Procurement
Contract Types
PMP · Procurement · 4 lessons · about 49 min
Part of the free PMP video course: every lesson starts with its video →
What this chapter covers
The contract type determines how buyer and seller share cost risk, and with it how much the buyer pays and how much the seller earns. It is one of the most important decisions in planning the procurement strategy. This chapter covers the four fundamental contract models in PMBOK 8 Appendix X4 (fixed-price, cost-reimbursable, time and materials, and target-cost contracts), together with the seven subtypes commonly used in the traditional classification of contracts. The emphasis is on calculations for fixed price incentive fee (FPIF) and cost plus incentive fee (CPIF) contracts. FPIF involves target cost, target profit, a sharing ratio, a ceiling price and the point of total assumption (PTA). CPIF involves target cost, target fee, a sharing ratio and minimum and maximum fees; it has no ceiling price and no PTA.
After this chapter you should be able to: choose the contract type according to how clear the scope is, how likely changes are and who carries the risk; use the FPIF formulas to calculate final profit, final price and PTA, and check the result; calculate the final fee and the buyer’s payment under a CPIF contract; tell time-and-materials contracts from cost-reimbursable contracts; state who bears the risk when costs overrun under each contract type; and describe the new contracting practices for adaptive environments.
Lessons in this chapter
- Lesson 1: Contract Types Overview and How to Choose. The four fundamental models, the seven subtypes, the ranking of buyer risk, the three bases for choosing a type, and recognition keywords.
- Lesson 2: Fixed-Price Contracts: FFP, FPIF and FP-EPA. Firm fixed price, fixed price incentive fee and fixed price with economic price adjustment; the FPIF formulas and two complete worked examples, including PTA, the price cap and working backward.
- Lesson 3: Cost-Reimbursable, Time-and-Materials and Target-Cost Contracts. CPFF, CPIF and CPAF; the minimum and maximum fee in CPIF; payment by the person-day under time and materials; how to tell time and materials from cost-reimbursable.
- Lesson 4: Contract Types, Risk and Finance, and New Trends in Contracting. A comparison table for the same work under three contracts; the effect on EAC; agile contracting, smart contracts, outcome-based, sustainable and collaborative contracts.
Chapter knowledge map
| Contract type | Who bears cost overruns | Typical signal | Lesson |
|---|---|---|---|
| Firm fixed-price | The seller bears all | Clear scope, few changes; overruns from the seller’s underestimate fall on the seller | Lesson 2 |
| Fixed price incentive fee | Shared by ratio; above the PTA the seller alone | Target cost, ceiling price, sharing ratio | Lesson 2 |
| Fixed price with economic price adjustment | Price adjusts for changes from external factors | Long performance period, fluctuating material prices | Lesson 2 |
| Cost plus fixed/incentive/award fee | Mainly the buyer | Unclear requirements; CPIF has fee limits, CPAF rests on subjective evaluation | Lesson 3 |
| Time and materials | Shared (in the middle by convention); total cost can keep growing when no cap is set | Scope or effort hard to define at the outset, trades and rates known, consulting services | Lesson 3 |
Study tips and practice
- Learn the recognition keywords in Lesson 1 first, then the calculations. The routine for calculations is: decide which segment you are in, apply the formula, then check the result.
- For sharing ratios, first establish who is the buyer and who is the seller. For FPIF, calculate the PTA first to see whether the price is capped.
- Learn the standard names of the contract types precisely; answer options often differ only by name.
- Most questions in this chapter are scenario questions, so it is best to do the chapter practice after finishing all four lessons.
Lesson 1
Contract Types Overview and How to Choose
Lesson overview
The contract type determines how buyer and seller share cost risk, and with it how much the buyer pays and how much the seller earns. Which family of contract to use is one of the most important decisions in the procurement strategy; it is made after the make-or-buy analysis, together with the procurement strategy, and the contract type must stay consistent with the chosen strategy. This lesson first builds the overall picture: the four fundamental contract models in PMBOK 8, the seven commonly used subtypes, the three bases for choosing a type, and the risk ranking. The next three lessons cover the details and calculations for fixed-price, cost-reimbursable and time-and-materials contracts. ECO: Process domain, Task 5 (Plan and manage procurement), covering select the preferred contract type.
What a contract does, and the four fundamental models
A contract is an agreement that binds both buyer and seller and puts their relationship under legal protection. PMBOK 8 explains that contract types define the terms and conditions under which goods, services or results are acquired from external sources, and establish the framework for financial arrangements, risk distribution and the nature of relationships among project stakeholders. Project managers should approach contract types from a dual perspective: as both a contractor and a client/customer, since a project manager may be the customer buying from suppliers and also the contractor serving a client. Each contract type has its advantages and disadvantages, and there are potential ways to exploit contractual terms; however, the goal should always be to structure contracts in a way that benefits all parties, creating a win-win scenario.
| Type | How payment works | Common settings | Client (buyer) perspective | Contractor (seller) perspective |
|---|---|---|---|---|
| Fixed-price contract | Establishes a predetermined fee against a clearly defined scope of work, transferring cost risk to the seller | Construction, product development, services that can be accurately estimated | Budget certainty, but the price may be higher because of risk premiums | Profit potential if managed efficiently, but bears the risk of cost overruns |
| Cost-reimbursable contract | The buyer pays the seller’s actual costs, plus a fee typically representing the seller’s profit | Research and development, complex construction, scope uncertain or high risk | Flexibility, but the risk of cost escalation | Lower financial risk, but profit potential may be limited |
| Time and materials (T&M) contract | A hybrid of cost-reimbursable and fixed-price features: the buyer pays for actual time and materials used plus a profit margin | Smaller projects, maintenance work, scope not clearly defined at the outset | Flexibility, but close monitoring is needed to control costs | Cost coverage is assured, but time and resource usage may be scrutinized |
| Target-cost contract | Sets a target cost, with provisions for sharing cost savings or overruns between buyer and seller | Large infrastructure projects, complex manufacturing | Encourages cost control, but target costs and sharing mechanisms must be clearly defined | Incentives for efficiency, but bears partial risk of cost overruns |
PMBOK 8 also notes that the types and names of contract types can vary in different industries and organizations, and that there can be hybrid contracts incorporating elements of both fixed-price and cost-reimbursable models. A single procurement also often combines types, for example cost-reimbursable for the design phase and fixed-price for the construction phase (common exam practice).
