Risk
Risk Management Plan
PMP · Risk · 3 lessons · about 33 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
Risk management starts with this chapter, which answers three questions: what a risk is (and how it differs from an issue and from a fact); how much risk the organization and its stakeholders can carry; and how this project intends to manage risk. The first two are conceptual groundwork. The third is the first process of the Risk performance domain, Plan Risk Management, whose output is the risk management plan. The categories, scales and thresholds set here are used by every later step: identifying, analyzing, responding and monitoring.
Questions in this chapter come in two forms. One is the "tell them apart" question: is this a risk or an issue, and does it belong in the risk register or the issue log? The other is the "which document" question: for how often to review, who holds risk management roles, or what counts as high risk, check the risk management plan first; for who owns a specific risk, check the risk register. The risk management plan is the "rule book" and contains no specific risks; specific risks first appear in the next chapter.
Lessons in this chapter
- Lesson 1: Risk, Issues and Risk Appetite. The definition of risk, the distinction between what has and has not occurred, the four kinds of uncertainty (risk classification), and the differences among appetite, threshold, tolerance and exposure.
- Lesson 2: Project Resilience, Integrated Risk Management and Tailoring. Risks nobody anticipated are handled through resilience and management reserve; escalate when a risk is beyond the project's scope or a proposed response is beyond the project manager's authority; how risk management is tailored for predictive and adaptive projects.
- Lesson 3: Plan Risk Management and the Risk Management Plan. The process's inputs and outputs, the contents of the plan, the RBS, definitions of probability and impact, and "which document to check first".
Chapter map
Risk (an uncertain event or condition; has a probability, and a positive or negative effect on objectives)
- Has occurred → issue → issue log
- Certain to occur (facts and requirements) → not a risk; managed as part of scope
- Has not occurred, uncertain → risk → risk register
Appetite (willingness) → expressed as a measurable threshold (the boundary of acceptable variation, used to judge priority and whether further action is needed) → written into the risk management plan; tolerance (ability) is separate and is a common exam concept
Plan Risk Management → plan: strategy, methodology, roles and responsibilities, funding, timing, RBS, appetite and thresholds, definitions of probability and impact
Tailoring: predictive = fairly complete planning early with periodic review / adaptive = continuous identification and assessment every iteration; both manage risk throughout the project
In the chapter practice set, do the core questions first, then the required questions.
Lesson 1
Risk, Issues and Risk Appetite
Lesson overview
Almost every risk question starts with the same query: is the thing in front of you a risk or an issue? This lesson covers the definition of risk, the difference between a risk and an issue, and the four kinds of uncertainty. It then turns to the set of concepts that describe how much risk an organization can carry: risk appetite, risk threshold, risk tolerance and risk exposure. All later analysis and response use these as the yardstick. The next lesson covers project resilience and tailoring. ECO: Business Environment domain, Task 5 (Plan and manage risk) and Task 4 (Remove impediments and manage issues).
Definition of risk and key points
A risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more portfolio, program, or project objectives. Potentially harmful risks are often called threats, and positive risks are better known as opportunities.
- "If it occurs": a risk is about something that has not happened yet; once it has happened, it is no longer a risk.
- "Positive or negative": risk is a neutral word, so both threats and opportunities must be managed.
- "Uncertain": it may occur or may never occur, so it must be reviewed regularly to see whether it has expired.
- "Event or condition": a risk is a real event or condition, not one person's worry.
A risk is analyzed through its probability of occurring and its impact on objectives. PMBOK 8 notes that a risk may be described in a "cause, event, and consequence" structure. For example: "Because the construction site is approaching the rainy season (cause), foundation work may be interrupted (event), extending the overall duration (consequence)."
VUCA—volatility, uncertainty, complexity and ambiguity—is one strategic prompt framework that can help identify sources of overall project risk.
Risks and issues: first ask "has it happened?"
