Risk
Decision Tree Analysis
PMP · Risk · 2 lessons · about 22 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Sometimes you must choose one of several alternatives, and the outcome of each is uncertain. Decision tree analysis draws the alternatives, the uncertain events and the outcomes as a tree, compares the alternatives by expected monetary value (EMV), and picks the best one. It is a quantitative data analysis technique within Perform Risk Analysis, and this chapter holds the most calculation questions in the risk topic. When the finance topic compares alternatives with probabilistic payoffs, it uses the same calculation.
By the end of this chapter you should be able to do the following. Recognize the three symbols: decision node, chance node and end of branch. Work out the EMV of each alternative in three steps (net path value, weight at chance nodes, take the maximum at decision nodes) and choose the best alternative. Judge how a change in probability affects the conclusion. Apply EMV to individual risks, with threats negative and opportunities positive, and total a group of risks. Understand the risk-neutral assumption behind EMV.
Lessons in this chapter
- Lesson 1: Decision tree symbols and expected monetary value (EMV). The square is our choice, the circle is an uncertain event decided by the environment, and the triangle is the end of a path; EMV is the sum of probability times net value; the three backward steps from right to left; how to draw a tree.
- Lesson 2: Worked decision trees and the EMV of risks. A full build-versus-expand example; the break-even probability; a multi-stage tree that validates before developing; the EMV of an individual risk; risk neutrality and risk attitude. It includes two calculation examples.
Chapter map
Decision node (square) — cost of each option
- Option 1 → chance node (circle) → each scenario: probability × net path value → node EMV
- Option 2 → chance node (circle) → each scenario: probability × net path value → node EMV
Take the largest EMV among the options → best alternative
Net path value = payoff − costs along the path; probabilities at one chance node sum to 100%
How the exam tests this
Questions in this chapter fall into three types. The first is recognizing symbols and rules, for example which node to draw for each of two choices, or what to do when the probabilities do not add up to 100%. The second is comparing alternatives: given probabilities, revenues and investments, calculate the EMV of each alternative and choose the best. The third is EMV at the risk level: multiply the probability by the impact for several threats and opportunities, then compare them or total them. The decision tree questions that compare alternatives use the same three backward steps, and the difficulty in all three types is care with negative numbers, investments and units.
Study tips and practice
- Work along with a pen and calculator instead of only reading. For every question, write out your work in this order: check that the probabilities total 100%, calculate the net path values, calculate the node EMVs, and finally take the maximum.
- The most common ways to lose points are dropping a negative number and deducting a cost twice. The common traps lists in Lessons 1 and 2 cover these.
- This chapter is easy to confuse with the other tools in Perform Risk Analysis: use a decision tree to choose among alternatives, Monte Carlo to ask about confidence, and sensitivity analysis to find the biggest impact.
Lesson 1
Decision Tree Symbols and Expected Monetary Value (EMV)
Lesson overview
You face several alternatives, and the result of each is uncertain: demand may be strong or weak, and a supplier may deliver on time or late. Which should you choose? Decision tree analysis draws the alternatives, the uncertain events and the outcomes as a tree, then calculates the expected monetary value (EMV) of each alternative so you can pick the best one with numbers. This lesson covers how to recognize and draw the three symbols, the EMV formula and the "right to left" calculation steps. The full worked examples and the EMV of risks are in the next lesson. ECO: Business Environment domain, Task 5 (Plan and manage risk).
What a decision tree is
Decision tree analysis is a diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty. Decision trees are used to support selection of the best of several alternative courses of action. Alternative paths through the project are shown in the decision tree using branches representing different decisions or events, each of which can have associated costs and related individual project risks (including both threats and opportunities). The end points of branches represent the outcome from following that particular path, which can be negative or positive. The decision tree is evaluated by calculating the expected monetary value of each branch, allowing the optimal path to be selected. Think of it as a "comparison table with probabilities": an ordinary comparison looks only at the best and worst cases, while a decision tree also factors in how likely each one is.
The three symbols and rules for drawing a tree
The names of the three legend symbols (decision node, chance node, end of branch) come from the legend of Figure 5-5 in PMBOK 8. The square, circle and triangle shapes are the usual way of drawing them on the exam.
| Symbol | Name | Meaning | Input and output |
|---|---|---|---|
| Square | Decision node | A choice the decision maker must make (we decide) | Input: cost of each option; output: the decision made |
| Circle | Chance node | An uncertain event outside the decision maker's control (the environment decides) | Input: probability and outcome of each scenario; output: the EMV of the node |
| Triangle | End of branch | The end of a path | Net path value = payoff − costs along the path |
To tell a square from a circle, ask one question: "who decides?" Whether to outsource, or which supplier to choose, is our choice and gets a square. Once we outsource, whether the supplier delivers on time and whether demand is strong or weak are beyond our control and get a circle.
