PMP Cheat Sheet: Agile and Hybrid
The key points and common traps of 42 lessons in 14 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.
The Agile Manifesto
Lesson 1: The Definition of Agile and the Four Values
- Use predictive when requirements are clear and stable, adaptive when there is uncertainty and a need for feedback, and hybrid when both are present. Agile approaches are adaptive.
- The weaknesses of a single-delivery predictive project are that value appears too late and that change after the baseline must go through the formal change process.
- Agile is a mindset. Scrum, Kanban and extreme programming are methods for putting it into practice.
- The four values: individuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; responding to change over following a plan.
- "Over" does not mean "instead of". The items on the right also have value, and when they conflict you protect the left item first.
- Agile does not mean no plans and no documentation: the items on the right also have value, but the items on the left come first.
- Hybrid does not have to be a 50/50 compromise. It combines predictive and adaptive elements in a way suited to the work, for example by deliverable, phase, workstream, or throughout the life cycle.
- Agile does not guarantee lower risk or lower cost. The main reason to adopt agile is to deliver value early and continuously.
- When the customer explicitly requires a document and it is really needed, you neither refuse nor switch to a predictive approach. You add it as a work item to the backlog or workflow, order it by necessity, and schedule it.
Lesson 2: The Twelve Principles (Part 1): Customer Value and Continuous Delivery
- Principle 1: "Our highest priority is to satisfy the customer through early and continuous delivery of valuable software."
- Principle 2: "Welcome changing requirements, even late in development." Change goes into the backlog and is reprioritized by value, and generally does not go through the predictive-style change control board approval (unless project governance says otherwise).
- Principle 3: "Deliver working software frequently, from a couple of weeks to a couple of months, with a preference to the shorter timescale." In Scrum, a Sprint is one month or less.
- Principle 7: "Working software is the primary measure of progress." Confidence is rebuilt with results, not with explanations or meetings.
- Question cues: if it asks what to focus on "first", choose customer value; if it asks how to reassure people, choose delivering working software.
- The benefit of adopting agile is that value is delivered earlier. It does not guarantee lower cost, and it does not make the team more capable in itself.
- While an iteration is under way, do not refuse all new requirements, do not ask the customer to sign change documents, and certainly do not lengthen the iteration. New requirements go into the backlog.
- "Progress" is measured by working software, not by the number of documents, lines of code or hours.
- Teamwork and self-organization are means, not agile's highest goal. The highest goal is customer value.
Lesson 3: The Twelve Principles (Part 2): Teams, Communication, Sustainable Pace and Simplicity
- Principle 4: business people and developers work together daily. If contact with the customer has lapsed, restore direct communication first.
- Principles 5 and 11: trust and support individuals, a self-organizing team decides for itself how to work, and team rules are set by the team itself.
- Principle 6: face-to-face conversation is the most efficient and effective, and distributed teams replace it with video conferencing.
- Principles 12 and 8: retrospectives drive continuous improvement, and the pace must be sustainable. When the team is worn out, first correct the overcommitment and restore a sustainable pace; do not rely on constant overtime or blindly add people, and evaluate adding people only if there is a real long-term need.
- Principles 9 and 10: pursue technical excellence and make technical debt visible; keep to simplicity and test the riskiest assumption at the lowest cost first.
- Agile does not relax quality and should not depend on constant overtime to rush work: principle 8 requires a sustainable pace and principle 9 requires technical excellence.
- When a team's technical approach is hard to scale and its retrospectives keep raising communication problems, empower the team to adjust itself and check the effect in later retrospectives, rather than taking over decisions or forcing a solution.
- When a team in transition lacks agile skills, assess the skills gap and provide appropriate training, coaching, pairing or self-study resources, so that the team really gets the capability it needs.
- Technical debt does not disappear because nobody mentions it. Paying it down goes into the backlog and is ordered along with the other items.
- Face to face does not mean "must be in the same office". Distributed teams use high-bandwidth means such as video conferencing.
Lesson 4: The Agile Mindset: Judging Scenario Questions with the Values and Principles
- Remember the twelve principles by theme: delivering value, embracing change, collaboration and communication, the team, pace and progress, quality and simplicity.
- The five questions for judging options: value-driven, transparent, servant leadership, the team solves it itself, change goes through the backlog.
- With contradictory feedback, communicate and clarify first, then order by value. Do not go through the change process, and do not rush the schedule.
- To introduce agile, first let the team understand the values and principles, then talk about specific practices. When there is doubt, first understand the person's concerns, then explain the reasoning behind the practice.
- Transparency comes from information radiators: task boards and burndown charts replace layers of status reports.
- Agile's first goal is to deliver value to the customer, not to be faster or cheaper. When you explain the benefits to stakeholders, focus on continuously delivering high-value increments.
- Customer satisfaction comes mainly from continuous involvement and feedback. It cannot rest on contract terms alone, and it does not come from adding features (contracts and change agreements remain valid; they just cannot replace collaboration).
- An "agile coach" is not a manager but a servant. Do not choose "assign tasks to members" or "require the team to report status".
- In scenario questions, first check whether the stem is predictive or agile. In a predictive question, a change affecting an approved baseline goes through a change request under the agreed process, and whether it goes to the change control board and who approves it depend on the change management plan and authorizations. In a purely agile question, a formal change request and a change control board are mostly wrong (exam tip; where the approach is hybrid or the contract or governance requires otherwise, follow the agreed mechanism).
- When a team has no agile experience, introducing agile should start by helping the team understand the principles, not by immediately applying all the ceremonies of a framework; the specific steps still need tailoring to the context.
Minimum Viable Product
Lesson 1: Minimum Viable Product (MVP): Why You Need One and What It Is
- The problem with predictive all-at-once delivery is that value appears late and risk piles up toward the end. Agile delivers something usable at every step.
- An MVP defines the scope of the first release of a solution to customers by identifying the fewest number of features or requirements that would deliver value.
- The two purposes of an MVP: to validate whether the objective is right, and to fail fast before a large investment.
- Defining the scope: methods such as MoSCoW and user story mapping can help with the trade-offs, and the test is the fewest features that deliver value and validate the key assumption. (A common approach is to start with the "Must have" items; whether to add "Should have" items depends on the goal of the first release.)
- Key signals: new market, uncertain customer acceptance, results needed quickly: choose an MVP. The difference from an MMF is validation versus marketability.
- An MVP is not a poor-quality product, and it is not a half-finished product: it is the smallest set that delivers value and can be used by customers. What you want is a bicycle, not half a car.
- An MVP is not the end of the project. It is the scope target of the first release, it may consist of one or several increments, and after release you keep iterating based on feedback.
- An MVP is different from an MMF: the MVP emphasizes validation, while the MMF emphasizes independently deliverable market or business value.
- To produce something demonstrable quickly, first determine the minimum functionality. Elaborating the WBS is a predictive practice. Splitting the backlog into phases can support release planning, but it cannot replace determining the minimum functionality first, and it does not guarantee that the first iteration has anything to demonstrate.
- Prioritization is the product owner's job. The project manager should not push it to the sponsor.
Lesson 2: Incremental Delivery and Iteration, and the MVP Under Budget or Time Constraints
- An iteration improves the same thing repeatedly, and an increment splits the product into usable small pieces delivered in batches. Adaptive approaches often use both.
- The MVP defines the minimum scope of the first release and can be formed by one or several increments, and later increments build on it.
- Benefits of incremental delivery: earlier feedback, earlier value, less rework, and easier handling of change.
- When budget, time or resources are constrained, or the scope is too large, rank by value with the product owner and deliver the MVP first. Do not cut evenly.
- To estimate the MVP budget, forecast from the story points of its user stories, combined with velocity and the cost per iteration.
