PMP Cheat Sheet: Procurement
The key points and common traps of 14 lessons in 4 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.
Make-or-Buy Analysis and Procurement Planning
Lesson 1: Plan Sourcing Strategy and Make-or-Buy Analysis
- PMBOK 8 has no separate procurement performance domain; of the 40 processes only Plan Sourcing Strategy (Governance performance domain) deals directly with procurement.
- The three stages in Appendix X4: identifying the procurement needs and planning (which involves the procurement strategy), conducting the procurements, and monitoring and controlling procurements (including closing out contracts).
- First establish procurement policies, procedures, guidelines and legal parameters; the pre-approved seller list and contract templates are organizational process asset inputs; market research is a common data-gathering tool and technique.
- Make-or-buy analysis: choose whichever option gives better value, counting both direct and indirect costs, and weighing skills, risk and long-term employment obligations.
- Lease-or-buy break-even: daily lease × days = purchase price + daily maintenance × days; below the break-even number of days, lease.
- The project manager acts for the buyer, taking part in evaluating sellers and giving opinions, and does not sign an agreement without explicit organizational authorization.
- The make-or-buy analysis takes place before the decision to outsource; the procurement statement of work and bid documents used for buying are usually prepared after the decision to buy has been made.
- When comparing costs, include indirect costs and continuing expenses such as maintenance and labor, not just the purchase price.
- The result of the analysis is a decision, not a document; the decision is recorded in the procurement strategy or sourcing strategy plan.
- The project manager takes part in evaluating sellers and gives opinions; without explicit authorization, the project manager does not sign legally binding contracts or give final approval.
- Acquire Resources and Monitor and Control Resourcing are processes for team, physical and virtual resources, not procurement process names.
Lesson 2: Source Selection Analysis, Selection Criteria and the Procurement Management Plan
- Six selection methods: least cost, qualifications only, quality-based/highest technical proposal score, quality and cost based, single source, fixed budget; match them by recognition keywords.
- Put the evaluation method into the bid documents and set the selection criteria before the bid documents go out; getting key stakeholders' agreement in advance is common exam practice.
- The procurement strategy settles three things: delivery method, type of agreement and how the procurement phases advance.
- The procurement management plan is a component of the project management plan and records roles and responsibilities, timetable, risk issues, independent estimates, jurisdiction and more.
- The procurement management plan should cover all relevant procurement activities and be coordinated with the project schedule and the procurement phases; the contract term should cover the corresponding procurement needs, and who approves the plan follows the project governance arrangements.
- The procurement management plan guides “how to procure”; it does not describe “what to procure”. The statement of work describes what is procured.
- To find out who is responsible for outsourcing and each party’s duties, look at the procurement management plan. The communications management plan and the stakeholder engagement plan do not record procurement responsibilities.
- If several proposals cannot be ranked objectively against criteria, the selection criteria may not have been set in advance (if all fall short of the minimum requirements, the tender is canceled or reissued as procurement governance provides). A list of pre-qualified sellers only narrows who is invited; it does not replace scoring criteria.
- If the procurement management plan has not considered the risks that sellers bring, add the risk management items to the plan and assess whether a performance bond or insurance is needed.
Lesson 3: Bid Documents, the Statement of Work and the Independent Cost Estimate
- The three types of bid document to master in this lesson, which are also the most common: an RFI collects market information, an RFQ compares prices, an RFP asks for a solution.
- The SOW is based on the scope baseline and prepared for each procurement, stating specifications, quantities, quality, performance, period of performance and location; it ends up incorporated into the agreement.
- In a dispute, check all components of the signed agreement, including the SOW incorporated in the contract, and follow the contract’s document-precedence and dispute-resolution clauses; a seller’s internal requirements document that was not incorporated into the contract usually cannot be relied on.
- The independent cost estimate is the benchmark for testing whether quotes are reasonable; when the gap is large, check the SOW and the seller’s understanding first.
- Compare quotes on life cycle cost, not only the purchase price.
- The statement of work describes what is being procured; the procurement management plan describes how it is procured.
