What this chapter covers
This is where the agile topic starts. This chapter answers four questions: why some projects do not suit a predictive approach, how to choose a development approach, what agile actually stands for, and how to use an agile mindset to judge scenario questions. In this course's agile topic, later practices such as Scrum, Kanban and extreme programming are examined in relation to the values and twelve principles of the Agile Manifesto, so this chapter is the root of the whole topic.
The source text is short, but it can be applied flexibly on the exam. You need to know the wording of the four values and twelve principles precisely, and, even more, be able to apply them to scenarios such as "the team is worn out", "the customer's feedback contradicts itself" and "the team does not understand agile". On the exam, this chapter appears mostly as scenario questions.
Lessons in this chapter
- Lesson 1: The definition of agile and the four values. The weaknesses of the predictive approach, how to choose among the three approaches, agile as a mindset, and the four values: "the items on the left over the items on the right, and the items on the right still have value".
- Lesson 2: The twelve principles (part 1): customer value and continuous delivery. Principles 1, 2, 3 and 7: continuous and early delivery of value, welcoming change, short cycles, and working software as the primary measure of progress.
- Lesson 3: The twelve principles (part 2): teams, communication, sustainable pace and simplicity. Principles 4, 5, 6, 11 and 12, then 8, 9 and 10: working together daily, trust and self-organization, face-to-face conversation, regular reflection; sustainability, technical excellence and simplicity.
- Lesson 4: The agile mindset: judging scenario questions with the values and principles. The twelve principles grouped by theme, five test questions, and three frequent scenarios: contradictory feedback, introducing agile, and facing doubt.
How to study this chapter
A suggested order: read Lesson 1 first and get the four values, and the point that the items on the right still have value, exactly right. In Lessons 2 and 3, learn the twelve principles by theme. You need not memorize them word for word, but know principles 1, 2, 7 and 8 well. After Lesson 4, go back to the scenario questions. For each one, first decide whether the approach is predictive, adaptive or hybrid, and then filter the options with the five questions. Do the core questions first, and for each mistake, reread the matching principle.
Chapter map
Predictive ─ lots of up-front planning, controlled change (value appears late in a single delivery, though incremental delivery is possible) ┐
Adaptive ─ iterative / incremental ├─ choosing an approach: clarity of requirements, uncertainty, complexity
Hybrid ─ choose per kind of work ┘
Agile = a mindset (the Agile Manifesto)
- Four values: individuals and interactions / working software / customer collaboration / responding to change
- Twelve principles
- Delivering value: 1 · 3
- Embracing change: 2
- Collaboration and communication: 4 · 6
- The team: 5 · 11 · 12
- Pace and progress: 7 · 8
- Quality and simplicity: 9 · 10
Scenario questions: decide predictive or agile → value-driven / transparency / servant leadership / the team solves it itself / change goes to the backlog
For practice on this chapter, use the chapter exercises, core questions first and then the required ones.
Lesson 1
The Definition of Agile and the Four Values
Lesson overview
This is the first lesson of the agile topic. It answers two questions: why some projects do not suit a predictive approach, and what agile actually stands for. Agile and hybrid questions together make up a large share of the exam, but the core ideas of agile follow the values and principles of the Agile Manifesto, so this lesson starts with the four values. It first covers the weaknesses of the predictive approach and how to choose among the three development approaches, then the definition of agile, and finally the four values one by one. The next lesson covers the principles that concern customer value.
Weaknesses of the predictive approach
A predictive approach may also be referred to as a waterfall, plan-driven, or traditional approach. It suits projects whose requirements are clear and stable early on: scope, schedule, cost, resources, quality and risks can all be well defined in the early phases of the life cycle and are expected to remain relatively stable. Then you detail the plan first and execute it, which usually gives more certainty and higher delivery efficiency.
When requirements are unstable and the environment is uncertain, the weaknesses show. Most requirements must be defined and elaborated early so that scope stabilizes early and a baseline is set. Once the baseline exists, changes to requirements that affect it are managed through the Assess and Implement Changes process (before a baseline is set, planning can elaborate and adjust directly). With insufficient tailoring, the up-front documentation and status reporting can be heavy and the feedback cycle long. With a single large delivery and no intermediate validation, value appears late and problems of direction surface late (a predictive approach does not itself require waiting until the end of the project to deliver; it can deliver in phases or increments). And it is hard to respond flexibly to changes in the market.
The most basic problem of a single-delivery predictive project is that value appears too late. Such projects are used to tracking progress by milestones: requirements analysis done, high-level design done, code written. But reaching a milestone is not the same as delivering value. The users still have nothing usable in their hands, and the first time they touch the product is at final delivery. If it then turns out that the direction was wrong, or the market has long since moved, the earlier investment may be wasted.
How to choose among the three approaches
A development approach is the means used to create and evolve the product, service or result during the project life cycle. The three in common use are predictive, adaptive and hybrid, which you can see as a spectrum: predictive at one end, adaptive at the other, hybrid in between. The project manager and project management team choose after evaluating the requirements, scope, timeline and objectives, the organization's culture and needs, the degree of stakeholder involvement, the risk profile, technical factors, and overall complexity. If requirements are clear and stable, predictive may be best. If requirements are less clear, complexity and uncertainty are higher and more feedback is needed, adaptive may be best. If both conditions are present, use hybrid.
Adaptive approaches are also called change-driven. A clear vision is established first, and the initial known requirements are then progressively elaborated, changed, or replaced in accordance with feedback, the environment or unexpected events. An adaptive approach can be iterative, refining and improving the result through repeated cycles; it can be incremental, delivering the final product in small, usable segments one at a time; and most of the time it is both.