- Iteration is not the same as increment: an iteration is repeated improvement and an increment is adding in batches. Adaptive approaches often use both.
- If, after the iteration review, the customer says the first deliverable has little value, the root cause usually lies earlier: the goal of the iteration should have been validated with the customer before the work began, rather than extending the timebox or doing more afterward.
- When the budget is cut, rank by value and protect the MVP first. Do not cut all the work evenly.
- When resources are tight and the full product cannot be delivered on time, and a smaller first release can still deliver value, focus on core value and deliver the MVP. Do not just work overtime, wait to hire people or escalate the problem and leave it there.
- To estimate the MVP budget, first estimate the story points of the user stories it contains, then convert using velocity and the cost per iteration. Do not simply apply the project-level BAC.
Scrum Framework
Lesson 1: Understanding Scrum Through a Shopping List, and How Scrum Flows
- The shopping-list analogy: the list is the Product Backlog, one trip is one Sprint, and what you bring home is the product Increment.
- Fixed time, a team that is usually stable, and scope negotiated by priority. A new change goes into the Product Backlog, usually for a later Sprint, and does not endanger the Sprint Goal.
- The flow: ideas, Product Backlog, Sprint Planning, Sprint (Daily Scrum), product Increment, Sprint Review, Sprint Retrospective.
- Two features of Scrum: fixed-length Sprints, and requirements that have a clear owner and a single person who orders them.
- The three pillars: transparency, inspection, adaptation.
- Do not add requirements casually within a Sprint. A new requirement goes to the Product Owner, who adds it to the Product Backlog and orders it, usually for a later Sprint. If it is truly necessary, the Developers can negotiate with the Product Owner to adjust the current Sprint Backlog, but this must not endanger the Sprint Goal, must not lower quality and does not call for extending the Sprint.
- Once the Product Backlog exists, each Sprint is started by Sprint Planning, followed by the development work. The Daily Scrum, the Sprint Review and the Sprint Retrospective all take place within that Sprint's timebox.
- The Sprint Review is about results and collecting feedback. The Sprint Retrospective is about the way of working and discussing improvements.
- Agile “embraces change” does not mean “change the current Sprint at any time”. It means “accept the change, put it in the backlog, and do it in a suitable Sprint”.
- The Sprint timebox is fixed. Items that are not finished go back to the Product Backlog, and the Sprint is not extended to fit them in.
Lesson 2: The Scrum Core 3-3-5-5 and the Five Values
- 3-3-5-5: three accountabilities, three artifacts, five events, five values.
- The Sprint is an event, and the other four events all happen within it. The Increment is an artifact.
- Artifacts are “things”: the Product Backlog, the Sprint Backlog and the Increment.
- The values: Commitment, Focus, Openness, Respect, Courage. In questions, catch the verb and the object and match them.
- Openness points to making things public and transparent, Focus to putting full effort into the committed work, and Courage to facing hard problems.
- The Sprint itself is an “event” and the Increment is an “artifact”. Meetings are not artifacts and people are not artifacts.
- 3-3-5-5 is what Scrum itself consists of. Pair programming, test-driven development and the like are not in it. They belong to Extreme Programming.
- Openness is “being transparent to the relevant parties”, and Focus is “putting your mind on the work you have committed to”. Do not mix them up just because both involve “work”.
- The order of the five values is Commitment, Focus, Openness, Respect, Courage. In a list question, do not eliminate an option because its order differs, but every one of the words must be there.
Lesson 3: Where Scrum Fits Among Agile Methods, and Scaling Agile
- Scrum is the most widely used and is one of the frameworks most frequently tested in PMP agile questions. PMBOK 8 plots agile methods by breadth and depth.
- A method has steps. A tool kit is a collection from which several methods can draw, such as DA.
- Scrum is a management framework and Extreme Programming is an engineering practice. They are complementary and often used together. Kanban focuses on visualization and limiting work in progress, and Lean focuses on eliminating waste.
- The Scrum of Scrums is a coordination mechanism between multiple teams that synchronizes cross-team dependencies and impediments. It is not the Daily Scrum.
- A large organization with dozens of teams should tailor by product structure, dependencies and organizational context, and may use a scaling framework such as SAFe or LeSS, or a coordination mechanism such as the Scrum of Scrums.
- The Scrum of Scrums is a coordination mechanism between multiple teams. It is not the Daily Scrum, it is not held on a fixed two-week cycle and it is not a leadership meeting.
- Scrum is a management framework (accountabilities, artifacts, events) and Extreme Programming focuses on software engineering and delivery practices. They are complementary, neither containing the other nor contradicting each other.
- Kanban itself does not require fixed-length iterations and is usually characterized by continuous flow and limited work in progress. When a question mentions “fixed Sprints, review and retrospective”, choose Scrum, not Kanban.
- When a large organization adopts agile, it cannot succeed merely by copying Scrum into every team, and it should not assume that management levels must be abolished. It tailors the approach to the product structure, the dependencies and the organizational context, and it may use a scaling framework such as SAFe or LeSS, or a cross-team coordination mechanism such as the Scrum of Scrums.
Scrum Roles
Lesson 1: The Product Owner: Decides What to Build, What Comes First and Whether to Accept It
- The Product Owner is the person responsible for maximizing the value of the product and accountable for the end product, and belongs to the Scrum Team.
- The Product Owner is accountable for the content, order and transparency of the Product Backlog; ordering is by value, with risk, cost and dependencies also considered.
- The Product Owner confirms whether results meet business needs against the acceptance criteria (common exam practice) and, within the authority granted, leads the timing and content of releases. Whether an Increment is done is judged by the Definition of Done.
- The Product Owner is the single person accountable for product decisions and the backlog. It must be one person, not a committee. The Developers can also work directly with stakeholders as agreed.
- When an item is unclear, go to the Product Owner. When several parties compete over priority, the Product Owner orders in one sequence and makes it public.
- The Product Owner does not direct the Developers on how to implement the work and does not manage task-level assignments.
- During development, the Product Owner still has a say on priorities. The role does not end once the requirements have been handed over.
- The project manager, the Scrum Master and the sponsor cannot order the Product Backlog in place of the Product Owner. As to whether a result meets business needs, common exam practice is to choose the Product Owner, confirming against the acceptance criteria, but formal acceptance still follows the governance arrangement and the authority relationships given in the stem.
- Only the Product Owner decides whether an item goes into the list and where it ranks. “Anyone can raise a requirement” does not mean “anyone can order it”.
- When stakeholders demand a trade-off or ask about the feature schedule, direct them to the Product Owner.
Lesson 2: The Scrum Master: Servant Leader
- The Scrum Master is a servant leader (usually working by coaching and facilitating, although agile coach is not a formal synonym) and makes sure Scrum is understood and carried out.
- Three parties served: the Product Owner, the Scrum Team and the organization.
- Six kinds of everyday work: removing impediments, coaching, shielding, facilitating collaboration, guarding the Scrum process and driving change.
- Facilitate without ruling: voice an opinion and leave the decision to the team; team conflicts go to the team first.
- Does not assign tasks, collect status reports or conduct individual reviews. Combining the role with Product Owner is generally not recommended (common exam practice treats the roles as not combinable, but the Scrum Guide does not explicitly forbid it).
- The Scrum Master is not a command-and-control manager (the Scrum Master is a servant leader, and the Scrum Guide calls the Scrum Master a true leader): the team does not report to the Scrum Master, and the Scrum Master does not carry out individual performance reviews.
- The Scrum Master does not have to be full time, and one experienced person can serve several teams.
