capability to perform a service that is required to be produced to complete a process, phase or project; includes ancillary results such as project management reports and documentation; may be described at a summary level or in great detail
Acceptance criteriaA set of conditions that are met before deliverables are accepted
Project exclusionsIdentify what is excluded from the project. Explicitly stating what is out of scope for the project helps manage stakeholders' expectations and can reduce scope creep

The more precisely the statement defines the work to be performed and the work that is excluded, the better the project management team can control the overall scope. The statement also records assumptions and constraints, which are the preconditions for the scope description and are used repeatedly in later schedule, cost and risk work.

Two places you must remember

The acceptance criteria are written in the scope statement. If a question asks "the project team wants to know what standard each deliverable must meet when it is handed to the customer," the answer is the scope statement. The project scope statement contains, or refers to, the acceptance criteria for the deliverables; detailed acceptance criteria for a particular WBS component or work package may also be recorded in the WBS dictionary. In a predictive project, the scope statement, the WBS and the WBS dictionary together form the scope baseline (in an adaptive project the baseline is defined at the beginning of each iteration based on the value expected from the delivery and aligned with the prioritized requirements), so judge by the level the question asks about. When a question asks only "what standard must the deliverable meet," choose the scope statement first. The project charter gives only measurable project objectives and success criteria, a high-level project description and key deliverables, and contains no specific acceptance criteria. The scope management plan sets the acceptance procedure and contains no specific criteria. The WBS itself is only a hierarchical decomposition and contains no acceptance criteria.

Exclusions are also written in the scope statement. When a question asks "how do we make clear what is not in the project and reduce scope creep," the answer is exclusions. Suppose a dispute arises at acceptance: the customer says some requirements were not implemented, and the project manager believes those requirements were never in scope. The first thing to do is review the exclusions in the statement together with the stakeholders, then decide whether it is a new request, and start change control only if needed.

Beyond the statement: the quality management plan

The objective of Define Scope also includes producing a quality management plan (the outputs listed in PMBOK 8 Figure 2-16 are only the project scope statement and the requirements documentation). It is a component of the project management plan that describes how an organization's policies, procedures and guidelines will be implemented to achieve the quality objectives, and the activities and resources necessary for the project management team to achieve them. The acceptance criteria in the statement tell you "what must be met," and the quality management plan tells you "how to show it is met." When a question asks whether a disputed item "belongs to the scope," do not turn to the quality management plan; it has nothing to do with the scope boundary.

Example: the skeleton of a scope statement (campus parcel locker project)

Project scope description: install 12 sets of smart parcel lockers at each of three campuses, with a pickup app and an administration web page. Deliverables: lockers and installation, pickup app, administration web page, operating manual, administrator training. Acceptance criteria: the locker doors open and close 5,000 times without failure; unlocking by scanning in the app takes no more than 3 steps; response time for unlocking at peak hours is no more than 2 seconds. Exclusions: no integration with courier company systems; no courier-side app; no off-campus collection points. Later a courier company asked to connect to its system. The project manager checked the exclusions and determined it was out of scope. If the sponsor still wants it, first assess the impact on scope, schedule, cost, resources and risk, then submit a change request under the change management plan for a decision by the authorized person.

Worked examples

Example 1 Scenario: a dispute about whether something is in scope at acceptance

Question 1Example

The first deliverable of the project is complete, and the project manager invites the stakeholders to accept it. One of them says some requirements were not implemented and refuses to accept, but the project manager believes those requirements were never within the project scope. What should the project manager do FIRST?

Show answer and explanation

Correct answer: A

At acceptance of the first deliverable, a stakeholder says some requirements were not implemented and refuses to accept, while the project manager believes they were never in scope. The question asks what the project manager should do “first.”

The point of dispute is whether these requirements belong to the scope, so the facts must be established first. The project exclusions in the scope statement explicitly identify what is excluded from the project scope, and the statement is also the baseline for evaluating whether additional work falls within the project's boundaries. Reviewing it together with the stakeholder shows whether the disputed requirements are in scope, and then the follow-up can be decided. The answer is A.

Why the other options are wrong

  • B. Accepting the demand and implementing it before checking whether these requirements belong to the scope may mean doing work outside the scope, which is scope creep.
  • C. Change control comes after it has been confirmed that these requirements are really outside the scope and the stakeholder still insists on adding them. Starting it now is premature.
  • D. The quality management plan explains quality requirements and how to show they are met. It has nothing to do with the dispute over whether something is in scope.