Seven commonly used subtypes
The traditional classification of contracts often divides the three broad families into seven named subtypes. There are three in the fixed-price family: firm fixed-price (FFP), fixed price incentive fee (FPIF) and fixed price with economic price adjustment (FP-EPA). There are three in the cost-reimbursable family: cost plus fixed fee (CPFF), cost plus incentive fee (CPIF) and cost plus award fee (CPAF). The seventh is time and materials (T&M). FPIF and CPIF use a “target cost plus sharing ratio” mechanism similar to the target-cost contract; they are subtype names from the traditional classification (a common exam term), and they are not the same thing as the PMBOK 8 target-cost contract.
Arranged by “buyer’s risk from lowest to highest” the order is roughly as follows (this is common exam practice): firm fixed-price, fixed price incentive fee, fixed price with economic price adjustment, time and materials, cost plus incentive fee, cost plus award fee, cost plus fixed fee. In general, the lower the buyer’s cost risk, the higher the seller’s cost risk tends to be (the actual position still depends on the contract terms, and the seven types are not in strict inverse order). Time and materials sits in the middle only by convention, because when scope is unclear nobody can say how large the risk is. The main direction to remember is: in the fixed-price family the seller carries the risk; in the cost-reimbursable family the buyer carries the risk.
Three bases for choosing a contract type
Choose the type mainly on three points: whether requirements and scope are clear, whether changes are likely, and who carries the risk. The matching recognition keywords are:
Key point
- Scope clear, requirements clear, few changes, low risk: fixed-price contract.
- Scope unclear, requirements unclear, high risk: cost-reimbursable contract.
- An accurate SOW cannot be written yet, but the staff or trades are known, and you need to add staff or hire experts: time-and-materials contract.
- Long performance period, material prices fluctuate with the market: fixed price with economic price adjustment.
- You want buyer and seller aligned on the same goals: build incentive and award fees into the contract.
These three bases are also the way to break down the wrong options: how famous a seller is and how high its quote is are factors for selecting a seller; which contract type the project manager is familiar with, or how long the contract text is, are not bases at all. Contract types can also be combined, for example cost-reimbursable in the design phase and, once the scope is settled, fixed-price in the construction phase.
Scenario: how to choose. Installing warehouse shelving: drawings, quantities and acceptance standards are all settled, market prices are stable, and the schedule is short. All three conditions point to “clear scope, few changes”, so use a firm fixed-price contract: the buyer locks in the budget and the seller builds to the drawings. Change it to the development of a new type of battery: performance targets cannot yet be stated and will be set as the work proceeds, so use a cost-reimbursable contract. And if you just hire an outside expert for a few weeks of consulting, paid by the person-day, use time and materials.
Worked examples
Example 1 (scenario question): clear scope and low risk; which contract?
A logistics company is installing a batch of shelving in a new warehouse. The drawings, quantities and acceptance criteria are all settled, market prices are stable, the schedule is short and the risk is low. Which contract should the project manager choose?
Show answer and explanation
Correct answer: C
The project is developing its procurement strategy. The scope of work is clear and the risk is low, and the question asks which contract type fits best.
The signals: the drawings, quantities and acceptance criteria are settled, market prices are stable, the schedule is short and the risk is low. All three conditions say the scope is clear and few changes are expected, so the buyer can agree a fixed price in advance and have budget certainty, while the seller builds to the drawings and earns more if it controls cost well. The answer is C.
Why the other options are wrong
- A. A time-and-materials contract suits small projects where an accurate SOW cannot be written, or topping up with experts. It settles on actual hours and materials, so the total price is not usually fixed in advance and may rise with actual input (a cap can be agreed separately). Using it on work with clear scope gives up the price certainty a fixed-price contract provides.
- B. A cost plus fixed fee contract is cost-reimbursable, so the buyer bears actual cost and it suits work whose scope is unclear. Here the scope is clear, and there is no need to make the buyer carry the risk of cost overruns.
- D. A cost plus award fee contract also leaves cost with the buyer, and the award rests on the buyer’s subjective evaluation. It suits work with unclear scope where performance needs incentives, which does not fit a low-risk, clear-scope scenario.
Key takeaway Clear scope, few changes and low risk point to a fixed-price contract.
Variation If the condition were changed to “performance measures cannot yet be stated and will be settled as the work proceeds”, choose a cost-reimbursable contract; if it were changed to “just hire an outside expert for a few weeks of consulting paid by the person-day”, choose time and materials.
Something wrong with this question?
Example 2 (concept question): the main basis for choosing a contract type
A project manager has to decide the contract type while developing the procurement strategy. Which of the following is the main basis for choosing a contract type?
Show answer and explanation
Correct answer: D
The question asks for the main basis for choosing a contract type.
Choose a contract type mainly on three bases: whether the requirements and scope are clear, whether changes are likely, and which of buyer and seller bears the risk. They determine how the price is set and how the cost risk is shared. Among the other options, a seller’s reputation and quote are considerations in selecting a seller, and personal preference, length of the contract and purchase amount are not main bases. The answer is D.
Why the other options are wrong
- A. A seller’s reputation and quote are factors in selecting a seller. They do not decide whether to use a fixed-price, cost-reimbursable or time-and-materials contract, and the height of the quote is something compared when evaluating bids.
- B. Personal preference is not a basis. The contract type has to serve the actual circumstances and risk allocation of the project, not what the project manager happens to be familiar with.
- C. The purchase amount affects approvals and the intensity of management, but the length of the contract is not a basis, and the amount alone does not determine the contract type.
Key takeaway Choose the contract type by how clear the requirements are, how likely changes are and who bears the risk, not by preference. Choosing a contract type is in essence allocating risk between buyer and seller.
Variation If the question asked what is usually chosen when scope is unclear and risk is high, the answer is a cost-reimbursable contract; for a long performance period with fluctuating material prices, choose fixed price with economic price adjustment.
Something wrong with this question?
Common traps
Common trap
- A fixed-price contract does not leave the buyer “with no risk at all”: if scope is unclear, or the seller defaults or goes bankrupt, the buyer still bears the consequences.
- A cost-reimbursable contract does not let the seller “spend freely”: the contract usually requires cost documentation and the buyer has to monitor costs.
- Time and materials and cost-reimbursable are easy to confuse. Settling at agreed hourly rates or material unit prices, with the amount of work uncertain, usually points to time and materials; reimbursing actual allowable costs plus a fee, with uncertain scope or higher risk, usually points to cost-reimbursable. In common exam practice, look at the pricing method in the stem: pay by the person-day rate, choose time and materials; actual cost plus fee, choose cost-reimbursable.
