Make-or-Buy Analysis and Procurement Planning

PMP · Procurement · 3 lessons · about 35 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

Procurement means acquiring goods, services or results from outside the project. This chapter covers the first stage of procurement: identifying the procurement needs and planning for them, which is the first stage described in Appendix X4 (and involves the procurement strategy). It corresponds to the only PMBOK 8 process that deals directly with procurement, Plan Sourcing Strategy (Governance performance domain). The chapter works through these points: first decide which work to do in-house and which to buy; once you decide to buy, determine the method for selecting the seller, the criteria for scoring, how procurement will advance, and which documents to send to sellers. The next three chapters cover contract types, conducting the procurements, and monitoring and controlling procurements, in that order.

After this chapter you should be able to: describe the three stages of procurement and tell Acquire Resources apart from procurement; run a make-or-buy analysis and calculate the lease-or-buy break-even point and total cost including indirect costs; match the right source selection method to its recognition keywords and name the common selection criteria; list the main contents of the procurement management plan; and distinguish an RFI, RFQ and RFP and explain what the statement of work and the independent cost estimate are for.

Lessons in this chapter

Chapter knowledge map

Question to answerTool or documentLesson
Should we buy from outside?Make-or-buy analysis (cost, skills, risk)Lesson 1
Which method selects the seller?The six source selection analysis methodsLesson 2
What criteria do we score against?Source selection criteria (part of the weighting system)Lesson 2
How does procurement proceed, and who is responsible?Procurement strategy, procurement management planLesson 2
What are we buying?Statement of work (SOW)Lesson 3
What do we ask sellers for?RFI, RFQ, RFPLesson 3
Is the quote reasonable?Independent cost estimateLesson 3

Study tips and practice

  • Get the order straight: the make-or-buy analysis comes before the decision to outsource; the SOW and bid documents come after it.
  • Memorize the recognition keywords of the six selection methods. For calculations, remember two: the lease-or-buy break-even point, and total cost as direct plus indirect cost.
  • Common exam practice: “What should you do FIRST?” questions in this chapter mostly test preliminary actions such as checking procurement policy, setting selection criteria, or clarifying the SOW.
  • Acquire Resources and Monitor and Control Resourcing belong to the Resources performance domain and apply to team, physical and virtual resources. Do not use them to mean procurement activities.

Lesson 1

Plan Sourcing Strategy and Make-or-Buy Analysis

Lesson video

Lesson overview

Procurement is the acquisition of goods, services or results from outside the project. Before getting into procurement, the project manager has to answer an earlier question: should we buy this from outside at all? This lesson first explains how PMBOK 8 arranges procurement, then covers where Plan Sourcing Strategy fits and what goes into it, and finally covers make-or-buy analysis, including the lease-or-buy break-even point and the comparison of direct and indirect costs. ECO: Process domain, Task 5 (Plan and manage procurement), covering plan procurement and plan and manage the procurement strategy. The next two lessons cover source selection, the procurement management plan and bid documents.

How PMBOK 8 arranges procurement

PMBOK 8 does not treat procurement as a separate performance domain. The reason is that project procurement is typically integrated into, or extends from, the larger organization’s procurement department, using established processes, policies and vendor relationships, which ensures consistency across projects and allows for economies of scale. Of the 40 processes, only Plan Sourcing Strategy deals directly with procurement, and it sits in the Governance performance domain. Appendix X4 divides procurement into three stages: identifying the procurement needs and then planning for them (which involves the procurement strategy, see X4.4), conducting the procurements, and monitoring and controlling procurements, where the last stage includes closing out contracts.

Do not use Acquire Resources or Monitor and Control Resourcing for procurement

These are two processes in the Resources performance domain. Acquire Resources covers team members, physical resources and virtual resources; Monitor and Control Resourcing covers only physical and virtual resources, and team members are managed through the Lead the Team process. They are not names for procurement stages. When resources come from an external seller, the agreement, seller selection and contract performance all follow the three stages above.

Plan Sourcing Strategy: first ask whether to buy

PMBOK 8 describes the process this way: “The Plan Sourcing Strategy process entails documenting project sourcing decisions, specifying the source selection approach, determining the scope of work for external sourcing, and selecting the appropriate contracts and sources for delivering the work.” It establishes a clear framework for acquiring project deliverables, either from within the organization or from external sources, defining what to acquire, how to acquire it, and when to acquire it. Put simply: first answer “should we buy?”, then “what, how and when?”