An issue is a current condition or situation that may have an impact on one or more project objectives. An issue has already occurred and may require immediate action or management attention. The key difference is just one thing: whether the event has happened. Issues have already occurred or are still occurring, whereas risks are potential future problems that have not yet occurred. PMBOK 8 notes that an issue may arise from a poorly managed risk. In practice, a threat that occurs usually turns into an issue to deal with, while an opportunity that is realized does not necessarily become one. Issues are recorded in the issue log and risks in the risk register. In a stem, check whether the event has already happened: "has already closed down" is an issue, while "may", "worried that" and "expected to" usually point to a risk.
The figure has one more branch: something certain to happen is a fact or requirement and goes straight into the scope, schedule and cost plans; it is not logged as a risk.
By whether the relevant knowledge exists, uncertainty falls into four types (PMBOK 8, Figure 2-46):
| Type | Meaning | Is it a risk? |
|---|---|---|
| Known-known | Facts and requirements | No |
| Known-unknown | Classic risk; there is knowledge to identify probability and impact | Yes; for an identified risk with a proactive response strategy in place, a contingency reserve may be set |
| Unknown-known | Hidden fact: knowledge exists in the community but not with the entity working on the endeavor | Yes |
| Unknown-unknown | Emergent risk: knowledge does not exist within the sphere of influence | Yes; absorbed through management reserve and project resilience |
Overall risk is the effect of uncertainty on the project as a whole. It may arise from everything that is uncertain or unknown in the project, including individual risks, and cannot simply be treated as the sum of the individual risks. If the overall risk to the project is too high, the organization may choose to cancel the project.
Risk appetite, risk threshold and risk tolerance
Risk appetite is the degree of uncertainty an organization or individual is willing to accept in anticipation of a reward; it answers "are we willing?" The risk threshold is the measure of acceptable variation around an objective that reflects the risk appetite of the organization and stakeholders. It is how appetite is quantified, and it answers "how large a variation calls for further response or escalation?" (the exam often shortens this to "do we need to act?"). A cost threshold of ±5% reflects a lower risk appetite than ±10%. Risk tolerance (a common exam term) is the upper limit that can be endured; it answers "can we withstand it?" Common exam practice is to remember the three this way: tolerance is the outer limit that can be endured, appetite is the willingness to accept uncertainty within that capacity, and the threshold is the measurable line that triggers action. An organization whose appetite goes beyond what it can withstand is taking reckless risk.
Risk exposure is an aggregate measure of the potential impact of all risks at any given point in time. The threshold is the warning water line drawn by stakeholders; exposure is the project's current actual water level. Exposure within the threshold is acceptable. Crossing the line triggers assessment and a decision: respond, escalate, negotiate an adjusted threshold with stakeholders, or accept with approval; in severe cases the project may even be halted (PMBOK 8 notes that the organization may still choose the acceptance strategy and proceed when overall risk exceeds the threshold).
Example: the sponsor's warning line
A community senior-care platform has a budget of $480,000. The sponsor says total spending, including reserves, may be at most $540,000, which means a cost risk exposure of at most $60,000 is allowed. Risk analysis puts the cost exposure at $40,000, for a projected total including reserves of $520,000. The exposure is within the threshold, so the project can go on. If the exposure were $80,000, with a projected total of $560,000, the line would be crossed. The project manager must explain this to the sponsor, who decides whether to add funds, reduce scope or drop the project.
The preferences of key stakeholders must be written into the risk management plan and expressed as measurable thresholds for each objective. In PMBOK 8, the Risk performance domain has six processes: Plan Risk Management, Identify Risks, Perform Risk Analysis, Plan Risk Responses, Implement Risk Responses and Monitor Risks.
Worked examples
Example 1 Has it happened or not
A data-center equipment-room renovation project is in the implementation phase. The only cable supplier announces that it is going out of business and can no longer deliver the cables stipulated in the contract, so the installation schedule may be affected. What should the project manager do FIRST?
