What this chapter covers

Once the risk register holds a long list of risks and resources are limited, the next question is "which ones do we manage first?" PMBOK 8 combines qualitative and quantitative analysis into one process, Perform Risk Analysis. This chapter covers the whole process and its qualitative part: assessing probability and impact, scoring and ranking risks with a matrix, putting low-probability, low-impact (low-priority) risks on the watch list, grouping risks by source, and finally writing the results back into the project documents.

The chapter has a small amount of calculation. When a numeric scale is used, a risk score can be calculated as probability × impact (with a descriptive scale, risks are ranked by priority rules set in advance). When impact is expressed as money, probability × amount gives the expected monetary value (EMV), which can serve as one reference for estimating contingency reserve. PMBOK 8 places EMV in decision tree analysis, a quantitative technique; it is borrowed here to illustrate "probability times amount". The exam more often asks scenario questions: what to do after risks are identified, how to handle a pile of low-rated risks, and how to categorize risks by source. The value of qualitative analysis is that it saves effort: it compresses twenty or thirty risks into a handful of priorities, puts low-probability, low-impact risks on the watch list, and keeps managing the rest in priority order.

Lessons in this chapter

Chapter map

Perform Risk Analysis (iterative)

  • Qualitative (always done, ranks risks): probability and impact assessment → matrix (numeric scale: score = probability × impact; descriptive scale: rank by predefined rules) → risk categorization → priorities, watch list
  • Quantitative (as needed, numeric): simulation · sensitivity analysis · decision tree analysis · influence diagrams

Key inputs: risk management plan (definitions, matrix, thresholds), risk register (plus baselines, assumption log, estimates, stakeholder register, enterprise environmental factors, organizational process assets, etc.)

Outputs: risk register, risk report, assumption log, issue log (project document updates)

Chapter practice: start with the core questions, then do the required questions.

Lesson 1

Perform Risk Analysis: Qualitative vs. Quantitative, Rank First and Dig Deeper Later

Lesson video

Lesson overview

The risk register already holds a long list of risks. Resources are limited, so you cannot devote the same response effort to every risk, and the next question is "which ones do we manage first?" That is what PMBOK 8 calls Perform Risk Analysis. This lesson covers the whole process: what qualitative and quantitative analysis each do, the inputs, tools and outputs, and where the process sits in the flow. The most common question type describes risks that have just been identified and asks "what should the project manager do next?" The answer is qualitative risk analysis. The next two lessons break qualitative analysis down in detail, and quantitative analysis comes in a later chapter.

Perform Risk Analysis: one process, two kinds of analysis

PMBOK 8 merges the former Perform Qualitative Risk Analysis and Perform Quantitative Risk Analysis into a single process: Perform Risk Analysis, "the process of analyzing risks using an iterative approach that may combine qualitative and quantitative risk analyses."

  • Qualitative risk analysis evaluates each identified individual project risk by assessing its probability of occurrence and impact, and ranks the risks by priority. In one sentence: qualitative analysis is for ranking. Despite the name, it still uses data; the data is simply less precise and often comes from expert judgment. It is conducted throughout the project and is always done.
  • Quantitative risk analysis is not always required and depends on the project. When it is used, it numerically analyzes the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives.

On the exam, the usual reasoning is "rank qualitatively first, then dig deeper quantitatively as needed": use qualitative analysis to decide the order, then run quantitative analysis on the few top risks and other sources of uncertainty (common exam practice). PMBOK 8 does not prescribe a fixed order, though; the two kinds of analysis can be iterated and combined. Many projects need only the qualitative part.

Qualitative vs. quantitative

  • Qualitative: the object is each individual risk; the methods are probability and impact assessment, the matrix and categorization; the result is a priority ranking; always done.
  • Quantitative: the object is the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives (sensitivity analysis can also show which individual risks or sources of uncertainty have the most impact); the methods are simulation, sensitivity analysis, decision tree analysis and influence diagrams; the result is a number; done as needed.

