Scope
Work Breakdown Structure
PMP · Scope · 3 lessons · about 32 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
The scope statement makes clear what the project will deliver; the work breakdown structure (WBS) answers what smaller pieces of work those deliverables are made of. The Develop Scope Structure process decomposes the whole scope level by level until each piece is small enough to assign to people, estimate for cost and duration, and track and measure. Its outputs, the WBS and the WBS dictionary, together with the project scope statement, make up the scope baseline, the yardstick that Monitor and Control Scope and Validate Scope later measure against.
The exam tests this chapter in a stable pattern: what a WBS and a work package are; that what is decomposed is deliverables, not activities; the 100% rule; the relationship among control accounts, planning packages and work packages; what goes in the WBS dictionary; what the scope baseline consists of; and what manages scope in predictive, adaptive and hybrid projects. Common mistakes are listing activities in the WBS and treating the scope baseline as if it were only the WBS.
Lessons in this chapter
- Lesson 1: WBS Definition and Decomposition. What a WBS is, and the inputs, technique and outputs of Develop Scope Structure; the five decomposition activities; ways to organize the second level; nodes are deliverables, not activities.
- Lesson 2: Work Packages, Planning Packages and Control Accounts. Where to stop decomposing; a control account has two or more work packages, and each work package belongs to a single control account; planning packages and rolling wave planning; the 100% rule that PMBOK 8 states explicitly (common exam practice adds the clear-responsibility principle), and the rules of thumb of 80 hours and 4-6 levels; a review by everyone to remove duplicates and fill gaps.
- Lesson 3: The WBS Dictionary and the Scope Baseline. What the dictionary holds and how it is completed step by step; scope baseline = scope statement + WBS + WBS dictionary; the product backlog in adaptive projects; managing hybrid projects part by part.
Chapter map
Predictive scope baseline (changed through formal change control)
- Project scope statement: scope, major deliverables, project exclusions
- WBS: hierarchical decomposition of all the work (100% rule) Control account (≥ 2 work packages, management control point)
- Planning package: content known, detailed activities not yet known (rolling wave planning)
- Work package: lowest level, can be estimated and assigned
- WBS dictionary: work description, resources, acceptance criteria and more for each component
Adaptive: product backlog (epics, features, user stories); hybrid: manage part by part
Lesson 1
WBS Definition and Decomposition: Breaking All the Scope Down to Work Packages
Lesson overview
In the ECO, under Process domain Task 2 (Develop and manage project scope), "decompose the scope" is singled out as a piece of work in its own right. The scope statement makes clear what is to be delivered, but deliverables are usually too big to assign directly to people or to estimate for cost and duration. This lesson explains what a work breakdown structure (WBS) is, how it is broken down step by step, and how to organize the second level. The next lesson covers where to stop decomposing, and the third covers the accompanying WBS dictionary and the scope baseline.
What a WBS is
A work breakdown structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Each descending level of the WBS represents an increasingly detailed definition of the project work. The lowest level is the work package. In PMBOK 8, predictive and hybrid projects use a WBS; in adaptive projects the counterpart is the product backlog, where work items can be broken down into epics, features and user stories.
First, read the name carefully. The WBS is a hierarchical decomposition of the total scope of work and includes all product and project work (including project management work). It is oriented toward deliverables and verifiable results; its nodes usually describe outcomes to be produced (upper-level components can also be divided by phases of the project life cycle). A work package is not the same as a schedule activity; specific actions are broken down into activities when the schedule is developed. For example, "booking page" is a node in the WBS, while "design the booking page" is an activity that appears later, when the schedule is built. Mixing the two up is one of the most common mistakes in this chapter.
In PMBOK 8 this process is called Develop Scope Structure. It is the bridge among the six processes of the Scope performance domain: it turns the project scope statement produced by Define Scope into a structure that can be assigned, estimated, tracked and measured. The main inputs are the project scope statement, the requirements documentation and approved changes. The main technique is decomposition, supplemented by brainstorming and expert judgment. The main outputs are the WBS and the WBS dictionary (in predictive projects these two, together with the project scope statement, make up the scope baseline; in adaptive settings the process also produces user stories and the product backlog).
