What this chapter covers
Once Plan Risk Management has set the rules, the next question is "what risks are actually in this project?" That is Identify Risks, and it produces the most important document in the Risk performance domain: the risk register. This chapter covers what Identify Risks does, why it is iterative, and the order in which to handle a newly raised risk. It covers the inputs and outputs and the three data gathering techniques; then the data analysis techniques and prompt lists; and finally what the risk register and risk report contain and how they fill up step by step.
Identify Risks is a core topic in risk management. The stems vary endlessly, but the answer is often the same action: record the newly identified risk in the risk register, then assess it, then respond to it.
Lessons in this chapter
- Lesson 1: Identify Risks: Purpose, Characteristics and Handling New Risks. Telling real risks from concerns and issues; identification is iterative; "cause, event, consequence"; a new risk is first recorded, then assessed, then responded to.
- Lesson 2: Identify Risks Inputs, Outputs and Data Gathering Techniques. The three key inputs; threats from flawed assumptions and opportunities from removing or relaxing constraints; when to use brainstorming, interviews and checklists.
- Lesson 3: Analysis Techniques, Prompt Lists, the Risk Register and the Risk Report. Root cause analysis, assumption and constraint analysis, document analysis and SWOT; prompt lists; what the register holds at the end of identification; the risk report.
Chapter map
Identify Risks (iterative)
- Inputs: risk management plan · assumption log · lessons learned register · baselines · agreements …
- Data gathering: brainstorming · interviews · checklists
- Tools and techniques: data analysis (root cause analysis · assumption and constraint analysis · document analysis · SWOT); interpersonal and team skills (facilitation); other (prompt lists)
- Outputs: risk register (list of risks, potential risk owners, potential responses) + risk report + document updates
When a new risk appears: decide whether it is a risk or an issue → record a risk in the risk register (an issue that has already occurred goes in the issue log) → assess → respond (escalate when the risk is outside the project scope or the response exceeds the project manager's authority)
In the chapter practice set, do the core questions first, then the required questions.
Lesson 1
Identify Risks: Purpose, Characteristics and Handling New Risks
Lesson overview
Plan Risk Management sets the rules; the next step answers "what risks are actually in this project?" That step is Identify Risks. It is the core topic of risk management. A stem describes a situation and asks "what should the project manager do?" When the stem clearly presents a new risk that has not yet been recorded, the common exam practice is to update the risk register first, then analyze and respond according to the risk management plan (the exact answer still depends on which step the stem is at). This lesson covers what Identify Risks does, why it is iterative and how to handle a new risk. The next lesson covers inputs, outputs and data gathering techniques. ECO: Business Environment domain, Task 5 (Plan and manage risk).
What Identify Risks does
Identify Risks includes recognizing both negative and positive risks. PMBOK 8 stresses that the process focuses on distinguishing genuine risks from nonrisks, such as concerns and issues. The main outputs are the risk register and the risk report; the process may also update project documents such as the assumption log, issue log and lessons learned register.
For a lead to become a risk on the register, it has to pass three filters. Has it already happened? (If yes, it is an issue and goes in the issue log.) Is it a specific event or condition? (A vague unease, with no stated thing that might go wrong, is not yet a risk; talk it through until it is clear.) Will it affect project objectives? (If not, there is no need to log it.) "The supplier has been short of cash lately, so delivery may be late" passes all three, so log it. "I just feel this project will go wrong" has no event, so first ask what exactly worries the person.
A risk description should be detailed and unambiguous. PMBOK 8 suggests the "cause, event, and consequence" structure, which separates the risk from its causes and effects:
| Part | Explanation | Example |
|---|---|---|
| Cause | A condition or fact that exists now | The cold-chain supplier is taking an order from this company for the first time |
| Event | Something that may or may not happen | Vehicle scheduling conflicts may occur |
| Consequence | The effect on objectives if the event happens | Raw-material deliveries are delayed and the central kitchen opening is pushed back |
One situation can produce an issue and a risk at the same time. The air conditioner broke down yesterday and was fixed today: that is an issue. "The aging air conditioner may fail again and bring down the servers" is a risk. PMBOK 8 lists artificial intelligence among the Identify Risks tools. For example, an AI tool can scan lessons learned, historical data and contracts to help find connections people tend to overlook, though care must be taken not to leak confidential information.
