Risk
Risk Response Strategies
PMP · Risk · 4 lessons · about 46 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Once risks have been prioritized, you have to decide what to do about each important one. Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks. It also identifies the resources, budget and activities needed, and records them in the project documents and the project management plan. This is the most heavily tested chapter in the risk topic. Threats have five strategies (escalate, avoid, transfer, mitigate, accept), opportunities have five (escalate, exploit, share, enhance, accept), and overall project risk has its own matching set. You also need to know contingent response strategies, fallback plans and workarounds, and the difference between secondary risks and residual risks.
By the end of this chapter you should be able to do the following. State the five qualities of a good response and compare options with cost-benefit analysis. Look at a scenario and name exactly which strategy was used for a threat or an opportunity. Tell exploit from enhance, avoid from mitigate, and transfer from share. Describe how overall project risk is addressed. Distinguish a contingency plan, a fallback plan and a workaround, and distinguish a secondary risk from a residual risk. Know which documents to update once planning is done and when to raise a change request.
Lessons in this chapter
- Lesson 1: Plan Risk Responses. The inputs, tools and outputs of the process; the five qualities of a good response (proportionate, cost-effective, feasible, agreed, one named owner); alternative analysis and cost-benefit analysis, including a worked cost-benefit comparison of three options.
- Lesson 2: Strategies for threats. The definitions of the five strategies, five ways of handling the same risk, the situations that are easy to misjudge, and how to combine several strategies on one risk.
- Lesson 3: Strategies for opportunities and for overall project risk. How the five opportunity strategies correspond to the threat strategies, the difference between exploit and enhance, and the five categories of overall-risk strategy, measured against the risk threshold.
- Lesson 4: Contingent response strategies, fallback plans, secondary risks and residual risks. Trigger conditions; contingency plans, fallback plans and workarounds compared; secondary versus residual risk; the updates and changes that follow planning.
Chapter map
| Object | Strategies | In one line |
|---|---|---|
| Threat | Escalate, avoid, transfer, mitigate, accept | Avoid eliminates the threat or protects the project from its impact; transfer shifts ownership of the response and the impact to a third party (usually for a fee); mitigate reduces probability or impact |
| Opportunity | Escalate, exploit, share, enhance, accept | Exploit makes sure it happens; share lets a third party share the benefit; enhance increases probability or impact |
| Overall project risk | Avoid, exploit, transfer or share, mitigate or enhance, accept | Act on the project as a whole, measured against the risk threshold |
| Identified risk | Contingency plan (PMBOK 8 calls these contingent response strategies; contingency plan and fallback plan are common exam terms, and common exam practice treats a fallback plan as the second-layer backup) | Triggered by conditions agreed in advance |
| Risk occurs with no prepared response | Improvise a response (workaround is a common exam term, typically for unidentified risks) | No plan existed, so the team works something out on the spot |
| After a response | Secondary risk, residual risk | A new risk caused by the response; the part of the original risk left after the response |
Study tips and practice
- Memorize the five threat strategies and the five opportunity strategies first, then learn how they correspond, and finally practice on scenarios. When you judge a scenario, ask three questions: does the event still occur, who bears the consequence, and did probability or impact come down?
Lesson 1
Plan Risk Responses: Purpose, Response Requirements and Cost-Benefit Analysis
Lesson overview
After risk analysis, the high-priority risks are on the table and the next question is what to do about them. Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks. This lesson covers the process itself: its inputs, tools and outputs; common exam practice for judging a good response against five criteria; and how to judge whether a response is worth its cost. The specific strategies are covered in the next lessons. ECO: Business Environment domain, Task 5 (Plan and manage risk). This lesson comes after Perform Risk Analysis and before Implement Risk Responses: planning writes the response, implementation carries it out.
Plan Risk Responses: what it does and what it produces
The key benefit is that it identifies suitable ways to address overall project risk and individual project risks, allocates resources or sets aside reserves, and puts the necessary activities into the project documents and the project management plan, throughout the project. In short, you develop strategies for overall project risk and for each individual risk that needs a response: reduce exposure to threats, increase or capture opportunities, and keep risk within acceptable thresholds. Risks with low probability and low impact are usually placed on a watch list in the risk register for future monitoring. If acceptance is chosen, you should also say whether it is active or passive acceptance and what arrangements go with it.
| Item | Content |
|---|---|
| Inputs | Project management plan (resource management plan, risk management plan, cost baseline and others); project documents (risk register, risk report, stakeholder register, lessons learned register, project schedule, project team assignments, resource calendars and others); enterprise environmental factors; organizational process assets |
| Tools and techniques | Expert judgment; interviews; facilitation; the four kinds of response strategy (threats, opportunities, contingent responses, overall project risk); alternative analysis and cost-benefit analysis; multicriteria decision analysis |
| Outputs | Change requests; project management plan updates; project document updates |
The risk management plan gives the roles, responsibilities and risk thresholds. The risk register gives the prioritized risks. The stakeholder register lists the people who could be risk owners. The cost baseline reflects the funding available and its constraints, the resource management plan explains how resources are acquired, allocated and monitored, and the resource calendars show when resources are available and for how long.
A good response meets five tests
The five points below are common exam practice for judging a good response. What PMBOK 8 requires is identifying suitable ways to address the risk and allocating resources or setting aside reserves.
- Proportionate to the importance of the risk: do not mount a big effort for a small risk, and do not play down a big one.
- Cost-effective: the money spent on the response is less than the loss it avoids or the benefit it brings.
- Feasible in the context of the current project: the technology, resources and time are available.
- Agreed by the relevant stakeholders and responsible parties.
- One named owner for each response, responsible for carrying it out (common exam practice). Not two or more people, and not "everyone together."
Several responses are often possible, so for each risk you need to pick the strategy or combination most likely to work. Multicriteria decision analysis can help: use a decision matrix to evaluate and rank the options against criteria such as risk level, uncertainty and value benefits.