Show answer and explanation
Correct answer: B
A data-center equipment-room renovation project is in implementation. The only cable supplier announces it is going out of business and cannot deliver the cables stipulated in the contract, so the installation schedule may be affected. The question asks what the project manager should do first.
First distinguish an issue from a risk. “Going out of business” and “can no longer deliver” describe facts that have already happened, so this is an issue; the “may” in “schedule may be affected” is only the consequence of that issue and does not change the fact that the closure has happened. A risk is an uncertain event that has not yet happened, while an issue has happened and needs handling. What has happened goes in the issue log, and action is taken right away to minimize the effect on the schedule, such as looking for a substitute supplier. So the first step is to update the issue log and act. The answer is B.
Why the other options are wrong
- A. How long the schedule will slip has not been assessed, so writing the delay straight into the schedule baseline treats an unassessed impact as settled. A baseline change must also go through the Assess and Implement Changes process, and the project manager cannot change it directly.
- C. A potential installation delay can indeed be logged as a consequence risk and analyzed afterward, but what must be dealt with first is the real problem that the supplier has gone out of business and cannot deliver. C looks only at the possible schedule consequence and does not record and drive resolution of the current issue, so it is weaker than B.
- D. When you can act within your own authority, handle and record it proactively instead of passing it up at the first sign of trouble; “approving the delay” is also not what needs solving now, since the first job is to find a way to reduce the impact.
Key takeaway What has already happened is an issue: record it in the issue log and act. The risk register holds only uncertain events that have not happened; follow-on effects of an event that has happened can be managed separately as risks if they have not yet occurred.
Variation If the stem were changed to “the supplier is short of cash and might go out of business”, nothing has happened yet, so it is a risk and should be recorded in the risk register and assessed.
Something wrong with this question?
Example 2 What to do when the impact crosses the threshold
A company sets the risk threshold for the cost objective at ±8%, and risks beyond this threshold exceed the project manager's decision authority. After assessment, the project manager finds that an identified threat, if it occurs, would cause a 15% cost overrun, which is beyond the threshold. What should the project manager do?
Show answer and explanation
Correct answer: B
The company sets a cost risk threshold of ±8%. An identified threat, if it occurs, would cause a 15% cost overrun, exceeding the threshold. The question asks what the project manager should do.
The risk threshold measures acceptable variation around an objective and reflects the risk appetite of the organization and stakeholders. The threat's impact is 15%, greater than 8%, so it has crossed the threshold and can no longer be passively accepted at the current tolerance; and the stem states that such risks exceed the project manager's decision authority, so someone with authority must decide. Therefore escalate it and submit it to the sponsor and governance level for a decision. The answer is B.
Why the other options are wrong
- A. Choosing a strategy alone and reporting afterward oversteps authority. The risk has crossed the threshold, the decision does not belong to the project manager, and reporting afterward is no safeguard.
- C. Adding contingency reserve only inside the project means the team absorbs the risk itself, bypassing the requirement that a risk over the threshold be decided by those with authority, and the sponsor and governance level do not know.
- D. Logging and monitoring is too passive for a threat that has crossed the threshold. The risk is beyond the project manager's authority, and someone must decide and respond; it cannot just be watched.
Key takeaway When a risk crosses the threshold and exceeds the project manager's authority, escalate it to the sponsor and governance level for a decision.
Variation If the threat would cause only a 5% overrun, within the threshold, the project manager could choose a response strategy within delegated authority, with no need to escalate.
Something wrong with this question?
Common traps
Common trap
- Something that has already happened is an issue and goes in the issue log, not the risk register.
- Known-known facts and requirements are managed as part of scope; they are not risks.
- Overall project risk is not the sum of the individual risks.
- An opportunity is also a risk. Risk appetite, risk threshold and risk tolerance are three different concepts; do not mix them up.
How the three "lines" differ
- Risk appetite: willingness to accept uncertainty; it is an attitude.
- Risk tolerance (a common exam term): whether you can withstand it; it is an upper limit.
- Risk threshold: a measure of acceptable variation; it is appetite quantified (the exam often shortens it to "do we need to act?", meaning that going beyond it calls for further response or escalation).