Inputs, tools and outputs

ItemContent
InputsProject management plan (risk management plan, the three baselines); project documents (assumption log, estimates, resource requirements, risk register, stakeholder register); enterprise environmental factors; organizational process assets
Tools and techniquesExpert judgment; interviews; facilitation; risk categorization; data analysis (risk probability and impact assessment, simulation, sensitivity analysis, decision tree analysis, influence diagrams); probability and impact matrix
OutputsProject document updates (assumption log, issue log, risk register, risk report)

Probability and impact assessment, the matrix and categorization are used for qualitative ranking; simulation, sensitivity analysis, decision trees and influence diagrams produce numbers and are used for quantitative analysis. The most important input is the risk management plan. Its definitions of probability and impact, the matrix, the risk categories and the thresholds of key stakeholders are the yardsticks for assessment, while the risk register holds the risks being assessed.

Where it sits in the flow

The six processes of the Risk performance domain run in this order: Plan Risk Management, Identify Risks, Perform Risk Analysis, Plan Risk Responses, Implement Risk Responses, Monitor Risks. When Monitor Risks turns up something new, you loop back to earlier processes for another round.

Figure 1: Order of the six Risk performance domain processes

Here is a small example that walks through the sequence. A community weekend market identifies two risks: rain (which would cost $6,000 in refunded vendor fees) and some vendors not showing up (a $2,000 loss). Qualitative: assess both probability and impact on the agreed scales; rain ranks first because it has both the higher probability (40% versus 20%) and the larger potential impact. Quantitative: expected loss by probability is 40% × $6,000 = $2,400 for rain and 20% × $2,000 = $400 for no-shows, $2,800 in total, which is used to judge the effect on the market's overall budget. Response: mitigate rain (if a rain canopy is rented in advance, the loss from rain drops to $1,000) and accept no-shows while reserving backup stalls. Monitor: on the day it does not rain but three vendors fail to appear, which triggers the backup stall plan. The result of every step is written back into the risk register.

How to decide "what next"

These questions almost always describe a risk that has "just been identified" and ask for the next step. A risk just identified, with no probability or impact assessed yet, calls for qualitative risk analysis. If the stem says to "focus on high-priority risks", "evaluate how important each risk is" or "rank the risks", that is qualitative. If it says to "estimate the combined effect on the overall schedule or cost" or "compare options numerically", that is quantitative (common exam practice: when a quantitative estimate is needed, qualitative analysis usually comes first to find the focus; PMBOK 8 does not require ranking to be complete before quantitative analysis, and the two can be iterated and combined). If the risks are already ranked and you must choose actions, that is Plan Risk Responses.

In practice, qualitative analysis is usually run as a meeting or interviews. Before the session, distribute the register, the probability and impact definitions, and the matrix. In the session, first agree on how each risk is described, then rate probability and impact separately. When opinions differ, ask for the reasoning instead of voting, and record the assumptions behind each rating. Afterward, calculate scores, set priorities, write them back to the register and confirm owners for the high-priority risks. Adaptive projects do this more lightly and more often: at the start of each iteration they quickly assess new risks, rank them qualitatively, and add quantitative analysis only when it is really needed.

Worked examples

Example 1: After identification, focus on high-priority risks

Question 1Example

A project manager is leading a new-energy battery development project. Team members have identified the sources of various risks and built a risk register. The project manager wants to concentrate effort on the high-priority risks. What should be done next?

Show answer and explanation

Correct answer: C

Risks have been identified and entered in the register, so the project is at the analysis stage of risk management. The project manager wants to focus limited effort on the high-priority risks, and you must decide what to do “next”.

The deciding signal is “concentrate on the high-priority risks”. To know which risks are high priority, you must first rank each one. The qualitative part of Perform Risk Analysis assesses the probability and impact of each individual risk and uses the probability and impact matrix to set priorities, so that the team can focus on the high-priority risks. It is also the natural next step after identification. In practice, qualitative analysis is usually used first to decide the focus, and quantitative analysis then digs deeper, as needed, into the key risks and overall risk. Decision tree analysis is itself one of the quantitative techniques, and none of these is the first thing to do now. The answer is C.

Why the other options are wrong

  • A. The sources of risk have been identified and the register is built, so identification is already done. Identification also only finds and records risks; it cannot put them in order.
  • B. Quantitative risk analysis primarily examines the combined effect of risks and uncertainty on overall project objectives and expresses the result numerically. It does not rank individual risks by probability and impact (although sensitivity analysis can show which risks have the greatest potential effect on project outcomes), and not every project requires it, so it is not the first step in ranking here.
  • D. Decision tree analysis is a quantitative technique that compares alternatives by EMV. It solves a choice among options and cannot give the high-to-low order of the risks.

