Risk
Quantitative Risk Analysis
PMP · Risk · 3 lessons · about 32 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Qualitative analysis answers "which risks matter more?" Quantitative analysis answers "taken together, where will the project end up?" This chapter belongs to the Perform Risk Analysis process in risk management. It covers the role of the quantitative part and three groups of tools: simulation (mainly Monte Carlo analysis), sensitivity analysis and influence diagrams, and it shows how to pick the right tool from the wording of a question. Decision tree analysis is also a quantitative tool and has its own chapter next.
By the end of this chapter you should be able to do the following. Explain how quantitative and qualitative analysis divide the work. Describe the inputs, method and outputs of Monte Carlo analysis. Read an S-curve and work out a budget and a contingency reserve from a confidence level. Read a tornado diagram and find the factor with the greatest impact. Choose among simulation, sensitivity analysis, decision trees and influence diagrams from the signals in the question.
Lessons in this chapter
- Lesson 1: The role of quantitative risk analysis and Monte Carlo simulation. Why quantitative analysis is done and why not every project needs it; Monte Carlo has the computer draw random values again and again and outputs a probability distribution; criticality analysis counts how often an activity falls on the critical path.
- Lesson 2: The S-curve, confidence levels and contingency reserve. The S-curve has cost or date on the horizontal axis and the probability of not exceeding that value on the vertical axis; given a budget, find the confidence, and given a confidence, find the budget; contingency reserve equals the cost at the target confidence level minus the base estimate. Includes a full worked calculation.
- Lesson 3: Sensitivity analysis, influence diagrams and choosing a quantitative tool. Hold the other factors fixed, change one at a time and draw a tornado diagram; an influence diagram shows causes and the order of events; use Monte Carlo for confidence, sensitivity analysis for the biggest impact and a decision tree for choosing among options.
Chapter map
| Question to answer | Tool | Output | Lesson |
|---|---|---|---|
| Where do the objectives land when the uncertainties combine | Simulation (Monte Carlo) | Histogram, S-curve | 1, 2 |
| How confident can we be of finishing within budget, and how much contingency reserve is needed | Reading the S-curve | Confidence level, contingency reserve | 2 |
| Which factor has the greatest effect on the outcome | Sensitivity analysis | Tornado diagram | 3 |
| How variables influence one another | Influence diagram | S-curve, tornado diagram | 3 |
| Which of several alternatives to choose | Decision tree analysis | EMV of each alternative | Next chapter |
Study tips and practice
- First separate "overall" from "one by one": quantitative analysis looks at overall project risk, using numbers.
- You must be able to read Monte Carlo results, but you do not need to operate the software. Practice the chart-reading method in Lesson 2 until it needs no thought.
- This chapter's questions concentrate on "choosing the tool" and "reading the result". In practice questions, first underline the signal words in the stem, then match them to a tool.
- The next chapter, decision tree analysis, has the most calculation. Finish the three lessons here before moving on.
Lesson 1
Quantitative Risk Analysis and Monte Carlo Simulation
Lesson overview
Qualitative analysis answers "which risks matter more?" and ranks them by priority. Quantitative analysis answers "taken together, where will the project end up?" and speaks in numbers. This lesson covers why quantitative risk analysis is done and what it produces, and then the most commonly used technique, Monte Carlo analysis. ECO: Business Environment domain, Task 5 (Plan and manage risk). The next lesson uses these results to draw an S-curve and set a contingency reserve.
Quantitative risk analysis: what it does
Quantitative risk analysis numerically analyzes the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives. Its viewpoint is "overall": the core is to quantify the combined effect of all the uncertainties on the overall objectives and see what range cost and schedule may end up in (sensitivity analysis can also compare how large each risk's impact is). It is often used to answer questions such as: how confident are we of finishing within the current budget; how much more budget or time is needed to raise that confidence; and which risks have the biggest impact.
| Comparison | Qualitative risk analysis | Quantitative risk analysis |
|---|---|---|
| Question answered | Which risks matter more and which to handle first | The numeric effect of the risks combined on cost and schedule |
| Form of result | Priority, high/medium/low, probability and impact matrix | Probability distribution, S-curve, tornado diagram, EMV |
| Object examined | Individual risks | Mainly overall project risk |
| Always required? | Normally always done | Depends on the project; done when needed |
Quantitative analysis is not mandatory and can be performed throughout the project. It quantifies opportunities as well as threats; counting only threats would make the overall result too pessimistic. PMBOK 8 combines qualitative and quantitative analysis in the Perform Risk Analysis process, and the quantitative tools are filed under data analysis: simulation, sensitivity analysis, decision tree analysis and influence diagrams.