Why identification is iterative
There is inherent uncertainty at the start of a project, and not all risks can be identified at the outset, so risk identification is iterative: as the project moves forward and information improves, risks are continuously identified and assessed, which keeps risk management dynamic. Every project has unique aspects, and the biggest risks often sit in exactly those aspects, so stakeholders raising new risks during execution is normal and is not a sign of a poor plan. Common points in time: initial identification in planning, before each phase starts, at key milestones, after a change, at risk review meetings, whenever someone raises a new concern, and, in adaptive projects, at the start of each iteration.
Common exam practice: when identifying individual project risks, encourage all project stakeholders and team members to take part; inviting only some of the project manager, team, experts or sponsor is too narrow. Interviewees may be experienced participants, sponsors, executives and experts.
When a new risk appears: the standard handling sequence
During execution someone raises a new situation. Handle it in this order (common exam practice). First decide whether it is a risk or an issue (something that has not happened and carries a "may" is a risk). If it is a risk, record it in the risk register first; do not start by making a change, switching suppliers or notifying other departments. Then assess probability and impact following the risk management plan, discussing it with the team and relevant stakeholders. Then plan a response. Escalate only when the risk is outside the scope of the project or the response would exceed the project manager's authority. A handy order: record, then analyze, then respond. The register is the main ledger; if you do not record the risk, nothing that follows has a basis.
Example: one complete identification
A community canteen renovation project has reached the construction phase, and a worker mentions: "The building next door is having its facade repaired, and the scaffolding may take up the access lane for our materials." The lane has not been blocked yet, it is a specific event, and it would affect the schedule, so it is a risk. The project manager first records it in the risk register: "Because the building next door is having facade repairs (cause), scaffolding may block the materials access lane (event), leading to delayed material transport and a late construction schedule (consequence)", notes who raised it and the date, and then arranges to assess its probability and impact.
Adaptive projects: assess readiness before the first iteration. This is an agile practice and common exam practice. Before the first iteration begins, assess the team's technical capability and organizational readiness (for example, whether the needed skills, environment, processes and support are in place). Treat a confirmed capability gap as an issue, and also record the uncertain consequences it may bring (for example, insufficient skills may cause rework or delay) in the register as a risk and keep tracking it, instead of discovering it halfway through. PMBOK 8's adaptive tailoring example says that a project with an agile life cycle may assess risk at the beginning of each iteration and hold a risk review meeting with stakeholders at the end of each iteration.
Worked examples
Example 1 A new risk appears during execution: record first, then assess
A central-kitchen expansion project for a restaurant chain has entered execution. The logistics supervisor, as a stakeholder, raises a new risk that had not been identified before: vehicle scheduling by the new cold-chain supplier may affect the timeliness of raw-material delivery. What should the project manager do?
Show answer and explanation
Correct answer: B
A central-kitchen expansion project is in execution. The logistics supervisor, a stakeholder, raises a risk not identified before: vehicle scheduling by the new cold-chain supplier may affect the timeliness of raw-material delivery. The question asks what the project manager should do.
Identifying risks is not done just once; it is an iterative process that runs throughout the project, and as information grows it is normal for new risks to appear during execution. On receiving a new risk, the project manager should first record it in the risk register so it is not lost, and then, following the process in the risk management plan, assess its probability, impact and priority together with the project team and relevant stakeholders. That way nothing goes unrecorded and the assessment has a full perspective. The risk has not yet been analyzed and there is no evidence that it exceeds the project manager's authority, so there is no need to rush to escalate. The answer is B.
Why the other options are wrong
- A. Confirming the register is complete and asking everyone to verify it is rechecking old content and does nothing about the newly found risk, besides implying that risk identification is not iterative.
