Cheat sheet · free to read or print
PMP Cheat Sheet: Risk
The key points and common traps of 23 lessons in 7 chapters, each linked to its lesson in the study guide. Other topics are on the cheat sheet hub.
Risk Management Plan
Lesson 1: Risk, Issues and Risk Appetite
- A risk is an uncertain event or condition and can be positive (opportunity) or negative (threat); describe it as cause, event and consequence.
- What has happened is an issue and goes in the issue log; what has not happened is a risk and goes in the risk register; what is certain is a fact or requirement.
- Four kinds of uncertainty: known-known is not a risk; known-unknown is a classic risk whose probability and impact can be identified (with a proactive response strategy, a contingency reserve may be set); unknown-known (someone knows, the performing entity does not) is also a risk; unknown-unknown relies on management reserve and project resilience.
- Overall project risk is not the sum of the individual risks (interactions between risks may amplify or cancel).
- Appetite answers "are we willing?", tolerance answers "can we withstand it?", and the threshold answers "how large a variation must be dealt with?" (often shortened to "do we need to act?" on the exam); common exam practice is to picture tolerance as the outer limit, appetite as the willingness within that capacity, and the threshold as the measurable trigger line.
- Exposure below the threshold is acceptable; crossing it should trigger assessment and a decision, which may be to respond, escalate or accept with approval; appetite goes into the risk management plan.
- Something that has already happened is an issue and goes in the issue log, not the risk register.
- Known-known facts and requirements are managed as part of scope; they are not risks.
- Overall project risk is not the sum of the individual risks.
- An opportunity is also a risk. Risk appetite, risk threshold and risk tolerance are three different concepts; do not mix them up.
Lesson 2: Project Resilience, Integrated Risk Management and Tailoring
- Project resilience is the ability to absorb impact and recover quickly, and it is used for unknown-unknowns.
- Ways to raise resilience: hold reserves, flexible change mechanisms, empower and trust the team, watch for early signals, and communicate with stakeholders in advance.
- Integrated risk management (a common exam term): risks flow up and down between levels; a risk beyond the project's scope or authority goes up under the escalate strategy.
- Tailor risk management to size, complexity, strategic importance, development approach and organizational appetite.
- Predictive projects usually identify and analyze risks and plan responses in a concentrated way early on, but still manage risk throughout; adaptive projects assess at the start of each iteration, review with stakeholders at the end, and order a risk-adjusted backlog.
- A spike (a common exam term) is a time-boxed quick experiment to confirm feasibility; exploratory code is usually not delivered as product, while the findings and knowledge are kept.
- Unknown-unknown risks are handled with reserves and resilience, not by "making identification more detailed".
- Common exam practice: risks can flow both up and down between levels, not only up as reports.
- An adaptive project does not skip risk management; it embeds it in every iteration. Common exam practice: an adaptive project usually has the cross-functional team manage risks together and should not hand the whole responsibility to a dedicated person; but large, complex or high-risk projects may still assign a dedicated risk manager for support as tailoring requires (PMBOK 8 mentions appointing dedicated risk managers in its large-project example).
- Common exam practice: in an adaptive project, risk response work suited to the team to carry out and track can go into the backlog and be ordered together with functional items.
Lesson 3: Plan Risk Management and the Risk Management Plan
- Plan Risk Management defines how to conduct risk management, produces the risk management plan and is completed early in the project.
- The risk management plan covers only how to manage; it records no specific risks.
- The stakeholder register is used to set roles, responsibilities and thresholds, and stakeholder analysis is used to establish risk appetite.
- Plan contents: risk strategy, methodology, roles and responsibilities, funding, timing, risk categories, stakeholder risk appetite, and definitions of probability and impact.
- The RBS is a hierarchical representation of risk sources; it helps with identification and with categorizing.
- How often to review, who is responsible, how reserves are used and what counts as high risk: check the risk management plan first.
- The risk management plan is procedural and contains no specific risks; specific risks are in the risk register.
- The risk register is not an output of Plan Risk Management; it starts with Identify Risks.
- Risk thresholds come from the preferences of key stakeholders; the project manager does not invent them.
