PMP · Procurement · 3 lessons · about 33 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

With planning done, procurement moves into the second stage in Appendix X4, conducting the procurements: obtaining responses from sellers, evaluating them, selecting a seller and awarding the contract. The chapter covers the whole path from bidding to signing, with the bidder conference as its first key event. The core idea is transparency and fairness: every potential seller gets an equal opportunity, evaluation follows criteria set in advance, and negotiation is led by a procurement team member who holds contract signing authority, with the project manager and other project management team members assisting as needed. This stage ends with selecting a suitable seller and settling and awarding the contract through negotiation.

After this chapter you should be able to: describe the flow of conducting the procurements and the dividing line at proposal submission; list the materials normally needed to conduct the procurements (a summary made in this chapter); explain why quality-based and similar methods evaluate the technical proposal first, and why the seller with the highest technical score is selected only after the financial proposal has been negotiated and accepted; explain what advertising and the bidder conference do and when they happen; evaluate proposals with the weighting system described in PMBOK 8 and check the result, and know the common practice of screening first against minimum requirements (common exam practice); say who leads procurement negotiation and what is negotiated; and list what agreements commonly contain and what to check before signing.

Lessons in this chapter

  • Lesson 1: Conducting the Procurements: Inputs, Seller Proposals and the Bidder Conference. The flow and the dividing line; the commonly summarized kinds of input; advertising to widen the seller list; the bidder conference keeps everyone’s understanding consistent and favors no one, questions and clarifications are communicated in writing and consistently to every potential seller, and if a clarification changes the bid documents a formal amendment is issued under the procurement rules.
  • Lesson 2: Evaluating Proposals: Weighting and Screening, and Procurement Negotiation. The four steps of the weighting system; a screening system with minimum requirements; a complete worked example with four suppliers; negotiation usually takes place after the seller is provisionally selected and before the contract is signed; under the quality-based/highest technical proposal score method, the seller is finally selected only once negotiation has confirmed that the financial proposal is acceptable.
  • Lesson 3: The Selected Seller and the Agreement. Approval at the level the organization’s authorization requires for high-value or high-risk procurements; what agreements commonly contain (grouped into five categories in this chapter to aid memory); filling in missing clauses before signing; a dispute is settled by the contract terms together with documents the contract references, such as the SOW.

Chapter knowledge map

WhenWhat the buyer doesKeywordsLesson
Before proposals are submittedIssue bid documents, advertise, hold the bidder conferenceFairness, consistent understanding, amendmentsLesson 1
After proposals are submittedEvaluate: weighting, screening, comparison with the independent cost estimateSelection criteria, weights, minimum requirementsLesson 2
After the seller is selectedNegotiate, clarify rights and obligationsProcurement team leadsLesson 2
SigningAgreement, approval as authorizedClear terms, force majeureLesson 3

Study tips and practice

  • On “what next?” questions, run through the flowchart in your head and find the box where the stem stops.
  • The bidder conference comes before proposals are submitted; negotiation comes after the seller is selected. Do not mix them up.
  • Work through weighted calculations as: check the weights, multiply each item, add up, apply the screening conditions, check.
  • The project manager may take part in evaluation and assist negotiation as the organization arranges; pricing decisions and signing the agreement must be done by people with the appropriate authority, and the project manager may not sign without authorization.

Lesson 1

Conducting the Procurements: Inputs, Seller Proposals and the Bidder Conference

Lesson video

Lesson overview

By the end of the planning stage the buyer holds the statement of work, the bid documents and the source selection criteria and, when the procurement approach calls for one, an independent cost estimate. Next comes the second stage in Appendix X4, conducting the procurements: getting responses from potential sellers and answering their questions (PMBOK 8 puts preparing and sending the bid documents in the planning stage, while common exam practice often treats issuing the bid documents as the first step of conducting the procurements), receiving the responses, evaluating them, selecting a seller and awarding the contract. This lesson covers the purpose of this stage, the overall flow, the inputs and seller proposals, and then the two actions before proposals are submitted: advertising and the bidder conference. The next two lessons cover evaluation, negotiation and the agreement. Exam content outline: Process domain, Task 5 (Plan and manage procurement), covering execute the procurement management plan and participate in negotiating the agreement.

