Risk
Monitor Risks
PMP · Risk · 5 lessons · about 1 h
Part of the free PMP video course: every lesson starts with its video →
Once the risk response plan is settled, risk management is only half done. This chapter covers the second half: putting the plan into action (Implement Risk Responses) and keeping a close watch on how risks change (Monitor Risks). The first makes the planned actions actually happen; the second keeps risk management current for the whole life of the project. The final lesson deals with a frequent exam scenario: a risk has actually occurred, so what do you do?
What this chapter covers
As a project moves forward, the probability, impact, priority and owner of each risk keep changing, new risks keep appearing and old ones become obsolete. Identifying, analyzing, responding to and monitoring risks therefore has to be done in a cycle. This chapter covers the last two of the six processes in the PMBOK 8 Risk performance domain. It maps to ECO: Business Environment domain, Task 5 (Plan and manage risk), and to the part of Task 4 (Remove impediments and manage issues) about recognizing when a risk is turning into an issue. The chapter is mostly scenario questions, and almost every one asks “FIRST” or “NEXT”. The five lessons follow the sequence “carry out the actions, watch what changes, use the tools, review in meetings, and what to do when a risk occurs”, and all of them work from the same risk register.
Lessons in this chapter
- Lesson 1: Implementing risk responses. Carry out the agreed actions; use influence to move owners outside the team; when the trigger of an identified risk appears, take the response actions set out in the risk register; if the risk has become a real issue, bring it into issue management as well.
- Lesson 2: Monitor Risks: purpose, inputs and outputs. The five things the process does, the three kinds of finding, and “which document do you update FIRST?”.
- Lesson 3: Tools for monitoring risks. Technical performance analysis, reserve analysis (with a worked calculation) and risk audits; read the question to see whether it asks about technical results, reserves or process.
- Lesson 4: Risk review meetings and the watch list. The five things a risk reassessment covers, reviewing watch-list items and moving them into active response, and information radiators and risk burndown charts on adaptive projects.
- Lesson 5: After a risk occurs. The line between a risk and an issue, contingency reserve versus management reserve, and which path to take after an identified or an unidentified risk occurs.
Chapter map
The upper figure shows what to do depending on what you find; the lower figure shows how the routine turns day to day. Study in order and keep Lesson 5 for last as a summary. When you see a question in which “a risk has occurred”, first ask yourself “was it registered in advance?” and only then choose an answer.
Lesson 1
Implement Risk Responses: Making the Agreed Actions Happen
Lesson overview
However well a risk response plan is written, it is worth nothing if it is not carried out. This lesson covers the fifth of the six processes in the Risk performance domain: Implement Risk Responses. It maps to ECO: Business Environment domain, Task 5 (Plan and manage risk), in particular carrying out the risk management plan. Questions on this lesson are almost all scenarios, and the core question is always the same: a registered risk has occurred, or an agreed action has no one doing it, so what does the project manager do FIRST? The previous chapter (risk response strategies) settled what to do; this lesson is about getting it done; the next lesson covers Monitor Risks.
What Implement Risk Responses is
PMBOK 8 defines it this way: “Implement Risk Responses is the process of implementing sufficient risk response plans. The key benefit of this process is that it ensures that agreed-upon risk responses are executed as planned to address overall project risk exposure, minimize individual project threats, and maximize individual project opportunities.”
Three points matter. First, it is execution, not planning. The strategy, specific actions, owner and trigger conditions were already set in Plan Risk Responses and are usually recorded in the risk register. How reserves will be used is recorded in the risk management plan, and the reserve amount of money or time goes into the relevant budget, cost or schedule documents according to the project's practice. This process puts the agreed actions into effect; it does not plan them again. Second, it addresses individual risks and also overall project risk exposure (“an aggregate measure of the potential impact of all risks at any given point in time in a portfolio, program, or project”). Third, doing the action is implementation, while checking whether the action was done and whether it worked is Monitor Risks. Do not mix the two.
Inputs, tools and outputs
| Item | Content |
|---|---|
| Inputs | Project management plan (risk management plan); project documents (lessons learned register, risk register, risk report); organizational process assets |
| Tools and techniques | Expert judgment; interpersonal and team skills (influencing); project management information system |
| Outputs | Change requests; project document updates (issue log, lessons learned register, project team assignments, risk register, risk report) |
The risk register is the most direct basis: the risks, owners, strategies, specific actions and trigger conditions are all in it. The tool most often overlooked is influencing. Many actions have to be done by people outside the team (the procurement department chasing a delivery, operations freeing up a maintenance window, a supplier raising capacity). They have their own managers and priorities, so the project manager can only make the value clear and help resolve their conflicts, not give orders. Among the outputs, raise a change request when an action needs to change a baseline, or when switching strategy would affect a baseline or the project management plan. If only project documents such as the risk register and risk report are updated, a project document update is enough. Update the applicable project documents as needed: update the risk register when risk status or response information changes, the issue log when a risk has become an issue, project team assignments when membership, roles or responsibilities change, and the lessons learned register when there is reusable learning.
How to do it: four things that put the actions into effect
Confirm the owner. Every action has someone who has accepted it, that person knows it, and has the authority to do it; if not, delegate authority or change the person. Coordinate resource conflicts. The people and equipment an action needs are often tied up elsewhere, so negotiate with functional managers, adjust the time window and update the schedule (update the project team assignments only when team members, roles or responsibilities change as a result). Make the action requirements clear. State the action, the completion criterion and the deadline, such as “sign a framework agreement with the backup supplier by October 31, including delivery within 15 days”, not “handle it as soon as possible”. Drive the action forward. Coordinate people, resources and authority and remove obstacles during execution. Actions are easiest to postpone while the risk has not occurred, and this is the most common starting point of failed risk management. Checking periodically whether actions were done and whether they worked belongs to the next process, Monitor Risks, covered in the later lessons.
If an action is not working or the risk situation has changed, consider another strategy promptly. If the new strategy affects a baseline, it is itself a change and must go through the change process.
The first reaction when an identified risk occurs
Check the risk register first and carry out the agreed actions in it. If the register already holds an applicable agreed action, you normally follow it first; you do not need to identify and analyze the risk again from scratch, or call a meeting to find a response, because that was already done during planning. If the action is missing, ineffective, or the situation differs greatly from the original assumptions, then analyze the current situation, develop a new response and raise a change if needed. If contingency reserve is needed, handle it according to the reserve-use approach in the risk management plan and organizational authorization. If that reserve is already inside the approved baseline, using it as planned normally does not change the baseline; a change request is needed only when the action changes the baseline. Exam tip (common exam practice): unless the question gives other conditions, the project manager may use contingency reserve within the authority already established, while management reserve needs separate authorization and a change. An identified threat that occurs becomes an issue and is also recorded in the issue log. When an opportunity is realized, update the risk register and track its positive effect; if it creates a current situation that needs action or monitoring, record it in the issue log too, according to the project's practice. The order is: check the register, carry out the action, use contingency reserve if necessary, record in the issue log, and discuss change only if the action is ineffective.
On predictive projects, actions go into the schedule and team assignments, and their status comes up at status reviews. On adaptive projects, actions that suit the development team can become backlog items, selected into the iteration at iteration planning, with higher-risk items placed first; other actions still move forward through their owners and the relevant management mechanisms. On hybrid projects, handle each component separately but roll the status up into the same risk register.