Common exam practice: tolerance is the outer limit, appetite is the willingness within that capacity, and the threshold is the measurable trigger line.
Key takeaways
- A risk is an uncertain event or condition and can be positive (opportunity) or negative (threat); describe it as cause, event and consequence.
- What has happened is an issue and goes in the issue log; what has not happened is a risk and goes in the risk register; what is certain is a fact or requirement.
- Four kinds of uncertainty: known-known is not a risk; known-unknown is a classic risk whose probability and impact can be identified (with a proactive response strategy, a contingency reserve may be set); unknown-known (someone knows, the performing entity does not) is also a risk; unknown-unknown relies on management reserve and project resilience.
- Overall project risk is not the sum of the individual risks (interactions between risks may amplify or cancel).
- Appetite answers "are we willing?", tolerance answers "can we withstand it?", and the threshold answers "how large a variation must be dealt with?" (often shortened to "do we need to act?" on the exam); common exam practice is to picture tolerance as the outer limit, appetite as the willingness within that capacity, and the threshold as the measurable trigger line.
- Exposure below the threshold is acceptable; crossing it should trigger assessment and a decision, which may be to respond, escalate or accept with approval; appetite goes into the risk management plan.
Lesson 2
Project Resilience, Integrated Risk Management and Tailoring
Lesson overview
This lesson answers three questions. What do you do about risks nobody could foresee (unknown-unknowns)? What do you do when a risk is beyond the project's own ability to handle? How does risk management differ between predictive and adaptive projects? The answers are project resilience, integrated risk management and tailoring of risk management. This topic is often tested in adaptive scenarios. The next lesson covers the Plan Risk Management process and the risk management plan. ECO: Business Environment domain, Task 5 (Plan and manage risk).
Project resilience: preparing for risks nobody can foresee
Unknown-unknown risks cannot be identified in advance, so there is no way to plan a response to each one. They are handled through project resilience: the ability to absorb impacts and recover quickly from setbacks or failures. Projects cannot avoid every disruption, so building resilience is part of risk management.
Common exam practice for building resilience includes:
- Hold reserves: contingency reserve covers known-unknowns and management reserve covers unknown-unknowns.
- Build a flexible change management mechanism, so that surprises can be assessed and approved quickly.
- Empower and trust the team: the people on the ground see the early signs first, and being authorized to act first allows fast recovery.
- Watch for early risk signals: trends, indicators and front-line feedback can all serve as warnings.
- Communicate with stakeholders in advance: agree beforehand the strategies that may be used in a surprise.
When a question asks "how to deal with an unknown-unknown risk", the direction is reserves and resilience, not "run a more detailed identification".
Integrated risk management: risks can flow up and down
This section covers how risk moves between levels. Integrated risk management is a common exam term: risks outside the project's scope or authority are escalated, risks identified at a higher level can be delegated down to the project team, and risk management across levels should remain consistent.
To decide whether to hand a risk up, check two things: does the impact extend beyond this project (for example, to other products sharing the same component), and do the resources or authority needed for the response exceed the project manager's remit? If either is true, escalate to the level that matches the affected objectives, and the relevant owner takes it over. After escalation the project team no longer monitors it, though it may still record it.
Tailoring: risk management should fit the project
PMBOK 8 lists these tailoring considerations: project size and complexity, the organization's risk appetite and threshold, a holistic view of project risk management (risk impacts and responses viewed across domains such as schedule, budget, scope and stakeholders), the strategic importance of the project, the development approach (predictive, adaptive or hybrid), flexibility in planning and implementing risk responses, use of complementary techniques such as generative AI and data analytics, and resilience planning for major disruptions.
Risk management in predictive and adaptive approaches
- Predictive: scope is relatively stable, risks are usually identified and analyzed and responses planned in a concentrated way early on, identified risks are managed with schedule and cost reserves, and reviews follow planned milestones. New risks are still identified, and responses implemented and monitored, throughout the project.