Purpose and flow of conducting the procurements

This stage picks out capable sellers and enters into a legally protected agreement with one of them setting out how the goods or services will be delivered. PMBOK 8 stresses that the core requirement of this stage is a transparent and fair process, providing equal opportunities for all potential sellers to participate and ensuring that the queries raised by bidders are duly and adequately addressed; the selection of a seller should be based on predefined criteria such as cost, quality and the seller’s ability to meet the project requirements and timelines.

PMBOK 8 summarizes the bid process as developing and publicizing bid documents, bidder conferences and selecting a bidder (that is, source selection, ending with the seller chosen). Laid out in order: the buyer states its needs and prepares the statement of work, does the make-or-buy analysis, and, once it has decided to buy, advertises and pre-qualifies or builds a short list as the procurement strategy and selection method dictate, sends out the bid documents, holds the bidder conference, sellers submit proposals, the buyer evaluates them, selects the seller, negotiates and signs the agreement.

Figure 1: Main steps in bidding

The dividing line is the submission of proposals. Before it comes preparing for bids and inviting them: the buyer advertises, issues bid documents and holds the bidder conference. After it comes evaluating and awarding: the buyer evaluates, negotiates and signs. If a question asks which stage evaluating proposals, selecting the seller, negotiating and signing the contract belong to, the answer is conducting the procurements. A performance review, inspection or procurement audit is already monitoring and controlling procurements, after signing.

Inputs and seller proposals

The inputs to this stage are mainly the results of the planning stage (the following is a commonly used summary):

  • Procurement documentation: all the documents used in signing, executing and closing agreements, and the supporting records for managing the procurement process; some exist before the project begins, for example the statement of work, payment information, drawings and correspondence.
  • Bid documents: the documents that invite sellers to bid, which sellers use to prepare their responses.
  • Statement of work: describes the objectives, requirements and results so that sellers can respond in quantified terms.
  • Independent cost estimate: used to judge whether a bidder’s proposal is reasonable.
  • Source selection criteria: describe how proposals will be evaluated, including the evaluation criteria and weights.

A seller proposal is a bidder’s response to the bid documents, and the evaluation team uses the information in it to select one or more sellers. Whether the price part is submitted and evaluated separately from the technical proposal depends on the bid documents and the source selection method. With a quality-based method the technical proposal is usually evaluated first and the financial proposal afterward, so that the technical evaluation is not swayed by price.

Key point

PMBOK 8 puts preparing and sending bid documents in planning; common exam practice makes issuing them the first step of conducting the procurements. Go by where the stem stops: SOW and criteria done -> issue the bid documents; bid documents issued -> bidder conference; proposals received -> evaluate and negotiate.

Advertising and the bidder conference

Advertising is a way of publicizing the procurement openly. Putting the procurement in newspapers or trade journals often lengthens the list of potential sellers. Whether public advertising is mandatory for government procurement depends on the applicable law, the value thresholds and the organization’s procurement policy. When the stem says “too few suppliers are responding and competition is inadequate”, the remedy is to widen the seller list through advertising.

The bidder conference, also called the contractors’ conference, vendors’ conference or pre-bid conference, is held before sellers submit proposals. The buyer should give all qualified or invited potential sellers an equal opportunity to attend and to obtain clarifying information, and communicate clarifications to everyone consistently. It has two purposes: each seller develops a clear and consistent understanding of the procurement requirements, and no single seller gets special treatment. PMBOK 8 also says that once the bid documents are distributed, the buyer generally has a bidder conference to respond to bidder questions and provide clarifying information.

What would happen without the conference? Imagine several suppliers. Supplier A phones to ask about the equipment requirements and the buyer answers. Supplier B asks about delivery time and the buyer answers that too. A does not know what B was told, and B does not know what A was told, so the suppliers hold unequal information. A conference makes the answers public: whichever supplier asks, everyone hears the buyer’s answer at the same time.

Other fair practices include collecting bidders’ questions before the meeting, or arranging a site visit for everyone together. The questions and answers at the meeting should not stay oral; they should be recorded in writing and communicated consistently to everyone. And if a clarification changes the content of the bid documents, a formal amendment is issued under the procurement rules, so that evaluation and the contract both rest on the same information.