Key point
The keywords for quantitative analysis are "overall" and "numeric". Wording such as "combined effect" or "how confident are we of finishing" signals quantitative; wording such as "prioritize", "high/medium/low" or "probability and impact matrix" signals qualitative.
Monte Carlo analysis: let the computer calculate again and again
Simulation models the combined effects of individual project risks and other sources of uncertainty to evaluate their potential impact on achieving project objectives. The most common technique is Monte Carlo analysis. It represents uncertainty with probability distributions and has the computer calculate repeatedly under different combinations of assumptions and risks to produce the possible outcomes.
Start with a small hand calculation. Design review A takes 3 or 5 days, and integration testing B takes 2 or 4 days, each with a 50% probability. Assume the two durations are independent, and the total duration is C = A + B. The four combinations give 5, 7, 7 and 9 days, so C is not a single fixed number: 5 days and 9 days each have a 25% probability and 7 days has 50%. In real projects, many activity durations are uncertain and a model may contain hundreds of activities, so calculating all combinations by hand is impractical. Instead the computer draws random values and adds them up thousands of times, and counts how often the total duration falls in each interval.
The method has four steps (common exam practice):
- Inputs: depending on the objective, use cost estimates with their probability distributions, or a schedule network model with duration estimates and their probability distributions (a triangular distribution is common, defined by an optimistic, a most likely and a pessimistic value).
- Random draws: the software draws a value for each uncertain input according to its distribution and calculates the total cost or total duration for that run.
- Many iterations: run a large number of random iterations. The number depends on the accuracy and convergence required, and thousands or more are common in practice.
- Output: organize the results into a histogram and then accumulate them into a cumulative probability distribution, which is the S-curve.
For example, take a small project with three uncertain costs. In iteration 1 the draws are design $42,000, development $188,000 and testing $31,000, for a total of $261,000. In iteration 2 they are $38,000, $205,000 and $36,000, for a total of $279,000. In iteration 4 the development cost happens to come out high, and the total is $311,000. With several thousand rows of totals side by side, you can see which intervals occur often and which are rare. The exam does not ask you to operate the software. Remember that the output is a probability distribution, not a single-point estimate.
Running Monte Carlo on a schedule model also supports criticality analysis (common exam practice in schedule risk analysis): count the share of iterations in which each activity falls on the critical path. If the simulation runs 10,000 times and integration testing is on the critical path in 8,200 of them, its criticality index is 82%. Activities with a high share are the ones that most often hold up the whole schedule, so focus on them and plan responses.
Schedule-based Monte Carlo analysis needs a schedule model and duration distributions; cost or flow-based simulations use the corresponding cost or flow model. Many adaptive projects deal with uncertainty through short iterations or flow-based work combined with frequent feedback, and Monte Carlo analysis based on a detailed schedule network is more common in predictive and hybrid settings. Common exam practice: quantitative-analysis questions are often framed in predictive situations, although the techniques can also be used in hybrid and adaptive settings.
Many factors changing together, or one at a time
Monte Carlo lets many uncertain inputs vary together according to their probabilities and reflects overall risk. Sensitivity analysis answers "which one matters most": in PMBOK 8 it correlates variations in project outcomes with variations in the elements of the model, and it usually shows the correlation coefficients in a tornado diagram. Common exam practice: simulation changes many factors at once, while sensitivity analysis is often done by "holding the other factors at their baseline values and changing one at a time". (The hand-calculated example in this lesson is Monte Carlo style, with several factors varying at once, so it is simulation.)
Worked examples
Example 1: Scenario: qualitative analysis is done, what next?
A project manager has just taken over a drone inspection system project that is in the planning phase. The team tells her that all the identified risks have been ranked by priority. The sponsor now asks for numbers showing the combined effect of these risks on the cost and schedule objectives. What should the project manager do next?