Worked example: one action from the register to completion
On a sorting line project, the register lists the threat “imported servo motors arrive more than 3 weeks late”. The action is to reserve 6 equivalent models from a domestic backup supplier and sign a framework agreement. The procurement manager owns it, due May 20. At the weekly meeting on May 6, the project manager finds that the backup supplier wants a 30% prepayment and finance approval is not finished. The project manager does not push the procurement manager. Instead, the project manager explains to the finance manager that this payment is already set aside within the contingency reserve, and approval comes through two days later. The agreement is signed on May 18, the project manager updates the risk register and records in the lessons learned register “start prepayment approval one week earlier”. The imported motors later arrive 4 weeks late, the backup arrangement covers the gap and the schedule is only slightly affected. What the project manager did was check, coordinate, push the approval and record. The project manager did not analyze the risk again.
Worked examples
Example 1: An identified risk occurs. What do you do first?
An industrial equipment installation project is working on commissioning activities on the critical path. The risk register already records the risk “delayed arrival of the imported control module”, with agreed responses and an owner. Today the supplier announces that the module will arrive ten days late, and equipment delivery will slip as a result. What should the project manager do FIRST?
Show answer and explanation
Correct answer: D
Commissioning activities on the critical path are affected. The risk is already in the register, with agreed responses and an owner, and today it has been triggered (the supplier announces a ten-day delay). The question is what to do FIRST.
Three signals matter: the risk is registered, responses are agreed, and the risk has been triggered. So a ready-made response exists, and the first job is to have the owner carry out the actions right away to contain the impact. If a response calls for contingency reserve or a baseline change, handle that as part of the response, and follow up with status records afterward. Updating the register, logging an issue and raising a change request are supporting actions, not the first step. The answer is D.
Why the other options are wrong
- A. Even if the delivery date is affected, first carry out the agreed response to determine the residual impact. If that residual impact requires a controlled baseline to change, submit a change request under the change management plan.
- B. Marking the risk as occurred in the register is a supporting step, not the first action. Carry out the agreed response first, then record it in the issue log and update the register status.
- C. How contingency reserve is used is set out in the response plan. It is not a first step separate from the response; carry out the plan first, then draw on reserve as needed.
Key takeaway When a registered risk is triggered, carry out the response plan first; then log the issue, use reserve and raise change requests as needed.
Variation Remove “agreed responses”: if the risk has not yet occurred, the answer becomes plan the response and then implement it. If it has occurred and there is no prepared response, treat it as an issue, develop a workaround and record it in the issue log. If it is a risk that was never identified, the answer is to bring the team together to find a workaround. The difference is whether the risk was registered beforehand and whether a response was agreed.
Something wrong with this question?
Example 2: The owner does not act. How does the project manager get things moving?
At a risk review meeting for a warehouse management system project, the project manager asks each risk owner for a progress report and finds that several of them are not acting on the agreed response strategies. To reduce risk exposure, what should the project manager do?
Show answer and explanation
Correct answer: B
At a risk review meeting the project manager finds that several risk owners are not acting on the agreed strategies. The goal is to reduce risk exposure. How should the project manager move things forward?
“Not acting on the agreed strategies” shows that the responses have not been executed, but it does not yet establish why. Without knowing why, you cannot fix it: there may be a resource conflict, lack of authority or a technical obstacle, or the strategy itself may not hold up. The project manager should talk with the owners one on one, understand the obstacles and help resolve them. This is how a project manager uses influence to get responses carried out; only when the responses are actually in place does risk exposure really come down. The answer is B.
Why the other options are wrong
- A. Giving orders without understanding the obstacles leaves the blockage in place. The same thing will happen at the next meeting, so this treats the symptom, not the cause.
- C. Going straight to the sponsor and recommending removal skips the conversation and deals with the person instead. It does not get the responses carried out and it damages team relationships.
- D. Reassigning risks without knowing the cause just passes the same obstacle to someone else, and the owners have not agreed to it. The cause remains unresolved.
Key takeaway When a risk owner is not carrying out the response, first talk to find the obstacle and help resolve it; only then consider reassigning or escalating.
Variation If you learn that the strategy itself is not feasible, the answer becomes reassess and replace the strategy, raising a change request if needed. If the owner is outside the team, it is still communication and coordination, not an administrative order.
Something wrong with this question?
Common traps
Common trap
- A newly identified risk must first be analyzed and have a response planned before it is implemented; you cannot jump straight to implementation.
- When people outside the team carry out an action, influencing is the first choice and administrative orders are not; if the action stays blocked and the risk response is affected, escalate according to the escalation criteria.
- “Checking whether the action was carried out” is Monitor Risks; implementing is “doing it”.
- After an identified risk occurs, “call the team to discuss responses”, “brainstorm solutions” and “analyze the risk again” are usually distractors.
Key takeaways
Key point
- Implement Risk Responses means carrying out the agreed actions to minimize threats, maximize opportunities and address overall risk exposure.
- Inputs: risk management plan, risk register, risk report, lessons learned register, organizational process assets. Tools: expert judgment, influencing, project management information system. Outputs: change requests, project document updates.
- Four things put actions into effect: confirm the owner, coordinate resource conflicts, make the action requirements clear and drive the action forward (checking periodically whether it was done and whether it worked belongs to Monitor Risks).
- Owners outside the team are moved by influence: first understand the obstacle, then help remove it.
- When an identified risk occurs: check the register, carry out the action, and use contingency reserve if necessary under the risk management plan and your authorization (common exam practice: the project manager decides within the established authority; when the reserve is already in the baseline, the baseline does not change), and record it in the issue log.
- If an action is ineffective, consider another strategy; if it affects a baseline, go through change control.
Lesson 2
Monitor Risks: Purpose, Inputs and Outputs
Lesson overview
Planning, identifying, analyzing and responding are all done, yet risk management is not over: the project environment keeps changing, and so do the probability and impact of risks. Monitor Risks is the last process in the Risk performance domain, and it runs from initiation to closure. This lesson answers three questions: what the process does, what its inputs and outputs are, and what kinds of findings one round of monitoring turns up and which document each finding requires you to update. Exam questions come in two kinds: those asking “what should the project manager do” (keep monitoring, reassess), and those asking “which document do you update FIRST” (usually the risk register). ECO: Business Environment domain, Task 5 (Plan and manage risk), covering monitoring and controlling risks, maintaining the risk register and communicating the status of risk impacts on the project.
What Monitor Risks is
PMBOK 8 defines it this way: “Monitor Risks is the process of monitoring the implementation of risk response plans, tracking identified risks, identifying and analyzing new risks, planning responses for new risks, and evaluating the effectiveness of risk responses and processes throughout the project. This process helps ensure that risk owners are assigned to maintain continuity and address emerging risks effectively.”
It breaks down into five things: monitor the implementation of response plans; track identified risks (has the probability, impact, priority or warning signs changed?); identify and analyze new risks (including what common exam practice calls secondary risks: new risks that arise from the response actions themselves); plan responses for the new risks; and evaluate effectiveness (are the actions working on the risk, and is the risk management process itself running well?). Why is it necessary? Risk identification is iterative. At the start of a project uncertainty is high and not every risk can be seen in advance, so Monitor Risks keeps feeding new information back, and the register does not stay a snapshot of the day the project started.
