Requirements Traceability Matrix

PMP · Scope · 2 lessons · about 25 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

The requirements documentation answers "what is wanted"; the requirements traceability matrix answers "where did each requirement come from, which deliverable does it land in, and has it been tested?" It is used together with the requirements documentation. PMBOK 8 defines it among the inputs and outputs in Section 4 without naming a single process that produces it, and common exam practice places it with the Elicit and Analyze Requirements line of work. The matrix links each requirement item by item to the business objectives, the project objectives, the WBS deliverables, the product design, product development, and the test strategy and test scenarios. That prevents requirements from being overlooked, and it also keeps extra requirements with no origin from slipping into the project.

The chapter has two lessons. Lesson 1 covers what the matrix is, its four purposes, the columns in the grid and the attributes recorded for each requirement. Lesson 2 covers the requirements management plan, which sets the structure of the matrix, and how the matrix is used in two situations: change and acceptance. The exam questions here are very focused: plain concept questions (the purposes of the matrix, which plan defines what), and scenario questions in which the customer says at acceptance that a requirement was not delivered. The answer to the latter is almost always "check the requirements traceability matrix."

Lessons in this chapter

How to study this chapter

First memorize the four purposes of the matrix (it links each requirement to the business and project objectives so that it adds business value; it provides a means to track requirements throughout the project life cycle; it helps ensure that approved requirements are delivered; and it provides a structure for managing changes to the product scope). These are a favorite for concept questions. Then memorize the direction of the chain: backward to the business objectives and project objectives, forward to the WBS deliverables, product design, product development, and test strategy and test scenarios. For scenario questions, first decide whether the stem is asking "how do we manage requirements" (look to the requirements management plan) or "has it been delivered" (check the requirements traceability matrix). When a customer says at acceptance that a requirement was not implemented, always verify before acting: check the matrix and confirm whether the requirement was approved, whether it was assigned to a deliverable, and whether it was tested. If it was approved but not met, assess the impact and handle the defect repair or corrective action through change control; if it was never approved, treat it as a new change request. The chapter is short, but it overlaps with three others (eliciting requirements, the scope statement, and validating scope). After finishing it, go back to those chapters and the whole line will be easier to connect.

Chapter map

Requirements management plan (defines the structure)

  • Requirements traceability matrix
    • Backward: business objectives · project objectives
    • Forward: WBS deliverables · product design · product development · test strategy and test scenarios
    • Attributes: source · priority · version · status …
    • Uses: tracking throughout the life cycle · change impact analysis · acceptance gap check (every approved requirement must be delivered)

Lesson 1

Requirements Traceability Matrix: Definition, Purposes, Columns and Attributes

Lesson video

Lesson overview

The requirements documentation answers "what is wanted." But as a project runs longer, questions pile up. Why are we building this requirement? Which deliverable does it land in? Has anyone tested it? If nobody can answer, one of two things happens: requirements get overlooked, or "extra requirements" with no origin slip in quietly. The requirements traceability matrix is designed to solve exactly this problem. This lesson covers what it is, its four purposes, the columns in the grid, and the attributes recorded for each requirement. The next lesson covers how it is used for change and acceptance, and the requirements management plan that defines its structure.

Definition and four purposes

The requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them. It is a requirements management tool used together with the requirements documentation (common exam practice places it with the Elicit and Analyze Requirements line of work). The requirements documentation describes what the requirements are and how they meet the business need; the matrix connects each requirement backward (tracing back) to its origin and objectives, and forward (tracing forward) to delivery and testing.

It has four purposes. Linking each requirement to the business and project objectives helps ensure that each requirement adds business value. It provides a means to track requirements throughout the project life cycle. It helps ensure that requirements approved in the requirements documentation are delivered at the end of the project. And it provides a structure for managing changes to the product scope. These four statements stay close to PMBOK's own wording, so exam stems often echo them: when a stem says "ensure that every requirement is linked to a business objective" or "ensure that every approved requirement is eventually delivered," the answer is the requirements traceability matrix.