- Adaptive: requirements keep evolving and risks can appear at any time. PMBOK 8's agile example: a risk assessment at the start of each iteration; a risk review meeting with stakeholders at the end of each iteration; and risk-adjusted backlogs to stay aligned with changing requirements.
- Hybrid: use predictive practices for the stable parts and adaptive practices for the changing parts.
For example, a new packaging line project has a stable scope: risk identification is concentrated early, reviews follow milestones, and the contingency reserve is estimated up front and included in the cost baseline, then adjusted through reserve analysis as risks change. A companion-robot prototype has requirements that change every month: risks are identified at the start of each iteration, the probability and impact scales are simplified to three levels, a contingency reserve is set as needed for identified risks, a management reserve is planned for unforeseeable work, and team empowerment is strengthened. Giving the first plan to the second project would leave risk management out of touch with reality.
A risk-adjusted backlog is a backlog that adds risk response work to the planned features and work items and orders everything by risk and value together. Risk response work can be written as stories, tasks and other backlog items and kept on the same list as functional items. The product owner is responsible for ordering; the team may discuss it during ongoing backlog refinement, and whether an item goes into the current iteration is decided at iteration planning. (Common exam practice.) In an adaptive project, risk management is a collaboration of everyone; no dedicated person carries it for the team, and newly found risks are first made known openly to the team.
A spike (a common exam term) is a time-boxed research or prototype experiment the team runs to reduce technical and solution uncertainty and find out whether something is technically feasible. When it is still uncertain whether a risk is real, one time-boxed spike works better than speculating about "what if it cannot be used". Even after a risk has been identified, a spike can be used when the response or its technical feasibility still needs to be validated. Once the risk has occurred, it is handled as an issue and the corresponding measures are carried out. Exploratory code is usually not handed to the customer as a deliverable, but the findings and knowledge can be kept.
Worked examples
Example 1 A risk beyond the project's scope
A project manager is in charge of developing an electric-vehicle battery pack. A team member points out that a control chip currently in use may fail at high temperatures. After an initial assessment, the project team and sponsor agree that the risk would affect both this project and other products under development that use the chip and is outside this project's scope. What should the project manager do?
Show answer and explanation
Correct answer: D
On an electric-vehicle battery pack project, a member points out that the control chip in use may fail at high temperatures, and other products under development that use the chip would be affected too. The question asks what the project manager should do.
After the initial assessment, the project team and sponsor have agreed that the risk is outside this project's scope, so it meets the condition for escalation. PMBOK 8 lists escalation as a threat response strategy when the project team or sponsor agrees that a risk is outside project scope or that the proposed response would exceed the project manager's authority. This project alone cannot solve the other products' problem, so escalate it to senior management. The answer is D.
Why the other options are wrong
- A. Risk analysis is an important step after identification, but quantitative analysis is not required for every risk; and since this risk's impact goes beyond this project, the key is to report to the management level that matches its impact, where a higher level can coordinate.
- B. Suspending the project and replacing the supplier is an overreaction: the risk has not been analyzed in depth or approved for such a step, and it looks after only this project while the effect on other products remains unaddressed.
- C. Passing the chip to purchasing while this project only logs and monitors it leaves a cross-project risk inside this project. A risk that affects other products should be actively reported upward, whoever manages it.
Key takeaway When a risk's impact goes beyond this project's scope or the response exceeds your authority, use the escalate strategy so that the level able to coordinate handles it.
Variation If the risk affected only this project and the response were within the project manager's authority, analyze and respond within the project, with no need to hand it up.
Something wrong with this question?
Example 2 Overall risk strategy for an adaptive project
A startup making innovative hardware runs an exploratory product project full of uncertainty and many risks, and the team uses an agile approach. What overall strategy should the project manager use to manage these risks?
Show answer and explanation
Correct answer: A
A startup's exploratory hardware product project has high uncertainty and many risks, and the team uses an agile approach, which is an adaptive environment. The question asks for the project manager's overall strategy for managing these risks.