Decomposition is a technique for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts. How far to decompose depends on the degree of control needed to effectively manage the project. The WBS must represent all product and project work, including project management work; the work at the lowest levels rolls up so that nothing is left out and no extra work is performed. This is the 100% rule, covered in more detail in the next lesson.
How decomposition is done
Decomposing the total project work into work packages generally involves five activities: identifying and analyzing the deliverables and related work; structuring and organizing the WBS; decomposing the upper WBS levels into lower-level detailed components; developing and assigning identification codes to the WBS components; and verifying that the degree of decomposition of the deliverables is appropriate. The test for the last step is that the lower-level components are necessary and sufficient for completion of the higher-level deliverable, and that each component is a verifiable product, service or result.
There are several common ways to organize the second level. One is to use phases of the project life cycle as the second level, with the product and project deliverables inserted beneath each phase. Another is to use the major deliverables directly as the second level. A third is to incorporate subcomponents developed by organizations outside the project team (for example, contracted work), where the seller develops a supporting contract WBS. There are also several methods: the top-down approach, the use of organization-specific guidelines or WBS templates, or a bottom-up approach that groups lower-level components.
Let's walk through an example. A convenience store chain is converting to self-checkout. The scope statement lists these major deliverables: checkout terminal software, in-store equipment installation, staff training and project management. Step 1 identifies the four pieces. Step 2 decides to arrange the second level by deliverable. Step 3 breaks them down: the checkout terminal software is divided into barcode recognition, payment integration and reconciliation reports; equipment installation is divided into delivered equipment that has been accepted, and on-site wiring that has been completed and tested; training needs no further breakdown and is a work package by itself; project management is broken into verifiable results such as the project management plan and status reports (details such as specific meeting schedules go into the activity list, and the WBS uses verifiable results or categories of work to represent the project management scope). Step 4 numbers each node, such as 1.1.2. Step 5 checks: if you add up all the lowest levels, do they exactly equal all the work of the conversion project? Is any node actually an action, such as "communication and coordination"? If you find a problem, go back and adjust.
As a way of thinking, breaking down level by level from the top is deduction: you start with the top-level objective and ask which pieces it must contain. Grouping from the bottom up is induction: you first identify lower-level components and then group them level by level into the upper structure. Organization guidelines and WBS templates are another kind of approach and can also be used for reference. These methods can be used alone or combined as the situation requires; the key is that the pieces at the same level do not overlap and together leave nothing out. Different deliverables can be decomposed to different numbers of levels: some reach the work package in one level, and some need more levels. A WBS can be drawn as an organizational chart or written as an outline.
Worked examples
Example 1 The deliverable is too big to assign: decompose it first
A project manager is responsible for several very large software modules that must be completed by a few senior engineers over the next few weeks. The modules are large and complex, and no single engineer can take on one of them alone. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
Several software modules are large and complex, and no single engineer can take on one alone. The question asks what the project manager should do first.
The root of the problem is that the modules are too big to assign to individuals, not that there are too few people or that an uncertain event has appeared. The Develop Scope Structure process uses decomposition to break large deliverables, level by level, into smaller, more manageable work packages. Work packages with clear boundaries that can be estimated can be assigned to specific engineers, and later estimating and tracking then have something to work on. So the first step is to break the modules down using Develop Scope Structure. The answer is D.
Why the other options are wrong
- A. The stem does not say people are short; the difficulty is that the modules are too big. Even with more people, the large modules still cannot be split among them, and there is no reason to go to change first.
- B. Handing the whole set of modules to whoever frees up first and letting him divide them leaves the scope division and responsibility unclarified, and pushes the decomposition onto an individual.
- C. The modules being too big is an existing fact, not an uncertain event that may or may not occur, so it should not be registered as a risk.
Key takeaway When a deliverable is too large to assign, decompose it into work packages first, then assign it.
Variation If the work packages are already defined but nobody knows the acceptance criteria of each, what must be added is the WBS dictionary; if the number of available engineers is insufficient, then it becomes a question of resources and schedule.
Something wrong with this question?
Example 2 Reverse question: which practice should not be used when creating a WBS
The project is in planning, the scope statement is complete, and the team is creating the WBS. Which of the following practices should NOT be used when creating the WBS?