- C. Analyzing only with the person who raised it gives a single viewpoint and may miss other risks and effects. Risk analysis and assessment should involve the project team and relevant stakeholders.
- D. The risk has not been analyzed, and whether it exceeds authority is unknown. Identifying, analyzing and planning responses are within the project manager's responsibility, and escalation to senior management is needed only when the risk is outside the project scope or beyond the project manager's authority.
Key takeaway Record a new risk in the risk register first, then assess it with the team and relevant stakeholders; do not rush to escalate.
Variation If the stem were changed to “the supplier notified us yesterday that it cannot supply”, the event has happened and is an issue, to be recorded in the issue log and acted on immediately.
Something wrong with this question?
Example 2 An adaptive project: how to surface risks early
A membership-system rebuild at a retail chain involves several teams, and the organization's governance level recently decided to move from a predictive to an agile approach. Halfway through, a team member finds that the team lacks the technical capability to support the real-time inventory synchronization requirement, so the project needs rework and the situation must be explained to all stakeholders. To avoid this, what should the agile project leader have done?
Show answer and explanation
Correct answer: D
A membership-system rebuild with several teams has just moved from predictive to agile. Halfway through, the team finds it lacks the technical capability for real-time inventory sync, rework is needed and all stakeholders must be told. The question asks what the agile project leader should have done beforehand.
The rework traces back to inadequate technical and organizational readiness that surfaced only midway. Before work began, whether the team's technical capability was sufficient was uncertain, and that uncertainty is itself a risk; the earlier it is identified, the lower the cost of dealing with it. A gap that has been confirmed is an issue, and the future effects it may cause, such as rework and delay, are tracked as risks. So the leader should have assessed the team's technical and organizational readiness before the first iteration began, identified risks on that basis, and logged and kept tracking them, closing the gap before requirements were built. “Identify risks early and throughout” is PMBOK 8's thinking, while “assess technical and organizational readiness before the first iteration” is common exam practice. The answer is D.
Why the other options are wrong
- A. The rework came from inadequate technical capability, not unclear acceptance criteria. Hiring outside experts to define acceptance criteria misses the point and does not close the capability gap.
- B. Defining acceptance criteria clearly at the start helps reduce disputes, and acceptance criteria also need timely clarification, but the root of the rework is the team's lack of technical capability; clarifying acceptance criteria alone cannot discover or close the capability gap, so it is not the best answer.
- C. More communication has no specific identification action. The product owner mainly handles requirements and priorities and can do little to confirm the team's technical capability, so it does not ensure the capability gap is found.
Key takeaway Whether capability is sufficient before work starts is uncertain, which makes it a risk; a confirmed gap is an issue. Assess technical and organizational readiness and identify risks before starting, instead of finding out halfway.
Variation On an agile project, run risk identification again at the start of every iteration afterward, so that capability-gap risks surface as early as possible.
Something wrong with this question?
Common traps
Common trap
- Something that has already happened is not a risk: "cannot deliver" or "has already shut down" goes in the issue log; a "may" goes in the risk register.
- A concern is not a risk. First ask what event the person is worried about and which objective it would affect.
- Record a new risk in the risk register first and then analyze it by the process; do not start by changing, responding or escalating.
- When a risk like one seen on past projects shows up during execution, check whether the lessons learned register was consulted thoroughly enough during identification, and also update the register and the lessons learned with this result (PMBOK 8: not all risks can be identified at the outset, and identification is iterative).
- When the person raising the risk bypasses the team and reports straight to management: if the description is clear enough to record, still record it in the register first and then assess; an improper channel is no reason to reject it. If all that is known is that there is a new risk, and neither its content nor the reason for escalating is clear, talk to the person first, then record and assess.
Key takeaways
- Identify Risks finds threats and opportunities, and the key is telling real risks from concerns and issues.
- Identification is iterative, and new risks appearing during execution is normal.