There are three rules for drawing a tree. The probabilities on the branches leaving one chance node must add up to 100%; if they do not, a scenario is missing or an estimate is wrong. Write the net path value at the end of each path, equal to the payoff minus the costs along the path. Branches from a decision node need no probabilities, because we choose which one to take. The steps are: write down the decision and the alternatives, draw a chance node for each alternative and mark the probabilities, then mark the net path value at each triangle; if another choice follows, attach another decision node. Many errors come from drawing the tree wrongly rather than from arithmetic: drawing something the environment decides as a square, or leaving out a scenario.
Expected monetary value (EMV)
Expected monetary value (EMV) is the estimated value of an outcome expressed in monetary terms. It is the sum of the products of each possible outcome and its probability:
is the probability of scenario i, and the probabilities at one node add up to 1. is the net value of that path, equal to the payoff minus the costs along the path. EMV is "if you did this many times, the average result each time". It is not a result that will actually occur on any single occasion.
Worked example: expected income of a training class
A training project runs one in-person class. With a 50% probability enrollment is high and net profit is $80,000. With a 30% probability enrollment is average and net profit is $30,000. With a 20% probability enrollment is low and there is a $40,000 loss.
- First check the probabilities: 50% + 30% + 20% = 100%.
- Multiply each: 0.5 × 80 = 40, 0.3 × 30 = 9, 0.2 × (−40) = −8 (in thousands of dollars).
- Add them: EMV = 40 + 9 − 8 = $41,000.
The actual result will be only one of $80,000, $30,000 or −$40,000, but if the same class is run many times, the average profit per class is $41,000.
Work through the whole tree backward from right to left in three steps: (1) calculate the net path values (payoff minus costs along the path); (2) calculate the EMV at each chance node (probability-weighted sum); (3) take the maximum at the decision node, and the corresponding option is the best path. You work from right to left because the choice on the left can be compared only once the outcomes on the right are known. With several decisions in series, calculate the rightmost first and work back level by level to the left.
Decision trees are often used early in a project, for example for make-or-buy, whether to invest more, or whether to run a pilot first. Monte Carlo looks at the overall range and sensitivity analysis finds the key factors, while a decision tree puts the "choice" itself into the model and chooses among alternatives.
Worked examples
Example 1: Core question: where to draw the square and the circle
A project manager is drawing a decision tree for the choice “whether to buy a component from an outside supplier” and for the uncertain event “whether the supplier delivers on time after purchase”. Which symbols should be used for these two, respectively?
Show answer and explanation
Correct answer: C
When drawing a decision tree for a choice among alternatives, you must pick symbols for “whether to buy a component from outside” and for “whether the supplier delivers on time after purchase”. The question asks which symbol each takes.
To tell the symbols apart, ask one question: “who decides?” Whether to buy is the project's own choice, so it is a decision node (square). Whether the supplier delivers on time is beyond the project's control and is an uncertain event, so it is a chance node (circle). The triangle only marks the end of a branch, the end point of a path. So the order is square, circle. The legend of Figure 5-5 in PMBOK 8 uses the square for a decision node, the circle for a chance node and the triangle for the end of a branch. The answer is C.
Why the other options are wrong
- A. Circle, square reverses the order. The decision maker's own choice should be a square, and only an uncontrolled uncertain event is a circle.
- B. The first item is a choice, yet it takes a triangle. A triangle marks the end of a branch; it represents neither a choice nor an uncertain event.
- D. The second item is an uncertain event and should be a chance node, a circle. A triangle is the end of a path and does not represent the event itself.
Key takeaway Square: we choose (decision). Circle: the environment decides (chance). Triangle: end of branch.
Variation “Whether to run a proof of concept” is a square, and “whether the validation result is good or poor” is a circle. The end of every path is always a triangle, marked with the net path value.
Something wrong with this question?
Example 2: Core calculation: the EMV of two alternatives
The sponsor and executive team of a consulting firm are preparing the business case for a new project and have two alternatives. Alternative 1: 40% probability of success, with a profit of $150,000 on success, and a total loss of the $50,000 invested on failure. Alternative 2: 60% probability of success, with a profit of $200,000 on success, and a total loss of the $100,000 invested on failure. Which statement is correct?
Show answer and explanation
Correct answer: B
In the business case stage, both alternatives have two outcomes, success and failure. They are compared by EMV, and the question asks which statement is correct.