Inputs, tools and outputs
| Item | Content |
|---|---|
| Inputs | Project management plan (risk management plan); project documents (issue log, lessons learned register, risk register, risk report); work performance data; work performance reports |
| Tools and techniques | Data analysis (technical performance analysis, reserve analysis); audits; meetings |
| Outputs | Work performance information; change requests; project management plan updates; project document updates (assumption log, issue log, lessons learned register, risk register, risk report); organizational process asset updates |
The tools are covered in the next two lessons. Among the inputs, the risk management plan supplies the rules (how often to review, who is responsible, report format). The risk register supplies the subject matter (risks, owners, actions, warning signs, what common exam practice calls residual and secondary risks, the watch list). The issue log tells you what has already happened, and repeated events of the same kind often show that a risk is not being managed well. Work performance data is raw data; once compared with plan components and project documents and analyzed, it becomes work performance information, and work performance information is then compiled into work performance reports. This process can also take work performance reports produced by other processes as input for further analysis. The most important output is the risk register update: newly added risks, risks whose status has changed (obsolete or occurred) and actions that have changed. When a change to actions or reserves affects a baseline, raise a change request. The easily forgotten one is the assumption log: if an earlier assumption no longer holds, record that.
How to do it: three kinds of findings and which document to update first
One round of monitoring mainly runs into three findings of different kinds (plus a fourth, everyday kind of status change, described below):
Finding 1: a new risk, not yet occurred. Identify it, go back to Perform Risk Analysis to assess probability and impact, plan a response if necessary, and take any action that moves a baseline through change control. Finding 2: an identified risk has occurred. Check the register and carry out the agreed actions. Where contingency reserve is needed, use it according to the risk management plan, the reserve-use approach and organizational authorization (exam tip, common exam practice: unless the question gives other conditions, the project manager may use it within the established authority), and record it in the issue log. Finding 3: a risk that was never identified has occurred. There is no ready-made response, so take a workaround (the usual exam term). First take a suitable temporary response and assess the impact. If genuinely unforeseeable work needs funding, apply to use management reserve according to the reserve-use approach and authorization (the usual exam judgment is to use management reserve), and if the baseline has to be adjusted, go through change control (the last two are compared side by side in Lesson 5). Then there is the fourth, everyday kind: the parameters of an identified risk are shifting. If probability rises and warning signs multiply and cross the threshold in the risk management plan, escalate as the plan requires. If the risk window has passed, close the risk and use reserve analysis to assess whether the reserve that corresponds to it should be reduced or released.
“Which document do you update FIRST?” can be judged from this table:
| Finding | Update FIRST |
|---|---|
| The probability, impact or priority of an identified risk changed; a new risk was identified | Risk register |
| A risk is obsolete or its window has passed | Risk register (close it), add a lesson learned, and adjust reserves based on reserve analysis |
| A risk has occurred | Issue log, and act on the response plan; mark the risk in the risk register as occurred or closed at the same time |
| An assumption no longer holds | Assumption log |
| The overall risk status has changed and management needs to know | Risk report |
The risk management plan is almost never the answer to “update FIRST”: it is a methodology document and does not record the values for any one risk. On rhythm, predictive projects monitor at the frequency the plan sets, often folded into status meetings. Adaptive projects can tailor it to the iteration cadence, for example assessing at the start of each iteration and reviewing at the end, with the exact frequency set by the risk management plan (Lesson 4 expands on this).
Worked example: three months of changes to a wastewater treatment plant's risk register
At the start the register held 12 risks. At the third-month review meeting the team went through them one by one. R-03, “geology does not match the survey”: excavation of the foundation is complete and conditions matched, so the risk is closed, reserve analysis shows that $15,000 of contingency reserve can be released (through change control if it sits inside the baseline), and a lesson learned is recorded. R-07, “delayed customs clearance of imported equipment”: customs added a new inspection, the probability rose from 20% to 40%, so the register is updated and the actions adjusted. R-09, “the owner's drawing review cycle”, is a newly found risk, added to the register and scored. R-11, “rainy season”, arrives half a month early, so the probability is updated and the team checks whether the reserve is enough. Four changes, and not one risk actually occurred. That is the value of Monitor Risks: bringing the status up to date before a risk turns into an issue.
Worked examples
Example 1: Signs of a risk appear. What do you do before replacing anything?
On a convenience store chain's checkout terminal rollout project, a make-or-buy analysis led to the core card reader module being supplied by one vendor, and the risk register records the risk of that vendor's financial deterioration together with a response strategy. During execution, a team member who works with the vendor tells the project manager that the vendor is short of cash and may go bankrupt and be unable to deliver; replacing the vendor would take a month. Before replacing the vendor, what should the project manager do?
Show answer and explanation
Correct answer: B
During execution, the vendor of a core module shows signs that it may go bankrupt. The risk has not yet occurred, and replacing the vendor would take a month. What should the project manager do before replacing the vendor?
“May go bankrupt” is a sign, not a fact, so this is monitoring risks: when new signs appear, reassess the likelihood of the risk occurring and check whether the existing response strategy is still effective, then decide whether to adjust the strategy (for example, activate a backup vendor) and whether to raise a change. “Before replacing” asks about this assessment step, not about direct action. The answer is B.
Why the other options are wrong
- A. Pausing all work when the risk has not occurred causes unnecessary loss and is not how risks are monitored.
- C. Not being bankrupt yet does not mean there is no risk. Ignoring the signs is passive and misses the chance to adjust the strategy.
- D. Adding budget before reassessing the risk is the wrong order. First reassess the risk and check the original response strategy, then decide whether to use reserves or adjust the strategy.
Key takeaway When new risk signs appear, check whether the original strategy is still effective and reassess the likelihood first, then decide on adjustments.
Variation Adjust the strategy only if the assessment shows the probability has risen sharply, and raise a change request if baselines are affected. If the vendor had already declared bankruptcy, the risk has occurred, and you would move to carrying out the plan or a workaround.
Something wrong with this question?
Example 2: The impact is growing. Which document do you update first?
During execution of an energy storage battery pack development project, the team finds that if an identified risk occurs, its impact will be wider than originally assessed. Which item should the project manager update FIRST?
Show answer and explanation
Correct answer: A
During execution, the impact of an identified risk, if it occurs, turns out to be wider than originally assessed. The risk has not occurred. Which item should be updated first?
“If it occurs” means the risk has not become reality; what has changed is an attribute of the risk itself (its impact). Information on an individual risk, such as probability and impact, is recorded in the risk register, which is updated continuously throughout risk management. So the new assessment should be entered in the risk register first. The answer is A.
Why the other options are wrong
- B. The risk management plan is a guiding document that sets out methods and rules. It does not record information on any particular risk, so it does not need updating for this.
- C. The issue log records only problems that have already occurred. This risk's impact has only grown and the risk has not occurred, so it does not belong in the issue log.
- D. A contingent response strategy is developed when risk responses are planned; here only the assessment information has changed, so the risk register is updated first and the response strategy is not the first item to update.
Key takeaway When the probability or impact of an identified risk changes, update the risk register first.
Variation If the existing responses are no longer enough after the impact grows, then assess whether to adjust them, and submit a change request if a baseline is affected. If you want management to understand a change in overall risk status, what is updated is the risk report.
