After Plan Resource Management, Estimate Resources and Acquire Resources, the Resources performance domain has two processes left: Lead the Team and Monitor and Control Resourcing. Monitor and Control Resourcing comes last. It watches planned versus actual use of resources, spots the gaps and corrects them in time. The three lessons in this chapter move from the process itself, to the order of response when a deviation appears, to the most common scenario of all: changes in team members.
What this chapter covers
PMBOK 8 describes the process this way: Monitor and Control Resourcing helps ensure that the physical or virtual resources assigned and allocated to the project are available as planned, monitors the planned versus actual use of those resources, and performs corrective actions as necessary. It runs continuously throughout the project life cycle. It is concerned with equipment, materials, supplies, facilities, infrastructure, software, testing environments, licenses, services and other relevant resources. Team members are addressed in the Lead the Team process, but exam scenarios about changes in team members call for the same line of thinking, so the last lesson of this chapter covers them. This chapter maps to ECO: Process domain, Task 4 (Plan and manage resources), in particular managing and optimizing resource requirements and availability, and some questions also touch on knowledge transfer and leading the team. Questions are mostly scenario-based and almost always ask what to do "FIRST" or "NEXT". One rule sits behind nearly all of them: assess first, then act. Lesson 1 builds the framework and the tools, Lesson 2 covers the order of response and change requests, and Lesson 3 applies that order to people changes. Studying them in this sequence works best.
Lessons in this chapter
- Lesson 1: Monitor and Control Resourcing: Purpose, Inputs, Outputs and Data Analysis Tools. Purpose and boundaries; the resource management plan, resource assignments and work performance data; performance reviews, trend analysis, alternative analysis and cost-benefit analysis (with a worked example).
- Lesson 2: Assess Before You Act: Resource Variances and Change Control. Confirm the facts, assess the impact, choose a remedy, then act or raise a change request; a side-by-side of eight high-frequency scenarios; what to do when a baseline exists.
- Lesson 3: Team Member Changes. What to do when a member is reassigned, resigns or takes long leave; knowledge handover; negotiating with the functional manager.
Chapter map
The first diagram shows the main line of the process: work from the plan, compare against the resource assignments, run a performance review, then assess and take corrective action, negotiate where needed, and raise a change request when the management plan or a baseline is affected. The second diagram shows the order to follow once a deviation is found: assessment first, change afterward. When a question says "FIRST", check whether the stem shows that the impact has already been assessed. If it has not, the answer is most likely the assessment.
Lesson 1
Monitor and Control Resourcing: Purpose, Inputs, Outputs and Data Analysis Tools
Lesson overview
However neatly resources are scheduled during planning, execution brings surprises: equipment arrives late, licenses run out early, the test environment is taken over by another project. Monitor and Control Resourcing is the last process in the Resources performance domain. It watches the gap between plan and actual and corrects course in time. This lesson answers three questions: what the process is for and where its boundaries lie, what its inputs and outputs are, and which tools to use when a deviation appears. ECO: Process domain, Task 4 (Plan and manage resources), covering managing and optimizing resource requirements and availability. There are two worked examples in this lesson: one asks what to do routinely to avoid a capacity gap, and the other asks how to handle a resource cost overrun. The next lesson covers "assess before you act", and the one after that covers team member changes.
Purpose and boundaries
PMBOK 8 says: "The Monitor and Control Resourcing process helps ensure that the physical or virtual resources assigned and allocated to the project are available as planned. The process also monitors the planned versus actual use of physical or virtual resources and performs corrective actions as necessary. The key benefit of this process is ensuring that the assigned physical or virtual resources are available to the project at the right time and in the right place and are released when no longer needed." The process should be performed continuously in all project phases and throughout the project life cycle.
The resources it is concerned with include equipment, materials, supplies, facilities, infrastructure, software, testing environments, licenses, services, or any other relevant resources. PMBOK 8 states plainly that team members are addressed in the Lead the Team process. Even so, exam scenarios about members being reassigned, going on leave or resigning use the same line of thinking as monitoring processes, and the last lesson of this chapter is devoted to them. Work performance information is usually intended for assessing resource usage as part of project status. PMBOK 8 notes that it is also common practice to use it to assess individual performance; team performance is assessed under Lead the Team.