Two situations for judging the approach
The sponsor of a community group-buying platform says from the start: we have not yet figured out how users behave, and our competitors launch new features every month. Uncertainty is high and change is frequent, so recommend an adaptive approach and deliver iteratively. Another project is replacing the shelving in a warehouse with a design that has been settled. The specification is clear and little will change, so a predictive approach is fine.
The definition of agile
The PMBOK 8 glossary defines agile as "a term used to describe a mindset of values and principles as set forth in the Manifesto for Agile Software Development." It is more abstract than any development framework, and agile approaches can be considered adaptive. The Agile Practice Guide describes agility as the ability to create and respond to change, a way of dealing with, and ultimately succeeding in, an uncertain and turbulent environment. The two statements do not conflict. For the exam, follow PMBOK 8: agile is first of all a mindset, and Scrum, Kanban and extreme programming are concrete methods for putting that mindset into practice.
Agile is closely linked to lean thinking. It takes in ideas such as focusing on value, reducing waste and delivering in small batches, and it also inherits practices from several iterative and incremental development methods: get the most value for the least cost and eliminate waste. This leads to three recurring claims. Do the most valuable thing first with a small investment. Experiment quickly: test the riskiest assumption first, continue if it holds, and cut your losses early if it does not. Put people first and let the team use its own intelligence to solve complex problems.
The four values
In 2001, seventeen software developers got together. They did not agree on specific methods, but they reached a consensus on ideas, and they published the Agile Manifesto. The four values all have exactly the same structure, "the item on the left over the item on the right":
| Left item (valued more) | Right item (still has value) | One-line memory aid |
|---|---|---|
| Individuals and interactions | Processes and tools | People first |
| Working software | Comprehensive documentation | Results first |
| Customer collaboration | Contract negotiation | Foster collaboration |
| Responding to change | Following a plan | Embrace change |
The Manifesto also adds a sentence: "That is, while there is value in the items on the right, we value the items on the left more." So "over" does not mean "instead of": processes, documents, contracts and plans are not all thrown out. Keep them as the project needs them. When they conflict, protect the item on the left first.
Using the four values to judge
Treat each value as the answer to a "conflict scenario", and questions become easy to judge:
- The team and the users disagree about the interface and are deadlocked: rely on customer collaboration. Let the users try it and give feedback, rather than settling who is right with a specification or by negotiation.
- Someone insists that all designs must be documented before work can begin: working software comes first, and documentation should be just enough for the team's actual needs. But a document the customer explicitly wants, or that is really needed, must still be written. Treat it as a work item in the backlog or workflow, order it by value, risk and necessity, and schedule it.
- Team members complain in a meeting that the tools are awkward and the process too heavy: individuals and interactions come first. Listen to people first, then adjust the process and tools, rather than making people adapt to the tools.
- The market changes halfway through: respond to change. Write the new requirement into the backlog and reprioritize, rather than clinging to the original plan.
When the team argues about whether to write a design document, the right thing is to explain the Manifesto to the team: working software comes first, but valuable documentation must still be written, especially in complex systems.
Worked examples
Example 1: Customer and users are deadlocked: which value applies?
An agile team is developing an order management system for a logistics company, and the company's warehouse administrators will use it daily after delivery. During an iteration, the team wants to deliver the streamlined entry screen defined in the signed specification in the contract appendix. The administrator, on the customer's side, insists on keeping the original multi-level menus. The two sides are deadlocked over the contract terms and development cannot move forward. To resolve the standoff between team and customer, which value in the Manifesto should the team rely on MOST?
Show answer and explanation
Correct answer: D
During iterative development, the team and the end user (a warehouse administrator on the customer's side) disagree about the entry screen. The team wants to deliver to the specification in the contract appendix, and the two sides are deadlocked over the contract terms until development stalls. The question asks which value in the Manifesto should be used to resolve it.
First find the signal: the deadlocked parties are the team and the user, and the disagreement is about what the screen should look like, not a dispute about documents or process. The team wants to follow the signed specification while the user wants the original menus, so what has to be resolved is the standoff between the contract terms and the user's current needs. A disagreement like this cannot be settled by arguing over clauses. Let the user try it and give feedback, and you can find a solution both accept. This corresponds to “customer collaboration over contract negotiation”: keep collaborating with the customer rather than haggling over terms. The answer is D.
Why the other options are wrong
- A. “Working software over comprehensive documentation” addresses a contest between documents and software. Nobody in this question is asking for documents first.
- B. “Individuals and interactions over processes and tools” addresses processes or tools that get in the way of people communicating. The problem here is not process or tools, and it is not poor communication within the team. It is that the team and the user on the customer's side see the product's form differently, which is resolved by involving the customer, letting them try it and give feedback, and that is customer collaboration.
- C. The administrator's current preference differs from the signed specification, so the stem does contain a change signal. However, the question expressly asks how to resolve a team-customer standoff centered on contract terms, which maps most directly to “customer collaboration over contract negotiation”. “Responding to change over following a plan” does not address that collaboration-versus-contract conflict as directly.
Key takeaway When the team and users disagree about the form of the product, rely on customer collaboration: let users try it and give feedback, not argue from the specification or negotiate.
Variation If the customer raises a new feature midway and the team wants to finish the original plan first, that corresponds to “responding to change over following a plan”. If the team wants to spend a month writing the design documents before coding, that corresponds to “working software over comprehensive documentation”.
Something wrong with this question?