Key takeaway After identification, priorities must be set: do qualitative risk analysis first, and then decide which risks deserve quantitative analysis.

Variation If the stem says the top three risks are already ranked and you must calculate their combined effect on total project cost, then quantitative risk analysis is next. If it says some risks have not yet been found, the answer returns to identifying risks.

Something wrong with this question?

Report an issue with this question

Example 2: A stakeholder is worried: assess first, then respond

Question 2Example

PMLyceum plans to cut over its inventory management system from the old system to the new one over a weekend. Several key stakeholders believe the cutover may take longer than planned. What should the project manager do?

Show answer and explanation

Correct answer: B

The weekend cutover of the inventory system has not happened yet. Key stakeholders think it may overrun the time window, and the question asks what the project manager should do.

“Believe it may take longer than planned” is a clue to a risk. It is not a problem that has already occurred, and no data confirms it. The order in risk management is to assess first and respond afterward: find out the probability that the cutover overruns the window and what consequences that would have, and then choose to add people, extend the window or take other action. Changing the plan or the schedule without an assessment is acting by reflex. The answer is B.

Why the other options are wrong

  • A. Adding people is a response. Changing the plan before assessing means you do not know how big the problem is, and you may add cost for nothing.
  • C. The risk management plan is a guiding document. The stem does not say the plan itself is flawed, and the answer for a specific risk is not in the plan, so reviewing the plan does not address the concern.
  • D. Extending the window directly is also a response made without assessment. The concern has not yet been verified with data, and changing the window may disturb the business downtime arrangements.

Key takeaway When you hear “something may go wrong”, assess its probability and consequences first, then choose a response. Do not change the plan directly.

Variation If the stem said “the cutover has already overrun”, the risk has become an issue and action should be taken immediately. If it said “the probability of overrunning the window has been assessed as very high”, the next step would be Plan Risk Responses.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • When risks have been identified and you need to rank them and focus on the high-priority ones, do qualitative risk analysis; the tool is the probability and impact matrix.
  • The matrix and probability and impact assessment are for ranking. Using numbers to estimate overall risk or compare options is quantitative analysis.
  • Quantitative analysis is not always required; qualitative analysis always is.
  • PMBOK 8 merges qualitative and quantitative analysis into one process, Perform Risk Analysis, so do not count seven risk processes any more. And "qualitative" does not mean "no data".

Key takeaways

  1. PMBOK 8 merges qualitative and quantitative analysis into Perform Risk Analysis, performed iteratively.
  2. Qualitative analysis assesses each risk's probability and impact and ranks priorities, throughout the project; quantitative analysis is done as needed and analyzes the combined effect on overall objectives.
  3. Ranking tools: probability and impact assessment, the matrix, risk categorization. Numeric tools: simulation, sensitivity analysis, decision trees, influence diagrams.
  4. The most important input is the assessment yardstick in the risk management plan; the outputs are updates to the risk register, risk report and other documents.
  5. After identification, the next step is Perform Risk Analysis, usually qualitative first.

Lesson 2

Risk Probability and Impact Assessment and the Probability and Impact Matrix

Lesson video

Lesson overview

Qualitative analysis has two core moves: assess the probability and impact of each risk, then use a matrix to rank them. This lesson covers how to assess, how to guard data quality, how scores are calculated and what to do with low-scoring risks. Exam questions here are mostly scenario-based, but you must be able to calculate "probability × impact" and to estimate reserves from products of probability and amount. The previous lesson covered the whole process; the next one covers risk categorization and outputs.

Risk probability and impact assessment

Risk probability assessment considers the likelihood that a specific risk will occur. Risk impact assessment considers the potential effect on project objectives such as schedule, cost, quality or performance; impacts are negative for threats and positive for opportunities. The two dimensions are assessed separately; you cannot give just one overall rating.

Assessment is usually done in interviews or meetings. Participants are chosen for their familiarity with the types of risk recorded in the register, and they can include knowledgeable people from outside the project. Score using the definitions in the risk management plan, so that everyone's "high" means the same thing. Differences in the levels perceived by stakeholders are to be expected; explore them, and record the assumptions and reasons that justify the level assigned.