- One person generally should not be both Scrum Master and Product Owner: one acts like a coach and the other like a decision-maker, and the roles easily conflict. (Common exam practice is to treat them as “cannot be combined”, although the Scrum Guide does not explicitly forbid it.)
- The coach can voice an opinion, but the decision stays with the team. Conflicts go first to the team to resolve, and the coach is a facilitator, not a judge.
- The Scrum Master does not write code or do estimating in place of the Developers. If the Scrum Master also takes on Developer duties (actively working on Sprint Backlog items), the Scrum Master may take part in development and in the team's estimating.
Lesson 3: The Developers: Self-Organizing, Cross-Functional and Decision-Making by Participation
- The whole Scrum Team is accountable for each Sprint's Increment. Within it the Developers are the people who commit to creating the Increment, and anyone in the Scrum Team who does that work is acting as a Developer.
- Five characteristics: small team (3–9 people), self-organizing, cross-functional, T-shaped people, and core members kept as stable and dedicated as possible.
- Estimates are made by the people who do the work, and how much to take in a Sprint is decided by the team.
- Disagreements are resolved through discussion and participative decision-making, and a decision made under the team's agreed rule should be respected.
- Empowerment returns to the team the decisions on how tasks are divided and how the work is done. (The order of the Product Backlog remains the Product Owner's. The Sprint Goal is set collaboratively by the Scrum Team, and the Developers select the items for this Sprint and decide the delivery plan.) Managers and coaches facilitate and do not do it for the team.
- On an agile team, “the project manager assigns tasks to members” is basically wrong. How tasks are divided is decided by the team itself (members can pick up work or have it allocated by negotiation).
- Self-organizing is not “no rules”, and it is not “members choose one another”. It means the team manages its own work.
- A technical disagreement is not decided by who is more senior or who has more study material, nor by copying management or another team. It is decided after discussion by the method the team has agreed on (aim for consensus, but not everyone needs to agree).
- The Developers have no sub-teams and titles do not matter. Cross-functional does not mean everyone is expert at everything. It means T-shaped: one deep specialty plus many skills.
- Frequently adding and removing members damages team stability. Part-time sharing usually adds task switching and dependencies and should be kept to a minimum, but it can be used when resources are constrained, with available time made clear.
Lesson 4: Problem-Solving in an Agile Environment: Let the Team Try First
- First work out who owns the problem: impediments, requirements and technical matters each have their own role.
- Common exam practice for the order of handling: collect data, analyze causes, take action.
- For problems the team finds itself, let the team find its own way first. The servant leader guides and supports without doing it for the team.
- When velocity falls or planned Sprint work is not completed, first look for causes through a retrospective. Do not first add people, money or change scope.
- When the team cannot solve it, it often reorders priorities with the Product Owner to protect the most critical deliverables (depending on the situation, coordinate dependencies or escalate if necessary).
- “Report to a superior”, “reassign”, “bring in outsiders” and “add budget” are often the wrong options in agile scenario questions.
- When velocity drops, first find the cause through a retrospective. Do not first swap people, change scope or add budget.
- Do not rush into action before the cause is clear. The common exam line of thinking is data, cause, action.
- When a technical idea conflicts with the project goal, let the Developers and the Product Owner talk directly. The project manager does not arbitrate.
- “Doing it yourself” is not the same as “deciding for the team”: the Scrum Master can clear impediments, but problems inside the team must be solved by the team itself.
Lesson 5: Removing Impediments and Shielding the Team from Outside Interference
- An impediment is anything that stops the team from moving forward, including outside interference. Helping get impediments removed is one of the Scrum Master's key responsibilities.
- What the team can solve internally: organize a brainstorm. What involves outside people and resources: the Scrum Master negotiates personally.
- A functional manager taking up members: negotiate the available time first. Do not send people back, tattle or cite the charter forcefully.
- A supervisor chasing progress: explain the way of working, take over the inquiries, and pass release concerns to the Product Owner.
- With several impediments, rank by urgency, impact, dependencies and risk, and handle first those that may cause a stoppage or serious violation. A servant leader's first reaction is to help resolve actively.
- Environmental, tooling and permission impediments, and outside interference, are removed with the Scrum Master's help. But for what the team can figure out within its own capability, let the team figure it out.
- For outside interference, usually communicate and negotiate directly first, with no confrontation and no tattling. If the impediment is beyond authority, negotiation fails or an established escalation criterion is met, escalate along the governance path in time and keep tracking the outcome.
- Shielding the team is not blocking. Explaining to the source of interference and taking over the inquiries is the long-term answer.
- Concerns about releases go to the Product Owner, and the Scrum Master does not order for the Product Owner.
- Impediments cannot be handled by “only giving advice” or “only escalating”. Help resolve them actively and follow through.
Product Backlog and Increment
Lesson 1: The Product Backlog: Nature, Ownership and Change Handling
- The Product Backlog is a dynamic, ordered list and the single source of work undertaken by the Scrum Team. Any new work you want the team to do should go into it first.
- The closer to the top, the more detailed and estimable the item; the closer to the bottom, the coarser. Content and order belong to the Product Owner, and estimates belong to the Developers.
- A change is recorded as an item and added to the backlog: a lower priority means deferral, and not adding it, or removing an existing item, means rejection.
- When an item's value changes because of changes in the external environment, go to the Product Owner first to reorder.
- The order for a new requirement is: record, assess and order it, then normally have the Developers select it at Sprint Planning; during a Sprint, scope may also be renegotiated with the Product Owner if the Sprint Goal is not endangered.
- The Product Backlog is not a requirements list fixed at project kickoff. It can change throughout the project, including during Sprints.
- A new request is not simply squeezed into the plan in the name of “embracing change”, and it does not wait for the next release cycle either. It goes into the backlog first and is ordered afterward.
- Reordering is the Product Owner's job. The team, the project manager and the customer cannot go around the Product Owner and change the order directly.
- The Developers do the estimating. The Product Owner cannot do it for them, and it is not the project manager's call.
- Changes in adaptive projects are usually handled by “going into the backlog and being reordered”, not by a traditional formal change request process (PMBOK 8: backlog management handles change, and there is typically no formal approval process). But if organizational governance, regulations or contract terms require it, the corresponding approval or contract change steps must still be followed.
Lesson 2: Backlog Refinement, Definition of Ready and the Sprint Backlog
- Refinement is an ongoing activity: detailing, estimating and ordering, led by the Product Owner with the team taking part.
- The definition of ready is a checklist for before an item enters a Sprint. If an item has no acceptance criteria, they can be added during refinement, usually before the item enters the Sprint; whether this comes before estimating is agreed by the team.
- Sprint Backlog = the items selected for this Sprint + tasks and a plan for delivery, and it belongs to the Developers.
- The Developers divide tasks themselves, and members can pick them up as the team agrees. A new request during the Sprint usually goes into the Product Backlog first.
- An urgent change is re-evaluated with the Product Owner for priority and impact. It is not absorbed by overtime and not passed to someone else.
- Refinement is not done all at once in the Sprint Planning meeting, and it has no fixed adjustment point. It is an ongoing activity.
- When an item is vague and has no acceptance criteria, ask the Product Owner to add them during refinement. Do not wait for the daily coordination meeting, the Sprint Review or the retrospective to deal with it.
- The Sprint Backlog belongs to the Developers and the tasks are divided by the Developers themselves (members can pick them up as the team agrees). The Product Owner does not assign tasks.
- A new request during the Sprint goes into the Product Backlog first. It is not written straight into the Sprint Backlog.
- An urgent change during the Sprint is not handled by working overtime or by passing it to another team. It is re-evaluated with the Product Owner.
Lesson 3: The Increment and Technical Debt
- Increment = the items done in this Sprint that meet the Definition of Done + earlier Increments, and it must be usable.