Scenario: one bidder has extra information. In a hospital information system procurement, the buyer finds that one bidder has privately learned an interface requirement that another did not hear. The right approach is to stop private communication first and assess the effect under the procurement rules. If the situation can be remedied, as here, do not quietly send the information only to the other bidder; hold a bidder conference or make it public to all bidders in writing, add it to the bid documents as an amendment, and continue the evaluation once the information is level again. If a serious violation is involved or fairness cannot be restored, disqualify the bidder or restart the procurement as the rules provide. By the same token, if a bidder is a close friend of the project manager and privately asks how the proposal should be written, decline to coach that bidder alone and make the answer available to all bidders.

Worked examples

Example 1 (scenario question): the SOW and selection criteria are done; what next?

Question 1Example

A company decides to outsource development of its customer service system. The statement of work, source selection criteria and bid documents have all been prepared, but the bid documents have not yet been issued, and the procurement management plan calls for national competitive bidding so that proposals are received from sellers. What should the project manager do next?

Show answer and explanation

Correct answer: B

The project is in the procurement stage. The statement of work, source selection criteria and bid documents are ready, no seller proposals have been received, and the question asks for the very next step.

The signals: the SOW, selection criteria and bid documents are all prepared, the procurement management plan requires competitive bidding so as to “receive proposals from sellers”, and no proposals have arrived. For sellers to write proposals they must first have the bid documents, so the very next step is to issue them. The bidder conference is held after the bid documents go out and before proposals are submitted; evaluation has to wait until proposals are in hand; negotiation comes after the seller is selected. The answer is B.

Why the other options are wrong

  • A. The bidder conference is held after the bid documents are issued and before proposals are submitted, to clarify requirements. The bid documents have not been issued, so there is nothing to hold a meeting about.
  • C. Evaluation takes place after sellers submit proposals, and there are none yet.
  • D. Procurement negotiation takes place after the seller is selected and before the contract is signed, which is much later.

Key takeaway Once the bid documents are completed, the next step is to issue them.

Variation If the stem said “the bid documents have been issued and sellers have many questions”, the next step is the bidder conference; if it said “all proposals have been submitted”, only then does evaluation come.

Something wrong with this question?

Report an issue with this question

Example 2 (scenario question): make several suppliers understand the bid requirements in exactly the same way

Question 2Example

Last month the project manager issued the bid documents for the curtain wall work on an office building and, from the firms that submitted pre-qualification materials, shortlisted several qualified suppliers. None has submitted a proposal yet. To make these firms understand the bid requirements in exactly the same way and prevent evaluation mistakes caused by information asymmetry, what should the project manager do?

Show answer and explanation

Correct answer: A

The project is in the bidding phase of conducting the procurements. The bid documents have been issued and no proposals have arrived yet, and the qualified suppliers must understand the bid content accurately and consistently. The question asks what to do now.

The signals: the bid documents are out, sellers have not submitted proposals, and the goal is “make the firms understand the requirements in exactly the same way”. That is the bidder conference: before proposals are submitted, call all potential sellers together, with the buyer answering questions and clarifying information in one place, each firm hearing the same content and seeing the other firms’ questions and answers, so that information is level. The answer is A.

Why the other options are wrong

  • B. Meeting them separately is troublesome, cannot guarantee that each is told exactly the same thing, and prevents anyone from seeing the other sellers’ questions and answers, which is against the principle of fairness.
  • C. The sellers have not yet submitted proposals, so there is nothing to review. Reviewing proposals comes later.
  • D. Contract negotiation takes place after the seller is selected. No proposals have even been received yet, so negotiation is premature.

Key takeaway To make several sellers understand the bid documents the same way, hold a bidder conference.

