Procurement

Monitoring and Controlling Procurements

PMP · Procurement · 4 lessons · about 45 min

Part of the free PMP video course: every lesson starts with its video →

What this chapter covers

After the agreement is signed, procurement enters the third stage described in Appendix X4, monitoring and controlling procurements. In this stage you manage the relationship with the seller, monitor contract performance, make necessary changes and corrections, handle claims and disputes, and finally close out the contract. The main thread fits in one sentence: everything goes by the contract. Most questions on this chapter take the form "something has gone wrong; what do you do first?"

By the end of this chapter you should be able to do the following. Identify the key information used when monitoring and controlling procurements, such as the agreement, procurement documentation and approved change requests (common exam practice). Insist that procurement changes are documented in writing first and approved second. When a dispute arises, check the facts against the contract and the documents it incorporates, such as the statement of work, and then negotiate (PMBOK 8 notes that negotiation and conflict-resolution skills are likely to be the first engagement in a dispute or claim; checking the contract first is common exam practice). Tell performance reviews, inspections and procurement audits apart, and use earned value measures in a performance review. Handle a claim by negotiating first, then using the ADR method the contract provides, such as mediation, arbitration, a dispute review board or expert determination, and going to litigation only when every other route has failed. Judge whether a contract can be closed, and name the three common situations in which a contract is terminated early and how each is compensated.

Lessons in this chapter

Chapter map

SituationFirst reactionLesson
The seller asks for a change or more moneyCheck the contract and SOW, go through change control, approve in writingLesson 1
The seller's performance falls shortPerformance review, compare with the contract, require correctionLesson 2
You want to sum up what went right and wrong in the procurementProcurement audit, feed the results into lessons learnedLesson 2
The two sides disagreeNegotiate directly as the contract provides; if unresolved, use mediation, arbitration, a dispute review board or similar; litigation lastLesson 3
The contract has reached its end date but there are defectsHave the seller fix them, confirm, then closeLesson 4
You need to terminate and replace a sellerCheck the termination clause and authority first, then involve procurement or contract administration under the organization's procedures and division of responsibilities (common exam practice: when the question asks what to do "first" and one option is to involve the procurement department, that option is often right; if another option is to check the contract's termination clause, check the contract first; whether this applies depends on the stem)Lesson 4

Study tips and practice

  • Common exam practice: for "first" and "first step" questions about performance deviations, changes or unclear contract terms, the answer is usually to check the contract first. For a dispute or claim itself, PMBOK 8 says negotiation is likely to be the first engagement (check the contract, then negotiate; if that fails, mediation, arbitration, litigation and so on). Replacing a seller or terminating comes later.
  • Remember the three kinds of review by their object and timing: a performance review looks at performance, an inspection looks at deliverables, and a procurement audit looks at the process.
  • A procurement change may be requested orally, but it must be recorded in writing promptly and may be carried out only after it is authorized under the contract and the formal change process. How far an oral agreement is binding depends on the contract and applicable law. A free improvement is still a change.
  • When you practice, write "what does the contract say?" on scratch paper before you choose an answer.

Lesson 1

Monitoring and Controlling Procurements: Purpose, Inputs and Procurement Changes

Lesson video

Lesson overview

After the agreement is signed, procurement enters the third stage in Appendix X4, monitoring and controlling procurements. This stage involves managing procurement relationships, monitoring contract performance, and making necessary changes and corrections, and it ends with closing out contracts. Effective contract management can ensure that the seller meets its obligations and that the project receives the required goods and services on time and within budget. This lesson covers the purpose of the stage, its inputs, procurement changes, and the appropriate first reaction: check the contract when obligations are disputed, but talk to an external party first when that party reports or causes a delay. ECO: Process domain, Task 5 (Plan and manage procurement), covering managing suppliers and contracts. The next three lessons cover performance reviews, claims and contract closure.

Everything goes by the contract

A contract is a legal relationship, and the project management team should be aware that its actions may have legal consequences. So the main thread of this stage fits in one sentence: everything goes by the contract. When a contractual obligation is unclear or disputed, the first reaction is neither to lose your temper nor to escalate, but to go back to the contract.

The work in this stage includes maintaining the relationship with the seller, keeping an eye on contract performance, making changes or corrections when necessary, handling claims and disputes, and finally closing out the contract. PMBOK 8 treats it in Appendix X4 as the last stage of the procurement process, monitoring and controlling procurements. Using the traditional process framework as a guide, the results of monitoring usually take the form of work performance information and change requests.

Inputs: the agreement, procurement documentation and approved change requests

Three important inputs (common exam practice):

  • The agreement. What the two parties settled on about their obligations. During monitoring, you compare it clause by clause to see whether the terms and conditions are being followed.
  • Procurement documentation. The full set of records needed to manage this procurement, such as the statement of work, payment information, contractor work performance information, plans, drawings and correspondence. Some of it may date from before the project started.
  • Approved change requests. A change request may be approved, deferred or rejected. An approved change that affects procurement or the contract is carried out under the relevant procedures, and it may involve changes to the terms and conditions of the contract.

Besides these three core inputs, you will often also consult the schedule baseline, the procurement management plan and work performance data. The procurement management plan usually states the requirements for closing out the contract and also sets out how the procurement is to be carried out and how often.