First, be clear about what each of the three documents does. The requirements documentation lists the requirements and describes how they meet the business need. The scope statement describes the scope to be delivered and the acceptance criteria. The requirements traceability matrix connects each requirement to its origin, its objectives, the project scope and WBS deliverables, and the design, development and test information, so that it can be traced. Your company may call it something else, such as a requirements tracking table or requirements traceability table; in essence it is the same kind of tool.

What the columns contain

The PMBOK 8 example expands each requirement in two directions: backward to the business objectives and project objectives, and forward to the project scope and WBS deliverables, product design, product development, and test strategy and test scenarios.

The matrix links requirements to objectives and to delivery
ColumnDescription
ID and associated IDA unique number for each requirement; the associated ID expresses how a high-level requirement relates to more detailed requirements
Requirements descriptionA written description of the requirement
Business needs, opportunities, goals and objectivesWhich business objective this requirement serves
Project objectivesThe project objective it corresponds to
WBS deliverablesWhich WBS deliverable satisfies it
Product design, product developmentWhere it is implemented in design and development
Test strategy and test scenariosThe tests used to prove the requirement is met (the column header in Figure 4-3 reads "Test Cases" and refers to the same column; a project can refine it into specific test cases such as TC-01)

How do you read this grid? Read across a row, left to right, and you get the full chain of why the requirement exists, where it is implemented and how it will be proven. Read down a column, and you see which requirements support a given objective or deliverable. Both directions are useful: the first is used for acceptance and for the impact analysis when one requirement changes, and the second shows which requirements are affected when an objective or deliverable changes.

Which attributes to record for each requirement

Besides the columns, you can record attributes for each requirement to make the key information clear. Typical attributes are: a unique identifier, a textual description, the rationale for inclusion, the owner, the source, the priority, the version, the current status (for example active, canceled, deferred, added, approved, assigned and completed) and the status date. To help ensure that the requirement has met stakeholder satisfaction, you can add stability, complexity and acceptance criteria.

Two of the attributes are asked about often. One is the source: who raised this requirement, so it can be traced if there is a dispute. The other is the status, which answers "what stage is it in now": just raised, added to the baseline, developed, or accepted. The status column makes the matrix the project's "requirements progress sheet."

Example: an excerpt from the matrix of a campus parcel locker project

IDRequirement descriptionBusiness objectiveWBS deliverableProduct designTest scenariosStatus
001Students can open a locker by scanning a codeShorten pickup time1.2 Locker-opening moduleLocker-opening flow designTC-01 scan succeeds, TC-02 expired-code messageApproved
002SMS reminder with pickup codeReduce overdue rate1.3 SMS serviceSMS templateTC-05 reminder sent on timeApproved
003Support facial-recognition pickup(no matching objective)(not assigned)——Deferred

The third row has neither a business objective nor a deliverable, and this is exactly the problem the matrix is meant to expose: it either lacks a basis in value or has not yet been brought into scope, and it should not be built without approval.

Worked examples

Example 1 Scenario: making every requirement tie to an objective

Question 1Example

A project manager takes over a large logistics park information system project with more than 100 team members. Progress is difficult and the expected benefits are hard to realize. The project manager wants every requirement to be tied to the business objectives and project objectives. What should the project manager do?

Show answer and explanation

Correct answer: D

The project is large with many people, progress is difficult and the expected benefits are hard to realize. The question asks for a management tool that lets “every requirement connect to an objective.”

One purpose of the requirements traceability matrix is to link each requirement to the business objectives or project objectives, which helps confirm that each requirement has business value. Using it, you can check item by item whether each requirement has a corresponding objective; requirements with no objective are exposed, and either a justification is added or the requirement is not built. It also tracks requirements throughout the life cycle. The answer is D.