- Every Sprint should produce an inspectable Increment. That it is potentially releasable is a technical matter; the actual release timing and authorization are decided by the Product Owner with the relevant stakeholders on the basis of value and organizational governance.
- Technical debt can come from deliberately adopting stopgap solutions to hit a deadline or from a lack of understanding; a change in requirements or the technical environment counts only when it exposes a shortcoming in the existing solution and creates extra repair cost. It is paid back later with extra effort, commonly through refactoring.
- Skipping tests and reviews to hurry is one common source of technical debt.
- Make technical debt visible: put it in the Product Backlog as items, assess the impact, then order it and pay it down.
- An Increment is not “how much was done” but “the part that is done and usable”. Anything that does not meet the Definition of Done does not count toward it.
- The items selected at the start of the Sprint are a plan (a forecast). The Sprint Goal is a one-sentence statement and is also the commitment attached to the Sprint Backlog, and the task list is the result of breaking the work down. None of the three is the Increment.
- An Increment that meets the Definition of Done must be usable and potentially releasable, but that does not mean it has already been delivered or released. The Product Owner works with the relevant stakeholders to decide the actual release timing and authorization on the basis of product value, following organizational governance.
- Technical debt does not disappear because nobody mentions it. Invisible debt cannot be ordered, and so it cannot be paid.
- Handling technical debt does not mean “put everything at top priority”, and it does not mean inflating story points to “reserve” time. First assess the impact, then have the Product Owner order it.
Definition of Done
Lesson 1: The Definition of Done: Meaning, Acceptance Criteria and the Definition of Ready
- The Definition of Done is a checklist the team creates jointly and everyone shares. The work is done only when every item is met.
- Whether an Increment is done depends on whether it meets the Definition of Done. Formal acceptance by stakeholders or the Product Owner's release decision are separate activities and do not change its done status.
- The definition of ready governs the time before a Sprint, acceptance criteria govern a single story, and the Definition of Done governs all Increments.
- Acceptance criteria only need to be settled before development starts. There is no need to write them for all stories at release planning.
- An item that does not meet the Definition of Done is honestly reported at the review and goes back to the Product Backlog. If needed the Developers update the estimate, and the Product Owner reorders it.
- The Definition of Done is adjusted by the team, commonly at the retrospective. The project manager does not set it unilaterally.
- Whether an Increment is done is judged by the Definition of Done. It is not judged by the definition of ready, and it is not decided by the timebox ending or the meeting finishing.
- If an item that is about to enter a Sprint lacks acceptance criteria, the team can include “acceptance criteria are clear enough” in its definition of ready and settle them through refinement or Sprint Planning before the item is selected. Whether this must come before estimating is for the team to agree (the definition of ready is not a mandatory artifact in the Scrum Guide).
- Acceptance criteria apply to a specific deliverable or Product Backlog item (usually a single story when user stories are used), while the Definition of Done is the general quality standard for all work items and Increments. Both must be met.
- Functionally complete does not mean done. If the technical work is not finished, the Definition of Done is not met and the gap cannot be ignored.
- When it is not met, do not cover it up and do not blame individuals. Say so honestly at the review and put the item back in the backlog.
Lesson 2: The Definition of Done and Quality
- Building quality in: make the quality requirements and acceptance criteria clear first, and in agile also use the Definition of Done to set the level of completion every Increment must reach, then safeguard quality with testing and inspection.
- Shifting testing left and test-driven development let defects be found early and while they are small.
- When defects rise: find the root cause first, involve the testers, and address the identified cause. Improve the Definition of Done or the team's working agreements when the analysis shows that the corresponding content is missing or unclear.
- When there is not enough testing time: split the stories smaller so that testing runs throughout the Sprint, instead of cutting people or slowing down.
- Performance, security and other non-functional requirements are identified first and brought into the requirements or the backlog: general ones go into the Definition of Done, specific-story ones into acceptance criteria, and both are checked in the relevant Sprint.
- Skipping testing or reviews to go faster creates technical debt and eventually slows the team down.
- An item that does not meet the Definition of Done cannot be “handed over first and fixed later”. It does not count as an Increment and goes back to the Product Backlog.
- When defects increase, look for the root cause first. If the root cause is that completion criteria are missing or unclear, then add the quality activities to the Definition of Done. Do not respond with overtime, added headcount or blaming individuals.
- If the organization already has a standard for the Definition of Done, the Scrum Team follows at least that standard; otherwise the Scrum Team creates one jointly, and the project manager does not set it unilaterally. The team can keep improving it based on inspection results, and the retrospective is a common occasion to adjust it.
- Do not leave non-functional requirements until the end: general requirements go into the Definition of Done, requirements for a particular story go into that story's acceptance criteria, and both are checked in the relevant Sprint.
Scrum Events
Lesson 1: The Sprint: A Fixed-Length Timebox
- A Sprint is a fixed-length event of one month or less, commonly 1 to 4 weeks, and it ends on time.
- The Sprint Goal does not change. New ideas go into the Product Backlog and are ordered by the Product Owner, normally for a later Sprint. If the Sprint Goal is not endangered, the Developers may negotiate the scope of the current Sprint with the Product Owner, but the timebox is never extended.
- Unfinished items are not part of the Increment. They return to the backlog, the Product Owner reorders them, and estimates are updated if necessary.
- Only the Product Owner can cancel a Sprint, and only when the Sprint Goal has lost its meaning.
- When something threatens the Sprint Goal, surface it early and transparently, negotiate scope changes with the Product Owner, and inform the relevant stakeholders in proportion to the impact.
- The Sprint length is "one fixed value", not "flexible between 1 and 4 weeks". A Sprint also cannot be extended for a new feature or out of goodwill toward the customer.
- If work is not going to be finished, you cannot extend the timebox. Surface and handle impediments promptly; the Developers may negotiate scope with the Product Owner as long as the Sprint Goal is not endangered, and items that have not met the Definition of Done at the end go back to the Product Backlog. Overtime is not a standard remedy, and whether to change staffing depends on the team's circumstances.
- Only the Product Owner can cancel a Sprint. The team, the Scrum Master and the project manager have no authority to stop one on their own.
- The reason for canceling is that the Sprint Goal has lost its meaning, not "we are behind schedule" or "someone wants to change direction".
- After unfinished items return to the backlog, update their estimates on the remaining work where necessary. Do not assume the old estimate still applies, and do not record "half" the points.
Lesson 2: Sprint Planning
- Sprint Planning addresses three topics: why the Sprint is valuable, what can be done, and how the chosen work will get done. As a common exam practice, a team may select stories, break them into tasks, and let members volunteer for tasks. The outputs are the Sprint Goal and the Sprint Backlog.
- The Product Owner proposes the value direction and is responsible for ordering the backlog. The Scrum Team defines the Sprint Goal together, and the Developers forecast and decide how many items to select.
- Past performance, including velocity when the team uses it consistently, is one important reference for assessing capacity. Forecast jointly from that evidence, upcoming capacity (vacation, training and similar factors), the Definition of Done, skill mix, dependencies and backlog readiness.
- For a one-month Sprint, Sprint Planning lasts at most 8 hours; for shorter Sprints it is usually shorter.
- Pressure caused by over-forecasting is solved at planning time by selecting only work the team is confident of finishing.
- When you find a cross-team dependency, tell the other team and confirm it has included the work in its plan.
- How much to select is forecast by the Developers based on their own capacity. It is not decided by the Product Owner, the project manager or the Scrum Master.
- Stories are selected by value and priority, not by difficulty or personal interest, and not to fill the Sprint to the top.
- If pressure comes from over-forecasting, select only work the team is confident of finishing during planning. Do not arrange stress-relief activities, add people or stagger vacations.