Judging whether a response is worth it
Alternative analysis compares the characteristics and requirements of several response options side by side to see which suits best. Cost-benefit analysis is used when the effect of a risk can be expressed in money, and compares what a response costs with what it brings. PMBOK 8 says only: "A cost-benefit analysis compares the cost of an activity to the expected benefit."
Under common exam practice, the calculation is:
For a threat, the "result of the response" is the expected loss avoided. The larger the ratio, the better the value. Net benefit is the result of the response minus the cost of the response. If the monetizable benefit is lower than the cost of the response, the direct financial net benefit is negative and the response usually has no cost advantage (common exam practice: in a worked example, an option that costs more than the loss it avoids is eliminated). PMBOK 8 stresses, however, that extra spending can still be worthwhile if it improves safety, meets regulatory requirements or improves overall outcomes, so the decision should also weigh the risk threshold, compliance and other non-financial benefits.
Worked example: choosing among three options
The threat is a failed database cutover, with 30% probability and an $80,000 loss. The original expected loss is 30% × $80,000 = $24,000.
- Avoid: cancel the cutover and keep the old system (switch to an approach that needs no cutover). Cost $20,000; probability falls to 0, so $24,000 is avoided. $24,000 ÷ $20,000 = 1.2; net benefit $4,000.
- Mitigate: add rehearsals and a rollback plan. Cost $6,000; probability falls to 5%, leaving $4,000 of expected loss, so $20,000 is avoided. $20,000 ÷ $6,000 ≈ 3.33; net benefit $14,000.
- Transfer: buy insurance (assume the policy covers the full $80,000 loss, with no deductible and no payout cap). Premium $12,000; the $24,000 expected loss is transferred to the insurer. $24,000 ÷ $12,000 = 2.0; net benefit $12,000.
Mitigate has both the highest ratio and the highest net benefit, so choose mitigate. Avoid is the most thorough, but spending $20,000 to net only $4,000 is the lowest value of the three, so it loses to mitigate.
When the ratio and the net benefit point to different options, look at how the question is worded. If it says "by ratio," use the ratio. If it says "greatest net benefit," use the difference. If it says only "most cost-effective" and gives no criterion, use the comparison method the question gives.
Predictive projects usually do most of this planning up front, record the results in the risk register, and keep reviewing and updating the responses throughout the project. After the baselines are approved, if a response would change a controlled baseline, a project management plan component, a deliverable or another controlled project document, raise a change request through change control. Adaptive projects build responses into the everyday rhythm. (The meeting arrangements that follow are common exam practice; as an example, PMBOK 8 describes software projects using an agile life cycle, where risks can be assessed at the start of each iteration, a risk review meeting held at the end of each iteration, and a risk-adjusted backlog used to keep everyone aligned.) Iteration planning selects the actions and puts them in the backlog, the daily coordination meeting tracks them, and the retrospective reviews how well they worked. Under common exam practice, both approaches require a response that is proportionate, cost-effective, agreed and has one named owner.
Worked examples
Example 1: Scenario question, the response costs more than the loss
In the planning stage of a software migration project, a response has been drafted for a high-priority threat, but estimates show that implementing it costs more than the loss the risk would cause if it occurred. Looking only at costs and benefits that can be expressed in money, what should the project manager do?
Show answer and explanation
Correct answer: D
A software migration project is planning risk responses. A response has been drafted for a high-priority threat, but estimates show that it costs more to implement than the loss if the risk occurs. The question asks what the project manager should do.
A risk response must be cost-effective. Looking only at costs and benefits that can be expressed in money (common exam practice), what is spent on a response should be less than the loss it avoids. The original response costs more than it avoids, so it is not worthwhile and should not be carried out. The right approach is to use alternative analysis and cost-benefit analysis to compare other response options and pick the one with the best cost-benefit, that is, a response cost lower than the loss avoided. The threat is high priority, so active options should be compared fully first; the answer is to change the response, not to give up or escalate. If no option is feasible or worthwhile, active or passive acceptance is still possible. The answer is D.
Why the other options are wrong
- A. Implementing a response that costs more than the loss it avoids defeats cost-effectiveness, and the management reserve is held for unknown risks, not to pay for an uneconomic response.
- B. Falling back to passive acceptance for a high-priority threat without comparing options amounts to giving up on an active response. Acceptance is considered only when no cost-effective option can be found after a thorough search.
- C. The threat is not beyond the project's scope or the project manager's authority, so there is no reason to escalate, and escalating would not solve the problem that the response is uneconomic.
Key takeaway Response cost should not exceed the loss avoided. If a response is uneconomic, change it, and compare options with cost-benefit analysis.
Variation Only if every option is infeasible or not worthwhile does acceptance come in: active acceptance means establishing a contingency reserve, while passive acceptance only records the risk and reviews it periodically.
Something wrong with this question?
Example 2: Calculation question, the cost-effectiveness of three options
A data migration project has a threat with a 40% probability of occurring and a loss of $50,000 if it does. The team has drafted three options: avoid (cost $15,000, reduces the probability to 0); mitigate (cost $5,000, reduces the probability to 10%); transfer (insurance premium $12,000, the insurer bears the whole loss if it occurs). The project manager uses cost-benefit analysis and compares the options by “expected loss avoided ÷ response cost.” Which option should she choose?
Show answer and explanation
Correct answer: A
A threat on a data migration project has a 40% probability and a $50,000 loss, with three options: avoid, mitigate and transfer. The options are to be compared by “expected loss avoided ÷ response cost” to find the best value.
First calculate the original expected loss, then calculate for each option how much loss it avoids and what it costs, and take the ratio. The higher the ratio, the more loss each dollar spent avoids, and the better the option. Avoiding cuts the probability to 0, which looks the most thorough, but its cost is high. Mitigating reduces the probability only to 10%, but it costs just $5,000, so its ratio is the highest (3). Note that the option with the biggest effect is not necessarily the best value. The answer is A.