Variation If a supplier privately asks the project manager how to write its proposal, the answer should likewise be made public to all bidders; if the question were “too few potential sellers”, the remedy is advertising to widen the list.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • The bidder conference is held after the bid documents go out and before proposals are submitted; no bidder conference is held after proposals are submitted, though during evaluation controlled clarifications can still be run uniformly under the bid documents and procurement rules (see the next point).
  • Meeting suppliers separately cannot guarantee that the same information is conveyed, and it is not fair.
  • If evaluation finds a defect in one proposal, handle it by the bid documents and procurement rules: where permitted, through a uniformly arranged clarification or revision (with no private coaching); where there is a material failure to respond, the proposal can be eliminated under the established criteria.
  • Whether the price proposal and the technical proposal are evaluated separately depends on the bid documents and the source selection method; under quality-based and similar methods, the technical proposal is evaluated first and the financial proposal afterward.
  • When procurement is running late, first find out why, assess the impact with the procurement team and prepare a recovery plan; escalate promptly if it exceeds your authority or reaches an escalation threshold (common exam practice: handle it first within your authority unless the stem shows it has gone beyond that authority or threshold).
  • The project manager usually takes part in requirements, evaluation and negotiation support; the contract must be signed by someone the organization has formally authorized with signing authority (PMBOK 8: negotiations should be led by a procurement team member with contract signing authority), who may come from management or the procurement department, and legal review follows organizational rules.

Key takeaways

Key point

  • Conducting the procurements: obtain responses, evaluate, select the seller, award the contract; the core is transparency, fairness and equal treatment of all potential sellers.
  • Flow: bid documents, bidder conference, proposals, evaluation, negotiation, agreement; the dividing line is proposal submission.
  • Inputs: procurement documentation, bid documents, SOW, independent cost estimate, source selection criteria.
  • Whether price and technical proposals are evaluated separately follows the bid documents and the selection method; under a quality-based method, technical first and financial afterward.
  • Bidder conference: before proposals are submitted, with all qualified or invited potential sellers having equal opportunity to attend and get clarifications; questions and clarifications are communicated in writing and consistently to everyone; if a clarification changes the bid documents, a formal amendment is issued under the procurement rules.
  • Advertising is used to widen the list of potential sellers.

Lesson 2

Evaluating Proposals: Weighting and Screening, and Procurement Negotiation

Lesson video

Lesson overview

Once the proposals are in, the buyer does two things: evaluate them and rank them, then negotiate to settle the contract terms. Evaluation relies on the source selection criteria fixed during planning, quantified through a weighting system and a screening system. Negotiation usually takes place after the seller is selected and before the contract is signed, led by the procurement team with the project manager assisting. This lesson includes a complete weighted-scoring calculation. Exam content outline: Process domain, Task 5 (Plan and manage procurement), covering participate in negotiating the agreement and determine a negotiation strategy.

Evaluating proposals: by the criteria, not by impression

Proposal evaluation is the buyer’s review and comparison of each proposal in order to select the seller. For a complex procurement, look at how each seller performs against each weighted criterion, and design a formal review process under the buyer’s procurement policy. Evaluation follows the source selection criteria set in advance; you may not decide on price alone or on a reviewer’s impression, apart from the criteria (where least cost applies to the procurement, price can be the deciding criterion). The criteria are set before the bid documents go out and are not changed casually midway through evaluation.

The weighting system quantifies qualitative data to reduce the effect of personal bias on seller selection. It has four steps: assign a weight to each evaluation criterion; rate each seller on each criterion; multiply the ratings by the weights; and add the products to get a total score. The highest total ranks first, and the ranking also sets the negotiating sequence.

A screening system sets minimum performance requirements for one or more evaluation criteria, and proposals that fall short are eliminated directly; it can be used together with the weighting system and the independent cost estimate. The screening system is common exam practice; use it the way your organization does. Screening is about “has the threshold been met”; weighting is about “what is the overall rank”.

How to do it: a complete weighting-plus-screening example

Bid evaluation for a data center construction project. Criteria and weights: technical proposal 40%, price 30%, relevant experience 20%, financial stability 10%. The four suppliers’ scores (out of 100) are below.