- Planning is about why the Sprint is valuable, what to do and how to do it. It is not necessary to settle each person's assignments in the meeting, and the team should not get lost in technical detail unrelated to planning. If the meeting drifts, the Scrum Master brings it back.
- An environment that was already set up in earlier Sprints is not counted again in this Sprint's capacity assessment. Past performance, including the velocity of past Sprints, is an important reference alongside current capacity and the Definition of Done.
Lesson 3: The Daily Scrum (Daily Coordination Meeting)
- The Daily Scrum: once every working day, 15 minutes or less, same time and place, managed by the Developers themselves.
- The three questions: what did I do yesterday, what will I do today, is anything blocking us.
- In the meeting, the focus is on synchronizing and adjusting the plan. Time-consuming discussion and problem solving are arranged separately afterward.
- The Scrum Master encourages self-management and does not call on people or hand out work. The Product Owner or Scrum Master attends as a Developer when working on Sprint Backlog items.
- After the meeting, update the Sprint Backlog according to the team's way of working, and update the task board, burndown chart and issue log as needed.
- When the team does not value the meeting, involve the team in improving it. Do not cancel or force it.
- The Daily Scrum is for synchronizing and surfacing impediments. It is not for assigning tasks, not for reporting to a manager, and not for detailed, time-consuming problem analysis (necessary short discussion and quick decisions can be done in the meeting).
- The Scrum Master makes sure the meeting takes place and may facilitate where needed, but does not call on people or hand out work, and does not turn the meeting into a roll-call report. The Developers manage the meeting themselves and decide its structure and techniques.
- Staying within 15 minutes does not by itself make a meeting a good one. The form can be compliant while the content is wrong.
- When the team does not value the meeting, involve the team in improving it. Do not cancel it, force it or punish people. The team agrees the meeting time itself.
- When a major risk or technical impediment comes up, raise it in the meeting and take the details offline afterward. Do not expand on it on the spot.
Lesson 4: The Sprint Review
- The Sprint Review is held at the end of the Sprint to demonstrate the Increment and get stakeholder feedback.
- Attendees: the Scrum Team plus internal and external stakeholders. Whether the Increment is done is judged against the Definition of Done, and the group inspects the results and discusses follow-up adjustments.
- Only work meeting the Definition of Done belongs to the Increment and can be presented; unfinished items are not presented and return to the backlog.
- For a one-month Sprint the review lasts at most 4 hours (Scrum Guide), and usually less for shorter Sprints. The review is a timeboxed event and is not postponed because work is unfinished.
- Review feedback may lead the Product Owner to adjust the Product Backlog and its ordering.
- The Sprint Review looks at what was done; the Sprint Retrospective looks at how the team works.
- The meeting for showing results is the Sprint Review, not a weekly update meeting, the Sprint Retrospective or the Daily Scrum.
- Only work meeting the Definition of Done can be presented as part of the Increment. Unfinished work is not presented; the team can explain its status, and it returns to the Product Backlog. The review must not turn into a progress briefing.
- The timebox does not move: do not extend the Sprint to make the demonstration complete, and do not cancel the review to hold the Sprint Retrospective first.
- If the Product Owner is absent, do not find someone to take over the role. Resolve the conflict early, and the Scrum Master makes sure the review proceeds effectively within the timebox. If there is disagreement about acceptance, first clarify it on the basis of the Definition of Done and the established authority.
- Feedback may lead the Product Owner to adjust the Product Backlog and its ordering. It does not change the current Sprint at will.
Lesson 5: The Sprint Retrospective
- The retrospective comes after the review and before the next planning, usually on the last day of the Sprint. For a one-month Sprint it lasts at most about 3 hours (set by the Scrum Guide).
- The retrospective looks at how the team works: summarize what went well and what did not, identify improvements, and decide what to implement (suitable ones go into the next Sprint).
- The whole Scrum Team attends. The Scrum Master is an equal participant and also helps the team use the meeting's rules well.
- Create a safe atmosphere that focuses on the issue, not the person. A timeline or emotion curve can build a shared picture.
- The results must be actionable: specific measures with owners assigned, the most impactful improvements implemented first, and suitable ones put into the next Sprint.
- Falling velocity, rework, process problems and the same problem recurring all point first to the retrospective.
- The retrospective changes process and collaboration, not product scope. Changes to product scope and ordering come from adjusting the Product Backlog after the Sprint Review.
- The retrospective comes after the Sprint Review and before the next Sprint Planning. It cannot be moved earlier or replace the review.
- Stakeholders' requirements are not relayed in the retrospective, and the Scrum Master does not attend on their behalf.
- Process problems the team can solve internally are usually analyzed first in the retrospective with the team. When a problem goes beyond the team's authority or meets the escalation criteria, escalate it promptly, using organizational process assets as needed. If an improvement affects a controlled baseline or a governance requirement, handle it through the change management process.
- The result of the retrospective should become action items that have an owner and can be checked. Discussion without follow-through is the same as not having held the meeting.
- Hold a retrospective in the closing phase even when there are no further Sprints.
User Stories
Lesson 1: User Story Format, Personas and Epic Decomposition
- A user story is a brief description from a stakeholder perspective, and a promise for a conversation to clarify details.
- Common format: As a [role], I want [goal], so that [benefit]. The benefit is the most important part.
- 3C: Card, Conversation, Confirmation. INVEST: Independent, Negotiable, Valuable, Estimable, Small, Testable.
- If stories for a key user group are missing, add to or correct the persona and collect the missing stories through interviews, workshops or story mapping.
- Split epics into stories and stories into tasks. Epics can be estimated roughly first; decompose and re-estimate before bringing an item into a near-term iteration, and slice vertically by value.
- Order of handling: put a newly identified need into the product backlog first, clarify it through continuing conversation, rewrite the story or acceptance criteria, and have the product owner reprioritize. Select it into a near-term iteration once it is clear enough and small enough.
- Writing a user story as a technical task ("create the orders table"): there is no role and no user value, so it is not a user story but a task split out of one.
- If a story does not match the customer's expectations, first clarify with the customer through conversation and then rewrite it. Do not first send people to training, change people or hand it over to a senior developer to rewrite.
- Words like "as fast as possible" and "friendly interface" make a story untestable. Turn them into quantifiable, verifiable acceptance criteria.
- If a big story cannot be finished, the answer is not to cut scope or ask the customer to simplify, but to split it small and deliver it incrementally over iterations.
- Decompose and re-estimate before bringing an item into a near-term iteration: an epic can be roughly estimated first, but a user story must be small enough to finish within one iteration and must not span iterations.
Lesson 2: Acceptance Criteria and Review for User Stories
- Acceptance criteria are the conditions a story must meet before it is accepted. For a user story, they apply to that story and are the Confirmation in the 3C; more generally they can apply to a deliverable.
- Write them as conditions that can be judged directly as yes or no, using numbers and observable behavior and no vague words.
- Setting acceptance criteria before coding and testing is the way to prevent missed testing.
- Completion is determined by the Definition of Done; in the Sprint Review, the Scrum Team and stakeholders jointly inspect the completed Increment, and the review is not an acceptance gate.
- When there is an objection to the Increment, first clarify expectations with the stakeholder, then rewrite the story, and order it in the product backlog.
- Do not write words like "friendly", "quickly" or "stable" in acceptance criteria, because they cannot be judged. Change them to numbers or observable behavior.
- Acceptance criteria are set before development, not added after coding and certainly not raised at the demonstration.
- The story-level acceptance criteria and the team's general definition of done must both be met. Neither replaces the other.