- The SOW exists before the bid documents go out; you do not issue the bid documents first and write the SOW afterward. The bid documents contain the SOW.
- An RFI mainly collects market information and is not used to solicit formal quotes or select a seller directly; an RFQ compares prices; an RFP asks for a solution.
- The independent cost estimate is a benchmark, not a scoring sheet; scoring uses the source selection criteria.
- The bidder conference takes place before sellers submit proposals; it is not used to test quotes.
Contract Types
Formulas
- FPIF: Final ProfitCommon exam practice: first determine whether actual cost is above the PTA; the difference in brackets is positive for a saving and negative for an overrun; the sharing ratio is written buyer/seller, for example 80/20; above the PTA the price is capped and the seller bears the whole overrun. For example, target cost 100, target profit 10, ceiling price 120, 80/20: at actual cost 90 profit = 10 + 20% × 10 = 12; at actual cost 125 profit = 120 − 125 = −5
- FPIF: Final PriceCommon exam practice: first determine whether actual cost is above the PTA, then apply the sharing ratio; If the calculated price exceeds the ceiling price, the ceiling price is paid (once actual cost passes the PTA the seller bears the whole overrun)
- Point of Total Assumption (PTA)Common exam practice; The actual cost at which the price just reaches the ceiling price; target price = target cost + target profit; use the buyer's sharing ratio as a decimal or percentage; first determine whether actual cost is above the PTA, then decide between the sharing ratio and the ceiling price; for example target cost 100, target price 110, ceiling price 120, buyer 80%: PTA = 100 + 10 ÷ 0.8 = 112.5
- CPFF: Final PaymentThe fee never changes; any extra cost is borne by the buyer
- CPIF: Final FeeIf the contract sets a minimum and maximum fee, limit the calculated fee to between them; do not assume limits the question does not give
- CPIF: Buyer's Final PaymentThere is no ceiling price; the buyer's total payment rises with actual cost
Lesson 1: Contract Types Overview and How to Choose
- The four fundamental models in PMBOK 8: fixed-price, cost-reimbursable, time and materials, and target-cost contracts; hybrid contracts also exist in practice, and combining types within a single procurement is common exam practice.
- The seven subtypes: FFP, FPIF, FP-EPA, CPFF, CPIF, CPAF, T&M.
- Choose the type on three points: whether requirements are clear, whether changes are likely, and who carries the risk.
- In the fixed-price family the seller carries the risk and in the cost-reimbursable family the buyer does; time and materials has features of both, and without a cap the total can keep rising.
- The project manager must be able to view a contract from the client’s side and from the contractor’s side.
- A fixed-price contract does not leave the buyer “with no risk at all”: if scope is unclear, or the seller defaults or goes bankrupt, the buyer still bears the consequences.
- A cost-reimbursable contract does not let the seller “spend freely”: the contract usually requires cost documentation and the buyer has to monitor costs.
- Time and materials and cost-reimbursable are easy to confuse. Settling at agreed hourly rates or material unit prices, with the amount of work uncertain, usually points to time and materials; reimbursing actual allowable costs plus a fee, with uncertain scope or higher risk, usually points to cost-reimbursable. In common exam practice, look at the pricing method in the stem: pay by the person-day rate, choose time and materials; actual cost plus fee, choose cost-reimbursable.
- “A time-and-materials contract has a capped total” is wrong unless the contract adds a cap.
Lesson 2: Fixed-Price Contracts: FFP, FPIF and FP-EPA
- Fixed-price contracts: the seller carries the cost risk and the buyer’s budget is certain; under FFP the seller carries the most risk.
- FPIF: final profit = target profit + seller’s sharing ratio × (target cost − actual cost); final price = actual cost + final profit, not above the ceiling price.
- PTA = target cost + (ceiling price − target price) ÷ buyer’s sharing ratio; beyond the PTA the seller bears the overrun alone.
- FP-EPA is for long-term procurements with fluctuating prices, adjusting the fixed price by an agreed index.
- Always check after calculating: price minus cost equals profit, and the price does not exceed the ceiling price.