First, turn the role around. In procurement questions the project manager usually represents the buyer, the organization that is purchasing. But in any organization of some size, signing contracts and taking legal responsibility on its behalf is normally done by people holding contract signing authority. That is often the procurement department, though it may be delegated to project team members or management. The project manager usually raises requirements, takes part in supplier evaluation, gives expert advice and supports negotiation; whether the project manager can sign a contract or give final approval depends on organizational policy and the contract authority explicitly granted, and without authorization no one may sign an agreement on the organization’s behalf. PMBOK 8 notes that participants in this process may include the purchasing or procurement department as well as personnel from the buying organization’s legal department, and that these responsibilities should be documented in the sourcing strategy plan.

A summary that is common exam practice: this planning step usually checks three kinds of organizational process assets. The first is the pre-approved seller list: sellers on the list have already been vetted, so repeated qualification work can be reduced and selection may take less time; whether any other bidding steps may be omitted depends on the organization's procurement policies and governance requirements. The second is procurement policies, procedures and guidelines: where the organization has no formal system, the team has to assemble the people and expertise to run the procurement itself. The third is contract templates, the standard texts for the three broad families of fixed-price, cost-reimbursable and time-and-materials contracts. A data-gathering technique that also applies is market research: learning about the industry as a whole and about what each seller can do and how well.

Key point

Common exam practice: on a question like “several suppliers want to work with you; what does the project manager do FIRST?”, first check the procurement policies, procedures, guidelines and legal parameters. Price lists, historical experience and the bill of materials come later, because until the framework is set, a negotiated price may not be compliant.

Make-or-buy analysis: choose the better value

A make-or-buy analysis is used to determine whether work or deliverables can best be accomplished by the project team or should be purchased from outside sources. The analysis looks at all relevant costs, direct and indirect; the result is a make-or-buy decision. Beyond cost, the factors PMBOK 8 lists are the organization’s current resource allocation, its skills and abilities, the need for specialized expertise, the desire to avoid expanding permanent employment obligations, and the need for independent expertise. The decision process also includes evaluating the risks involved with each make-or-buy decision.

Advantages of insourcing/makeAdvantages of outsourcing/buy
Leverages internal expertise when it is available internallyLeverages external expertise when it is missing internally
Is often less expensive if substantial new innovation is requiredIs often less expensive if the goods or services are common
Provides tighter integration with strategic advantage or value propositionFrees up capacity and capital to focus on competitive strengths
Increases control and oversight of deliverablesTransfers delivery risk to the supplier and maintains supplier relations

When you need to quantify, you can use payback period, return on investment (ROI), internal rate of return (IRR), net present value (NPV) and cost-benefit analysis; the calculations are in the Net Present Value lesson. The two calculations that appear most often on the exam follow.

How to do it: two worked examples

Example 1: lease or buy. A project needs a piece of testing equipment. Leasing costs $300 per day; buying costs $4,500 up front plus $120 per day for maintenance.

  1. Write the total costs: lease = 300n, buy = 4,500 + 120n, where n is the number of days of use.
  2. Set the two equal to find the break-even point: 300n = 4,500 + 120n, 180n = 4,500, n = 25 days.
  3. Decide: if use is under 25 days, lease; if over 25 days, buy.
  4. Check: at 18 days, leasing costs $5,400 and buying costs 4,500 + 2,160 = $6,660, so leasing is cheaper; at 40 days, leasing costs $12,000 and buying costs 4,500 + 4,800 = $9,300, so buying is cheaper; at 25 days both sides are $7,500, which agrees with the break-even point.
Figure 1: Break-even point between leasing and buying

Example 2: do not compare direct costs only. A packaging design job. If the team does it: labor $38,000, materials $12,000, plus $9,000 of allocated indirect cost for premises, management and so on. If outsourced: the seller quotes $52,000, and the buyer also bears $4,000 of management cost for acceptance and coordination and $2,000 for a performance bond.

  1. Total cost to make = 38 + 12 + 9 = $59,000.
  2. Total cost to buy = 52 + 4 + 2 = $58,000.
  3. Buying is $1,000 cheaper than making, so by “choose whichever option gives better value” the choice is to buy.
  4. Check: comparing direct costs only gives $50,000 to make against a $52,000 quote, the opposite conclusion. The conclusion is reliable only when indirect costs are added to both sides.