Guard data quality. Data will never be precise and often rests on expert judgment, but it must not be wildly off: if a risk that would cost only $10,000 is estimated at $1,000,000, the whole ranking is distorted. Before assessing, confirm the data source, its accuracy and whether it is biased; all of this has to be checked during probability and impact assessment. When the basis changes, reassess: if a probability was estimated against an early technical design, verify those assumptions and data after the design changes. Other characteristics can also be considered: manageability, proximity (how soon the risk may occur and its impact appear), relationships with other risks, and common causes.

The probability and impact matrix

The probability and impact matrix maps each risk's probability of occurrence and its impact on project objectives onto a grid. Threats and opportunities share one matrix, using negative impact definitions on the threat side and positive impact definitions on the opportunity side. When numeric values are used, probability and impact are multiplied to give a probability–impact score that allows the relative priority of individual risks to be compared. Prioritization rules may be specified by the organization in advance or tailored to the project.

Figure 1: Probability and impact matrix (threats and opportunities shown symmetrically)

In the figure, dark cells are high priority, light cells are medium and blank cells are low. The boundaries between levels are set by the organization in the risk management plan. The example in the figure treats a score of 0.24 or more as high, anything above 0.05 and below 0.24 as medium and 0.05 or less as low.

Worked example: scoring and ranking risks

A campus student-registration system is being upgraded. The impact scale is 0.05 / 0.10 / 0.20 / 0.40 / 0.80:

RiskTypeProbabilityImpactScoreLevel
A. Server overload at the registration peakThreat0.700.400.28High
B. Payment channel temporarily suspendedThreat0.300.800.24High
C. Legacy data formats inconsistentThreat0.900.200.18Medium
D. The school opens registration earlyOpportunity0.300.400.12Medium
E. Text-message channel delayThreat0.100.100.01Low, watch list

Ranking: A > B > C > D > E. Risk B has a probability of only 0.30 but ranks second because its impact is very large, while risk C, with a probability of 0.90, ranks lower. The ranking depends on the product, not on probability alone. Opportunity D is scored with the same yardstick, and you consider separately how to exploit it.

Probability times amount gives the expected monetary value (EMV; EMV is a quantitative-analysis calculation, which PMBOK 8 uses in decision tree analysis, and it is borrowed here to illustrate probability times amount). It can serve as one reference for estimating contingency reserve. If a risk would cost $8,000 when it occurs and has a 25% probability, the expected loss is $2,000, not $8,000. Take three threats with losses of $12,000 (30%), $5,000 (50%) and $20,000 (10%). The expected losses are $3,600, $2,500 and $2,000, for a total expected loss of $8,100, not the $37,000 you get by adding up the losses. This total is an expected value in the long-run statistical sense and can be an input to reserve analysis; the actual reserve must also take into account correlation among risks, probability distributions, risk appetite and simulation results. Common exam practice: in simple questions, treat the total expected loss as the contingency reserve.

Low-probability, low-impact risks do not call for heavy management effort. Include them in the risk register as part of a watch list for future monitoring. They are not ignored: review them periodically, and reassess if probability or impact changes. Opportunities are also scored and ranked, with impact defined positively. An opportunity in a high-priority area is one that lands in a high-priority cell under the matrix rules: typically high probability and large positive impact, though one dimension can also be very high so that the product reaches the threshold.

Worked examples

Example 1: How to manage many low-rated risks

Question 1Example

On a smart speaker development project, the project manager has a team member track risks. The member reports that the register holds many risks whose probability and impact are both very low and does not know how to manage them. How should the project manager advise?

Show answer and explanation

Correct answer: B

The register holds many risks whose probability and impact are both very low, and the team member does not know how to manage them. The question asks how the project manager should advise on allocating effort.

“Both probability and impact very low” corresponds to the low-priority area of the matrix. Such risks do not need heavy effort. They go on the watch list in the risk register and are reviewed periodically, and if their probability or impact rises they are reassessed. Effort goes to the high-priority risks. In this way nothing is missed and no resources are wasted. The answer is B.

Why the other options are wrong

  • A. Tracking everything to the same degree dilutes effort, so high-priority risks do not get enough attention. It violates the principle of allocating resources by priority.
  • C. Low-priority risks must still be recorded. Their priority may rise when conditions change, and without a record you lose the chance to monitor them. Waiting until they occur and treating them as issues is a passive approach.
  • D. Making a detailed plan and setting aside dedicated funds for every low-priority risk puts in effort out of proportion to the benefit. It is over-management.