Why monitor continuously? PMBOK 8 gives three examples. Failing to secure critical equipment or infrastructure on time may delay manufacture of the final product. Ordering low-quality materials may damage product quality and cause a high rate of recalls or rework. Keeping too much inventory raises operational costs, while an unacceptably low inventory level hinders the ability to satisfy customer demand, and both reduce the organization's profit. The process is concerned with:
- Monitoring resource expenditures.
- Identifying and dealing with resource shortages and surpluses in a timely manner.
- Ensuring that resources are used and released according to the plan and project needs.
- Informing appropriate stakeholders if any issues arise with relevant resources.
- Influencing the factors that can create resource utilization changes.
- Managing the actual changes as they occur.
Inputs and outputs
| Item | Content |
|---|---|
| Inputs | Resource management plan; issue log, lessons learned register, physical or virtual resource assignments, project schedule, resource breakdown structure, risk register; work performance data; agreements; organizational process assets |
| Tools and techniques | Data analysis (alternative analysis, cost-benefit analysis, performance reviews, trend analysis); problem-solving; interpersonal and team skills (negotiation, influencing); project management information system; value stream mapping, continuous improvement, theory of constraints, control charts, branch and bound, etc. |
| Outputs | Work performance information; change requests; project management plan updates (resource management plan, schedule baseline, cost baseline); project document updates (assumption log, issue log, lessons learned register, physical resource assignments, resource breakdown structure, risk register) |
Put the inputs and outputs together and you get the main line. Work from the resource management plan, compare against the resource assignments, and run a performance review on the work performance data to find the gap between planned and actual use. Then assess the gap and take suitable corrective action: negotiate where needed, and raise a change request when the plan or a baseline is affected. Without actual usage data there is nothing to monitor, so data collection has to be continuous. Resources that are surplus or no longer needed should be released promptly.
The four data analysis tools
PMBOK 8 notes that the Monitor and Control Resourcing techniques discussed here are those used most frequently on projects implementing a predictive approach. Figure 2-45 lists only the names of these four data analysis tools. The descriptions below reflect common exam practice. Each one answers a different question:
- Performance reviews: measure, compare and analyze planned versus actual resource usage. Question answered: how big is the gap?
- Trend analysis: use current performance information to judge resource needs in future periods and see how performance changes over time. Question answered: what will happen?
- Alternative analysis: pick the best corrective option from several, such as renting equipment temporarily, switching to substitute facilities, shifting when resources are used or delivering in phases (people issues belong under Lead the Team). Question answered: what are the options?
- Cost-benefit analysis: compare the cost of each alternative with its expected benefit and choose the option with the best overall benefit or the most cost-effective one (the best option may require extra spending). Question answered: which one is worth it?
In addition, negotiation and influencing are used to obtain resources or coordinate conflicts, problem-solving identifies and resolves resource problems, and the project management information system tracks resource use. Value stream mapping, continuous improvement, theory of constraints, control charts and branch and bound are used to analyze and optimize when resources show bottlenecks or waste.
Worked example: test servers over-used
A bank's core-system migration project plans to use 4 test-environment servers per week. From week 3 on, actual use is 6 servers per week. A performance review finds a weekly overrun of 2 servers. Trend analysis shows that if the test scope stays unchanged, the overrun will continue for the next four weeks, adding up to 8 extra server-weeks. The project manager compares three alternatives: rent cloud servers temporarily at $1,500 per server-week; stagger the test windows so the peak returns to 4 servers, which extends the overall testing period by one week; or reduce the test scope. Cost-benefit analysis shows that reducing scope would remove mandatory regression tests and is therefore unacceptable; renting 8 server-weeks costs $12,000, while a one-week delay carries an indirect cost of about $30,000, so renting is chosen. The project manager then submits a change request on that basis; once it is approved, the resource management plan and cost baseline are updated. All four kinds of analysis were used in turn, and the result is a change request, not an immediate cut or an immediate cash injection.
Worked examples
Example 1 Installation delay: what to do routinely to spot capacity problems early
At PMLyceum, a data-center expansion project is behind because rack installation was delayed, and many later activities are affected. The equipment delivery manager tells the project manager that there is not enough specialized lifting equipment, and there are not enough tools, for rack installation, so capacity cannot keep up. What should the project manager have done to avoid this situation?