- “A time-and-materials contract has a capped total” is wrong unless the contract adds a cap.
Key takeaways
Key point
- The four fundamental models in PMBOK 8: fixed-price, cost-reimbursable, time and materials, and target-cost contracts; hybrid contracts also exist in practice, and combining types within a single procurement is common exam practice.
- The seven subtypes: FFP, FPIF, FP-EPA, CPFF, CPIF, CPAF, T&M.
- Choose the type on three points: whether requirements are clear, whether changes are likely, and who carries the risk.
- In the fixed-price family the seller carries the risk and in the cost-reimbursable family the buyer does; time and materials has features of both, and without a cap the total can keep rising.
- The project manager must be able to view a contract from the client’s side and from the contractor’s side.
Lesson 2
Fixed-Price Contracts: FFP, FPIF and FP-EPA
Lesson overview
A fixed-price contract transfers cost risk to the seller and gives the buyer budget predictability. PMBOK 8 Appendix X4.8.1 lists four fundamental contract models, of which fixed-price, cost-reimbursable and time and materials are the most common basic types. As common exam practice, the fixed-price family is also divided into three types: firm fixed-price, fixed price incentive fee and fixed price with economic price adjustment (this lesson follows that division). The sequence of “target cost, target profit, sharing ratio, ceiling price, and point of total assumption” appears regularly in calculation questions. The FPIF and point of total assumption (PTA) formulas are common exam practice (the PMBOK 8 target-cost contract is not the same thing as FPIF). This lesson takes the method apart step by step and checks every worked example. ECO: Process domain, Task 5 (Plan and manage procurement), covering select the preferred contract type.
Three kinds of fixed-price contract
Firm fixed-price contract (FFP): the price is set once and for all. Whatever the seller’s actual cost, the buyer pays the same amount. The buyer’s risk is lowest, the seller bears all the cost overrun risk, and the clearer the scope the better it fits. For example, with a contract price of $3,000,000 and an actual seller cost of $2,800,000, the seller earns $200,000; if the actual cost rises to $3,300,000, the seller loses $300,000 and the buyer still pays $3,000,000.
Fixed price incentive fee contract (FPIF): the contract sets a target cost, a target profit, a ceiling price, and a ratio for sharing savings or overruns between buyer and seller. When the seller’s actual cost is below target cost, the seller earns more profit; when it is above, the seller earns less; the price is capped at the ceiling price. The purpose is to align buyer and seller and have them control cost together.
Fixed price with economic price adjustment contract (FP-EPA): the total price is fixed, but it is adjusted by a pre-agreed index for external factors such as inflation, material prices or exchange rates, which protects the seller from being dragged down by uncontrollable price movements over a long contract. It suits procurements with a long performance period and material prices that move with the market. For example, take a base price of $5,000,000 in which materials account for 40%, that is $2,000,000, adjusted by a material price index. If during performance the index rises from 100 to 110, the materials portion becomes 2,000,000 × 110 ÷ 100 = $2,200,000 and the contract price is adjusted to 5,000,000 + 200,000 = $5,200,000.
The six quantities in FPIF and the formulas
| Quantity | Meaning |
|---|---|
| Target cost | The expected cost both parties agree on |
| Target profit | The seller’s profit when actual cost equals target cost |
| Target price | Target cost plus target profit |
| Ceiling price | The most the buyer is willing to pay; however high the seller’s cost, the buyer pays no more |
| Sharing ratio | The share of the difference between target cost and actual cost that buyer and seller each bear or enjoy, written buyer share/seller share |
| Point of total assumption (PTA) | The actual cost at which the price just reaches the ceiling price; beyond it, the seller bears the entire overrun |
The difference in the parentheses is positive for a saving, which increases the seller’s profit, and negative for an overrun, which reduces it. After the PTA the price no longer increases, and the seller alone bears the part of actual cost beyond it.
How to do it: complete worked examples
Example 1. An equipment installation project uses FPIF: target cost $1,000,000, target profit $100,000, target price $1,100,000, ceiling price $1,200,000, sharing ratio 80/20 (buyer 80%, seller 20%).
- Actual cost $900,000: saving 1,000,000 − 900,000 = $100,000; the seller’s share is 20% × 100,000 = $20,000; final profit 100,000 + 20,000 = $120,000; final price 900,000 + 120,000 = $1,020,000, below the ceiling. Check: the buyer’s share of the saving is $80,000, and the buyer pays 1,100,000 − 80,000 = $1,020,000, which agrees.
- Actual cost $1,050,000: overrun $50,000; the seller bears 20% × 50,000 = $10,000; final profit 100,000 − 10,000 = $90,000; final price 1,050,000 + 90,000 = $1,140,000, below the ceiling. Check: the buyer bears $40,000 of the overrun and pays 1,100,000 + 40,000 = $1,140,000, which agrees.
- Find the PTA: PTA = 1,000,000 + (1,200,000 − 1,100,000) ÷ 80% = 1,000,000 + 125,000 = $1,125,000. Check: at an actual cost of 1,125,000 the overrun is $125,000, the seller bears $25,000, profit is $75,000 and the price is 1,125,000 + 75,000 = $1,200,000, exactly the ceiling price.
- Actual cost $1,250,000: this is past the PTA, so the price is capped at $1,200,000; the seller’s profit is 1,200,000 − 1,250,000 = −$50,000, a $50,000 loss. Check: if you applied the formula blindly, the overrun is 250,000, the seller bears 50,000, profit is 50,000 and the price is 1,250,000 + 50,000 = $1,300,000, which exceeds the $1,200,000 ceiling. So the buyer must pay the ceiling of $1,200,000, and profit is 1,200,000 − 1,250,000 = −$50,000.
Example 2 (working backward, with a different set of numbers). Target cost $4,000,000, target profit $400,000, ceiling price $4,600,000, sharing ratio 70/30 (buyer 70%, seller 30%).
- Target price = 4,000,000 + 400,000 = $4,400,000.
- PTA = 4,000,000 + (4,600,000 − 4,400,000) ÷ 70% = 4,000,000 + 285,714 ≈ $4,285,714.
- Actual cost $3,800,000: saving 200,000, the seller’s share 30% × 200,000 = 60,000, profit 460,000, price 3,800,000 + 460,000 = $4,260,000.