Worked examples

Example 1 (scenario question): several suppliers are eager to work with you; what do you do first?

Question 1Example

A supermarket chain’s store renovation project buys large quantities of shelving and light fixtures every week. Several suppliers want to work with the project, and the project manager is confident of negotiating a good price. The requirements, specifications, quantities and weekly delivery schedule are all settled. To get the best overall value from the future contract, what should the project manager do FIRST, before negotiating with the suppliers?

Show answer and explanation

Correct answer: A

A store renovation project buys shelving and light fixtures in large weekly volumes. The requirements, specifications, quantities and weekly delivery schedule are settled, and negotiation with suppliers has not started. The question asks what to do first before negotiating so that the future contract delivers the most value.

There are two signals: “the requirements are settled” and “FIRST, before negotiating”. The requirements analysis is done, so the next step is to confirm the boundaries within which the contract will be negotiated. The organization’s procurement policies, procedures and guidelines (organizational process assets) and the applicable legal parameters are the boundaries the contract must respect; external laws and regulations also have to be identified and complied with separately. Once these are clear, the bidding, negotiation and contract that follow are compliant, and a good price can be pursued inside that framework. Price lists and past experience are inputs you can use afterward. The answer is A.

Why the other options are wrong

  • B. Price is an important negotiating factor, but collecting price lists before you know the contract’s constraints may produce quotes that do not meet the rules; that comes later.
  • C. Past purchasing practice is only a reference. Every project’s needs and value differ, so start with this project’s constraints.
  • D. A time-phased bill of materials belongs to requirements analysis, and the stem says the requirements, quantities and delivery schedule are already settled, so this step is done.

Key takeaway Once requirements are settled and before negotiation, first establish the policies, procedures, guidelines and legal parameters the contract must follow, and then negotiate the price.

Variation If the requirements, specifications and quantities were not yet clear, you would first analyze the project’s needs thoroughly and determine the resources required, and only then deal with the compliance framework. If the question were how to shorten the time needed to select a seller, the answer would be the pre-approved seller list.

Something wrong with this question?

Report an issue with this question

Example 2 (scenario question): do it ourselves or outsource, and what comes first?

Question 2Example

An e-commerce company is setting up a customer service center for its promotion season and estimates that it needs 80 call agents: weekdays 9 a.m. to 6 p.m., and weekends 9 a.m. to 1 p.m. Management has not decided whether to hire the people itself or hand the work to an outside company. The project manager must provide a basis for this decision. Which of the following analyses should the project manager use?

Show answer and explanation

Correct answer: B

The project must set up a customer service center with a clear headcount, but it has not been decided whether to do it internally or outsource it. The question asks which analysis gives a basis for that decision.

The key information is that the headcount and shifts are settled but “hire ourselves or outsource” is not. For a decision about whether to do the work and who should do it, use make-or-buy analysis: it compares in-house hiring with outsourcing on cost, risk, skills and long-term employment obligations. The conclusion comes only after the analysis and is then written into the procurement strategy. None of the other three is a tool for deciding between making and buying. The answer is B.

Why the other options are wrong

  • A. Earned value analysis measures the performance of work already completed and needs actual performance data. The stem is about deciding whether to hire or outsource, and there is no completed work to measure.
  • C. Reserve analysis compares contingency reserves with the remaining risk to judge whether the reserve is enough. It is not a way of comparing in-house work with outsourcing.
  • D. Trend analysis looks at how performance changes over time to forecast what comes next. It too needs data that already exists and cannot decide between hiring and outsourcing.

Key takeaway To decide whether to do the work yourself or outsource it, compare the options with make-or-buy analysis, and then record the conclusion in the procurement strategy.

Variation If the stem said the analysis was finished and the conclusion was to outsource, the next step would be to prepare the statement of work. If it asked how to compare the costs of the two options, you would include indirect costs.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The make-or-buy analysis takes place before the decision to outsource; the procurement statement of work and bid documents used for buying are usually prepared after the decision to buy has been made.
  • When comparing costs, include indirect costs and continuing expenses such as maintenance and labor, not just the purchase price.
  • The result of the analysis is a decision, not a document; the decision is recorded in the procurement strategy or sourcing strategy plan.
  • The project manager takes part in evaluating sellers and gives opinions; without explicit authorization, the project manager does not sign legally binding contracts or give final approval.
  • Acquire Resources and Monitor and Control Resourcing are processes for team, physical and virtual resources, not procurement process names.