- Original expected loss = 40% × $50,000 = $20,000
- Avoid: avoids $20,000 at a cost of $15,000; 20 ÷ 15 ≈ 1.33
- Mitigate: remaining 10% × $50,000 = $5,000, so it avoids $20,000 − $5,000 = $15,000 at a cost of $5,000; 15 ÷ 5 = 3
- Transfer: avoids $20,000 at a premium of $12,000; 20 ÷ 12 ≈ 1.67
- Compare: 3 > 1.67 > 1.33, so mitigate is highest. Net benefit is also largest for mitigate ($15,000 − $5,000 = $10,000), so the conclusion is consistent
Why the other options are wrong
- B. Avoid reduces the probability to 0, which looks the most thorough, but at a cost of $15,000 the ratio is 20 ÷ 15 ≈ 1.33, the lowest of the three. This is the classic mistake of looking at the effect without calculating the cost.
- C. Transfer avoids the full $20,000, but the $12,000 premium gives 20 ÷ 12 ≈ 1.67, lower than mitigate's 3. It treats “someone else bears all the loss” as best and ignores the premium.
- D. Accepting costs nothing but avoids nothing: the $20,000 expected loss remains, so there is no “loss avoided” at all, and it is not the option with the best cost-benefit.
Key takeaway Cost-benefit analysis looks at loss avoided against response cost. The option with the biggest effect is not necessarily the best value.
Variation Compared by net benefit (loss avoided − cost): mitigate 10, avoid 5, transfer 8 (in thousands of dollars), so mitigate is still largest. If mitigation could only reduce the probability to 30%, it would avoid $5,000, the ratio would be 1, and transfer would then be better.
Something wrong with this question?
Common traps
Common trap
- Plan Risk Responses develops responses for risks that have already been prioritized. It is not identifying risks and it is not carrying out the responses.
- Common exam practice: there is one owner, not two or more, and not "the whole team."
- Looking only at monetizable benefit, the response cost should usually be lower than the loss avoided or the benefit gained (common exam practice). But PMBOK 8 points out that extra spending that improves safety, meets regulatory requirements or builds stakeholder confidence can still be worthwhile, so judge it together with the risk threshold.
- Alternative analysis compares characteristics and requirements; cost-benefit analysis compares costs with benefits.
- Management reserve is for unknown risks; contingency reserve is the one that matches identified risks.
Key takeaways
Key point
- Plan Risk Responses: determine the response to overall and individual risks, allocate resources or set aside reserves, throughout the project.
- Inputs include the risk management plan, risk register and stakeholder register; outputs are change requests, project management plan updates and project document updates.
- Five points of a good response (common exam practice): proportionate to importance, cost-effective, feasible in context, agreed by all, one owner.
- Tools: expert judgment, alternative analysis, cost-benefit analysis, multicriteria decision analysis and others.
- Cost-benefit analysis: PMBOK 8 requires only comparing cost with benefit. Under common exam practice, the calculation is effectiveness = result of response ÷ cost of response. When the effect can be monetized, cost should usually be below the loss avoided (safety, compliance and other non-financial benefits are judged separately).
- Planning writes the response; implementation carries it out.
Lesson 2
Strategies for Threats: Escalate, Avoid, Transfer, Mitigate, Accept
Lesson overview
A threat has five possible response strategies: escalate, avoid, transfer, mitigate and accept. This is the most heavily tested point in the risk topic, and a question often gives you only a scenario and asks which strategy was used. This lesson first defines the five strategies, then shows all five applied to one scenario, and ends with a method for judging. ECO: Business Environment domain, Task 5 (Plan and manage risk). Learn the strategy names word for word, because the answer options are exactly these words.
The five strategies defined
A risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more portfolio, program, or project objectives, and when analyzing an individual risk you usually assess probability and impact. Avoid works on the event, so that it no longer happens. Mitigate works on probability and impact, so that the event happens less often or costs less. Transfer shifts ownership of a specific threat, together with its impact, to a third party. Accept acknowledges the threat and takes no proactive action to reduce its probability or impact (active acceptance can set aside a contingency reserve). Escalate applies when the threat is beyond your authority and goes to a higher level.
| Strategy | What you do | Example | Key point |
|---|---|---|---|
| Escalate | Used when the threat is outside the scope of the project, or the response would exceed the project manager's authority; it is managed at the portfolio level, program level or another relevant part of the organization | A computer virus affecting several projects is escalated to the portfolio manager | The receiving party must accept ownership; after escalation the project team no longer monitors it, though it may be recorded in the risk register |
| Avoid | Eliminate the threat (reduce its probability to zero) or protect the project from its impact | Clarify requirements, obtain information, acquire expertise; extend the schedule, change the strategy, reduce scope | Suited to high-priority threats with high probability and large negative impact |
| Transfer | Shift ownership of the response to a third party, who also bears the impact | Insurance, performance bonds, warranties, guarantees | Usually involves paying a risk premium to the party taking on the threat |
| Mitigate | Reduce the probability and/or impact of the threat | Adopt less-complex processes, run more tests, choose a more stable seller, build a prototype, design in redundant components | Acting early is often more effective than repairing damage afterward |
| Accept | Acknowledge the threat and take no proactive action | Active: establish a contingency reserve. Passive: review periodically | Suited to low-priority threats, and also used when other responses are not possible or not cost-effective |
One risk, five responses
A retail chain is fitting out a new store and has identified a threat: custom imported tiles may arrive late and push back the opening.
- Avoid: switch to domestic tiles that are in stock, so the imported-tile event disappears from the project. The source of the threat is gone.
- Mitigate: place the order a month earlier and sign a backup supply letter of intent with a domestic factory. A delay can still happen, but its probability and impact are both pushed down. Backups and redundancy that reduce probability or impact are usually mitigation. Whether "preparing early" counts depends on what the action actually does: if it only sets aside time, money or resources for use after the event (a contingency reserve), that is active acceptance. Separately, common exam practice calls a response carried out only when a specific trigger condition appears a contingency plan or fallback plan, and PMBOK 8 lists contingent response strategies as a tool (the next lesson separates the two). Do not call something mitigation just because it reduces the loss once carried out; decide from the strategy the question asks about, the timing of the action, and whether it merely accepts the risk and sets a reserve.