Example 2: The customer really wants documentation: how do you write it and still protect value?
The customer raises a new requirement: a detailed interface specification document must be provided before delivery. After checking, the agile team confirms the document is really necessary. What should the team do?
Show answer and explanation
Correct answer: A
The project uses an agile approach, and the customer adds a requirement for a detailed interface document. The team checks and confirms it is really necessary. In an agile setting, the team must meet this requirement without giving up agile practice.
The key is the closing sentence of the Manifesto: while there is value in the items on the right, we value the items on the left more. “Working software over comprehensive documentation” is a ranking, not a ban on documents. Since the document is really necessary, the team should treat writing it as work and schedule it into an iteration, while still delivering value to the customer. That respects customer collaboration and does not depart from agile priorities. The answer is A.
Why the other options are wrong
- B. Switching to a predictive approach for the rest of the project over one document is out of proportion. The development approach is chosen by the nature of the project and is not switched at will for one requirement.
- C. Treating “agile means no documents” as a principle is a classic misreading of the Manifesto, and refusing a really necessary requirement also goes against customer collaboration.
- D. The stem has already confirmed that the document is required and must be detailed. Keeping only a minimal note fails to meet the requirement, and it mistakes “value more” for “only the left item”.
Key takeaway In the Manifesto the items on the right also have value: a document that is really necessary is written and scheduled into an iteration, but not at the expense of delivering value.
Variation If the stem were changed to “the team thinks the document is unnecessary but the customer asks for it”, the answer is still to talk with the customer first, understand the real need, and then decide how much to write. If it were changed to “the team wants to finish all the design documents before coding”, that would go against working software first.
Something wrong with this question?
Common traps
Common trap
- Agile does not mean no plans and no documentation: the items on the right also have value, but the items on the left come first.
- Hybrid does not have to be a 50/50 compromise. It combines predictive and adaptive elements in a way suited to the work, for example by deliverable, phase, workstream, or throughout the life cycle.
- Agile does not guarantee lower risk or lower cost. The main reason to adopt agile is to deliver value early and continuously.
- When the customer explicitly requires a document and it is really needed, you neither refuse nor switch to a predictive approach. You add it as a work item to the backlog or workflow, order it by necessity, and schedule it.
Two statements
- Agile Practice Guide: agility is the ability to create and respond to change in order to succeed in an uncertain and turbulent environment.
- PMBOK 8: agile is a mindset of values and principles as set forth in the Manifesto for Agile Software Development, broader than any one development framework.
Key takeaways
- Use predictive when requirements are clear and stable, adaptive when there is uncertainty and a need for feedback, and hybrid when both are present. Agile approaches are adaptive.
- The weaknesses of a single-delivery predictive project are that value appears too late and that change after the baseline must go through the formal change process.
- Agile is a mindset. Scrum, Kanban and extreme programming are methods for putting it into practice.
- The four values: individuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; responding to change over following a plan.
- "Over" does not mean "instead of". The items on the right also have value, and when they conflict you protect the left item first.
Lesson 2
The Twelve Principles (Part 1): Customer Value and Continuous Delivery
Lesson overview
The four values give the direction; the twelve principles bring them down to everyday practice. This lesson covers the four that center on customer value: principle 1 (continuous, early delivery), principle 2 (welcome change), principle 3 (short cycles) and principle 7 (working software is the primary measure of progress). These are the core of the whole set. Questions often ask "what should you focus on first", "how do you reassure stakeholders" or "how do you explain the benefits to management", and the answer usually lies here. The next lesson covers the principles on teams, communication and sustainability.
Principle 1: Deliver value continuously and early
The text reads: "Our highest priority is to satisfy the customer through early and continuous delivery of valuable software." Each of the three key words carries weight. "Continuous": value is not delivered all at once. Every iteration should produce a usable, potentially releasable increment, and delivery should be frequent, at a rhythm that suits the product and the customer. "Early": the earlier you deliver, the earlier the feedback, and the earlier you can correct a wrong direction. "Value": reaching a milestone is not itself delivering value. Only results and benefits the customer can really use count.
Furnishing a home is a good analogy. The predictive way is to do all the construction and finishing work first, then buy the furniture, then install the appliances, and you can move in only when the last step is done. The agile way is to put in a bed you can sleep on first, which gives value the same day, then add the water heater and the kitchen, layer by layer. First make something usable available; then make it better. Early delivery has another benefit: customers know whether something is what they wanted only when they can see it, and the earlier the feedback, the less the rework.
Agile also rests on a plain observation: some of the features in a product create most of the value, and others are rarely used. So teams generally do the higher-value items first (while also weighing dependencies, risks and constraints), put low-value items later, or do not do them at all. This is also why agile's first goal is value, not faster or cheaper, or just "finishing on plan". When you explain the benefits of agile to stakeholders, focus on "continuously delivering high-value increments and getting feedback early". That is far safer than talking about "cheaper" or "faster".
Principle 2: Welcome change
The text reads: "Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage." Predictive and adaptive approaches handle change differently:
| Predictive | Adaptive | |
|---|---|---|
| How change is handled | Assess the impact, submit and record a change request, and have it reviewed by the designated approver under the change management plan (with the change control board where applicable); if approved, update the plans, relevant documents and change log, notify the affected stakeholders, and then implement it | Conduct a proportionate impact analysis, write it as an item, put it in the backlog and reprioritize accordingly |
| Current work | Continue on the approved baseline | Do not lengthen the iteration or endanger its goal; as more is learned, its scope may be clarified and renegotiated with the Product Owner, otherwise select the item in a later iteration |
| Fate of a low-priority change | Goes through formal change control and, after impact analysis, is approved, deferred or rejected | Is deferred, or may never be reached |
PMBOK 8 also says that adaptive approaches generally have no formal "approval" process, and a lower priority means the change is deferred. So on an agile project, when a customer raises a new requirement in the middle of an iteration, you should neither flatly refuse it, nor generally ask the customer to sign a separate change document (unless the contract, regulations or project governance say otherwise), nor lengthen the iteration to fit it. The right approach is to assess its impact and write it into the backlog. The backlog owner (the Product Owner in Scrum) decides its order with regard to value, impact, dependencies and constraints.