Something wrong with this question?
Common traps
Common trap
- Monitor Risks is not just checking the original risks: you also identify new risks and close obsolete ones.
- A risk that has not occurred does not go in the issue log; it goes in only once it has occurred.
- Stopping work at the first sign, or adding budget straight away, skips steps: reassess first, then adjust the strategy, and raise a change request if a baseline is affected.
- Risk reviews follow the frequency in the risk management plan. If the plan says every two weeks, you cannot go two months without one.
Key takeaways
Key point
- Monitor Risks: monitor the implementation of response plans, track identified risks, identify and analyze new risks, and evaluate the effectiveness of responses and processes; it runs throughout the project.
- Inputs: risk management plan, risk register, issue log, risk report, lessons learned register, work performance data, work performance reports.
- Outputs: work performance information, change requests, project management plan updates, project document updates (including the assumption log), organizational process asset updates.
- Risk register updates fall into three kinds: newly added risks, risks whose status has changed and actions that have changed.
- Three main findings (plus everyday parameter changes): a new risk goes back to analysis; an identified risk that occurs means check the register; an unidentified risk that occurs means a workaround, and if funding or a baseline change is needed, apply for management reserve under your authority and go through change control.
- When signs of a risk appear, reassess first and check whether the strategy is still effective. When a risk is obsolete, close it, update the register, record a lesson learned and adjust reserves based on reserve analysis.
Lesson 3
Risk Monitoring Tools: Technical Performance Analysis, Reserve Analysis and Risk Audits
Lesson overview
The previous lesson covered what Monitor Risks does. This lesson covers what you use to do it. PMBOK 8 groups the tools for monitoring risks into three kinds: data analysis (technical performance analysis and reserve analysis), audits, and meetings. The most important meeting is the risk review meeting, which is left for the next lesson. The exam pattern is very regular: the stem describes a need, the options list several tools, and you match one to the other. So the main job is to remember the question each tool answers. Technical performance analysis asks "are the technical results on target?" Reserve analysis asks "are the reserves enough to cover the remaining risk?" A risk audit asks "is the risk management process effective?" This lesson also includes one small calculation: comparing the remaining contingency reserve with the expected loss from the remaining risks. ECO: Business Environment domain, Task 5 (Plan and manage risk), covering monitoring and controlling risks.
Technical performance analysis
PMBOK 8 describes it this way: "Technical performance analysis compares technical accomplishments during project execution to the schedule of technical achievement. The analysis requires the definition of objective, quantifiable measures of technical performance, which can be used to compare actual results against targets. Such technical performance measures may include weight, transaction times, number of delivered defects, storage capacity, etc. Deviation can indicate the potential impact of threats or opportunities."
Three keywords. Objective and quantifiable: "the prototype's battery life feels a bit shaky" does not count; "target 40 minutes, three tests averaging 34 minutes" does. Compared with a schedule: technical results also have planned milestones, and when the date arrives you compare the measured value against the target. Deviation points to risk: an actual result that departs from the target may signal a threat or an opportunity, and you judge which by what the measure means and which direction is desired. For example, battery life below target is a threat, while battery life well above target may be an opportunity. It turns "is this technical risk getting worse?" from a judgment into a measurement. Do not confuse it with earned value analysis: earned value looks at schedule and cost performance (PV, EV, AC), while technical performance analysis looks at technical measures.
Reserve analysis
PMBOK 8: "Reserve analysis is a method used to evaluate the amount of risk on the project and the amount of schedule and budget reserve to determine whether the reserve is sufficient for the remaining risk." First, separate the two kinds of reserve:
| Item | Contingency reserve | Management reserve |
|---|---|---|
| What it covers | Known risks that have been identified and have a response strategy | Unforeseeable work (unknown-unknown risks) |
| In the baseline? | Usually inside the schedule or cost baseline (PMBOK 8 allows an organization to hold it outside the initial budget if it prefers) | Outside the baseline; it can be used only through a change |
| Who uses it | Used under the risk management plan and organizational authority (common exam practice: the project manager uses it according to the response plan); when it is already inside the baseline, using it as planned does not change the baseline | Usually decided by senior management, through the change process |
PMBOK 8 points out that as project information becomes clearer, contingency reserves may be used, reduced or eliminated, so reserves must be reviewed as risks change. A common simplified approach has four steps (common exam practice; PMBOK 8 requires you to evaluate the amount of risk and the amount of reserve and decide whether the reserve is sufficient for the remaining risk). Calculate the remaining reserve (original reserve minus what has been used). Calculate the remaining risk (the sum of the expected losses of risks not yet closed, that is probability times impact; the details are in the chapter on decision tree analysis. Summing EMV is only a simplified method under particular assumptions, and in practice you should also use whatever quantitative analysis applies). Compare (reserve greater than or equal to expected loss is enough; less is a shortfall). Decide and record (a shortfall is handled under organizational governance and authority rules; if adding reserve would change an approved baseline, raise a change request, or strengthen the response actions to reduce the amount of risk. Releasing surplus reserve works the same way: if it changes a baseline, it goes through change control). Any change to a baseline must go through integrated change control, and a project manager cannot casually move unused contingency reserve to other activities.
Worked example: cost reserve on a highway widening project
The contingency reserve inside the cost baseline was originally $80,000, and $30,000 has been used as planned. Three risks are still open: Risk 1, rework after component quality inspection (probability 40%, impact $60,000); Risk 2, flood-season rainfall (30%, $60,000); Risk 3, delay in relocating utility lines (50%, $28,000).
- Remaining contingency reserve = $80,000 − $30,000 = $50,000.
- Expected loss = 40% × $60,000 + 30% × $60,000 + 50% × $28,000 = $24,000 + $18,000 + $14,000 = $56,000.
- $50,000 < $56,000, so there is a shortfall of about $6,000.
Conclusion: raise a change request to add about $6,000, or strengthen the actions on Risk 1 and Risk 2 to reduce their expected loss. Conversely, if the total expected loss were only $30,000, the surplus $20,000 should be released, which also changes the baseline and must go through a change. The schedule reserve must likewise be compared with the remaining schedule risks. But whether a schedule risk affects the finish date depends on the critical path and the logic between activities, so it usually needs schedule network analysis and suitable quantitative analysis. You cannot simply copy the cost EMV sum and change the unit to days.
Two reminders. An EMV sum is an expected value, and "just enough" does not mean safe. Once a risk occurs, it is no longer counted in the remaining risk at its probability-weighted value; the impact that has already occurred, or is still continuing, moves to issue management and is counted in actual cost or in the forecast at completion. Management reserve is not part of this comparison; it is the last line of defense.
Risk audits
PMBOK 8 lists audits as a tool for monitoring risks, and the one that relates to risk is the risk audit: "A risk audit is a type of audit that may be used to consider the effectiveness of the risk management process. The project manager is responsible for ensuring that risk audits are performed at an appropriate frequency, as defined in the project's risk management plan. Risk audits may be included during routine project review meetings, may form part of a risk review meeting, or the team may choose to hold separate risk audit meetings. The format for the risk audit and its objectives should be clearly defined before the audit is conducted."