- Transfer: write liquidated damages for late delivery into the contract, or buy delay insurance. The delay can still happen, but the supplier or insurer bears the loss, and the project pays a premium or a higher purchase price.
- Accept: set aside 5 days of schedule contingency reserve and use it if the delay occurs. Setting a contingency reserve is active acceptance; merely noting it in the register and checking now and then is passive acceptance.
- Escalate: if the issue is a change in import tariff policy that affects every store in the group, it is beyond a single project's authority and should be escalated to the procurement director or the portfolio level.
When you judge, ask three questions in order. (1) Has the threat been eliminated, or have the project objectives been isolated from its impact? If so, that is avoid; if probability or impact is only reduced, that is mitigate. (2) Has responsibility for a specific threat and its impact been shifted to a third party through insurance, a contract or another agreement? If so, that is transfer (paying a fee is a common feature, not a requirement). (3) Did we bring probability or impact down? If yes, it is mitigate; if not and we accept the consequence, it is accept. Escalate applies when the threat or the proposed response is beyond the project's authority. One more difference between transfer and mitigate is who bears the loss: if you manage it yourself, you bear the loss when it happens; if you bought insurance, once the insured risk occurs the insurer pays the corresponding loss within the limits of the contract.
Situations that are easy to misjudge
- A data center adds a second, redundant power feed that is live in parallel with the first, so one failure no longer interrupts service: that is mitigate. If the standby feed is held ready and switched in only after a trigger (power loss), it is a contingent response strategy (a contingency plan, a common exam term).
- A third-party component is found to be high-risk and you remove the dependency on it entirely and take another approach, so the failure threat no longer exists: that is avoid. If you merely switch to a more stable component of the same kind, the failure probability falls but the threat remains: that is mitigate.
- A very difficult subsystem is handed to a specialist firm, and the contract says the firm bears the corresponding responsibility and impact: paying a third party to bear it is transfer.
- A minor defect that might occur is tolerated and a small rework contingency reserve is set aside in case it does: accept.
- An agile team is unsure about the performance of a third-party interface and schedules a short exploration task (a spike) to prototype it: it exposes the problem early, so it is mitigate.
Suppose the in-stock tiles turn out to have quality problems. That does not mean the avoidance strategy failed. Avoid deals only with the one risk in front of you, and "quality problems with in-stock tiles" is a new risk that must be identified separately. This is the secondary risk covered in a later lesson.
Strategies are not single-choice. High-priority threats often use a combination: first avoid or mitigate to push probability and impact down, then transfer or accept what is left. When a question asks "which two strategies were used," split the actions apart, with one action matching one strategy. When it asks for only the "main" one, look at the stated goal: "no longer happens" is avoid, "reduce" is mitigate, "borne by someone else" is transfer.
Worked examples
Example 1: Avoid: typhoon forecast, location shoot moved indoors
A film production company planned to shoot a major scene at a seaside location. The weather service forecasts a strong typhoon during the shooting week, and the crew cannot work offshore. The head of production decides to move the scene to an indoor studio. Which risk response strategy did the head of production use?
Show answer and explanation
Correct answer: B
A film company planned to shoot a major scene at a seaside location. A strong typhoon is forecast for the shooting week and the crew cannot work offshore, so the head of production moves the scene to an indoor studio. Which response strategy is this?
The key is whether the threat still exists after the action. Avoid takes action to eliminate the threat or to protect the project from its impact, typically by changing the plan or strategy. After the scene moves indoors the typhoon no longer affects it at all, so the threat is eliminated and the strategy is avoid. If the crew still shot on location and only reinforced equipment or raced the clock, that would be mitigate, because the threat would remain. The answer is B.
Why the other options are wrong
- A. Mitigate keeps the risk and only reduces probability or impact, for example reinforcing equipment and still shooting on location. Here the location was changed outright and the typhoon no longer matters to this scene.
- C. Accept takes no proactive action and deals with the event if it happens. The head of production actively changed the shooting plan, which is action, not acceptance.
- D. Transfer gives the consequences to a third party, for example by buying insurance for the shoot. The stem has no third party bearing the impact of the typhoon. The typhoon will still arrive; it just no longer affects this scene.
Key takeaway Changing the plan so the threat no longer affects the project is avoid; if the threat remains and only its impact is reduced, it is mitigate.
Variation Buying typhoon insurance on the equipment so the insurer pays for damage is transfer. Preparing wind-protection gear but still shooting on location is mitigate.
Something wrong with this question?
Example 2: Two strategies used at once
The project manager of an HR software go-live project learns that an earlier project that used the same software package lost employee data when it moved to the new system. She decides to make a full backup of the data before migration so it can be restored if something goes wrong. She also buys insurance to pay for manually re-entering data if the import fails. Which two response strategies did she use?
Show answer and explanation
Correct answer: B
The project manager of an HR software go-live project knows that an earlier project using the same package lost employee data during import. Before migration she makes a full data backup and buys insurance to pay for re-entering data. The question asks which two threat response strategies she used.
Match each action separately. A full backup lets the data be restored if something goes wrong and reduces the impact of data loss, but the loss can still happen; that is mitigate. Buying insurance means paying a premium and handing the cost of re-entering data to the insurer, which gives the consequence to a third party; that is transfer. So the strategies are mitigate and transfer. The answer is B.
Why the other options are wrong
- A. Neither action is acceptance. Acceptance means acknowledging the risk without trying to reduce or transfer it and dealing with it only if it occurs (for example by using reserves). A backup reduces impact and insurance transfers cost, so neither is acceptance.
- C. Share is a strategy for opportunities, used to share the benefit of an opportunity with a third party. It is not one of the threat strategies and cannot be mixed in.
- D. Avoid eliminates the threat entirely, for example by changing the plan so the risk cannot occur. Neither a backup nor insurance stops data loss from happening, so neither is avoidance.
Key takeaway Reducing probability or impact is mitigate; paying to hand the consequence to a third party is transfer; share belongs to opportunities.