- When there is an objection in a review, first clarify the expectation through conversation. Do not immediately change the current iteration, and do not start a formal change request process. You still analyze the impact of the change, and the product owner reorders the backlog.
- A requirements traceability matrix cannot replace testable acceptance criteria and does not solve missed testing.
Story Points, Planning Poker and Velocity
Lesson 1: Story Points, Relative Estimating and Planning Poker
- A story point is a unit of relative effort or complexity, not absolute time, and not lines of code.
- Relative estimating: choose a reference story and agree its point value (the common practice is 1 point), and compare the others by multiples.
- Story points and velocity are each team's own scale; they cannot be compared between teams or used to appraise individuals.
- Estimating is done jointly by the developers, and the team understands the stories clearly before estimating.
- Planning poker: reveal at the same time; when the spread is large, the lowest and highest players explain first, then another round; no averaging.
- The key to wideband Delphi is independent estimating and several rounds of discussion that converge.
- Planning poker does not take an average; when the spread is large, first have the two extremes state their assumptions.
- Story points are each team's own relative scale. Velocity cannot be compared between teams or used to reward or appraise.
- Estimating is done jointly by the developers, not by the product owner, the Scrum Master, a business expert or another team on their behalf.
- Story points are not hours or days, and lines of code are not used either.
- Make sure the team understands every story first and then estimate; do not skip the discussion and go straight to playing cards.
Lesson 2: Velocity: Calculation, Stability and Forecasting
- Velocity = the story points completed and accepted within one iteration; what is unfinished or not accepted does not count.
- Forecast: remaining story points ÷ the average velocity of the last few iterations, rounded up.
- Velocity is not a performance target and need not rise every iteration; it settles into a relatively stable range only after several iterations, and forecasts use that recent range. It is used mainly by the same team to forecast from its own history and may be shown openly to stakeholders, but it is not used to compare teams or appraise individuals.
- A gap midway through an iteration: gap = planned amount − (completed + still able to complete); the developers negotiate with the product owner and, without endangering the iteration goal, adjust scope (the common exam practice is to move out low-priority stories).
- When velocity falls: first find the cause, improve in the retrospective, then negotiate with the product owner to adjust the plan, and stay transparent.
- Velocity counts only completed and accepted story points. Partial completion earns no credit, and the amount planned in is not velocity.
- Forecast with the average of the last few iterations, not the highest, lowest or best ever; round the number of iterations up.
- Steadier velocity is better; it does not have to be higher than the last iteration every time. It cannot be used to compare different teams or appraise individuals.
- When an iteration is running out of time: do not extend it, work overtime or add tasks; clear impediments and update the plan first. If scope truly has to be cut, the developers negotiate with the product owner and, without endangering the iteration goal, adjust the work (the common exam practice is to move out low-priority stories).
- When velocity falls, first look for the cause and improve in the retrospective; do not work overtime, add people, compress the iteration or change the estimate numbers.
Lesson 3: Spikes
- A spike is a quick experiment run when requirements or the technical approach are unclear and the work cannot be estimated.
- Three conditions: a timebox, a clear question, and knowledge rather than product as the output.
- When the experiment ends, the code is normally discarded, the knowledge is kept, and the team returns to the story to estimate and schedule it.
- It can be written as a spike story in the product backlog and ordered together with the other items.
- When the stem says “not sure”, “cannot estimate” or “technical feasibility unknown”, think spike.
- A spike is not iteration zero; both are common exam terms.
- The output of a spike is mainly knowledge and is normally not released directly as an increment; to keep a prototype, write a separate story and build it into a proper increment against the definition of done. It cannot be treated as a completed feature.
- When both requirements and technology are unclear, spike first and then develop formally; do not force an estimate or replace experiment with argument.
- A spike and iteration zero are not the same concept: iteration zero (a common exam term) is usually a preparation period at the start of a project or release and may include environment, infrastructure, an initial backlog, and initial architectural decisions. A spike is a time-limited exploration of a particular unknown with a clear learning goal and may be scheduled during iteration zero.
- A spike needs a timebox and a clear question; it is not open-ended “research”.
- When facing technical uncertainty, the product owner cannot decide alone, and the answer is not to ask a functional manager to assess it or to hold a meeting to discuss whether it “could in theory” improve efficiency.
Burndown Charts and Information Radiators
Formulas
- Ideal Burndown LineThe ideal line falls at a constant rate from the committed total to zero at the end of the timebox; actual remaining minus ideal remaining shows ahead or behind
Lesson 1: Reading Burndown and Burnup Charts: Remaining Work, Completed Work and Scope
- Burndown chart: time on the horizontal axis and remaining work on the vertical axis; compare with the ideal line to read the variance; actual above the ideal line means behind.
- Ideal line = selected total ÷ number of days as the daily decrease, falling from the selected total to zero.
- Only stories that meet the definition of done are deducted from the remaining work.
- Burnup chart: a cumulative completed line plus a total scope line; remaining = total scope − cumulative completed.
- Choose a burnup chart when scope can change and a burndown chart for an iteration with stable scope; an iteration chart covers one iteration, and a release-level chart covers the whole release.
- A burndown chart shows “how much is left” and goes down; an earned value curve shows completed work in terms of the authorized budget and accumulates upward. When the stem asks about “remaining work”, the answer is the burndown chart.
- An iteration burndown chart covers one iteration only and cannot be used to answer how much of the whole release remains.
- A burndown line going up does not necessarily mean the team has slowed down; scope may have increased, so find the cause first.
- A half-done story is not deducted from the remaining work; only a story that meets the definition of done is.
- When you need to separate progress from scope change, prefer the burnup chart; a burndown chart shows only the net remaining amount.
Lesson 2: Forecasting Progress with Charts, Making Decisions, and Information Radiators
- Look at the trend, not a single day; when the line goes up, first find the cause: new requirements, underestimated stories or more defects.
- Forecasting within an iteration: use the daily completion rate of the last few days to work out the remaining days and compare it with the timebox.
- Release forecast: remaining story points ÷ velocity, rounded up.
- When behind, negotiate early: within an iteration do not extend the iteration and, without endangering the iteration goal, negotiate scope adjustment with the product owner; negotiate release scope or date only when the release is behind; no overtime.
- Information radiators are usually low tech and high touch and should be easy to update and updated frequently; displaying progress openly reduces dependence on lengthy status reports, with formal reports alongside where needed.
- Deciding that the team's capability has degraded and arranging a performance review just because velocity falls is wrong. Velocity goes up and down. Find the cause first; it is used only for the team's own forecasting.
- When behind, do not work overtime and do not wait until delivery is near; negotiate early. Within an iteration, do not extend the iteration; without endangering the iteration goal, negotiate scope adjustment with the product owner. Negotiate an adjustment to release scope or date only when the release is behind.
- Ordering the product backlog is the product owner's responsibility (after hearing stakeholders). Scope adjustment within an iteration is negotiated by the developers and the product owner; the agile coach and the project manager do not cut it for them.
- To forecast whether an iteration will be completed, use the iteration burndown trend line; at release level use the release burndown trend line. Neither uses SPI or CPI.
- PMBOK 8 says an information radiator is usually a low-tech physical display maintained by hand rather than generated electronically, so there is no need to chase an electronic dashboard; what matters is that it is prominent and updated promptly, not technically advanced.
- When a stakeholder wants to see progress and an information radiator can meet their communication need, steer them to look at it first; when the communication management plan, governance requirements or their preference calls for a formal status report, still provide one.
Release Planning and Prioritization
Formulas
- Average VelocityOnly accepted stories count; usually expressed in story points completed per iteration
- Iterations NeededRound up when whole iterations are needed to deliver
Lesson 1: From Vision to Iteration Plan: Planning Levels, the Product Roadmap and the Planning Onion
- A vision answers why, how success is defined and how to tell when the team is drifting; it is developed by the team and key stakeholders together.