- When the ratio is written “80/20”, first find out who gets the 80%. It is normally written buyer/seller; if the stem says “the seller bears 20%”, multiply the difference by 20%.
- FPIF profit can be negative: when actual cost is above the ceiling price, the seller takes a loss.
- Beyond the PTA, costs are no longer shared by ratio and the price is the ceiling price. First decide which side of the PTA the actual cost falls on, then pick the formula.
- Do not confuse FPIF with CPIF. FPIF has a price ceiling; CPIF’s fee may be bounded by a minimum and a maximum if the contract sets them, and the buyer’s payment has no fixed ceiling.
- If the scope has not changed and the contract has no cost-sharing or price-adjustment mechanism, an overrun that the seller caused by underestimating the quantities falls on the seller and a request for extra money is refused; this most likely points to a firm fixed-price contract. Under FPIF, before the PTA the buyer still shares, by ratio, the part above target cost.
Lesson 3: Cost-Reimbursable, Time-and-Materials and Target-Cost Contracts
- CPFF: payment = actual cost + fixed fee. CPIF: fee = target fee + seller’s ratio × (target cost − actual cost), held between the minimum and maximum fee if the contract sets them. CPAF: the award is decided subjectively by the buyer.
- In a cost-reimbursable contract the buyer carries the cost risk and has to monitor costs.
- Time and materials: pay for actual hours and materials at unit prices agreed in advance; without a cap the total rises with usage; it suits cases where the SOW cannot be written but the staff are known, small projects and consulting.
- Target-cost contract: a target cost is set and the way savings and overruns are shared is specified.
- Common exam practice: unclear requirements, unclear trades and settlement by actual cost plus fee, choose cost-reimbursable; SOW cannot be written, trades known and settlement by unit price, choose time and materials.
- For the buyer, CPFF and CPIF usually have no final total price fixed in advance; the payment varies with reimbursable actual cost and keeps rising when costs overrun, so costs must be monitored (if the contract sets a separate cost or payment cap, follow the contract terms). A cost-reimbursable contract lowers the seller’s financial risk.
- When scope is unclear, either may apply: if hours, materials or resource unit prices can be agreed and settled by actual quantity, consider time and materials; if settlement is by actual cost plus a fee and the buyer carries more of the cost risk, consider cost-reimbursable. On a question, go by the pricing and risk-allocation terms in the stem.
- Once a contract is signed and the budget is overrunning, the project manager cannot change the contract type unilaterally, nor refuse payments without verifying them. Do a performance review first to confirm that fees are reasonable, reimbursable and documented, then handle payment through the contract’s change or dispute procedure.
- An incentive has objective rules and an award rests on the buyer’s subjective evaluation; do not mix up CPIF and CPAF.
Lesson 4: Contract Types, Risk and Finance, and New Trends in Contracting
- When costs overrun: under FFP the seller bears all; under CPFF the buyer bears all; under FPIF the risk is shared by ratio up to the PTA and borne by the seller alone beyond it. When costs are saved, the seller retains the benefit under FFP, the buyer receives the benefit under CPFF, and the parties share it by the agreed ratio under FPIF.
- Under a fixed-price contract the buyer’s budget is certain and the price contains a risk premium; under a cost-reimbursable contract the buyer has to monitor costs.
- With the scope as agreed, the buyer’s payment under FFP is fixed (the final payment under FPIF varies with the incentive calculation but is limited by the ceiling price, and FP-EPA adjusts the price by the agreed economic price adjustment mechanism); under a cost-reimbursable contract the buyer re-forecasts EAC from the seller’s cost performance.
- Adaptive projects often use time-and-materials or cost-reimbursable arrangements paid by iteration or milestone; scope adjustments already agreed in the contract follow its mechanism, and changes beyond the established mechanisms, capacity or approved budget go through contract change control.
- New trends: agile contracting, smart contracts, outcome-based contracts, sustainable contracts, collaborative contracts; integrated project delivery (IPD) is a collaborative delivery method.