- Definitions of probability and impact must be tailored; do not copy the example scale. If there is no risk management plan, plan risk management first; do not start by identifying risks.
Risk Register
Lesson 1: Identify Risks: Purpose, Characteristics and Handling New Risks
- Identify Risks finds threats and opportunities, and the key is telling real risks from concerns and issues.
- Identification is iterative, and new risks appearing during execution is normal.
- Describe a risk as cause, event and consequence; common exam practice: identification should encourage all stakeholders and team members to take part.
- What has happened is an issue; only what has not happened and is uncertain is a risk.
- Record a new risk first, then assess it, then respond; escalate only when it exceeds your authority.
- An adaptive project assesses technical and organizational readiness before the first iteration (agile practice and common exam practice) and keeps identifying risks in each iteration after that.
- Something that has already happened is not a risk: "cannot deliver" or "has already shut down" goes in the issue log; a "may" goes in the risk register.
- A concern is not a risk. First ask what event the person is worried about and which objective it would affect.
- Record a new risk in the risk register first and then analyze it by the process; do not start by changing, responding or escalating.
- When a risk like one seen on past projects shows up during execution, check whether the lessons learned register was consulted thoroughly enough during identification, and also update the register and the lessons learned with this result (PMBOK 8: not all risks can be identified at the outset, and identification is iterative).
- When the person raising the risk bypasses the team and reports straight to management: if the description is clear enough to record, still record it in the register first and then assess; an improper channel is no reason to reject it. If all that is known is that there is a new risk, and neither its content nor the reason for escalating is clear, talk to the person first, then record and assess.
Lesson 2: Identify Risks Inputs, Outputs and Data Gathering Techniques
- Outputs of Identify Risks: the risk register and the risk report, with updates to the assumption log, issue log and lessons learned register.
- Three key inputs: the risk management plan (categories, roles), the assumption log, and the lessons learned register (knowledge gained, including risks that materialized; historical risks are also in the lessons learned repository).
- Inaccurate, unstable, inconsistent or incomplete assumptions may give rise to threats; removing or relaxing constraints may give rise to opportunities.
- Brainstorming gives speed and volume; interviews are useful for confidential information and can dig deep (best held in an atmosphere of trust and confidentiality, common exam practice); checklists come from historical information and cannot replace identification.
- When an important participant is absent from a workshop, do not simply ignore it; reschedule, collect input online or in writing, or interview them afterward as the situation requires.
- A checklist contains specific risk items and comes from historical information; it cannot replace identification work.
- Choose the technique by the conditions in the stem: on the spot and in volume, use brainstorming; digging deep and in confidence, use interviews.
- Problems with assumptions usually bring threats, and relaxing constraints usually brings opportunities.
- The outputs of Identify Risks also include updates to the assumption log, issue log and lessons learned register, not only the risk register.
- When an important participant is absent from a workshop, you cannot simply ignore their input or compile the list alone; depending on urgency, options include rescheduling, collecting input online or in writing, and interviewing them afterward.
Lesson 3: Analysis Techniques, Prompt Lists, the Risk Register and the Risk Report
- Root cause analysis digs for the underlying source (common exam practice: find threats from problem statements and opportunities from benefit statements); flawed assumptions bring threats and relaxed constraints bring opportunities.
- SWOT: strengths and weaknesses analyze internal conditions, and opportunities and threats may come from the external environment or be triggered by internal conditions (PMBOK 8: SWOT includes internally generated risks); the opportunities and threats are the risks to identify.
- Prompt lists give only categories: for individual risks, use the lowest-level RBS categories; for overall risk, use PESTLE, TECOP or VUCA.
- The risk register starts with Identify Risks and fills up step by step through later processes; at the end of identification it holds the list of risks, potential owners and potential responses.
- The risk report presents the sources of overall risk and a summary of individual risks.
- A checklist holds specific risks, while a prompt list gives only risk categories; both are aids only and cannot replace identification work.
- The lowest-level RBS categories correspond to individual risks; PESTLE, TECOP and VUCA correspond to overall project risk.
- Specific risks are recorded in the risk register, not in the risk management plan; the risk report must also describe overall project risk.