The key point: a risk audit examines the process, not any single risk. It checks whether the agreed actions were actually carried out, whether use of reserves was recorded and authorized, whether risks were reviewed at the required frequency, and whether the register was updated on time. For example, the register says a chiller unit is to get a spare compressor, but the budget was diverted to buy other equipment. The unit never broke down, yet the agreed action was not carried out. That is exactly the kind of process defect an audit is meant to find.
Worked examples
Example 1: Which tool tells you whether the management process is effective?
At a status review meeting on a consulting project, the project manager and key stakeholders are to discuss whether the risk management process is running effectively, in particular whether the agreed risk responses are being carried out. Which process does this work belong to?
Show answer and explanation
Correct answer: D
At a status review meeting on a consulting project, the topic is whether the risk management process is running effectively, and in particular whether the agreed risk responses are being carried out. What does this work belong to?
The key points are “whether the process is running effectively” and “whether the responses are being carried out”: what is being evaluated is the existing risk management process and the responses, not looking for new risks or ranking them. A risk audit is a tool used in Monitor Risks to consider the effectiveness of the risk management process, which includes checking whether the agreed responses are being carried out, so this work belongs to Monitor Risks. The answer is D.
Why the other options are wrong
- A. Identify Risks finds new individual project risks and sources of overall project risk. This question evaluates existing responses and the management process.
- B. Perform Risk Analysis (including qualitative analysis) assesses the probability and impact of risks and ranks them. It does not evaluate whether the management process is effective.
- C. Plan Risk Responses selects strategies and develops actions for risks, and takes place before responses are carried out. It does not evaluate how well the responses are working.
Key takeaway Evaluating the effectiveness of the risk management process and the responses is a risk audit in Monitor Risks.
Variation If the question asked about the “tool” with options such as brainstorming or the assumption log, the answer would still be a risk audit. If it asked who is responsible for ensuring audits happen at the frequency set in the plan, the answer is the project manager, with the frequency defined in the risk management plan.
Something wrong with this question?
Example 2: The weather forecast turns bad. What happens to the reserve?
A highway maintenance project has set aside part of its contingency reserve for weather risk, based on the official weather forecast. The latest forecast shows that weather over the next several weeks will be worse than predicted at planning time. What should the project manager do?
Show answer and explanation
Correct answer: A
During risk monitoring, the weather risk is already identified and contingency reserve has been set aside based on the old forecast. The latest forecast shows worse weather, and the project manager has to act on it.
The signals are "contingency reserve already set aside" and "forecast got worse": the risk is an identified one, what has changed is its size, and the original reserve may not be enough. The project manager should do a reserve analysis, comparing the remaining contingency reserve with the remaining risk, and if more is needed, go through change control under the organization's rules and submit a change request. The answer is A.
Why the other options are wrong
- B. You cannot take reserve away from other activities just because their risks are smaller. First compare remaining reserve with remaining risk through reserve analysis, and use or adjust it within your authority; when a cost baseline change or additional funding is involved, follow the formal change control procedure.
- C. Management reserve is for unknown-unknowns. The weather risk is an identified one, so first see whether the contingency reserve is enough; additional funds come up only if it is not.
- D. Checking only the total budget does not assess whether the contingency reserve itself is sufficient, and it skips the change control procedure. It is less complete than a reserve analysis.
Key takeaway When an identified risk worsens, do a reserve analysis first; if reserve is short, supplement it through a change.
Variation If the assessment shows the reserve is sufficient, keep monitoring and no change is needed. If the forecast improves, assess whether surplus reserve can be released through a change. For example, with a 20-day schedule reserve of which 8 days are used, 12 days remain. Assuming the remaining risks are all on the critical path and their delays add up, if they are expected to cause 11.5 days of delay in total, 12 > 11.5 is enough but with a thin margin; with an expected delay of 14 days the shortfall is 2 days and a change is needed (in practice this also has to be checked against the schedule network).
Something wrong with this question?
Common traps
Common trap
- A risk audit evaluates the effectiveness of the risk management process, not an individual risk. The project manager is responsible for ensuring it is carried out at the planned frequency; senior management, the sponsor and a risk management department only support it or set requirements.
- Reserve analysis compares the "remaining reserve" with the "remaining risk". Risks that have already occurred are no longer counted.
- If adjusting or releasing contingency reserve would change an approved baseline, submit a change request and follow the formal process. Where a reserve sits outside the baseline, follow organizational governance and authority rules. Management reserve is for unknown-unknowns and cannot be used to fill a shortfall on an identified risk.
- Technical performance analysis needs objective, quantifiable measures. It looks at technical measures; it is not earned value analysis.
Key takeaways
Key point
- Tools for monitoring risks: data analysis (technical performance analysis, reserve analysis), audits and meetings.
- Technical performance analysis: compare actual results with targets using objective, quantifiable technical measures; deviation signals threats or opportunities.
- Reserve analysis: compare the remaining reserve with the expected loss of the remaining risks; a shortfall or surplus is handled under governance and authority rules, and if it changes an approved baseline, raise a change request.
- Contingency reserve is usually inside the baseline, covers identified risks, and is used under the risk management plan and authority (common exam practice: the project manager uses it); management reserve is outside the baseline, covers unknown risks, and goes through change.
- A risk audit examines the risk management process, not a single risk; the project manager is responsible for ensuring it is done at the planned frequency.
- Read what the stem is asking: technical results call for technical performance analysis, "is the reserve enough?" calls for reserve analysis, and "is the process effective?" calls for a risk audit.
Lesson 4
Risk Review Meetings and the Watch List: Monitoring Risks in Predictive and Adaptive Projects
Lesson overview
The third kind of tool for monitoring risks is the meeting, and the most important meeting is the risk review meeting. This lesson covers four things: what a risk review meeting does; why low-priority risks on the watch list still need to be rechecked; how the rhythm of watching risks differs between predictive and adaptive projects; and how adaptive projects use information radiators and the risk burndown chart to make risks visible. This lesson has a strong agile flavor, and many of its scenarios are agile or hybrid projects. The exam content outline says that about 60% of exam questions use adaptive or hybrid approaches, so this material deserves close attention. ECO: Business Environment domain, Task 5 (Plan and manage risk), covering monitoring and controlling risks and communicating the status of risk impact on the project.
Risk review meetings
The PMBOK 8 glossary defines risk review as "the process of analyzing the status of existing risks and identifying new risks. May also be known as a risk reassessment." A risk review meeting does this work in a meeting. It should be scheduled at the frequency set in the risk management plan, and its focus is to analyze the status of existing risks, identify new risks and update the risk register. The meeting can also be used to learn whether the response actions are working. The practice that specifically evaluates the effectiveness of the risk management process is the risk audit. PMBOK 8 says a risk audit may form part of a risk review meeting, but the two are not the same thing.
A review meeting usually does five things. Identify new individual risks (including secondary risks caused by response actions). Reassess current risks (have probability and impact changed? Use the definitions in the risk management plan). Close risks that are no longer relevant, and use reserve analysis to decide whether to reduce or eliminate reserves accordingly, for example when the typhoon season ends. Discuss issues that came from risks that occurred. Capture lessons learned. A review can be folded into a status meeting or held on its own; the attendee list, the conclusions, and the risks added and closed should all be recorded. Reviews must not stop at project closure either: close the risks that can no longer occur, explicitly accept or hand over to operations, the customer or a later phase any risks still unresolved, and capture lessons learned.