Show answer and explanation
Correct answer: D
In planning, the scope statement is complete and the team is creating the WBS. Note that the question asks which practice should not be used when creating the WBS.
The nodes of a WBS are deliverables and work results; the “work” in its name refers to work products that are the result of activities, not to the activities themselves. Listing every activity needed to complete the deliverables in the WBS confuses the WBS with the activity list; activities are derived later from the work packages when the schedule is developed. So D should not be used. A, B and C are all practices that PMBOK 8 recognizes. The answer is D.
Why the other options are wrong
- A. Components developed by organizations outside the project team can be included as subcomponents, with the seller developing a separate WBS for the contract. This is a common practice.
- B. Using the major deliverables as the second level is one of the common ways to organize the second level.
- C. Deliverables differ in complexity, so they can be decomposed to different depths, according to the degree of control needed for management.
Key takeaway The WBS decomposes deliverables, not activities; activities are listed later, when the schedule is developed.
Variation On the question of whether project management work belongs in the WBS, the answer is yes; on a question about the inputs of Develop Scope Structure, choose the project management plan, project documents (including the project scope statement and requirements documentation), approved changes and so on, and the list is not limited to these.
Something wrong with this question?
Common traps
Common trap
- The WBS decomposes deliverables, not activities. An option that lists "every activity needed to complete the deliverables" in the WBS confuses the WBS with the activity list.
- Requirements are not scope, and they are not the WBS. Collecting requirements only records stakeholder expectations; it does not guarantee that all the work has been listed.
- When a deliverable is too big to hand out, decompose it first and then assign it. Do not add people first, and do not register a risk first.
- Project management work is also project work and belongs in the WBS.
WBS vs. activity list
- WBS: noun-style work results, answering "what things are to be delivered" level by level.
- Activity list: verb-style actions, broken down from work packages when the schedule is developed, answering "what has to be done."
Key takeaways
Key point
- The WBS is a hierarchical decomposition of the total scope of work, and its lowest level is the work package; predictive and hybrid projects use a WBS, and adaptive projects use the product backlog as the counterpart.
- The main technique of Develop Scope Structure is decomposition; the main outputs are the WBS and the WBS dictionary (adaptive projects also produce user stories and the product backlog), which in a predictive project, together with the project scope statement, make up the scope baseline.
- Five decomposition activities: identify the deliverables, set the structure, decompose level by level, assign codes, verify the degree of decomposition.
- The second level can be organized by phase or by major deliverable; outsourced parts can be included, with the seller developing a separate WBS; different deliverables can have different numbers of levels.
- Nodes are deliverables, not activities; all product work and project management work must be included.
Lesson 2
Work Packages, Planning Packages and Control Accounts: Where to Stop Decomposing
Lesson overview
The previous lesson covered how to break things down level by level. This lesson answers two very practical questions: at which level can you stop, and how does the level where you stop relate to the control account used for reporting to management? The exam tests this part in a stable pattern: either it asks about the characteristics of a work package, or it asks which principles you must follow when creating a WBS and which are only rules of thumb. After this lesson, look at the WBS dictionary in the third lesson and the whole scope structure will be complete.
Work packages, planning packages and control accounts
The lowest level of the WBS is a work package with a unique identifier. It is the work defined at the lowest level of the WBS for which cost and duration can be estimated and managed. These identifiers provide a structure for hierarchical summation of cost, schedule and resource information and form a code of accounts. To decide whether a node should be decomposed further, ask three questions. Can a clearly responsible person be named? Can cost and duration be estimated directly? Would further decomposition make the management cost greater than the benefit? PMBOK 8 bases the decision on this: the cost and duration of a work package should be estimable and manageable, and the level of decomposition depends on the degree of control needed to effectively manage the project. So you can stop decomposing when the work can be estimated and managed and the level of detail is enough for control; being able to name a responsible person and the management cost of further decomposition are supporting considerations.
A control account is a management control point where the scope, budget and schedule are integrated and compared to the earned value for performance measurement. It sits above the work packages: a control account has two or more work packages, though each work package is associated with a single control account. A planning package sits in between: it is a WBS component below the control account and above the work package with known work content but without detailed schedule activities. A control account may include one or more planning packages.