- Describe a risk as cause, event and consequence; common exam practice: identification should encourage all stakeholders and team members to take part.
- What has happened is an issue; only what has not happened and is uncertain is a risk.
- Record a new risk first, then assess it, then respond; escalate only when it exceeds your authority.
- An adaptive project assesses technical and organizational readiness before the first iteration (agile practice and common exam practice) and keeps identifying risks in each iteration after that.
Lesson 2
Identify Risks Inputs, Outputs and Data Gathering Techniques
Lesson overview
This lesson covers "where to look for risks" and "what methods to use". The first half is inputs and outputs: which documents serve as leads and which documents come out. The second half is the three data gathering techniques: brainstorming, interviews and checklists. A common question is "how can you avoid missing a certain kind of risk?", and the answer usually lands on a particular input document or technique. The next lesson covers data analysis techniques, the risk register and the risk report. ECO: Business Environment domain, Task 5 (Plan and manage risk).
Identify Risks inputs, tools and outputs
| Item | Content |
|---|---|
| Inputs | Project management plan (including the requirements, schedule, financial, quality, resource and risk management plans, and the scope, schedule and cost baselines); project documents (assumption log, cost estimates, duration estimates, issue log, lessons learned register, requirements documentation, resource requirements, stakeholder register); agreements; enterprise environmental factors; organizational process assets |
| Tools and techniques | Expert judgment; data gathering (brainstorming, checklists, interviews); data analysis (SWOT analysis, root cause analysis, document analysis, assumption and constraint analysis); facilitation; prompt lists; meetings; artificial intelligence |
| Outputs | Risk register; risk report; project document updates (assumption log, issue log, lessons learned register) |
You do not need to memorize the inputs one by one. Keep one idea in mind: risks hide where the plan is "not yet sure". Baselines and estimates hide assumptions, requirements and resources hide dependencies, agreements hide contractual obligations, and lessons learned hold pitfalls that others have already stepped into. Three items deserve to be remembered separately.
The risk management plan sets roles and responsibilities and risk categories (which can be expressed as an RBS); where the plan specifies risk categories, the RBS can serve as a framework for identifying and categorizing. The assumption log holds assumptions and constraints that may give rise to individual risks and also affect the level of overall risk. The pattern is that threats may be identified from the inaccuracy, instability, inconsistency or incompleteness of assumptions, and that constraints may give rise to opportunities through removing or relaxing a limiting factor. An assumption is "we think it will be this way", such as "the senior engineer will be available then"; if its accuracy is in doubt, that may give rise to a threat (once it is known to be false, update the assumption log, treat current effects as issues and record uncertain future consequences as risks). A constraint is "we are boxed in", such as "the contract forbids night work"; if the owner agrees to relax it, working hours become flexible, which is an opportunity. The lessons learned register records the knowledge gained in this project, phase or iteration, which can include risks that have materialized; historical risks from similar past projects come mainly from the lessons learned repository among the organizational process assets, and may also show up in checklists compiled from it. When a risk "that also happened on past projects of this kind" shows up during execution, it often means these materials were not consulted during identification.
The outputs are the risk register and the risk report, with updates to three documents: write inaccurate assumptions back into the assumption log; write what has already happened into the issue log; and write insights worth keeping into the lessons learned register.
Data gathering techniques
Brainstorming produces ideas in a free or structured form, and risk categories such as the RBS can serve as an identification framework. Its purpose is to produce a large number of ideas in a short time, and it can be done in a team, online, in writing or individually (a team session is generally run by a facilitator, and the online form can also allow anonymous sharing). What they all share is encouraging quantity and holding off on evaluation. The traditional team form suits cases that need many ideas quickly and where members can attend on the spot.