- During initiation and early planning, the vision, the product roadmap and the product backlog can be built up gradually; which artifacts are used is tailored to the project context.
- The onion from the outside in: product vision, product roadmap, release plan, iteration plan, daily plan.
- A roadmap is a high-level timeline, often in quarters, for management and investors.
- When the vision changes, after clarifying, assessing the impact and confirming within governance authority, bring the team together in a synchronous meeting so it understands, and the relevant roles adjust the backlog and the plans.
- When the vision changes, do not blast out an email, and do not have the lead change the plan and then notify people. Make sure the team understands face to face, and then have the Product Owner and the Developers adjust the backlog and plans within their respective responsibilities.
- A roadmap is not a release plan: the roadmap is coarse, long term and for management; the release plan is detailed, short term and for the team.
- Agile does not mean no plans; it means planning in layers on a rolling basis: the vision is the coarsest and the daily plan the finest.
- A vision is not the same document as a project charter: a vision is more inspiring, and a charter is more explicit and concrete; the two can also be combined.
- Before creating a roadmap, the product vision must exist first.
Lesson 2: Agile Release Planning: Forecasting a Release with Velocity
- A release plan is a timeline on the scale of a few months that sets the number of iterations in the release cycle and roughly predicts which features each iteration may deliver (which stories are actually selected is decided at iteration planning).
- The release plan sets the number and rhythm of iterations, and the iteration plan arranges the specific features; a common practice is to estimate features in story points and tasks in hours.
- Iterations needed = remaining story points ÷ velocity, rounded up; with a fixed date, deliverable amount = velocity × number of iterations.
- Give a range using the lowest and highest velocity, arrange the most important part first, and keep updating the forecast with actual velocity; the lower end of the range is not a guarantee.
- Deliver the minimum marketable feature first (a common exam term); when velocity falls short of expectations, revise the release plan by actual velocity.
- A release plan is not a contract and not an exhaustive specification; it is a rough, adjustable plan. When requirements change often, do not go down to a daily level. Commitments get coarser the further out they are: go broad first and become specific as uncertainty falls. Each team decides how many iterations to commit to according to its own velocity and confidence, so when two teams commit to different numbers of iterations, you cannot compare them one to one.
- An iteration is not a release: a release contains several iterations, an iteration produces an increment, and a release is handing it to users.
- The common practice is story points for features (stories) and hours for tasks; estimates at the same level should use consistent units, and you should not mix units in a single calculation.
- Velocity is a team-specific forecasting metric; velocities of different teams cannot be compared directly, and velocity should not be used as a performance appraisal measure.
- When velocity is not enough, adjust the release plan to fit actual velocity; do not work overtime or run more stories at the same time.
- When whole iterations are needed for delivery, round the number of iterations up; convert to dates by the iteration rhythm, and give a forecast range when there is enough data.
Lesson 3: Prioritization: Value, Cost, Risk and Common Methods
- Ordering combines value, dependencies, and technical or operational risk, weighed together with cost or effort; the purpose is to deliver the most valuable part first.
- MoSCoW has four classes: must have, should have, could have and will not have; Kano analysis centers on must-be, performance and delighter attributes, with indifferent and reverse as two more (the attribute classes are a common exam term).
- The 100-point method orders by total points; cost of delay (common exam practice is cost of delay ÷ duration, larger first; PMBOK 8 lists only the method name).
- When velocity is limited: deliverable amount = velocity × remaining iterations; fill by priority and move the rest out.
- For priority disagreements or new requirements, go to the product owner and reorder with value data; do not jump the queue or decide unilaterally.
- The ordering basis in PMBOK 8 is value, dependencies, and technical or operational risk (in practice cost or effort can also be weighed); it is not how convenient something is to build or whose voice is loudest.
- When velocity is not enough, focus on ordering by value; do not add people, work overtime or squeeze estimates.
- Do not treat “do the easy ones first” as priority; items that can be finished quickly are not necessarily of high value.
- A feature with low value but high risk should not be put first just because of the risk (except foundational work that threatens feasibility or compliance).
- Planning poker is an estimating technique, SMART is goal setting, and cause-and-effect diagrams find root causes; none of them is an ordering method.
Lesson 4: Agile Risk Management: Risks in the Backlog
- Risk response work can go into the product backlog as items, ordered with the features, forming a risk-adjusted backlog.
- In iteration planning, add risk-based iteration tasks for high-risk stories.
- The usual order of the quadrants (a common exam practice, not a fixed rule): high value, high risk; high value, low risk; low value, low risk; low value, high risk (avoid unless it is foundational work that must be dealt with).
- Risk score = probability × impact; the risk burndown chart tracks the sum over all items over time.
- Use the information radiator and the daily coordination meeting to keep risk visible.
- “Do high risk first” has a precondition: the item also has fairly high value. A low-value, high-risk feature should not move to the front just because it is high risk.
- Risk response work can go into the backlog as items just like features; it does not need a separate document.
- High-risk items should be validated or dealt with early, not left for discussion at the retrospective; whether they go into the current iteration is decided by weighing value, capacity, dependencies and risk.
- High-value, high-risk goes first; low-value, high-risk does not go first.
- A risk burndown chart tracks risk exposure (common exam practice is the total of probability times impact), not how many response actions have been completed.
- A technology choice should be decided by the appropriate roles and the team together, weighing value, architectural constraints and risk; using proven technology, trying a new one or changing the approach can each be a reasonable risk response.
Kanban
Formulas
- Little’s LawHolds for stable flow with a consistent system boundary; counting only work in progress gives average cycle time; counting the backlog queue as part of the system (backlog + WIP) gives average lead time; throughput = work items completed per unit of time; it gives an average and cannot fix a pile-up at one step. For example, 20 items in progress and 5 finished a day: cycle time = 4 days; 6 items in progress plus 3 in the backlog at 3 items/day: cycle time = 6 ÷ 3 = 2 days, lead time = 9 ÷ 3 = 3 days
Lesson 1: Kanban Boards, Pull and WIP Limits
- The core features of the Kanban method: visualize the workflow, pull work through, and limit WIP.
- The kanban board: columns are states, left to right is the direction of flow, and a card's position is its status.
- Five steps to set up a board: list the day-to-day work, lay out the board, set limits on the columns that need control, agree the definition of done, and agree whether to hold a short meeting and how often (a daily coordination meeting can be used to move cards face to face).
- Signs of a bottleneck: WIP in this column is at its limit and finished items are piled up in the column upstream. The response is swarming, not raising the limit.
- Average time = WIP ÷ throughput (count only work in progress for cycle time; add the backlog for lead time). To shorten it, either reduce WIP or raise throughput.
- Equating Kanban with electronic task software is a mistake: the value lies in a visible process and limited parallel work; the tool is only a carrier.
- When a column is full, temporarily raising the limit or removing it gives up the point of having a limit. What needs solving is the bottleneck, not the number.
- Agile teams emphasize cross-functional collaboration and encourage members to broaden their skills, so developers with the right skills helping Test is normal agile practice.
- A WIP limit is not swarming: the first puts a cap on quantity, the second is everyone working together on the same work item.
- Little's Law gives an average. It cannot fix a pile-up at one step; pile-ups are handled by setting limits.
Lesson 2: Cumulative Flow Diagrams, Cycle Time vs. Lead Time, and Kanban vs. Scrum
- Cumulative flow diagram: time on the horizontal axis, cumulative count on the vertical axis, one band per state. Read WIP vertically, time horizontally, throughput from the completion-line slope, and other state-entry rates from their boundary-line slopes.