- When identification is complete, the register's focus is the list of risks, with any identified potential owners and potential responses recorded too; columns like probability and impact are usually filled in at the analysis stage; the register must be reviewed and updated continuously during execution.
Qualitative Risk Analysis
Formulas
- Risk ScoreThe probability-impact score, used to compare relative priority; threats use negative impacts and opportunities positive ones
Lesson 1: Perform Risk Analysis: Qualitative vs. Quantitative, Rank First and Dig Deeper Later
- PMBOK 8 merges qualitative and quantitative analysis into Perform Risk Analysis, performed iteratively.
- Qualitative analysis assesses each risk's probability and impact and ranks priorities, throughout the project; quantitative analysis is done as needed and analyzes the combined effect on overall objectives.
- Ranking tools: probability and impact assessment, the matrix, risk categorization. Numeric tools: simulation, sensitivity analysis, decision trees, influence diagrams.
- The most important input is the assessment yardstick in the risk management plan; the outputs are updates to the risk register, risk report and other documents.
- After identification, the next step is Perform Risk Analysis, usually qualitative first.
- When risks have been identified and you need to rank them and focus on the high-priority ones, do qualitative risk analysis; the tool is the probability and impact matrix.
- The matrix and probability and impact assessment are for ranking. Using numbers to estimate overall risk or compare options is quantitative analysis.
- Quantitative analysis is not always required; qualitative analysis always is.
- PMBOK 8 merges qualitative and quantitative analysis into one process, Perform Risk Analysis, so do not count seven risk processes any more. And "qualitative" does not mean "no data".
Lesson 2: Risk Probability and Impact Assessment and the Probability and Impact Matrix
- Assess probability and impact separately (negative impact for threats, positive impact for opportunities), score with the definitions in the plan, and record the assumptions and reasons.
- Data must be reliable: verify source, accuracy and bias, and reassess when the basis changes.
- Score = probability × impact. Threats and opportunities share one matrix, and the level boundaries are set by the plan.
- When impact is in money, the contingency reserve can be estimated as probability times amount (the total expected loss) rather than adding up worst cases.
- Low-probability, low-impact risks go on the watch list and are reviewed periodically. After identification, assess first, and only then talk about responses.
- Assess probability and impact separately, then multiply to get a score. Do not give a single overall rating.
- When the basis for an assessment changes, verify the assumptions and data and reassess if needed; do not keep the old rating.
- Low-probability, low-impact risks are not ignored; they go on the watch list and are reviewed periodically.
- The boundaries between levels are set by the plan, so do not memorize the 0.24 in the figure. Opportunities must also be scored and ranked.
- If impact is expressed in money, probability × amount gives the expected monetary value, which can be one reference for setting contingency reserve (not the sum of all losses; PMBOK 8 also allows a reserve to be a percentage of the estimated cost, a fixed number, or developed with quantitative analysis methods). Matrix scoring is for ranking; it is not a response tool.
Lesson 3: Risk Categorization and the Outputs of Perform Risk Analysis
- Risk categorization finds the areas most exposed to uncertainty. Risks can be grouped by source (RBS), area affected (WBS), other categories or common root cause.
- The four sample RBS categories are technical, management, commercial and external; the project's risk management plan governs.
- Categorize by root source: requirements and product standards are technical risks, contracts and suppliers are commercial risks, and factors outside the organization are external risks.
- The outputs are project document updates: risk register, risk report, assumption log and issue log.
- After analysis the register gains probability, impact, score, priority, confirmed risk owners, category and the watch list.
- Categorize by source with the RBS. Categorizing by area affected can use the WBS. Do not mix the two.
- The categories and subcategories in the project's risk management plan govern; the sample is only a sample.
- Categorize by a risk's root source, not by which objective it ends up affecting.
- The output of Perform Risk Analysis is project document updates, not project management plan updates (unlike Plan Risk Management). The watch list is part of the register, not a separate document.
Quantitative Risk Analysis
Formulas
- Contingency Reserve (from the S-Curve)Pick the confidence level according to the organization's risk attitude (for example 75% or 85%), then read the total cost off the S-curve (common exam practice); management reserve cannot be read directly from the S-curve
Lesson 1: Quantitative Risk Analysis and Monte Carlo Simulation
- Quantitative risk analysis numerically analyzes the combined effect of risks on overall objectives. The keywords are "overall" and "numeric".