Interviews are useful for obtaining confidential information (PMBOK 8). Common exam practice is to hold them in an atmosphere of mutual trust and confidentiality, which helps people speak frankly, while still identifying and cross-checking possible bias. Interviewees may be experienced participants, sponsors, executives and experts, or external groups affected by the project (such as neighboring residents). They suit situations where key people cannot attend together, sensitive information is involved or a specific concern needs to be probed. Method: prepare an outline beforehand, state that the discussion is confidential, use open-ended questions and press until a specific event emerges, then write up the notes as items and have the interviewee confirm them.
A checklist is a list of items to be considered, compiled from historical information on similar projects, and it preserves specific risks that have occurred before. It cannot be exhaustive and cannot replace identification work; items outside the list must still be examined, and the list should be reviewed regularly and obsolete items removed.
| Technique | When it fits | Limitation |
|---|---|---|
| Brainstorming | The team is present (or online or in writing), time is short, many ideas are needed | Easily dominated by strong voices; needs a facilitator |
| Interviews | Probing one person's concerns in depth, or confidential matters | Usually one-on-one, so doing them one by one is time-consuming (multi-person interviews are possible) |
| Checklists | Historical information from similar projects exists | Can be confined to "known types," so items outside the list must also be explored |
The three techniques are often combined: checklists provide a starting point, brainstorming broadens the search, and interviews dig deeper. When running an identification workshop, send the RBS, past risks and the assumption log to everyone beforehand; at the workshop, diverge first and organize afterward, with each idea stating cause, event and consequence; afterward, merge duplicates, strip out issues and concerns, and then write the items into the register; interview absentees separately.
Worked examples
Example 1 The lessons learned repository: avoid missing risks
During an industrial IoT project, a problem emerges that can be solved only by adding budget and extending the schedule. The team had not listed it as a risk during identification, and the sponsor points out that similar situations occurred on the company's past projects. What should the project manager have done beforehand to avoid this oversight?
Show answer and explanation
Correct answer: A
During an industrial IoT project, a problem emerges that requires added budget and a longer schedule. It was not listed as a risk during identification, and the sponsor points out that similar situations occurred on past company projects. The question asks what the project manager should have done beforehand.
The key signal is “occurred on past projects”, which points to historical information. Risk identification should make full use of organizational process assets, among which the archived lessons learned repository and the historical risk data of past projects record the risks and lessons of similar earlier projects. Consulting them during identification would have revealed risks that occurred before and may occur here, avoiding the omission. So beforehand the project manager should have consulted the lessons learned repository and the risk data of past projects. The other three are a plan framework, an organizational attitude and a response measure, and none of them brings in historical risks. The answer is A.
Why the other options are wrong
- B. The risk categories in the risk management plan are only a framework for identifying and recording, helping to classify; they do not tell the project what specific risks have occurred.
- C. Risk appetite decides how much risk the organization is willing to take. It answers “how much can we accept” and does not help identify “what risks there are”.
- D. Contingency reserve is a response to identified risks. If a risk has not been identified, there is nothing to allocate reserve to in a targeted way, and this is a response, not identification.
Key takeaway To avoid missing risks that have occurred before, consult the lessons learned repository and past projects' risk data during identification.
Variation If the stem said the company had never done a similar project and there was no history to consult, you would rely on brainstorming, interviews and expert judgment instead.
Something wrong with this question?
Example 2 Which technique to use when time is critical
A new-energy battery R&D team learns that a new industry regulation makes a process it currently uses noncompliant, and a new process must be adopted. Time is very tight, and the project manager must identify the resulting risks in the shortest time and draft a response for each. All team members took part in trials of this process and can attend a meeting on the spot, while one-by-one interviews and an outside expert assessment would each take weeks. What should the project manager do?
Show answer and explanation
Correct answer: B
A battery R&D project must switch to a new process because of a new industry regulation. Time is tight, and the project manager must identify risks and draft responses in the shortest time. Team members all took part in the trials and can attend on the spot, while one-by-one interviews and an outside expert assessment would take weeks.
Three factors decide it: “shortest time”, members who “all know the process” and who “can attend on the spot”. Brainstorming gathers the relevant people in one session, produces many risks on the spot and can also generate potential response options, taking the least time while using the team's familiarity with the process. Those options still need to be evaluated through risk analysis and confirmed during Plan Risk Responses. The other approaches either take weeks or merely report without producing risks. The answer is B.