Show answer and explanation
Correct answer: D
A drone inspection system project is in the planning phase and the identified risks have all been ranked by priority. The sponsor wants numbers showing the combined effect of these risks on the cost and schedule objectives. You must judge the next step in the risk analysis flow.
“Already ranked by priority” shows that qualitative risk analysis is done; the ranking settles “which to manage first”. What the sponsor wants now are “numbers” and the “combined effect”, that is, a quantified conclusion on overall project objectives, which is the task of quantitative risk analysis: a numeric analysis of the combined effect of identified risks. The core evidence is the two words “numbers” and “combined”. The scenario does not ask for new risks to be found or for response measures. So the next step is quantitative risk analysis. The answer is D.
Why the other options are wrong
- A. Concentrating on the top-ranked risks is how the ranking is used. The sponsor wants numbers, not an order of priority, so this option does not answer the question.
- B. Recording additional sources of risk is work in the Identify Risks stage. Although identification can continue, once the risks are ranked, adding sources cannot give the numeric combined effect the sponsor wants, and it is not the action to take now.
- C. Developing a response plan for each risk is Plan Risk Responses and comes after analysis. Quantitative analysis is not a universal prerequisite for response planning, but here the sponsor explicitly asks for the combined effect to be quantified, so that analysis need should be met first and the responses refined from it.
Key takeaway After qualitative ranking, when you must show the overall effect of risks with numbers, the next step is quantitative risk analysis.
Variation If the sponsor asked only “which risk should be handled first?”, the ranking already answers it and no quantitative analysis is needed. If the question were “how confident are we of finishing within the current budget?”, quantitative analysis is still needed, using Monte Carlo simulation.
Something wrong with this question?
Example 2: Identifying the technique: thousands of iterations and a cumulative probability curve
To evaluate overall project risk, a risk analysis group uses software to iterate its quantitative risk analysis model thousands of times and draws a cumulative probability curve (S-curve) showing the probability that project cost will not exceed each value. Which technique are they using?
Show answer and explanation
Correct answer: B
A risk analysis group is evaluating overall project risk. It uses software to iterate the model thousands of times and draws a cumulative curve of the probability that cost does not exceed each value. You must judge the quantitative technique from the method and the output.
The stem has two markers: software that iterates the model thousands of times, and an output that is a cumulative probability curve, the S-curve. Each iteration draws random values from the distributions of the uncertain factors and calculates one result, and thousands of results accumulate into the “probability that cost does not exceed a given figure”. This is the typical approach of simulation, and the most common simulation technique is Monte Carlo analysis. Decision tree analysis and sensitivity analysis do not use this kind of large-scale random iteration to generate an S-curve; an influence diagram can yield an S-curve only when its model is evaluated using a simulation technique such as Monte Carlo analysis. The answer is B.
Why the other options are wrong
- A. Decision tree analysis multiplies the probability and payoff of each branch to compare the expected monetary values of alternatives. Its output is a number for each alternative; it does not iterate and has no cumulative probability curve.
- C. Sensitivity analysis (common exam practice) varies one factor at a time with the rest held still, and outputs a tornado diagram sorted by size of effect. It answers “which factor matters most”, not the overall probability distribution.
- D. An influence diagram only represents the causal relationships and dependencies among variables, and it does not iterate by itself. To get the distribution of outcomes from the relationships in an influence diagram you still need Monte Carlo, and it cannot produce an S-curve on its own.
Key takeaway Software iterating repeatedly and a cumulative probability curve (S-curve) point to Monte Carlo analysis.
Variation In a question such as “which of the following is a technique available for quantitative risk analysis?”, the probability and impact matrix, SWOT analysis and assumption and constraint analysis are not quantitative techniques; they are tools for qualitative analysis or for identifying risks.
Something wrong with this question?
Common traps
Common trap
- "Quantitative analysis must always be done" is wrong; it is done as the project requires.
- Monte Carlo is not a single calculation but a large number of iterations (thousands or more are common). The output is a probability distribution, not a single number.
- Criticality analysis counts the share of iterations in which an activity is on the critical path. It is not total float.
- Quantitative analysis quantifies opportunities as well as threats.
- The probability and impact matrix and risk categorization are not quantitative techniques; they are often slipped into the answer options.
Key takeaways
Key point
- Quantitative risk analysis numerically analyzes the combined effect of risks on overall objectives. The keywords are "overall" and "numeric".