Why the other options are wrong

  • A. Reviewing all the requirements every week is costly on a project of more than a hundred people, and a review by itself does not systematically create and maintain item-by-item links between requirements and objectives.
  • B. Reviewing the project management plan thoroughly helps in understanding the overall arrangement, but the plan does not record the relationship between each requirement and its objective one by one.
  • C. The project charter contains only high-level requirements. Writing every requirement into it is neither appropriate nor a way to build item-by-item links to objectives.

Key takeaway When you see “ensure that every requirement is linked to the business objectives,” choose the requirements traceability matrix.

Variation If the stem were changed to “ensure that every approved requirement in the requirements documentation is delivered by the end of the project,” the answer would still be the requirements traceability matrix; that is another of its purposes.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: what must be handed to the outsourced testers

Question 2Example

PMLyceum outsources the functional verification of a benefits lookup app to a third-party testing firm. Before the firm starts testing, which TWO documents would BEST help it determine the test arrangements and ensure requirements coverage?

Show answer and explanation

Correct answer: D

Functional verification is outsourced to a third-party testing firm. The question asks which two documents, before testing starts, would best help the firm determine the test arrangements and ensure requirements coverage.

Outsourced testing needs two things. The test plan explains the method, scope and arrangements for testing. The “test strategy and test scenarios” column of the requirements traceability matrix maps each requirement to the corresponding test cases or test scenarios, and with it the testing firm can make sure every requirement is verified and none is missed. Without the plan, it is harder for the firm to determine how to test; without the matrix, it is harder to check requirements coverage systematically. Both should be available before testing starts, so the answer is D.

Why the other options are wrong

  • A. The risk register records project risks. It does not specify which requirements the tests must cover, and it helps a service provider little in carrying out functional verification.
  • B. Defect reports are usually produced after tests are executed, so they cannot replace the test plan and the requirements traceability matrix for planning this round of testing and checking requirements coverage. Who writes the test scripts depends on the contract and the division of responsibilities; they are not the documents that best help determine the test arrangements and requirements coverage here.
  • C. The requirements traceability matrix is needed before the start, but defect reports are usually produced only after testing finds problems, so they cannot be used to schedule this round of testing or to check requirements coverage.

Key takeaway The “test strategy and test scenarios” column of the matrix links requirements to test cases or test scenarios; before outsourced testing begins, it can be provided to the service provider to help check requirements coverage.

Variation If the stem asked “after testing finds problems, what should the provider submit to the project manager,” the answer would become the defect report.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The requirements traceability matrix is not the requirements documentation: the documentation lists requirements, and the matrix links them.
  • The matrix is not the scope statement: the scope statement covers scope and acceptance criteria, and the matrix shows where each requirement lands and whether it has been tested.
  • The matrix's "test strategy and test scenarios" column links requirements to testing. A defect report exists only after tests are run; it is not a document produced when eliciting requirements.
  • The change log only records changes. To check whether each requirement has been delivered, look at the matrix.
  • The project charter provides a high-level project description, boundaries, major deliverables, project objectives and similar information. It does not link each requirement to an objective one by one, so it cannot replace the matrix.

Key takeaways

  1. The requirements traceability matrix is a grid that links each requirement to its origin, its objectives and the deliverable that satisfies it.
  2. Four purposes: each requirement adds business value; requirements can be tracked throughout the life cycle; every approved requirement is delivered; it provides a structure for product scope changes.
  3. Columns: ID, requirements description, business objectives, project objectives, WBS deliverables, design, development, test strategy and test scenarios.
  4. Attributes: source, rationale, owner, priority, version, status and status date; stability, complexity and acceptance criteria can be added.
  5. When you see "link every requirement to an objective" or "prevent omissions," choose the requirements traceability matrix.