Here is a way to remember the division of labor among the three. The work package is the unit for doing and estimating the work. The control account is the unit for reporting and measuring performance: management looks at how much the software portion has cost and how its schedule is going, without having to watch every work package. The planning package is a placeholder for "we know it has to be done, but we cannot schedule it in detail yet."
Some deliverables will not start until very late, and information now is insufficient; breaking them down in detail now would only go out of date. In that case, leave them at a coarser level as a planning package and elaborate them when conditions are ripe. This is rolling wave planning, which fits the progressive elaboration of a project. For example, in the convenience-store project, what the reconciliation reports under the checkout terminal software will contain is not known until the finance department fixes the report format. For now only "reconciliation reports" and a rough budget are written, with no further breakdown. Once the format is final, it is broken into two work packages: daily closing reports and monthly reconciliation.
Principles for creating a WBS
The creation rule that PMBOK 8 states explicitly is the 100% rule: the WBS includes all product and project work, with nothing left out and no extra work, and the work at the lower level adds up to the level above. Common exam practice pairs it with the clear-responsibility principle, that every component has a clearly responsible person, as the two principles that "must be followed." Responsibility can be reflected in the WBS dictionary (responsible organization) and in the responsibility assignment matrix. The rules of thumb are the 80-hour rule (a work package should be about 80 hours or less) and the 4-6 levels rule (generally do not decompose too finely). These two numbers are only experience-based guides. PMBOK 8 stresses that the level of decomposition depends on the degree of control needed to manage, and that excessive decomposition reduces efficiency.
| Principle | Meaning | Nature |
|---|---|---|
| 100% rule | All the work is there, nothing missing and nothing extra | Must follow |
| Clear-responsibility principle | Each component has a clearly responsible person | Common exam practice as a must-have |
| 80-hour rule | A work package is about 80 hours or less | Rule of thumb |
| 4-6 levels rule | Generally no more than 4 to 6 levels | Rule of thumb |
Decomposing more finely is not always better. If you break things down too finely, management effort is wasted, data is harder to roll up through the levels, and the efficiency of performing the work also falls. Likewise, project management work belongs in the WBS and is represented by deliverables such as the project management plan and status reports; details such as specific meeting schedules are listed as activities when the schedule is developed. If the tests and reviews required by the quality management plan will use resources and time, they too must be included in the project work that the WBS represents: where necessary they can be set up as separate work packages, or included as activities within related work packages and carried into the estimates and schedule. Otherwise the budget and schedule have no place for them.
The most effective way to achieve "nothing left out and nothing extra" is to have the people involved review it together. When departments each build their own part, the combined result easily contains duplicates or gaps. When everyone is brought together for a joint review, each person can see the content of the others' work, and before the WBS is finalized the duplicates can be deleted and the gaps filled.
Worked examples
Example 1 A deliverable that can already be estimated, managed and assigned becomes a work package
While creating the WBS, the team confirms that a deliverable has been decomposed to the level of detail needed for control, its cost and duration can be estimated and managed, and one responsible person can be named. What should the project manager do?
Show answer and explanation
Correct answer: C
While creating the WBS, you must decide whether a deliverable should be decomposed further. It has reached the level of detail needed for control, its cost and duration can be estimated and managed, and one responsible person can be named.
The work package is the lowest level of the WBS: work whose cost and duration can be estimated and managed. The stem states that the detail is sufficient for the required control, cost and duration can be estimated and managed, and a responsible person can be named, so it should be kept as a work package and not decomposed further in the WBS; when the schedule is developed later, the work package can still be progressively elaborated into specific activities. Decomposing further only adds burden to rolling up and managing. The answer is C.
Why the other options are wrong
- A. Breaking it into a day-by-day task list is going too far. Excessively fine decomposition wastes management effort and makes rolling up data through the levels harder.
- B. A planning package sits below a control account and above the work-package level, for known work that has not yet been elaborated into work packages. The stem says the detail is sufficient for control and cost and duration can be estimated and managed, so there is no reason to leave it as a planning package awaiting elaboration.