Procurement changes: in writing first, then approved

A change to the terms of a contract should be recorded and authorized under the contract change procedure and applicable law before it is carried out. An oral promise that has not gone through those steps cannot be used to justify a change in payment, and how binding it is depends on the contract and applicable law. Other project changes related to procurement are handled under the development approach and change management arrangements the project uses. A contract may be amended before it is closed: when both parties agree, it can be revised at any time under the change control clause in the agreement, and the revision is again recorded in writing. If the contract has no change procedure, the parties should negotiate a supplementary clause. Neither side may change the contract unilaterally, and ignoring the problem is not an option. Large projects often have several sellers, and a change requested by one may affect another. So an important part of contract management on a multi-seller project is coordinating communication among the sellers.

Disputes and deviations: check the contract first

When a dispute arises, review the contract and the documents it incorporates, such as the statement of work. Whether the statement of work is binding depends on the terms of the contract and applicable law. In a dispute with a seller or a customer, look at the contract first; if the contract is silent, look at the statement of work it refers to; only after the facts are clear do you decide whether to negotiate, change or hold someone accountable. PMBOK 8 says that the project manager's negotiation and conflict-resolution skills are likely to be the first engagement in a dispute or claim. So after checking the contract you usually negotiate with the other party first, and if that fails you use an alternative dispute resolution (ADR) method as the contract provides, going to litigation only when every other route has failed. For a performance deviation, choose the first step from the facts. If an external party is delayed, talk to that party first to understand the situation. If an obligation is disputed or responsibility must be established, first check the contract and the statement of work it incorporates. Then assess the project impact, identify affected stakeholders, and choose between correction, a change or accountability. If the seller delivers something defective, do not hide it and do not terminate the contract at once; give written notice and require correction as the contract provides.

Scenario: "This report costs extra." During execution, a consulting firm says that a weekly report the project manager has asked for is outside the original scope and must be billed separately. The project manager should first check whether the contract and the statement of work require a weekly report. If they do, it is within scope, there is no extra charge, and the seller must deliver as the contract says. If they do not, it is new work outside the scope: go through the contract change control procedure, assess the impact, and carry it out only after written approval. The project manager neither agrees orally nor flatly refuses.

Scenario: a predecessor's oral promise. A new project manager finds that a predecessor privately promised orally to raise the mobilization advance payment from 15% to 25%. The contractor arrives with a payment application for 25% and asks for a signature. The oral promise has not been recorded and approved under the change procedure in the contract, so the project manager cannot approve a 25% payment on the strength of it. The project manager should verify the authority, the contract terms and applicable law, and arrange a formal change. Until then, payment follows the 15% written in the contract.

Worked examples

Example 1: Scenario question: outsourced terminals fall short; what do you do first?

Question 1Example

A smart-campus access control project has entered implementation. The face-recognition terminals are supplied by an outside vendor. A key stakeholder writes to say that the terminals that arrived do not meet the agreed requirements for use. As project manager, what should you do FIRST?

Show answer and explanation

Correct answer: C

An access control project is in implementation, the terminals are outsourced to a vendor, and a key stakeholder reports that the delivered terminals fall short. The question asks what the project manager does “first”.

Signals: “first”, and purchased terminals that fail to meet requirements. When buyer and seller disagree or things are unclear, everything goes by the contract. First read what the contract requires of the terminals and what remedies it provides for nonconforming deliveries, and only then decide between correction, a claim or something else. The answer is C.

Why the other options are wrong

  • A. A claim needs a basis in the contract. Until you have read it, you cannot tell whether the vendor is in breach or what you can claim.
  • B. Whether the vendor must correct the defect, and whether a change request is needed at all, depends on the procurement agreement and the impact of the correction. Raising a change request before checking the agreement or confirming the terminals are nonconforming is the wrong order. If the remedy involves a formal change to the agreement or the project baselines, a change request is then submitted through change control.
  • D. Replacing the vendor is something you might do only after you know what the contract says. The question asks what to do first.

Key takeaway When a procurement dispute arises, look at the contract first, then act.

Variation If the contract does not state the requirement, verify what the two sides agreed using the statement of work and other procurement documents. Only after you confirm the vendor is in breach do you talk about written notice to correct, a claim or replacing the vendor. Common exam practice: checking the contract first is the usual first step in monitoring and controlling procurements; claims, replacing the vendor and change requests all come later.

Something wrong with this question?

Report an issue with this question

Example 2: Scenario question: can a predecessor's oral promise be honored?

Question 2Example

A new project manager takes over a server-room renovation project and finds that the predecessor privately promised the contractor orally to raise the mobilization advance payment from 15% to 25%, but the change was neither recorded in writing nor formally approved. The contractor now submits a payment application filled in at 25% and is waiting for a signature to release the money. How should you respond?

Show answer and explanation

Correct answer: D

After a change of project manager on a server-room renovation, the contractor applies for payment at the 25% advance rate that the predecessor orally agreed to. The new project manager must decide whether to sign.

Signal: the predecessor only “privately promised orally”, and now the new manager is asked to sign off the payment. A procurement change must be recorded in writing and formally approved before it is carried out, and an oral agreement cannot be the basis for payment, so payment stays at the percentage written in the contract. Note that the point is not that a contract can never be changed: to change it, go through change control and approve in writing. The answer is D.