  1. Check the weights: 40% + 30% + 20% + 10% = 100%.
  2. Calculate each supplier’s weighted score:
    • A: 85 × 0.4 + 70 × 0.3 + 80 × 0.2 + 90 × 0.1 = 34 + 21 + 16 + 9 = 80
    • B: 90 × 0.4 + 60 × 0.3 + 85 × 0.2 + 70 × 0.1 = 36 + 18 + 17 + 7 = 78
    • C: 75 × 0.4 + 90 × 0.3 + 70 × 0.2 + 80 × 0.1 = 30 + 27 + 14 + 8 = 79
    • D: 80 × 0.4 + 85 × 0.3 + 90 × 0.2 + 60 × 0.1 = 32 + 25.5 + 18 + 6 = 81.5
  3. Using the weighting system alone: D (81.5) ranks first, followed by A, C and B.
  4. Now add screening conditions: technical proposal at least 78, financial stability at least 70. C’s technical score of 75 is eliminated, and D’s financial stability of 60 is eliminated, which leaves A and B; A (80) is above B (78), so A ranks first and goes into negotiation.
  5. Check: multiply each supplier’s four scores by the weights again, and the totals match those above. D has the highest total score but is screened out for missing a threshold, which is exactly what the screening system is for.
SupplierTechnical (40%)Price (30%)Experience (20%)Financial (10%)Weighted totalPasses screening
A8570809080Yes
B9060857078Yes
C7590708079No (technical 75)
D8085906081.5No (financial 60)

A complex procurement usually evaluates price, quality, technical capability and other criteria together; a standard or routine procurement can use the least cost method fixed in advance (PMBOK 8: least cost may be appropriate for standard or routine procurements, and should be avoided in more complex ones). Whichever method is used, evaluate against the criteria published in the bid documents. When quotes differ widely, first find the cause and assess reasonableness, possibly by comparing with the independent cost estimate, instead of deciding by whether the price is high or low.

Procurement negotiation

Procurement negotiation usually takes place after the seller is selected and before the contract is signed. Under the quality-based/highest-technical-score method, however, the top-ranked seller is finally selected only after its financial proposal has been negotiated and accepted. Its function is to clarify the structure of the contract, the parties’ rights and obligations and the other terms, so that both sides reach a shared understanding; every point agreed must end up in the wording of the contract. PMBOK 8 says that almost everything can be negotiated, from cost to delivery and payment dates, to location of work, ownership of intellectual property and so forth.

The sequence is to negotiate first with the seller ranked highest after evaluation, and to sign the agreement only when agreement is reached. The goal is an agreement that benefits the project and that both sides can perform, not pushing the price as low as possible. Push it too low and the seller may cut corners during performance, or even fail to perform.

Who negotiates? The lead negotiator should be a member of the procurement team who has authority to sign the contract. The project manager does not have to lead but may attend, clarify technical and schedule requirements and make sure the terms match the project’s needs. So when a supplier’s quote exceeds the budget, the project manager works with the procurement team to negotiate; the project manager does not decide the price alone or change the contract unilaterally and then ask the other side to sign.

Some common situations. With only one bidder and a markedly high quote, first find out which terms can be negotiated and work for a more reasonable price. When the quote is far from the budget, first analyze why: do the two sides understand the scope differently, or is the estimate wrong? Then negotiate or adjust the approach. When negotiation is deadlocked, first move things forward through direct communication, and if nothing results, start a fallback such as an alternative supplier. If before signing you find the contract gives the buyer too little protection, add to it during negotiation; you cannot sign first and fill the gaps afterward.

Worked examples

Example 1 (scenario question): five proposals are in; how should they be evaluated?

Question 1Example

A company’s new logistics center information system is out to public tender, and the tender documents specify weighted scoring against source selection criteria established in advance. The procurement team has received five proposals and is about to evaluate them. What should be done in the evaluation?

Show answer and explanation

Correct answer: C

The project is in the evaluation phase of conducting the procurements. Five proposals have been received, and the question asks for the correct way to evaluate them.

The signals: “public tender”, “five proposals” and “how should evaluation be done”. Evaluation follows the source selection criteria fixed in advance and written into the bid documents, using the weighting system: set a weight for each criterion, score each seller on each criterion, multiply the scores by the weights and add them up for a total. This reduces personal bias and also makes it easy to explain the basis of the evaluation publicly. The answer is C.