In an adaptive project, requirements and solutions keep evolving and risks change with them, so risk planning done once at the start is not enough. The overall strategy is to assess risks continuously throughout the project and adjust the priorities of the backlog as the work progresses and requirements change, so that newly emerging risks and opportunities are scheduled into the work promptly. This fits the adaptive rhythm of small iterative steps and constant feedback. The answer is A.
Why the other options are wrong
- B. Concentrating risk analysis in the retrospective at the end of the project is too late. Risk management must run through the whole project; by the end, risks have long since happened or disappeared.
- C. Appointing a dedicated agile risk manager to carry it alone goes against the agile emphasis on the whole team sharing responsibility and watching risk, and it does not ensure that risks are assessed continuously and reflected in priorities.
- D. A risk matrix can serve as a tailored tool for tracking and evaluating risk, but it is only a means; it cannot replace continuous risk assessment and the overall strategy of adjusting backlog priorities accordingly.
Key takeaway Managing risk in an adaptive project: assess continuously throughout, and adjust priorities as the work progresses, not plan once.
Variation With a predictive approach, risk planning is usually more systematic early on, and risks are identified, analyzed, responded to and monitored as planned throughout the life cycle.
Something wrong with this question?
Common traps
Common trap
- Unknown-unknown risks are handled with reserves and resilience, not by "making identification more detailed".
- Common exam practice: risks can flow both up and down between levels, not only up as reports.
- An adaptive project does not skip risk management; it embeds it in every iteration. Common exam practice: an adaptive project usually has the cross-functional team manage risks together and should not hand the whole responsibility to a dedicated person; but large, complex or high-risk projects may still assign a dedicated risk manager for support as tailoring requires (PMBOK 8 mentions appointing dedicated risk managers in its large-project example).
- Common exam practice: in an adaptive project, risk response work suited to the team to carry out and track can go into the backlog and be ordered together with functional items.
Key takeaways
- Project resilience is the ability to absorb impact and recover quickly, and it is used for unknown-unknowns.
- Ways to raise resilience: hold reserves, flexible change mechanisms, empower and trust the team, watch for early signals, and communicate with stakeholders in advance.
- Integrated risk management (a common exam term): risks flow up and down between levels; a risk beyond the project's scope or authority goes up under the escalate strategy.
- Tailor risk management to size, complexity, strategic importance, development approach and organizational appetite.
- Predictive projects usually identify and analyze risks and plan responses in a concentrated way early on, but still manage risk throughout; adaptive projects assess at the start of each iteration, review with stakeholders at the end, and order a risk-adjusted backlog.
- A spike (a common exam term) is a time-boxed quick experiment to confirm feasibility; exploratory code is usually not delivered as product, while the findings and knowledge are kept.
Lesson 3
Plan Risk Management and the Risk Management Plan
Lesson overview
This lesson moves on to the first process of the Risk performance domain, Plan Risk Management, which answers "how will we manage risk on this project?" and produces the risk management plan. The question types are very stable: they either ask "what is in the plan?" or "which document do you check first in this situation?" Specific risks do not appear until the next chapter, on the risk register. ECO: Business Environment domain, Task 5 (Plan and manage risk).
Plan Risk Management: process, inputs and outputs
Plan Risk Management defines how to conduct risk management activities for a project. PMBOK 8 stresses that the process should begin when a project is conceived and be completed early in the project, because it determines how every later risk activity is done.
Like the plans for scope, schedule and financial management, the plan it produces is procedural: it mainly describes "how" risk management activities will be carried out, and it does not record specific individual project risks. Specific risks are recorded in the risk register, which is not produced by this process; it is first compiled in Identify Risks. So the risk management plan contains no specific risk at all.
| Item | Content |
|---|---|
| Inputs | Project charter; project management plan; project documents (stakeholder register); enterprise environmental factors; organizational process assets |
| Tools and techniques | Expert judgment; data gathering (interviews); data analysis (stakeholder analysis); meetings |
| Outputs | Project management plan updates (risk management plan) |
The project charter gives objectives, summary-level risks and high-level requirements, and is the starting point. The stakeholder register supplies each party's role, needs and influence, which is used to set risk management roles and responsibilities. Stakeholder analysis and interviews then reveal each party's risk appetite, and the appetite and measurable thresholds are recorded in the risk management plan.