Why the other options are wrong

  • A. An oral agreement is not a basis for payment. The predecessor's personal promise cannot replace a written, approved contract change.
  • B. Contract terms can be changed, but only through the change control procedure with written approval. The claim that they can “never be changed” is itself wrong.
  • C. The point is not whether you personally know the background but that the change was never approved in writing. Even if you knew, the conclusion would be the same.

Key takeaway A procurement change must be recorded in writing and formally approved; an oral agreement cannot be the basis for payment.

Variation If the contractor produces a written change order that has been approved, pay at the changed percentage. If the contract contains no change procedure, the two parties should negotiate a supplementary clause.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • A change proposed by the seller, even if it is free and even if it improves the result, should first be assessed whenever it affects the contract terms, the agreed deliverables, the project baselines or configuration-controlled items. It is handled under the contract change procedure and the change management arrangements the project uses. Do not approve it straight away, do not reject it straight away, and do not implement it first.
  • When payment terms are fixed in the agreement, pay as the agreement says. Do not advance money on your own, and do not change the payment arrangement because the other party delivered early.
  • Legal clauses in a contract are usually drafted by procurement or legal professionals. The project manager should take part in procurement planning and in the choice of contract type. Negotiation is led by procurement staff with signing authority, and the project manager can attend to help as needed. During performance, keep reviewing the seller's performance against the contract.
  • In a dispute, look at the contract first. Do not escalate to your boss first and do not send a claim letter first.

Key takeaways

Key point

  • Monitoring and controlling procurements: manage the procurement relationship, monitor contract performance, change and correct, and close the contract; everything goes by the contract.
  • Three inputs: the agreement, procurement documentation and approved change requests. The procurement management plan sets out how the procurement is carried out and states the closure requirements.
  • A change to the contract terms is recorded in writing and authorized under the contract and applicable law before it is carried out; an oral agreement that has not been recorded and authorized under the contract change procedure cannot justify a change in payment, and its legal effect depends on the contract and applicable law. Other procurement-related changes follow the development approach and change management arrangements the project uses.
  • For a dispute, check the contract; for an external-party delay, talk to that party first. Then consult the statement of work as needed, assess the impact, and choose correction, a change or accountability.
  • On a multi-seller project, coordinate communication among the sellers.

Lesson 2

Performance Reviews, Inspections and Procurement Audits Compared

Lesson video

Lesson overview

Monitoring and controlling procurements uses three common tools: performance reviews, inspections and procurement audits. The names sound alike but the objects and timing differ, and exam questions often put them in the same set of options. This lesson first gives a way to tell them apart, then shows how to use earned value and trend analysis in a performance review, and finally covers procurement audits and lessons learned. ECO: Process domain, Task 5 (Plan and manage procurement), covering evaluating supplier performance and verifying that the objectives of the procurement agreement are met.

Telling the three tools apart

The way to tell them apart is to look at the object and the timing.

ToolWhat it reviewsWhenTypical approach
Performance reviewThe seller's contract work performance: quality, resources, schedule, costDuring performance, at regular intervalsMeasure, compare and analyze against the agreement; use earned value analysis to calculate variances and indices, and trend analysis to forecast the estimate at completion
InspectionThe seller's deliverables, or the work in progress itselfDuring performance, when a phase result is produced, or before final acceptanceCheck conformity against the acceptance criteria in the agreement, as a basis for formal acceptance; can also be a structured review on site
Procurement auditWhether the whole procurement process is proper, complete and effective (the project managers of both buyer and seller should pay attention to the results)Mostly at contract closure, as a source of lessons learned (common exam practice); can also be done during procurement when neededA structured, relatively independent review that checks whether the contract and the contracting process are complete, accurate and effective

In one sentence: a performance review reviews performance, an inspection reviews deliverables, and a procurement audit reviews the process. A performance review happens while the seller is working, and looks at the results it delivers and the performance numbers. A procurement audit can be carried out during the procurement when needed and is also often used at contract closure to pull together lessons learned. It examines the whole procurement process for problems (it cannot replace continuous monitoring of the contract work performance), such as whether a seller was chosen in advance, whether the process complied with rules and whether there was fraud. The rights and obligations related to audits should be described in the procurement contract. When an audit finds problems, the project managers of both buyer and seller should pay attention so that the project can be adjusted, and lessons learned are produced.

Performance reviews: let the numbers talk

A performance review needs a standard. Agree measurable indicators with the seller and record them in writing. The review compares performance with the performance requirements in the contract, not with impressions, the industry average, or bid promises and oral promises that were not made part of the contract. If the contract has no quantifiable performance indicators, the evaluation will be less objective: first evaluate against the existing contract requirements, and if you really need to add or refine indicators, agree them with the seller and confirm them in writing through the contract change mechanism. When performance falls short, first assess the cause and ask for correction as the contract provides. Do not lower the standard, and do not rush to terminate the contract.

A performance review can use earned value analysis. Worked example. A systems integration project is outsourced to a seller. The budget for the contract work (BAC) is $1,000,000. At the end of this month the planned value (PV) is $400,000, the earned value (EV) of the work actually completed is $360,000, and the actual cost (AC) incurred and confirmed for the completed contract work is $420,000 (assume in this example that the amount paid equals the actual cost confirmed for the period).