Lesson 2

Requirements Management Plan, and Using the Matrix for Change and Acceptance

Lesson video

Lesson overview

The previous lesson showed what the matrix looks like. This lesson covers two things. First, which columns the matrix has and which attributes it records are defined in the requirements management plan. Second, the matrix is used throughout the project life cycle: for aligning objectives, analyzing the impact of changes, tracking development and checking at acceptance. The two situations tested most are change and acceptance. The question pattern is very consistent: before or after acceptance, the customer says a requirement was not delivered and asks what the project manager should do; or a question asks which plan defines how requirements are managed. Memorize two sentences first: to see how requirements are managed, look at the requirements management plan; to see whether a requirement has been delivered, check the requirements traceability matrix.

The requirements management plan: how requirements are managed

The requirements management plan (some organizations call it a business analysis plan) describes how project and product requirements will be analyzed, documented and managed. It is created when you plan scope management; it is a component of the project management plan and, together with the scope management plan, an output of Plan Scope Management. Its components may include:

  • How requirements activities will be planned, tracked and reported;
  • Configuration management activities: how changes will be initiated, how impacts will be analyzed, how changes will be traced, tracked and reported, and the authorization levels required to approve changes;
  • The requirements prioritization process;
  • The metrics that will be used and the rationale for using them;
  • The traceability structure that reflects the requirement attributes captured in the requirements traceability matrix, that is, the design of the columns of the matrix in the previous lesson.

How it differs from the scope management plan is a frequent exam point. The scope management plan documents how the project and product scope will be defined, developed, monitored, controlled, and validated; the requirements management plan describes how requirements will be analyzed, documented and managed. Both cover only "how." The scope management plan contains no actual scope, and the requirements management plan contains no actual requirements. The actual requirements are in the requirements documentation, and the actual scope is in the scope baseline. The requirements management plan is also not the configuration management plan (which governs versions of products and documents) or the change management plan (which governs how changes are handled), even though its content includes configuration management activities.

When a change is requested: impact analysis along the matrix

When someone asks to change a requirement, the project manager first needs to know how far the change reaches. Tracing backward along that row shows which business objective the requirement serves, and whether changing it would damage that objective. Tracing forward shows which WBS deliverable, which design, which development work and which tests it lands in, and therefore what else has to change with it. That is what "provides a structure for managing changes to the product scope" means: impact analysis is not done from memory but by consulting the grid. After the analysis, a change request in a predictive project still goes through change control; an adaptive project does the impact analysis and then adjusts and reprioritizes the backlog under the governance rules. After a change is approved, update the requirements documentation, the requirements traceability matrix and related plans according to the impact; if approved scope is affected, update the scope baseline as well.

At acceptance: check item by item and close the gaps

Every approved requirement in the matrix has a corresponding deliverable and test arrangement, so at acceptance each one can be checked off, which avoids the customer discovering on site that a requirement was not met. Check three things: whether every approved requirement has a corresponding WBS deliverable; whether there is a test strategy and test scenarios (or other verification evidence) showing it was satisfied; and whether the status is "completed." Fix whatever is missing:

  • No linked deliverable: first check the scope baseline and the WBS. If the matrix entry was simply left blank, complete the traceability. If the approved requirement really was never brought into the baseline, go through change control to add it to scope and plans; do not quietly build it.
  • Empty "test strategy and test scenarios" column: first check verification records such as the test plan and test results. If the entry was only left blank, complete the traceability. If there really is no verification arrangement or evidence, add the applicable tests, inspections, certifications or other verification activities in line with the acceptance criteria, then submit for acceptance.
  • Requirement never entered in the matrix: add it immediately, then check the scope baseline, WBS, test plan and verification records. Complete the trace links where corresponding items exist; where they do not, assess the impact and address the gaps through change control and the quality plan before updating the matrix.

When the customer arrives for acceptance and says a requirement was not done, do not rush to agree to build it, and do not rush to deny it either. The correct order is: first check the matrix to see whether the requirement was approved, whether it was assigned to a deliverable and whether it was tested. If it was in fact approved but missed, assess the impact and process the needed defect repair or corrective action through change control; once it is approved, implement it, reverify the deliverable and re-run acceptance. If it is not in the approved scope, it is a new request and goes through change control.