- Working backward: the buyer actually paid $4,330,000; what was the actual cost? Price = cost + 400,000 + 30% × (4,000,000 − cost) = 70% × cost + 1,600,000. Setting this equal to 4,330,000 gives cost = 2,730,000 ÷ 0.7 = $3,900,000. Check: saving 100,000, seller’s share 30,000, profit 430,000, price 3,900,000 + 430,000 = $4,330,000, which agrees.
- Judge first, then calculate: 4,330,000 is below the ceiling price of 4,600,000 and the cost of 3,900,000 is below the PTA of about 4,285,714, so the formula can be used.
Common trap
- When the ratio is written “80/20”, first find out who gets the 80%. It is normally written buyer/seller; if the stem says “the seller bears 20%”, multiply the difference by 20%.
- FPIF profit can be negative: when actual cost is above the ceiling price, the seller takes a loss.
- Beyond the PTA, costs are no longer shared by ratio and the price is the ceiling price. First decide which side of the PTA the actual cost falls on, then pick the formula.
- Do not confuse FPIF with CPIF. FPIF has a price ceiling; CPIF’s fee may be bounded by a minimum and a maximum if the contract sets them, and the buyer’s payment has no fixed ceiling.
- If the scope has not changed and the contract has no cost-sharing or price-adjustment mechanism, an overrun that the seller caused by underestimating the quantities falls on the seller and a request for extra money is refused; this most likely points to a firm fixed-price contract. Under FPIF, before the PTA the buyer still shares, by ratio, the part above target cost.
Worked examples
Example 1 (scenario question): have the seller bear the greatest risk; which fixed-price type to sign?
PMLyceum is building an online course platform and you are the project manager. After taking stock of internal staff, you find there are not enough testers and plan to hand stress testing whose scope and acceptance criteria are already clear to a qualified outside company. You want the outside company to bear as much of the risk as possible. Which contract should you sign?
Show answer and explanation
Correct answer: A
The project is at the stage of planning the sourcing strategy, with some work to be outsourced. The question asks which contract makes the seller bear the greatest risk.
The signal: you want the outside company to bear as much of the risk as possible. In the fixed-price family the seller bears the cost risk, and under a firm fixed-price contract the price is set at the start and all cost overruns fall on the seller, so its risk is greatest. Among the other options, a fixed price with economic price adjustment contract adjusts the price for external factors, so the seller’s risk is smaller, and the two cost-reimbursable contracts have the buyer reimburse costs, so the risk lies with the buyer. The answer is A.
Why the other options are wrong
- B. A cost plus incentive fee contract is cost-reimbursable, so the buyer reimburses actual cost and the risk lies mainly with the buyer.
- C. Fixed price with economic price adjustment belongs to the fixed-price family, but price changes caused by external factors such as inflation and exchange rates are adjusted in the price, so the seller’s risk is lower than under a firm fixed-price contract.
- D. A cost plus award fee contract is also cost-reimbursable: the buyer bears the cost and pays an additional award fee at its own discretion.
Key takeaway For a clearly defined scope, choose a firm fixed-price contract to make the seller bear the greatest cost-overrun risk.
Variation If the question asked instead what gives the buyer the most certain budget, the answer would also be a firm fixed-price contract; if it asked where the buyer bears the greatest cost risk, the answer would be the cost-reimbursable family.
Something wrong with this question?
Example 2 (scenario question): the seller underestimated the quantities and asks for the difference to be paid, and is refused
The project manager outsources a park landscaping job and gives the supplier construction drawings and a bill of quantities. During construction the supplier says it underestimated the quantities at the start, so its costs have run over, and asks the project manager to make up the difference. The contract has no cost-sharing or price-adjustment clause, and the project manager refuses. Which contract did the two parties most likely sign?
Show answer and explanation
Correct answer: B
The project is in construction with drawings and a quantity list in place, and the supplier asks for a higher price because of its own estimating error. The question asks which contract type this corresponds to.
The signal: the supplier says it underestimated the quantities and asks for the difference, and the project manager refuses. That means the price does not change because of the seller’s estimating error, and the cost overrun is the seller’s own to bear. This is a firm fixed-price contract. Under a fixed price incentive fee contract the contract must have a sharing ratio, and before the ceiling price the buyer shares by ratio the part above target cost, which does not fit “no cost-sharing clause at all”. Under time and materials and cost plus incentive fee contracts the buyer pays for the added cost, so a refusal would have no contractual basis. The answer is B.
Why the other options are wrong
- A. A time-and-materials contract settles on actual hours and materials, so the added work has to be paid for anyway and would not be refused.
- C. Under a cost plus incentive fee contract the buyer reimburses actual cost and has to pay more when cost rises, so refusing to make up the difference would have no contractual basis.
- D. A fixed price incentive fee contract has a sharing ratio above target cost, so the buyer shares the part above target cost by ratio and would not refuse it all. Only past the point of total assumption (where the price reaches the ceiling) does the whole overrun fall on the seller.
Key takeaway Refusing a price increase caused by the seller’s own estimating error corresponds to a firm fixed-price contract.
Variation If the contract allowed the price to be adjusted for rising material prices, it would be a fixed price with economic price adjustment contract and the seller’s request would have a basis; if the added work came from the buyer changing the scope, the seller could seek compensation through the change procedure.
Something wrong with this question?
Common traps
How to tell the three fixed-price contracts apart
- Firm fixed-price: the price is fixed, and the seller bears all the overrun.
- Fixed price incentive fee: a ratio for sharing savings or overruns is set around the target cost, and the price is capped at the ceiling price.
- Fixed price with economic price adjustment: the price is fixed but adjusts with agreed external factors (inflation, materials, exchange rates); used for long contracts.
Key takeaways
Key point
- Fixed-price contracts: the seller carries the cost risk and the buyer’s budget is certain; under FFP the seller carries the most risk.
- FPIF: final profit = target profit + seller’s sharing ratio × (target cost − actual cost); final price = actual cost + final profit, not above the ceiling price.
- PTA = target cost + (ceiling price − target price) ÷ buyer’s sharing ratio; beyond the PTA the seller bears the overrun alone.
- FP-EPA is for long-term procurements with fluctuating prices, adjusting the fixed price by an agreed index.
- Always check after calculating: price minus cost equals profit, and the price does not exceed the ceiling price.
Lesson 3
Cost-Reimbursable, Time-and-Materials and Target-Cost Contracts
Lesson overview
Fixed-price contracts suit work whose scope is clear. When scope is uncertain or risk is high and things are settled as the work proceeds, consider a cost-reimbursable contract; when scope is unclear at the start but the trades and rates are known, consider time and materials. This lesson covers the three subtypes of cost-reimbursable contract and the payment calculation for CPIF, then the time-and-materials contract and the PMBOK 8 target-cost contract, and ends with a method for telling the two families apart. ECO: Process domain, Task 5 (Plan and manage procurement), covering select the preferred contract type.