  1. Cost variance CV = EV − AC = 360,000 − 420,000 = −$60,000: over budget.
  2. Schedule variance SV = EV − PV = 360,000 − 400,000 = −$40,000: behind schedule.
  3. Cost performance index CPI = EV ÷ AC = 360,000 ÷ 420,000 ≈ 0.857; schedule performance index SPI = EV ÷ PV = 360,000 ÷ 400,000 = 0.9.
  4. If the project continues at the current cost performance, estimate at completion EAC = BAC ÷ CPI = 1,000,000 ÷ 0.857 ≈ $1,167,000, and estimate to complete ETC = EAC − AC ≈ 1,167,000 − 420,000 = $747,000.
  5. Check: the budget for the remaining work is 1,000,000 − 360,000 = $640,000; at a CPI of 0.857 it needs 640,000 ÷ 0.857 ≈ $747,000, which agrees with the ETC.
  6. Reading the result: these are numbers a buyer under a cost-reimbursable contract should watch, because the buyer bears the overrun. Under a firm-fixed-price (FFP) contract, absent an approved contract change, the buyer's payment is fixed, but the seller may cut quality or stop work to limit its losses, so you still review the cause and require correction as the contract provides.

Inspections and procurement audits

An inspection is a structured examination of the seller's deliverables or work in progress. At acceptance, you compare against the acceptance criteria in the agreement. If a supplier delivers flooring whose moisture content is above the limit, then even if it arrives early it does not meet the contract's quality requirements and cannot be accepted. Inspecting interim results regularly can reveal quality problems before overall acceptance.

A procurement audit reviews the buyer's procurement process; it is not an evaluation of one supplier. When a project is nearly over, if the parties understand the contract terms differently or acceptance keeps being repeated, a procurement audit can serve as a structured review to find the problems and sum up what worked and what did not. The conclusions go into the lessons learned register and organizational process assets for future projects. If you find a financial problem in a settlement that you cannot explain, use audit methods to verify it first; do not jump to a conclusion.

Scenario: look at results first, then at the process. Team members report that the supplier of a key component is having trouble carrying out an approved product change. The project manager's first step is to review that supplier's work performance: what it has delivered, and how the schedule and quality actually look. If you then need to check process compliance, identify process defects or verify that the approved change was implemented, carry out a quality audit under the quality management arrangements (quality audits can also be planned or random). Common exam practice: verify actual performance first and then decide on an audit. Scheduling an audit or calling a change control meeting right away usually skips the first step.

Worked examples

Example 1: Scenario question: you want to learn lessons from the whole procurement process

Question 1Example

The project manager at a software company has just finished a largely outsourced systems integration project in which the two sides read the contract terms differently, acceptance was repeated, and the whole procurement went badly. The project manager wants to avoid the same mistakes on the next project. What should the project manager do?

Show answer and explanation

Correct answer: B

The project manager wants to capture the problems and experience from this procurement for use on the next project and must decide which approach to use.

A procurement audit is a structured review of the procurement process, including the contract and contracting process. Its purpose is to find problems in procurement management and to sum up what worked and what did not as lessons learned for future projects. The stem says the whole procurement process went badly and the aim is to avoid a repeat on the next project, which is exactly what a procurement audit is for. The answer is B.

Why the other options are wrong

  • A. The issue log records specific problems that need tracking and resolution while a project is under way, and this project has ended. A PMO also does not take on a project's procurement problems one by one. This approach cannot systematically find process defects.
  • C. An oral review in a meeting is not structured and produces no reusable record. The lessons are not put into the lessons learned register or organizational process assets, so the next project may repeat the mistakes.
  • D. Adding clauses on the spot addresses only the individual problems exposed this time. It does not first review the whole procurement process, so it finds no root cause and does not cover other potential problems.

Key takeaway To learn lessons from the whole procurement process, use a procurement audit for a structured review and put the conclusions into lessons learned.

Variation If the question asks how to judge a supplier's performance this month, use a performance review, not a procurement audit. If it asks about accepting a delivery of floor tiles, use an inspection.

Something wrong with this question?

Report an issue with this question

Example 2: Scenario question: after a quality failure, how do you prevent it from happening again?

Question 2Example

A project manager at a logistics company finds that an outside software supplier delivered a feature module on budget, but at acceptance it did not meet the agreed quality standard, and the supplier could only rework it, which delayed the whole project. The after-the-fact review finds that the problem came from a lack of oversight of the supplier's delivery process. What should the project manager do to keep such problems from happening in later procurements?

Show answer and explanation

Correct answer: D

A supplier has already delivered a module that failed quality and delayed the schedule, and the review concludes that the problem was a lack of oversight of the supplier's delivery process. To prevent a recurrence, a preventive method of monitoring and controlling procurements is needed.

An inspection examines the contractor's deliverables or work in progress, and inspecting interim results regularly can reveal quality problems before overall acceptance. A procurement audit is a structured review of the procurement process, including contracts and contracting processes, for completeness, accuracy, and effectiveness so that shortcomings can be identified and improvements made. The two together are the way to “avoid future procurement problems”. The answer is D.

Why the other options are wrong

  • A. The contract is already signed. Renegotiating terms and price will not prevent the next quality failure, because the real problem is the lack of oversight of the delivery process.
  • B. Revising the quality management plan only adjusts a document and is not itself oversight of the supplier's delivery process. The stem already says the problem was a lack of oversight, so the oversight method is what needs to be added.
  • C. A penalty is a remedy after the fact. Holding the supplier accountable for rework that has already happened does nothing to prevent the same problem later, and it may not match the contract's penalty terms.