Principle 3: Short cycles, frequent delivery
The text reads: "Deliver working software frequently, from a couple of weeks to a couple of months, with a preference to the shorter timescale." In Scrum this cycle is the Sprint, a fixed-length event of one month or less. The shorter the cycle, the faster the feedback, the earlier a wrong direction is corrected, and the faster the risk converges.
Principle 7: Working software is the primary measure of progress
"Working software is the primary measure of progress." To measure progress, do not look at how many documents were written, how many lines of code, or how many hours were spent, but at whether what was built can be used. Only when the bed you can sleep on is built does progress exist; if a lot of preparation was done but nothing can be used, progress is close to zero. Teams often use velocity to assess their output. Velocity measures the amount of work the team produces and has accepted in each iteration, and it likewise counts only finished, usable items; when story points are used for estimating, it can be expressed as the sum of the story points of the items completed in that iteration.
This principle directly gives the way to rebuild confidence. When stakeholders doubt whether the team can finish on time, explaining the benefits of self-organization ten thousand times is not as good as showing, at the end of every iteration, software with more complete functionality that really works. With results in front of them, the doubts fade.
Getting the customer to say "this is what I wanted"
A bakery chain asks a team to build a loyalty mini-app. The client keeps saying "the features are not what I wanted," and the team's reaction is to write the requirements specification in more and more detail. A more principled approach is to produce a small piece that runs in every iteration, for example launching scan-to-earn points first and asking the store manager to try it in the store, aligning requirements with real software rather than piling up more text. After the first iteration the manager says "points should be redeemable for cash." That feedback goes into the backlog and is scheduled into the second iteration.
Worked examples
Example 1: What should an agile team focus on first?
A project manager has just taken over an agile project to develop a membership app for a retail chain, and the requirements list has been compiled. What should the project manager remind the team to focus on FIRST?
Show answer and explanation
Correct answer: B
The project manager has just taken over an agile project, and the requirements list has been compiled. The question asks what to remind the team to focus on first, so you must identify the highest goal of an agile project.
The first of the twelve principles reads: our highest priority is to satisfy the customer through early and continuous delivery of valuable software. So what an agile team focuses on first is providing value to the customer, and cost, schedule and teamwork are considerations that serve that goal. The fact that the requirements list is already compiled is only a starting point and does not change the ordering. The answer is B.
Why the other options are wrong
- A. Lowering cost deserves attention, but agile does not make minimizing cost its highest goal, and adopting agile does not guarantee lower cost.
- C. Finishing on time deserves attention, but in agile, schedule is derived from priorities and team velocity and is not defended as a rigid baseline. Besides, working software is the measure of progress.
- D. Cooperation within the team is a means to achieve value, not the goal itself. Treating a means as the goal is a common switch.
Key takeaway The first goal of agile is to deliver value to the customer. When asked what to focus on “first”, think customer value first.
Variation If the question asks about the main benefit of agile to explain to stakeholders, the answer likewise lands on delivering high-value increments early and continuously, not lower cost or higher speed.
Something wrong with this question?
Example 2: How do you restore the confidence of a manager who doubts progress?
An agile team at a consulting firm is overhauling the procurement approval system for a manufacturer. Midway through the project, two department heads at the manufacturer doubt whether the team can finish on time. What is the MOST effective way to rebuild their confidence?
Show answer and explanation
Correct answer: A
Midway through the project, two department heads doubt whether the team can finish on time. The question asks what most effectively rebuilds their confidence.
Agile principle 7 is: working software is the primary measure of progress. Stakeholders' confidence comes from results they can see and touch. Delivering working software with more complete functionality at the end of every iteration is the most persuasive evidence there is, more effective than any explanation. The answer is A.
Why the other options are wrong
- B. More communication meetings add information, but they produce no new results, so the root of the doubt, whether it can be finished, goes unanswered.
- C. Self-organization is the team's way of working, not a result the stakeholders care about. Stressing the way of working cannot replace results.
- D. Agile calls for problems to be surfaced early and transparently, not for fewer problems to be shown. Deliberately showing fewer problems damages trust and goes against transparency.
Key takeaway The most powerful way to reassure stakeholders is to keep delivering working software every iteration.
Variation If the stem were changed to “stakeholders want to know progress at any time”, the answer shifts to information radiators (task boards, burndown charts). If it asked how to measure progress, the answer is still working software, not the number of documents or hours.
Something wrong with this question?
Common traps
Common trap
- The benefit of adopting agile is that value is delivered earlier. It does not guarantee lower cost, and it does not make the team more capable in itself.
- While an iteration is under way, do not refuse all new requirements, do not ask the customer to sign change documents, and certainly do not lengthen the iteration. New requirements go into the backlog.
- "Progress" is measured by working software, not by the number of documents, lines of code or hours.
- Teamwork and self-organization are means, not agile's highest goal. The highest goal is customer value.
Key takeaways
- Principle 1: "Our highest priority is to satisfy the customer through early and continuous delivery of valuable software."