Example: a matrix check before acceptance

The campus parcel locker project has 40 approved requirements. Before acceptance, a check of the matrix finds that 3 have an empty "WBS deliverables" column and 2 have an empty "test strategy and test scenarios" column. For the 3 with no deliverable, first check the scope baseline and the WBS. If the entries were simply left blank, complete the traceability. If it is confirmed that these 3 approved requirements were never brought into the baseline, the project manager submits a change request, and once it is approved adds them to scope, schedule and cost, and then arranges development. For the 2 with an empty test column, the deliverables exist, so first check the test plan and test results: if the entries were only left blank, fill them in; if there really are no verification records, add the applicable tests or inspections in line with the acceptance criteria and submit for acceptance after they pass. Solve both kinds of problem before the acceptance meeting, and the customer will have no surprises when they arrive.

Predictive vs. adaptive

A predictive project builds the matrix during planning, and once the requirements form a baseline they are changed only through formal change control. An adaptive project collects requirements as user stories, places them in the backlog by priority, usually attaches acceptance criteria to the user stories and elaborates them progressively over the iterations; tracing relies more on the backlog and the definition of done.

Worked examples

Example 1 Concept: which plan defines how requirements are managed

Question 1Example

A project manager takes over a member management system project that is already in the execution phase and finds that the customer has never provided accurate product requirements. According to which of the following plans should the project manager analyze, document and manage the requirements?

Show answer and explanation

Correct answer: A

The project is already in execution and the customer has never provided accurate product requirements. The question asks which plan sets out the rules for how requirements are analyzed, documented and managed.

The requirements management plan describes how project and product requirements will be analyzed, documented and managed. Its content includes how requirements activities will be planned, tracked and reported, configuration management activities, the requirements prioritization process, metrics, and the traceability structure that reflects the requirement attributes. Note that the stem says “according to the plan”: you are looking for the plan where the rules are, not the document where the requirements themselves are (that is the requirements documentation). What has to be decided here is exactly “how to analyze, document and manage requirements,” so the answer is A.

Why the other options are wrong

  • B. The configuration management plan governs how versions and configurations of products and documents are managed. It does not set out how requirements are analyzed and documented.
  • C. The scope management plan explains how scope will be defined, developed, monitored, controlled and validated. Scope and requirements are two different things: the plan contains no requirements and does not set out how requirements are recorded.
  • D. The change management plan governs how changes are handled. It is not the basis for analyzing and documenting requirements.

Key takeaway For how to analyze, document and manage requirements, look at the requirements management plan; do not confuse it with the scope management plan.

Variation If the stem were changed to “which document should be used to determine how to prepare the scope statement, create the WBS and accept deliverables,” the answer would be the scope management plan.

Something wrong with this question?

Report an issue with this question

Example 2 Scenario: the customer says a requirement was not implemented at acceptance

Question 2Example

A training company's learning platform project is close to delivery. The customer representative arrives on site for acceptance, finds that one requirement he proposed has not been implemented, and is very upset. What should the project manager do?

Show answer and explanation

Correct answer: B

The project is close to delivery. At acceptance the customer representative says a requirement he proposed was not implemented, and he is upset. The question asks what the project manager should do.

When a customer says a requirement was not implemented, verify the facts first and then decide on action. The requirements traceability matrix links requirements to deliverables and tests, so consulting it confirms whether the requirement was approved and recorded, whether it was assigned to a deliverable, and whether it was implemented and tested. After verifying, if it was indeed approved but missed, assess the impact and process the needed defect repair or corrective action through change control; once it is approved, implement it, reverify the deliverable and re-run acceptance. If it is not within the approved scope, it is a new request and goes through change control. The answer is B.