EMV is the sum of each outcome's probability times its net value, and a loss on failure enters the calculation as a negative number. Calculate both branches of each alternative, then check the alternative and the figure in each of the four options. The EMV of Alternative 1 is $30,000 and that of Alternative 2 is $80,000, so Alternative 2 has the higher expected return. The answer is B.
- Alternative 1: 0.4 × 150 + 0.6 × (−50) = 60 − 30 = $30,000
- Alternative 2: 0.6 × 200 + 0.4 × (−100) = 120 − 40 = $80,000
- Probability check: the probabilities of both alternatives total 100%
- Comparison: 80 is greater than 30, so Alternative 2 has the higher expected return, matching option B
Why the other options are wrong
- A. Mixes up the two EMVs: Alternative 1 is actually $30,000, and it is Alternative 2 that is $80,000.
- C. 100 = 200 − 100: this subtracts the failure loss directly from the success profit without multiplying by the probabilities, so it is not an expected value.
- D. 60 = 0.4 × 150: this calculates only the success branch and leaves out the failure branch of −$30,000, so the figure is too high.
Key takeaway EMV = Σ (probability × net value). Calculate both the success and failure branches, with failure negative.
Variation If Alternative 2's probability of success fell to 40%, EMV = 0.4 × 200 − 0.6 × 100 = $20,000, below Alternative 1's $30,000, and the conclusion would flip.
Something wrong with this question?
Common traps
Common trap
- The square is a decision node (we choose), the circle is a chance node (the environment decides) and the triangle is the end of a branch.
- The probabilities on the branches of one chance node must add up to 100%. A decision node needs no probabilities: compare the EMVs directly and take the maximum.
- Failures and losses enter the calculation as negative numbers. Dropping the minus sign is the most common error.
- The net path value already has the cost subtracted, so do not deduct it again after calculating EMV.
- EMV is a weighted average, not a result you are sure to get on any one occasion. A decision tree is a quantitative technique, not a qualitative tool for rating risks.
Key takeaways
Key point
- Decision tree: diagramming plus calculation, used to choose the best of several alternatives under uncertainty; a data analysis technique in quantitative risk analysis.
- Symbols: the square is a decision node, the circle is a chance node and the triangle is the end of a branch.
- The probabilities on the branches of one chance node add up to 100%.
- Net path value = payoff − costs along the path; EMV = Σ (probability × net value).
- Three backward steps: calculate net path values, take the weighted sum at chance nodes, take the maximum at decision nodes.
- Signal in the question: two or more alternatives, each with probabilities and amounts, and you must pick the highest expected value.
Lesson 2
Worked Decision Trees and the EMV of Risks
Lesson overview
The previous lesson introduced the symbols, the EMV formula and the three backward steps. This lesson puts them to work: you walk through a complete two-alternative decision tree, see how the conclusion changes when a probability changes, and then look at a multi-stage tree. After that you apply EMV to individual risks, with threats negative and opportunities positive, and total several risks. This lesson has the most calculation questions, so work through them by hand. ECO: Business Environment domain, Task 5 (Plan and manage risk).
A full example: build new or expand
Worked example: build a new logistics center or expand the existing warehouse?
Market demand is uncertain: strong demand has a 60% probability and weak demand 40%.
- Alternative A, build new, with an investment of $800,000. Revenue is $1,500,000 under strong demand and $600,000 under weak demand.
- Alternative B, expand, with an investment of $300,000. Revenue is $800,000 under strong demand and $450,000 under weak demand.
Step 1: net path values (revenue − investment): A strong $700,000, A weak −$200,000, B strong $500,000, B weak $150,000.
Step 2: EMV at each chance node
- A: 0.6 × 700 + 0.4 × (−200) = 420 − 80 = $340,000
- B: 0.6 × 500 + 0.4 × 150 = 300 + 60 = $360,000
Step 3: take the maximum at the decision node. $360,000 is greater than $340,000, so choose alternative B. The EMV of the decision is $360,000.
The best outcome for A is more attractive, but there is a 40% chance of losing $200,000, and weighted, A comes out lower. A decision tree puts the "best result" and "how likely it is" side by side, so you are not drawn to the most eye-catching number. You can also calculate the EMV of the revenue first and then subtract the investment; the result is the same, but the investment can be deducted only once.
If the probability changes, does the conclusion change?
Let p be the probability of strong demand. Then A = 900p − 200 and B = 350p + 150 (in thousands of dollars). The two are equal when p ≈ 63.6%, called the break-even probability. If the probability of strong demand is above it, A is better; below it, B is better. The question gives 60%, slightly below, so B is chosen. If research revises it to 70%, A is $430,000 and B is $395,000, and the conclusion switches to A.