- Principle 2: "Welcome changing requirements, even late in development." Change goes into the backlog and is reprioritized by value, and generally does not go through the predictive-style change control board approval (unless project governance says otherwise).
- Principle 3: "Deliver working software frequently, from a couple of weeks to a couple of months, with a preference to the shorter timescale." In Scrum, a Sprint is one month or less.
- Principle 7: "Working software is the primary measure of progress." Confidence is rebuilt with results, not with explanations or meetings.
- Question cues: if it asks what to focus on "first", choose customer value; if it asks how to reassure people, choose delivering working software.
Lesson 3
The Twelve Principles (Part 2): Teams, Communication, Sustainable Pace and Simplicity
Lesson overview
Besides the customer value covered in the last lesson, the other eight of the twelve principles are about how people collaborate, how the pace is kept and how to show restraint in the work. Principles 4, 5, 6, 11 and 12 cover teams and communication, and principles 8, 9 and 10 cover sustainability, technical excellence and simplicity. Their wording is very short, but exam questions often present them as scenarios, such as a worn-out team, a lost link to the customer, or a team that wants a set of rules of behavior. This lesson goes through each principle's text, meaning and typical practice. The next lesson groups the twelve by theme and covers how to judge scenario questions.
Teams and communication: principles 4, 5, 6, 11 and 12
Principle 4: "Business people and developers must work together daily throughout the project." Business direction enters the team's daily life directly, which echoes the Scrum Product Owner's role of continuously clarifying product direction, ordering the product backlog and facilitating collaboration. A typical scenario: contact between the team and the customer has lapsed for a while, and what was built differs from what the customer wanted. The first thing the project manager should do is restore direct, frequent contact with the customer, not write more documents or meeting minutes.
Principle 5: "Build projects around motivated individuals. Give them the environment and support they need, and trust them to get the job done." In Scrum, this principle can be seen in the Scrum Master's servant leadership, coaching and impediment removal. A coach is not a commander but someone who releases the team's potential. Team performance is roughly potential minus interference, so do two things: bring out the potential and clear away the interference. Morale is maintained mainly through trust, empowerment and support, not by adding pressure, close monitoring or relying on bonuses alone, and recognition and rewards should be tailored to members' motivations and cultural backgrounds.
Principle 6: "The most efficient and effective method of conveying information to and within a development team is face-to-face conversation." Face to face, you get facial expressions, gestures and tone at the same time, and the information content is greatest. So if a team habitually uses instant messages for requirements and often misunderstands, encourage face-to-face talk; if members are in different places, replace it with a high-bandwidth method such as video conferencing. With new team members or a dispute over requirements, sitting down together is far faster than forwarding documents back and forth.
Principle 11: "The best architectures, requirements, and designs emerge from self-organizing teams." A self-organizing team leads itself, has the resources it needs to do the work, has the cross-functional capability to do it as a whole, and its members take on leadership as needed. The manager's role changes from assigning tasks to motivating and serving. For example, when a team says it wants a set of rules of behavior, the team should write them itself, rather than the lead applying another project's rules.
Principle 12: "At regular intervals, the team reflects on how to become more effective, then tunes and adjusts its behavior accordingly." This corresponds to the retrospective in Scrum. PMBOK 8 says a retrospective is a form of lessons learned meeting, held at a minimum at the end of each iteration. The team puts the improvements raised in a retrospective into practice itself and checks the effect in later retrospectives.
Pace and restraint: principles 8, 9 and 10
Principle 8: "Agile processes promote sustainable development. The sponsors, developers, and users should be able to maintain a constant pace indefinitely." Agile does not get speed from overtime. How much a team can finish in an iteration depends on available hours, skills, work complexity, dependencies and impediments, and a stable team can estimate how much it can finish next iteration from the actual velocity of earlier iterations (velocity still varies as these factors change). So agile often fixes the timebox and the team and flexes the scope within those constraints: put in the highest-priority content first and return whatever does not fit to the backlog. Predictive approaches usually set the scope, schedule and cost baselines early and manage adjustments through change control.
When a team has worked flat out for several iterations in a row and is visibly tired, the Scrum Master's best move is to work with the team to bring the pace back to a level it can sustain over the long term. The first measure is to correct the overcommitment and restore a sustainable pace. "Hold on for a few more iterations" is not acceptable, since continuing to overdraw only drags down quality and output. Adding people or meetings should be considered only when there is a real long-term need and after the cost of integration and the hours it takes have been evaluated; they must not be used to sustain constant overload (exam tip: when the stem says only that the team is worn out, choose bringing the pace back).
Principle 9: "Continuous attention to technical excellence and good design enhances agility." Related to this is technical debt: to meet a deadline, a compromise is made where the best solution should have been used, buying short-term speed at an extra cost later. Common consequences are more failures, delivery delays, more defects and lower customer satisfaction. The way to manage it is to make it visible: put paying down technical debt in the product backlog, then decide whether to pay it down at once or in installments. Invisible debt cannot be prioritized or paid off.
Principle 10: "Simplicity--the art of maximizing the amount of work not done--is essential." Simplicity means maximizing the amount of unnecessary work not done. One application is testing the riskiest assumption with the smallest useful experiment. Someone who wanted to check whether "shoes can be sold online" did not open a shop and buy stock. They photographed shoes in nearby stores and posted them online, and bought the shoes only when someone placed an order. This kind of low-cost validation is one application of simplicity, and the idea behind the minimum viable product in the next chapter. Documentation works the same way: enough for the team, neither "not at all" nor "the more detailed the better".