Show answer and explanation
Correct answer: C
A data-center expansion project is behind because rack installation was delayed, and many later activities are affected. The equipment delivery manager says there is not enough specialized lifting equipment, and there are not enough tools, for installation, so capacity cannot keep up. The question asks what the project manager “should have done”, that is, the routine practice that would have prevented this.
Monitor and Control Resourcing deals with physical resources such as equipment, materials and facilities. Throughout the life cycle it keeps comparing planned with actual use of resources, to ensure they are available at the right time and place, and takes corrective action when a gap appears. Regularly reviewing the availability and capacity of installation equipment and tools with the delivery manager would have exposed the gap before it hit the schedule, which is exactly what PMBOK 8 means by identifying and dealing with resource shortages in a timely manner. The answer is C.
Why the other options are wrong
- A. The stem does not say the capacity problem came from not following the resource management plan. Requiring people to “follow the plan” would neither find the capacity gap nor prevent the next one.
- B. Meeting regularly with crews to check activity conflicts has some value, but conflicts are not the root of the shortage of equipment and tools. Finding out whether resources are available and sufficient is more direct than checking schedules.
- D. The scope statement describes scope; it is not the document that sets out skill requirements. Even if it did, it would not detect changes in actual resource availability.
Key takeaway Monitor and Control Resourcing is continuous: regularly review resource availability and capacity so gaps are found before delays occur.
Variation If the stem were changed to “a capacity gap has already appeared; what should you do?”, you would first run a performance review and trend analysis, assess the impact, then negotiate or raise a change request.
Something wrong with this question?
Example 2 Rented equipment costs more than planned: how to handle it
A distribution-center renovation project at PMLyceum has entered execution. While monitoring resources, the project manager finds that actual spending on rented forklifts and warehouse equipment is already above plan and is expected to keep overrunning. What should the project manager do?
Show answer and explanation
Correct answer: C
A distribution-center renovation project is in execution. While monitoring resources, the project manager finds that actual spending on rented forklifts and warehouse equipment is already above plan and expected to keep overrunning. The question asks what to do.
The data analysis techniques for Monitor and Control Resourcing include alternative analysis and cost-benefit analysis. Facing an overrun on rented equipment, first list the different resource mixes (quantities, rental periods, rent or buy, staggered usage times), compare cost and benefit for each, and choose the mix that meets work needs while controlling cost. If the adjustment touches a baseline, then raise a change request. This is “analyze first, act after”. The answer is C.
Why the other options are wrong
- A. Cutting proportionally without analysis may leave too little resource, delay the schedule and trade delivery for cost.
- B. Additional budget should be considered after analyzing the resource mix and other feasible alternatives. Applying for extra money without that analysis commits prematurely to one solution.
- D. Leaving the overrun until closure amounts to giving up monitoring. Cost variances should be handled during execution; lessons learned are an after-the-fact supplement, not a response.
Key takeaway When resource costs overrun, use alternative analysis and cost-benefit analysis to optimize the resource mix instead of simply cutting or adding money.
Variation If the stem asked “how much more than planned is actual usage?”, that is a performance review; if it asked “will it keep overrunning in the coming weeks?”, that is trend analysis.
Something wrong with this question?
Common traps
Common trap
- Monitor and Control Resourcing is continuous, not something done only when a problem appears. Regularly reviewing resource availability and capacity is how you find a gap before a delay occurs.
- When resource costs overrun, first use alternative analysis and cost-benefit analysis to optimize the resource mix instead of simply cutting or simply adding money.
- The resource management plan is the basis, but asking people to "follow the plan" is not monitoring. Monitoring compares actual usage data against the plan.
- The scope statement describes scope; it is not the document that sets out skill requirements.
- Performance reviews ask "how big is the gap?", trend analysis asks "what will happen?", alternative analysis asks "what are the options?" and cost-benefit analysis asks "which one is worth it?"
Key takeaways
Key point
- Monitor and Control Resourcing: ensure physical or virtual resources are available as planned, monitor planned versus actual use and take corrective action as necessary; it runs throughout the life cycle, and resources are released when no longer needed.
- Inputs include the resource management plan, physical or virtual resource assignments and work performance data; outputs are work performance information, change requests, and plan and document updates.
- Main line: compare against the plan and the assignments, use performance reviews to find the gap, then assess and take suitable corrective action; negotiate where needed, and raise a change request when the plan or a baseline is affected.