Why the other options are wrong

  • A. Looking at price alone ignores criteria such as the technical approach, capability and quality; apart from standard or routine procurements, a pure lowest-price choice should be avoided.
  • B. Ranking by impression has no common standard, is highly subjective, cannot be explained publicly and is not fair.
  • D. Size and reputation do not mean the best fit for the requirements, and ranking by them departs from the evaluation criteria set in advance.

Key takeaway Evaluation relies on criteria and weights set in advance, scoring item by item and adding up, not on price alone or on impressions.

Variation If the stem said the procurement was standard or routine with a well-defined outcome, the least cost method could be used, selecting the lowest price among proposals that meet the minimum requirements; where a criterion has a minimum requirement, common exam practice also adds a screening system, so that proposals falling short are eliminated directly.

Something wrong with this question?

Report an issue with this question

Example 2 (scenario question): proposals are evaluated but contract terms are not confirmed; what next?

Question 2Example

A project manager is in charge of the interior fit-out of an office building and plans to outsource the curtain wall installation. After the bids came in, the team finished evaluating the proposals and has selected one supplier, but the structure of the contract and its terms have not yet been confirmed with that supplier. What should be done next?

Show answer and explanation

Correct answer: D

The project is in the middle of conducting the procurements. The proposals have been evaluated and a supplier determined, but the contract terms have not yet been confirmed with it. The question asks for the very next work.

The signals: the proposals are evaluated and the supplier is selected, but “the structure of the contract and its terms have not been confirmed”. After the seller is selected and before the contract is signed, what you do is procurement negotiation: clarify the structure of the contract, the parties’ rights and obligations and the other terms so that both sides reach a shared understanding, and the final contract wording reflects everything agreed. The answer is D.

Why the other options are wrong

  • A. The statement of work is written after the decision to outsource and before the bid documents are issued. Since the proposals have already been evaluated, a statement of work obviously exists.
  • B. The bidder conference is held before proposals are submitted so that all potential sellers understand the same thing. The seller has already been selected, so that step is long past.
  • C. Awarding the contract before the terms are confirmed leaves rights and obligations unclear. It means signing first and negotiating afterward, and it leaves the seeds of disputes.

Key takeaway After the seller is selected and before the contract is signed, conduct procurement negotiation first.

Variation If negotiation reaches a deadlock, first communicate face to face to move it forward, and if there is still no result start a fallback; if you find during negotiation that the contract protects the buyer too little, fill the gap before signing.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • To choose objectively among several suppliers with different terms, the answer is to score by weighting against the source selection criteria, not to pick the cheapest or best-known one.
  • The highest total score does not necessarily go into negotiation: proposals that failed the screening conditions have already been eliminated.
  • Negotiation is usually after the seller is selected and before the contract is signed; do not confuse it with the bidder conference, which is before proposals are submitted.
  • The project manager does not set prices or sign contracts alone; price questions are left to the procurement team to negotiate.
  • The goal of negotiation is an agreement both sides can perform, not the lowest possible price.

Key takeaways

Key point

  • Evaluation follows the source selection criteria set in advance; the criteria are fixed before the bid documents go out and are not changed midway.
  • Weighting system: set weights for the criteria, rate each seller, multiply scores by weights and add up; the highest total ranks first and sets the negotiating sequence.
  • Screening system (common exam practice): set minimum performance requirements and eliminate proposals that do not meet them; it can be combined with the weighting system and the independent estimate.
  • Negotiation usually comes after the seller is selected and before signing; it clarifies the structure and the rights and obligations so both sides reach a shared understanding.
  • The procurement team leads and the project manager assists; the project manager does not set prices or sign contracts alone.

Lesson 3

The Selected Seller and the Agreement

Lesson video

Lesson overview

With negotiation settled, conducting the procurements moves to its close: confirming the selected seller and signing the agreement. Once the agreement is signed, procurement shifts from “choosing someone” to “managing someone” and enters the monitoring and controlling stage. This lesson covers whether selecting a seller needs senior approval, whether several sellers can be selected at once, and what an agreement normally says. These requirements are also the source of “everything goes by the contract” in the later monitoring and controlling stage. Exam content outline: Process domain, Task 5 (Plan and manage procurement), covering develop a delivery solution.