How to use this: treat the principles as an "option filter"
The behaviors that go with these eight principles are quite fixed, so you can use them directly to filter options in a question:
| What appears in the question | The preferred practice |
|---|---|
| Little contact with the customer, results that differ | Business people and the team work together daily (principle 4) |
| Low morale, a tense team | Trust, empowerment and support (principle 5) |
| Many misunderstandings in communication | Face-to-face or video conversation (principle 6) |
| The team wants rules or a solution | The team decides itself (principle 11) |
| The same problem keeps recurring | Improve in the retrospective (principle 12) |
| Constant overtime, exhaustion | Return to a sustainable pace (principle 8) |
| Falling quality, a lot of rework | Technical excellence, paying down technical debt (principle 9) |
| Wanting to test an idea and reduce waste | Simplicity: do the smallest test first (principle 10) |
An iteration where the pace got out of control
On an internal system project for a pharmacy chain, the team has worked overtime every day for five iterations in a row, and the number of defects is rising rather than falling. The Scrum Master does not suggest that the team keep relying on overtime, and does not ask for another tester. Instead, in the retrospective, the Scrum Master looks at the data with the team: each iteration the team actually completes about 30 story points but has been given 40. So the Developers, referring to historical velocity, adjust the work selected for the next iteration to about 30 story points and plan around the Sprint Goal, and put the surplus items back in the backlog. The pace returns to a sustainable level.
Worked examples
Example 1: The customer cannot state requirements clearly: how do you make sure of final satisfaction?
A project manager at PMLyceum has just taken over a newly formed team and is doing agile release planning for an internal expense-reimbursement app. The customer representative knows little about the technical details and can give only very general feature requirements. To make sure the customer is satisfied with the final product, what should the project manager do?
Show answer and explanation
Correct answer: C
A newly formed team is doing agile release planning, and the customer representative knows little about the technology and describes requirements only in general terms. The question asks how to make sure the customer is satisfied with the final product.
Two signals: the customer cannot state the requirements clearly, and wants to be satisfied in the end. The Manifesto values customer collaboration over contract negotiation, and principle 4 requires business people and developers to work together daily. The most effective way is to have the customer representative take part continuously in every iteration: at the iteration review and in daily exchanges they keep seeing results and giving feedback, the requirements become clearer through that feedback, increasing the likelihood of customer satisfaction. The answer is C.
Why the other options are wrong
- A. Having the customer hire a technical consultant to turn requirements into specifications pushes the responsibility back to the customer, slows the start, and does not address the root of the communication gap.
- B. Scheduling extra features on your own to “make up” for general requirements is guessing. The extra features have no value basis, they add waste, and satisfaction is not assured.
- D. Spelling out acceptance requirements item by item in the contract is “contract negotiation over customer collaboration”. The customer cannot state requirements clearly in the first place, so the terms could not be written in detail anyway.
Key takeaway Customer satisfaction comes from continuous involvement and feedback, not from contract terms and not from adding features.
Variation If the stem were changed to “contact between the team and customer broke off for a while and what was built does not match”, the answer is to restore direct, frequent communication with the customer first, on the same basis, principle 4.
Something wrong with this question?
Example 2: The team keeps rushing: what the Scrum Master does
An ordering system project for a retailer uses Scrum, and the team has worked flat out for five Sprints in a row, with members visibly tired. What is the Scrum Master's BEST course of action?
Show answer and explanation
Correct answer: A
On a project using Scrum, the team has worked flat out for five Sprints in a row and members are visibly tired. The question asks for the Scrum Master's best course of action.
The signals are “flat out in a row” and “visibly tired”, which point to principle 8: agile processes promote sustainable development, and the sponsors, developers and users should be able to maintain a constant pace indefinitely. How much work the team can finish is forecast from past performance, current capacity, work complexity, dependencies and impediments, and continuing to overdraw only hurts quality and output. The Scrum Master should work with the team to adjust the pace to a level it can sustain over the long term. The answer is A.
Why the other options are wrong
- B. The stem does not say resources are short. Adding people at short notice does not fix chronic overdrawing, and new people take time to integrate, which slows things down in the short term.
- C. The Daily Scrum is a 15-minute event whose purpose is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary. Lengthening the event violates its timebox; difficulties needing deeper discussion can be addressed afterward.
- D. Asking the team to hold on for a few more Sprints is continuing to overdraw, which goes against sustainable development. Once fatigue builds up, quality and output both decline.
Key takeaway When a team is worn out, first adjust the pace back to a sustainable one. Do not add people or meetings or keep rushing.
Variation If the stem were changed to “overtime only in the last Sprint, occasionally”, you need not adjust the whole pace at once and can inspect it in the Sprint Retrospective. Once the pace is unsustainable, adjust promptly however many Sprints it has lasted.
Something wrong with this question?
Common traps
Common trap
- Agile does not relax quality and should not depend on constant overtime to rush work: principle 8 requires a sustainable pace and principle 9 requires technical excellence.
- When a team's technical approach is hard to scale and its retrospectives keep raising communication problems, empower the team to adjust itself and check the effect in later retrospectives, rather than taking over decisions or forcing a solution.
- When a team in transition lacks agile skills, assess the skills gap and provide appropriate training, coaching, pairing or self-study resources, so that the team really gets the capability it needs.
- Technical debt does not disappear because nobody mentions it. Paying it down goes into the backlog and is ordered along with the other items.
- Face to face does not mean "must be in the same office". Distributed teams use high-bandwidth means such as video conferencing.