- Data analysis: performance reviews, trend analysis, alternative analysis, cost-benefit analysis.
- Team member matters are addressed in the Lead the Team process.
Lesson 2
Assess Before You Act: Resource Variances and Change Control
Lesson overview
When monitoring finds a deviation, the project manager's most common mistake is to "do something right now": escalate immediately, add people immediately, change the plan immediately. The exam tests exactly this order. This lesson covers the line of thinking shared by monitoring processes: establish the facts, assess the impact, then decide on a remedy; and if the remedy touches a baseline, go through change control instead of changing it yourself. Typical stems in this lesson include a key member who may leave, a resource shortage causing delays, a plan that does not match team capability, resource allocation that conflicts with priorities, and a senior-management decision that shrinks the team. The previous lesson covered the tools; this one covers the order of response when a deviation appears.
Assess first, then act
Monitor and Control Resourcing is concerned with "identifying and dealing with resource shortages and surpluses in a timely manner" and "managing the actual changes as they occur" (PMBOK 8, Section 2.6.2.5). Those two phrases carry a built-in order: identify first, then deal. Broken down, it becomes four steps (common exam practice):
- Confirm the facts. Is the deviation real, how big is it, and has it already happened or might it happen?
- Assess the impact. Look at the effect on schedule, cost, quality, scope and risk, using methods such as performance reviews and trend analysis.
- Choose a remedy. Use alternative analysis and cost-benefit analysis to compare several options and pick the most worthwhile one.
- Act or raise a change. If the remedy is within your authority, do it directly. If it touches a baseline or an item under configuration control, raise a change request in line with the change management plan, the configuration management plan and your authorization, and follow the change control procedure.
Scenario comparison
First, a point about ownership. PMBOK 8 states that Monitor and Control Resourcing is concerned with physical and virtual resources (the availability and usage variances of equipment, materials, facilities, software, testing environments, licenses and so on). A team member leaving, being absent, lacking a skill or being cut from the team is addressed in the Lead the Team process; in common exam practice it is combined where necessary with Monitor and Control Project Performance, Develop Schedule and Assess and Implement Changes. The people scenarios in the table below are a common way the exam tests "assess before you act", and they often appear alongside monitoring processes. The same method applies to physical and virtual resources, as the software license row shows.
The table below puts the common exam scenarios side by side. The left column is the signal in the stem and the right column is what to do first:
| Scenario in the stem | What to do first | Why |
|---|---|---|
| A key member may leave because of a company merger | Assess the impact of the departure on the project, then carry out the mitigation set out in the plan | It is only a "might"; it is not yet a fact. Assess before acting |
| A commissioning engineer will be absent for two weeks | Check the activities that person owns and assess the real effect on the schedule | The impact is unknown, so updating the plan has no basis |
| The schedule's workload exceeds the team's skills and capacity | Assess the capability gap, then adjust the plan or add resources | Quantify the gap first, and you can choose the right remedy |
| Resources are insufficient and there are delays in several places | Call the team together to discuss and assess the next action | Assess internally first, then agree; do not escalate directly |
| High-priority work gets fewer resources | Adjust the allocation to the established priorities and update the physical or virtual resource assignments | The allocation departs from established priorities, so correct it per the plan and update the records |
| The company is laying off staff and 20% of the team has been assessed as being on the list | First assess the impact of losing that 20% on schedule, cost, scope and risk, then discuss with the sponsor whether the project is still viable and agree the next step (if the impact analysis already shows the current scope and baselines cannot be maintained, go straight to the sponsor) | A senior-management decision is shrinking the team; scope and baselines may have to be renegotiated |
| Software licenses in the acceptance-test environment expire next week, but testing needs three more weeks | Check the license renewal cycle and the remaining usage need, assess the effect on the test schedule, then renew or adjust the plan | This is an availability deviation in a virtual resource; get the facts straight before choosing a remedy |
| An agile project keeps a schedule baseline; half the members are reassigned and cannot be replaced | Assess the remaining resources and submit a change request to modify the schedule or scope baseline | When the assessment shows the schedule or scope baseline must change, a change request is required; re-measuring velocity is only an input to the assessment; if the problem can be fixed within the current baseline and your authority, handle it under the change management plan |
Change control: used only after assessment
PMBOK 8 defines a change request as a formal proposal to modify a document, deliverable, or baseline, reviewed and handled by the Assess and Implement Changes process, which itself includes evaluating change requests and conducting impact analysis. Whether a formal request is needed is set by the change management plan, the scope of configuration control and your authority; a baseline change is not the only case that calls for one. Common exam practice: in a scenario question, you usually first learn the facts and make a preliminary assessment of the impact; when a formal change turns out to be needed, you raise a change request, complete the impact analysis and approval in the Assess and Implement Changes workflow, implement after approval, and do not modify baselines yourself. The outputs of Monitor and Control Resourcing (Figure 2-45) include change requests and also updates to the resource management plan, schedule baseline and cost baseline (project management plan updates), which is exactly the two-step "request first, update after approval". When resources shrink and a baseline exists, the project manager first assesses what can be done, then uses a change request to adjust the baseline and supplies alternatives for someone with authority to decide.