The selected seller

The selected seller is the one or more bidders judged most suitable against the established evaluation criteria. As common exam practice, for a complex, high-value or high-risk procurement, organizational policy and authorization thresholds may require senior management or an appropriate governance body to approve the choice before the contract is awarded. The buyer may also sign with several sellers at the same time to spread risk, so that if one has a problem the impact on the whole project is smaller.

Agreements and legally binding contracts

“Agreement” is the broader term. PMBOK 8 says that agreements can be contracts, purchase orders, memoranda of agreement (MOAs) or service-level agreements (SLAs). A contract is an agreement that is legally binding on buyer and seller. It comes about like this: bid documents are issued, sellers submit proposals, the buyer evaluates them by the source selection method and evaluation criteria announced in advance, determines a suitable seller or a negotiating sequence, negotiates with that seller, and finally drafts the agreement, which both sides sign. Without a formal procurement agreement that the organization has accepted, the buyer would find it hard to assert its rights (legal remedies depend on the applicable law and on whether a binding agreement exists), which is why industry practice says “no contract, no work”.

An agreement contains a lot. Memorize it by category:

CategoryCommon contents
Scope and qualityStatement of work or deliverables, delivery location, inspection and acceptance criteria, warranty period, product support
ScheduleDelivery dates, schedule baseline, period of performance, performance reports
Price and paymentPrice, payment terms, fees and deposits, incentives, performance bond
Liability and riskScope of liability, insurance, liability for breach or penalties, force majeure
Change and terminationChange handling, termination terms, alternative dispute resolution methods, roles and responsibilities

Events beyond the parties’ reasonable control, such as an earthquake, war or tsunami, are often covered in the contract’s force majeure clause; whether it applies, and the consequences, depend on the contract terms and the applicable law. When a dispute arises, look at the contract first, since it has legal force; anything the body of the contract does not state is then looked up in documents that the contract expressly references or incorporates, such as a statement of work incorporated into the contract.

Worked example (clause check): filling in the delivery terms. A draft equipment purchase contract says only “delivery on time”. Checking against the table: in the scope and quality category, the delivery location, acceptance criteria and warranty period are missing; in the schedule category, the delivery date is missing; in the price category, the payment conditions should be tied to acceptance. The contract has not been signed yet, so before signing the project manager should have the delivery time, location and acceptance criteria written into it. After signing, the seller may not accept new requirements, and filling in later costs the buyer its negotiating leverage.

How price and payment clauses work in practice. Take a total contract price of $2,000,000 and suppose it provides: an advance payment of 10% after signing, progress payments of 60% by milestones, 25% on passing acceptance, and the remaining 5% held as retention, paid when the warranty period ends with no defects; the seller also provides a performance bond of 5% of the contract price.

  1. Advance payment = 2,000,000 × 10% = $200,000; progress payments = 2,000,000 × 60% = $1,200,000; acceptance payment = 2,000,000 × 25% = $500,000; retention = 2,000,000 × 5% = $100,000.
  2. Check: 200,000 + 1,200,000 + 500,000 + 100,000 = $2,000,000, equal to the total contract price. The performance bond is 2,000,000 × 5% = $100,000, which the buyer can claim if the seller defaults; it is not a payment.
  3. Meaning: payment milestones are tied to acceptance, and the buyer still holds a $100,000 lever during the warranty period. The clearer the clauses, the more there is to rely on when “go by the contract” applies in the monitoring and controlling stage.

Signing, changing and terminating a contract should be done by people formally authorized by the organization under its procurement policy, which may involve the procurement department, management, project team members and legal staff; the project manager may not make contract commitments beyond his or her authority. The project manager’s responsibility is to make sure the terms are clear and unambiguous and the rights and obligations of both sides are well understood, and to monitor the seller against the contract during performance.

Worked examples

Example 1 (scenario question): the delivery terms in the draft contract are vague

Question 1Example

Reviewing a draft equipment purchase contract, the project manager finds that the delivery clause says only “deliver on time” and states no delivery time, location or acceptance criteria. The contract has not yet been signed. What should the project manager do?