- It is done as the project needs, can run throughout the project, and quantifies both threats and opportunities.
- Its tools are filed under data analysis: simulation, sensitivity analysis, decision tree analysis and influence diagrams.
- Monte Carlo: input the estimates and distributions, draw random values, iterate thousands of times, and output a histogram and an S-curve.
- Criticality analysis counts how often an activity is on the critical path; activities with a high count get focused management.
- Common exam practice: many factors changing together is simulation; one factor at a time is sensitivity analysis. In PMBOK 8, sensitivity analysis correlates variation in the outcome with variation in each model element.
- "Quantitative analysis must always be done" is wrong; it is done as the project requires.
- Monte Carlo is not a single calculation but a large number of iterations (thousands or more are common). The output is a probability distribution, not a single number.
- Criticality analysis counts the share of iterations in which an activity is on the critical path. It is not total float.
- Quantitative analysis quantifies opportunities as well as threats.
- The probability and impact matrix and risk categorization are not quantitative techniques; they are often slipped into the answer options.
Lesson 2: The S-Curve, Confidence Levels and Contingency Reserve
- The S-curve is a cumulative probability curve: total cost or date on the horizontal axis, the probability of not exceeding that value on the vertical axis.
- Two ways to read it: given a budget, find the confidence; given a confidence, find the budget.
- The confidence level is the likelihood of finishing within budget. Common exam practice: conservative organizations often choose a higher value such as 75% or 85%.
- Contingency reserve = total cost at the target confidence level − base estimate excluding reserve.
- Wording such as "confidence", "raise to a certain probability" or "how much more" points to Monte Carlo and the S-curve.
- The higher the confidence, the larger the reserve; weigh it against the sponsor's needs.
- The horizontal axis is total cost (or date) and the vertical axis is the probability of not exceeding that value. Read it backward and nothing lines up.
- Contingency reserve = total cost at the target confidence level − base estimate, not the total cost itself.
- The confidence level is an organizational choice; higher is not always better.
- Contingency reserve covers identified risks, while management reserve covers unknown risks and is not given by the S-curve.
- If the curve is drawn for cost, talk about adding budget; if it is drawn for dates, talk about extending the schedule.
Lesson 3: Sensitivity Analysis, Influence Diagrams and Choosing a Quantitative Tool
- Sensitivity analysis finds the factor with the greatest effect. The approach in this lesson holds other factors at their baseline values and changes one at a time.
- Tornado diagram: bars represent factors, ordered from largest effect at the top to smallest at the bottom, wide at the top and narrow at the bottom.
- Influence diagram: shows causal influences and the time ordering of events, represents uncertain elements with distributions, and is evaluated with simulation.
- Choose the tool by the question: confidence means Monte Carlo, greatest impact means sensitivity analysis, choosing among options means a decision tree, cause and effect means an influence diagram.
- Sensitivity analysis finds the priorities and Monte Carlo gives the overall range; the two complement each other.
- Common exam practice: sensitivity analysis changes one factor at a time, while Monte Carlo changes many at once. In PMBOK 8, sensitivity analysis correlates variation in outcomes with variation in model elements.
- The length of a tornado diagram bar represents the size of the effect, not the probability of occurrence.
- Sensitivity analysis finds "the most important factor"; it does not answer "how confident are we of finishing within budget".
- A decision tree compares the EMV of alternatives; it does not answer "which risk has the greatest impact".
- A cause-and-effect diagram is a tool for finding causes, not a quantitative risk analysis tool. An influence diagram shows causes and time ordering, represents uncertain elements with distributions, and is evaluated by simulation.
Decision Tree Analysis
Formulas
- Expected Monetary Value (EMV)Pi is the probability of scenario i; the probabilities at one node add up to 1; Vi is the net value of that path, equal to the payoff minus the costs along the path
Lesson 1: Decision Tree Symbols and Expected Monetary Value (EMV)
- Decision tree: diagramming plus calculation, used to choose the best of several alternatives under uncertainty; a data analysis technique in quantitative risk analysis.