- D. Once merged with the adjacent deliverable, it no longer appears separately in the WBS. This deliverable can already be assigned to one owner and estimated for cost and duration, so merging it would blur responsibility and the basis of the estimate, and there is no need for it.
Key takeaway A component at the lowest level of the WBS whose cost and duration can be estimated and managed is a work package and need not be decomposed further in the WBS; it can still be progressively elaborated into specific activities when the schedule is developed.
Variation If this deliverable will not start for another six months and all that is known now is what has to be done, with no further detail possible, keep it as a planning package and elaborate it on a rolling basis when the information is clear.
Something wrong with this question?
Example 2 Duplicates found after separate drafting: hold a review with everyone
A project spans several departments. The project manager met with each department's members separately, and each prepared the WBS for the part it was responsible for. After the WBS was finalized, it was found that some work appeared twice in the parts of different departments. To avoid this kind of problem, what should the project manager have done?
Show answer and explanation
Correct answer: D
A project spans several departments. The project manager met with each department separately and each prepared its own WBS; after finalization, some work was found duplicated in different departments' parts. The question asks what the project manager should have done.
A WBS has to have all the work with nothing missing and nothing extra. When departments build their parts separately, they cannot see each other's content, and duplicates and gaps show up only after the parts are merged. Had all members been convened beforehand to review the WBS together, everyone could compare each other's work content, and duplicates could be deleted and omissions filled before the WBS was finalized. The answer is D.
Why the other options are wrong
- A. Subject matter experts giving guidance on scheduling address a scheduling problem and cannot eliminate duplicates in the WBS structure.
- B. Improving communication channels is a long-term measure. It does not target the review step of the WBS and cannot ensure duplicates are found before finalization.
- C. A responsibility assignment matrix is a tool for assigning responsibility after the WBS is done. It cannot prevent duplication within the WBS itself.
Key takeaway When departments build their WBS parts separately, use a joint review by everyone to remove duplicates and fill omissions before finalizing.
Variation If the question asks how to prevent omitted work from being discovered only after the WBS is finalized, the answer is still to conduct a joint review before finalization. If the omission is discovered after the scope baseline has been approved, the current response is to assess the impact and use formal change control. If what is wrong is that a member does not know which work package they are responsible for, clarify responsibility with a responsibility assignment matrix.
Something wrong with this question?
Common traps
Common trap
- The work package is the lowest level of the WBS. Bigger is not better, and smaller is not better. Stop decomposing when its cost and duration can be estimated and managed and the level of detail is enough to exercise the control needed; clear responsibility can serve as a supporting consideration.
- Each work package belongs to only one control account; it cannot hang under two control accounts at once.
- A planning package is for the case of "content known, detailed activities unknown." Even if a rough budget or a high-level duration estimate already exists, it can remain a planning package, until the work is elaborated to the lowest level at which cost and duration can be estimated and managed and then forms work packages.
- 80 hours and 4-6 levels are only rules of thumb. Common exam practice: when a question asks which principles are "must follow" and these two are among the options, choose the 100% rule and the clear-responsibility principle.
- A responsibility assignment matrix can assign and clarify responsibility based on identified WBS components or activities, but it cannot replace a WBS review for removing duplicates.
Work package, planning package, control account
- Work package: lowest level, can be estimated and assigned, used for doing the work.
- Planning package: below the control account and above the work package, with known work content and unknown detailed activities.
- Control account: a management control point that integrates scope, budget and schedule and is compared to earned value; contains at least two work packages.
Key takeaways
Key point
- A work package is the lowest level of the WBS; its cost and duration can be estimated and managed, and it also makes it easy to name a clearly responsible person.
- A control account is a management control point with two or more work packages; each work package belongs to a single control account.
- A planning package is below the control account and above the work package: known content, unknown detailed activities, used for rolling wave planning.
- The 100% rule must be followed (the WBS includes all product and project work, with nothing left out and nothing extra); assigning clear responsibility is an important management practice that can be reflected in the WBS dictionary and the responsibility assignment matrix; 80 hours and 4-6 levels are only rules of thumb.