One point is easy to mix up. When a team uses an agile approach but the project also keeps a schedule baseline, a hybrid project facing a major resource change follows common exam practice: "baseline means change request". If the resource change makes it necessary to modify the schedule baseline or another formally controlled item, raise a change request under the change management plan; otherwise, correct within your authorization and the current baseline. Re-measuring velocity can supply data for the assessment but cannot replace the change request, and "being agile" is no reason to skip change control.
Worked example: a shrinking test team
A government-services platform upgrade is a predictive project with an approved schedule baseline and a 12-week delivery plan, in which the testing phase was originally four weeks with a five-person test team. In week 6, the department tells the project manager, Daniel, that two test team members will be pulled next week to support another urgent project and cannot be replaced in the short term. Daniel does not immediately ask the sponsor for help, and he does not ask the remaining people to work overtime. He does three things first. He checks the test scope owned by those two people and the effective hours of the remaining three, which cover only 60% of the original plan. He assesses the impact: assuming constant per-person productivity and linear scaling of the workload, the testing phase would stretch from 4 weeks to about 6.7 weeks, so delivery would be about 2.7 weeks late (close to three weeks). He compares three alternatives: first, deliver about three weeks late; second, go live in phases and move non-core features to a second release; third, ask a contractor to add one tester temporarily at a cost of about $40,000. He writes the assessment and the alternatives into a change request and submits it to the change control board. Once someone with authority has chosen and approved an option, he updates the relevant baselines, resource calendars and other project documents to match.
Worked examples
Example 1 A key member may be reassigned: what to do next
A retail-system upgrade project at PMLyceum is in execution. The company announces a merger of two business units, and several key members of the project may be reassigned as a result. What should the project manager do NEXT?
Show answer and explanation
Correct answer: D
A retail-system upgrade is in execution. The company announces a merger of two business units, and several key members “may” be reassigned. The question asks what the project manager should do next, so the order of actions matters.
Start with the word “may”: the members have not left, so the risk has not become a fact. The project manager should first determine what their leaving would do to the project and identify the potential risks, then carry out mitigation measures according to the project management plan, to keep the schedule and other objectives from being hurt. This is the common order for monitoring processes: assess first, then act. The option “assess the impact and carry out mitigation” contains both steps. The answer is D.
Why the other options are wrong
- A. Talking to the members and supporting them in the transition has its place, but it does not address the impact on the project and offers no mitigation. It is not what to do first.
- B. Finding replacements is one mitigation measure and should follow the impact assessment; besides, the members only “may” leave, which is not yet a fact.
- C. The merger is a company-level decision, so the project manager cannot “make sure” it will not affect the project. Analyze the impact proactively first instead of going to the sponsor first.
Key takeaway When key members may leave: assess the impact on the project first, then carry out mitigation measures according to the plan.
Variation If the stem said a key member “has already submitted a resignation”, you would still assess the impact first, but the risk has become fact, so you move into response: handover, replacement and plan adjustment.
Something wrong with this question?
Example 2 An agile team keeps a schedule baseline and half the members are reassigned
A 6-person team at PMLyceum is building an order system using an agile approach, and the project also keeps a schedule baseline. The project manager's assessment shows that the team's current velocity just meets the schedule baseline. Halfway through the project, the sponsor tells the project manager that 3 team members are being moved to another, higher-priority project and cannot be replaced. What is the project manager's BEST next action?