Key takeaways
- Principle 4: business people and developers work together daily. If contact with the customer has lapsed, restore direct communication first.
- Principles 5 and 11: trust and support individuals, a self-organizing team decides for itself how to work, and team rules are set by the team itself.
- Principle 6: face-to-face conversation is the most efficient and effective, and distributed teams replace it with video conferencing.
- Principles 12 and 8: retrospectives drive continuous improvement, and the pace must be sustainable. When the team is worn out, first correct the overcommitment and restore a sustainable pace; do not rely on constant overtime or blindly add people, and evaluate adding people only if there is a real long-term need.
- Principles 9 and 10: pursue technical excellence and make technical debt visible; keep to simplicity and test the riskiest assumption at the lowest cost first.
Lesson 4
The Agile Mindset: Judging Scenario Questions with the Values and Principles
Lesson overview
Agile has few knowledge points, yet the exam has many scenario questions: the stem sets a scene and asks what the project manager or Scrum Master should do. These questions are not won by memorizing details but by a steady way of thinking. This lesson compresses the values and principles of the first three lessons into a workable judging process: first decide whether the question is about a predictive or an agile approach, then filter the options with five test questions, and finally look at three common scenarios: contradictory feedback, introducing agile, and resistance and doubt. By the end you should be able to eliminate half the options within 30 seconds.
The twelve principles by theme
You do not need to memorize the twelve principles word for word. Remember them by theme; the principle numbers are in parentheses:
| Theme | Key points |
|---|---|
| Delivering value | Our highest priority is to satisfy the customer through early and continuous delivery of valuable software (1); deliver working software frequently, preferring the shorter timescale (3) |
| Embracing change | Welcome changing requirements; agile processes harness change for the customer's competitive advantage (2) |
| Collaboration and communication | Business people and developers work together daily (4); face-to-face conversation is the most effective (6) |
| The team | Build projects around motivated individuals, with environment, support and trust (5); self-organizing teams (11); regular reflection (12) |
| Pace and progress | Working software is the primary measure of progress (7); sustainable development (8) |
| Quality and simplicity | Technical excellence and good design (9); simplicity (10) |
The five test questions
After reading a scenario question, first ask: is this predictive or adaptive? If it is adaptive, test each option with the five questions below:
- Is it value-driven? While respecting necessary dates and schedule constraints (a value proposition is usually time-sensitive), keep prioritizing work by value and adjust the plan based on feedback.
- Is it transparent? Problems and progress are visible to everyone, and information radiators (task boards, burndown charts) replace layers of status reports.
- Is it servant leadership? In adaptive environments, servant, coaching-style leadership that empowers self-managing teams is usually preferred: you facilitate the team rather than command, assign or decide everything for it. The project manager should still choose a leadership style that fits the situation, authority and urgency. A Scrum Master and a project manager are different roles.
- Does the team solve it itself? For problems inside the team, let the team work out its own solution first, with the coach guiding rather than taking over.
- Does change go through the backlog? A purely adaptive project usually manages change through the backlog, without formal change requests or a change control board, and does not ask the customer to sign change documents. For hybrid projects, and wherever the contract, compliance or governance require it, the agreed change control mechanism still applies. A new requirement normally goes into the backlog first, and you do not casually add work that endangers the Sprint Goal (in Scrum, where necessary, the current scope can be renegotiated with the Product Owner without endangering the Sprint Goal, and when the Sprint Goal becomes obsolete, the Product Owner can cancel the Sprint).
Exam tip: options containing wording such as "report to a superior", "reassign", "bring in outsiders", "require the team to", "pause the iteration" or "write more detailed documents" are mostly wrong in agile scenario questions, while options with "communicate", "clarify", "let the team discuss", "order by value" or "let stakeholders see" are mostly right. This is a tendency on the exam, so judge it against the stem. Reporting upward merely to shift responsibility is usually not the first choice, but when a problem exceeds the team's authority, reaches the escalation threshold set in the communications management plan, or involves governance and compliance, escalating promptly is exactly the right thing.
Three frequent scenarios
Scenario 1: contradictory feedback. Before the iteration starts, the team builds a prototype, and the customer gives a pile of mutually contradictory comments. Some members argue for starting the iteration right away; others want to review the prototype with management first and then go back to the customer. The contradictions show the requirements are not yet clear, and the right approach is to talk with the customer in depth, clarify the requirements, and prioritize by value. Do not treat it as a risk to analyze qualitatively and quantitatively, do not go through a change request, and do not finish building to the original design first and then go back to the customer; that only produces more rework.
Scenario 2: the team has no agile experience and agile is to be introduced. First let the team understand the values and principles of agile, that is, train them, and only afterward talk about specific practices such as the daily coordination meeting and iterations. Starting meetings first, collecting requirements first, or first "balancing theory and practice" are none of them the first step. If people do not buy into the practices, the ceremonies become empty.
Scenario 3: someone doubts or will not cooperate. Some members feel certain agile ceremonies are unnecessary, senior leaders want the whole company to use agile, or some organizational processes add no value. First understand the person's specific concerns and their causes; then explain the values and principles behind the practices and tailor accordingly. When processes conflict, weigh customer value, governance and compliance requirements together, tailor processes that add no value within your authority, and negotiate or escalate those you cannot bypass yourself. When senior leaders want a blanket rollout, first understand their goals and concerns, then suggest piloting on suitable projects and expanding once it succeeds. Do not copy rashly, and do not refuse flatly.