Key takeaways

Key point

  • PMBOK 8 has no separate procurement performance domain; of the 40 processes only Plan Sourcing Strategy (Governance performance domain) deals directly with procurement.
  • The three stages in Appendix X4: identifying the procurement needs and planning (which involves the procurement strategy), conducting the procurements, and monitoring and controlling procurements (including closing out contracts).
  • First establish procurement policies, procedures, guidelines and legal parameters; the pre-approved seller list and contract templates are organizational process asset inputs; market research is a common data-gathering tool and technique.
  • Make-or-buy analysis: choose whichever option gives better value, counting both direct and indirect costs, and weighing skills, risk and long-term employment obligations.
  • Lease-or-buy break-even: daily lease × days = purchase price + daily maintenance × days; below the break-even number of days, lease.
  • The project manager acts for the buyer, taking part in evaluating sellers and giving opinions, and does not sign an agreement without explicit organizational authorization.

Lesson 2

Source Selection Analysis, Selection Criteria and the Procurement Management Plan

Lesson video

Lesson overview

Once the make-or-buy conclusion is “buy”, three more things have to be settled in the planning stage: which method selects the seller, which criteria are used for scoring, and how the whole procurement will advance and be written into a plan. This lesson covers, in order, the six methods of source selection analysis, source selection criteria, the procurement strategy and the procurement management plan. ECO: Process domain, Task 5 (Plan and manage procurement), covering select the preferred contract type and plan and manage the procurement strategy. The next lesson covers bid documents and the independent cost estimate.

Source selection analysis: six methods

Source selection analysis settles, in the planning stage, which method will be used to select the seller. Competitive selection methods may require sellers to invest a large amount of time and resources up front, so it is good practice to include the evaluation method in the tender documents so that bidders know how they will be evaluated; this transparency also helps infuse stakeholder trust in the selection method. PMBOK 8 lists six commonly used methods:

MethodWhen it fitsKey point
Least costStandard or routine procurements where well-established practices exist and the outcome is well definedAvoid it for complex procurements, where it may negatively impact quality
Qualifications onlyThe value of the procurement is relatively small, so a full selection process does not make senseEstablish a short list and select the bidder with the strongest qualifications, expertise and references
Quality-based/highest technical proposal scoreEvaluate the technical proposal first; negotiate the financial proposal only if the technical proposal is acceptableThe seller with the highest ranked technical proposal is selected if its financial proposal can be negotiated and accepted
Quality and cost basedCost is one factor among several in the evaluationWhen risk and/or uncertainty are greater, quality should be a key element compared with cost
Single sourceOnly one supplier can satisfy the requirements, because of unique technical competence, patents or exclusive rightsNot an attempt to contract with a favored provider; used when no other options are available
Fixed budgetThe SOW is precisely defined, no changes are anticipated, and the budget is fixed and cannot be exceededThe available budget is disclosed to invited sellers; the highest ranking technical proposal within the budget is selected

These recognition keywords are a first clue (a common exam mapping), but judge by each method’s full conditions and by the priority of the competing demands: standard and routine points to least cost; small value to qualifications only; technical proposal evaluated first to quality-based; high risk where quality matters more to quality and cost based; only one supplier able to do it to single source; a budget that cannot be exceeded to fixed budget.

Source selection criteria

Source selection criteria are part of a weighting system that is used to score and rank all the proposals and to establish the negotiating sequence. The criteria may be a numerical score, a color code or a written description of how well the seller satisfies the buying organization’s needs. PMBOK 8 says the criteria may include but are not limited to: capability and capacity; product cost and life cycle cost; delivery dates; regulatory, compliance or industry standards expertise or experience; technical expertise and approach; specific relevant experience; adequacy of the proposed approach and work plan in responding to the SOW; key team members’ qualifications, availability and competences; financial stability of the firm; management experience; suitability of the knowledge transfer program, including training; and sustainability credentials of the supplier. For international projects, evaluation criteria may include “local content” requirements, for example including local personnel among the proposed key team members.