Multi-stage decisions: validate first or just build
A decision tree can chain several decisions: a chance node can be followed by another decision node. The calculation still starts at the far right, and each time you return to a decision node you choose the best path (when paths are expressed as payoffs or signed net values, take the largest number; when only cost or loss amounts are listed as positive figures, take the smallest amount), and then treat that value as the outcome of the path one level up.
Worked example: should we run a proof of concept first?
The development investment is $300,000. After success, revenue is $700,000, and after failure it is $100,000, so the net path value of developing is +$400,000 on success and −$200,000 on failure.
- Develop directly, with a 49% probability of success: EMV = 0.49 × 400 + 0.51 × (−200) = $94,000.
- Validate first, for $20,000. When the result is good (40%), the probability of success rises to 85%: EMV of developing = 0.85 × 400 − 0.15 × 200 = $310,000, so develop. When the result is poor (60%), the probability of success falls to 25%: EMV of developing = 0.25 × 400 − 0.75 × 200 = −$50,000, so do not develop, and that branch is worth 0 before the fee (the $20,000 fee is deducted once, at the validation node).
- EMV of the validation node = 0.4 × 310 + 0.6 × 0 − 20 = $104,000.
104 is greater than 94, so validate first. The gross gain from validation (before the fee) is 124 − 94 = $30,000. After the $20,000 fee, the net gain is 104 − 94 = $10,000, which is still better than developing directly (validation pays off as long as its fee is under $30,000). Choosing "do not develop" when the result is poor avoids a loss, which is the value of a multi-stage tree.
Applying EMV to individual risks
The EMV of an individual risk = probability × impact. Common exam practice: the EMV of an opportunity is normally shown as positive and the EMV of a threat as negative, and the EMVs of a group of risks are added to give the expected total gain or loss. For example, a threat with a 30% probability and a $40,000 loss has an EMV of −$12,000, and an opportunity with a 20% probability and a $150,000 gain has an EMV of +$30,000. Common exam practice: to compare which risk most deserves attention, rank by the absolute value of the EMV (in practice, threats and opportunities are usually ranked and treated separately). PMBOK 8 says contingency reserves are for identified risks and may also be developed using quantitative analysis methods. Common exam practice: the EMVs of opportunities and threats can be combined into an expected total gain or loss. Common exam practice: when the question asks you to "set a contingency reserve for threats", add up only the EMVs of the threats and do not offset them with the gains from opportunities. When the question asks for the overall expected gain or loss, or net risk exposure, include opportunities and threats together. First check which basis the question is asking for.
EMV rests on the assumption of risk neutrality: the decision maker neither avoids nor seeks risk and looks only at the weighted average. A sure $50,000 and a 50% chance of $100,000 both have an EMV of $50,000. A risk-averse person takes the first and a risk-seeking person takes the second; EMV does not reflect this attitude.
Worked examples
Example 1: Core question: build in-house or buy, which to choose?
PMLyceum must choose how to implement a new data analytics module (see the decision tree in the figure, which shows amounts in thousands of dollars). Alternative A is to build in-house, with an investment of $120,000. Alternative B is to buy an off-the-shelf product, with an investment of $50,000. The probability of high market demand is 40% and of low demand 60%. In-house development brings revenue of $300,000 under high demand and $100,000 under low demand. Buying brings revenue of $150,000 under high demand and $80,000 under low demand. By EMV, which alternative should be chosen, and what is the EMV of the whole decision?
Show answer and explanation
Correct answer: D
At the stage of choosing an alternative, demand is uncertain, and a decision tree is used to compare building in-house (A) with buying (B) and to find the EMV of the whole tree. The stem gives revenues and investments.
The stem gives revenues and investments, so first calculate the net path values (revenue minus investment), then weight by probability at the chance nodes and finally take the larger at the decision node. The investment is deducted only once. A's EMV is $60,000 and B's is $58,000, A is larger, and the EMV of the whole decision is $60,000. The answer is D.
- Probability check: 40% + 60% = 100%
- Net path values: A high 300 − 120 = 180, A low 100 − 120 = −20; B high 150 − 50 = 100, B low 80 − 50 = 30 (in thousands)
- EMV(A) = 0.4 × 180 + 0.6 × (−20) = 72 − 12 = $60,000
- EMV(B) = 0.4 × 100 + 0.6 × 30 = 40 + 18 = $58,000
- Take the maximum at the decision node: 60 is greater than 58, so choose A and the decision EMV is $60,000
Why the other options are wrong
- A. B's EMV of $58,000 is calculated correctly, but it is smaller than A's $60,000. At the decision node you take the larger, and you cannot treat the smaller as the best.