Transparency and information radiators
In agile, "transparency" means that progress, problems, risks and decisions are visible to the people concerned at any time, not relayed by a few people. The usual carrier is the information radiator, such as a task board, a burndown chart or a velocity chart, placed where the team can see it. Digital tools such as a shared online board can also provide similar transparency. Stakeholders can check progress promptly through information radiators; if the communications management plan or governance mechanism requires formal reports, you still provide them as agreed.
A typical "choose by the agile mindset" question
An old textile mill wants to digitize its production, and the project manager is asked to introduce agile on the new project, but nobody on the team has done it before. The project manager's list of choices: gather everyone to explain the agile principles (training), schedule the daily coordination meeting first, hold a meeting on "the balance point between theory and practice", or have the Product Owner collect requirements first. Using the thread "first let the team understand the values", the answer is the first item. The other three are later steps, not the first.
Worked examples
Example 1: The customer's feedback contradicts itself: what do you do first?
Before an iteration begins, an agile team builds a prototype of a feature. After seeing it, the customer gives a large amount of mutually contradictory feedback, and the team discusses it. Some members argue for starting this iteration right away. Others want to review the prototype with management first and only then go back to the customer. What should the team do?
Show answer and explanation
Correct answer: C
On an adaptive project, the team built a prototype before the iteration started and the customer's feedback was heavily contradictory. The team itself disagrees about whether to start the iteration and review with management first. The question asks what the team should do.
“Contradictory feedback” shows that the requirements have not yet been clarified, not that the plan has changed. Adaptive projects resolve this by frequent communication: talk with the customer in depth, find out what is really needed, then set priorities by value and run the iteration on that basis. This reflects value-driven work and customer collaboration. The answer is C.
Why the other options are wrong
- A. Treating the contradictory comments as a risk to analyze qualitatively and quantitatively is the wrong direction. When requirements are unclear, what is needed is communication and clarification.
- B. Submitting a change request and waiting for the customer's confirmation is how requirement changes are controlled against a baseline. Iterative work adjusts requirements through the backlog and communication, and here the requirements were never settled in the first place.
- D. Finishing to the original design first and going back to the customer afterward means continuing to develop with the contradictions unresolved. Later rework will be greater, which goes against early feedback.
Key takeaway With contradictory feedback, communicate and clarify first, then order by value. Do not go through the change process and do not push on to hit the schedule.
Variation If the stem were changed to “during the iteration, the customer raises a new feature that does not conflict with the original requirements”, the answer is to write it into the product backlog for the Product Owner to order.
Something wrong with this question?
Example 2: The team has no agile experience: what do you do first?
An old textile mill plans to digitize its production and has set up a new project, asking the project manager to introduce an agile framework in it. Nobody on the team has ever developed in an agile way. What should the project manager do FIRST?
Show answer and explanation
Correct answer: A
A traditional textile mill's digitization project is to introduce an agile framework, and nobody on the team has used agile development. The question asks what the project manager does first.
The signal is “nobody has used agile”. If the team does not understand the values and principles of agile, going straight to practices tends to become mere form. So the first step is to bring everyone together and explain the agile principles, so that the team understands why things are done this way, and then specific practices such as the daily coordination meeting and iterations have a foundation. The answer is A.
Why the other options are wrong
- B. The daily coordination meeting is one of the practices for putting agile into effect. Holding it before the principles are understood leaves members unsure of its purpose, and it easily becomes a formal status report.
- C. Exploring the balance between theory and practice presupposes that the team already knows agile theory. For a team starting from zero, it is not the first step.
- D. Gathering the customer's requirements is work for the Product Owner later on, and it has nothing to do with the current obstacle that the team does not know agile.
Key takeaway To introduce agile, first have the team understand the principles, then talk about specific practices.
Variation If the stem were changed to “everyone has agile experience, but their ways of working differ”, the first step shifts to agreeing the team's working agreements (the team charter) and building a shared understanding.
Something wrong with this question?
Common traps
Common trap
- Agile's first goal is to deliver value to the customer, not to be faster or cheaper. When you explain the benefits to stakeholders, focus on continuously delivering high-value increments.
- Customer satisfaction comes mainly from continuous involvement and feedback. It cannot rest on contract terms alone, and it does not come from adding features (contracts and change agreements remain valid; they just cannot replace collaboration).
- An "agile coach" is not a manager but a servant. Do not choose "assign tasks to members" or "require the team to report status".
- In scenario questions, first check whether the stem is predictive or agile. In a predictive question, a change affecting an approved baseline goes through a change request under the agreed process, and whether it goes to the change control board and who approves it depend on the change management plan and authorizations. In a purely agile question, a formal change request and a change control board are mostly wrong (exam tip; where the approach is hybrid or the contract or governance requires otherwise, follow the agreed mechanism).
- When a team has no agile experience, introducing agile should start by helping the team understand the principles, not by immediately applying all the ceremonies of a framework; the specific steps still need tailoring to the context.
Key takeaways
- Remember the twelve principles by theme: delivering value, embracing change, collaboration and communication, the team, pace and progress, quality and simplicity.
- The five questions for judging options: value-driven, transparent, servant leadership, the team solves it itself, change goes through the backlog.
- With contradictory feedback, communicate and clarify first, then order by value. Do not go through the change process, and do not rush the schedule.
- To introduce agile, first let the team understand the values and principles, then talk about specific practices. When there is doubt, first understand the person's concerns, then explain the reasoning behind the practice.
- Transparency comes from information radiators: task boards and burndown charts replace layers of status reports.
This chapter has 37 questions in the full bank; the questions beyond the worked examples are practiced in the question bank. Practice this chapter.