- When departments draft WBS parts separately, use a review by everyone to remove duplicates and fill gaps; project management work belongs in the WBS too (represented by deliverables such as the project management plan and status reports).
Lesson 3
The WBS Dictionary and the Scope Baseline: How Predictive, Adaptive and Hybrid Projects Manage Scope
Lesson overview
The WBS gives only the structure. What each node does, who is responsible and how it will be accepted have to be explained by its companion document. This lesson first covers the WBS dictionary, then the scope baseline made up of the scope statement, the WBS and the WBS dictionary, and finally how scope is managed differently in the three types of project. The later chapters on Monitor and Control Scope and Validate Scope both use the scope baseline as the yardstick, so this lesson is the "instructions" for the scope baseline.
The WBS dictionary
In projects with complex or interdependent deliverables, a WBS dictionary can be developed to provide detailed deliverable, activity, scheduling, cost and resource information about each component in the WBS. It supports the WBS by elaborating on elements such as scope descriptions, milestones, responsible parties, resource needs and acceptance criteria, which enhances clarity and consistency within the team. Most information included in the WBS dictionary is created by other processes and added to this document at a later stage.
The dictionary is not written all at once. When the WBS is first created, record the information already clear at that point (such as the code of accounts and the description of work). As PMBOK 8 says, most information is created by other processes and added later: quality requirements are added when quality is planned, milestones and associated activities when the schedule is built, and cost estimates when costs are estimated. The dictionary entry for each component may include: code of account identifier, description of work, assumptions and constraints, responsible organization, schedule milestones, associated schedule activities, resources required, cost estimates, quality requirements, acceptance criteria, technical references and agreement information.
A comparison helps fix the division of labor. The WBS is like a table of contents: it tells you which work packages there are, each with a number. The WBS dictionary is like a specification sheet for each entry: it tells you what the work package does, who is responsible for it, what resources it needs and what counts as acceptable. When a new member takes over a module and wants to know what work is in the work packages they are responsible for and what resources they need, they should look in the dictionary, not only at the WBS. When components are being integrated and the interfaces do not match, checking the work descriptions of the components also means going to the dictionary.
The scope baseline
The scope baseline is the approved version of formal scope documents that can be changed using formal change control procedures and is used as the basis for comparison to actual results. It is a component of the project management plan and includes three items: the project scope statement (which describes the project scope, major deliverables and project exclusions), the WBS and the WBS dictionary. In a predictive project the scope baseline is part of the performance measurement baseline, along with the schedule baseline and the cost baseline.
So the "scope baseline" is not the same as the WBS. When a question asks what the scope baseline includes, the answer is the scope statement plus the WBS plus the WBS dictionary; if an option says "requirements documentation" or "project charter," those are outside the scope baseline.
Adaptive and hybrid environments
An adaptive project has no scope baseline frozen in advance. PMBOK 8 says that for adaptive approaches the baseline is defined at the beginning of each iteration and aligned with the prioritized requirements, based on the value expected from the delivery; in adaptive environments it is usually a product owner who dynamically approves changes, in a more flexible environment, without a formal change control procedure. The counterpart of the WBS is the product backlog: a dynamic, prioritized list of work items and features, in which work items can be broken down into epics, features and user stories. When a stakeholder worries about whether a feature has been included, have them look at the backlog.
A hybrid project combines the two approaches. The overall expectations are set with a scope baseline, a schedule baseline and a cost baseline, while the sub-teams below work through the user stories lined up on the backlog iteration by iteration. A common situation is that different parts use different approaches, for example a smart speaker project in which the hardware follows a predictive approach and the companion app an adaptive one. Scope is then managed part by part: the predictive hardware part has a scope baseline, and changes go through formal change control; the adaptive app part carries its scope in a backlog, and the product owner dynamically prioritizes and approves by value.
Scope carriers for the three types of project
- Predictive: scope baseline (scope statement + WBS + WBS dictionary); changes go through formal change control.
- Adaptive: product backlog; the baseline is set at the start of each iteration, and the product owner dynamically approves changes.
- Hybrid: managed part by part; the predictive part uses a baseline and the adaptive part uses a backlog.