The order for developing the plan: read the charter; use the register and interviews to understand the key stakeholders' appetites; write those appetites as measurable thresholds around each objective (for example, "report to the sponsor when cost variance exceeds ±10%"); use them to define probability and impact; set categories, responsibilities, funding and timing; then review with key stakeholders and incorporate the plan into the project management plan.
What the risk management plan contains
The risk management plan is a component of the project management plan that describes how risk management activities will be structured and performed. PMBOK 8 says it may include some or all of the following: risk strategy (the general approach), methodology (approaches, tools and data sources), roles and responsibilities, funding (including protocols for the application of contingency and management reserves), timing (when and how often the risk processes are performed), risk categories (commonly structured with a risk breakdown structure), stakeholder risk appetite (measurable thresholds around each objective) and definitions of risk probability and impacts.
Organizing it by question works better for scenario questions:
| Question | Which part of the plan to check |
|---|---|
| How often are risks reviewed? | Timing |
| Who identifies, and who responds? | Roles and responsibilities |
| What is the protocol for using contingency reserve? | Funding |
| Is this cost variance high or low? | Definitions of probability and impact, thresholds |
| Which category does this risk belong to? | Risk categories (RBS) |
The risk breakdown structure (RBS) is a hierarchical representation of potential sources of risk. It helps with identification (the lowest-level risk categories can serve as a prompt list, asking level by level downward) and also categorizes identified risks.
The definitions of probability and impact must fit the project context: the number of levels is tailored to the project's needs, with three levels for a simple process and five or more for a more detailed one. The same scale can evaluate both threats and opportunities, with impact interpreted as negative for threats and positive for opportunities. Scales should be tailored to the thresholds of the project and the organization. The example in PMBOK 8, Table 4-2, uses absolute ranges: probability in six bands (<1%, 1%-10%, 11%-30%, 31%-50%, 51%-70% and >70%, labeled insignificant, very low, low, medium, high and very high); time impact from "no change" through 1 week, 1-4 weeks, 1-3 months and 3-6 months to >6 months; and cost impact in dollar bands from "no change" through <US$100K, US$100K-$500K, US$501K-$1M and US$1M-$5M to >US$5M. The scale below is a numeric scale commonly seen in training (values from 0.05 to 0.80 and percentage ranges). It is an illustrative example used here only to practice reading a scale:
| Project objective | Very low | Low | Medium | High | Very high |
|---|---|---|---|---|---|
| Numeric value (example) | 0.05 | 0.10 | 0.20 | 0.40 | 0.80 |
| Cost | Insignificant increase | Increase under 10% | Increase of 10%-20% | Increase of 20%-40% | Increase over 40% |
| Schedule | Insignificant delay | Delay under 5% | Delay of 5%-10% | Delay of 10%-20% | Delay over 20% |
Example: from risk appetite to impact definitions
A supermarket chain is building a loyalty-points mini-app. The sponsor says: if launch is up to two weeks late, stores can still adjust promotions, but if it is more than four weeks late, the holiday sales window is missed and he wants to be told. The project manager therefore sets the schedule risk threshold at "four weeks late", and the schedule impact scale follows: up to one week is "low", over one week up to two weeks is "medium", over two weeks up to four weeks is "high", and over four weeks is "very high". From then on everyone understands "high" the same way.
Is the matrix part of the risk management plan?
PMBOK 8's list of plan contents does not include a probability and impact matrix. Ranking rules can be specified by the organization in advance or tailored for the project, and the matrix, as a tool, is covered in the Perform Risk Analysis chapter.