Why the other options are wrong
- A. Interviewing one by one means scheduling each separately, and the stem says it takes weeks, which conflicts with “shortest time”. Interviews suit cases that need an in-depth look at one person's views; here everyone is present and there is no need to talk to them one at a time.
- C. Briefing the sponsor and asking them to review the risk list is reporting and reviewing; it produces no new risks or responses and is not a technique for identifying risks, so it cannot achieve “identify quickly and draft responses”.
- D. A written assessment from an outside expert also takes weeks, which is too long; the team members are themselves the people who know the process best, so there is no need to wait weeks for an outside assessment first.
Key takeaway When time is tight and the people know the situation and can attend, brainstorming gives the fastest output of risks and potential response ideas; formal responses still require subsequent analysis and confirmation.
Variation To find out what a particular group's representative is worried about, or when people are dispersed, cannot attend at once or confidentiality is involved, use interviews instead.
Something wrong with this question?
Common traps
Common trap
- A checklist contains specific risk items and comes from historical information; it cannot replace identification work.
- Choose the technique by the conditions in the stem: on the spot and in volume, use brainstorming; digging deep and in confidence, use interviews.
- Problems with assumptions usually bring threats, and relaxing constraints usually brings opportunities.
- The outputs of Identify Risks also include updates to the assumption log, issue log and lessons learned register, not only the risk register.
- When an important participant is absent from a workshop, you cannot simply ignore their input or compile the list alone; depending on urgency, options include rescheduling, collecting input online or in writing, and interviewing them afterward.
Key takeaways
- Outputs of Identify Risks: the risk register and the risk report, with updates to the assumption log, issue log and lessons learned register.
- Three key inputs: the risk management plan (categories, roles), the assumption log, and the lessons learned register (knowledge gained, including risks that materialized; historical risks are also in the lessons learned repository).
- Inaccurate, unstable, inconsistent or incomplete assumptions may give rise to threats; removing or relaxing constraints may give rise to opportunities.
- Brainstorming gives speed and volume; interviews are useful for confidential information and can dig deep (best held in an atmosphere of trust and confidentiality, common exam practice); checklists come from historical information and cannot replace identification.
- When an important participant is absent from a workshop, do not simply ignore it; reschedule, collect input online or in writing, or interview them afterward as the situation requires.
Lesson 3
Analysis Techniques, Prompt Lists, the Risk Register and the Risk Report
Lesson overview
The last two pieces of Identify Risks are in this lesson. One is the data analysis techniques and prompt lists: how to dig for risks once you have the raw material. The other is the two main products of Identify Risks, the risk register and the risk report (Identify Risks also updates project documents such as the assumption log, issue log and lessons learned register as needed). The register is the most important document in the risk chapters; later analysis, response and monitoring are all written onto it. You need to know what it looks like when identification is done and how it fills up afterward. The next chapter covers Perform Risk Analysis. ECO: Business Environment domain, Task 5 (Plan and manage risk).
Data analysis techniques
Root cause analysis is an analytical method used to determine the basic underlying reason that causes a variance, defect or risk, so that preventive measures can be set. Common exam practice also describes root cause analysis as using a problem statement to identify threats and a benefit statement to identify opportunities. For example, "go-live is late": why? Integration testing started late. Why? The interface document was not delivered on time. Why? The supplier's interface lead is supporting three projects at once. Only once you reach this layer can you see "key people tied up on several projects" as a manageable source of risk, which you then write as a risk: because key people are tied up on multiple projects, the interface document may be delayed again, causing a late go-live.
Assumption and constraint analysis tests whether the assumptions and constraints the plan relies on are valid: inaccurate, unstable, inconsistent or incomplete assumptions may bring threats, and removing or relaxing constraints may bring opportunities. Document analysis is a structured review of project documents such as plans, contracts and requirements; contradictions and vagueness between documents often hide risks.