- It is done as the project needs, can run throughout the project, and quantifies both threats and opportunities.
- Its tools are filed under data analysis: simulation, sensitivity analysis, decision tree analysis and influence diagrams.
- Monte Carlo: input the estimates and distributions, draw random values, iterate thousands of times, and output a histogram and an S-curve.
- Criticality analysis counts how often an activity is on the critical path; activities with a high count get focused management.
- Common exam practice: many factors changing together is simulation; one factor at a time is sensitivity analysis. In PMBOK 8, sensitivity analysis correlates variation in the outcome with variation in each model element.
Lesson 2
The S-Curve, Confidence Levels and Contingency Reserve
Lesson overview
The result of a Monte Carlo simulation is a probability distribution of the project outcome. Accumulate it into a cumulative probability curve and it is usually S-shaped, which exams and practice habitually call the S-curve. (Note that this differs from the cost-versus-time S-curve diagram in the PMBOK 8 glossary, "a graph that displays cumulative costs over a specified period of time.") This lesson teaches you to read the curve and to answer the three questions a project manager is asked most often: is the current budget enough, how much more is needed for greater confidence, and how much contingency reserve should be held. It is the most down-to-earth lesson in quantitative analysis, because it turns risk analysis directly into a budget and a date. ECO: Business Environment domain, Task 5 (Plan and manage risk). Monte Carlo from the previous lesson is the prerequisite; for the cost baseline and contingency reserve, see the cost management topic.
What the S-curve is and how to read it
The several thousand Monte Carlo iterations are first drawn as a histogram: the horizontal axis is total cost and the height is the number of iterations falling in that interval. Accumulate the bars from left to right and you get a cumulative probability curve. It is steep in the middle and flat at both ends, resembling the letter S, hence the name S-curve. The horizontal axis is total project cost (or finish date), and the vertical axis is the probability that actual total cost will not exceed that value.
There are two ways to read it, and you use both:
- Given a budget, find the confidence. Find the budget on the horizontal axis, go up to the curve, then left to the vertical axis to read the probability of finishing within budget.
- Given a confidence, find the budget. Find the probability on the vertical axis, go right to the curve, then down to the horizontal axis to read the budget required.
This probability is the confidence level. "The budget at 85% confidence" is the budget for which you are 85% sure that actual cost will not exceed it. Dates work the same way: you can read the probability of finishing by a given date.
How to do it: set the contingency reserve from the S-curve
Common exam practice: conservative organizations often choose a higher confidence level such as 75% or 85%, while organizations willing to take on risk can choose a lower one. Once the level is chosen:
The base estimate is normally the sum of the activity estimates before contingency reserve is added. (PMBOK 8 notes that cost estimates may include contingency reserves; if the activity estimates already include contingency reserve, remove it first and then apply the method in this lesson.) Contingency reserve addresses identified risks and is usually included in the cost baseline (PMBOK 8 allows it to be placed outside the initial budget according to organizational preferences or external factors). Management reserve addresses unknown risks, is not in the cost baseline, and cannot be obtained directly from an S-curve.
Worked example: an equipment installation project
The base estimate is $380,000. A simulation gives these points on the curve:
| Total cost ($) | 340,000 | 360,000 | 380,000 | 400,000 | 420,000 | 440,000 | 460,000 |
|---|---|---|---|---|---|---|---|
| Probability of not exceeding | 5% | 20% | 45% | 70% | 85% | 95% | 99% |
Step 1: given the budget, find the confidence. A budget of $380,000 corresponds to 45%, which is less than even odds.
Step 2: given the confidence, find the budget. The sponsor wants 85% confidence, which corresponds to $420,000.
Step 3: find the contingency reserve. $420,000 − $380,000 = $40,000, about 10.5% of the base estimate.
Step 4: check. Budget = $380,000 + $40,000 = $420,000, which corresponds to 85%, so the requirement is met.
If 75% were required and is not in the table, interpolate in a straight line between 70% ($400,000) and 85% ($420,000): $400,000 + (75 − 70)/(85 − 70) × $20,000 ≈ $407,000, so the reserve is about $27,000. The exam generally gives you the points directly or has you read them off a chart.