Variation Only buying insurance would be transfer, and only making a backup would be mitigate. When a question involves several strategies, count the actions one by one and match each.
Something wrong with this question?
Common traps
Common trap
- Transfer does not eliminate the threat itself; it shifts ownership of a specific threat to a third party to manage it and bear its impact, and it usually costs money. Insurance, performance bonds, warranties and guarantees are typical tools.
- Redundant components, prototypes built to reduce risk and additional testing are usually mitigate, not avoid. For a backup or standby arrangement, look at what it does: reducing probability or impact is mitigate, while merely reserving resources or switching on after a trigger may be active acceptance or a contingent response.
- Accept is not doing nothing: the most common form of active acceptance is establishing a contingency reserve, and passive acceptance requires periodic review.
- Escalate means a higher level takes it over and manages it, and the project team no longer monitors it; it applies only to threats beyond the project's scope or the manager's authority.
- Exploit, share and enhance are opportunity strategies; avoid, transfer and mitigate are threat strategies; escalate and accept are used for both.
Key takeaways
Key point
- Five threat strategies: escalate, avoid, transfer, mitigate, accept.
- Avoid: the event no longer happens; suited to high-priority threats with high probability and high impact.
- Transfer: give it to a third party, usually with a risk premium, and the risk itself is not eliminated. Mitigate: reduce probability or impact; backup and redundancy belong here.
- Accept: active acceptance sets a contingency reserve; passive acceptance reviews periodically.
- Escalate: beyond project scope or the manager's authority; a higher level takes over and the project team no longer monitors it.
- Three judging questions: does the event still happen, who bears the consequence, and did probability or impact come down?
Lesson 3
Strategies for Opportunities and for Overall Project Risk
Lesson overview
Threats must be guarded against, and opportunities must be seized. Opportunities also have five response strategies: escalate, exploit, share, enhance and accept, and they line up one for one with the strategies for threats. This lesson first covers the five opportunity strategies, with the focus on telling exploit from enhance. It then covers responses to overall project risk: the same set of strategies, but aimed at the whole project instead of a single risk. ECO: Business Environment domain, Task 5 (Plan and manage risk).
How threat strategies and opportunity strategies correspond
| Threat | Opportunity | What they have in common |
|---|---|---|
| Avoid: make the threat no longer occur | Exploit: make the opportunity definitely occur | Both push probability to an extreme (0 or 100%) |
| Transfer: hand ownership of the threat to a third party, who manages it and bears the impact | Share: let a third party share in the benefit | Both rely on a third party and often involve paying a risk premium |
| Mitigate: reduce probability and/or impact | Enhance: increase probability and/or impact | Both adjust the degree and do not aim for an absolute |
| Escalate, accept | Escalate, accept | Used for both threats and opportunities |
Strategies for opportunities
| Strategy | What you do | Example |
|---|---|---|
| Escalate | Used when the opportunity is outside the project's scope, or when the response would exceed the project manager's authority. It is handed to the portfolio, program or another part of the organization. After escalation the project team does not monitor it further (it may be recorded in the risk register for information). | For example, a market opportunity beyond the project manager's authority goes to management; escalate to the level that matches the objectives the opportunity would affect |
| Exploit | Used when the organization wants to ensure that a high-priority opportunity is realized: probability is raised to 100% so that it definitely happens. | Assign the organization's most talented resources to shorten the schedule; use new technology to reduce cost and duration |
| Share | A third party takes ownership of the opportunity and shares some of the benefit. A risk premium is often paid. | Risk-sharing partnerships, teams, special-purpose companies or joint ventures |
| Enhance | Increase the probability and/or impact of the opportunity. | Add resources to an activity so that it finishes early |
| Accept | Acknowledge the opportunity but take no proactive action. | Active acceptance: set up a contingency reserve. Passive acceptance: review the opportunity periodically. |
Take a cloud provider's limited-time compute subsidy (worth about $60,000 in savings) as an example. Making it mandatory to win the subsidy and assigning the strongest back-end team is exploit. Adding a consultant who knows the application process makes approval more likely but does not guarantee it, so that is enhance. Applying jointly with a partner company that already holds the required qualification, and splitting the benefit, is share. If the subsidy requires the whole company to move onto the cloud ecosystem, which is beyond this project's authority, you escalate. With no extra resources available, you keep a small margin and accept.
Exploit versus enhance
The difference is whether the strategy seeks to ensure the outcome. Exploit takes probability to 100%, and its means are the most talented resources or the newest technology. Enhance only raises probability or impact, for example by adding people or strengthening training. Exam tip (common exam practice): if the stem says "ensure" or "make sure it is realized", it is exploit; if it says "improve the chance of success" or "success cannot be guaranteed", it is enhance. "Most talented resources" and "new technology" are only examples of exploiting responses that PMBOK 8 lists, so you still have to ask whether the purpose of the action is to ensure the opportunity happens.
Once an opportunity is escalated, ownership moves to the receiving party. After you confirm that the relevant party has accepted ownership, the project team does not monitor the opportunity further, although it may keep a record in the risk register. If a question asks what to do next after escalating, the answer is to stop monitoring it and keep a record.
Strategies for overall project risk
Overall risk is the effect of uncertainty on the portfolio, program, or project as a whole; it may arise from everything that is uncertain or unknown in the project, including individual risks. The responses use the same strategies as for individual risks, but the target is the whole project, and the key reference is the project risk threshold: when overall risk is outside (or promises to be better than) the agreed thresholds, you take action aimed at the project as a whole.