Cost-reimbursable contracts: CPFF, CPIF and CPAF
Under a cost-reimbursable contract the buyer pays the seller’s actual costs, plus a fee typically representing the seller’s profit. The buyer carries the cost, so the buyer has to monitor costs, and the contract usually requires the seller to provide cost documentation. By the way the fee is set there are three kinds:
- Cost plus fixed fee contract (CPFF): the fee is a fixed amount set when the contract is signed and does not change with actual cost. If cost rises, the buyer pays more cost and the fee stays the same.
- Cost plus incentive fee contract (CPIF): a target cost, a target fee and a sharing ratio are set; when actual cost is below target the seller earns more fee, and when above target the seller earns less. The contract may set a minimum and maximum fee (common exam practice, not a built-in condition of every CPIF).
- Cost plus award fee contract (CPAF): the award portion of the fee is decided by the buyer on its subjective evaluation of the seller’s performance, and the amount of the award is at the buyer’s sole discretion.
There is also a cost plus percentage of cost contract (CPPC), in which the fee is a percentage of actual cost: the more the seller spends, the more it earns, so the seller has no incentive to control cost and the buyer carries the greatest risk when risk allocation is compared. It is restricted or prohibited in many countries and agencies and is rarely used in practice; in exams it appears mainly as the extreme case of highest buyer risk.
“Incentive” and “award” are different. An incentive is written into the contract with objective calculation rules, so the seller can work out its gain in advance; an award depends entirely on the buyer’s subjective evaluation, with more given if the buyer is satisfied, and normally cannot be recalculated by an objective formula the way CPIF can (whether it can be reviewed or appealed depends on the contract terms). When the stem says “subjective judgment” or “at the buyer’s discretion”, it is a cost plus award fee contract. Incentives are also not limited to cost: schedule, quality and other performance can be tied in as well. For example, if service levels are met, or the defect rate is below the agreed value and the system goes live early, an extra incentive fee is paid; the purpose is to align buyer and seller.
Payment calculations for CPFF and CPIF
CPFF is the simplest: final payment = actual cost + fixed fee. On a research and development project with a $150,000 fee: with an actual cost of $1,800,000 the buyer pays $1,950,000; with an actual cost of $2,200,000 the buyer pays $2,350,000. The fee is always $150,000, and the extra $400,000 of cost is borne by the buyer.
Why does a CPIF contract often set a minimum and maximum fee? Pure sharing has a loophole: when cost far exceeds target, the amount the seller must bear could be more than the entire fee, driving the fee negative and exposing the seller to excessive downside risk. The contract can set a minimum fee to limit that risk. A maximum fee caps only the fee portion; the buyer’s total payment still rises with actual cost and has no total price ceiling. The minimum and maximum fee are only limits the contract may set. When the stem gives upper and lower limits, calculate the fee by the sharing formula first and then bring it within that range; when the stem does not give them, do not assume any. The calculation for CPIF follows the same logic as for FPIF, but the final payment has no ceiling price:
Worked example. A system development project uses CPIF: target cost $3,000,000, target fee $240,000, sharing ratio 80/20 (buyer 80%, seller 20%), minimum fee $120,000 and maximum fee $360,000.
- Actual cost $2,700,000: saving $300,000; the seller’s share is 20% × 300,000 = $60,000; fee 240,000 + 60,000 = $300,000, which lies between 120,000 and 360,000; the buyer pays 2,700,000 + 300,000 = $3,000,000. Check: the buyer’s share of the saving is $240,000, and the buyer’s payment = target cost + target fee − 240,000 = 3,240,000 − 240,000 = 3,000,000, which agrees.
- Actual cost $2,000,000: saving $1,000,000; the seller’s share is $200,000; the calculated fee is $440,000, which exceeds the maximum fee, so use $360,000; the buyer pays 2,000,000 + 360,000 = $2,360,000.
- Actual cost $3,800,000: overrun $800,000; the seller bears $160,000; the calculated fee is 240,000 − 160,000 = $80,000, which is below the minimum fee, so use $120,000; the buyer pays 3,800,000 + 120,000 = $3,920,000. Check: the buyer pays 3,920,000 − 3,240,000 = $680,000 more than the target, made up of $800,000 more cost and $120,000 less fee (240,000 − 120,000), and 800,000 − 120,000 = 680,000; there is no price ceiling.
- Order of judgment: calculate the fee first, see which side of the minimum and maximum it falls on, and finally add the actual cost.
Time-and-materials contracts
A time-and-materials contract (T&M) has aspects of both cost-reimbursable and fixed-price contracts: the buyer typically pays for actual time and materials used plus a profit margin. Unit rates (such as the price per person-day) are normally agreed in advance; if the contract sets no cap, the total amount rises with actual hours and material quantities. It applies when an accurate statement of work cannot be written quickly; when staff need to be added, experts hired or outside support sought; and for small, short, uncomplicated projects. PMBOK 8 notes that it is often used for smaller projects, maintenance work or when the scope is not clearly defined at the outset, and that it is common in technology services, consulting and some construction projects.
If no cost cap is set, the total rises with actual usage, and the buyer must monitor it closely or scope creep and a runaway budget are likely. A collaborative contracting approach is to add a cap to the time-and-materials contract, reduce the rate or introduce performance incentives, so that both parties share the risk.
Worked example. A software maintenance contract sets $2,000 per person-day, with materials reimbursed at actual cost plus a 10% handling fee. This month 30 person-days are used and materials actually cost $40,000. Labor is 30 × 2,000 = $60,000; materials and handling fee are 40,000 × (1 + 10%) = $44,000; the buyer’s payment for the month is 60,000 + 44,000 = $104,000. Next month the payment will change with the effort put in; there is no fixed total price.
Target-cost contracts, and telling time and materials from cost-reimbursable
A target-cost contract is the fourth fundamental model listed in the PMBOK 8 appendix: it sets a target cost, with provisions for sharing cost savings or overruns between buyer and seller, and it encourages efficiency and cost control while maintaining flexibility. FPIF and CPIF also use a “target cost plus sharing ratio” mechanism and belong to the fixed-price and cost-reimbursable families respectively.