Dates work the same way. Suppose the schedule simulation shows a 55% probability of finishing by 30 September and 80% by 15 October. To have 80% confidence, the delivery date should be set at 15 October. If 30 September is the planned finish date without reserve, then the extra 15 days needed to reach 80% confidence is the schedule contingency reserve. If 30 September is not defined that way, the 15 days is simply the gap between the 55% confidence date and the 80% confidence date.
Confidence level and the shape of the curve
The higher the confidence, the larger the reserve and the more money and time are tied up. How high to go therefore depends on the risk appetite and risk thresholds of the organization and its key stakeholders, and is agreed by the stakeholders with the relevant governance authority. Higher is not always better.
The shape of the curve carries information too. A steeper curve means results are concentrated and uncertainty is small. A flatter curve means a wider range, and buying 10% more confidence costs a lot more budget. If the whole curve shifts right, newly identified threats or upgraded threats are usually the cause. After the proposed responses are implemented and the simulation is rerun, compare the cost or date at the same confidence level. When the responses work, the curve usually shifts left or becomes steeper, but it may also simply change shape, and the response measures themselves may add cost or time. Before comparing, check whether the rerun already includes the cost or duration of the responses themselves. If it does, the difference between quantiles at the same confidence level is the net effect and nothing more should be deducted. If it does not, deduct the cost of the measures from the benefit of the risk reduction before deciding whether they are worthwhile. When the baseline or the risks change, update the curve.
Predictive projects often use cost or schedule models and rerun simulations as risks and estimates change, while adaptive projects may also use simulation or forecast ranges to communicate likely release outcomes. In either environment, report "a range plus a confidence level" rather than a lone number.
Worked examples
Example 1: Core question: confidence is 70% and must be raised to 90%; which technique?
At a budget review meeting for a data platform migration project, the project manager says that, with several risks acting together, the confidence of completing the project within the current budget is 70%. The sponsor asks how much additional budget would be needed to raise that confidence to 90%. Which technique should the project manager use to answer?
Show answer and explanation
Correct answer: A
At a budget review for a data platform migration project, the project manager says that with several risks acting together the confidence of finishing within the current budget is 70%. The sponsor asks how much more budget is needed to raise the confidence to 90%. You must decide which technique answers this question.
“Several risks acting together” and “confidence” are both probability statements at the level of the whole project. Monte Carlo simulation combines the risks and uncertainties and iterates to obtain a cumulative probability distribution of cost, the S-curve, with cost on the horizontal axis and the probability of not exceeding that cost on the vertical axis. A 70% confidence corresponds to one cost point on the curve and 90% to another, and the difference between the two points is the additional budget, usually held as contingency reserve. One probability corresponding to one budget is exactly how an S-curve is read. The answer is A.
Why the other options are wrong
- B. Sensitivity analysis finds the factors with the greatest effect on objectives. It gives no correspondence between overall completion confidence and budget, so it cannot answer “how much more”.
- C. Decision tree analysis compares the expected monetary value of several alternative courses of action. The stem has no alternatives to choose among; instead, it requires reading the costs associated with different confidence levels from a cumulative cost distribution.
- D. Alternative analysis picks one from several response or implementation options. It does not output a correspondence between “confidence” and “budget”, so it cannot answer how much additional budget.
Key takeaway “How much confidence, how much extra budget”: read the two costs for the two probabilities from the Monte Carlo S-curve and subtract.
Variation If the S-curve shows $5,000,000 at 70% and $5,600,000 at 90%, the additional budget is 5,600,000 − 5,000,000 = $600,000. If the question were changed to “the probability of finishing by the end of October”, it is still Monte Carlo, only with the S-curve in terms of schedule.
Something wrong with this question?
Example 2: Concept question: what does the analyst deliver each quarter?
The project manager asks the risk analyst to run a quantitative analysis of overall cost risk every quarter and to submit the results. What should the analyst submit?
Show answer and explanation
Correct answer: B
The project asks the risk analyst to run a quantitative analysis of overall cost risk every quarter and to submit the results. You must judge what the typical result of this quantitative analysis is.
The most common way to analyze overall cost risk quantitatively is Monte Carlo simulation: put the cost uncertainties into a model and iterate repeatedly to obtain a probability distribution of cost. This distribution is often drawn as a cumulative probability curve, the S-curve, from which management can read the probability that cost will not exceed a given figure and then set the contingency reserve. So the result is a cumulative probability distribution curve. The other three are outputs about individual risks or groups of risks, not quantitative conclusions about overall cost risk. The answer is B.