- Under a fixed-price contract, if the customer on an agile project wants to add scope, you cannot simply accept it without adjusting the contract; go through change control or trade off priorities.
- Do not think that once “risk is transferred” you can stop managing it: if the seller defaults, goes bankrupt or the scope is unclear, the buyer still bears the consequences, and also pays a risk premium for the transfer.
- A cap on a time-and-materials contract only limits the buyer’s payment risk. What happens once the cap is reached (the seller absorbs the excess cost, stops work, or the buyer separately approves more) depends on the contract terms. A cost cap does not itself adjust the two sides’ gains and losses by how fast delivery happens, so it does not solve a problem of unsettled design and a limited schedule; this differs from collaborative contracting, where the cap, performance incentives and risk sharing are designed together.
- An early-cancellation option serves both sides’ interests through the termination fee, and a dynamic scope option serves flexibility and the seller’s risk through scope swaps within a fixed budget; but neither directly addresses design uncertainty or delivery deadline risk, so do not choose them in that scenario.
Conducting the Procurements
Lesson 1: Conducting the Procurements: Inputs, Seller Proposals and the Bidder Conference
- Conducting the procurements: obtain responses, evaluate, select the seller, award the contract; the core is transparency, fairness and equal treatment of all potential sellers.
- Flow: bid documents, bidder conference, proposals, evaluation, negotiation, agreement; the dividing line is proposal submission.
- Inputs: procurement documentation, bid documents, SOW, independent cost estimate, source selection criteria.
- Whether price and technical proposals are evaluated separately follows the bid documents and the selection method; under a quality-based method, technical first and financial afterward.
- Bidder conference: before proposals are submitted, with all qualified or invited potential sellers having equal opportunity to attend and get clarifications; questions and clarifications are communicated in writing and consistently to everyone; if a clarification changes the bid documents, a formal amendment is issued under the procurement rules.
- Advertising is used to widen the list of potential sellers.
- The bidder conference is held after the bid documents go out and before proposals are submitted; no bidder conference is held after proposals are submitted, though during evaluation controlled clarifications can still be run uniformly under the bid documents and procurement rules (see the next point).
- Meeting suppliers separately cannot guarantee that the same information is conveyed, and it is not fair.
- If evaluation finds a defect in one proposal, handle it by the bid documents and procurement rules: where permitted, through a uniformly arranged clarification or revision (with no private coaching); where there is a material failure to respond, the proposal can be eliminated under the established criteria.
- Whether the price proposal and the technical proposal are evaluated separately depends on the bid documents and the source selection method; under quality-based and similar methods, the technical proposal is evaluated first and the financial proposal afterward.
- When procurement is running late, first find out why, assess the impact with the procurement team and prepare a recovery plan; escalate promptly if it exceeds your authority or reaches an escalation threshold (common exam practice: handle it first within your authority unless the stem shows it has gone beyond that authority or threshold).
- The project manager usually takes part in requirements, evaluation and negotiation support; the contract must be signed by someone the organization has formally authorized with signing authority (PMBOK 8: negotiations should be led by a procurement team member with contract signing authority), who may come from management or the procurement department, and legal review follows organizational rules.
Lesson 2: Evaluating Proposals: Weighting and Screening, and Procurement Negotiation
- Evaluation follows the source selection criteria set in advance; the criteria are fixed before the bid documents go out and are not changed midway.
- Weighting system: set weights for the criteria, rate each seller, multiply scores by weights and add up; the highest total ranks first and sets the negotiating sequence.
- Screening system (common exam practice): set minimum performance requirements and eliminate proposals that do not meet them; it can be combined with the weighting system and the independent estimate.
- Negotiation usually comes after the seller is selected and before signing; it clarifies the structure and the rights and obligations so both sides reach a shared understanding.
- The procurement team leads and the project manager assists; the project manager does not set prices or sign contracts alone.
- To choose objectively among several suppliers with different terms, the answer is to score by weighting against the source selection criteria, not to pick the cheapest or best-known one.
- The highest total score does not necessarily go into negotiation: proposals that failed the screening conditions have already been eliminated.