Key takeaway Low-probability, low-impact risks go on the watch list for periodic review. They are neither ignored nor a focus of investment.

Variation When the probability of a watch-list risk rises because of external change, reassess it and, if necessary, take it off the watch list and plan a response. If a risk is high probability and high impact, a response plan is needed.

Something wrong with this question?

Report an issue with this question

Example 2: Where an opportunity sits in the matrix

Question 2Example

In a probability and impact matrix, what is the most typical feature of an opportunity located in the high-priority area?

Show answer and explanation

Correct answer: D

Threats and opportunities are placed in the same probability and impact matrix. The question asks what characterizes an opportunity located in the high-priority area.

The matrix sets priority from predefined rules for combining probability and impact, and when numeric scoring is used the product of probability and impact can be calculated. For an opportunity, impact means the positive benefit if it occurs. High probability together with large positive impact is the most typical case of a high-priority opportunity, although the exact zones depend on the matrix the project uses. An opportunity with a high likelihood and a large benefit is both likely to occur and highly rewarding if it does, so it deserves priority attention. The answer is D.

Why the other options are wrong

  • A. Low probability, large benefit: whether it falls in the high-priority area depends on the matrix definitions in the risk management plan, and it can be high priority when the product reaches the threshold, but that is not the “most typical” feature. The most typical case is large on both dimensions at once.
  • B. High probability but a small benefit gives a product that is not high, so it usually falls in the medium or low priority area. It also does not satisfy “large on both dimensions”.
  • C. What goes on the watch list are risks with both low probability and low impact, the opposite of “high priority”. A low-probability opportunity can reach a high-priority cell only if its impact is extremely large and the product reaches the threshold, which is not the most typical feature.

Key takeaway In the matrix, both opportunities and threats get their priority from the combination of probability and impact, and high probability with high impact is the most typical high-scoring case.

Variation If the question asked about a threat in the high-priority area, it would be high probability with a large negative impact, which needs a response arranged first. If it asked for the next step after finishing the register at identification, the answer is to assess probability and impact using the definitions in the plan.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Assess probability and impact separately, then multiply to get a score. Do not give a single overall rating.
  • When the basis for an assessment changes, verify the assumptions and data and reassess if needed; do not keep the old rating.
  • Low-probability, low-impact risks are not ignored; they go on the watch list and are reviewed periodically.
  • The boundaries between levels are set by the plan, so do not memorize the 0.24 in the figure. Opportunities must also be scored and ranked.
  • If impact is expressed in money, probability × amount gives the expected monetary value, which can be one reference for setting contingency reserve (not the sum of all losses; PMBOK 8 also allows a reserve to be a percentage of the estimated cost, a fixed number, or developed with quantitative analysis methods). Matrix scoring is for ranking; it is not a response tool.

Key takeaways

  1. Assess probability and impact separately (negative impact for threats, positive impact for opportunities), score with the definitions in the plan, and record the assumptions and reasons.
  2. Data must be reliable: verify source, accuracy and bias, and reassess when the basis changes.
  3. Score = probability × impact. Threats and opportunities share one matrix, and the level boundaries are set by the plan.
  4. When impact is in money, the contingency reserve can be estimated as probability times amount (the total expected loss) rather than adding up worst cases.
  5. Low-probability, low-impact risks go on the watch list and are reviewed periodically. After identification, assess first, and only then talk about responses.

Lesson 3

Risk Categorization and the Outputs of Perform Risk Analysis

Lesson video

Lesson overview

Once risks are ranked, two things remain. One is to group the risks so you can see which parts of the project are most exposed to uncertainty; this is risk categorization. The other is to write the results of the analysis back into the project documents so that later response and monitoring have a record to work from. The focus here is categorizing by source using the four top-level categories of the risk breakdown structure (RBS), a common exam topic, followed by the outputs of the process. Quantitative methods come in a later chapter, and responses in the chapter on risk response strategies.

Risk categorization

Risk categorization identifies the areas of the project most exposed to the effects of uncertainty. The team can then concentrate effort on the areas of highest risk exposure, or develop a generic response for a group of related risks. There are three bases for categorizing: by source of risk (using the RBS: technical, management, commercial, external); by area of the project affected (using the WBS, to find the work packages where risk is most concentrated); and by other useful categories (project phase, project budget, roles and responsibilities). Risks can also be grouped by common root cause. If three risks all stem from one carrier's lack of capacity, replacing the carrier or adding a backup carrier is a single response that reduces all three at once.