Why the other options are wrong
- A. The probability and impact matrix is a result of qualitative risk analysis. It grades and ranks individual risks by probability and impact and does not give a probability distribution of overall cost.
- C. A risk categorization summary groups risks by source or area affected to show where risk is concentrated. It is a qualitative organization of information and contains no numeric probability conclusions.
- D. The watch list records low-priority risks that are not being actively addressed for now. It is a product of qualitative analysis and has nothing to do with quantitative analysis of overall cost risk.
Key takeaway The typical result of quantitative analysis (Monte Carlo) is a cumulative probability curve (S-curve), used to read probabilities and reserves.
Variation If the question asked “what is the output of Monte Carlo?”, the answer is a probability distribution of a range of outcomes, often represented by a histogram or cumulative probability curve, rather than a single-point estimate or priority ranking. If it asked what to use to grade individual risks, it is the probability and impact matrix.
Something wrong with this question?
Common traps
Common trap
- The horizontal axis is total cost (or date) and the vertical axis is the probability of not exceeding that value. Read it backward and nothing lines up.
- Contingency reserve = total cost at the target confidence level − base estimate, not the total cost itself.
- The confidence level is an organizational choice; higher is not always better.
- Contingency reserve covers identified risks, while management reserve covers unknown risks and is not given by the S-curve.
- If the curve is drawn for cost, talk about adding budget; if it is drawn for dates, talk about extending the schedule.
Key takeaways
Key point
- The S-curve is a cumulative probability curve: total cost or date on the horizontal axis, the probability of not exceeding that value on the vertical axis.
- Two ways to read it: given a budget, find the confidence; given a confidence, find the budget.
- The confidence level is the likelihood of finishing within budget. Common exam practice: conservative organizations often choose a higher value such as 75% or 85%.
- Contingency reserve = total cost at the target confidence level − base estimate excluding reserve.
- Wording such as "confidence", "raise to a certain probability" or "how much more" points to Monte Carlo and the S-curve.
- The higher the confidence, the larger the reserve; weigh it against the sponsor's needs.
Lesson 3
Sensitivity Analysis, Influence Diagrams and Choosing a Quantitative Tool
Lesson overview
Monte Carlo tells us where the project as a whole "lands". Management's next question is: which few factors should we watch? That is what sensitivity analysis answers. This lesson first covers sensitivity analysis and the tornado diagram, then briefly the influence diagram, and finally puts the four quantitative risk analysis tools side by side so you can pick the right one from a question's wording, which is where this chapter loses the most points. ECO: Business Environment domain, Task 5 (Plan and manage risk).
Sensitivity analysis and the tornado diagram
Sensitivity analysis helps to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes. The method is "controlling variables": hold every other factor at its baseline value, let one factor vary across its range at a time, record how much total cost or total duration changes, then move to the next factor and finally compare them. This is the one-factor-at-a-time approach used in this lesson (a common exam way to tell the techniques apart: sensitivity analysis moves one factor at a time). PMBOK 8 defines sensitivity analysis as correlating variations in project outcomes with variations in elements of the quantitative risk analysis model, and the tornado diagram displays the correlation coefficient of each element with the outcome.
The results are shown in a tornado diagram. Each bar represents a factor, and its length reflects the factor's effect on the outcome (PMBOK 8 uses the correlation coefficient between the element and the project outcome). Bars are ordered from the largest effect at the top to the smallest at the bottom, wide at the top and narrow at the bottom, like a tornado.
Take a plant construction project with a baseline total cost of $1,200,000. The results of varying each factor on its own are:
| Factor | Total cost range ($ thousand) | Swing ($ thousand) |
|---|---|---|
| Steel price fluctuation | 1,130 to 1,290 | 160 |
| Design changes | 1,150 to 1,260 | 110 |
| Labor rates | 1,170 to 1,245 | 75 |
| Exchange rate movement | 1,180 to 1,230 | 50 |
| Severe weather | 1,190 to 1,225 | 35 |
| Approval cycle | 1,195 to 1,210 | 15 |
Reading the chart takes three steps. Look at the ranking: the longest bar, steel price fluctuation, has the greatest effect, and the first two factors have the largest one-factor swings, so management effort should go to them first, for example by locking in steel prices or hedging and by tightening change control. Look at the direction: a steel price rise could cost up to $90,000 more, while a fall saves only $70,000, which shows that this factor is skewed toward cost overruns. Look at the bottom: the approval cycle swings total cost by only $15,000 in this example, so it is less sensitive. Whether to accept it or use another response should still be decided together with its probability, its effect on other objectives such as schedule, and the risk thresholds (common exam practice: when you have only the tornado diagram, the factor at the bottom can be accepted and monitored first).