Time and materials and cost-reimbursable contracts are easily confused. PMBOK 8 Appendix X4 puts it this way: T&M contracts are used when the scope is not clearly defined at the outset, and cost-reimbursable contracts when the project scope is uncertain or the project is high risk; the two are not cleanly separated by how clear the scope is. As common exam practice, go by the pricing method and staffing described in the stem. If settlement is by person-day or hourly rate, the trades needed (architects, algorithm engineers and so on) are already known, but an accurate SOW cannot be written, choose time and materials, for example when hiring outside consultants. If settlement is by actual cost plus a fee, neither the requirements nor the trades are clear and the buyer carries the cost risk, choose cost-reimbursable.
Worked examples
Example 1 (scenario question): neither the requirements nor the trades are clear; which contract?
PMLyceum is launching development of a new underwater cleaning robot, and you are appointed project manager. After research you find that management has not specified what functions the product must have and cannot say which work the development should start with, and the statement of work gives only a rough budget. The development is expected to be long and large with high technical risk, and the buyer will have to bear and monitor actual cost. Which contract should be chosen?
Show answer and explanation
Correct answer: D
Neither the requirements nor the scope is clear, and it is not even clear which work the development should start with. The question asks for the contract type.
Eliminate in two steps. The requirements are unclear and the scope is highly uncertain, and the fixed-price family needs the scope defined before a price can be set, so rule it out. A time-and-materials contract can be used where scope is unclear at the start, but it fits better small, consulting or supporting work priced by trade or unit rate. This is the development of a brand-new product with high scope uncertainty and high risk overall, so a cost-reimbursable contract fits better: the buyer reimburses actual cost, which suits development settled as the work proceeds, and D is the only cost-reimbursable contract among the options. The answer is D.
Why the other options are wrong
- A. A time-and-materials contract usually has no fixed total price or exact quantities at signing, and its value may rise with actual hours and material costs (a limit on amount and duration can also be set). It fits small, consulting or supporting work priced by agreed rates and unit prices. Here there are no agreed hourly or material unit prices, and the stem says the buyer will bear and monitor actual cost, so the cost-reimbursable family fits better than time and materials.
- B. Fixed price incentive fee belongs to the fixed-price family, so the scope must be defined clearly before a target cost and ceiling price can be set, which cannot be done when requirements are unclear.
- C. Fixed price with economic price adjustment suits procurements with a long performance period and prices that move with the market, and it too is fixed-price, requiring a clear scope.
Key takeaway Unclear requirements and highly uncertain development overall point to a cost-reimbursable contract.
Variation If the stem added “architects and other staff have been approved to join, but an SOW cannot be written”, time and materials would fit better; if it also gave a target cost and a sharing ratio, it would point more clearly to a cost plus incentive fee contract.
Something wrong with this question?
Example 2 (scenario question): the SOW cannot be written yet, but the staff are known
PMLyceum is developing a cross-border live-stream e-commerce platform. Management attaches great importance to it and has agreed to engage the architects and algorithm engineers you identified through an outside supplier at hourly rates to join the project team. Because live-streaming formats change quickly, the sponsor cannot give an exact statement of work (SOW). Which contract type might the project use?
Show answer and explanation
Correct answer: D
An accurate SOW cannot be written but the staff are known, and the question asks which contract to choose.
Two signals together: the sponsor cannot give an exact SOW (the scope is hard to determine), but the architects and algorithm engineers named will be bought from an outside supplier at hourly rates (the trades and rates are known, while the amount of work and duration are uncertain). This is exactly where a time-and-materials contract applies: payment for actual hours and materials plus a profit margin, suited to cases where you need to add staff or hire experts. The answer is D.
Why the other options are wrong
- A. Fixed price with economic price adjustment is also fixed-price, so it requires a clear scope, and it is used where the performance period is long and material prices move with the market.
- B. A firm fixed-price contract requires a clear scope. If an SOW cannot be written, no price can be set.
- C. Cost plus fixed fee suits cases where the seller undertakes a whole body of work of uncertain scope and the buyer reimburses costs. Here the purchase is of designated professionals billed by the hour, which time and materials fits better.
Key takeaway When an SOW cannot be written but the staff or trades are known, choose time and materials. Unit prices are agreed in advance; if no cap is agreed, the total floats with actual hours, risk is split between buyer and seller, and the buyer has to monitor hours closely; if a maximum amount is agreed it is bound by that.
Variation If the stem said “it is not even clear which trades are needed and the development direction is not set”, choose a cost-reimbursable contract instead; if the scope were clear and the work were built to drawings, choose a fixed-price contract.
Something wrong with this question?
Common traps
Common trap
- For the buyer, CPFF and CPIF usually have no final total price fixed in advance; the payment varies with reimbursable actual cost and keeps rising when costs overrun, so costs must be monitored (if the contract sets a separate cost or payment cap, follow the contract terms). A cost-reimbursable contract lowers the seller’s financial risk.
- When scope is unclear, either may apply: if hours, materials or resource unit prices can be agreed and settled by actual quantity, consider time and materials; if settlement is by actual cost plus a fee and the buyer carries more of the cost risk, consider cost-reimbursable. On a question, go by the pricing and risk-allocation terms in the stem.
- Once a contract is signed and the budget is overrunning, the project manager cannot change the contract type unilaterally, nor refuse payments without verifying them. Do a performance review first to confirm that fees are reasonable, reimbursable and documented, then handle payment through the contract’s change or dispute procedure.
- An incentive has objective rules and an award rests on the buyer’s subjective evaluation; do not mix up CPIF and CPAF.
Key takeaways
Key point
- CPFF: payment = actual cost + fixed fee. CPIF: fee = target fee + seller’s ratio × (target cost − actual cost), held between the minimum and maximum fee if the contract sets them. CPAF: the award is decided subjectively by the buyer.
- In a cost-reimbursable contract the buyer carries the cost risk and has to monitor costs.
- Time and materials: pay for actual hours and materials at unit prices agreed in advance; without a cap the total rises with usage; it suits cases where the SOW cannot be written but the staff are known, small projects and consulting.
- Target-cost contract: a target cost is set and the way savings and overruns are shared is specified.
- Common exam practice: unclear requirements, unclear trades and settlement by actual cost plus fee, choose cost-reimbursable; SOW cannot be written, trades known and settlement by unit price, choose time and materials.