In SWOT analysis, strengths and weaknesses are used to analyze internal conditions, while opportunities and threats may come from the external environment or be triggered by internal project or organizational conditions (PMBOK 8: SWOT analysis includes internally generated risks); the opportunities and threats here are the risks to be identified. The method is to find strengths and weaknesses first, then the opportunities that strengths bring and the threats that weaknesses cause, and analyze to what extent strengths can offset threats and whether weaknesses hinder opportunities. Facilitation improves the effectiveness of techniques such as brainstorming, interviews and SWOT.
Example: a SWOT walk-through
A regional pharmacy chain is launching online reservation and pickup of prescriptions. Strengths: dense store coverage and ready-made pickup points. Weaknesses: no in-house development team. External opportunity: relaxed policy on online health-insurance settlement. Threat: a subsidy war among rival platforms. Cross analysis: dense stores can offset part of the subsidy-war threat; the lack of a development team may hinder capturing the insurance-settlement opportunity. The register gains two entries as a result: outsourced development may slip and miss the insurance integration window (threat); opening of online insurance settlement could let the stores expand the online channel (opportunity).
Prompt lists
A prompt list is a predetermined list of risk categories that might give rise to individual project risks and could also act as sources of overall project risk, helping the team generate ideas. For individual project risks, use the lowest-level categories of the RBS; for overall project risk, use PESTLE (political, economic, sociocultural, technological, legal, environmental), TECOP (technical, environmental, commercial, operational, political) or VUCA (volatility, uncertainty, complexity, ambiguity). Several kinds of list can be used alone or together, and overlap does no harm. A checklist lists specific risk items; a prompt list lists only categories, hinting "which direction to think in".
The risk register and the risk report
The risk register records the details of identified individual project risks. It is first compiled in the Identify Risks process; the Perform Risk Analysis, Plan Risk Responses, Implement Risk Responses and Monitor Risks processes that follow keep updating the register with information on individual risks, update overall and summary information in the risk report, and update other project documents as needed, so the register's content grows gradually. Only Plan Risk Management does not produce it. When a risk occurs, check the register first; it often already holds a response.
When identification is complete, the register includes the list of identified risks (each with a unique identifier, described in enough detail to be understood unambiguously) and, where already identified, the potential risk owners (recorded if known, confirmed during analysis) and the list of potential risk responses (recorded if already thought of, confirmed during response planning). PMBOK 8 says the content "may include but is not limited to" these. Depending on the format specified in the plan, it can also record a short title, category, current status, causes, effects, triggers, WBS references and timing information. Columns such as probability and impact are not filled in until the analysis stage.
The risk report presents information on sources of overall project risk, together with summary information on identified individual project risks, and it is developed progressively through the risk processes. When identification is complete it may include the sources of overall risk (indicating the most important drivers of overall exposure) and a summary of individual risks, such as the number of threats and opportunities, distribution across categories, metrics and trends. The register handles "every item" and is the detailed ledger; the report handles "the whole and the summary" and is the summary table.
Worked examples
Example 1 Which analysis technique to use: SWOT
While identifying risks, a project team wants to first find the organization's strengths and weaknesses, then judge to what extent the strengths can offset threats and whether the weaknesses will hinder opportunities from emerging. Which analysis technique should be used?
Show answer and explanation
Correct answer: B
While identifying risks, the team wants to first find the organization's strengths and weaknesses, then judge how far strengths can offset threats and whether weaknesses hinder opportunities.
“Strengths”, “weaknesses”, “offset threats” and “hinder opportunities” in the stem are one method's full routine: list the organization's strengths and weaknesses, then look at the opportunities that strengths bring and the threats that weaknesses cause, and analyze how much strengths can offset threats and whether weaknesses will hinder opportunities. That is SWOT analysis, which can identify both threats and opportunities. The answer is B.