Key takeaway To prevent procurement quality problems, use inspections to monitor the seller's deliverables and a procurement audit to sum up the shortcomings in the procurement process.

Variation If the question asks for the first step after finding a supplier quality problem, first review the supplier's performance, check the contract to confirm responsibility, and then require correction. A procurement audit looks more like an after-the-fact review of the process.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • A procurement audit reviews the buyer's procurement process, not one batch of the seller's products. Reviewing the seller's products is an inspection.
  • Common exam practice: a procurement audit is mostly done at contract closure to sum up lessons learned; it does not replace a performance review in the middle of performance.
  • A performance review compares with the requirements agreed in the contract, not with "the industry average" or oral promises made at bid time.
  • The quality of outsourced work is also part of project quality management.
  • For a supplier with poor quality, first find the cause and require correction as the contract provides; do not penalize or terminate immediately.

Key takeaways

Key point

  • A performance review reviews performance (during performance, against the agreement, using earned value and trend analysis); an inspection looks at deliverables; a procurement audit reviews the procurement process (common exam practice: mostly at contract closure).
  • Agree performance standards with the supplier and record them in writing; compare with the contract, not with impressions.
  • Earned value: CV = EV − AC, SV = EV − PV, CPI = EV ÷ AC, EAC = BAC ÷ CPI.
  • The conclusions of a procurement audit go into the lessons learned register and organizational process assets.
  • The quality of outsourced work is part of project quality management.

Lesson 3

Claims Administration and Alternative Dispute Resolution

Lesson video

Lesson overview

Claims and disputes are common in projects. In construction projects, the direct cost of disputes is about 0.5% to 5% of the total contract value, and time and cost overruns, often caused by variation orders, are among the primary factors leading to disputable claims. This lesson covers where claims come from, the order in which to handle them, the types of alternative dispute resolution (ADR), and the project manager's role and professional ethics. ECO: Process domain, Task 5 (Plan and manage procurement), covering managing suppliers and contracts.

Where claims come from

A contested change is called a claim. If it remains unresolved, it may escalate under the contract's claims procedure into a dispute and potentially an appeal. There are two common causes. In the first, the buyer believes a piece of work is not a change and deserves no extra payment, while the seller believes it is a change and will not do it without extra payment. In the second, the buyer has the seller do something outside the contract, and the seller asks to be compensated after doing it; this is called a constructive change (a common exam term). When the two sides cannot agree on whether something is a change, or on compensation for a change, a claim arises.

The order of handling is: negotiation comes first, then other ADR methods that involve a third party, such as mediation, and litigation comes last. The figure below shows this escalation.

Figure 1: The order for handling claims and disputes

Types of alternative dispute resolution (ADR)

PMBOK 8 lists the following types of ADR (the order of the list does not rank them by formality: arbitration is more formal than negotiation, and litigation is the last option when everything else has failed):

  • Negotiation: "Negotiation involves direct discussions between parties to resolve disputes without third-party intervention."
  • Mediation: "Mediation brings in a neutral third party to facilitate discussions between disputing parties to reach a mutually acceptable solution." The mediator does not make a decision.
  • Arbitration: "Arbitration is a more formal process where an arbitrator or panel hears both sides and makes a binding decision."
  • Dispute review boards: "A dispute review board is a panel of neutral experts appointed at the start of a project to provide ongoing dispute avoidance and resolution."
  • Expert determination: "Expert determination is when an independent expert is appointed to make a decision on a specific technical or financial issue."
  • Litigation: "If all other means are exhausted but the disagreement between the stakeholders persists, litigation becomes the last option, where the dispute is referred to a court to be resolved."

Common exam practice treats the order in three steps: negotiate, then the other alternative methods (mediation, a dispute review board, arbitration and so on), and finally litigation. PMBOK 8 also lists negotiation as a type of ADR, but in terms of order, direct negotiation is still the first choice.

Why is litigation the last choice? First, the time and cost are high. A lawsuit over an implementation contract across regions can take years, the project may be long over, and winning the case can mean losing the business. Second, it affects reputation: court records may become public (how much is made public depends on applicable law and court procedure). Third, it affects future cooperation and some qualification reviews. So most companies negotiate where they can and mediate where they can.

The project manager's role and professional ethics

The project manager is often the first point of contact in a dispute. PMBOK 8 advises the following. Understand the contract terms thoroughly and identify potential areas of dispute early. Maintain detailed records of all project activities, changes and communications to support potential claims. Keep communication open and clear to minimize misunderstandings. Recognize conflicts early and address them promptly to prevent escalation. For this reason, improve your negotiation and conflict-resolution skills and work well with the organization's legal team.

Where legal action is involved, there are also sensitivities to watch. Be mindful of the language in written communications, including emails, because they can be used as evidence in legal proceedings. Establish a protocol in advance for when and how to escalate disputes to legal action. Maintain strict confidentiality about dispute details. Stay impartial, focusing on facts rather than emotions or personal relationships. These are also requirements of professional ethics.

Scenario: does the battery pack meet the contract? Testing on a power-tool development project is slowed down because of battery packs the supplier delivered. The project manager concludes they are nonconforming; the supplier insists everything meets the contract. If this is not resolved within a week, the launch will be affected. The first step is to study the contract to understand both sides' rights and obligations, and then negotiate a solution with the supplier; negotiation is the preferred method. Escalating directly, changing the contract first, or demanding termination and a penalty all skip this step.