- Symbols: the square is a decision node, the circle is a chance node and the triangle is the end of a branch.
- The probabilities on the branches of one chance node add up to 100%.
- Net path value = payoff − costs along the path; EMV = Σ (probability × net value).
- Three backward steps: calculate net path values, take the weighted sum at chance nodes, take the maximum at decision nodes.
- Signal in the question: two or more alternatives, each with probabilities and amounts, and you must pick the highest expected value.
- The square is a decision node (we choose), the circle is a chance node (the environment decides) and the triangle is the end of a branch.
- The probabilities on the branches of one chance node must add up to 100%. A decision node needs no probabilities: compare the EMVs directly and take the maximum.
- Failures and losses enter the calculation as negative numbers. Dropping the minus sign is the most common error.
- The net path value already has the cost subtracted, so do not deduct it again after calculating EMV.
- EMV is a weighted average, not a result you are sure to get on any one occasion. A decision tree is a quantitative technique, not a qualitative tool for rating risks.
Lesson 2: Worked Decision Trees and the EMV of Risks
- Three steps: net path values, weighted sum at chance nodes, best path at decision nodes (when paths are expressed as payoffs or signed net values, take the largest number; when only cost or loss amounts are listed as positive figures, take the smallest amount).
- First check that the probabilities total 100%, then multiply term by term, without dropping a minus sign or deducting a cost twice.
- A change in probability can change the conclusion. When the EMVs of two alternatives are close, check the probabilities; the break-even probability is the one at which the two are equal.
- For multi-stage decision trees, work back from the far right to the left, choosing the best path at each decision node: take the largest number when paths are expressed as payoffs or signed net values, and the smallest amount when only cost or loss amounts are listed as positive figures.
- EMV of an individual risk = probability × impact; opportunities positive, threats negative.
- EMV assumes a risk-neutral decision maker and does not reflect attitude toward the worst outcome.
- Subtract the investment first to get the net path value, then multiply by the probability; do not deduct it again after calculating EMV.
- At a chance node take the weighted sum; at a decision node choose the best path: when paths are expressed as signed net values take the largest number, and when only cost or loss amounts are listed as positive figures take the smallest amount. Do not mix these up.
- Assign each endpoint the actual net result of its path: a loss is a negative number, and a failed path that has already incurred costs must not be written as zero.
- The EMV of a threat is negative and that of an opportunity positive; compare size by absolute value (common exam practice).
- The risk with the highest probability does not necessarily have the largest EMV, and neither does the one with the greatest impact.
- Common exam practice: when setting contingency reserve for threats, do not offset with the gains from opportunities; when the question asks for total gain or loss or net risk exposure, include opportunities and threats together.
- EMV is a weighted average and assumes a risk-neutral decision maker.
Risk Response Strategies
Lesson 1: Plan Risk Responses: Purpose, Response Requirements and Cost-Benefit Analysis
- Plan Risk Responses: determine the response to overall and individual risks, allocate resources or set aside reserves, throughout the project.
- Inputs include the risk management plan, risk register and stakeholder register; outputs are change requests, project management plan updates and project document updates.
- Five points of a good response (common exam practice): proportionate to importance, cost-effective, feasible in context, agreed by all, one owner.
- Tools: expert judgment, alternative analysis, cost-benefit analysis, multicriteria decision analysis and others.
- Cost-benefit analysis: PMBOK 8 requires only comparing cost with benefit. Under common exam practice, the calculation is effectiveness = result of response ÷ cost of response. When the effect can be monetized, cost should usually be below the loss avoided (safety, compliance and other non-financial benefits are judged separately).
- Planning writes the response; implementation carries it out.
- Plan Risk Responses develops responses for risks that have already been prioritized. It is not identifying risks and it is not carrying out the responses.
- Common exam practice: there is one owner, not two or more, and not "the whole team."
- Looking only at monetizable benefit, the response cost should usually be lower than the loss avoided or the benefit gained (common exam practice). But PMBOK 8 points out that extra spending that improves safety, meets regulatory requirements or builds stakeholder confidence can still be worthwhile, so judge it together with the risk threshold.
- Alternative analysis compares characteristics and requirements; cost-benefit analysis compares costs with benefits.