Show answer and explanation
Correct answer: A
This is a hybrid project: a 6-person team develops an order system with an agile approach and the project keeps a schedule baseline, and velocity currently just meets the baseline. Halfway through, the sponsor says 3 of the members are moving to a higher-priority project and cannot be replaced.
The key conditions are that the project “keeps a schedule baseline” and that headcount is “cut in half with no replacement”. Team capacity shrinks sharply, velocity is expected to drop significantly, and continuing against the original baseline is unrealistic; nor does using an agile approach let you bypass change control. The project manager should first assess what the remaining resources can deliver, then use a change request to adjust the schedule baseline (the baseline the stem explicitly keeps) and propose options for scope or the release plan, for someone with authority to decide. PMBOK 8 says change requests that affect project baselines are evaluated and implemented through the formal Assess and Implement Changes process; in adaptive environments, scope changes are typically approved dynamically by the product owner, but this question keeps a schedule baseline. Because this is a team-member issue, the project manager should assess the impact through Lead the Team. Because the schedule baseline is affected, the project manager should then submit a change request. The answer is A.
Why the other options are wrong
- B. Running several more iterations to re-measure velocity would delay the decision. Velocity data can serve as an input to the assessment but cannot replace the change request.
- C. Demanding overtime and paying bonuses without analysis squeezes the team. Overtime can hardly make up for a gap of half the people, and it does not deal with the baseline.
- D. Whether the project is terminated is not the project manager's decision, and change requests and alternatives can still be tried. Announcing termination outright is a defeatist response.
Key takeaway Resources are cut and a baseline exists: assess first, then use a change request to adjust the baseline and offer alternatives.
Variation If the stem were changed to a purely agile project with no formally controlled baseline, the product owner would reorder the product backlog, the team would update its forecast and communicate release expectations to stakeholders; if the project keeps a formal baseline, changing it must go through change control.
Something wrong with this question?
Common traps
Common trap
- When the options include "immediately escalate to the sponsor", "just add people", "change the baseline directly" and "assess the impact", check whether the assessment step comes first. The option that assesses or analyzes is usually the correct answer.
- A member who "may" leave has not left yet: assess and mitigate per the plan. Do not start by lining up a replacement, and certainly do not start by asking the sponsor to "make sure the project is not affected".
- Common exam practice: a change request comes after the assessment. A change raised without assessment is usually treated as out of order in scenario questions; impact information such as schedule and cost must be available before approval.
- Do not push the schedule through with overtime and bonuses without assessment, and do not announce the project's termination outright. Compare options such as crashing or outsourcing, and when the assessment shows a baseline must change, go through a change request.
- When resource shortages cause delays, first call the team together to assess, then agree on action; do not escalate directly.
Key takeaways
Key point
- The shared order for monitoring processes: confirm the facts, assess the impact, choose a remedy, then act or raise a change.
- A key member may leave, a key resource will be absent, or the plan does not match capability: assess first, then act.
- When the assessment confirms a formal change is needed, raise a change request under the change management plan and your authorization; changing a baseline or an item under configuration control requires the formal change control procedure, never a unilateral edit.
- Resources are cut and a baseline exists: assess first; if the current baseline cannot be maintained, raise a change request to adjust it and supply alternatives.
- Resource allocation departs from priorities: correct it to the established priorities and update the physical or virtual resource assignments.
- A senior-management decision shrinks the team: first assess the impact on schedule, cost, scope and risk (when the stem already gives the assessment result, start from the next step), then discuss project viability with the sponsor and decide the next step.
Lesson 3
Team Member Changes: Assessment, Handover and Negotiating with the Functional Manager
Lesson overview
The most common resource change in a project is not equipment but people: members are reassigned, resign, take long leave or get pulled away by the functional manager for other work. PMBOK 8 handles day-to-day team member matters in the Lead the Team process. When a member changes, you assess the impact, update project documents such as the resource calendars and project team assignments where needed, and go through the change process if the project management plan or a baseline is affected, so the thinking from monitoring processes comes in handy. Although this lesson is placed under the resource monitoring topic, team member changes belong to Lead the Team in PMBOK 8, and they are a frequent exam theme. Stems fall into four types: a key member is reassigned or leaves, knowledge handover after a newcomer takes over, a member is occupied by other work, and a member who wants to resign or take long leave. The answers share one idea: communicate and assess first, escalate and change later. ECO: Process domain, Task 4 (Plan and manage resources); some questions also touch People domain, Task 3 (Lead the project team) and Task 7 (Help ensure knowledge transfer), which means identifying knowledge critical to the project and creating an environment for knowledge transfer. The previous lesson covered the general order of assessment; this lesson applies it to people.