Key takeaway When it is disputed whether scope includes a requirement, look at the scope statement first (especially the exclusions), and only then talk about change.

Variation If the review shows that the requirements really are in scope and approved, the answer becomes building them as defect repair or corrective action through the applicable change process, re-verifying, and then submitting for acceptance; only if they are in the exclusions and the customer insists on having them do you submit a change request.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: which document holds the acceptance criteria

Question 2Example

The project management plan of an industrial software project has been approved and the team is developing. The test lead finds that he does not know what acceptance criteria each deliverable must meet when it is handed to the customer in order to count as acceptable, and goes to the project manager. Which document should the project manager tell him to look at?

Show answer and explanation

Correct answer: D

During execution, the test lead does not know what acceptance criteria each deliverable must meet when delivered to the customer. The question asks which document he should look at.

Acceptance criteria are a set of conditions that are met before deliverables are accepted. They are written in the project scope statement as one of its four main components (project scope description, deliverables, acceptance criteria, exclusions). Each document has its own job: the charter gives high-level direction, the scope management plan sets the procedure, the WBS decomposes the work, and only the scope statement records “the conditions the deliverables must meet.” Because the acceptance criteria are recorded in the scope statement, he should look at the scope statement. The answer is D.

Why the other options are wrong

  • A. The project charter holds high-level project information and success criteria, not the acceptance criteria of each deliverable.
  • B. The WBS is a hierarchical decomposition of work and deliverables and does not itself contain acceptance criteria; the primary source for acceptance criteria is the project scope statement, and the WBS dictionary can add detail for each work package.
  • C. The scope management plan sets out how deliverables will be formally accepted, that is, the procedure; it does not contain specific acceptance criteria.

Key takeaway The primary source for acceptance criteria is the project scope statement.

Variation If what he is looking for is the detailed acceptance criteria and responsible party of a particular work package, the answer can be the WBS dictionary.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Exclusions are written in the scope statement, not in the project charter or the scope management plan.
  • Acceptance criteria: the scope statement contains or refers to them; detailed criteria for a specific WBS component may also be in the WBS dictionary; when a question asks only for deliverable criteria, the scope statement is usually the answer.
  • In a scope dispute, check the statement first (especially the exclusions) to confirm whether the item is in scope, and only then talk about change. Do not build it straight away, and do not raise a change straight away.
  • The quality management plan covers quality requirements and how to show they are met; it has nothing to do with disputes about whether something is in scope.
  • Deliverables are not only the product itself; they also include ancillary results such as project management reports and documentation.

Key takeaways

  1. The scope statement describes the project scope, major deliverables, assumptions and constraints, and covers both project scope and product scope.
  2. The detailed statement has four components: project scope description, deliverables, acceptance criteria and project exclusions.
  3. Acceptance criteria are in the scope statement; exclusions are in the scope statement and are used to manage expectations and reduce scope creep.
  4. The statement is the basis for judging whether a change request or additional work is within the project's boundaries.
  5. The quality management plan is also an objective of Define Scope; it describes how to show that quality requirements are met.
  6. Scope dispute: review the scope statement first, then decide whether to go through change control.

Lesson 4

Charter, Requirements Documentation and Scope Statement: Progressive Elaboration

Lesson video

Lesson overview

The project charter, the requirements documentation and the scope statement have similar names and all describe "what the project wants," so beginners confuse them easily. This lesson lines them up in a chain from coarse to fine: the charter gives direction, the requirements documentation lists wishes, and the scope statement makes decisions. It then covers how the statement relates to the scope baseline, and the working principle "if the statement is not approved, clarify before executing." This lesson closes the scope statement chapter; the next chapter covers how to decompose the scope in the statement into a WBS.

Three documents, from coarse to fine

The three documents become progressively more detailed. The project charter gives a high-level project description, the boundaries and the key deliverables, and authorizes the project manager to apply organizational resources. The requirements documentation expands these into individual requirements, and captures all the requirements that were raised. The scope statement then selects from the requirements documentation the part that will actually be done, lands it in specific deliverables and acceptance criteria, and also states what will not be done.