The criteria are set before the bid documents go out and are included in the bid documents, so that bidders know how they will be evaluated (X4.6); getting key stakeholders to agree to them in advance is common exam practice. Suppose that midway through the evaluation the sponsor asks you to add a supplier whose quote is lower but who does not necessarily meet the requirements. The project manager should neither add the supplier outright nor refuse outright. Instead, call a meeting and evaluate this supplier against the published selection criteria and procurement governance; if the criteria really do need adjusting, handle that through governance or the change procedure, so that the process stays fair and compliant (on the exam, “call a meeting and reach agreement with the sponsor” reflects this approach). Financial stability is listed as a criterion to reduce the risk of the seller going bankrupt or defaulting partway through.

Procurement strategy and the procurement management plan

Once the decision is made to acquire from outside the project, a procurement strategy should be identified. It answers three questions: which delivery method will be used, which type of legally binding agreement, and how the procurement will advance through the procurement phases. Delivery methods differ by the kind of work. For professional services they include buyer/services provider with no subcontracting, with subcontracting allowed, a joint venture between buyer and services provider, and buyer/services provider acting as the representative. For industrial, integration or build-out supply projects they include turnkey, design-build (DB), design-bid-build (DBB), design-build-operate (DBO), build-own-operate-transfer (BOOT), and others. PMBOK 8 adds integrated project delivery (IPD): a multiparty agreement involving all key stakeholders, shared risks and rewards based on project outcomes, early involvement of key participants, collaborative decision-making and open-book accounting.

Information on procurement phases may include: sequencing or phasing of the procurement, a description of each phase and its specific objectives; procurement performance indicators and milestones used in monitoring; criteria for moving from phase to phase; a monitoring and evaluation plan for tracking progress; and a process for knowledge transfer for use in subsequent phases.

The procurement management plan is a component of the project management plan that describes how a team will acquire goods and services from outside of the performing organization, and it contains the activities to be undertaken during the procurement process. It can be formal or informal, and as detailed or broad as the project needs. It may include guidance on: coordination of procurement with other aspects of the project; the timetable of key procurement activities; procurement metrics for managing the contracts; the roles and responsibilities of stakeholders involved in procurement, including the authority and constraints between the team and the procurement department; constraints and assumptions; pre-qualified sellers to be used; risk management issues, including performance bonds or insurance contracts; whether to prepare independent estimates and use them as evaluation criteria; and the jurisdiction and the currency of payment.

Scenario: the contract term does not cover all the work. On a company's 30-month software modernization project, a consulting firm won the bid, but the buyer signed a contract for only 12 months, and the remaining 18 months had to be re-tendered. The buyer's procurement management plan and procurement strategy had not provided for the later phases, the contract term did not cover the corresponding procurement needs, and the term and phasing had not been confirmed through the applicable governance arrangements. A phased procurement management plan, prepared in advance to cover all relevant procurement activities and confirmed as governance requires, would have exposed the gap early.

Common trap

  • The procurement management plan guides “how to procure”; it does not describe “what to procure”. The statement of work describes what is procured.
  • To find out who is responsible for outsourcing and each party’s duties, look at the procurement management plan. The communications management plan and the stakeholder engagement plan do not record procurement responsibilities.
  • If several proposals cannot be ranked objectively against criteria, the selection criteria may not have been set in advance (if all fall short of the minimum requirements, the tender is canceled or reissued as procurement governance provides). A list of pre-qualified sellers only narrows who is invited; it does not replace scoring criteria.
  • If the procurement management plan has not considered the risks that sellers bring, add the risk management items to the plan and assess whether a performance bond or insurance is needed.

Worked examples

Example 1 (scenario question): several bids received but no winner can be chosen

Question 1Example

An agricultural machinery company plans to develop an intelligent irrigation control system, and the project manager decides to outsource the development to a more experienced supplier. After the bid documents are issued, several bids come in. The project manager analyzed them on technical merit and quality and still cannot decide who should win the contract. What document should the project manager have prepared in advance to avoid this?

Show answer and explanation

Correct answer: D

The decision to outsource has been made and the bid documents issued, and several bids have come in, but no winner can be selected. The question asks what document should have been prepared in advance.

The signal: several bids received, technical and quality aspects analyzed, and still no winner. What is missing is a common basis for judgment, not information. Source selection criteria are part of a weighting system, are set before the bid documents are issued, and are used to score and rank all proposals and to establish the negotiating sequence; they can cover technical, quality, cost, financial stability and more. Preparing them in advance gives the evaluation a framework. The answer is D.