Why the other options are wrong
- A. Root cause analysis starts from a problem statement or a benefit statement and asks about the deeper cause behind it; it does not analyze how strengths and weaknesses offset one another.
- C. Checklist analysis goes through a list built from past similar projects item by item as a reminder; it does not cross-analyze strengths and weaknesses.
- D. Assumption and constraint analysis tests whether the assumptions the project rests on are valid and whether constraints can be relaxed; it has nothing to do with the organization's strengths and weaknesses.
Key takeaway Strengths offsetting threats and weaknesses hindering opportunities is the signature of SWOT analysis.
Variation “Test whether the premises behind the plan are valid” is assumption and constraint analysis; “trace the deeper cause of a problem” is root cause analysis.
Something wrong with this question?
Example 2 An assumption fails: record it in the register
During the bidding stage, a software outsourcing company prepared its project management plan on the assumption that “senior architects will be available during project execution”. After the contract is awarded, the project manager learns from the functional manager that those architects will not be available then, and under the current plan delivery may slip by two weeks. The project has not started yet. What should the project manager do?
Show answer and explanation
Correct answer: A
At bidding, a software outsourcing company prepared its plan on the assumption that senior architects would be available during execution. After winning, it learns they will not be available then, and delivery may slip by two weeks. The project has not started. The question asks what the project manager should do.
The plan rests on the assumption that “the architects will be available then”, and the functional manager has confirmed they will not, so the resource assumption has failed. Resource unavailability is already fact, but the two-week delivery delay that it causes has not happened, and the project has not started, so it remains an uncertain consequence, which makes it a risk. The project manager should assess ways to prevent or mitigate the potential schedule delay and update the risk register with this schedule risk and the potential response options. Of the options, only A both assesses options and records the risk. Changing the plan directly, writing into the risk management plan or drafting another plan all skip the steps of assessing and recording. The answer is A.
Why the other options are wrong
- B. Revising the schedule treats a potential delay as an accomplished fact and skips risk assessment; adjusting the schedule also has to go through the Assess and Implement Changes process first, so it is not the next step.
- C. The risk management plan is a guiding document and does not record specific risks or schedule changes; a contingency plan is activated only when its trigger condition appears, which is not the case yet.
- D. Drafting a separate phased delivery plan sidesteps the problem: it does not assess the risk created by the failed assumption and does not update the risk register, jumping straight to a solution.
Key takeaway When an assumption the plan rests on fails, it may create a threat; assess it and record it in the risk register first, instead of changing the plan directly.
Variation If the project had already started and the architects did not show up, their nonavailability would be an issue to record in the issue log and address immediately; any resulting schedule delay that had not yet occurred would still be assessed and managed as a risk.
Something wrong with this question?
Common traps
Common trap
- A checklist holds specific risks, while a prompt list gives only risk categories; both are aids only and cannot replace identification work.
- The lowest-level RBS categories correspond to individual risks; PESTLE, TECOP and VUCA correspond to overall project risk.
- Specific risks are recorded in the risk register, not in the risk management plan; the risk report must also describe overall project risk.
- When identification is complete, the register's focus is the list of risks, with any identified potential owners and potential responses recorded too; columns like probability and impact are usually filled in at the analysis stage; the register must be reviewed and updated continuously during execution.
Key takeaways
- Root cause analysis digs for the underlying source (common exam practice: find threats from problem statements and opportunities from benefit statements); flawed assumptions bring threats and relaxed constraints bring opportunities.
- SWOT: strengths and weaknesses analyze internal conditions, and opportunities and threats may come from the external environment or be triggered by internal conditions (PMBOK 8: SWOT includes internally generated risks); the opportunities and threats are the risks to identify.
- Prompt lists give only categories: for individual risks, use the lowest-level RBS categories; for overall risk, use PESTLE, TECOP or VUCA.
- The risk register starts with Identify Risks and fills up step by step through later processes; at the end of identification it holds the list of risks, potential owners and potential responses.
- The risk report presents the sources of overall risk and a summary of individual risks.
This chapter has 45 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.