Progressive elaboration from the project charter to the scope statement

The requirements documentation and the statement are linked in both directions: the statement selects requirements when scope is defined, and the result of the selection may trigger updates to the requirements documentation. A handy analogy is ordering lunch. The list of wishes has pizza, sushi and burritos, but with limited resources you can pick only one. The one chosen, say burritos, is what is in scope, and the other candidates are not in scope; those that need to be protected against misunderstanding can be written explicitly into the exclusions. So there are usually more candidate requirements collected than requirements included in the final scope. The final scope consists of the requirements that were analyzed, determined and approved, together with the corresponding project work.

Notice in the figure that "voice booking support" in the requirements documentation did not make it into the deliverables; it was written into the exclusions. A requirement is not the same as scope: the requirements documentation is "what was collected," and the scope statement is "what was decided." Putting every requirement into scope without analysis, or setting the scope by listening only to key stakeholders, can leave scope unfocused, requirements missed and work redone, and later invites scope creep. In a predictive project the correct order is usually this: first elicit and analyze requirements, define scope to settle the scope, obtain appropriate approval under the governance arrangements and build consensus among stakeholders, and then create the WBS on that basis. In an adaptive project, requirements and scope are collected, prioritized and elaborated continuously over the iterations.

The statement and the scope baseline

In a predictive environment, the approved scope statement, WBS and WBS dictionary together make up the scope baseline. The description, deliverables, acceptance criteria and exclusions in the scope statement are part of the scope baseline. Once approved, the scope baseline in a predictive environment can be changed only through formal change control. In an adaptive environment, the baseline is usually represented by the prioritized requirements or the iteration backlog, and a product owner dynamically approves changes under the established governance. The scope baseline is also the basis for comparison to actual results. A way to remember it: the statement says "what to do and what not to do," the WBS says "what work it breaks down into," and the WBS dictionary says "the details of each piece of work"; together they form the scope baseline.

Working principle: if the statement is not approved, clarify before executing

The scope statement defines the project's boundaries, deliverables and acceptance criteria. It is the basis for creating the WBS and is part of the scope baseline. Suppose the project charter has been issued, the scope statement has not been approved, and management is pressing you to start work. The project manager should explain to management the risks of starting when the scope boundary and the course of action are not yet enough to support reliable execution. (Whether specific work may start also depends on the project governance and the project management plan; PMBOK 8 says that execution can begin when the team has enough understanding of and confidence in the course of action.) The main risks are that the work may drift from the objectives, producing wasted effort, and that there will be no basis for acceptance afterward. The charter contains only high-level information and cannot replace the statement. Do not walk away because of the pressure, and do not start work and "fill in the scope as you go."

If you take over a project already under execution and want to understand its high-level boundaries and major deliverables, check the project charter first; if you want to know what must be achieved and what will not be done, check the scope statement. This is another application of "the charter governs direction, the statement governs boundaries."

Example: the customer asks for another feature in a project already under execution

A predictive project is already in its implementation phase and its scope baseline has been approved. The customer asks for another feature. After checking, the project manager confirms it is consistent with the project objectives. That is only one condition of the assessment. The combined impact on scope, schedule, cost, resources and risk must still be analyzed first, and then a change request submitted under the change management plan; the feature can be added to scope only after approval; until approval, the team continues to execute the current plan. After approval, the affected documents are updated according to the configuration management arrangements: the scope statement records the boundary and acceptance criteria of the new requirement; the WBS, the WBS dictionary, the requirements documentation and the requirements traceability matrix are updated in step; and, according to the results of the impact analysis, the corresponding schedule and cost plans or baselines are updated where necessary. Exam questions of this kind usually ask "which document is updated to record the addition to scope," and the answer is the scope statement. The scope management plan contains no scope, and the project management plan is too general; neither is the answer to this kind of question.

Worked examples

Example 1 Scenario: how to collect requirements and settle the scope

Question 1Example

A project manager is assigned to manage a warehouse process optimization project. Before preparing the project management plan, the project manager consults organizational process assets and finds that similar past projects suffered scope creep because stakeholder needs were not handled properly. How should the project manager collect and determine the requirements?

Show answer and explanation

Correct answer: D

In the planning phase of a predictive project, similar past projects suffered scope creep because stakeholder needs were not handled properly. The question asks how to collect and determine the requirements.