- Management reserve is for unknown risks; contingency reserve is the one that matches identified risks.
Lesson 2: Strategies for Threats: Escalate, Avoid, Transfer, Mitigate, Accept
- Five threat strategies: escalate, avoid, transfer, mitigate, accept.
- Avoid: the event no longer happens; suited to high-priority threats with high probability and high impact.
- Transfer: give it to a third party, usually with a risk premium, and the risk itself is not eliminated. Mitigate: reduce probability or impact; backup and redundancy belong here.
- Accept: active acceptance sets a contingency reserve; passive acceptance reviews periodically.
- Escalate: beyond project scope or the manager's authority; a higher level takes over and the project team no longer monitors it.
- Three judging questions: does the event still happen, who bears the consequence, and did probability or impact come down?
- Transfer does not eliminate the threat itself; it shifts ownership of a specific threat to a third party to manage it and bear its impact, and it usually costs money. Insurance, performance bonds, warranties and guarantees are typical tools.
- Redundant components, prototypes built to reduce risk and additional testing are usually mitigate, not avoid. For a backup or standby arrangement, look at what it does: reducing probability or impact is mitigate, while merely reserving resources or switching on after a trigger may be active acceptance or a contingent response.
- Accept is not doing nothing: the most common form of active acceptance is establishing a contingency reserve, and passive acceptance requires periodic review.
- Escalate means a higher level takes it over and manages it, and the project team no longer monitors it; it applies only to threats beyond the project's scope or the manager's authority.
- Exploit, share and enhance are opportunity strategies; avoid, transfer and mitigate are threat strategies; escalate and accept are used for both.
Lesson 3: Strategies for Opportunities and for Overall Project Risk
- Five opportunity strategies: escalate, exploit, share, enhance, accept.
- Correspondence: avoid with exploit, transfer with share, mitigate with enhance; escalate and accept are shared.
- Exploit: probability to 100%, using the most talented resources or new technology. Enhance: increase probability and/or impact.
- Share: give ownership of the opportunity to a third party so that it shares the benefit; a risk premium is often paid.
- Five strategy types for overall project risk: avoid, exploit, transfer/share, mitigate/enhance, accept, all measured against the project risk thresholds.
- Canceling the project is the most extreme avoidance at the overall level.
- Exploit aims for "it definitely happens" and uses the strongest resources or new technology. Enhance only increases probability or impact and does not guarantee anything.
- Share gives part of the benefit to a third party (opportunities). Transfer hands the impact to a third party and usually involves paying a risk premium (threats).
- Escalate and accept are used for both threats and opportunities. After an opportunity is escalated, the project team does not monitor it further and only keeps a record in the risk register.
- At the overall level, the extreme form of avoidance is canceling the project, but it is used only when the overall threat is, and will remain, unacceptable.
- Overall-risk strategies target the whole project: "mitigate" for negative risk, "enhance" for positive risk.
Lesson 4: Contingent Responses, Fallback Plans, Workarounds, Secondary and Residual Risk
- A contingent response strategy is launched by a trigger condition agreed in advance; it is often called a contingency plan (a common exam term).
- Fallback plan: a common exam term, often the backup used when the contingency plan fails. Workaround: improvise when there is no plan.
- Secondary risk: a new risk created directly by a response. Residual risk: the original risk that remains after a response, and a contingency reserve may be set aside for it.
- After planning, update the risk register: strategies and actions, triggers, budget and schedule activities, contingency and fallback plans, residual and secondary risks.
- When a response changes scope, schedule or cost, submit a change request and change the baseline only after approval.
- A contingency plan covers a risk for which a plan was prepared and is started by a trigger condition. A workaround covers a risk with no plan in advance (commonly an unidentified risk).
- PMBOK 8 lists contingent response strategies as a tool; by common exam practice they are used only if a trigger occurs, and contingency plan and fallback plan are common exam and older-PMI terms. Common exam practice often describes the fallback plan as the backup used when the contingency plan fails, but in both cases the key is that the plan is prepared in advance and started by a trigger condition. A trigger may occur before the risk happens, or it may be the occurrence of the risk event itself, so a plan can include recovery steps taken after the event.