| Strategy | What you do, with examples | When it applies |
|---|---|---|
| Avoid | Reduce the negative effect of uncertainty on the project as a whole and bring the project back within the thresholds. Remove high-risk elements of scope; if the project cannot be brought back within the thresholds, cancel it (the most extreme avoidance). | Overall risk is significantly negative and outside the thresholds |
| Exploit | Capture the positive effect of uncertainty on the project as a whole. Add high-benefit elements of scope, or modify the thresholds with the agreement of key stakeholders to embrace the opportunity. | Overall risk is significantly positive and outside the thresholds |
| Transfer/share | A third party manages the risk on behalf of the organization: for negative risk, transfer (possibly paying a risk premium); for highly positive risk, ownership is shared to reap the benefits. Joint venture, special-purpose company, subcontracting key elements of the project. | Overall risk is high and the organization cannot address it effectively |
| Mitigate/enhance | Change the level of overall project risk: mitigate when it is negative, enhance when it is positive. Replan the project; change scope and boundaries, priority and resource allocation. | Mitigate when overall risk is negative, enhance when it is positive |
| Accept | Continue with the project as currently defined when no proactive response is possible. Active: set up an overall contingency reserve for the project. Passive: periodically review the level of overall risk. | No proactive response to overall risk is possible |
At the overall level, avoidance may be used whenever overall threat has a significantly negative effect and is outside the agreed thresholds. Measures include removing high-risk elements of scope. Canceling the project is the most extreme form of avoidance and is used only if the overall level of threat is, and will remain, unacceptable; it is the last resort. For example, a smart campus project requires that cost at 80% confidence not exceed $500 million, but the simulation gives $560 million, mainly because of one new-technology subsystem. Moving that subsystem out of this phase's scope is avoidance. Outsourcing the whole subsystem to a contractor on a fixed-price contract is transfer. Delivering the project in phases is mitigation. Setting an overall contingency reserve and carrying on is acceptance.
Worked examples
Example 1: Enhance: training raises the chance of success but does not guarantee it
A software company takes on a project to optimize a route-planning algorithm. If the team can quickly master a new framework, the algorithm may reach its target early and win an extra order from the customer. The project manager hires an outside senior expert to give the team a week of focused training. This raises the likelihood of the opportunity but does not guarantee it. Which opportunity response strategy is this?
Show answer and explanation
Correct answer: A
A software company takes on a route-planning algorithm optimization project. If the team masters a new framework quickly, the algorithm may reach its target early and win an extra order, which is an opportunity. The project manager has an outside expert give a week of focused training, which raises the likelihood of the opportunity but does not guarantee it. Which opportunity response strategy is this?
The training targets the cause that decides whether the opportunity occurs: the better the team has mastered the framework, the greater the chance of an early finish and an extra order. The stem says it “raises the likelihood” but “does not guarantee,” so the probability or impact of the opportunity is only increased, not made certain. That is enhance. Measures like this work better the earlier they are taken. The answer is A.
Why the other options are wrong
- B. Exploit takes action to make sure the opportunity is realized, raising the probability to 100%, for example by assigning the best people to it full time. The stem says explicitly that success is not guaranteed, so this is not exploit.
- C. Share gives the opportunity to a third party who is best able to seize it and shares the benefit, as in a joint venture or partnership. The outside expert only provides training and shares no project benefit.
- D. Escalate is for an opportunity beyond the project's scope or the project manager's authority, reporting it to a higher level. Here the project manager acts directly within their own authority and does not escalate.
Key takeaway Exploit makes sure the opportunity happens; enhance only increases its probability or impact.
Variation If the stem said “success guaranteed” and assigned the best expert full time, it would be exploit. The matching threat strategies are avoid and mitigate.
Something wrong with this question?
Example 2: Overall project risk: negative risk is too high for the organization to handle
A coffee chain decides to launch a membership subscription platform project. A key stakeholder points out that to make a profit in this market it must adopt an entirely new subscription model, and whether users will accept it is highly uncertain. This leaves the project as a whole facing a high level of negative risk, the organization cannot address it effectively itself, and it could hinder achievement of the project objectives. Which overall project risk response strategy should the project manager use?
Show answer and explanation
Correct answer: B
A coffee chain is running a membership subscription platform project. A key stakeholder points out that an entirely new model must be adopted whose user acceptance is highly uncertain, the overall negative risk is high, and the organization cannot address it effectively itself. You must decide which overall project risk response strategy to use.
What is being judged here is overall project risk, not an individual risk. PMBOK 8's strategies for overall project risk are likewise five: avoid, exploit, transfer/share, mitigate/enhance and accept. If the level of overall project risk is high but the organization is unable to address it effectively, a third party may be involved to manage the risk on behalf of the organization. Where overall project risk is negative, a transfer strategy is required, which may involve payment of a risk premium; share applies only when it is positive. This situation is a negative overall risk the organization cannot address effectively, so the answer is B.
Why the other options are wrong
- A. PMBOK 8 gives adding high-benefit elements of scope as an example of exploit for overall risk, used when overall risk is clearly positive. The stem describes negative risk, so the direction is wrong.
- C. A risk workshop with experts only discusses responses; it does not itself change the level of overall risk and is not a response strategy, so it does not directly raise the chance of meeting the objectives.
- D. Qualitative risk analysis is analysis work that comes before response planning and mainly concerns individual risks. Here the question is the response strategy for overall risk, not further analysis.
Key takeaway When overall risk is highly negative and the organization cannot address it effectively, transfer it to a third party. Use share only when overall risk is positive.
Variation If overall risk were clearly positive, the same condition would call for share, with a third party taking part of it and sharing the benefit. Negative calls for transfer and positive for share.
Something wrong with this question?
Common traps
Common trap
- Exploit aims for "it definitely happens" and uses the strongest resources or new technology. Enhance only increases probability or impact and does not guarantee anything.
- Share gives part of the benefit to a third party (opportunities). Transfer hands the impact to a third party and usually involves paying a risk premium (threats).
- Escalate and accept are used for both threats and opportunities. After an opportunity is escalated, the project team does not monitor it further and only keeps a record in the risk register.
- At the overall level, the extreme form of avoidance is canceling the project, but it is used only when the overall threat is, and will remain, unacceptable.
- Overall-risk strategies target the whole project: "mitigate" for negative risk, "enhance" for positive risk.
Key takeaways
Key point
- Five opportunity strategies: escalate, exploit, share, enhance, accept.
- Correspondence: avoid with exploit, transfer with share, mitigate with enhance; escalate and accept are shared.