Scenario: no reply from the other side. The project manager has given the seller written notice of the dispute and asked to negotiate, and the other party has not responded. The next step is not litigation but starting alternative dispute resolution, for example asking a neutral third party to mediate, and only afterward considering arbitration or litigation. Keep a written record of every step as evidence for any later claim.

Worked examples

Example 1: Scenario question: does the battery pack meet the contract; each side insists it is right

Question 1Example

Testing on a power-tool development project has slowed because of problems with battery packs the supplier delivered. The project manager concludes that the battery packs are nonconforming, while the supplier insists that all the goods meet the contract. If this is not resolved within a week, the product launch will be affected. How should the project manager handle it?

Show answer and explanation

Correct answer: C

During testing, buyer and seller each insist on their own view of whether the battery packs meet the contract, and the schedule is threatened. The question asks what the project manager does.

Signals: each side insists it is right, and failing to resolve it within a week will affect the launch. In a dispute, look at the contract first to understand each side's rights and obligations, then negotiate a solution with the supplier. Negotiation is the preferred method of resolving a dispute, and the order of handling can be remembered as: check the contract, negotiate, then escalate step by step as needed. The other options skip these two steps: reporting without reading the contract cannot show a breach, and amending the contract or terminating directly has no basis. The answer is C.

Why the other options are wrong

  • A. Reporting before reviewing the contract cannot show the supplier failed to perform, and you should negotiate first before considering escalation.
  • B. The contract is already signed, so an amendment must go through the change control procedure, and the contract does not reflect what needs to be changed. This should not be the first step.
  • D. Terminating and fining directly has no basis, may put you in breach, and would further affect the schedule.

Key takeaway In a procurement dispute, check the contract first and then negotiate with the supplier.

Variation If negotiation fails, use mediation, arbitration, or another dispute-resolution method as the contract provides; litigation is the last resort after other means are exhausted. Keep written records throughout.

Something wrong with this question?

Report an issue with this question

Example 2: Scenario question: the two sides see the result of a clause differently; which method comes first?

Question 2Example

On a supplier contract for an outdoor billboard installation project, the two sides see the result of performing several clauses differently. The project team believes it followed the clauses strictly; the supplier believes the requirements were not met. The two sides have not yet communicated formally, and each holds its ground. To keep the situation from escalating, which method should the project manager use FIRST to resolve the dispute?

Show answer and explanation

Correct answer: A

On a project, the two sides see the result of performing contract clauses differently and have not yet communicated formally. The question asks which method to use first to resolve the dispute.

The usual first step is direct negotiation by the two parties (PMBOK 8 Appendix X4 defines negotiation as direct discussions between parties to resolve disputes without third-party intervention). If negotiation fails, consider, under the contract's dispute resolution clause, mediation, a dispute review board or other methods that involve a neutral third party, or the more formal arbitration. Litigation is the last option when all other means are exhausted. Negotiation is direct, efficient and confidential, and it preserves the working relationship, so negotiate first. The answer is A.

Why the other options are wrong

  • B. Arbitration is a more formal procedure, and whether and when it is used depends on the contract's dispute resolution clause. Here the two sides have not formally communicated, so they should not skip direct negotiation and proceed immediately to arbitration.
  • C. Litigation is the last resort and is considered only after all other means have failed. It cannot be the first move.
  • D. Mediation brings in a neutral third party and is usually used under the contract after direct negotiation fails. Here the two sides have not formally communicated, so going to a third party and skipping direct negotiation is premature.

Key takeaway For a dispute, negotiate directly first; if that fails, consider mediation or other methods with a neutral third party, or arbitration, as the contract provides. Litigation is the last choice.

Variation If the stem says the two sides have negotiated several times without result, the next step, as the contract provides, can be mediation, a dispute review board or another method with a third party. If the question asks about having an independent expert decide a technical or financial issue, that is expert determination.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • In a dispute, look at the contract first. Do not escalate to your boss first and do not send a claim letter first.
  • If negotiation gets no response, the next step is alternative dispute resolution, and only after that litigation. Do not skip levels.
  • A claim rests on evidence: the actual results plus the standard agreed in the contract. You need both.
  • Involve the procurement team and legal staff who know the contract. The project manager should not decide on the basis of an oral promise.
  • A mediator does not make a decision; an arbitration award is binding.

Key takeaways

Key point

  • A contested change is called a claim; if unresolved, it may escalate under the contract's claims procedure into a dispute and potentially an appeal. A constructive change (a common exam term) is when the buyer's instruction or conduct leads the seller to do work outside the contract scope, and the seller then asks to be compensated.
  • Common exam practice: negotiate first, then other dispute resolution methods (mediation, arbitration, a dispute review board, expert determination and so on), and litigation last; PMBOK 8 also lists negotiation as a type of ADR.
  • Project manager: understand the contract, keep records, keep communicating, address conflict early, and work with the legal team.
  • Legal sensitivity: be careful with written wording, set up an escalation protocol, keep confidentiality and stay impartial.
  • For a dispute, review the whole contract and its component documents (including the statement of work and acceptance criteria it incorporates), and follow the claims and dispute resolution procedures the contract provides.