Categorizing by source: the four RBS categories

The sample RBS in PMBOK 8 (see the figure in the lesson on Plan Risk Management) has four top-level categories, each broken into subcategories:

CategoryLevel 2 examples
Technical riskScope definition, requirements definition, estimates, assumptions and constraints, technical processes, technology, technical interfaces
Management riskProject management, program/portfolio management, operations management, organization, resourcing, communication
Commercial riskContractual terms and conditions, internal procurement, suppliers and vendors, subcontracts, client/customer stability, partnerships and joint ventures
External riskLegislation, exchange rates, site/facilities, environmental/weather, competition, regulatory

The RBS is a sample. An organization may use a generic one or tailor one to the project type, and the categories and subcategories in the project's risk management plan govern. To categorize a risk, ask what it "originates from":

Figure 1: Assigning risks to the four RBS categories by source
  • Risks that originate in technical matters within the project scope, such as requirements, scope, technical processes and product standards, are technical risks.
  • Risks that originate in project management processes, responsibilities, resource arrangements or communication are management risks.
  • Risks that originate in transactional factors such as procurement, contracts, subcontractors, suppliers and customers are commercial risks.
  • Risks that originate outside the organization, such as regulations, exchange rates, weather and competition, are external risks.

For example: an ambiguous interface document is a technical risk. A project manager running three projects at once so that reviews cannot be scheduled is a management risk. A subcontractor taking on this type of work for the first time and possibly being unfamiliar with the specifications is a commercial risk. Heavy summer rain, or a new regulation that adds a testing step, is an external risk.

There are three typical traps in categorizing. First, symptom versus root cause: a risk that ends up showing as a schedule delay is not therefore a schedule risk. The RBS classifies by source, not by consequence, so "ambiguous requirements leading to rework" originates in requirements and is a technical risk. Second, internal versus external: a standard the team has not finished writing, or a review the team cannot schedule, is internal however troublesome; external risk means factors outside the organization. Third, procurement: relationships with suppliers, contracts and subcontractors belong to commercial risk, whereas "reviews cannot be scheduled within the project team, or the approval chain is too long" originates in internal management and belongs to management risk.

Example: where does a missing definition of done belong?

An adaptive team finds that several backlog items have no clear definition of done (DoD). The DoD is a checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use, so it belongs to requirements and product standards. Its absence leaves it uncertain whether a deliverable is acceptable, so the risk originates in requirements and product standards and is usually classified as a technical risk under the RBS (common exam practice when the stem says only that the definition of done is missing). If the root cause is that the team never set up or followed a shared process, it could also be classified as a management risk; this depends on the project's RBS and the root cause. It has nothing to do with a procurement contract, so it is not a commercial risk, and the definition of done is established within the team or organization, so it is not an external risk.

Categorization exists to support decisions. Suppose a project to build an Internet-of-Things system has 20 risks, 9 of them technical and 6 of those in technical interfaces. You could prioritize experienced people for the interfaces and assess whether one dedicated integration-testing response could address several related risks. The categorization results also go into the risk report.

Outputs of Perform Risk Analysis

The outputs are updates to project documents, not updates to the project management plan: the risk register, the risk report, the assumption log and the issue log. When risks are first identified, the register records mainly the list of identified risks, potential risk owners and potential responses (PMBOK 8 says the content "may include but is not limited to" these; additional data such as category, causes, effects and triggers can be recorded according to the risk management plan). After analysis, the register is updated with each risk's probability, impact and priority, the scores and categories according to the method used, potential risk owners confirmed as risk owners, and low-probability, low-impact risks entered on the watch list. The risk report shows the number of threats and opportunities, their distribution across risk categories and the main drivers of overall risk exposure. New assumptions found during analysis are written back to the assumption log.

The qualitative results also determine what happens next. For a higher-priority risk with several alternative courses of action, where the probability and the costs and benefits of each branch can be estimated, a decision tree can calculate the expected monetary value (EMV) to compare options. When the combined effect of several risks on the finish date or total cost is unclear, simulation analyzes overall risk. Risks that exceed an established threshold or need active treatment go on to Plan Risk Responses. Low-probability, low-impact risks go on the watch list and are reviewed periodically, with reassessment if their probability or impact changes (PMBOK 8: the watch list is "for future monitoring"). Going straight to quantitative analysis without ranking is time-consuming and may spend effort on unimportant risks.