Lesson 4
Contract Types, Risk and Finance, and New Trends in Contracting
Lesson overview
The previous three lessons covered how each kind of contract works. This lesson puts them back in one table for comparison: for the same work and the same cost changes, under different contracts, how much does the buyer pay and how much does the seller earn? It then covers how the contract type affects risk and finances, and ends with the new trends in contract management that PMBOK 8 mentions and how a contract can keep up with iterations in an adaptive environment. ECO: Process domain, Task 5 (Plan and manage procurement), covering select the preferred contract type.
The same work under three contracts
Risk transference is one kind of risk response: a fixed-price contract transfers cost risk to the seller, and the buyer gets budget predictability in return, at the price of the seller building a risk premium into the price. A cost-reimbursable contract leaves the cost risk with the buyer. A time-and-materials contract has features of both; where no cap is set, the buyer’s total payment can keep rising, and the actual risk allocation depends on the contract terms. Transference does not make the risk disappear; it only hands the responsibility to the other party, usually at a price.
Worked example. The estimated cost of some work is $2,000,000. There are three contracts: FFP at a fixed price of $2,200,000; CPFF with a fixed fee of $200,000; and FPIF with target cost $2,000,000, target profit $200,000, ceiling price $2,400,000 and sharing ratio 80/20 (buyer/seller; the FPIF sharing method is common exam practice). Compare the buyer’s payment and the seller’s profit when actual cost is $1,800,000, $2,000,000 and $2,400,000.
- FFP: the payment is always $2,200,000; the seller’s profit = 2,200,000 − cost, which in the three cases is $400,000, $200,000 and −$200,000.
- CPFF: payment = cost + 200,000, which is $2,000,000, $2,200,000 and $2,600,000; the seller’s profit is always $200,000.
- FPIF: first find the PTA = 2,000,000 + (2,400,000 − 2,200,000) ÷ 80% = $2,250,000.
- Cost $1,800,000: saving 200,000, the seller’s share 40,000, profit 240,000, payment $2,040,000.
- Cost $2,000,000: profit 200,000, payment $2,200,000.
- Cost $2,400,000: this is beyond the PTA of 2,250,000, so the payment is capped at $2,400,000 and the seller’s profit is 0.
- Check: at a cost of 1,800,000 the buyer pays FFP 2,200,000, FPIF 2,040,000 and CPFF 2,000,000; the benefit of the saving goes entirely to the buyer under CPFF and entirely to the seller under FFP. At a cost of 2,400,000 the buyer pays FFP 2,200,000, FPIF 2,400,000 and CPFF 2,600,000; the overrun risk is borne entirely by the buyer under CPFF and entirely by the seller under FFP, with FPIF in between.
| Actual cost | FFP payment / seller profit | CPFF payment / seller profit | FPIF payment / seller profit |
|---|---|---|---|
| $1,800,000 | 2,200,000 / 400,000 | 2,000,000 / 200,000 | 2,040,000 / 240,000 |
| $2,000,000 | 2,200,000 / 200,000 | 2,200,000 / 200,000 | 2,200,000 / 200,000 |
| $2,400,000 | 2,200,000 / −200,000 | 2,600,000 / 200,000 | 2,400,000 / 0 |
The effect on finances
PMBOK 8 says that the choice between a fixed-price and a time-and-materials contract depends on the risk distribution and cost certainty, and that the finance processes should work with the procurement strategy to minimize the risk of cost overruns. In terms of forecasting: under a firm fixed-price contract (FFP) the buyer’s payment is fixed, so the buyer’s estimate at completion does not have to move with the seller’s cost performance (FPIF calculates the final payment by the incentive mechanism and is limited by the ceiling price, and FP-EPA adjusts the price by the economic price adjustment mechanism in the contract). Under a cost-reimbursable contract the buyer absorbs overruns, so the estimate at completion (EAC) has to be re-forecast from the seller’s cost performance. An adaptive project needs a contract structure, payment arrangements and financial forecasts that can support iterative delivery, and the contract structure should match iteration progress and budget spending; only when a change goes beyond the established contract mechanisms or the approved budget is it adjusted through governance and the change process.
Contracts in predictive and adaptive approaches
A predictive project has clear scope and few changes, so it commonly uses a fixed-price contract that fixes scope, price and delivery date. On an adaptive project requirements change from iteration to iteration and scope is hard to fix. The usual approach is to base the contract on time and materials or cost-reimbursable, pay on iteration deliverables or milestones, and leave room for change. Under a fixed-price contract, if the customer wants to add scope it can only be handled through the contract change control procedure, often by reprioritizing within the same amount of work. The contract for a hybrid project has to support incremental delivery.
PMBOK 8 Appendix X4 lists emerging trends in contract management. Agile contracting applies agile principles to the fundamental contract types, for example a T&M contract with iteration-based deliverables. Smart contracts integrate blockchain technology with traditional contract structures and automate execution of contract items; they are usually implemented in milestone-based payments. Outcome-based contracts shift from input-based pricing models; they apply to fixed-price and cost-reimbursable contracts and focus on measurable results rather than prescribed processes. Sustainable contracting embeds environmental, social and governance (ESG) principles into contractual agreements. Collaborative contracting uses an enhanced risk-sharing or reward-sharing mechanism within fundamental contract types, for example a cap on a T&M contract, a reduced rate or performance incentives. AI-powered contract analysis tools can also assess risk more accurately and speed up negotiation. In addition, PMBOK 8 lists integrated project delivery (IPD) contracts in the procurement strategy as a more formalized and structured approach to collaborative project delivery, typically used in complex construction projects where early involvement of all parties can significantly benefit the project outcome.
Scenario: risk and a deadline together. For a subsea power transmission line, the detailed design will not be finished until several months after the contract is signed, but the line must be in service within 30 months. The buyer wants to keep risk balanced between the two sides. One approach is to cut the work into increments, each with a fixed price and payment after acceptance (fixed-price increments); the part whose design is not yet settled uses a graduated time-and-materials contract, with the rate varying by delivery time (for example a higher rate for early delivery and a lower rate for late delivery, so that the schedule risk is shared). Both approaches let the two sides share risk phase by phase: the first locks in the price of each segment, and the second keeps flexibility for the part whose design is undecided.
Fixed-price increments, graduated time and materials, an early-cancellation option and a dynamic scope option are contract practices commonly used on adaptive projects; the terms come from the PMI Agile Practice Guide, and they are common exam practice. In an early-cancellation option the buyer can end the remaining work, after paying an agreed termination fee, once it has received enough value; in a dynamic scope option the buyer reprioritizes or swaps scope.
Worked examples
Example 1 (concept question): under which contract does the buyer bear the greatest cost risk?