A review meeting looks at the risks. The risk audit from the previous lesson looks at the process. An audit can be held inside a review meeting, but the purposes are different.
The watch list
PMBOK 8 says: "Risks with low probability and impact may be included within the risk register as part of a watch list for future monitoring." The watch list is part of the register. The risks on it are "not actively responded to, but watched", and a change in conditions can move them into active response. Monitoring involves three things. Recheck periodically the probability and impact. If the change is clear or a warning sign appears, move the risk into active response, and send it through analysis and response planning. If the risk window passes, close it. When you move it into active response, the first thing to update is the risk register, not the risk management plan.
Worked example: how a watch list risk moves into active response
A smart agriculture project has a watch list risk: "a new batch of sensor chips may drift in bulk". Probability is 10%, impact is $8,000, expected loss is $800, and it is rechecked monthly. In month 2 the test team finds that 1 of 5 samples from the same batch is out of tolerance, and the probability is raised to 40%, which lifts the expected loss to $3,200. The project manager first updates the probability and warning signs in the register and moves the risk into active response. The chosen strategy is mitigate (inspect every unit on arrival and keep a two-week buffer), the procurement manager is named as owner, and the sponsor is informed through the risk report.
Predictive versus adaptive: different rhythms
Predictive projects review at the frequency set in the risk management plan. The review can be folded into the regular status meeting, on a weekly or monthly basis. Adaptive projects move faster. The agile example in PMBOK 8 has the team assess risks at the beginning of each iteration and hold a risk review meeting with stakeholders at the end of each iteration. The team then adjusts its strategies, and uses risk-adjusted backlogs to stay aligned with changing requirements. In a hybrid project, each part follows its own rhythm, but the risks are kept in one register and their status is kept consistent.
Adaptive projects have several common practices. (PMBOK 8 puts assessing risks every iteration and holding risk review meetings in a tailoring example in the Risk performance domain. The details are for the team to decide based on how urgent the risks are, the risk thresholds and its own working agreements.)
Make a new risk visible first, and handle it in routine activities. Put it on the team board and raise it at the next daily coordination meeting (daily standup). There is no need to call an all-hands meeting on it immediately or to pull in senior management. But a severe or urgent risk should not wait for the next meeting; work on it with the team right away, and escalate it according to the escalation criteria when they are met. Work to handle risks goes into the product backlog, where the product owner orders it. At iteration planning, the team negotiates with the product owner and selects what to do in this iteration, based on priority, the iteration goal and the team's capacity. When a severe new risk appears in the middle of an iteration, assess it immediately. The team can adjust its plan for the current iteration and negotiate scope with the product owner while protecting the iteration goal. If it does not affect the current iteration goal and cannot be handled within the iteration, turn it into a backlog item and order it. If it will affect the current iteration goal, assess it immediately first, negotiate an adjustment to the iteration with the product owner, and escalate according to the criteria when they are met. For a risk that affects several iterations, agree on a response with the team during backlog refinement or iteration planning. Do not turn other meetings into risk review meetings. The daily coordination meeting is short and is for synchronizing information; the retrospective inspects how the team works and improves it, and is not the place to assess and rank individual risks.
Visualizing risk in adaptive projects
An information radiator is a large visual chart placed in a prominent location, such as a whiteboard or board in a co-located team room, that uses graphics to show project status and information (the product backlog, issue lists, an iteration burndown chart). PMBOK 8 describes it as "a visible, physical display that provides information to the rest of the organization, enabling timely knowledge sharing", often "low tech and high touch", easy to update and updated frequently. One example is a risk log containing the risk description, likelihood, impact, rating, response and owner. The team posts the higher-priority risks on the whiteboard and regularly gathers around to discuss them; that is how it is used. Stakeholders who can be on site or who have access can see risks and issues at any time through the information radiator. Whether a status report is still needed, and its format and frequency, should be set by the communications management plan and the stakeholders' needs (PMBOK 8 says a work performance report can include a summary of risks). Common exam practice: when the stem says the team already has a visual board and stakeholders want to stay informed at any time, prefer the information radiator rather than writing a separate duplicate report.
The risk burndown chart is one kind of chart commonly shown on an information radiator. One common way to draw it puts iterations on the horizontal axis and, on the vertical axis, the total remaining risk exposure quantified by the method the project has agreed (for example the sum of the exposure values of all open risks). A falling line means the remaining risk exposure, calculated on that chart's basis, is decreasing, which may be because of risk responses, risk closure or reassessment. PMBOK 8 notes that "a burndown chart can show the number of story points remaining or the amount of risk exposure that has been reduced."
If the line rises in some iteration, the exposure added by new risks and upward reassessments exceeded the exposure removed through responses, closure and downward reassessments, and this should be a focus of the review meeting at the end of the iteration. It differs from the iteration burndown chart, which tracks the work remaining in the iteration backlog and compares it with an ideal burndown line. It does not show risk.
Worked examples
Example 1: A severe new risk appears in iteration 4
An agile team is in its fourth iteration when it finds a user story carrying a serious new risk, and it confirms that this risk did not appear in any of the first three iterations. The risk does not affect the current iteration's goal and cannot be handled within the current iteration. What should the team do?
Show answer and explanation
Correct answer: D
In the fourth iteration, the team finds a user story carrying a serious new risk that did not exist in the first three iterations. It does not affect the current iteration goal and cannot be handled within the current iteration. The question asks what the team should do.
Adaptive projects manage risk through a risk-adjusted backlog: risk response work and technical debt are also handled as backlog items. Team members can raise them, they are added to the product backlog, and the product owner prioritizes them to decide what the next iteration will do. A serious new risk follows the same path: add the story that addresses it to the product backlog and prioritize it. The stem states that the risk does not affect the current goal and cannot be handled in this iteration, so the team does not act on it now but turns it into a backlog item. If it did threaten the current iteration goal, it would need immediate assessment and a conversation with the product owner about adjusting the iteration. The answer is D.
Why the other options are wrong
- A. Work in an iteration should come from the agreed backlog. Adding goals mid-iteration undermines the stability of the iteration.
- B. Recording it in the register and waiting for the next retrospective leaves a serious new risk out of the backlog and unprioritized, so it is not handled in time. The retrospective is about process and collaboration, not assessing and ranking individual risks.
- C. Ignoring a serious risk to protect speed lets it get worse, and it goes against the agile practice of finding and responding early.
Key takeaway On adaptive projects, a new risk becomes a backlog item that the product owner prioritizes.
Variation If the new risk will affect the next two iterations, agree on a response with the team at backlog refinement; if the goal is just to make sure everyone knows, put it on the board and raise it at the next daily coordination meeting.
Something wrong with this question?
Example 2: Reading a risk burndown chart
On an agile team's risk burndown chart, the horizontal axis is iterations and the vertical axis is the sum of scores of risks not yet closed. The curve falls steadily from iteration 1 to iteration 5. What does the curve show?
Show answer and explanation
Correct answer: C
The risk burndown chart plots iterations on the horizontal axis and the sum of scores of unclosed risks on the vertical axis. The curve falls from iteration 1 to iteration 5, and the question asks what it shows.