Why the other options are wrong

  • A. The statement of work describes the products, services or results to be procured so that sellers know what is being bought. It does not provide criteria for scoring sellers.
  • B. The procurement management plan guides how procurement is carried out. It does not contain the specific criteria for scoring sellers item by item.
  • C. A list of pre-qualified sellers narrows who is invited. The sellers on the list still have to be compared using criteria.

Key takeaway If you cannot select a seller, the usual cause is that source selection criteria were not set in advance.

Variation If the stem said the sponsor asked midway through evaluation to add a low-price supplier, the answer would be to call a meeting and evaluate the supplier against the published selection criteria and procurement governance with the sponsor; if it said only one supplier holds the patent, that points to the single source method.

Something wrong with this question?

Report an issue with this question

Example 2 (scenario question): the contract term does not cover all the work

Question 2Example

A company launches a 30-month software modernization project. After a fiercely competitive procurement, a consulting firm wins the contract. The company sponsor asks the buyer's project manager why the contract with the consulting firm was signed for only 12 months and does not cover the full 30 months. The project manager finds that an unplanned second tender is needed to keep the service going until the project ends. To avoid this, what should the project manager have done?

Show answer and explanation

Correct answer: D

The contract term covers only part of the project, so an unplanned second tender is needed. The question asks what should have been done beforehand to avoid it.

The signal is a buyer-side 30-month project covered by only a 12-month contract, followed by an unplanned re-tender. The procurement management plan did not cover all relevant procurement needs and key procurement activities across the project life cycle, and the contract term and phasing were not confirmed through the applicable governance arrangements. Preparing a phased procurement management plan covering all relevant procurement activities and obtaining the required governance confirmation would expose the gap early. The other options are either after-the-fact fixes or unrelated to the problem. The answer is D.

Why the other options are wrong

  • A. The client can take part in key decisions, but having it join every round of negotiation and approve in advance is unnecessary and does not ensure the plan covers all the work.
  • B. Negotiating the second contract only after the first is signed is a remedy after the problem arises. It prevents nothing, and it presumes the project continues with this firm.
  • C. Agreeing on how often to report is only a communications arrangement. It has nothing to do with the contract term being too short.

Key takeaway The procurement management plan should cover the procurement needs, required contract periods and key procurement activities over the whole project life cycle and be reviewed by the relevant stakeholders under the project's governance arrangements; that is how to avoid an unplanned second tender.

Variation If the stem asked who is responsible for outsourcing and what their duties are, the answer would still be the procurement management plan; if it asked for a detailed description of the item procured, the answer would be the statement of work.

Something wrong with this question?

Report an issue with this question

Common traps

What each of three “plan-type” documents does

  • Procurement management plan: how procurement is carried out, who is responsible and when.
  • Procurement strategy: delivery method, type of agreement and how the procurement phases advance; it is one of the bases for the procurement management plan.
  • Source selection criteria: how sellers are scored; they cover only “who to select”.

Key takeaways

Key point

  • Six selection methods: least cost, qualifications only, quality-based/highest technical proposal score, quality and cost based, single source, fixed budget; match them by recognition keywords.
  • Put the evaluation method into the bid documents and set the selection criteria before the bid documents go out; getting key stakeholders' agreement in advance is common exam practice.
  • The procurement strategy settles three things: delivery method, type of agreement and how the procurement phases advance.
  • The procurement management plan is a component of the project management plan and records roles and responsibilities, timetable, risk issues, independent estimates, jurisdiction and more.
  • The procurement management plan should cover all relevant procurement activities and be coordinated with the project schedule and the procurement phases; the contract term should cover the corresponding procurement needs, and who approves the plan follows the project governance arrangements.

Lesson 3

Bid Documents, the Statement of Work and the Independent Cost Estimate

Lesson video

Lesson overview

After the decision to buy and the choice of selection method and criteria, the planning stage still has to spell out what is being bought and prepare the documents that ask sellers to respond. This lesson covers three documents: the bid documents (RFI, RFQ, RFP), the statement of work (SOW) and the independent estimate (the term used in the PMBOK 8 procurement management plan, commonly called the independent cost estimate), and what each does later in evaluation, contracting and disputes. The next chapter covers contract types, after which come the procurements themselves. ECO: Process domain, Task 5 (Plan and manage procurement), covering plan procurement.