Worked examples
Example 1 To look up the details of a work package, use the WBS dictionary
A bakery chain's store app development project is at its midpoint. The member responsible for testing has moved to another project and a new member takes over. He wants to understand the description of work, the deliverable and the resources required for one of the work packages. Which document should the project manager have him consult?
Show answer and explanation
Correct answer: D
At the midpoint of the project, a new member takes over testing. He wants to know the description of work, what is to be delivered and the resources required for one work package. The question asks which document to consult.
The three items of information in the stem are all details at the level of a single work package. The WBS dictionary provides detailed information for each WBS component, such as the code of account identifier, description of work, resources required and acceptance criteria, which matches exactly. The WBS shows only the hierarchy and the names of the work packages, and the details have to be filled in from the dictionary. The answer is D.
Why the other options are wrong
- A. The scope statement describes the scope, major deliverables and exclusions of the whole project. It does not go down to a single work package and has no resources required.
- B. The project charter gives only high-level objectives and requirements, with no detail at the work package level.
- C. The WBS presents the levels of decomposition and the names of work packages. It does not provide the description of work and resource requirements of each component.
Key takeaway To learn the detailed information of a work package, look at the WBS dictionary; the WBS gives only structure. The WBS dictionary is the companion document of the WBS, and together with the scope statement and the WBS it forms the scope baseline.
Variation To find the major deliverables and exclusions of the whole project, look at the project scope statement; if asked what makes up the scope baseline, answer the scope statement, the WBS and the WBS dictionary.
Something wrong with this question?
Example 2 How to manage the scope of a hybrid project part by part
A smart home project uses a hybrid approach: the hardware part proceeds predictively, and the application software part is developed using an adaptive, iterative approach. How should scope management be arranged?
Show answer and explanation
Correct answer: A
A hybrid project: the hardware part proceeds as predictive and the application software part is developed using an adaptive, iterative approach. The question asks how scope management should be arranged.
In a hybrid project the overall expectations are set by the scope baseline, schedule baseline and cost baseline, while the sub-teams below may work through the user stories on the backlog iteration by iteration. So scope is managed part by part. The hardware is predictive and gets a scope baseline (project scope statement, WBS, WBS dictionary), with changes going through formal change control; the software is adaptive and carries its scope in a backlog, with the product owner dynamically ordering and approving by value. The answer is A.
Why the other options are wrong
- B. Freezing the software part as well takes away its flexibility to adjust by iteration and respond to feedback, which goes against the adaptive approach.
- C. The hardware proceeds as predictive and needs a scope baseline and formal change control; a backlog alone cannot manage it.
- D. This swaps the methods: what needs a baseline is the predictive hardware, and what can be adjusted dynamically is the adaptive software.
Key takeaway A hybrid project is managed part by part: the predictive part has a baseline, and the adaptive part uses a backlog.
Variation If the whole project were adaptive, you would usually not freeze an overall scope baseline in advance but set the baseline for each iteration at its start; if requirements change on the hardware part, you still raise a change request and go through change control.
Something wrong with this question?
Common traps
Common trap
- For a work package's description of work, resources required and acceptance criteria, look in the WBS dictionary. The WBS gives only the hierarchy and numbers, and the scope statement covers the whole project, not a single component.
- The scope baseline is a set of three things, not just the WBS, and it does not include the requirements documentation or the project charter.
- A hybrid project does not freeze a baseline for everything, and it does not use only a backlog for everything.
- Do not swap the methods: the part that needs a baseline and formal change control is the predictive part, and the part that can be adjusted dynamically is the adaptive part.
- The adaptive counterpart of the WBS is the product backlog, not the user story (a user story is only one entry in it).
Key takeaways
Key point
- The WBS dictionary provides detailed information for each WBS component, such as work description, resources required, quality requirements and acceptance criteria; most of it is created by other processes and added later.
- Scope baseline = project scope statement + WBS + WBS dictionary; in predictive projects it is changed through formal change control, and it is the basis for comparing actual results later.
- Adaptive projects use the product backlog; the baseline is set at the start of each iteration, and the product owner dynamically approves changes.
- Hybrid projects are managed part by part: the predictive part has a baseline and goes through change control, and the adaptive part uses a backlog.
This chapter has 32 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.