The order for handling member changes
First, a boundary: the PMBOK 8 Monitor and Control Resourcing process is concerned with physical and virtual resources, and team member matters are addressed in the Lead the Team process. The exam uses member changes as a resource-change scenario, and the thinking is the same as above. You can work through five steps (common exam practice):
- Assess the impact. Which activities does this person own, and how much would their absence affect schedule, cost, quality and risk?
- Check against the plan. Look at the resource management plan, responsibility assignment matrix and risk register for arrangements or responses already written down.
- Propose responses. Add people, redistribute duties, postpone, train, cross-train, and use alternative analysis where needed.
- Notify and negotiate. Communicate with the functional manager, the sponsor and stakeholders. If the response requires changing the project management plan, a baseline or a configuration-controlled artifact, follow the change process specified by the development approach, change management plan, configuration management plan and authority, raising a formal change request where required.
- Hand over knowledge and record. Make sure knowledge does not leave with the person, write the experience into the lessons learned register, and update the resource calendars and project team assignments (and the responsibility assignment matrix where needed).
Typical scenarios: when a member is replaced, the project manager first assesses the impact of the replacement and, if needed, adjusts resources further. When a resource is reassigned, first analyze the impact on the project, then decide whether to notify, raise a change or update the plan. When a key specialist leaves because of organizational downsizing, first check the resource management plan, then reassess and reallocate resources. When an external expert is about to leave, first discuss with the team and assess the impact, then decide on follow-up action. When a member requests three months of leave, first check the responsibility assignment matrix to find the affected activities, then check the risk register for an existing response.
Knowledge handover: when people leave, knowledge must not
The real risk in staffing changes is lost knowledge. Three rules apply. First, when a new member takes over complex work, the project manager should arrange explanation and coaching proactively; handing over a document library and leaving the person to work it out is not enough. Have the newcomer read the documents first, then arrange a meeting to explain the details, then assign the tasks. Second, prevent knowledge from concentrating in one person: use cross-training so members hold complementary skills, which means a senior member's departure does not stop a module. Third, when a member wants to leave, communicate first to learn the reason and find a solution together; do not force them to stay, and do not simply hand the problem to someone else. When a member resigns late in an iteration, the project manager takes the lead and agrees a mitigation plan with stakeholders.
Negotiating with the functional manager
In a matrix environment, the functional manager usually controls or takes part in allocating team resources, and the exact authority depends on the type of matrix. What the project manager negotiates with the functional manager is the "time" members commit to the project and how it is arranged. When a member is pulled away for other work and the impact is not yet known, first find out how the delay affects schedule and cost; if the impact is already clear and the question asks how to recover the resource, start by talking directly with the functional manager concerned, explaining the project's priorities and the risk of delay, and working with the member to find ways to speed up delivery. When the resource side has no time, proactive coordination to agree a time that works for both sides beats escalating or telling subordinates to sort it out themselves. When one member is shared by two teams, the teams should negotiate the time split directly, without delay and without escalating at the first sign of trouble.
Worked example: a core architect's three-month leave
A chain pharmacy's membership platform project is in month 7, slightly ahead of schedule and within budget. The systems architect, Mei, comes to the project manager, Alex, and says that a family member is ill and she needs three months of leave. Alex neither agrees at once nor looks for a replacement at once. He first opens the responsibility assignment matrix: Mei owns 4 work packages, 2 of which are already wrapping up, while the other 2 (payment integration and inventory sync) will be affected. He then checks the risk register, where the "key person absence" entry has a response: key roles should have a backup. The backup for payment integration is back-end engineer Priya, but inventory sync has none. On that basis Alex agrees with Mei that she will complete a handover within two weeks, writing up the interface notes and key decision records and recording a walkthrough session. He negotiates with the functional manager to borrow an engineer from the architecture group for three months as the inventory sync backup, which covers Mei's leave exactly. As soon as the arrangement is settled, he updates the project team assignments, resource calendars and responsibility assignment matrix; after the handover is complete, he records the arrangement in the lessons learned register.