Worked examples
Example 1 Which document do you check first: how often to review
A project at PMLyceum involves several suppliers and has heavy delivery pressure. At a regular meeting, the sponsor asks how often risks are reviewed. Which document should the project manager consult FIRST?
Show answer and explanation
Correct answer: B
A project involves several suppliers and has heavy delivery pressure. At a regular meeting, the sponsor asks how often risks are reviewed. The question asks which document to consult first.
The sponsor's question is about the rule, “how often to review”, not about the state of one specific risk. Rule-type content, including the timing and frequency of risk management activities, roles and responsibilities, risk categories and thresholds, is set in the risk management plan, which defines how often the risk processes are performed over the life cycle. So consult the risk management plan first. Information on specific risks is in the register, what has happened is in the issue log, and reports on risk status are in the risk report; none of them defines frequency. The answer is B.
Why the other options are wrong
- A. The risk register records specific details of identified individual risks, such as responses, owners and status; it does not set how often risk is reviewed.
- C. The issue log records issues that have occurred and how they were handled, tracking what has already happened; it has nothing to do with the rule on how often risks are reviewed.
- D. The risk report summarizes overall project risk and the state of individual risks. It reports results and does not define how often risk reviews take place.
Key takeaway For how often risks are reviewed and how they are managed, check the risk management plan; for the state of a specific risk, check the risk register.
Variation For “who is responsible for responding to a certain kind of risk”, check the roles and responsibilities in the plan; for “the owner of one specific risk”, check the risk register.
Something wrong with this question?
Example 2 Which item is not part of the plan
Which of the following is NOT content that a risk management plan should contain?
Show answer and explanation
Correct answer: C
To find the item that should not appear in the risk management plan, you must separate what belongs in the risk management plan from what belongs in the risk register.
The risk management plan sets “how to manage risk”. Its content is rules and framework and it does not record specific risks. The trigger conditions and owner of each threat are information about one identified risk and change risk by risk, so they belong in the risk register. The other three are rules: risk categories group risks, roles and responsibilities set who does what, and measurable risk thresholds express the stakeholders' risk appetite. The stem asks for the item that does NOT belong, so the answer is C.
Why the other options are wrong
- A. Risk categories (often grouped with a risk breakdown structure) are one element of the risk management plan, used to categorize individual risks; they are a rule and should appear in the plan.
- B. Roles and responsibilities for the risk management activities are set out in the plan, saying who leads, who supports and who takes part; they belong in the plan and are not the item to exclude.
- D. Measurable risk thresholds set for each project objective quantify stakeholders' risk appetite and go into the plan; they are plan content and not the item to exclude.
Key takeaway The risk management plan says “how to manage”; detailed information such as a specific risk's triggers and owner goes in the risk register, while the risk report may summarize information about individual risks.
Variation For the difference between plan and register, remember one sentence: the plan covers “how to manage” and the register covers “what to manage”.
Something wrong with this question?
Common traps
Common trap
- The risk management plan is procedural and contains no specific risks; specific risks are in the risk register.
- The risk register is not an output of Plan Risk Management; it starts with Identify Risks.
- Risk thresholds come from the preferences of key stakeholders; the project manager does not invent them.
- Definitions of probability and impact must be tailored; do not copy the example scale. If there is no risk management plan, plan risk management first; do not start by identifying risks.
Key takeaways
- Plan Risk Management defines how to conduct risk management, produces the risk management plan and is completed early in the project.
- The risk management plan covers only how to manage; it records no specific risks.
- The stakeholder register is used to set roles, responsibilities and thresholds, and stakeholder analysis is used to establish risk appetite.
- Plan contents: risk strategy, methodology, roles and responsibilities, funding, timing, risk categories, stakeholder risk appetite, and definitions of probability and impact.
- The RBS is a hierarchical representation of risk sources; it helps with identification and with categorizing.
- How often to review, who is responsible, how reserves are used and what counts as high risk: check the risk management plan first.
This chapter has 34 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.