Show answer and explanation

Correct answer: A

The contract has not been signed, and its draft delivery clause is vague. The question asks what the project manager should do.

The signal: the contract is “not yet signed” and the delivery clause says only “deliver on time”. An agreement normally covers the deliverables, delivery location, inspection and acceptance criteria, delivery schedule and milestones, and so on. Before signing is when the buyer has the most negotiating power, so write the delivery time, location and acceptance criteria into the contract to avoid disputes later. The answer is A.

Why the other options are wrong

  • B. After signing, the seller may not accept new requirements. Filling in later loses negotiating leverage, and the risk of disputes falls on the project.
  • C. Deleting the delivery clause strips the buyer of its hold over delivery and makes disputes more likely.
  • D. Reputation cannot replace a written agreement. Without a clear clause there is nothing to rely on in a dispute.

Key takeaway The delivery clause in an agreement must state time, location and acceptance criteria, and the gaps are filled before signing.

Variation If the vagueness were found only after signing, first assess the impact, then follow the contract change-control mechanism to negotiate the terms with the seller and obtain an authorized written amendment. If the question asked what to look at first in a dispute, the answer is the complete contract, including any statement of work it expressly references or incorporates; requirements not incorporated into the contract go through the contract’s change, claim or dispute-resolution mechanism. What the two have in common is that terms must be written clearly and gaps filled before signing, since filling them after signing loses negotiating leverage.

Something wrong with this question?

Report an issue with this question

Example 2 (concept question): what must be ensured before signing

Question 2Example

The organization and the selected seller are about to sign an equipment purchase contract. What should the project manager make sure of before it is signed?

Show answer and explanation

Correct answer: D

The project is after the seller has been selected and before the contract is signed, and the question asks what to make sure of before signing.

The signals: “about to sign” and “what should be ensured”. A contract binds both parties and sets up a buyer-seller relationship under legal protection. An agreement normally includes the statement of work or deliverables, price, payment terms, inspection and acceptance criteria, change handling, termination mechanisms and roles and responsibilities, and before signing you must ensure the terms are clear and unambiguous and each side’s rights and obligations are clear. The answer is D.

Why the other options are wrong

  • A. Payment should follow the contract’s payment terms and the state of acceptance. Paying in full before signing exposes the buyer to substantial risk.
  • B. What matters in a contract is clear terms and clear rights and responsibilities, not a longer text.
  • C. Setting only the total price omits terms such as deliverables, acceptance criteria and change handling, and invites disputes during performance.

Key takeaway Before signing, make sure the terms are clear and the rights and obligations are well defined.

Variation If the question asked who signs the contract, the answer is a person in the organization who holds the appropriate signing authority (often a procurement or contract authorized representative); the project manager signs a legally binding contract on the organization’s behalf only if formally authorized. For high-value, high-risk procurements, whether senior management approval is also needed depends on the organization’s authorization thresholds.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • Paying in full before signing exposes the buyer to substantial risk; payment follows the contract’s payment terms and the state of acceptance.
  • A longer contract is not a better contract; what matters is clear terms and clear rights and obligations. Writing only the total price and agreeing everything else during performance is a source of disputes.
  • When the seller says a report costs extra, first check whether the contract or the statement of work requires it to be delivered; neither agree outright nor refuse outright.
  • In a dispute, consult the complete contract documents and the attachments the contract expressly incorporates. A statement of work that is referenced in or incorporated into the contract has contractual force; a seller’s own requirements document that is not incorporated into the contract does not bind the parties.

Key takeaways

Key point

  • The main result of conducting the procurements: selecting a suitable seller, completing contract negotiation and awarding the contract.
  • For high-value, high-risk procurements the selection result may need approval from senior management or an appropriate governance body, following organizational policy and authorization thresholds (common exam practice/organizational authorization); several sellers can also be selected to spread risk.
  • What an agreement contains: scope and quality, schedule, price and payment, liability and risk, change and termination.
  • The force majeure clause can cover events such as earthquakes, war and tsunamis; whether it applies and the consequences depend on the contract terms and the applicable law.
  • In a dispute look first at the contract and the documents it incorporates (for example the SOW the contract references); fill in missing clauses before signing.

This chapter has 27 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.