Worked examples
Example 1 A core developer is reassigned and the newcomer has little experience
A mobile app team at PMLyceum develops with Scrum. An experienced core developer is moved away and replaced by a less experienced newcomer. A key stakeholder worries that the newcomer will take too long to get up to speed and the project may not deliver on time. What should the project manager do to help ensure successful delivery?
Show answer and explanation
Correct answer: B
A Scrum team develops a mobile app. An experienced core developer is moved away and replaced by a less experienced newcomer, and a key stakeholder worries that the newcomer will ramp up slowly and delivery will be late. The question asks what the project manager should do to ensure successful delivery.
The replacement is already a fact, so the project manager should first lead an assessment of its impact, such as the newcomer's skill gap and the effect on velocity and the delivery date, and then act on it: arrange knowledge transfer or coaching, let the Developers adjust the division of work themselves and coordinate extra resources if needed. This is the “assess first, then act” order of monitoring processes, and it answers the stakeholder's worry directly. The answer is B.
Why the other options are wrong
- A. The replacement has already happened, so first assess the skill gap and its effect on velocity and the delivery date. The possible delay can still be logged as a derived risk, but it should not be escalated to the PMO without assessment.
- C. The functional manager has limited knowledge of this project's specifics, and the project manager should lead the impact assessment; if resource support is needed after the assessment, negotiate then.
- D. Reversing the reassignment is often impractical (the original member may already have new tasks), does not solve how the newcomer gets integrated and causes fresh disruption.
Key takeaway When a member is replaced: assess the impact first, then adjust resources as needed; do not start by escalating or reversing.
Variation If the assessment shows the newcomer lacks business knowledge, arrange walkthroughs, pairing and knowledge handover; only if the assessment shows the delivery date will certainly be affected do you raise a change request.
Something wrong with this question?
Example 2 A senior data engineer is moved to a higher-priority project: what to do first
A data-platform construction project is under way, and a senior data engineer who is critical to the project is moved by the company to another, higher-priority project. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
A data-platform construction project is in execution, and a senior data engineer critical to the project is moved by the company to a higher-priority project. The question asks what the project manager should do “first”.
At this point the project manager does not yet know how much the transfer will affect schedule, cost and scope, so the first step is to analyze the impact and then choose a response accordingly. This is “assess first, then act”. In the analysis, use the resource management plan and the responsibility assignment matrix to find the activities the engineer owns, then check whether the risk register already holds a response. The answer is A.
Why the other options are wrong
- B. The project management plan needs updating only after the impact is clear and a response has been chosen; updating before the impact is known has no basis.
- C. The fact of the transfer can be shared in due course, but how big the impact is remains unclear, and communication is more targeted after you have analyzed the impact and set the direction of the response. It is not the first thing to do.
- D. A change request is a possible measure after the impact analysis and is submitted only when the analysis shows a baseline or plan really must change. It is not the first step.
Key takeaway When a resource is pulled away: analyze the impact on the project first, then decide whether to notify, change or update the plan.
Variation If the stem asked for the step after the analysis, then depending on the size of the impact, choose among negotiating with the functional manager, adjusting the division of work, adding resources or raising a change request.
Something wrong with this question?
Common traps
Common trap
- When a member is replaced or reassigned, assess the impact first and act on it: escalating first, reversing the adjustment first, raising a change first or updating the plan first are all skipped steps.
- Merely "notifying stakeholders" without first assessing the impact does not support a decision; raising a change request to add staff before assessing has no basis.
- When a member wants to leave, communicate first to find out why; do not force them to stay and do not pass the problem to someone else.
- A new member taking over complex work cannot be left to work it out alone; proactively explain and coach.
- When a functional manager takes up a member's time, go to that functional manager directly to negotiate; do not just put up with it, and do not escalate first.
Key takeaways
Key point
- Answering order for member changes: assess the impact, check the resource management plan, responsibility assignment matrix and risk register, then notify, negotiate or raise a change.
- Knowledge must not leave with people: coach newcomers who take over, cross-train, and keep knowledge from concentrating in one person.
- A member who wants to resign: communicate first to understand why and work out a solution together; for a late-iteration resignation, agree a mitigation plan with stakeholders.
- A member occupied by other work: first find out the effect of the delay, then negotiate directly with the functional manager and work with the member on ways to speed up.
- Communicate and assess first; escalate and change later.
This chapter has 20 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.