Start with what the vertical axis means: the sum of the scores of risks not yet closed. A falling sum means that, under the chart's chosen measure, the remaining exposure from unclosed risks is steadily shrinking; the curve alone does not establish why it fell. A risk burndown chart shows risk reduction, not schedule, cost or the number of issues. Common exam practice is to plot the sum of the scores of unclosed risks on the vertical axis of a risk burndown chart, so a falling curve means remaining risk exposure is shrinking. The answer is C.
Why the other options are wrong
- A. Velocity is reflected by the amount of work completed and is not what a risk burndown chart shows. For velocity, look at an iteration burndown chart or a velocity chart.
- B. Budget consumption comes from cost data. The vertical axis of a risk burndown chart is risk score, not money.
- D. The chart counts risks not yet closed, not issues that have occurred. Risks and issues are different things.
Key takeaway A falling risk burndown chart (PMBOK 8: a burn chart can show reduced risk exposure) means the remaining exposure from identified risks is decreasing.
Variation If the vertical axis were remaining story points, it would be an iteration burndown chart reflecting workload. For “what shows stakeholders risk exposure falling by iteration,” the answer is still the risk burndown chart.
Something wrong with this question?
Common traps
Common trap
- A falling risk burndown chart means remaining risk exposure is decreasing. It does not mean higher velocity, a slower budget burn, or the number of issues that have occurred. The iteration burndown chart is the one that tracks work.
- An information radiator is a way of displaying information, not a meeting. The risk review meeting is the meeting.
- Agile projects can let stakeholders keep up with risks through information radiators. Whether a separate status report is needed is decided by the communications management plan and stakeholder needs.
- Risks on the watch list must be rechecked periodically; the approach is not "deal with it when it happens".
- The retrospective and the daily coordination meeting are not the main places for risk review. Put new risks on the board, and put the work to handle them in the backlog.
Key takeaways
Key point
- Risk review (risk reassessment): analyze the status of existing risks and identify new risks, at the planned frequency; it can be folded into a status meeting or held separately.
- The review meeting does five things: identify new risks, reassess, close outdated risks and adjust reserves through reserve analysis, discuss issues that have occurred, and capture lessons learned.
- Watch list: low-probability, low-impact risks are listed in the register and rechecked periodically; move them into active response when the change is clear. Update the risk register first.
- Predictive projects review at the planned frequency. For adaptive projects you can follow the PMBOK 8 tailoring example: assess risks at the start of each iteration and hold a risk review meeting with stakeholders at the end; the actual rhythm is tailored to the project.
- New risks in adaptive projects: put them on the board and raise them at the next daily coordination meeting; work to handle them goes into the backlog, ordered by the product owner.
- An information radiator is a way of displaying information; a falling risk burndown chart means remaining risk exposure is decreasing.
Lesson 5
When a Risk Occurs: Reserves, the Issue Log and Workarounds
Lesson overview
The first four lessons mostly dealt with risks that have not yet happened. This lesson pulls together what to do when a risk actually occurs. It is the most typical kind of scenario question in the risk topic, and the easiest one to lose points on: even though the wording is the same, "a risk occurred", an identified risk and an unidentified risk are handled differently and draw on different reserves. By the end you should be able to decide within ten seconds: was it registered in advance? If so, check the register, carry out the agreed action and use the contingency reserve; the baseline usually stays the same (when the reserve is already inside the baseline). If not, develop a workaround. If the response goes beyond your authority, needs management reserve, or requires changing a baseline or another controlled item, submit a change request and implement it once approved. An identified threat that occurs becomes an issue and must be recorded in the issue log. When an opportunity is realized, update the risk register and track its positive impact; if it creates a current situation that needs action or monitoring, record it in the issue log as well, following project practice. ECO: Business Environment domain, Task 4 (Remove impediments and manage issues) and Task 5 (Plan and manage risk). When baselines change, this also connects to Task 3 (Manage and control changes).
Where the line between a risk and an issue falls
PMBOK 8 defines an issue this way: "An issue is a current condition or situation that may have an impact on one or more project objectives. An issue has already occurred and may require immediate action or management attention." Risks and issues "may be closely related as an issue may arise from a poorly managed risk. However, issues also differ from risks as issues have already occurred or are still occurring, whereas risks are potential future problems that have not yet occurred."
There is only one line: has it already happened? When a threat occurs, mark its status in the register and open an entry in the issue log, with an owner and a due date. Read the two documents together: when the same kind of event keeps appearing in the issue log, it often points to a risk that is not being managed well. A common bad practice is to leave an occurred risk untouched in the register while the issue log stays almost empty.
Reserves: tell the two apart first
| Contingency reserve | Management reserve | |
|---|---|---|
| What it covers | Known risks that are identified and have a proactive response strategy | Unforeseeable work; used for unknown-unknown risks |
| Where it sits | Inside the schedule or cost baseline (usually) | Outside the baseline; once used, it is added to the baseline |
| Who decides | Used under the risk management plan and organizational authority (common exam practice: the project manager uses it according to the response plan) | Usually senior leadership or management |
| When it is used | The baseline does not change and no change request is needed | Used after a change is approved, and the amount is added to the cost baseline |
In the common traditional structure, project budget = cost baseline + management reserve, so using management reserve changes the baseline and must go through integrated change control. PMBOK 8 also stresses that the exact makeup of the budget and the baselines depends on the organization's policies and governance arrangements. Common exam practice: submit the change request first, and use the reserve once it is approved.
What to do: the decision flow when a risk occurs
The decision flow used in exam practice starts with three questions. Was it identified in advance? (check the register). Is there an agreed action? (if so, carry it out, and use contingency reserve if there is some). Are the action and the reserve enough? (if the reserve is not enough, or the action requires changing a baseline, analyze the impact and submit a change request). These correspond to three situations.
Situation 1: an identified risk occurs. Check the register and carry out the agreed risk response (if a contingency plan has been triggered, execute it as planned). If contingency reserve is needed, use it under the risk management plan and organizational authority (common exam practice: the project manager decides within the authority already granted). If the reserve is already inside the baseline, using it as planned does not change the baseline. Record it in the issue log. Carry out the action and assess its impact. If the contingency reserve is not enough, or the action requires changing a baseline or another controlled item, analyze the impact under the change management plan and submit a change request.
Situation 2: a risk not identified in advance occurs (usually an unknown-unknown). There is no ready-made response plan, so all you can do is a workaround (the common exam term): an unplanned response, put together on the spot, to a risk that has occurred and was not identified or planned for in advance. The project manager gathers the team to find a way. If money is needed, submit a change request, and once it is approved management reserve can be used (it is for unforeseeable work), with the amount added to the cost baseline. In an emergency (an earthquake, for example), pre-authorized emergency actions can be carried out immediately. If the action needed goes beyond the established authority or would change a baseline, get approval as quickly as possible through the organization's emergency change procedure and document it promptly; do not assume you can act first and paper it afterward.
Situation 3: an identified risk does not occur. The risk window passes and the risk is closed through risk review. Unused contingency reserve can be reduced or eliminated according to reserve analysis. If that reserve sits inside the cost baseline, first update the baseline through formal change control, and only then release it to other projects or operations as organizational governance provides.