Lesson 4

Closing Out Contracts and Early Termination

Lesson video

Lesson overview

Closing out a contract is the last step of monitoring and controlling procurements, and it is also one of the things that must be done when a project or phase is closed. This lesson covers when a contract can be closed, what to do at closure, the usual order of steps, and the three situations of early termination and their compensation. ECO: Process domain, Task 5 (Plan and manage procurement), covering verifying that the objectives of the procurement agreement are met, and Process domain, Task 10 (Manage project closure).

Closing out the contract

Common exam practice: when the procurement is complete, the buyer, usually through an authorized contract administrator, notifies the seller in writing that the contract has been fulfilled. What counts as formal closure is usually already set out in the contract terms, and the procurement management plan also records it. Common exam practice: first check three things: (1) all deliverables have been delivered and formally accepted, and meet the agreed time, quality and technical requirements; (2) there are no open claims or invoices; and (3) all final payments have been made. These three are not the full set of closure conditions. You must also settle outstanding guarantees, warranties and disputes under the contract and confirm that all contractual obligations have been met with nothing left outstanding. Before closing the procurement, the project management team must first confirm that all related deliverables have been formally accepted by the customer or by the acceptance authority named in the contract.

PMBOK 8 gives the following activities that should be verified when closing out contractual agreements in the Close Project or Phase process:

  • Confirm formal acceptance of the external source's work.
  • Finalize any open claims, guarantees, and warranties.
  • Update records to reflect the final results.
  • Ensure all invoices due to external sources are paid.
  • Archive relevant information for future use.
  • Resolve any disputes that may arise or refer them to the dispute board.

Acceptance, payment, approval and closure all follow the contract. Before formal closure, confirm that the work has been formally accepted, that amounts due have been paid, and that the contractual obligations have been met; do not change this because the other party is in a hurry. When you find defects, require the seller to correct them as the contract provides, and handle the money under the contract's terms on payment, retention, warranty and claims. Do not formally close the contract until the closure conditions are met. If a hidden defect appears only after acceptance, it goes to the seller under the contract during the warranty period. Archive the procurement documentation in full, not just one copy of the contract, and put the lessons learned into the organizational knowledge repository.

Scenario: the customer refuses to close. On a network engineering contract, all the equipment has been delivered and the seller asks to close. After inspecting, the buyer finds two configurations that do not meet the acceptance criteria and refuses to close. The project manager should compare against the contract's acceptance criteria, check the gaps with all parties, and agree what remedial work to do. After the seller completes it and it passes acceptance, pay the final payment, issue the formal closure notice and archive the documents. If the acceptance criteria themselves are unclear, have authorized procurement and legal staff and both parties to the contract clarify or amend them in writing under the contract change procedure, and then carry out acceptance.

Early termination of a contract

Early termination is a special case of closing out a procurement. Common exam practice divides it into three situations (the contract and applicable law decide the details): both parties agree to terminate early; termination because one party is in breach; and termination for the buyer's convenience, where the contract gives the buyer a right to terminate for convenience and the buyer ends the contract early for its own convenience.

Payment, compensation, offsets and claims after early termination are determined by the contract, the reason for termination and applicable law. Common exam practice is to keep two accounts. Work that has been completed and accepted is paid for as agreed. On termination for convenience, the reasonable termination costs and the seller's preparatory work are usually handled under the termination clause. If the contract is terminated because the seller is in breach, the seller's preparation costs are not automatically compensated. If it is terminated because the buyer is in breach, the seller may claim compensation under the contract and applicable law. Terminating a contract and replacing a seller are matters for the procurement function. The project manager should first verify the contract terms and the limits of authority, and have authorized procurement, legal or management staff in the organization get involved under the governance arrangements. Then assess the impact on the project, study alternatives, and carry out the termination or replacement. When answering exam questions (common exam practice): if the company has already decided to terminate and the question asks what to do "first", choose "involve the procurement department" if it is an option; if an option also says "check the contract's termination clause", check the contract first and then involve the procurement department. If there is a dispute over termination costs, first reach agreement through negotiation. Do not wait for the other party to act, and never alter data.

Worked example: compensation on termination. An equipment contract has a total price of $500,000, divided into four milestones of $125,000 each. The buyer terminates early for convenience. The first two milestones have been completed and accepted. The third milestone is half complete but not accepted. For the third and fourth milestones the seller has bought $20,000 of special-purpose material (this $20,000 is material that has not yet been put to use; material already used in the work in progress on the third milestone counts as work in progress and is not compensated twice). The contract says preparatory work is compensated at actual expenditure.

  1. Accepted work: 125,000 × 2 = $250,000, paid as agreed.
  2. The half-finished, unaccepted milestone: it cannot be priced as complete unless the contract says so; first settle it under the contract's treatment of work in progress.
  3. Compensation for preparatory work: $20,000 of special-purpose material, compensated against receipts.
  4. The buyer must pay at least 250,000 + 20,000 = $270,000, plus whatever the contract provides for work in progress. Check the termination clause for any cap on the total settlement; do not assume that payments plus compensation are limited to $500,000 unless the contract says so. Nothing extra is paid for the fourth milestone, which is not complete.

Worked examples

Example 1: Scenario question: the contract has expired and a defect is still not fixed; how do you close?

Question 1Example

A customer service system outsourcing contract expires next week. At acceptance, a small number of defects are found that have not been fixed. The contract provides that the deliverables must be confirmed by the buyer to be defect-free before the contract can be closed. What should the project manager do?

Show answer and explanation

Correct answer: C

The contract is about to expire but defects remain. The question asks what to do.