- Negotiation is usually after the seller is selected and before the contract is signed; do not confuse it with the bidder conference, which is before proposals are submitted.
- The project manager does not set prices or sign contracts alone; price questions are left to the procurement team to negotiate.
- The goal of negotiation is an agreement both sides can perform, not the lowest possible price.
Lesson 3: The Selected Seller and the Agreement
- The main result of conducting the procurements: selecting a suitable seller, completing contract negotiation and awarding the contract.
- For high-value, high-risk procurements the selection result may need approval from senior management or an appropriate governance body, following organizational policy and authorization thresholds (common exam practice/organizational authorization); several sellers can also be selected to spread risk.
- What an agreement contains: scope and quality, schedule, price and payment, liability and risk, change and termination.
- The force majeure clause can cover events such as earthquakes, war and tsunamis; whether it applies and the consequences depend on the contract terms and the applicable law.
- In a dispute look first at the contract and the documents it incorporates (for example the SOW the contract references); fill in missing clauses before signing.
- Paying in full before signing exposes the buyer to substantial risk; payment follows the contract’s payment terms and the state of acceptance.
- A longer contract is not a better contract; what matters is clear terms and clear rights and obligations. Writing only the total price and agreeing everything else during performance is a source of disputes.
- When the seller says a report costs extra, first check whether the contract or the statement of work requires it to be delivered; neither agree outright nor refuse outright.
- In a dispute, consult the complete contract documents and the attachments the contract expressly incorporates. A statement of work that is referenced in or incorporated into the contract has contractual force; a seller’s own requirements document that is not incorporated into the contract does not bind the parties.
Monitoring and Controlling Procurements
Lesson 1: Monitoring and Controlling Procurements: Purpose, Inputs and Procurement Changes
- Monitoring and controlling procurements: manage the procurement relationship, monitor contract performance, change and correct, and close the contract; everything goes by the contract.
- Three inputs: the agreement, procurement documentation and approved change requests. The procurement management plan sets out how the procurement is carried out and states the closure requirements.
- A change to the contract terms is recorded in writing and authorized under the contract and applicable law before it is carried out; an oral agreement that has not been recorded and authorized under the contract change procedure cannot justify a change in payment, and its legal effect depends on the contract and applicable law. Other procurement-related changes follow the development approach and change management arrangements the project uses.
- For a dispute, check the contract; for an external-party delay, talk to that party first. Then consult the statement of work as needed, assess the impact, and choose correction, a change or accountability.
- On a multi-seller project, coordinate communication among the sellers.
- A change proposed by the seller, even if it is free and even if it improves the result, should first be assessed whenever it affects the contract terms, the agreed deliverables, the project baselines or configuration-controlled items. It is handled under the contract change procedure and the change management arrangements the project uses. Do not approve it straight away, do not reject it straight away, and do not implement it first.
- When payment terms are fixed in the agreement, pay as the agreement says. Do not advance money on your own, and do not change the payment arrangement because the other party delivered early.
- Legal clauses in a contract are usually drafted by procurement or legal professionals. The project manager should take part in procurement planning and in the choice of contract type. Negotiation is led by procurement staff with signing authority, and the project manager can attend to help as needed. During performance, keep reviewing the seller's performance against the contract.
- In a dispute, look at the contract first. Do not escalate to your boss first and do not send a claim letter first.
Lesson 2: Performance Reviews, Inspections and Procurement Audits Compared
- A performance review reviews performance (during performance, against the agreement, using earned value and trend analysis); an inspection looks at deliverables; a procurement audit reviews the procurement process (common exam practice: mostly at contract closure).
- Agree performance standards with the supplier and record them in writing; compare with the contract, not with impressions.
- Earned value: CV = EV − AC, SV = EV − PV, CPI = EV ÷ AC, EAC = BAC ÷ CPI.
- The conclusions of a procurement audit go into the lessons learned register and organizational process assets.
- The quality of outsourced work is part of project quality management.
- A procurement audit reviews the buyer's procurement process, not one batch of the seller's products. Reviewing the seller's products is an inspection.