The difference between a contingency plan and a workaround is whether it was prepared in advance. PMBOK 8 calls the former contingent response strategies; contingency plan is a common exam term, and older PMI material also says it. A contingency plan is for an identified risk and is written in the register beforehand. A workaround is usually for a risk that has occurred and was not identified, or had no effective response plan beforehand (including when the original plan fails and there is no fallback plan), and is worked out after the fact. If the risk is still there after the action has been carried out, first reassess whether the action is effective, then adjust the response plan. Changing the schedule directly, going to the change control board or going to a manager are all skipped steps.
Worked example: two "risk occurred" events on the same project
A utility tunnel project has a cost baseline of $4,200,000, which includes a contingency reserve of $180,000 (of which $70,000 has already been used, leaving $110,000). The management reserve is $200,000.
First event: the register has an identified risk, "the tunnel boring machine hits a boulder", with probability 30% and impact $90,000, and its expected value of $27,000 is part of the project-level pooled contingency reserve, which the project manager is authorized to use. The boulder appears, and breaking it up actually costs $85,000. The project manager checks the register, brings in equipment as the action specifies, and uses $85,000 of the remaining $110,000 contingency reserve at their own discretion. The cost baseline does not change, and the event is recorded in the issue log. The reserve drops to $25,000, while the total expected loss of the remaining risks is $40,000, which leaves a $15,000 shortfall, so a separate change request is submitted to top up the contingency reserve.
Second event: upstream releases water suddenly and floods the foundation pit. This was never identified in the register. The project manager immediately organizes pumping and reinforcement (a workaround) and estimates it needs $150,000. Only $25,000 of contingency reserve is left, and it is held for other identified risks, so it cannot be diverted. A change request is submitted, and once it is approved management reserve is used (dropping from $200,000 to $50,000). The cost baseline increases by $150,000, and the event is also recorded in the issue log.
Comparison (common exam practice, assuming the contingency reserve is already inside the baseline): an identified risk is "check the register, carry out the action, use contingency reserve, baseline unchanged"; an unidentified risk is "workaround; if money is needed, raise a change, use management reserve, and the baseline changes accordingly".
Worked examples
Example 1: Can the time contingency reserve cover it?
You are a project manager at a smart hardware company. Your team is developing a companion app for a new product. Early in the project the team identified risks and planned responses, and for one specific risk set aside part of the schedule as contingency reserve. During execution that risk occurs and delays the related activities by one week. It is not yet clear whether the project completion date will be affected. What should you do next?
Show answer and explanation
Correct answer: C
During execution, a risk identified early, with part of the schedule set aside as contingency reserve, occurs and delays the related activities by one week. It is not yet clear whether the completion date is affected. The question asks for the next step.
The signals are “identified early,” “set aside time as contingency reserve” and “one week delay”: this is a registered risk with a planned response and reserve, but the schedule impact still needs to be analyzed using the activity logic, total float and placement of the reserve. First consult the risk register, check the response and analyze the schedule impact to determine whether the planned response and contingency reserve can absorb the delay. If they can, use the reserve within your authority (common exam practice); if the reserve is already inside the baseline, the baseline does not change. If they cannot absorb the delay and a baseline must change, raise a change request. The answer is C.
Why the other options are wrong
- A. Analyzing the impact is part of the first step, but A bundles it with immediately submitting a change request. Submit a change request only if the analysis shows that the planned response and reserve cannot absorb the delay and a baseline must change.
- B. A workaround is for threats with no planned response or where the existing response is ineffective. This risk has a response and a reserve, so check the register first and handle it as planned.
- D. The risk has occurred, so its probability is 100%. There is no need to assess probability and impact or re-rate it.
Key takeaway When an identified risk occurs, check the register and analyze the impact to determine whether the planned response and contingency reserve can absorb it; use change control if a baseline must change.
Variation With 3 days of reserve and a 7-day activity delay, analyze the effect on the completion date using the activity logic and total float; raise a change request only if the analysis shows that a baseline must change. If the planned response and 10 days of reserve can absorb a 7-day delay, use the reserve within your authority, and if it is already in the baseline, the baseline stays unchanged.
Something wrong with this question?
Example 2: An unidentified risk occurs
A mobile app development project is in execution when the project manager meets a risk event that is in no risk response plan and was never identified. What should the project manager do first?
Show answer and explanation
Correct answer: B
During execution, a risk event occurs that is in no response plan and was never identified. The question asks what the project manager should do first.
The signals are "in no response plan" and "never identified." This is an unknown-unknown risk. There is no ready-made response to look up and no contingency reserve set aside for it. The first action is a workaround (a common exam term), which the project manager develops by calling the team together. If funds are needed, then submit a change request to use management reserve. The answer is B.
Why the other options are wrong
- A. Management does need to be informed, but that is not the first action. The project manager should lead the team in working out a response instead of waiting for a decision.
- C. Contingency reserve is set aside for identified risks, so it cannot be used directly for an unidentified one.
- D. Using management reserve requires a change. That comes after the workaround is settled and funds are needed; it is not the first step.
Key takeaway When an unidentified risk occurs, first develop a workaround; if funds are needed, submit a change request to use management reserve.
Variation If the stem said the event was recorded in the register, the answer would be to carry out the response and draw on contingency reserve as needed. If the question asked what to do when the workaround needs funds, the answer is to submit a change request to use management reserve.
Something wrong with this question?
Common traps
Common trap
- When an identified risk occurs, carry out the agreed response. When contingency reserve is needed, use it under the risk management plan and authority. To use management reserve, submit a change request first.
- When an identified risk occurs and the action is already agreed, options such as "call the team together to discuss", "brainstorm", "re-identify" or "reanalyze" are mostly distractors.
- A threat that occurs moves into the issue log, but the priority is to carry out the agreed action immediately and update the issue log at the same time or promptly afterward.
- Carrying out an approved response that does not modify any controlled item usually needs no new change request. If a baseline, a configuration-controlled plan or document, a deliverable and so on must be modified, submit a change request under the change management plan.
- Seeing signs of a risk is not the same as its occurring: first review whether the existing strategy is effective and reassess the likelihood, rather than going straight to the reserve.
Compare
| Identified | Unidentified | |
|---|---|---|
| Basis | The risk register | None; decided on the spot |
| Action | Carry out the agreed response (including a contingency plan that has been triggered) | Workaround |
| Reserve | Contingency reserve, used under authority (exam practice: the project manager decides) | Management reserve, after change approval |
| Baseline | Unchanged | The amount used is added to the baseline |
| Issue log | Record it | Record it |
Key takeaways
Key point
- The line between a risk and an issue is "has it already happened?". A threat that occurs becomes an issue and goes in the issue log (when an opportunity is realized, update the risk register; a current situation that needs action or monitoring may also go in the issue log).
- An identified risk occurs: check the register, carry out the action, use contingency reserve (used under authority, usually decided by the project manager; if already inside the baseline, the baseline is unchanged), and record it in the issue log.
- If the contingency reserve is not enough, or the action requires changing a baseline or another controlled item, analyze the impact and submit a change request.
- An unidentified risk occurs: workaround; if money is needed, submit a change request, and once approved management reserve can be used (for unforeseeable work), with the amount added to the cost baseline.
- An identified risk does not occur: close the risk, and unused contingency reserve can be released.
- If the risk remains after the action is carried out: first reassess the action's effectiveness, then adjust the response plan.
This chapter has 57 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.