Signals: the contract expires next week, defects remain, and the contract says closure requires confirmation that there are no defects. Common exam practice: first check that all deliverables have been delivered and accepted, there are no open claims or invoices, and all final payments have been made; this is not an exhaustive list, and the contract and applicable closure requirements may add conditions. Remaining defects mean the conditions are not met, so require the supplier to fix them under the contract and, once this is confirmed, close formally. The answer is C.

Why the other options are wrong

  • A. The contract explicitly requires confirmation of no defects before it can close. Expiry does not mean the closure conditions are met. Closing anyway breaches the agreed closure condition and may be read as accepting the defects, which affects later recovery.
  • B. Paying the final amount before the defects are fixed weakens the buyer's payment leverage and, depending on the contract, may be treated as acceptance of defective deliverables.
  • D. Fixing defects is already the supplier's obligation under the original contract. Signing a new contract would make the buyer pay extra for it.

Key takeaway Closing a procurement requires the conditions to be met: if defects are not fixed, have the other side fix them under the contract before closing.

Variation If the defect is a hidden one found only during the warranty period after acceptance, handle it with the seller under the contract. The contract is closed only when everything has been accepted, payments are settled and there are no open claims, and the contract administrator notifies the seller in writing.

Something wrong with this question?

Report an issue with this question

Example 2: Scenario question: the company decides to terminate the contract and replace the supplier; what do you do first?

Question 2Example

A project manager responsible for deploying a chain store's checkout system is very dissatisfied with the terminal equipment supplier, whose deliveries are always late and often lack key components. The company has decided to terminate the contract and replace the supplier, but the only candidate for the new supplier is an overseas company. To move this replacement forward, what should the project manager do FIRST?

Show answer and explanation

Correct answer: A

On a project, the company has decided to terminate the contract and replace the supplier. The question asks what the project manager does “first”.

Terminating a contract and replacing a supplier involve contract terms and legal consequences and should be handled by people in the organization who have the appropriate procurement or contract authority, following the process. Here there is a procurement department, so the project manager should first bring it in to help terminate the existing contract and move the follow-on procurement forward. Learning about culture, hiring a translator and finding contacts are preparations to take up once the termination and procurement arrangements are clear, and they are not the first thing to do. The answer is A.

Why the other options are wrong

  • B. Cultural differences matter when negotiating with the new supplier, but that is preparation to take up after the termination and the new procurement arrangements are clear. It is not the first thing to do.
  • C. A translator is preparation for communicating with the overseas supplier. The existing contract has not yet been dealt with, so this is not the first step.
  • D. Finding mutual contacts is a way to approach the new supplier. The existing contract has not been dealt with, so this is not the first step either.

Key takeaway Early termination and replacing a supplier should be handled by people with procurement or contract authority. In this question, the project manager first brings in the procurement department.

Variation If the question asks what to do about work already done after termination, work completed and accepted is paid as agreed, and whether the seller's preparatory work is compensated depends on the reason for termination and the contract terms. If you are unsure whether there is a right to terminate, check the contract's termination clause first.

Something wrong with this question?

Report an issue with this question

Common traps

Common trap

  • A contract reaching its end date does not mean it can be closed. Common exam practice: first check that the work has been delivered and accepted and the amounts due have been paid. You must also settle any open claims, guarantees, warranties and disputes under the contract and confirm that all contractual obligations have been met.
  • When you find a defect, handle the final payment under the contract's acceptance and payment terms. As the contract provides, you may use measures such as retention, withholding the related payments, requiring a fix, warranty or a claim. Paying the final payment does not automatically end warranty and claim rights that survive under the contract.
  • Fixing defects is already the supplier's obligation under the original contract. Do not sign a new contract or pay extra for it.
  • After early termination, work that has been completed and accepted is paid as agreed. On termination for convenience, or where the contract says otherwise, the seller's reasonable preparatory work is compensated as agreed. Termination for the seller's breach does not automatically compensate the seller; on termination for the buyer's breach, the seller may claim compensation under the contract and the law.
  • Archive the procurement documentation in full and put lessons learned in the repository; do not keep only the contract.

Key takeaways

Key point

  • Closing out a contract: first check that everything was delivered and accepted and that amounts due are paid, then settle open claims, guarantees, warranties and disputes under the contract and confirm that all contractual obligations have been met. The contract administrator notifies the seller in writing.
  • Order: usually confirm formal acceptance first, then complete payment and any necessary approvals under the contract, and finally close formally; the contract terms and organizational governance decide the details. If a defect is not fixed, have the seller fix it as the contract provides before closing.
  • Three situations of early termination (common exam practice): mutual agreement, one party's breach, and the buyer's convenience (the contract must provide for it).
  • After termination: work that has been completed and accepted is paid for; on termination for convenience or where the contract says so, reasonable preparation costs are compensated; termination for the seller's breach does not automatically compensate (on termination for the buyer's breach, the seller may claim compensation under the contract and the law); a termination by agreement follows the termination agreement.
  • Termination and replacing a supplier: the project manager first verifies the contract terms and authority, then has authorized procurement, legal or management staff get involved under the governance arrangements (common exam practice: when the question asks what to do "first" and "involve the procurement department" is an option, it is often chosen; if "check the contract's termination clause" is also an option, check the contract first; whether this applies depends on the stem). Archive the procurement documentation and put lessons learned into the knowledge repository.

This chapter has 58 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.