A tornado diagram does not show the probability that a risk occurs by itself; it orders the model elements by the strength of their correlation with the project outcome. If the model already includes probability distributions or occurrence probabilities, that information affects the ordering. Common exam practice: when a question gives only swings, treat them as "impact only". A factor with a large impact that will almost never occur and a factor with a moderate impact that is very likely to occur are hard to tell apart on the chart, so combine the chart with the probability judgments from qualitative analysis. Factor ranges change, so repeat the analysis as the project advances.
Influence diagrams
An influence diagram is a graphical tool for making decisions under uncertainty. It shows causal influences among variables and outcomes, the time ordering of events and other relationships. Elements made uncertain by risks are represented with ranges or probability distributions, and the diagram is then evaluated with a simulation technique such as Monte Carlo analysis to find which elements have the greatest influence on key outcomes. The outputs are similar to those of other quantitative methods, such as S-curves and tornado diagrams. For example, on a smart-hardware project, equipment failure affects prototype building, staff turnover affects circuit design and supplier delay affects getting materials ready, and all three paths lead to the "prototype completion date". The exam asks about this rarely; remember the two keywords "cause and effect" and "time ordering".
How to choose among the four tools
| Tool | Question it answers | Typical output | Signals in the question |
|---|---|---|---|
| Simulation (Monte Carlo) | Where the outcome lands overall, and how confident we can be of meeting the target | Histogram, S-curve | "confidence", "probability", "how much more budget" |
| Sensitivity analysis | Which factor has the greatest effect | Tornado diagram | "which has the greatest impact", "change one factor at a time" |
| Decision tree analysis | Which of several alternatives has the highest EMV | EMV of each alternative | "alternatives", "probability and amount", "which to choose" |
| Influence diagram | How variables influence each other | S-curve, tornado diagram | "cause and effect", "order of events" |
Look at the "shape" of the question. If it asks for the confidence of meeting a target, or the budget needed at a given confidence, that is simulation. If it asks "which is biggest", that is sensitivity analysis. If it asks "which option to choose", that is a decision tree. If it asks "how they influence each other", that is an influence diagram.
Sensitivity analysis vs. Monte Carlo
Sensitivity analysis (common exam practice: one factor at a time) outputs a tornado diagram and tells you "who matters most". Monte Carlo lets all the factors vary together according to their distributions and outputs an S-curve that tells you "where the whole lands and how confident we are". The two complement each other: the tornado diagram finds the priorities and the S-curve gives the conclusion, and they are often done in the same round of analysis.
Worked examples
Example 1: Core question: it is unclear which risk has the greatest impact
The sponsor is worried that the project has several risks but cannot say which one has the greatest effect on the cost objective. Which tool should the project manager use to address this concern?
Show answer and explanation
Correct answer: D
The sponsor is worried that the project has several risks but cannot say which has the greatest effect on the cost objective. The project manager must choose a suitable tool to address this concern.
“Which one has the greatest effect” is about the relative size of each factor's effect, which is exactly what sensitivity analysis answers. In PMBOK 8 it correlates variations in project outcomes with variations in elements of the quantitative risk analysis model, and the results are usually shown in a tornado diagram. By common exam practice, the analysis lets “one uncertain factor at a time vary across its range” and sees how much total cost changes, then arranges the factors from largest effect to smallest. The bars at the top correspond to the factors that most deserve priority management. What is needed here is “ranking by size”, not “comparing options” or “finding causes”. The answer is D.
Why the other options are wrong
- A. Decision tree analysis compares the expected monetary value of alternative courses of action. The stem has no options to choose among, and it is not comparing the size of the effects of the risks.
- B. A cause-and-effect (fishbone) diagram traces the causes of a problem and helps find root causes. It does not quantify the effect of each risk on the cost objective and cannot rank them by size.