Bid documents: RFI, RFQ and RFP

Bid documents are used to solicit responses from potential sellers. When sellers are selected mainly on price (for commercial or standard items), terms such as “bid”, “tender” and “quote” are common; when selection is mainly on technical ability or approach, the term “proposal” is common. The bid process includes developing and publicizing bid documents, bidder conferences and selecting a bidder. The three common types of bid document are:

DocumentWhen to use itWhat the buyer wants
Request for information (RFI)To gather more information from the market before sending out bid documents to a set of selected vendorsTo learn which approaches and suppliers exist
Request for quote (RFQ)Price is the main deciding factor and the proposed solution is readily availableA price for a ready-made solution
Request for proposal (RFP)The project has a complex or complicated scope and the buyer is looking for the vendor to provide a solutionThe vendor proposes a solution and a price

Another common form is the invitation for bids (IFB), also called an invitation to tender (ITT), which in the procurement overview is listed alongside the RFP; for this lesson, concentrate on the three above. Procurement documents should include the required response format, the relevant statement of work and any required contract provisions.

The statement of work: spell out what you are buying

The statement of work (SOW) is based on the project scope baseline and is prepared separately for each procurement, covering only the portion of scope that will be included in that contract. It must be detailed enough for a potential seller to judge whether it can supply the item, and it usually states specifications, quantities, quality levels, performance measures, period of performance, work location and other requirements. For service procurements the term “terms of reference” (TOR) is also commonly used.

The SOW can be revised and refined during the procurement process and ends up incorporated into the agreement the two parties sign, becoming part of it. So if buyer and seller later disagree over scope, quality or acceptance criteria, the contract and the SOW are what you check. It is the buyer’s document, and through bidding and negotiation it enters the contract and has legal force. A seller’s own requirements document is an internal project document of the seller; unless it is incorporated into or referenced by the contract, it usually cannot stand alone as the basis of the parties’ rights and obligations (whether it is binding depends on the signed agreement and the documents it incorporates), and it is not something the buyer supplies to the seller.

If requirements are vague, different sellers will understand them differently and their quotes cannot be compared. If you find the requirements vague before the bid documents are prepared, clarify the SOW first and then issue it; do not count on the bidders to interpret it for themselves.

The independent cost estimate: do not be led by the quotes

The buyer can prepare an independent estimate itself, or hire an outside professional estimator to do it (also called an independent cost estimate; the two names are used interchangeably below), as a benchmark for judging whether a seller’s quote is reasonable. On a large procurement, you can break the equipment down into components and price them one by one to arrive at a price range you are confident in; once the proposals arrive, use it to test whether the quotes sit at a reasonable market level.

What does it mean when a quote differs markedly from the independent estimate? The SOW may be deficient or unclear, or the seller may have misunderstood it or not fully responded to it. Note that a markedly low quote does not mean the buyer will necessarily save a lot of money.

Worked example: comparing quotes with the independent estimate. The buyer’s independent estimate for a batch of server components is $2,000,000. Three sellers quote: A $1,920,000, B $2,050,000, C $1,300,000.

  1. Using $2,000,000 as the benchmark, A is 4% lower and B is 2.5% higher, small deviations (suppose the organization’s rule is that anything within ±5% of the independent estimate is a normal review range; both are inside it).
  2. C is 35% lower, a marked difference.
  3. Do not select C outright, and do not eliminate it outright. First find out why: did it leave out installation or warranty, did it misunderstand the performance measures in the SOW, or is the SOW itself vague?
  4. Check: (2,000,000 − 1,300,000) ÷ 2,000,000 = 35%, (2,000,000 − 1,920,000) ÷ 2,000,000 = 4%, (2,050,000 − 2,000,000) ÷ 2,000,000 = 2.5%.

Quotes should also be compared on life cycle cost. Equipment A sells for $500,000 with a lifetime warranty; equipment B sells for $200,000 with a one-year warranty, and after that each replacement part costs $100,000. If B is expected to need three replacements during the rest of its service life after the warranty ends, B’s total cost is 200 + 300 = $500,000, the same as A, and the buyer also carries the risk of downtime. A low price does not mean a low cost.

Worked examples

Example 1 (concept question): which document spells out the system’s functions, measures and delivery date?

Question 1Example

A food company plans to upgrade its cold storage management system. After assessing its internal capabilities, it finds that no one in-house has the necessary skills and decides to outsource. The project manager is now putting together a document that spells out what functions the system must have, what the performance measures are and when it is due, so that interested suppliers can judge whether they can take the job on. Which of the following is this document?