- Common exam practice: a procurement audit is mostly done at contract closure to sum up lessons learned; it does not replace a performance review in the middle of performance.
- A performance review compares with the requirements agreed in the contract, not with "the industry average" or oral promises made at bid time.
- The quality of outsourced work is also part of project quality management.
- For a supplier with poor quality, first find the cause and require correction as the contract provides; do not penalize or terminate immediately.
Lesson 3: Claims Administration and Alternative Dispute Resolution
- A contested change is called a claim; if unresolved, it may escalate under the contract's claims procedure into a dispute and potentially an appeal. A constructive change (a common exam term) is when the buyer's instruction or conduct leads the seller to do work outside the contract scope, and the seller then asks to be compensated.
- Common exam practice: negotiate first, then other dispute resolution methods (mediation, arbitration, a dispute review board, expert determination and so on), and litigation last; PMBOK 8 also lists negotiation as a type of ADR.
- Project manager: understand the contract, keep records, keep communicating, address conflict early, and work with the legal team.
- Legal sensitivity: be careful with written wording, set up an escalation protocol, keep confidentiality and stay impartial.
- For a dispute, review the whole contract and its component documents (including the statement of work and acceptance criteria it incorporates), and follow the claims and dispute resolution procedures the contract provides.
- In a dispute, look at the contract first. Do not escalate to your boss first and do not send a claim letter first.
- If negotiation gets no response, the next step is alternative dispute resolution, and only after that litigation. Do not skip levels.
- A claim rests on evidence: the actual results plus the standard agreed in the contract. You need both.
- Involve the procurement team and legal staff who know the contract. The project manager should not decide on the basis of an oral promise.
- A mediator does not make a decision; an arbitration award is binding.
Lesson 4: Closing Out Contracts and Early Termination
- Closing out a contract: first check that everything was delivered and accepted and that amounts due are paid, then settle open claims, guarantees, warranties and disputes under the contract and confirm that all contractual obligations have been met. The contract administrator notifies the seller in writing.
- Order: usually confirm formal acceptance first, then complete payment and any necessary approvals under the contract, and finally close formally; the contract terms and organizational governance decide the details. If a defect is not fixed, have the seller fix it as the contract provides before closing.
- Three situations of early termination (common exam practice): mutual agreement, one party's breach, and the buyer's convenience (the contract must provide for it).
- After termination: work that has been completed and accepted is paid for; on termination for convenience or where the contract says so, reasonable preparation costs are compensated; termination for the seller's breach does not automatically compensate (on termination for the buyer's breach, the seller may claim compensation under the contract and the law); a termination by agreement follows the termination agreement.
- Termination and replacing a supplier: the project manager first verifies the contract terms and authority, then has authorized procurement, legal or management staff get involved under the governance arrangements (common exam practice: when the question asks what to do "first" and "involve the procurement department" is an option, it is often chosen; if "check the contract's termination clause" is also an option, check the contract first; whether this applies depends on the stem). Archive the procurement documentation and put lessons learned into the knowledge repository.
- A contract reaching its end date does not mean it can be closed. Common exam practice: first check that the work has been delivered and accepted and the amounts due have been paid. You must also settle any open claims, guarantees, warranties and disputes under the contract and confirm that all contractual obligations have been met.
- When you find a defect, handle the final payment under the contract's acceptance and payment terms. As the contract provides, you may use measures such as retention, withholding the related payments, requiring a fix, warranty or a claim. Paying the final payment does not automatically end warranty and claim rights that survive under the contract.
- Fixing defects is already the supplier's obligation under the original contract. Do not sign a new contract or pay extra for it.
- After early termination, work that has been completed and accepted is paid as agreed. On termination for convenience, or where the contract says otherwise, the seller's reasonable preparatory work is compensated as agreed. Termination for the seller's breach does not automatically compensate the seller; on termination for the buyer's breach, the seller may claim compensation under the contract and the law.
- Archive the procurement documentation in full and put lessons learned in the repository; do not keep only the contract.