- C. SWOT analysis is used to identify risks by laying out strengths, weaknesses, opportunities and threats. It gives no numeric effect of each risk on cost and cannot answer “which is greatest”.
Key takeaway To know which risk or factor has the greatest effect, use sensitivity analysis, with the result drawn as a tornado diagram.
Variation If the question were changed to “find out how much each factor affects cost on its own”, the answer is still sensitivity analysis. If it asked “which piece of risk work is this?”, the answer is quantitative analysis within Perform Risk Analysis.
Something wrong with this question?
Example 2: Comprehensive question: three questions, three techniques
At a risk analysis meeting, the sponsor asks three questions in a row: (1) which of several uncertain factors has the greatest effect on total cost; (2) how confident can we be of finishing the project within the current budget; (3) which of two alternatives has the higher expected monetary value. Which group of techniques should the project manager use to answer, in order?
Show answer and explanation
Correct answer: B
At a risk analysis meeting, the sponsor asks three questions at once: which uncertain factor has the greatest effect on total cost, how confident we can be of finishing within the current budget, and which of two alternatives has the higher expected monetary value. You must match a suitable technique to each of the three questions in order.
Look for the signal in each question. (1) “Greatest effect” compares the size of each factor's effect, so use sensitivity analysis. (2) “How confident we can be of finishing” asks for an overall probability, so use Monte Carlo analysis to obtain an S-curve. (3) “Expected monetary value” and “two alternatives” is a comparison of options, so use decision tree analysis. In order, that is sensitivity analysis, Monte Carlo analysis, decision tree analysis. The four options are only different orderings of these three techniques, and when all three questions are matched correctly the answer is unique. The answer is B.
Why the other options are wrong
- A. This swaps (1) and (2). Monte Carlo mainly gives the probability distribution of the overall result, and to compare the size of each factor's effect directly you should use sensitivity analysis (simulation results can also be used for sensitivity ranking after correlation analysis). Sensitivity analysis itself cannot give the confidence of finishing within budget.
- C. This swaps (2) and (3). A decision tree compares the expected monetary value of options and cannot give the confidence of finishing. Monte Carlo can model outcome distributions for different decisions or courses of action, but the explicit request to compare expected monetary value calls for decision tree analysis. Both are mismatched.
- D. Only (2) happens to be right. (1) is wrong: a decision tree compares options and cannot find the factor with the greatest effect. (3) is wrong: sensitivity analysis looks only at the size of a single factor's effect and cannot calculate the expected monetary value of alternatives.
Key takeaway Choose the tool by the question: greatest effect means sensitivity analysis, confidence of finishing means Monte Carlo, and comparing options means a decision tree.
Variation If the three questions are reworded as “the probability of finishing within budget”, “which option to choose” and “which factor has the greatest effect”, the matching does not change: Monte Carlo, decision tree, sensitivity analysis, matched correctly whatever the order.
Something wrong with this question?
Common traps
Common trap
- Common exam practice: sensitivity analysis changes one factor at a time, while Monte Carlo changes many at once. In PMBOK 8, sensitivity analysis correlates variation in outcomes with variation in model elements.
- The length of a tornado diagram bar represents the size of the effect, not the probability of occurrence.
- Sensitivity analysis finds "the most important factor"; it does not answer "how confident are we of finishing within budget".
- A decision tree compares the EMV of alternatives; it does not answer "which risk has the greatest impact".
- A cause-and-effect diagram is a tool for finding causes, not a quantitative risk analysis tool. An influence diagram shows causes and time ordering, represents uncertain elements with distributions, and is evaluated by simulation.
Key takeaways
Key point
- Sensitivity analysis finds the factor with the greatest effect. The approach in this lesson holds other factors at their baseline values and changes one at a time.
- Tornado diagram: bars represent factors, ordered from largest effect at the top to smallest at the bottom, wide at the top and narrow at the bottom.
- Influence diagram: shows causal influences and the time ordering of events, represents uncertain elements with distributions, and is evaluated with simulation.
- Choose the tool by the question: confidence means Monte Carlo, greatest impact means sensitivity analysis, choosing among options means a decision tree, cause and effect means an influence diagram.
- Sensitivity analysis finds the priorities and Monte Carlo gives the overall range; the two complement each other.
This chapter has 15 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.