The requirements documentation captures all the requirements that were raised. The scope is selected from them through Define Scope, and after appropriate approval under the governance arrangements it forms the scope statement, from which the WBS is then created; the requirements documentation itself is not a component of the scope baseline. A requirement is not the same as scope, and defining it this way in advance is what prevents scope creep. So the correct approach is to collect all requirements in planning, select the scope and obtain appropriate approval, and then create the WBS. The answer is D.

Why the other options are wrong

  • A. Interviewing only the key stakeholders and setting their requirements directly as the scope misses the needs of everyone else and may take impractical demands straight into scope.
  • B. After the scope is set, new requirements are not all refused; they must be assessed through change control. Refusing everything is unrealistic and does not follow change management.
  • C. The first half is wrong: a requirement is not the same as scope, and all the requirements cannot go straight into scope. The second half, assessment and change, is how extra requirements are handled after the baseline is set; it cannot replace the trade-offs made in planning.

Key takeaway Requirements are collected, scope is selected; after approval, decompose it into the WBS.

Variation If the stem were set after the scope baseline was established and the customer raised a new requirement, you would no longer collect again; you would assess it and go through change control, then update the scope statement and other baseline documents after approval.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: the scope statement is not approved and management pushes to start

Question 2Example

A renewable energy company treats a project as a top priority and requires it to be completed within ten months. The project charter has been issued but the scope statement has not yet been approved, and senior management urges the project manager not to wait and to start work immediately. What should the project manager do NEXT?

Show answer and explanation

Correct answer: B

The charter has been issued, the scope statement has not been approved, and senior management urges the project manager to start immediately. The question asks what the project manager should do next.

The scope statement defines the project's scope boundary, deliverables and acceptance criteria, is the basis for creating the WBS and is part of the scope baseline. Starting without approval risks the work drifting from the objectives, producing wasted effort, and leaving no basis for acceptance afterward. Under adaptive or hybrid approaches, or with authorized rolling wave planning, work that is already clear can start first; this stem gives no such authorization, so the project manager should explain to senior management the risks of starting without approval and try to get approval done first. The answer is B.

Why the other options are wrong

  • A. The project manager can speak to management directly anyway. Merely reporting and logging it, without explaining to the executives pushing for a start what starting without approval would lead to, and without pushing for approval of the scope statement, leaves the pressure and the risk in place.
  • C. The project charter contains only high-level information. After it is issued, detailed planning should continue, and starting right away skips defining scope.
  • D. Quitting the project at the first pressure is not acceptable. The project manager should explain the risks to management and push to resolve the problem.

Key takeaway Without an approved scope statement, and without authorization to start the work already clear, do not rush into work; explain the risks to management first.

Variation If the scope statement were approved and only the schedule were incomplete, work that is already clear could proceed according to the scope baseline while the schedule is completed as soon as possible.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The requirements documentation holds all collected requirements, and the scope statement holds the ones selected to be done; do not put every requirement straight into scope.
  • The scope statement, the WBS and the WBS dictionary together make up the scope baseline; the statement is only one of the three.
  • The charter gives only high-level boundaries and is not the detailed scope. Issuing the charter only means the project is authorized; whether conditions for reliable execution are in place depends on the governance arrangements and on whether the team has enough understanding of and confidence in the course of action.
  • Once the scope baseline is set, new requirements can still come in, but they must be handled under the applicable change governance (formal change control in a predictive project). You cannot reject them all, and you cannot quietly accept them.
  • When the statement is not approved, the project manager's correct move is to explain the risks to management; not to report it upward and leave it there, not to just comply, and not to walk away.

Key takeaways

  1. The charter, the requirements documentation and the scope statement are progressive elaborations: high-level, all requirements, selected scope.
  2. There are usually more candidate requirements collected than are finally included in scope; requirements are collected and scope is selected from them, so you cannot compare the two counts directly.
  3. The statement and the requirements documentation are linked in both directions: Define Scope may trigger an update to the requirements documentation.
  4. In a predictive project, the scope statement, WBS and WBS dictionary together make up the scope baseline.
  5. First collect the requirements, settle the scope and obtain appropriate approval and consensus under the governance arrangements, and only then create the WBS.
  6. Common exam practice: when the statement is not approved and the scope boundary is unclear, do not start work rashly; explain the risks to management first.

This chapter has 40 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.