Show answer and explanation

Correct answer: C

The project has decided to outsource and is in the sourcing planning stage. The question asks which deliverable the project manager is preparing.

The signals: outsourcing has been decided; the document states functions, performance measures and delivery time; its purpose is to let suppliers judge whether they can take the job on. This is the statement of work: prepared for this procurement from the scope baseline, it describes the product, service or result to be procured in enough detail for a seller to judge whether it can supply it, and it ends up incorporated into the agreement. The answer is C.

Why the other options are wrong

  • A. Make-or-buy analysis happens before the decision to outsource and decides whether to do the work in-house or outsource it. Here outsourcing has already been decided.
  • B. The procurement management plan guides how procurement is carried out. It is not a detailed description of the item procured.
  • D. Bid documents ask sellers for proposals and are issued after the statement of work is prepared, and they contain it.

Key takeaway Once outsourcing is decided, spell out what is being bought in a statement of work.

Variation If the stem said “decide whether to do it ourselves or outsource”, that would be make-or-buy analysis; “a document asking sellers for proposals” would be bid documents; “how procurement is carried out” would be the procurement management plan. The “management plan” option describes how to procure, not what to procure, and this is the most common confusion.

Something wrong with this question?

Report an issue with this question

Example 2 (technique question): how do you judge whether a quote is reasonable?

Question 2Example

A project manager at PMLyceum is in charge of a large project. After a make-or-buy analysis, the team decides to buy a batch of standard components. After the request for quote is issued, quotes arrive from several sellers. What should the project manager use to judge whether the quotes are reasonable?

Show answer and explanation

Correct answer: B

The make-or-buy analysis is done, the request for quote has been issued and the sellers’ quotes have been received. The question asks what to use to test whether the quotes are reasonable.

The signals: the decision to buy is made, the quotes are in, and the core task is “judging whether the quotes are reasonable”. To judge that you need a price benchmark independent of the sellers: an independent estimate (the term in the PMBOK 8 procurement management plan; “independent cost estimate” is a common exam term) prepared by the buyer or by an outside estimator. Compare the quotes against it once they arrive; if the difference is marked, then check whether the statement of work is deficient and whether the seller misunderstood the requirements. The answer is B.

Why the other options are wrong

  • A. Proposal evaluation can assess responsiveness, price and other established criteria, but it is not itself an independent price benchmark for testing whether quotes are reasonable.
  • C. Expert judgment can be used to prepare an independent cost estimate, but it is not itself the benchmark for comparing quotes, and it is less directly tied to the stem than the independent cost estimate.
  • D. The bidder conference is held before sellers submit proposals, and the quotes have already been received.

Key takeaway The independent cost estimate is the buyer’s benchmark for testing whether the seller’s quote is reasonable.

Variation If a quote is far below the independent estimate, first check the statement of work and the seller’s understanding rather than assume it will save money; if the question asks how to make all bidders understand the same thing, the answer is the bidder conference.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The statement of work describes what is being procured; the procurement management plan describes how it is procured.
  • The SOW exists before the bid documents go out; you do not issue the bid documents first and write the SOW afterward. The bid documents contain the SOW.
  • An RFI mainly collects market information and is not used to solicit formal quotes or select a seller directly; an RFQ compares prices; an RFP asks for a solution.
  • The independent cost estimate is a benchmark, not a scoring sheet; scoring uses the source selection criteria.
  • The bidder conference takes place before sellers submit proposals; it is not used to test quotes.

Key takeaways

Key point

  • The three types of bid document to master in this lesson, which are also the most common: an RFI collects market information, an RFQ compares prices, an RFP asks for a solution.
  • The SOW is based on the scope baseline and prepared for each procurement, stating specifications, quantities, quality, performance, period of performance and location; it ends up incorporated into the agreement.
  • In a dispute, check all components of the signed agreement, including the SOW incorporated in the contract, and follow the contract’s document-precedence and dispute-resolution clauses; a seller’s internal requirements document that was not incorporated into the contract usually cannot be relied on.
  • The independent cost estimate is the benchmark for testing whether quotes are reasonable; when the gap is large, check the SOW and the seller’s understanding first.
  • Compare quotes on life cycle cost, not only the purchase price.

This chapter has 32 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.