For the same batch of work, assuming the usual risk allocation for each contract type and no special provisions such as an additional cost cap, under which type of contract does the buyer bear the greatest cost risk?
Show answer and explanation
Correct answer: A
A comparison, from the buyer’s side, of how the cost risk is borne under different contract types.
Under the stem’s assumption of usual risk allocation and no special provisions such as an additional cap, compare cost risk from the buyer’s side. Under a cost-reimbursable contract the buyer reimburses the seller’s actual cost, so cost-overrun risk lies mainly with the buyer, who therefore has the greatest risk. Under a firm fixed-price contract the price is fixed and the buyer’s risk is lowest; a fixed price incentive fee contract has a ceiling price; uncapped time and materials sits in the middle and usually exposes the buyer to less risk than cost-reimbursable. The answer is A.
Why the other options are wrong
- B. Under a firm fixed-price contract the price is fixed and the seller bears cost overruns, so the buyer’s risk is lowest.
- C. A fixed price incentive fee contract has a ceiling price, and beyond the point of total assumption (where the price reaches the ceiling) the price stays at the ceiling and the overrun falls entirely on the seller, so the buyer’s payment has an upper limit.
- D. Under time and materials the buyer pays for actual hours and materials. Under the stem’s assumption that no additional cost cap applies, its risk usually lies between fixed-price and cost-reimbursable contracts, and the buyer bears less risk than under a cost-reimbursable contract.
Key takeaway Under a cost-reimbursable contract the buyer bears the risk; under a fixed-price contract the seller bears it; time and materials is in the middle.
Variation If the question asked where the seller bears the greatest cost risk, the answer would be a firm fixed-price contract; if it asked what gives the buyer the most certain budget, that would also be a firm fixed-price contract.
Something wrong with this question?
Example 2 (multiple-response question): design not settled and time limited; how do you balance buyer and seller risk?
An energy company plans to build a subsea power transmission line linking three coastal cities and hires a contractor for the construction. The detailed design of the work will not be finished until several months after the contract is signed, but the company requires the line to be in service within 30 months. The company does not intend to terminate the contract midway or to change the agreed scope of the line. The project manager wants the price mechanism to have the company and the contractor share risk so that the risk allocation between them is balanced. When planning the sourcing strategy or procurement strategy, which TWO contracting techniques should be considered? (Choose two.)
Show answer and explanation
Correct answer: AE
At signing the detailed design and implementation details are not settled and the schedule is limited. The company does not intend to terminate midway or adjust the scope. The question asks which contracting techniques keep risk balanced between buyer and seller (these techniques are common exam terms for adaptive projects).
The stem has three conditions: the detailed design is completed several months after signing (the design and implementation details are not settled), the date for entering service is fixed, and the aim is to balance risk between buyer and seller. Among the contracting techniques commonly used on adaptive projects (“fixed-price increments” and “graduated time and materials” are common exam terms), fixed-price increments cut the work into increments, each separately priced and paid after acceptance, so as the design becomes clear the two sides re-agree increment by increment, and neither has to bear all the uncertainty at once. Graduated time and materials has the two sides share financial risk: for early delivery the seller is paid a higher hourly rate, and for late delivery the rate is reduced, so both share the consequences of savings and delays. The answers are A and E.
Why the other options are wrong
- B. A firm fixed-price contract puts all the design change risk on the seller, but the detailed design is completed several months after signing and the design and implementation details are still uncertain, so the risk allocation clearly favors the buyer and cannot achieve the balance the stem asks for.
- C. In the stem the company does not intend to terminate midway. An early cancellation option mainly gives the buyer more flexibility to end early and protects the seller through a termination fee. It does not directly correspond to phased pricing or risk sharing in the price.
- D. In the stem the company does not intend to adjust the scope. A dynamic scope option lets the buyer swap scope by priority at milestones, which addresses scope flexibility and not risk sharing in price or rates.
Key takeaway To balance risk between buyer and seller use fixed-price increments and graduated time and materials: the first prices segment by segment by increment and the second adjusts the rate by how fast delivery is made.
Variation If the stem emphasized “the buyer wants maximum flexibility and may terminate at any time”, that would point to an early cancellation option; if it emphasized “scope is adjusted by priority”, to a dynamic scope option.
Something wrong with this question?
Common traps
Common trap
- Under a fixed-price contract, if the customer on an agile project wants to add scope, you cannot simply accept it without adjusting the contract; go through change control or trade off priorities.
- Do not think that once “risk is transferred” you can stop managing it: if the seller defaults, goes bankrupt or the scope is unclear, the buyer still bears the consequences, and also pays a risk premium for the transfer.
- A cap on a time-and-materials contract only limits the buyer’s payment risk. What happens once the cap is reached (the seller absorbs the excess cost, stops work, or the buyer separately approves more) depends on the contract terms. A cost cap does not itself adjust the two sides’ gains and losses by how fast delivery happens, so it does not solve a problem of unsettled design and a limited schedule; this differs from collaborative contracting, where the cap, performance incentives and risk sharing are designed together.
- An early-cancellation option serves both sides’ interests through the termination fee, and a dynamic scope option serves flexibility and the seller’s risk through scope swaps within a fixed budget; but neither directly addresses design uncertainty or delivery deadline risk, so do not choose them in that scenario.
Key takeaways
Key point
- When costs overrun: under FFP the seller bears all; under CPFF the buyer bears all; under FPIF the risk is shared by ratio up to the PTA and borne by the seller alone beyond it. When costs are saved, the seller retains the benefit under FFP, the buyer receives the benefit under CPFF, and the parties share it by the agreed ratio under FPIF.
- Under a fixed-price contract the buyer’s budget is certain and the price contains a risk premium; under a cost-reimbursable contract the buyer has to monitor costs.
- With the scope as agreed, the buyer’s payment under FFP is fixed (the final payment under FPIF varies with the incentive calculation but is limited by the ceiling price, and FP-EPA adjusts the price by the agreed economic price adjustment mechanism); under a cost-reimbursable contract the buyer re-forecasts EAC from the seller’s cost performance.
- Adaptive projects often use time-and-materials or cost-reimbursable arrangements paid by iteration or milestone; scope adjustments already agreed in the contract follow its mechanism, and changes beyond the established mechanisms, capacity or approved budget go through contract change control.
- New trends: agile contracting, smart contracts, outcome-based contracts, sustainable contracts, collaborative contracts; integrated project delivery (IPD) is a collaborative delivery method.
This chapter has 18 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.