- A secondary risk is a new risk brought by a response. A residual risk is what remains of the original risk after a response.
- When an identified risk occurs, check the register and carry out the contingency plan first. Do not jump straight to a "workaround".
- In predictive environments, or wherever formal configuration control applies, a response that changes a baseline must go through a change request and be approved before the baseline is changed. Adaptive environments usually evaluate and reprioritize changes through the backlog and do not necessarily have a formal approval process.
- Contingency reserve is for identified risks (including residual risk). Management reserve is for unknown risks.
Monitor Risks
Lesson 1: Implement Risk Responses: Making the Agreed Actions Happen
- Implement Risk Responses means carrying out the agreed actions to minimize threats, maximize opportunities and address overall risk exposure.
- Inputs: risk management plan, risk register, risk report, lessons learned register, organizational process assets. Tools: expert judgment, influencing, project management information system. Outputs: change requests, project document updates.
- Four things put actions into effect: confirm the owner, coordinate resource conflicts, make the action requirements clear and drive the action forward (checking periodically whether it was done and whether it worked belongs to Monitor Risks).
- Owners outside the team are moved by influence: first understand the obstacle, then help remove it.
- When an identified risk occurs: check the register, carry out the action, and use contingency reserve if necessary under the risk management plan and your authorization (common exam practice: the project manager decides within the established authority; when the reserve is already in the baseline, the baseline does not change), and record it in the issue log.
- If an action is ineffective, consider another strategy; if it affects a baseline, go through change control.
- A newly identified risk must first be analyzed and have a response planned before it is implemented; you cannot jump straight to implementation.
- When people outside the team carry out an action, influencing is the first choice and administrative orders are not; if the action stays blocked and the risk response is affected, escalate according to the escalation criteria.
- “Checking whether the action was carried out” is Monitor Risks; implementing is “doing it”.
- After an identified risk occurs, “call the team to discuss responses”, “brainstorm solutions” and “analyze the risk again” are usually distractors.
Lesson 2: Monitor Risks: Purpose, Inputs and Outputs
- Monitor Risks: monitor the implementation of response plans, track identified risks, identify and analyze new risks, and evaluate the effectiveness of responses and processes; it runs throughout the project.
- Inputs: risk management plan, risk register, issue log, risk report, lessons learned register, work performance data, work performance reports.
- Outputs: work performance information, change requests, project management plan updates, project document updates (including the assumption log), organizational process asset updates.
- Risk register updates fall into three kinds: newly added risks, risks whose status has changed and actions that have changed.
- Three main findings (plus everyday parameter changes): a new risk goes back to analysis; an identified risk that occurs means check the register; an unidentified risk that occurs means a workaround, and if funding or a baseline change is needed, apply for management reserve under your authority and go through change control.
- When signs of a risk appear, reassess first and check whether the strategy is still effective. When a risk is obsolete, close it, update the register, record a lesson learned and adjust reserves based on reserve analysis.
- Monitor Risks is not just checking the original risks: you also identify new risks and close obsolete ones.
- A risk that has not occurred does not go in the issue log; it goes in only once it has occurred.
- Stopping work at the first sign, or adding budget straight away, skips steps: reassess first, then adjust the strategy, and raise a change request if a baseline is affected.
- Risk reviews follow the frequency in the risk management plan. If the plan says every two weeks, you cannot go two months without one.
Lesson 3: Risk Monitoring Tools: Technical Performance Analysis, Reserve Analysis and Risk Audits
- Tools for monitoring risks: data analysis (technical performance analysis, reserve analysis), audits and meetings.
- Technical performance analysis: compare actual results with targets using objective, quantifiable technical measures; deviation signals threats or opportunities.
- Reserve analysis: compare the remaining reserve with the expected loss of the remaining risks; a shortfall or surplus is handled under governance and authority rules, and if it changes an approved baseline, raise a change request.
- Contingency reserve is usually inside the baseline, covers identified risks, and is used under the risk management plan and authority (common exam practice: the project manager uses it); management reserve is outside the baseline, covers unknown risks, and goes through change.
- A risk audit examines the risk management process, not a single risk; the project manager is responsible for ensuring it is done at the planned frequency.