- B. 180 is actually the net path value of the high-demand branch of A (300 − 120). It takes a single branch, with no weighting and no low-demand branch.
- C. 72 = 0.4 × 180 is the weighted value of the high-demand branch only and leaves out the low-demand branch, 0.6 × (−20) = −$12,000.
Key takeaway Calculate the net path values first, then weight by probability, and finally take the maximum at the decision node. Deduct the investment only once.
Variation The two EMVs differ by only $2,000, which is very close. In that case go back and check whether the probability estimates are reliable, and use the break-even probability to judge whether the conclusion could flip.
Something wrong with this question?
Example 2: Core question: four uncertain events, which first?
A project manager has four newly identified uncertain events. Threat A: probability 70%, and if it occurs cost increases by $50,000. Threat B: probability 20%, cost increases by $250,000. Opportunity A: probability 50%, can save $90,000. Opportunity B: probability 10%, can save $400,000. Using expected monetary value analysis and ranking by the absolute value of EMV (the size of the expected effect), which has the greatest effect?
Show answer and explanation
Correct answer: C
At the risk analysis stage there are two threats and two opportunities. The question asks which has the greatest effect when ranked by the absolute value of EMV using expected monetary value analysis.
The stem requires “expected monetary value analysis”, so calculate the EMV of each item: probability times impact, with threats negative and opportunities positive. The question explicitly ranks by absolute value (the size of the expected effect), not by probability or amount alone. Ranking threats and opportunities together by absolute value is common exam practice, but in practice threats and opportunities are usually ranked and treated separately. Among the four, Threat B has the greatest expected effect. The answer is C.
- Threat A: −0.7 × 50 = −$35,000
- Threat B: −0.2 × 250 = −$50,000
- Opportunity A: +0.5 × 90 = +$45,000
- Opportunity B: +0.1 × 400 = +$40,000
- Compare absolute values: 50 > 45 > 40 > 35, so the largest is Threat B
Why the other options are wrong
- A. Threat A has the highest probability (70%) but a small amount, so its EMV is only −$35,000, less than Threat B's $50,000.
- B. Opportunity B has the largest single effect ($400,000) but a probability of only 10%, so its EMV is only +$40,000, third in rank.
- D. Opportunity A's EMV is +$45,000, less than Threat B's $50,000.
Key takeaway Calculate EMV before comparing. The highest probability or the largest amount does not necessarily give the largest EMV.
Variation If you look only at threats, it is still Threat B; if only at opportunities, it is Opportunity A (45 is greater than 40). If the question asked for the total contingency reserve for threats, add up only the threats: 35 + 50 = $85,000.
Something wrong with this question?
Common traps
Common trap
- Subtract the investment first to get the net path value, then multiply by the probability; do not deduct it again after calculating EMV.
- At a chance node take the weighted sum; at a decision node choose the best path: when paths are expressed as signed net values take the largest number, and when only cost or loss amounts are listed as positive figures take the smallest amount. Do not mix these up.
- Assign each endpoint the actual net result of its path: a loss is a negative number, and a failed path that has already incurred costs must not be written as zero.
- The EMV of a threat is negative and that of an opportunity positive; compare size by absolute value (common exam practice).
- The risk with the highest probability does not necessarily have the largest EMV, and neither does the one with the greatest impact.
- Common exam practice: when setting contingency reserve for threats, do not offset with the gains from opportunities; when the question asks for total gain or loss or net risk exposure, include opportunities and threats together.
- EMV is a weighted average and assumes a risk-neutral decision maker.
Key takeaways
Key point
- Three steps: net path values, weighted sum at chance nodes, best path at decision nodes (when paths are expressed as payoffs or signed net values, take the largest number; when only cost or loss amounts are listed as positive figures, take the smallest amount).
- First check that the probabilities total 100%, then multiply term by term, without dropping a minus sign or deducting a cost twice.
- A change in probability can change the conclusion. When the EMVs of two alternatives are close, check the probabilities; the break-even probability is the one at which the two are equal.
- For multi-stage decision trees, work back from the far right to the left, choosing the best path at each decision node: take the largest number when paths are expressed as payoffs or signed net values, and the smallest amount when only cost or loss amounts are listed as positive figures.
- EMV of an individual risk = probability × impact; opportunities positive, threats negative.
- EMV assumes a risk-neutral decision maker and does not reflect attitude toward the worst outcome.
This chapter has 13 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.