- Exploit: probability to 100%, using the most talented resources or new technology. Enhance: increase probability and/or impact.
- Share: give ownership of the opportunity to a third party so that it shares the benefit; a risk premium is often paid.
- Five strategy types for overall project risk: avoid, exploit, transfer/share, mitigate/enhance, accept, all measured against the project risk thresholds.
- Canceling the project is the most extreme avoidance at the overall level.
Lesson 4
Contingent Responses, Fallback Plans, Workarounds, Secondary and Residual Risk
Lesson overview
The first three lessons covered which strategy to choose. This lesson covers what comes after a strategy is chosen. Some actions start only when a trigger appears: these are contingent response strategies. PMBOK 8 uses that name; older PMI material and the exam often say contingency plan or fallback plan instead (common exam terms), and exam questions often treat the fallback plan as the second layer of backup behind the contingency plan. What if the risk was never thought of in advance? Then you use a workaround. Responses can also create new risks and leave old ones behind, and these are called secondary risk and residual risk (these three are common exam terms). Finally, the lesson covers which documents to update when planning is done. ECO: Business Environment domain, Task 5 (Plan and manage risk). Two questions keep everything apart: was there preparation in advance, and is the risk new?
Contingent response strategies and the contingency plan
A contingent response strategy is designed on purpose to be used only if certain predefined conditions occur. Common exam practice often adds that the warning has to come early enough for the response to be launched in time. Such strategies are often called a contingency plan or a fallback plan. The advantage is that you do not spend resources on the response too early, and attention shifts from the risk's impact to its triggers. Triggers must be written down in advance and be monitorable, for example "failure rate above 5% for 10 minutes in a row", not "when the risk gets bigger". Common exam practice: when the chosen strategy turns out not to be fully effective, or an accepted risk occurs, you invoke the contingency plan and draw on the time or cost contingency reserve already set aside for that risk during planning.
An early warning sign is an indication that a risk is about to occur, such as a supplier slipping twice in a row. A trigger condition is a condition agreed in advance that, once it appears, starts the contingency plan, such as "delay of more than two weeks". As a study aid, you can separate general warning signs from the trigger conditions that launch a plan (the first makes you alert, the second makes you act). PMBOK 8 says the risk register may record risk triggers (events or conditions that indicate that a risk is about to occur), and the team may record other warning information as needed.
Fallback plans and workarounds
Common exam practice is to use these strategies only if a trigger occurs; PMBOK 8 lists them as contingent response strategies, and the terms contingency plan and fallback plan are common exam terms. Older PMI material and the exam often treat the two as names for the same kind of plan. Common exam practice also frequently describes the fallback plan as a backup used only when the contingency plan itself fails (a second layer of backup). When a question draws that distinction, follow the layering the stem gives. A workaround deals with a risk for which there was no plan in advance: it is improvised only after the problem occurs (exam questions usually say it applies to unidentified risks). Take the live-streaming risk "main CDN failure leaves viewers unable to watch":
- Contingency plan: the trigger is "buffering rate on the main CDN above 5% for 3 minutes in a row". When it is reached, switch to the backup CDN.
- Fallback plan (the second layer of backup in common exam practice): the backup CDN fails too, so stream from a local on-site encoder and publish a link to the recording.
- Workaround: on the day of the stream, construction crews accidentally cut power to the server room. Nobody identified this risk in advance and there is no plan, so the team has to move the stream to a temporary mobile server room on the spot.
| Name | Which risks it covers | Prepared in advance? | When it is used |
|---|---|---|---|
| Contingency plan | Identified risks | Yes, recorded in the risk register | When the trigger condition appears |
| Fallback plan (a common exam term: a second layer of backup) | Identified risks | Yes, as a backup to the contingency plan | When the contingency plan fails (common exam practice) |
| Workaround (a common exam term) | Risks with no plan in advance (usually called unidentified risks in exams) | No | Improvised after the risk occurs |
The working rule is this. When a risk occurs, check the risk register first. If an applicable response or contingency plan exists, carry it out. If there is no applicable plan in advance (the usual exam case is an unidentified risk), devise a workaround for the problem that has occurred, and then identify and analyze any new risks discovered along the way and add them to the register. If a workaround would change a baseline, it must go through change control. Common exam practice: in an emergency such as an earthquake, follow the organization's emergency change procedure to request and authorize the change quickly; even if it is started verbally, record it in writing promptly; a contingency action that was pre-authorized can be carried out immediately; do not assume you may act first and paper it later.
Secondary risk and residual risk
A secondary risk is a new risk that arises directly from carrying out a response. It would not exist if the original risk had not been addressed, and it must be identified, recorded and given a response plan. A residual risk is the part of a risk that remains after the planned response has been taken. If it is assessed as acceptable, record it and handle it with the accept strategy, and a contingency reserve may be set aside for it. For example, workers are asked to work overtime to finish before the rainy season. Fatigue-related accidents caused by continuous overtime are a secondary risk. Even after the overtime, a small chance remains that the work will not be finished before the rainy season: that is a residual risk.
Residual risk can be quantified. A cutover failure originally has an EMV of 30% × $80,000 = $24,000. After mitigation the probability falls to 5%, so the residual EMV is 5% × $80,000 = $4,000. You can set aside a contingency reserve for that $4,000 or simply accept it.
| Comparison | Secondary risk | Residual risk |
|---|---|---|
| Origin | A new risk created by the response | The part of the original risk that was not fully eliminated |
| A new risk? | Yes | No, it is still the original risk |
| How it is handled | Identify, record, plan a response | Record it; accept it or set aside a contingency reserve |
After planning: what to update, and why changes arise
The following update list is common exam practice. PMBOK 8 itself says only that the outputs of Plan Risk Responses include project document updates such as the risk register and the risk report. Update the risk register with: the agreed response strategies and actions; early warning signs and trigger conditions; the budget and schedule activities required; contingency plans, fallback plans, residual risk and secondary risk. The risk report records the agreed actions for high-priority risks and for overall risk exposure.