- Read what the stem is asking: technical results call for technical performance analysis, "is the reserve enough?" calls for reserve analysis, and "is the process effective?" calls for a risk audit.
- A risk audit evaluates the effectiveness of the risk management process, not an individual risk. The project manager is responsible for ensuring it is carried out at the planned frequency; senior management, the sponsor and a risk management department only support it or set requirements.
- Reserve analysis compares the "remaining reserve" with the "remaining risk". Risks that have already occurred are no longer counted.
- If adjusting or releasing contingency reserve would change an approved baseline, submit a change request and follow the formal process. Where a reserve sits outside the baseline, follow organizational governance and authority rules. Management reserve is for unknown-unknowns and cannot be used to fill a shortfall on an identified risk.
- Technical performance analysis needs objective, quantifiable measures. It looks at technical measures; it is not earned value analysis.
Lesson 4: Risk Review Meetings and the Watch List: Monitoring Risks in Predictive and Adaptive Projects
- Risk review (risk reassessment): analyze the status of existing risks and identify new risks, at the planned frequency; it can be folded into a status meeting or held separately.
- The review meeting does five things: identify new risks, reassess, close outdated risks and adjust reserves through reserve analysis, discuss issues that have occurred, and capture lessons learned.
- Watch list: low-probability, low-impact risks are listed in the register and rechecked periodically; move them into active response when the change is clear. Update the risk register first.
- Predictive projects review at the planned frequency. For adaptive projects you can follow the PMBOK 8 tailoring example: assess risks at the start of each iteration and hold a risk review meeting with stakeholders at the end; the actual rhythm is tailored to the project.
- New risks in adaptive projects: put them on the board and raise them at the next daily coordination meeting; work to handle them goes into the backlog, ordered by the product owner.
- An information radiator is a way of displaying information; a falling risk burndown chart means remaining risk exposure is decreasing.
- A falling risk burndown chart means remaining risk exposure is decreasing. It does not mean higher velocity, a slower budget burn, or the number of issues that have occurred. The iteration burndown chart is the one that tracks work.
- An information radiator is a way of displaying information, not a meeting. The risk review meeting is the meeting.
- Agile projects can let stakeholders keep up with risks through information radiators. Whether a separate status report is needed is decided by the communications management plan and stakeholder needs.
- Risks on the watch list must be rechecked periodically; the approach is not "deal with it when it happens".
- The retrospective and the daily coordination meeting are not the main places for risk review. Put new risks on the board, and put the work to handle them in the backlog.
Lesson 5: When a Risk Occurs: Reserves, the Issue Log and Workarounds
- The line between a risk and an issue is "has it already happened?". A threat that occurs becomes an issue and goes in the issue log (when an opportunity is realized, update the risk register; a current situation that needs action or monitoring may also go in the issue log).
- An identified risk occurs: check the register, carry out the action, use contingency reserve (used under authority, usually decided by the project manager; if already inside the baseline, the baseline is unchanged), and record it in the issue log.
- If the contingency reserve is not enough, or the action requires changing a baseline or another controlled item, analyze the impact and submit a change request.
- An unidentified risk occurs: workaround; if money is needed, submit a change request, and once approved management reserve can be used (for unforeseeable work), with the amount added to the cost baseline.
- An identified risk does not occur: close the risk, and unused contingency reserve can be released.
- If the risk remains after the action is carried out: first reassess the action's effectiveness, then adjust the response plan.
- When an identified risk occurs, carry out the agreed response. When contingency reserve is needed, use it under the risk management plan and authority. To use management reserve, submit a change request first.
- When an identified risk occurs and the action is already agreed, options such as "call the team together to discuss", "brainstorm", "re-identify" or "reanalyze" are mostly distractors.
- A threat that occurs moves into the issue log, but the priority is to carry out the agreed action immediately and update the issue log at the same time or promptly afterward.
- Carrying out an approved response that does not modify any controlled item usually needs no new change request. If a baseline, a configuration-controlled plan or document, a deliverable and so on must be modified, submit a change request under the change management plan.
- Seeing signs of a risk is not the same as its occurring: first review whether the existing strategy is effective and reassess the likelihood, rather than going straight to the reserve.