Why the other options are wrong

  • A. Agreeing to build it before checking whether the requirement truly belongs to the approved scope can bypass change control and may mean doing work outside the scope.
  • C. The benefits management plan focuses on how benefits will be realized and measured. It does not contain the customer's specific requirements and cannot be used to check whether requirements were implemented.
  • D. The scope management plan only explains how scope is managed. It contains no specific requirements, so asking the customer to compare against it would not reveal the gap.

Key takeaway When a customer says a requirement was not met, check the requirements traceability matrix first, and only then talk about building it or going through change.

Variation If the matrix shows that the requirement was never approved, it is a new request. It cannot simply be built; submit a change request, and include it in scope only after assessment and approval.

Something wrong with this question?

Report an issue with this question

Example 3 Scenario: an approved requirement was never entered in the matrix

Question 3Example

The project manager checks and finds that 6 approved requirements were never entered in the requirements traceability matrix, so they cannot be traced to deliverables or tests, and the acceptance date is approaching. What should the project manager do?

Show answer and explanation

Correct answer: B

The acceptance date is approaching. A check finds that 6 approved requirements were never entered in the requirements traceability matrix, so they cannot be traced to deliverables or tests. The question asks what the project manager should do.

One purpose of the matrix is to ensure that every approved requirement is delivered by the end of the project. These 6 requirements are approved but not tracked by the matrix, which may mean only that the records are incomplete, or may mean nobody has built or tested them. Enter them immediately, then check the scope baseline, WBS, deliverables, test plan and verification records. Complete trace links where corresponding items exist; where they do not, assess the impact and address the gaps through change control and the quality plan before updating the matrix. The answer is B.

Why the other options are wrong

  • A. Waiting until acceptance to enter them means that when omissions are found it is too late to build or test them, which defeats the purpose of tracking throughout the process.
  • C. Asking the test team to judge from experience whether they are covered has no basis, cannot prove the requirements were met, and leaves no traceable record.
  • D. These 6 are approved requirements and cannot be treated as deferred on one's own. If an adjustment is really needed, it must go through change control.

Key takeaway Approved requirements must all be traceable; if records are missing, enter them, verify the underlying evidence, and then complete valid links or address the gaps through governance.

Variation If the check had found “a requirement has a deliverable but no test case,” the remedy would be to add tests and submit for acceptance after they pass, not to re-enter the requirement.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The scope management plan contains no scope, and the requirements management plan contains no requirements: both plans cover only how things are managed.
  • The configuration management plan governs versions and the change management plan governs how changes are handled; neither is the basis for "how requirements are analyzed, documented and managed."
  • When the customer says a requirement was not done: verify against the matrix first, then decide whether to build it or go through change control. Do not agree straight away, and do not judge from memory or experience.
  • An approved requirement cannot be put on hold just because "the customer did not mention it." In a predictive project, once the scope baseline is set, adding or dropping requirements goes through change control. In an adaptive project, the product owner usually handles it by managing the backlog, reprioritizing and iteration planning, following the established governance rules.
  • The structure of the matrix is defined by the requirements management plan; it is not a table made up on the spot.

Key takeaways

  1. The requirements management plan describes how requirements will be analyzed, documented and managed: planning, tracking and reporting of activities, configuration management, prioritization, metrics and the traceability structure.
  2. The requirements management plan contains no actual requirements; it differs from the scope management plan, the configuration management plan and the change management plan.
  3. When a requirement changes, do impact analysis along the matrix. A predictive project then goes through change control; an adaptive project adjusts the backlog under governance rules. Update the documents and the matrix as well.
  4. At acceptance, check item by item: is there a deliverable, is there a test strategy and test scenarios, and is the status completed?
  5. When the customer says a requirement was not implemented, check the matrix first. If an approved requirement has no record, add it immediately, verify the underlying artifacts and complete valid trace links; address real gaps through change control and the quality plan.

This chapter has 17 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.