This process may produce a change request when a planned risk response requires a change to an approved baseline or another formally controlled plan component. Assess the impact first, submit the change request under the change management plan, and update the affected baseline or controlled document only after approval through the Assess and Implement Changes process.
Worked examples
Example 1: Core question: two layers of backup, and what each one is
The operating rooms in a hospital must have power around the clock. The facilities department has made arrangements in advance: if the main line loses power, it switches at once to a second utility feed; in addition it keeps a diesel generator set in case both utility feeds are unavailable. Under common exam practice, which of the following is this an example of?
Show answer and explanation
Correct answer: A
The operating rooms in a hospital must have power around the clock. The facilities department has arranged in advance: if the main line loses power it switches at once to a second utility feed, and it keeps a diesel generator in case both feeds are unavailable. You must decide what each of the two layers is.
PMBOK 8 calls strategies designed for use only if certain predefined conditions occur contingent response strategies; “contingency plan” and “fallback plan” are common exam terms for these. Both layers here were prepared in advance for an identified risk (a power loss). Under common exam practice: in the first layer, when the risk occurs the team follows the predefined steps and switches to the second utility feed, which is a contingency plan. The second layer, “in case both feeds are unavailable,” is a backup that comes into use only when the contingency plan fails, which is a fallback plan. This layering is common exam practice. A workaround is an improvised response developed after a threat occurs when no applicable response was planned. Both layers here were prepared in advance, so neither is a workaround and the answer is A.
Why the other options are wrong
- B. The second layer is not a workaround. A workaround is a makeshift fix thought up after the fact, whereas the diesel generator was prepared in advance, so under common exam practice it is a fallback plan.
- C. The first layer is not a workaround. A power loss is an identified risk, and switching to the second feed is a predefined step, so it is a contingency plan.
- D. The second layer is also planned in advance and is not an improvised reaction developed because no applicable response was available, so it does not fit a workaround. “Contingent response strategy” is also the name of the whole category and does not distinguish the two layers.
Key takeaway Responses prepared in advance and used when a trigger condition occurs are contingent response strategies. Under common exam practice, the contingency plan is the first layer, the fallback plan is the backup if it fails, and a workaround is improvised after a threat occurs when no applicable response was planned.
Variation If the cause of the failure had been something nobody anticipated and the team could only improvise, that would be a workaround, not a contingency plan or a fallback plan.
Something wrong with this question?
Example 2: Core question: watching the supplier, and what the remaining risk is called
A project manager temporarily takes over a project that is already under way. A key stakeholder warns that the SMS gateway provider the project now depends on has a poor reputation. The project manager assigns a team member to watch the provider's service quality full time, but even so this cannot guarantee that the service will not have problems. How should the project manager handle the risk that remains?
Show answer and explanation
Correct answer: C
A project manager temporarily takes over a project under way. A key stakeholder warns that the SMS gateway provider the project depends on has a poor reputation. The project manager assigns a member to watch the provider's service quality full time, but this still cannot guarantee that the service will not have problems. You must decide how to handle the risk that remains.
First characterize the “remaining risk.” (“Residual risk” and “secondary risk” are common exam terms.) Residual risk is the risk that remains after the planned response has been implemented. Assigning someone to monitor does not eliminate the risk: the possibility of service problems is still there; it is the part of the original risk that was not fully eliminated, so it is a residual risk and should be recorded in the risk register, with a contingency reserve set aside for it if needed. A secondary risk is a new risk created by the response itself, and no new risk appears here. The answer is C.
Why the other options are wrong
- A. A secondary risk is a new risk brought about by a response. Here the original provider risk has not been fully eliminated and no new risk has appeared, so it is not a secondary risk.
- B. The issue log records problems that have already happened. The service has not failed yet, so this is still an uncertain event that has not occurred and belongs in the risk register, not the issue log as a potential issue.
- D. Setting aside a contingency reserve for a residual risk is fine, but calling the reserve a workaround is wrong. A workaround (a common exam term) is improvised after a threat occurs when no applicable response was planned; here the risk has not occurred and a response arrangement already exists.
Key takeaway A residual risk is what is left of the original risk after the response; a secondary risk is a new risk the response creates. Record both.
Variation If assigning someone to watch the service quality had left the team short of people and created a new staffing risk, that new risk would be a secondary risk.
Something wrong with this question?
Common traps
Common trap
- A contingency plan covers a risk for which a plan was prepared and is started by a trigger condition. A workaround covers a risk with no plan in advance (commonly an unidentified risk).
- PMBOK 8 lists contingent response strategies as a tool; by common exam practice they are used only if a trigger occurs, and contingency plan and fallback plan are common exam and older-PMI terms. Common exam practice often describes the fallback plan as the backup used when the contingency plan fails, but in both cases the key is that the plan is prepared in advance and started by a trigger condition. A trigger may occur before the risk happens, or it may be the occurrence of the risk event itself, so a plan can include recovery steps taken after the event.
- A secondary risk is a new risk brought by a response. A residual risk is what remains of the original risk after a response.
- When an identified risk occurs, check the register and carry out the contingency plan first. Do not jump straight to a "workaround".
- In predictive environments, or wherever formal configuration control applies, a response that changes a baseline must go through a change request and be approved before the baseline is changed. Adaptive environments usually evaluate and reprioritize changes through the backlog and do not necessarily have a formal approval process.
- Contingency reserve is for identified risks (including residual risk). Management reserve is for unknown risks.
Key takeaways
Key point
- A contingent response strategy is launched by a trigger condition agreed in advance; it is often called a contingency plan (a common exam term).
- Fallback plan: a common exam term, often the backup used when the contingency plan fails. Workaround: improvise when there is no plan.
- Secondary risk: a new risk created directly by a response. Residual risk: the original risk that remains after a response, and a contingency reserve may be set aside for it.
- After planning, update the risk register: strategies and actions, triggers, budget and schedule activities, contingency and fallback plans, residual and secondary risks.
- When a response changes scope, schedule or cost, submit a change request and change the baseline only after approval.
This chapter has 48 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.