Worked examples

Example 1: What to use to categorize risks by source

Question 1Example

A shared EV-charger maintenance and upgrade project in a residential complex is in execution, and team members keep reporting potential risks to the project manager. The project manager wants to categorize these risks by source of risk. What should be used?

Show answer and explanation

Correct answer: D

The project is in execution and team members keep reporting potential risks. The project manager wants to categorize the risks by source of risk. The question asks which tool or document to use.

The key clues are “by source of risk” and “categorize”. The risk breakdown structure (RBS) is a hierarchical representation of potential sources of risk. It is generally divided into the categories technical, management, commercial and external and then broken down further, which is just what is needed to sort identified risks by source, and it can also show which source categories hold the concentrated risk. The answer is D.

Why the other options are wrong

  • A. The work breakdown structure decomposes the work, dividing it by deliverables and work packages. It can be used to categorize by area of the project affected, but not by source of risk.
  • B. The risk report summarizes the latest status of overall project risk and individual risks. It is an output document and provides no categorization framework.
  • C. The risk register records the information about identified risks. It does not itself provide a hierarchical structure for categorizing by source; for that you use the RBS.

Key takeaway Categorize by source with the RBS; categorize by area affected with the WBS.

Variation If the stem were changed to “categorize risks by area of the project affected”, the WBS could be used. If it were changed to “summarize the overall risk situation for the sponsor”, the answer is the risk report.

Something wrong with this question?

Report an issue with this question

Example 2: Which category ambiguous requirements belong to

Question 2Example

While doing qualitative risk analysis, a subscription music app team finds that the requirements of several backlog items are vaguely defined and have no acceptance criteria, so it is impossible to judge whether a deliverable is acceptable. Under the source categories of the risk breakdown structure, which category should this risk belong to?

Show answer and explanation

Correct answer: A

While doing qualitative risk analysis on an adaptive project, the team finds that the requirements of several backlog items are vaguely defined and have no acceptance criteria, so it cannot judge whether a deliverable is acceptable. The question asks which RBS source category it belongs to.

The signal words are “requirements definition” and “acceptance criteria”: the root of the problem is uncertainty in the requirements and product standards themselves, which belongs on the technical side. The PMBOK sample RBS places requirements definition under technical risk, alongside scope definition, estimates, assumptions and constraints, technical processes, technology and technical interfaces (Figure 4-5). So the answer is A.

Why the other options are wrong

  • B. Management risk comes from project management, organization, resourcing and communication arrangements. The crux in this question is vague requirements, not a failure in management arrangements.
  • C. Commercial risk originates in transactional factors such as procurement, contractual terms and subcontractors. The stem mentions no contract or supplier, so it has nothing to do with vague requirements and missing acceptance criteria.
  • D. External risk comes from outside the organization, such as regulation, markets and competition. Backlog items and acceptance criteria are the team's own work, not an external factor.

Key takeaway In PMBOK 8's sample RBS, the Level 1 categories are technical, management, commercial and external; requirements-definition problems fall under technical risk.

Variation “The contract has no clear acceptance terms and the customer rejects the work afterward” leans toward commercial risk; “the resource manager suddenly pulls away the testers” leans toward management risk; “a new regulation is issued” is external risk.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Categorize by source with the RBS. Categorizing by area affected can use the WBS. Do not mix the two.
  • The categories and subcategories in the project's risk management plan govern; the sample is only a sample.
  • Categorize by a risk's root source, not by which objective it ends up affecting.
  • The output of Perform Risk Analysis is project document updates, not project management plan updates (unlike Plan Risk Management). The watch list is part of the register, not a separate document.

Key takeaways

  1. Risk categorization finds the areas most exposed to uncertainty. Risks can be grouped by source (RBS), area affected (WBS), other categories or common root cause.
  2. The four sample RBS categories are technical, management, commercial and external; the project's risk management plan governs.
  3. Categorize by root source: requirements and product standards are technical risks, contracts and suppliers are commercial risks, and factors outside the organization are external risks.
  4. The outputs are project document updates: risk register, risk report, assumption log and issue log.
  5. After analysis the register gains probability, impact, score, priority, confirmed risk owners, category and the watch list.

This chapter has 28 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.