- Cycle time: from start to completion. Lead time: from put on the board to delivery. In a steady state, cycle time = WIP ÷ throughput.
- A widening in-progress band = completion slower than starts = a pile-up. Stop new intake immediately, setting or enforcing a WIP limit if needed; if the limit is already effective, diagnose why work is stuck.
- Kanban is based on flow, with no fixed iterations and continuous delivery. Scrum is based on iterations, with timeboxes and three defined accountabilities.
- For work with hard-to-predict demand, such as operations and service support, consider Kanban first.
- A cumulative flow diagram shows the cumulative amount in each state. A burndown chart shows what remains, a burnup chart shows work completed against scope, and a value stream map shows the work and waiting time at each step.
- Cycle time counts from "started work"; lead time counts from "put on the board". Do not mix them up.
- A widening band is a signal of pile-up. Stop new work from entering the full state; set or enforce a WIP limit if needed, then diagnose the blockage. Do not start by adding people or lengthening the timebox.
- A Kanban team holding a daily meeting does not make Kanban Scrum. Kanban itself does not require iterations, the Sprint Review and Retrospective, or that fixed rhythm (a team may add a fixed rhythm itself, or combine Kanban with Scrum Sprints).
- Service-type work whose demand arrives at any time suits Kanban. In Scrum the Scrum Team collaboratively defines a Sprint Goal at Sprint Planning, with the Developers selecting Product Backlog items through discussion with the Product Owner, and no change that would endanger the Sprint Goal is made during the Sprint, although scope may still be clarified and renegotiated with the Product Owner as more is learned.
Lean
Lesson 1: Lean Thinking: the Seven Principles, the Seven Wastes and Value Stream Mapping
- Waste: an activity that consumes resources and/or time without adding value. Lean means finding and eliminating it.
- The seven lean principles for software: eliminate waste, amplify learning, decide as late as possible, deliver as fast as possible, empower the team, build quality in, see the whole.
- The seven wastes: overproduction, waiting, transportation, over-processing, inventory, motion, defects.
- Value stream map: the process steps plus the time each takes, used to identify waiting and other waste.
- Process efficiency = value-adding time ÷ total time. In the worked example only, all processing time is assumed to be value-adding. Waiting time is the improvement focus.
- "Make decisions as early as possible" is not a lean principle. Lean stresses deciding once enough information is in hand and delaying irreversible decisions, but this is not procrastination or avoiding decisions. For a "which one is NOT correct" question, this is the one to catch.
- A value stream map shows where the process has waste. A burndown chart and a burnup chart show progress, and earned value shows schedule and cost performance. Do not mix them up.
- A value stream map does not just add up working time; it is used to identify waiting, rework and other forms of waste.
- Waiting between activities cannot all be eliminated, but it should be reduced by improving the process.
- Lean advocates delaying irreversible decisions, not deciding early.
- Lean is a philosophy and a set of principles; the value stream map is one of its tools.
Lesson 2: How Lean, Kanban and Scrum Relate
- Lean is a philosophy, Kanban is a method based on lean principles, Scrum is an iteration-based framework, and Extreme Programming particularly emphasizes engineering practices.
- Kanban: visualize, limit WIP, deliver continuously. Scrum: fixed timeboxes, three accountabilities and five events.
- Lean scheduling: bring work in only when there is capacity, and limit queues by pulling.
- When a column is full, do not put in new items for now. Clear the bottleneck first and do not raise the limit.
- The two can be combined: use a kanban board to manage tasks inside a Scrum Sprint.
- Lean is a philosophy, Kanban is a method and Scrum is a framework. They are not at the same level, so do not ask "lean or Kanban?".
- Kanban is based on lean principles but is not the same as lean. The value stream map and visual controls are lean tools.
- Scrum sets its rhythm with fixed-timebox Sprints; limiting work in progress is not its core.
- Extreme Programming particularly emphasizes engineering practices, though it also contains rhythm practices such as small releases and the planning game. Waterfall is not continuous delivery.
- When the bottleneck column is full, stop putting in new items. Do not raise or remove the limit.
Extreme Programming
Lesson 1: Extreme Programming: the Twelve Practices
- XP is an agile method from the technical point of view and often uses short iterations of 1 to 2 weeks. Scrum manages the project rhythm; XP manages engineering practices.
- The twelve practices: planning game, small releases, system metaphor, simple design, test-driven development, refactoring, pair programming, collective ownership, continuous integration, 40-hour week, on-site customer, coding standards.
- The four high-frequency ones: test-driven development, pair programming, refactoring, continuous integration.
- Unique to XP: "slack". Add extra low-priority stories, and drop them first if time runs over.
- XP periodically inspects its practices, culture and goals, in order to improve continuously and make the team more effective.
- Extreme Programming does not mean overtime: a 40-hour week; if overtime is truly necessary, one week now and then is acceptable, but not a second week in a row.
- Scrum does not prescribe how to write code; XP does. The two can be used together.
- "Slack" is a practice XP names explicitly and that the Scrum framework itself does not prescribe; timeboxes, iteration planning, respect and courage are also found in Scrum.
- Periodically inspecting practices, culture and goals is continuous improvement. It is not gathering material for a particular retrospective, and it is not tracing the cause of a particular defect.
- Feature-Driven Development, the Dynamic Systems Development Method and Crystal are not XP practices.
Lesson 2: XP Technical Practices: Test-Driven Development, Refactoring, Pair Programming and Continuous Integration
- Test-driven development: write a failing test first, then just enough code, then tidy up once it passes.
- Refactoring: change only the internal structure, not external behavior, to reduce complexity and technical debt. It needs test protection.
- Pair programming: two people at one computer, real-time code review, knowledge transfer. Partners are self-organized and can rotate.
- Continuous integration: merge and test automatically as soon as each small piece is written, to find problems early. Only with a continuous delivery pipeline can it be deployed at any time.
- Simple design: meet only the needs in front of you and reduce redundancy.
- Refactoring does not add new features and does not fix defects. Anything that changes external behavior is not refactoring.
- "When should code be merged once it is written?" The answer is immediately, not at the end of the iteration and not after all the features are done.
- Continuous integration is not continuous delivery or continuous release. It keeps code integrated frequently, and only together with a continuous delivery pipeline can it be deployed at any time; whether to release is a business decision.
- The pairing partners in pair programming are decided by the team and swap freely. The project manager does not assign or fix them.
- For a skill gap, consider first using pair programming to transfer knowledge while working (common exam practice), rather than re-estimating or switching to easy tasks. You should still choose mentoring, coaching, training or another way of sharing knowledge according to the nature of the gap.
Lesson 3: XP Team Practices: Collective Ownership, Sustainable Pace, the On-Site Customer and Coding Standards
- Collective ownership: anyone can change any code, everyone is responsible for all the code, paired with coding standards.
- 40-hour week: sustainable pace. If overtime is truly necessary one week, there must not be overtime the next.
- On-site customer: a real user who contributes is on the team, answers questions full time, and feedback is always at hand.
- Osmotic communication: co-located work, with information flowing without effort.
- Scrum provides a framework of accountabilities, events and artifacts for product development; XP provides more specific software development, planning and team collaboration practices; Kanban manages flow. The three can be used together.
- Osmotic communication comes from co-location, not from pair programming, refactoring or test-driven development.
- Collective ownership does not mean no one is responsible; it means everyone is responsible, and it must be paired with coding standards.
- Sustainable pace does not favor overtime week after week. Overtime is not an agile way to speed up.
- The on-site customer is a real user on the team who can actually contribute, not a customer representative who occasionally attends reviews.
- XP is not a replacement for Scrum. They divide the work differently and are often used together.